DHS Headquarters Consolidation Project:
Issues for Congress

William L. Painter
Analyst in Emergency Management and Homeland Security Policy
September 21, 2012
Congressional Research Service
7-5700
www.crs.gov
R42753
CRS Report for Congress
Pr
epared for Members and Committees of Congress

DHS Headquarters Consolidation Project: Issues for Congress

Summary
The Department of Homeland Security (DHS) was established in early 2003, bringing together
existing parts of 22 different federal agencies and departments in a new framework of operations.
In its first few years, the department was reorganized multiple times, and more focus was given to
ensuring its components were addressing the perceived threats facing the country rather than to
addressing the new organization’s management structure and headquarters needs. Therefore, the
consolidation of physical infrastructure that one might expect in creating an operation of such size
and breadth did not occur.
As the Coast Guard began to plan consolidating its leases on headquarters facilities into secure
federally owned space, DHS was finding its original headquarters space at the Nebraska Avenue
Complex too limited to meet its evolving needs. In 2006, the George W. Bush Administration
proposed combining the two projects into one $3.45 billion headquarters consolidation project on
the West Campus of St. Elizabeths Hospital in Anacostia.
Since that year, Administrations of both parties have requested funding for this initiative.
However, this project has not received sustained funding from Congress—over 80% of the
funding it has received so far came in FY2009 when a surge of supplemental funding combined
with the regular appropriations for the General Services Administration (GSA) and DHS provided
almost $1.1 billion for the project. With the completion of its first key component (a new
headquarters for the Coast Guard), this project faces an important turning point as budget
pressures are impacting potential capital projects across the government and the Administration is
developing a new construction plan and cost estimate for DHS headquarters in response.
The purpose of this report is to outline the policy considerations to be evaluated in deciding
whether to continue funding the consolidated DHS headquarters at St. Elizabeths, and to explore
some of the benefits and consequences of several possible ways forward.
The fate of this initiative could have significant impact on the department operationally,
budgetarily, and culturally. Operationally, the consolidated headquarters would provide a higher
level of security for many DHS headquarters functions, and would provide a more capable
departmental operations center to help coordinate the federal response to natural disasters and
terrorist attacks. Budgetarily, the department would benefit from reduced overhead costs in the
long term, but would face significant pressure on its near term budget to see the construction
through to completion. Culturally, the new headquarters could help promote the integration of the
department’s components into “One DHS,” and have some direct and indirect contributions to
improving departmental morale.
The report looks at five potential ways forward for the headquarters project: immediate
termination of it and disposal of the site; moving the Coast Guard in but going no further; moving
the Coast Guard in and proceeding with developing the departmental operations center complex
and top management offices; rescoping the Coast Guard building as a smaller headquarters for the
department overall; and aggressively funding the project to accelerate completion.
Whatever decision is made—even an option to not make a decision on the long-term fate of the
project—will bear significant costs, manifested as a combination of up-front construction costs,
ongoing lease expenses, and operational and management tradeoffs that are difficult to quantify.
This report will be updated as events warrant.
Congressional Research Service

DHS Headquarters Consolidation Project: Issues for Congress

Contents
Background...................................................................................................................................... 1
Arguments for and Against Headquarters Consolidation .......................................................... 3
Justifications Made for Consolidation................................................................................. 3
Concerns Voiced over Consolidation .................................................................................. 4
Funding History......................................................................................................................... 5
Current Status ............................................................................................................................ 7
Project Status....................................................................................................................... 7
FY2013 Appropriations....................................................................................................... 9
Other Congressional Action .............................................................................................. 10
Considerations for Congress.......................................................................................................... 12
Implications of the Consolidated Headquarters Project .......................................................... 12
Operations ......................................................................................................................... 12
Budget ............................................................................................................................... 15
Culture............................................................................................................................... 18
Options .................................................................................................................................... 20
Termination and Site Disposal .......................................................................................... 20
Completion of Coast Guard Headquarters Only ............................................................... 21
Coast Guard Headquarters, Operations Center, and Management .................................... 22
Rescoping Coast Guard Headquarters to House Other Elements ..................................... 22
Expediting Project Completion ......................................................................................... 23
Conclusion ..................................................................................................................................... 23

Figures
Figure 1. GSA and DHS funding for DHS St. Elizabeths Headquarters, FY2006-2012................. 6

Tables
Table A-1. DHS and GSA Appropriations for St. Elizabeths (FY2006-FY2012).......................... 27

Appendixes
Appendix. History of Project Appropriations ................................................................................ 24

Contacts
Author Contact Information........................................................................................................... 28

Congressional Research Service

DHS Headquarters Consolidation Project: Issues for Congress

Background
The Department of Homeland Security (DHS) was established by the Homeland Security Act of
2002 (P.L. 107-296, hereafter the HSA) and became operational January 24, 2003, barely sixteen
months after the terrorist attacks on the Pentagon and World Trade Center on September 11, 2001.
Rather than being as a completely new entity, the department was established by assembling
existing parts of 22 different federal agencies and departments into a new framework.1 The timing
and means of establishing DHS, coupled with the perceived urgency of its mission in its early
years, hastened the growth and development of the department’s operational capabilities. At the
same time, these factors hindered potential efforts to more fully integrate the functions of the
department’s different components.
The headquarters functions of the department’s components were not physically consolidated at
the time, but instead were left scattered across the National Capital Region in accordance with
their past history, rather than their new role in the DHS. As a result, DHS today stands as the
third-largest department of the federal government,2 but runs its operations from about 50
different locations in the National Capital Region.
In 2004, the Coast Guard (one of the larger components of the newly-minted DHS) began to
explore how to meet its needs for new headquarters facilities. The General Services
Administration (GSA), the Office of Management and Budget (OMB), and DHS determined that
a federally-owned site would be more cost-effective than securing a replacement lease. In the
meantime, the current location of the DHS headquarters—a former Navy facility at the corner of
Nebraska and Massachusetts Avenues in northwest Washington, DC (known as “the NAC”—
short for “the Nebraska Avenue Complex”)—was proving to be inadequate. One of the initial
assumptions at the time of the establishment of DHS was that the department would only need a
headquarters staff of roughly 800 persons. Once the department was established and roles,
responsibilities, and management needs became clear, DHS determined that the NAC was
inadequate to meet mission execution requirements.3
GSA had determined that the St. Elizabeths Hospital4 site in Anacostia, which had recently been
declared excess by the Department of Health and Human Services, was a potential site for federal
agencies with high security requirements.
President George W. Bush’s FY2006 budget request had announced the Administration’s plan to
consolidate the Coast Guard’s headquarters on the West Campus of St. Elizabeths—an initiative
that received initial funding in GSA’s budget that year.5 The Administration’s FY2007 budget
request sought the initial tranche of funding for the new Coast Guard headquarters through the
DHS appropriations bill, but both House and Senate appropriators, when briefed on the idea of a
larger consolidation project for DHS headquarters at the site, directed DHS to not proceed on
either project until a new headquarters master plan was completed.6

1 A complete list can be found at http://www.dhs.gov/xabout/history/editorial_0133.shtm.
2 This relative ranking is based on the number of employees.
3 CRS discussions with GSA and DHS staff during site visit to St. Elizabeths, November 16th, 2011.
4 The formal name of the site is “St. Elizabeths Hospital,” spelled without an apostrophe.
5 U.S. General Services Administration, FY 2006 Congressional Justifications, Washington, DC, February, 2006.
6 H.Rept. 109-699, p. 118-199.
Congressional Research Service
1

DHS Headquarters Consolidation Project: Issues for Congress

In October 2006, DHS Secretary Michael Chertoff put forward a master plan for “unifying …
core headquarters facilities with those of our operating components,” which essentially broadened
the Coast Guard project to include the overall DHS headquarters consolidation as well, moving
14,000 of the 22,000 people that staff headquarters functions for the department and its
components to St. Elizabeths.7 Earlier that year, the White House issued a report entitled “The
Federal Response to Katrina: Lessons Learned.” While this report did not call for a consolidated
DHS headquarters per se, it did state a need to develop a joint departmental operations center
with robust command and control functions to promote more efficient incident response. 8 This
need would be used to help advocate for the consolidated headquarters project in future years.
Since that year, Administrations of both parties have requested funding for this initiative to
support a coordinated construction plan. However, this project has not received consistent
funding—over 80% of the funding it has received so far came in FY2009 when a surge of
supplemental funding combined with the regular appropriations for GSA and DHS provided
almost $1.1 billion for the project.
Given this lack of consistent funding, Administration officials have indicated that the coordinated
construction schedule is no longer feasible and will need to be revised for future phases of the
project. The Obama Administration’s FY2013 budget request seeks funding for operational
transition costs associated with moving the Coast Guard into its newly constructed headquarters
building on the West Campus of St. Elizabeths, and to build highway infrastructure to support its
operation, but no funding for GSA construction of later phases. The Administration has indicated
that they will present a revised construction schedule and cost estimate for the project in the
FY2014 budget request, or earlier. The decision on FY2013 funding coupled with the
Administration’s new plan for consolidation presents a unique opportunity for Congress to make
clear its long-term vision for the department’s headquarters and DHS overall.
The fate of this initiative could have significant impact on the department operationally,
budgetarily, and culturally. Operationally, the consolidated headquarters would provide a higher
level of security for many DHS headquarters functions compared to their current locations, and
would provide a more capable departmental operations center to help coordinate the federal
response to natural disasters and terrorist attacks. Budgetarily, the department would benefit from
reduced overhead costs in the long term, but would face significant pressure on its near term
budget to see the construction through to completion. Culturally, the new headquarters could help
promote the integration of the department’s components into “One DHS,”9 and have some direct
and indirect contributions to improving departmental morale.

7 Department of Homeland Security, Department of Homeland Security National Capital Region Housing Master Plan:
Building a Unified Department
, Washington, DC, October 2006, p. 2.
8 The White House, The Federal Response to Hurricane Katrina: Lessons Learned, Washington, DC, February 23,
2006, p.91.
9 “One DHS” is a term used by past and present secretaries of the department to describe a DHS that operates as a
single unit rather than a collection of individual components.
Congressional Research Service
2

DHS Headquarters Consolidation Project: Issues for Congress

Arguments for and Against Headquarters Consolidation
Justifications Made for Consolidation
The initial DHS National Capital Region Housing Master Plan stated that increased consolidation
and co-location of DHS headquarters functions was needed to accomplish five objectives:
• Improve mission effectiveness;
• Create a unified DHS organization;
• Increase organizational efficiency;
• Adjust the size of the real estate portfolio to better fit the mission of DHS; and
• Reduce real estate occupancy costs.
In testimony before the House Appropriations Committee Homeland Security Subcommittee on
March 25, 2010, Elaine Duke, Under Secretary for Management for the department, simplified
this list to three reasons:
• To increase effectiveness and efficiency;
• To enhance communication; and
• To “foster a “one DHS” culture that would optimize department-wide,
prevention, response and recovery capabilities.”
Former DHS Secretary Michael Chertoff, who signed the original DHS Consolidation Master
Plan, recently described the consolidation project as being “very important both from symbolic
and operational standpoint. It would provide an enormous amount of leverage in defining the
department.”10
Many of DHS’s components are in leased facilities, despite the fact that the government’s existing
policy is to use federally owned sites for national security functions.11 Consolidation would help
bring DHS in line with that policy, which would also reduce the department’s overhead costs.
Why St. Elizabeths?
The DHS Housing Master Plan analyzed fifteen possible sites to see if they could meet the
department’s requirements. DHS and GSA determined in their program of requirements for DHS
in the National Capital Region that DHS needed a minimum of 4.5 million square feet of office
space specifically for headquarters functions on a secure campus, housing nearly 14,000 DHS

10 Chertoff, Michael, response to question posed to a panel on “The Department of Homeland Security: Past, Present,
and Future,” at the Aspen Security Forum, July 28, 2012. Video available at http://aspensecurityforum.org/2012-video-
day-3.
11 General Services Administration, “DHS Headquarters Location Analysis,” September, 2008, p. 6.
Congressional Research Service
3

DHS Headquarters Consolidation Project: Issues for Congress

personnel, out of an overall need for 7.1 million square feet in the region.12 The NAC, if fully
developed, could only provide 1.2 million square feet.13
Aside from space, the other requirements noted in the study were:
• Compatibility with DHS security needs;
• Closeness to the White House and Congress;
• Availability for development by DHS;
• Ability to be ready on DHS’s timetable;
• Proximity to major roadways;
• Proximity to mass transit;
• Proximity to neighborhood amenities; and
• Availability of an adjacent parcel that can accommodate additional office
development and parking.
The analysis found St. Elizabeths was the best match, meeting eight of the nine requirements
(neighborhood amenities were not deemed present at the time, but were anticipated to develop).
According to GSA, St. Elizabeths was the only site available that was capable of meeting DHS’s
needs.14
In addition, under 41 CFR Section 102-73.255, “prior to acquiring, constructing, or leasing
buildings (or sites for such buildings), Federal agencies must use, to the maximum extent
feasible, historic properties available to the agency.”15
Other benefits often cited for consolidation at the St. Elizabeths Campus include economic
benefits to the local community and security benefits to nearby federal facilities. St. Elizabeths,
since its establishment, has been a government-controlled closed campus. It overlooks Joint Base
Anacostia-Bolling16 and the Defense Information Systems Agency, which has expressed its desire
that the property remain a government-controlled closed campus.
Concerns Voiced over Consolidation
Opponents of consolidation have questioned the need for a single large headquarters. Some critics
have expressed the belief that the single headquarters concept is outdated, proposing “distributed”
headquarters facilities connected via the Internet.17 With new constraints on the DHS budget, the

12 Department of Homeland Security, Department of Homeland Security National Capital Region Housing Master
Plan: Building a Unified Department
, Washington, DC, October 2006, p. 5.
13 Ibid., p. 7.
14 Department of Homeland Security, Department of Homeland Security National Capital Region Housing Master
Plan: Building a Unified Department
, Washington, DC, October 2006, pp. 4-5.
15 41 CFR 102-73.255, as downloaded from GPOAccess’s “Electronic Code of Federal Regulations,”
http://ecfr.gpoaccess.gov.
16 Former known as Bolling Air Force Base and the Anacostia Naval Annex.
17 Slabbert, Nicholas, “Telecommunities,” Urban Land Institute, May 2005. As downloaded from
http://www.virtualadjacency.com/wp-content/uploads/2008/01/9-uli-telecommunities-may2005.pdf.
Congressional Research Service
4

DHS Headquarters Consolidation Project: Issues for Congress

department’s workforce is unlikely to meet growth projections that formed part of the justification
for the project’s size. Others oppose consolidation on the grounds that the department’s
establishment was flawed and that its overall structure should be revisited.18
As is noted in later sections of the report, concerns have been voiced by Members of Congress
about schedule delays and cost increases.
Why Not St. Elizabeths?
Some historic preservationists voiced concerns that the project would fail to preserve the historic
character of the site,19 while others have balked at the cost of “constructive reuse” of the site’s
historic buildings. Some in the local community have questioned whether a secure campus like
the envisioned DHS headquarters will support significant economic activity in the surrounding
area.20 According to GSA testimony in 2010, the project would create 30,000 direct and indirect
jobs during construction.21 As of July 2012, according to GSA’s website for the project, 4,690
people have been employed by the project, including 717 District residents.22
As noted in later sections of the report, concerns have been voiced by Members of Congress
about the operational impacts of the Coast Guard being the only part of DHS that moves to the
site.
Funding History
Funding for civilian federal government facilities is often provided through two separate
sources—through the GSA, which is funded in the Financial Services and General Government
Appropriations bill, and through the appropriations bill that funds the agency that will use the
facility. The construction of basic buildings in most cases is done through contracts let by and
funded through GSA. The department that will use the building pays for “tenant
improvements”—security, furniture, mission-specific equipment, amenities and other finishes that
make the building functional for its occupants.

18 O’Connell, Jonathan, “St. Elizabeths Renovation as Security Campus Faces Resistance,” The Washington Post,
March 30, 2012.
19 Moe, Richard, “A Disaster for St. Elizabeths,” The Washington Post, January 8, 2009.
20 Sheridan, Mary Beth, “Scouting a New Home for Homeland Security,” The Washington Post, October 14, 2007.
21 Written testimony of Robert Peck, Commissioner, Public Buildings Service, General Services Administration,
“Homeland Security Headquarters Facilities,” before the House Appropriations Committee’s Homeland Security
Subcommittee, March 25, 2010. Available at http://www.gsa.gov/portal/content/104271.
22 General Services Administration, Opportunities Center Employment Summary, available at
http://stelizabethsdevelopment.com, as of viewed September 11, 2012.
Congressional Research Service
5


DHS Headquarters Consolidation Project: Issues for Congress

Figure 1. GSA and DHS funding for DHS St. Elizabeths Headquarters, FY2006-2012
(millions of dollars of budget authority)

Source: FY2006-FY2012 conference reports and the U.S. General Services Administration’s FY2012 Expenditure
Plan and Reprogramming Request for the Federal Buildings Fund.
Note: Some of GSA’s appropriations for St. Elizabeths pay for infrastructure and improvements that would be
needed for any redevelopment of the site—a core responsibility of the GSA. As it could be argued that these
costs therefore are not directly attributable to the DHS headquarters project, CRS has attempted to distinguish
between the two. A detailed table of requests and appropriations is provided in the Appendix.
Figure 1 shows the funding requests made by previous and present Administrations through GSA
and DHS for DHS headquarters consolidation at St. Elizabeths, including funding for
infrastructure improvements at the site once the initial headquarters project was announced, and
the appropriations provided by Congress in response, from FY2006 through FY2012.23
The St. Elizabeths project has to date received more than $1.3 billion in appropriations. The
original cost estimate for the consolidation of DHS headquarters at St. Elizabeths was $3.4
billion.24 According to DHS, all funded components of the project have proceeded on time and
within their budget projections.25 However, the project has not been consistently funded to the
levels requested under Administrations of either party.

23 GSA had a separate project to fund infrastructure upgrades at St. Elizabeths for future use, separate from the DHS
headquarters consolidation project. However, as these upgrades support the headquarters consolidation, they are
included to provide a more complete picture of the funding stream.
24 Duke, Elaine C., DHS Under Secretary for Management, written testimony, “Homeland Security Headquarters
Facilities,” before the House Appropriations Committee Homeland Security Subcommittee, March 25, 2010, p. 11.
Available at http://ipv6.dhs.gov/ynews/testimony/testimony_1274279995276.shtm.
25 Borras, Rafael, DHS Under Secretary for Management, written testimony, “Department of Homeland Security
Facilities Hearing,” before the House Appropriations Committee Homeland Security Subcommittee, March 21, 2012.
Available at http://www.dhs.gov/news/2012/03/29/written-testimony-under-secretary-management-rafael-borras-
house-appropriations.
Congressional Research Service
6

DHS Headquarters Consolidation Project: Issues for Congress

As the figure illustrates, requests for funding were made but not fulfilled for the larger
consolidation project in FY2007 and FY2008, which slowed the start of the project. The original
DHS National Capital Region Master Plan envisioned the Coast Guard moving into its new
headquarters in the last quarter of FY2010—a move now slated for the second half of FY2013.26
FY2009 was the only year the St. Elizabeths project as presently envisioned received funding of
more than $100 million from either the DHS or GSA budget. The first of two consolidated
appropriations bills27 included funding for the Department of Homeland Security, including $98
million for the Coast Guard Headquarters element of the project.28 Five months later, outside the
traditional allocation-constrained debate of regular appropriations bills, the American Recovery
and Reinvestment Act of 200929 (ARRA) invested $650 million in this capital project.30 The
FY2009 regular appropriations process concluded about three weeks later with the second of the
two consolidated appropriations bills,31 which included $347 million for the project through GSA,
matching the level requested by the Administration through the GSA budget request.32
Requests for funding in FY2011 and FY2012 were only partially met. As a result of these lower
funding levels, the projected project completion date has slipped to the point that the coordinated
construction plan—designed to maximize efficiency in construction by doing the work in large
simultaneous phases—is being revisited, and a new cost estimate is being generated along with
that plan.
Table A-1, which outlines the history of requests and appropriations for this project in detail is
included in the appendix, as well as a summary of the appropriations provisions from the other
years where funding was requested.
Current Status
Project Status
In the final consolidated appropriations bill for FY2012, the overall combined request of $377
million for GSA and DHS contributions to St. Elizabeths garnered $93 million in appropriations,
with enough funding provided to DHS to complete only the construction of the Coast Guard
portion of the headquarters.33 GSA provided $37 million out of the $50 million it received for
construction projects nationwide.

26 Department of Homeland Security, Department of Homeland Security National Capital Region Housing Master
Plan: Building a Unified Department
, Washington, DC, October 2006, p.16.
27 P.L. 110-329, 122 Stat. 3574.
28 House Appropriations Committee Print, Consolidated Security, Disaster Assistance, and Continuing Appropriations
Act, 2009
(P.L. 110-329), Division D—Department of Homeland Security Appropriations Act, 2009, p. 589.
29 P.L. 111-5, 123 Stat. 115.
30 H.Rept. 111-16, p. 48, 432. ARRA was an economic stimulus package that provided almost $800 billion in
appropriations and revenue provisions passed in the midst of a recession.
31 P.L. 111-8, 123 Stat. 524.
32 House Appropriations Committee Print, Omnibus Appropriations Act, 2009 (P.L. 111-8), Division D—Financial
Services and General Government Appropriations Act, 2009
, p. 907.
33 In their spending plan released on January 27, 2012, GSA indicated they would spend $37 million on the St.
Elizabeths project.
Congressional Research Service
7

DHS Headquarters Consolidation Project: Issues for Congress

Discussions with DHS officials and testimony before Congress have indicated DHS is preparing a
new approach to the St. Elizabeths project in light of the limitations on available funding. The
original plan for St. Elizabeths was a coordinated approach, intended to maximize cost savings by
coordinating construction efforts across the campus. DHS has indicated that continuing with the
original integrated construction plan given the level of appropriations in FY2011 and FY2012
(which would not be feasible due to the level of appropriations required in individual future
years) would stretch the timeline for project completion to FY2022 and raise the estimated overall
cost to $4 billion.34 DHS Under Secretary for Management Rafael Borras noted in testimony
before the House Appropriations Committee’s Homeland Security subcommittee that future
requests would be scoped and packaged as individual segments rather than as larger coordinated
pieces.35
CRS has made inquiries with DHS regarding revisions to the schedule and cost estimates for the
project. The department indicated that no additional information had been approved for release
beyond the information provided in the FY2013 budget request.36 The budget request indicates
DHS has funding to complete the first phase of the project, including the Coast Guard
Headquarters, perimeter security and utilities to support the headquarters, and adaptive reuse of
six historic buildings to support the Coast Guard presence.37 However, briefing materials
provided by DHS indicate that GSA did not receive the minimum required funding for
completing its first phase requirements,38 and they have had to delay several items in Phase I that
are not critical to Coast Guard occupancy. These will have to be completed later at higher cost,
but redirecting that funding will allow the Coast Guard headquarters part of the project to go
ahead.39
The original plans called for a consolidated departmental operations center to be excavated and
built at the same time as the Coast Guard headquarters. As the Coast Guard headquarters building
was built into the side of a hill, the original construction plan would have taken advantage of the
availability of the specialized crew and open space created by the construction to facilitate
development of this new facility. Funding was not provided for this work, however, so this piece
of the project will have to be developed at a later date and most likely at a higher cost, according
to DHS and GSA. Should Congress fund the provide the necessary operational transition costs for
the Coast Guard to move to St. Elizabeths in FY2013, the operations center for the Coast Guard
and campus security control center will occupy some of the available space. 40
Aside from individual cases like the one noted above in which efficiencies from concurrent
construction will not be realized, delays in construction are projected to result in other cost
increases. According to Borras, “It is expected that future construction work will increase in cost

34 E-mail to CRS from DHS Legislative Affairs, September 4, 2012.
35 Rafael Borras, response to questioning during “Department of Homeland Security Facilities Hearing,” before the
House Appropriations Committee Homeland Security Subcommittee, March 21, 2012.
36 Author telephone conversation with DHS officials, August 7, 2012.
37 U.S. Department of Homeland Security, Fiscal Year 2013 Congressional Justification, Departmental Management
and Operations, DHS Headquarters Consolidation Project, Washington, DC, February 13, 2012, p. 4.
38 According to DHS, GSA needed $76 million to complete all activities associated with Phase I of the project, which
generally encompassed the Coast Guard headquarters and groundwork for the rest of the consolidated headquarters
campus.
39 U.S. Department of Homeland Security, DHS Headquarters Consolidation Congressional Staff Tour/Update, July
27, 2012, p. 4.
40 Author’s conversations with DHS and GSA officials, November 16, 2011.
Congressional Research Service
8

DHS Headquarters Consolidation Project: Issues for Congress

due to current industry escalation standards, which indicate annual increases between 5 and 12
percent through 2017.”41
FY2013 Appropriations
The Administration’s FY2013 budget request for the Department of Homeland Security includes
$89 million for construction related to St. Elizabeths, and $24.5 million for the Coast Guard to
cover operational transition costs for the move to the new facility. The GSA budget includes no
funding request for the project. However, it is noteworthy that the DHS budget justification
indicated the request is “to construct I-295/Malcolm X Avenue interchange improvements and
West Campus access road extension from Gate 4 of the U. S. Coast Guard Headquarters Building
to Malcolm X Avenue.”42 Funding for this type of infrastructure, which in this case supports
access to multiple federal facilities aside from the St. Elizabeths campus, has traditionally been
requested and provided in the GSA budget.
The House Appropriations Committee recommended no funding for the highway interchange or
any part of the St. Elizabeths project through the management accounts, noting in its report the
irregularity of funding a highway interchange through the Homeland Security bill. The bill does
provide the Administration’s requested funding for the Coast Guard. In addition, $10 million is
provided through the Coast Guard’s construction budget to provide additional support for the
project.
In the report accompanying H.R. 5855, the committee noted the following:
The Committee recommends no new construction funding in the bill for new Departmental
Headquarters Consolidation expansion. This is $89,000,000 below the request. Funding is
included, as requested, as part of the Coast Guard appropriation to cover the costs associated
with completing the move of the Coast Guard headquarters to St. Elizabeths. Associated with
this, as described below, is additional funding under Coast Guard construction to ensure
completion of the current project, improve site access, and support analysis for follow on
work and any necessary planning adjustments for schedule, scope, and cost.

The Committee understands that the Department … is actively exploring options to
creatively modify or consolidate current leases, in the expectation that a permanent
headquarters construction site will be significantly delayed or amended. The Committee
encourages the Department to continue this effort and to inform the Committee of its
progress in consolidation no later than 90 days after the date of enactment of this Act,
including a revised schedule and cost estimates. Further, as noted above, the Committee
includes $10,000,000 under the Coast Guard Acquisition, Construction, and Improvements
account to complete Phase 1 of construction, ensure Coast Guard will be able to move in

41 Borras, Rafael, DHS Under Secretary for Management, written testimony, “Department of Homeland Security
Facilities Hearing,” before the House Appropriations Committee Homeland Security Subcommittee, March 21, 2012.
Available at http://www.dhs.gov/news/2012/03/29/written-testimony-under-secretary-management-rafael-borras-
house-appropriations.
42 U.S. Department of Homeland Security, Fiscal Year 2013 Congressional Justification, Departmental Management
and Operations, DHS Headquarters Consolidation Project, Washington, DC, February 13, 2012, p. 5.
Congressional Research Service
9

DHS Headquarters Consolidation Project: Issues for Congress

2013 and that there will be no obstacles to access and transportation into the site, and to
support orderly planning and analysis for the overall project.43
In the minority views accompanying the report, the ranking members of the subcommittee and
full committee noted the following:
The bill also fails to provide the $89 million for site access, including necessary road and
interchange improvements, for DHS personnel to access the new DHS headquarters. The
new DHS headquarters project has been shortchanged over the past few years, causing
repeated schedule delays and increasing the costs from $3.4 billion to just over $4 billion if
all three phases are constructed. In the interim, the Coast Guard may be the only tenant at
this new facility for the next 3-5 years, as the bill funds only this relocation in 2013. The bill
does not include any funding for Phase 2, which was to begin construction for DHS central
headquarters and FEMA.44
The Senate Appropriations Committee recommended $89 million for the highway interchange,
although it was funded as a part of the Under Secretary for Management’s office through a
general provision rather than as a stand-alone appropriation in departmental operations as
requested. The committee also fully funded the Coast Guard’s operational transition costs for the
move. No funding was provided for the project through the Coast Guard construction budget. An
amendment45 was offered in full committee markup on May 22, 2012, to use the $89 million for
the highway interchange as an offset for an unrelated amendment. The amendment failed on a 15-
15 vote, and the funding remains in the reported version of the legislation.
In the report accompanying S. 3216, the committee noted the following:
Pursuant to section 549, a total of $89,000,000 is provided for ‘‘Office of the Under
Secretary for Management’’ for costs associated with headquarters consolidation and
mission support consolidation. The Under Secretary shall submit an expenditure plan no later
than 90 days after the date of enactment of this act detailing how these funds will be
allocated, including a revised schedule and cost estimates for headquarters consolidation.
Quarterly briefings are required on headquarters and mission support consolidation activities,
including any deviation from the expenditure plan. According to the Department, an updated
plan is being developed in coordination with the General Services Administration to
complete the headquarters consolidation project in smaller, independent segments that are
more fiscally manageable in the current budget environment. The Department expects this
updated plan to be completed by the end of summer 2012 and it is to be submitted to the
Committee upon its completion. The Committee expects the plan to identify the discrete
construction segments, the associated resource requirements for each segment, and the
proposed timeline for requesting funding to complete each segment.46
Other Congressional Action
During its hearings on the FY2013 budget request the House Appropriations Committee’s
Homeland Security Subcommittee held a hearing on DHS facilities, focusing on two major DHS
construction projects for which funding has been sought in recent years with limited success: the

43 H.Rept. 112-492, pp. 19-20.
44 H.Rept. 112-492, p. 204.
45 Senator Dan Coats and Senator Kay Bailey Hutchison
46 S.Rept. 112-169, p. 20.
Congressional Research Service
10

DHS Headquarters Consolidation Project: Issues for Congress

consolidated headquarters project and the National Bio- and Agro-defense Facility. Subcommittee
Chairman Robert Aderholt pointed out that both projects “are complex and expensive
undertakings with multi-year timelines,” and “are also operating under significantly tighter
budgets than anticipated when planning began several years ago.” He went on to say that
Congress “must take a more realistic look at [the St. Elizabeths project] and balance delays
against possible cost increases,” while asking DHS for minimum funding requirements and
alternative solutions.47
Prior to the completion of the FY2012 appropriations process, on September 23, 2011, the House
Committee Transportation and Infrastructure’s Subcommittee on Coast Guard and Maritime
Transportation held a hearing to review the status of the DHS headquarters consolidation project,
focusing on the move of the Coast Guard to the new location, and the effect it would have on the
Coast Guard’s budget and operations. The subcommittee chairman noted that in 2006, the Coast
Guard authorization bill required GSA to provide in its master plan for another agency of DHS to
move to St. Elizabeths at about the same time. This was done out of concern that the Coast Guard
would be “isolated” at the Anacostia site, both in the sense of continuing the pattern of
fragmentation of DHS component headquarters, and the lack of needed road infrastructure to
access the site, which he noted was a long-standing concern of the subcommittee.48 The
subcommittee ranking member noted that “No one’s questioned the need to complete the
consolidation. For that matter, no one…has seriously proposed its termination.” He went on to
say that not funding the project would lead to “a DHS that is less efficient, less coordinated and
less effective than it could be if this project was successfully completed.”49
S. 1546, the Department of Homeland Security Authorization Act of 2011, which was marked up
by the Senate Homeland Security and Governmental Affairs Committee on September 21, 2011,
included a section on DHS headquarters consolidation, directing that DHS consolidate its
headquarters function at St. Elizabeths no later than the end of FY2018, and that all remaining
departmental components and activities that be consolidated “to as few locations within the
National Capitol [sic] Region as possible.”50
There is a comparatively high volume of commentary on the legislative record regarding the DHS
headquarters consolidation project from the appropriations committees relative to the authorizing
committees and individual members. The appropriators generally respond to the Administration’s
annual requests for funding in a specific fashion and often with an explanation of their position,
and therefore touch on most topics that have funding needs associated with them on an annual
basis. The authorizers do not necessarily present legislation and accompanying reports on a
specific topic like this each year, and floor time dedicated to this particular issue has been limited.
Members of the House and Senate have a variety of ways to express their position on a particular
issue, many of which are not readily available for analysis. Therefore, an absence of on-the-

47 Representative Robert Aderholt, opening statement to “Department of Homeland Security Facilities Hearing,” before
the House Appropriations Committee Homeland Security Subcommittee, March 21, 2012.
48 Representative Frank LoBiondo, opening statement to “Review and Status of the Multibillion-Dollar Department of
Homeland Security Relocation Project in Washington, DC, and its Impacts on the U.S. Coast Guard,” House
Transportation and Infrastructure Subcommittee on Coast Guard and Maritime Transportation, September 23, 2011, p.
1.
49 Rep. Rick Larsen, opening statement to “Review and Status of the Multibillion-Dollar Department of Homeland
Security Relocation Project in Washington, DC, and its Impacts on the U.S. Coast Guard,” House Transportation and
Infrastructure Subcommittee on Coast Guard and Maritime Transportation, September 23, 2011, p. 3.
50 Sec. 211, S. 1546.
Congressional Research Service
11

DHS Headquarters Consolidation Project: Issues for Congress

record commentary does not necessarily reflect the degree of concern with, support for, or
opposition to the project.
Considerations for Congress
Implications of the Consolidated Headquarters Project
Consolidating DHS headquarters anywhere would change the department’s current operating
patterns in the National Capital Region. These changes would have operational, budgetary and
cultural implications for DHS, and the consolidation vision presented in the St. Elizabeths project
would provide its own particular texture to these changes.
Operations
Consolidating the headquarters components of DHS at a single site would facilitate both
“vertical” coordination between departmental and component leadership and “horizontal”
coordination among the department’s components. With headquarters functions operating in
spaces designed for a unified department, the structural hurdles to coordination are lowered.
Having a single campus makes collaboration with other components easier to accomplish and can
facilitate more effective departmental leadership.
The lack of a consolidated headquarters has hindered the development of a cohesive, maximally
effective department in the eyes of some observers close to DHS.51 Former Coast Guard
Commandant Thad Allen testified on July 12, 2012 before the Senate Committee on Homeland
Security and Governmental Affairs:
In the Washington Area the Department remains a disjointed collection of facilities and the
future of the relocation to the St. Elizabeths campus remains in serious doubt. One of the
great opportunity costs that will occur if this does not happen will be the failure to create a
fully functioning National Operations Center for the Department that could serve as the
integrating node for departmental wide operations and establish the competency and
credibility of the Department to coordinate homeland security related events and responses
across government as envisioned by the Homeland Security Act. As with the mission support
functions discussed earlier, the Department has struggled to evolve an operational planning
and mission execution coordination capability. As a result, the most robust command and
control functions and capabilities in the Department reside at the component level…
The combination of these factors, in my view, has severely constrained the ability [of] the
Department [to] mature as an enterprise. And while there is significant potential for
increased efficiencies and effectiveness, the real cause for action remains the creation of
unity of effort that enables better mission performance. In this regard, there is no higher

51 For example, Rep. Bennie Thompson, opening statement to “Consolidating DHS: An Update on the St. Elizabeths
Project,” hearing before the Subcommittee on Management, Investigations, and Oversight of the Committee on
Homeland Security, House of Representatives, March 26, 2009, available at https://www.hsdl.org/?view&did=25147;
and Chertoff, Michael, “The Department of Homeland Security: Past, Present, and Future,” at the Aspen Security
Forum, July 28, 2012. Video available at http://aspensecurityforum.org/2012-video-day-3.
Congressional Research Service
12

DHS Headquarters Consolidation Project: Issues for Congress

priority than removing barriers to information sharing within the department and improved
operational planning and execution.52
National Operations Center
Currently, DHS operates a National Operations Center (NOC) at the Nebraska Avenue Complex.
However, its ability to provide a robust command and control function and coordinate federal
government incident response to an incident is constrained by its limited size and infrastructure.
Establishment of the type of NOC described in Admiral Allen’s testimony would have direct
impact on both day-to-day and crisis operations of the department. Establishment of a new NOC
was recommended in The Federal Response to Katrina: Lessons Learned, the White House’s
extensive after-action report from the hurricanes that hit the Gulf Coast in 2005. The report’s
specific recommendation is as follows:
In order to strengthen DHS’s operational management capabilities, we must structure the
Department’s headquarters elements to support the Secretary’s incident management
responsibilities. First and most important, Federal government response organizations must
be co-located and strengthened to manage catastrophes in a new National Operations Center
(NOC). The mission of the NOC must be to coordinate and integrate the national response
and provide a common operating picture for the entire Federal government.53
In addition, under the plan for the consolidated headquarters, the new NOC would be co-located
with the operations centers of the individual DHS components. In Homeland Security:
Opportunities Exist to Enhance Collaboration at 24/7 Operations Centers Staffed by Multiple
DHS Agencies
, GAO agreed that DHS’s plans to co-locate its headquarters, its component
headquarters and their respective staffs and operations centers at one location “could further
enhance collaboration among DHS’s component agencies,” along with adoption of other key
practices.54 DHS has further indicated that increased operational effectiveness would result from
the co-location of operations centers, and real estate efficiencies could be found from shared
common functions, support rooms, and incident management spaces.55
The establishment of a new, more capable NOC without the presence of a consolidated
headquarters would be difficult. The consolidated headquarters project brings, for the first time,
the executive leadership of the department and a leadership presence from all its components
together. Without consolidation, the NOC would necessarily be separated from either the
executive levels of DHS or the leadership of components implementing the response.

52 Statement of Thad W. Allen, Admiral, U.S. Coast Guard (retired), “The Future of Homeland Security: The
Evolution of the Homeland Security Department’s Roles and Missions,” Senate Committee on Homeland Security and
Government Affairs, 112th Cong., 1st sess., July 12, 2012. Available at http://www.hsgac.senate.gov/hearings/the-
future-of-homeland-security-the-evolution-of-the-homeland-security-departments-roles-and-missions.
53 The White House, The Federal Response to Katrina: Lessons Learned, Washington, DC, 2006, pp. 69-70.
54 GAO-07-89, Homeland Security: Opportunities Exist to Enhance Collaboration at 24/7 Operations Centers Staffed
by Multiple DHS Agencies,
October 2006, p. 8.
55 E-mail from DHS Legislative Affairs, September 4, 2012. Available from author on request.
Congressional Research Service
13

DHS Headquarters Consolidation Project: Issues for Congress

Physical Facility Security
One operational question that arises in relation to this project is the advisability of a consolidated
headquarters capacity from a security standpoint. Does consolidating the leadership of DHS at a
single facility make it easier to secure, a more appealing target for efforts to disrupt it, or both?
In 1995, the Interagency Security Committee (ISC) was established by Executive Order 12977,
and tasked with establishing policies for security of federal facilities, including developing and
evaluating security standards. In 2003, it became part of DHS.
There are five levels of security standards for federal office buildings. Under the standards
developed by the ISC, the proposed consolidated DHS headquarters would be classified as a
Level V facility, the highest level on the scale. Buildings at this level are similar to those at the
next level below in that they occupy more than 150,000 square feet and host more than 450
employees. The distinguishing characteristics of Level V facilities are that their missions “are
considered critical to national security,” and the buildings themselves are “high threat/high profile
facilities.”56
While the operators of Level V facilities customize their facility security to meet their mission
needs, minimum standards for this type of facility include 100-foot perimeter setbacks, 100-foot
separation between parking facilities and buildings, and protected ventilation equipment (located
away from high-risk areas) for the buildings.57 It is impossible for DHS to ensure this level of
security for all its headquarters components in its current state of dispersal across the National
Capital Region. The status quo would leave parts of the headquarters function in facilities that do
not meet Level V security standards. While the Nebraska Avenue Complex (NAC), where the
Secretary’s Office is currently located provides Level V security,58 it is too small to accommodate
the needs of a consolidated headquarters outlined in the master plan.
Planning documents indicate that part of the reasoning behind the selection of the St. Elizabeths
site was the ability to implement Level V security standards at this particular location.59 The St.
Elizabeths site was the only site in the District able to accommodate the office space requirement
and the security standards.60
The security question extends beyond DHS headquarters’ offices. These offices, for the most part,
do not have the same level of security as the NAC, and often occupy leased office space in
commercial buildings. If they are targeted by terrorist violence, it is likely neighboring offices,
buildings and their personnel could be affected.
CIA headquarters and the Pentagon are high profile, consolidated headquarters that are
considered Level V facilities. Both have been the targets of terrorist attacks. In the cases of
attacks on both facilities, collateral damage was limited. If attacks using similar methodologies
were carried out against DHS headquarters functions in their current locations, collateral damage

56 GSA, “DHS Headquarters Consolidation Location Analysis,” September 2008, pp. 9-10.
57 Ibid, pp. 11-12.
58 E-mail from DHS Legislative Affairs, August 8, 2012.
59 In a side note, according to briefings by DHS officials, use of the site by DHS also will also contribute to the security
of government communications and military facilities that the site overlooks.
60 Ibid, p. 15-63.
Congressional Research Service
14

DHS Headquarters Consolidation Project: Issues for Congress

would likely be greater due to the lack of separation of the DHS elements from the general
population. For example, in February, 2010, a man flew a private plane into a commercial office
building housing IRS offices in leased space. While the IRS was his intended target, the crash and
fire affected other tenants in the building, including multiple non-federal businesses.61
It is also worth noting that both Level V facilities continued to operate in the face of the attacks. It
is unlikely that targeted DHS offices with lower levels of security would be able to do the same.
One question would then seem to be, as there is already a Level V facility for part of DHS
headquarters, does consolidating the headquarters function at St. Elizabeths further raise the
profile of DHS, and make it a more likely target? This seems unlikely—DHS is already the third
largest component of the federal government and is a well-known entity domestically and
overseas. While the new headquarters would be larger, and parts are visible from a distance, it can
be argued that the facility is no more intrusive than other defense-related facilities along the
Potomac and Anacostia, the campus benefits from a significant setback, and the campus may be
deemed a harder target than DHS’s existing facilities as it was planned and built with DHS’s
needs in mind.
Regardless of whether the department’s profile would be higher at St. Elizabeths, the essential
question is whether whatever additional security risk that is entailed by consolidation is
counterbalanced by whatever other operational, budgetary and cultural benefits may accrue,
including the additional protection afforded headquarters elements currently outside the NAC that
move to the new facility.
Budget
Priorities
In previous years, the St. Elizabeths project was treated as a high priority for the Administration.
However, the last time current DHS Secretary Janet Napolitano mentioned headquarters
consolidation in testimony for Congress was before the Senate Homeland Security and
Governmental Affairs Committee on February, 2011, when she testified that the department
“propose[d] to delay construction of the Federal Emergency Management Agency (FEMA)
headquarters at St. Elizabeths as well as the deferral of other office co-locations, and building
maintenance and enhancements to prioritize frontline security operations.”62 While a lower public
profile for the project might be considered simply a change in legislative tactics, in September
2011, as Congress was working on the FY2012 appropriations bills, Secretary Napolitano said:
With respect to DHS, yes, I expect we will flatten out and that’s—that’s not surprising. I
mean, at the beginning of a department, of course you’re going to be putting in more and
more money until you get things kind of established and set up. There are things we’d like to
do that are going to have to be postponed. St. Elizabeths is a good example, that’s supposed
to be our headquarters. We will have to postpone that... I’d rather have the money to

61 Furness, Ashley and Jacob Dirr, “City and County Dedicate Web Site to Austin Plane Crash,” February 18, 2010.
http://www.bizjournals.com/austin/stories/2010/02/15/daily41.html?page=all
62 Statement of The Honorable Janet Napolitano, Secretary, United States Department of Homeland Security, “The
Homeland Security Department's Budget Submission for Fiscal Year 2012,” Senate Committee on Homeland Security
and Governmental Affairs, 112th Cong., 1st sess., February 17, 2011.
Congressional Research Service
15

DHS Headquarters Consolidation Project: Issues for Congress

complete building a National Security Cutter for the Coast Guard and support the Secret
Service in its activities, and sustain our efforts at the border [rather] than [have] a new
building, and so that is why St. Es is on the chopping block for now. I think ultimately it will
happen, but not now.63
The DHS Chief Financial Officer released the following statement shortly thereafter:
The Secretary’s comments that the DHS Headquarters Consolidation Project [is] on the
“budget chopping block” was in context of a conversation on how congressional budget cuts
are impacting the Department. The Administration is committed to building a new
headquarters for the Department in DC and will continue to work with Congress to move this
project forward while maintaining frontline operations. However, we are revisiting the
original assumptions on the use of the space as St. Elizabeth’s [sic] based on projected
budgets and growth of the Department. 64
As the Secretary alludes to in the former statement, the headquarters consolidation project was
conceived in a different budget environment than exists today. At the time, projections for future
budgets could have more easily accommodated such a significant capital investment. The DHS
budget grew every year from the establishment of the department until it peaked in FY2010.
In the future fiscal environment influenced by the Budget Control Act65 (BCA), it is reasonable to
expect that the DHS budget will either remain relatively flat in nominal terms, or decline over the
near future. The Administration’s budget projections for the Department of Homeland Security
through FY2018 show an increase of $3.2 billion—barely 8%—over six years. While the
projections in the Administration’s budget request are not binding, the minimal increases
projected for FY2014-2018 indicate that a significant expansion in available budgetary resources
is not anticipated.66
This project is significantly affected not only by the DHS budget, but the GSA’s budget as well.
Over $2 billion of the initially projected $3.4 billion in project costs was to be borne by the GSA
through their budget.67 However, as shown in Figure 1, as with DHS appropriations, GSA
appropriations have not kept pace with the construction plan for the project. GSA’s budget faces
similar constraints as that of DHS. The amount appropriated for construction and acquisition of
facilities has declined from nearly $894 million in FY2010 to $50 million in FY2012.68 The
fallout from recent scandals over inappropriate use of taxpayer funds at GSA could make

63 Secretary of Homeland Security Janet Napolitano, press briefing, September 8, 2011, as recorded by Jason Miller of
Federal News Radio and provided to CRS. Partial quote available in Jason Miller and Julia Ziegler’s article, “DHS St.
E’s to be Victim of Budget Axe,” FederalNewsRadio.com, September 9, 2011. http://www.federalnewsradio.com/?
nid=741&sid=2534819
64 Staff memorandum to Members of the House Committee on Transportation and Infrastructure Subcommittee on
Coast Guard and Maritime Transportation, in re: Hearing on “Review and Status of the Multibillion-Dollar Department
of Homeland Security Relocation Project in Washington, DC, and its Impacts on the U.S. Coast Guard,” dated
September 16, 2011.
65 P.L. 112-25, 125 Stat. 240.
66 Budget of the United States Government, Fiscal Year 2013, p. 240.
67 Oral testimony of Robert Peck, Commissioner, Public Buildings Service, General Services Administration,
“Homeland Security Headquarters Facilities,” before the House Appropriations Committee’s Homeland Security
Subcommittee, March 25, 2010.
68 CRS Report R40801, Financial Services and General Government (FSGG): FY2010 Appropriations, coordinated by
Garrett Hatch, and CRS Report R42008, Financial Services and General Government: FY2012 Appropriations,
coordinated by Garrett Hatch, p. 63.
Congressional Research Service
16

DHS Headquarters Consolidation Project: Issues for Congress

increases to GSA’s budget politically unpalatable, and the growing backlog of construction needs
could create more competition for GSA’s limited construction budget.
Even in this environment of fiscal constraint, however, Congress and the Administration continue
to make affirmative choices to invest in a range of projects and services. The projected costs for
DHS headquarters at St. Elizabeths could be met within the bounds of a BCA-influenced budget,
or even a more limited one—the operative question is what level of priority is placed on this
project in the overall budget by the Administration and, ultimately, by Congress. This
prioritization could change significantly should the country be faced with another Katrina-scale
incident where the lack of a more capable department-level operations center appears to constrain
an effective federal response.
Overhead Savings
GSA and DHS have in previous years cited an estimated cost savings of $600 million over 30
years for the St. Elizabeths project. With the delays and cost increases described by Under
Secretary Borras, these numbers would need to be revised based on the Administration’s new
timetable and segmented approach if it is approved.
Generally speaking, government agencies pay lease costs to the GSA or private real estate owners
for the facilities they operate from. Reducing these costs by moving from leased properties to
government-owned facilities can free up additional resources, alleviating pressure from declining
agency budgets over the long term. The up-front costs of these projects in times of tightening
budgets can be difficult for agencies to absorb in formulating their budget requests or for
Congress to approve in the context of balancing other priorities, as the appropriations process
makes no accounting for longer term savings.
As DHS has been attempting to consolidate its headquarters functions and other offices, its
components that occupy leased space have faced another complicating factor. In testimony before
the House Appropriations Committee’s Homeland Security subcommittee, DHS noted that they
currently have 181 leases in 53 locations for headquarters components, 87% of which expire by
2016.69 As their leases have matured, they have added short term extensions so they can move to
the envisioned new facilities or to space freed up by the movement of other offices. Delays in the
completion of new space requires these offices to use more short term leases, which are more
expensive, and thus raise the department’s overhead costs.70 With budgeting tending toward an
environment where absorbing rising costs requires matching reductions in spending elsewhere,
this could in turn, reduce the funding available for front line operations.
Aside from savings from lower leasing costs, some savings are to be expected with a consolidated
headquarters from increased centralization of some support services. This should not be confused
with the benefits of a “shared services” model for supporting the department or federal
government. The use of shared services can generate efficiencies as well, but generally involves

69 DHS handout, “Schedule Impacts to Migration Plan,” distributed at “Department of Homeland Security Facilities
Hearing,” House Appropriations Committee Homeland Security Subcommittee, March 21, 2012.
70 Oral testimony of Robert Peck, Commissioner, Public Buildings Service, General Services Administration,
“Homeland Security Headquarters Facilities,” before the House Appropriations Committee Homeland Security
Subcommittee, March 25, 2010.
Congressional Research Service
17

DHS Headquarters Consolidation Project: Issues for Congress

developing a different internal managerial relationship between enterprise operations and support
functions, rather than simply consolidating them.71
Culture
“One DHS”
One common line of thought among secretaries of the department from the very beginning has
been the need to fuse the diverse components of the department into a single unit—development
of “one DHS.”72 However, the department has yet to accomplish this goal. As retired Coast Guard
Commandant Admiral Thad Allen testified before the Senate Homeland Security and
Governmental Affairs Committee, “There has been hesitancy by components to relinquish control
and resources to a Department that appears to be still a work in progress.”73
The question of whether the Department of Homeland Security should exist is not currently the
focus of congressional debate. Although no authorization bill for the entire department has passed
either chamber since the department was established, it is also true that no legislation to
fundamentally alter the structure of DHS has been marked up since December, 2010.74 Current
issues include defining and refining the department’s mission, and ensuring that the department
can perform these missions effectively and efficiently. However, the persistence of some
components’ organizational structures from the pre-DHS era, the lack of integration between
components with similar missions, and statements by prominent political figures75 suggest that
the issue is not completely settled.
Completion of a consolidated headquarters and co-location of headquarters functions is not
sufficient to create the unified department with strong integrated management capacity across its
components that is sought by Congress and the Administration. A repeated theme found in GAO
analyses and in observations of witnesses testifying before the department’s oversight committees
is that successful integration of the department will take a long time to accomplish and require
ongoing effort to maintain once it is achieved. Cathleen Berrick, in her capacity as Managing
Director for Homeland Security and Justice Issues for the Government Accountability Office
(GAO) had this to say in testimony before Congress on this particular challenge:
In 2003, we designated the implementation and transformation of DHS as high risk because
it represented an enormous and complex undertaking that would require time to achieve in an
effective and efficient manner, and it has remained on our high-risk list since. We reported
that the components that became part of DHS already faced a wide array of existing
challenges, and any failure to effectively carry out the department’s mission would expose

71 Accenture, “Beyond Centralization: Deriving High Performance Through Fully Realized Shared Services,” 2007, p.
5.
72 Booz Allen Hamilton and Partnership for Public Service, “Securing the Future: Management Lessons of 9/11,”
August, 2011, p. 7.
73 ADM Thad W. Allen, USCG (ret.), written testimony before the Senate Committee on Homeland Security and
Governmental Affairs, “The Future of Homeland Security: The Evolution of the Homeland Security Department’s
Roles and Missions,” July 12, 2012, p. 7.
74 CRS analysis of Legislative Information System data as of September 18, 2012.
75 Lee, Tony, “Gingrich Hopes New Contract Will Re-Energize Campaign,” Human Events, October 3, 2011, p. 10.
Laing, Keith, “George McGovern calls for eliminating TSA, Homeland Security,” The Hill, November 17, 2011.
Congressional Research Service
18

DHS Headquarters Consolidation Project: Issues for Congress

the nation to potentially serious consequences. In designating the implementation and
transformation of DHS as high risk, we noted that building an effective department would
require consistent and sustained leadership from top management to ensure the
transformation of disparate agencies, program, and mission into an integrated organization,
among other needs. Our prior work on mergers and acquisitions, undertaken before the
creation of DHS, found that successful transformations of large organizations, even those
faced with less strenuous reorganizations than DHS, can take years to achieve.76
The departmental leadership is aware of this challenge. Speaking at a hearing before the Senate
Judiciary Committee, Secretary Napolitano noted:
We continue to excavate differences in systems and cultures and protocols and procedures.
There has been a lot accomplished over the past nine years by my two predecessors, and over
the past three-plus years now that I’ve been Secretary.
But given the size and scope of the merger that is underway, it does take time. The
Department of Defense took, by most accounts, 40 years to really become unified as a
department. My goal is to substantially beat that record.77
Consolidation of headquarters functions can contribute to this effort, and some observers believe
it is a necessary step, but it is no “magic bullet” for the issues facing the department. The
Department as recently as 2011 viewed consolidation of DHS headquarters operations as only one
of seven key initiatives to integrate its management functions.78
Morale
Morale issues at DHS have been a matter of concern for both congressional authorizers and
appropriators. Some observers have commented that DHS’s low employee morale could be
exacerbated by the lack of a unified organizational culture, one of the problems a consolidated
headquarters was intended to address.
The most recent documentation of the comparatively low morale at the department can be found
in the Partnership for Public Service’s “Best Places to Work in the Federal Government”79
analysis based on questions from the Office of Personnel Management’s FedView survey of
federal employees. There was no data reported from the OPM survey80 to either directly confirm
or refute the idea that headquarters consolidation would have an impact on morale. In fact, the
issue of the adequacy of departmental facilities was not directly raised in the survey questions.
However, attitudes of DHS component staff reflected in several questions from the FedView
survey could be reasonably expected to be impacted by the projected benefits of a consolidated

76 Statement of Cathleen Berrick before the Subcommittee on Oversight of Government Management, the Federal
Workforce, and the District of Columbia, U.S. Senate Committee on Homeland Security and Governmental Affairs,
September, 30, 2010 (GAO-10-911T), pp. 1-2
77 Napolitano, Janet, response to question, “Oversight of the Department of Homeland Security” Senate Judiciary
Committee, April 25, 2012.
78 GAO Report GAO-11-278, pp. 93-94.
79 http://bestplacestowork.org/BPTW/rankings/
80 United States Office of Personnel Management, 2011 Federal Employee Viewpoint Survey: Empowering Employees,
Inspiring Change
, Washington, DC, September 22, 2011, pp. 35-38, http://www.fedview.opm.gov.
Congressional Research Service
19

DHS Headquarters Consolidation Project: Issues for Congress

headquarters. For example, for those relocating to St. Elizabeths, the new headquarters is
designed to include daycare facilities. This could be expected to improve the department’s
bottom-ranking scores linked to family-friendly culture and benefits among that group of
employees. It is also possible that existence of a consolidated headquarters could change
perceptions or performance of leadership more broadly across the department. However, issues of
pay, advancement, diversity and matching employee skills to their missions would likely remain
unaffected.81
Congressional decisions on capital investments in the department such as headquarters
consolidation could be perceived by the employee base as an indirect validation or criticism of
the department’s work by Congress, or as a measure of the effectiveness of the departmental
leadership in representing DHS interests before Congress.
Options
When Congress considers appropriations or authorization for the department, it could take a
number of different approaches to the DHS headquarters consolidation process. The following
five examples of possible ways forward are discussed below:
• Termination and site disposal—choosing to invest no further funding in a DHS
presence and not having them occupy the St. Elizabeths campus;
• Completion of Coast Guard Headquarters only—consolidating the Coast Guard
headquarters on the St. Elizabeths campus, but not proceeding with the rest of the
project;
• Coast Guard Headquarters, Operations Center and Management—consolidating
the Coast Guard headquarters on the St. Elizabeths campus, and proceeding with
the next phase;
• Rescoping Coast Guard Headquarters—using the new facility originally intended
for the Coast Guard as the site of a rescoped DHS headquarters; and
• Expediting project completion—going beyond the existing funding request and
taking steps to accelerate full consolidation.
Termination and Site Disposal
If Congress believes that consolidating DHS headquarters at St. Elizabeths is no longer
appropriate, and that in light of that, consolidating Coast Guard headquarters in Anacostia would
not have a beneficial effect, it could choose to cease funding for the project altogether and
legislatively bar the Coast Guard from occupying the new building. If Congress were to pursue
this option, and the proposed highway infrastructure project could be deferred.
Under this option, the Coast Guard would not move into its new facility, and would have to
identify new headquarters facilities on an expedited basis. DHS headquarters functions would
remain distributed across the National Capital Region. The department’s headquarters would still

81 The Partnership for Public Service, “The Best Places to Work in The Federal Government,” 2011. Rankings for the
Department of Homeland Security as downloaded from http://bestplacestowork.org/BPTW/rankings/detail/HS00 on
May 15, 2012.
Congressional Research Service
20

DHS Headquarters Consolidation Project: Issues for Congress

be heavily reliant on leased space for its real estate needs, which in addition to bearing higher
costs than federally-owned space, would run counter to the government’s stated preference to use
federal owned space for national security real estate needs.
GSA would still need to maintain the St. Elizabeths campus until another use is identified for it
and the nearly-completed building intended for the Coast Guard, or the property is disposed of.
This would entail continued costs to GSA,82 and disposal would be complicated by the St.
Elizabeths’ status as a National Historic Landmark, and the security concerns of the White House
Communications Agency (WHCA), which has facilities overlooked by the St. Elizabeths campus.
It seems highly unlikely the Federal government would recover its investment in the property.
Completion of Coast Guard Headquarters Only
Congress may not choose to invest further in the consolidated headquarters for DHS due to
budget constraints or a desire for DHS to rethink the consolidated headquarters model. However,
it may choose to fund completion and operational transition costs for the Coast Guard to occupy
their portion of the facility, to ensure more of a return on the investment already made in the site
than expected under the above-described termination option.
This would satisfy the Coast Guard’s immediate needs for headquarters space, and provide
operational benefits, as their new headquarters would be a single facility built expressly for them,
as opposed to their current situation—multiple leased offices on different sites not built to their
specifications.83 However, it is worth noting that the campus would have been designed
differently for the Coast Guard as a single tenant—shared facilities at the campus center would
have been moved to the Coast Guard building to minimize the footprint, and costly upgrades to
the campus utility infrastructure to support follow-on phases of the consolidation would not have
been made. Capital costs would still be incurred to establish a new security perimeter for the
scaled-down facility, but these would be significantly less than the costs of completing the St.
Elizabeths project as envisioned. This option would bring the Coast Guard headquarters into
compliance with GSA’s practice of putting its secured areas for national security in federally
owned facilities.
The more modern and capable facility could have positive impacts on the morale of the Coast
Guard, although this could be balanced by perceptions of the new headquarters being isolated due
to its location, which would not be near other DHS components or connected to other federal
facilities. It could also have a negative impact on departmental cohesiveness, as the remainder of
the department’s headquarters functions would still remain at existing distributed facilities on
short-term leases.

82 Oral testimony of Robert Peck, Commissioner, Public Buildings Service, General Services Administration, “Review
and Status of the Multibillion-Dollar Department of Homeland Security Relocation Project in Washington, DC, and its
Impacts on the U.S. Coast Guard,” House Transportation and Infrastructure Subcommittee on Coast Guard and
Maritime Transportation, September 23, 2011. Available at http://www.gpo.gov/fdsys/pkg/CHRG-112hhrg68482/pdf/
CHRG-112hhrg68482.pdf.
83 Oral testimony of VADM John Currier (USCG), Deputy Commandant for Mission Support, “Review and Status of
the Multibillion-Dollar Department of Homeland Security Relocation Project in Washington, DC, and its Impacts on
the U.S. Coast Guard,” House Transportation and Infrastructure Subcommittee on Coast Guard and Maritime
Transportation, September 23, 2011. Available at http://www.gpo.gov/fdsys/pkg/CHRG-112hhrg68482/pdf/CHRG-
112hhrg68482.pdf.
Congressional Research Service
21

DHS Headquarters Consolidation Project: Issues for Congress

The proposed highway infrastructure project could be deferred, as it is needed to address
anticipated traffic volume from later phases of the project. GSA would still need to maintain
portions of the St. Elizabeths campus until another use for the remaining property is identified, or
the property is disposed of. As in the termination scenario, this would entail continued costs to
GSA, and disposal would be complicated by the status of St. Elizabeths as a historic property.
Security concerns of WHCA would be mitigated somewhat by the presence of the Coast Guard
on part of the property, although the interim fence line providing security for the Coast Guard
headquarters would not encompass all potentially sensitive areas of the property.
Coast Guard Headquarters, Operations Center, and Management
If Congress chooses to support further DHS consolidation at St. Elizabeths, including the post-
Katrina recommendation to establish a more capable department-wide operations center, but not
fund the remainder of the project as envisioned due to budget constraints, it could choose to go
beyond the above scenario. The next step would be to provide additional funding for completion
of the departmental operations center and the renovation of the necessary buildings to relocate the
executive-level departmental management to the St. Elizabeths campus.
This would address the single operational concern raised repeatedly by Admiral Allen—namely,
the lack of the department-wide operations center. While funding the reuse of the existing
historical buildings to house the Secretary’s offices would represent a significant investment and
would not generate all the management efficiencies of the original project, this alternative could
allow for further consolidation to be reconsidered and funded at a future time. It would also
leverage part of the investment that has been made in campus infrastructure. Increasing the
number of personnel at the site would increase the need to improve the surrounding highway
system.
In terms of the cultural impact on the department, this option could show continuing progress
toward a more fully integrated DHS, although the end point of the project would remain unclear.
Given the evolving nature of best workplace practices, including increasing use of telecommuting
and shared office spaces, this could provide useful flexibility should DHS wish to significantly
revise its plan.
Rescoping Coast Guard Headquarters to House Other Elements
Congress could attempt to capture some of the benefits of headquarters consolidation with a
smaller up-front investment by mandating a reconfiguring of the Coast Guard headquarters as an
ad hoc departmental headquarters space. Under this scenario, the DHS Secretary’s office would
occupy part of the newly constructed space as would a departmental operations center. This
would provide a limited operational benefit—the 1.2 million square feet of space Coast Guard
headquarters will provide is newer, but with roughly the same overall space as the NAC—but at
the cost of disrupting Coast Guard headquarters functions that would remain divided, rather than
consolidated, and further delaying occupancy of the headquarters.
Given the limitations of trying to repurpose the already designed and constructed Coast Guard
space, it may well not be possible to establish a more robust departmental operations center than
already exists at the NAC for DHS under this scenario. Ceasing development of the consolidated
Coast Guard headquarters would deny the Coast Guard the operational benefits of their own
consolidated headquarters and could undermine the component’s morale.
Congressional Research Service
22

DHS Headquarters Consolidation Project: Issues for Congress

Expediting Project Completion
Congress could also choose to make this project a higher priority among those in the
discretionary budget and fund this project aggressively, in an attempt to expedite its completion
and salvage whatever savings are possible from coordinated construction of the remaining
elements.
This option would provide the maximum operational return, providing the infrastructure
requested by DHS in its plans for a consolidated headquarters. As such, if seen to completion,
pursuing this option could help reduce barriers to information flow, support coordinated planning
and promote the development of a “One DHS” culture. There is a question as to whether the
department’s six year old plans still adequately reflect the needs of present-day DHS, given the
changes in the DHS budget and changing workplace practices (such as the growth of telework).
It is difficult to assess the precise budgetary impact of this option, as the Administration has
indicated they are developing a new construction schedule and revised cost estimate. However, it
would clearly require a significant adjustment of priorities across the federal discretionary budget
to make room in the DHS and GSA allocations for a level of investment significantly higher than
what has been provided since FY2009. While this option could capitalize on some savings from
coordinated construction, many of those savings are no longer available.
Pursuit of this option could be interpreted as a statement that the general DHS structure is a
settled matter for Congress and could provide the benefits outlined in DHS’s justifications for this
project. However, there is no guarantee of improved departmental performance or enhanced
morale with this or any of these options.
Conclusion
In can be argued that the creation of DHS was a reaction to a national crisis. After years of
reaction, departmental reorganization, and increasing distance from the events that led to the
creation of the department, there are issues that remain from that more tumultuous time that have
yet to be addressed.84 The consolidation of DHS headquarters functions is one of those
unresolved issues. Congress and the department are operating in a different environment than
when the consolidation plan was originally drawn up, both in terms of the security threats the
nation faces and the budgetary situation. The Administration’s new proposal for St. Elizabeths
may fit these new realities better than the existing plan.
It is worth noting that any option Congress chooses—even an option to not make a decision on
the long-term fate of the project—will bear significant costs. The costs manifest themselves as
construction and move costs for a consolidated headquarters, continued rents for leases across the
National Capital Region for maintaining existing headquarters facilities, or the possible (and
more difficult to quantify) security, management, communications, logistics, and command and
control impacts presented by both the status quo or any proposed change. Given the size of the
department and the importance of its missions, how the DHS headquarters functions are housed
and managed will be an issue of congressional interest for years to come.

84 “The Department of Homeland Security: Past, Present and Future,” Panel Discussion at the Aspen Security Forum,
July 27, 2012. Video available at http://aspensecurityforum.org/2012-video-day-3.
Congressional Research Service
23

DHS Headquarters Consolidation Project: Issues for Congress

Appendix. History of Project Appropriations
Analysis of Fiscal Years with Denied Requests or Partial Funding
Appropriations for the DHS headquarters consolidation effort are carried in two bills: the
construction needs for the basic buildings and infrastructure are typically funded in the Financial
Services and General Government appropriations bill, through the General Services
Administration (GSA), while the mission-specific needs are typically funded through the
Homeland Security appropriations bill. Table A-1 at the end of the appendix provides a summary
of funding requested and ultimately appropriated for the consolidation of Coast Guard and DHS
headquarters at St. Elizabeths.
FY2007
In the course of developing the FY2007 appropriations bills, the House Appropriations
Subcommittee for Homeland Security stated that the initial proposal for Coast Guard
headquarters evolved into a consolidated headquarters project without answers being provided to
the committee on the reasoning behind the site choice, the full range of costs involved and what
components would move. The Committee rejected funding for the Coast Guard Headquarters
project in the report accompanying the bill.85 Roughly a month later, the Senate Homeland
Security appropriations report took a substantively similar position, which was echoed in the final
conference report. Both House and Senate appropriators were concerned that DHS was wasting
money on investing in the Nebraska Avenue Complex, which they would then abandon for a
newer, larger, more expensive headquarters at St. Elizabeths.86
When the House Appropriations Committee reported out the Transportation, Treasury and
Housing and Urban Development appropriations bill, which at the time included GSA, the
committee report for the bill also rejected the Coast Guard project, but on the basis of their belief
that the project would have little positive impact on the local community.87 The Senate
companion report was silent on the project, and the year ending continuing resolution (P.L. 110-5)
expressly denied funding for a Coast Guard Headquarters at St. Elizabeths.88
FY2008
For FY2008, the House Appropriations Committee recommended partial funding for the project,
while still expressing concerns about overinvesting in the Nebraska Avenue Complex and the
breadth of the St. Elizabeths project.89 The Senate also provided partial funding for the project,
but in the Consolidated Appropriations Act, 2008 (P.L. 110-161), $6 million was provided for
continuing improvements at the Nebraska Avenue Complex, rather than the $101 million

85 U.S. Congress, House Committee on Appropriations, Subcommittee on Homeland Security, Department of
Homeland Security Appropriations Bill, 2007
, Report together with Additional Views to accompany H.R. 5441, 109th
Cong., 2nd sess., May 22, 2006, H.Rept. 109-476 (Washington: GPO, 2006), pp. 15-16.
86 H.Rept. 109-699, pp. 118-119.
87 H.Rept. 109-495, p. 175.
88 P.L. 110-5, Revised Continuing Appropriations Resolution, 121 Stat. 57.
89 H.Rept. 110-181, p. 18-19.
Congressional Research Service
24

DHS Headquarters Consolidation Project: Issues for Congress

provided in the House bill for the NAC and St. Elizabeths or the $88 million provided in the
Senate for St. Elizabeths alone.90
In FY2008, the GSA appropriations were moved to the Financial Services and General
Government Appropriations Act, where they remain today. The House Financial Services
Appropriations Subcommittee expressed concern about the size of the Coast Guard project, and
about possible overinvestment in the NAC given the impending move, but did not explicitly
restrict funding for the projects, despite undesignated cuts to the accounts that would support the
projects.91 The Senate funded the requested projects in full, but in the final version of P.L. 110-
161, only $28 million in funding for the NAC remained.92
FY2011
No request was made for the St. Elizabeths project for FY2010 through either GSA or DHS. In
FY2011, the requested budget for the project was unmet, falling over half a billion dollars short
of the combined request, despite testimony before the House Appropriations Committee’s
Homeland Security Subcommittee about the urgency of the need and the potential long-term
budget savings.93 FY2011 appropriations for federal government operations were provided
through a year-long CR, which included $77 million for the headquarters consolidation project
through DHS.94 The GSA had requested $381 million for St. Elizabeths, ultimately provided $30
million to the project from the $82 million it received for construction projects nationwide under
the CR.95
FY2012
For FY2012, the Administration requested $215 million for headquarters consolidation through
the DHS budget, including $160 million for new construction at St. Elizabeths, and $55 million
for lease consolidation. They also requested $217 million in the General Services Administration
budget for the project through the Federal Buildings Fund, including funding for planned
highway alterations to provide better motor vehicle access to the campus.
The House did not fund the project in the House-passed DHS appropriations bill. In report
language, the Committee stated:
…[B]oth costs and schedule of the current project are matters of concern for the Committee.
In hearings the Committee held on the St. Elizabeths project in 2010, it became clear that
adequate cost controls were essential for this project … Yet costs have grown in a year from
$3,400,000,000 to $3,600,000,000 chiefly due to increases in the General Services

90 House Appropriations Committee Print, Consolidated Appropriations Act, 2008 (P.L. 110-161), Division E—
Department of Homeland Security Appropriations Act, 2008
, p. 1022.
91 H.Rept. 110-207, p. 63-64.
92 P.L. 110-161, Division D—Financial Services and General Government Appropriations Act, 2008, p. 828.
93 U.S. Congress, House Committee on Appropriations, Subcommittee on Homeland Security, Hearings, Part 2,
Homeland Security Headquarters Facilities, 111th Cong., 2nd sess., March 25, 2010 (Washington: GPO, 2010), pp. 333-
405.
94 P.L. 112-10, 125 Stat. 140.
95 Department of Homeland Security, “DHS Headquarters Consolidation: CRS St. Elizabeths Tour” slide deck,
November 16, 2011, p. 7.
Congressional Research Service
25

DHS Headquarters Consolidation Project: Issues for Congress

Administration share of the project. The Committee notes that dependence on GSA funding
requires coordination of funding and management, and that the proposed DHS request, even
if resources were available, would likely not coincide with necessary GSA funding.
Furthermore, delays are already being factored into the Department’s planning, as it has
projected it will postpone work on the FEMA section of the facility.96
In minority views included in the report, the ranking members of the House subcommittee and
full committee had a different perspective:
Of particular concern is the decision to provide no funding for the new DHS headquarters or
for the consolidation of leased property, a penny-wise and pound-foolish decision. Already,
based on the delay in finalizing the 2011 bill and the reduced resources provided in that bill
for DHS headquarters construction activities, the cost of the headquarters project has grown
by $200 million, from a total cost of $3.4 billion to $3.6 billion. The decision to deny an
additional $159,643,000 in 2012 to finalize construction of the first phase of the new
headquarters project and begin construction on the second phase will result in higher costs in
the out years and will delay, by at least one year, when the Coast Guard can move into its
new headquarters facility (phase one), which is already under construction.97
The Senate Appropriations Committee recommended $56 million in Title V of their version of the
DHS appropriations bill to complete the Coast Guard headquarters facility, $159 million (74%)
below the President’s requested funding level. The Senate Appropriations Committee also
expressed concern that limited funding would result in no other DHS headquarters components
using the St. Elizabeths campus, and included in their bill a requirement that DHS provide within
60 days of enactment an expenditure plan and an initial analysis of the mix of offices to be
housed at the headquarters complex.98
The House Appropriations Committee’s Financial Services Subcommittee rejected the
Administration’s entire $840 million request for construction and acquisition under GSA’s
Federal Buildings Fund. In zeroing out the request for construction, the report noted “Adding to
the Federal inventory of buildings is not welcomed at a time when the management and use of the
current inventory is less than optimal.”99 The chairmen of the House subcommittee and full
committee expressed concern about the deep cuts in GSA’s budget, noting that it reversed a
position taken by the current chamber majority in the FY2008 bill. However, the report does not
mention the DHS project specifically.
The Senate Appropriations Committee’s Financial Services Subcommittee provided $65 million
for the entire construction and acquisition activity at GSA, rather than the $840 million requested.
No mention is made in the bill or report of the DHS headquarters project.100
In the final consolidated appropriations bill for FY2012, the overall combined request of $377
million for GSA and DHS contributions to St. Elizabeths resulted in only $93 million in

96 H.Rept. 112-91, p. 16.
97 Ibid., p. 202.
98 S.Rept. 112-74, pp. 161-162.
99 U.S. Congress, House Committee on Appropriations, Subcommittee on Financial Services and General Government,
Financial Services and General Government Appropriations Bill, 2012, Report to accompany H.R. 2434, 112th Cong.,
1st sess., July 7, 2011, H.Rept. 112-136 (Washington: GPO, 2011), pp. 48-49.
100 The Senate Appropriations Committee Financial Services Subcommittee provided $65 million for the entire
construction and acquisition activity at GSA, rather than the $840 million requested
Congressional Research Service
26

DHS Headquarters Consolidation Project: Issues for Congress

appropriations, with $56 million provided to DHS to complete only the construction of the Coast
Guard portion of the headquarters.101 The remaining $37 million for the St. Elizabeths project
came from the $50 million GSA received for construction projects nationwide. DHS has indicated
that the GSA funding was inadequate to complete work as planned for the Coast Guard to occupy
its new headquarters, so several elements of Phase I have been delayed and the funding for those
elements redirected to ensure the needed work could be done.
Table A-1. DHS and GSA Appropriations for St. Elizabeths (FY2006-FY2012)
(in thousands of dollars of budget authority)
FY Dept.
Activity
Request
Appropriation
GSA
Coast Guard Consolidation
24,900
24,900
2006
GSA
St. Elizabeths West Campus Infrastructure
13,095
13,095

Total 37,995
37,995
GSA
Coast Guard Consolidation
306,139
0
GSA
St. Elizabeths West Campus Infrastructure
6,444
6,444
2007

GSA Subtotal
312,583
6,444
DHS
Coast Guard Headquarters (Operating Expenses)
50,200
0

Total 356,339
6,444
DHS Consolidation and Development of St. Elizabeths
GSA
Campus 318,887
0
GSA
St. Elizabeths West Campus Infrastructure
20,752
0
GSA
St. Elizabeths West Campus Site Acquisition
7,000
0
2008

GSA Subtotal
346,639
0
DHS
Consolidated Headquarters at St. Elizabeths
120,000
0

Total 466,639
0
DHS Consolidation and Development of St. Elizabeths
GSA
Campus 331,390
331,390
GSA
St. Elizabeths West Campus Infrastructure
8,249
8,249
GSA
St. Elizabeths West Campus Site Acquisition
7,000
7,000
2009

GSA Subtotal
346,639
346,639
DHS
Coast Guard/DHS Headquarters
120,000
97,578

Total 466,639
444,217
GSA
Consolidated Headquarters at St. Elizabeths
n/a
450,000
2009
DHS
Consolidated Headquarters at St. Elizabeths
n/a
200,000
(ARRA)

Total ARRA funds

650,000
2010
No
Request


2011
GSA
St. Elizabeths DHS Consolidation and Development
267,675
30,000

101 In their spending plan released on January 27, 2012, GSA indicated they would spend $37 million on the St.
Elizabeths project.
Congressional Research Service
27

DHS Headquarters Consolidation Project: Issues for Congress

FY Dept.
Activity
Request
Appropriation
GSA
St. Elizabeths West Campus Infrastructure
99,281
0
GSA
St. Elizabeths Historic Preservation Mitigation
4,990
0
GSA
St, Elizabeths Highway Interchange
8,350
0

GSA Subtotal
380,296
30,000
DHS
Consolidated Headquarters at St. Elizabeths
287,800
77,245
Total
668,096
107,245
GSA
St. Elizabeths Activities
100,000
0
GSA
St. Elizabeths East Campus Road Development
20,400
0
GSA
St. Elizabeths Highway Interchange
55,400
0
2012
GSA
St. Elizabeths West Campus Infrastructure
41,906
37,300

GSA Subtotal
217,706
37,300
DHS
Consolidated Headquarters at St. Elizabeths
159,643
55,979
Total
377,349
93,279
Source: CRS analysis of GSA and DHS budget request documents and appropriations conference reports.
Notes: GSA funding for headquarters consolidation and St. Elizabeth has been provided under multiple project
names over the course of the project. Subtotals are therefore included in the table for GSA. In FY2007, funding
for Coast Guard Headquarters consolidation was requested under Coast Guard Operating Expenses,
Headquarters Directorates. GSA provided $30 million in FY2011, designated for critical occupancy issues for the
Coast Guard and the first stages of the Departmental Operations Center. It was not attributed to specific
projects.


Author Contact Information

William L. Painter

Analyst in Emergency Management and Homeland
Security Policy
wpainter@crs.loc.gov, 7-3335

Congressional Research Service
28