Military Construction: Analysis of the FY2012 Appropriation and Authorization

July 13, 2011 (R41885)

Contents

Tables

Appendixes

Summary

This report focuses on those government activities funded under the FY2012 military construction appropriation, examines trends in military construction funding, and outlines military construction issues extant in each of the major regions of U.S. military activity.

President Barack Obama submitted his FY2012 appropriations request to Congress on February 14, 2011. His military construction appropriations request for $14.7 billion in new budget authority fell approximately $9.9 billion below the amount enacted for FY2010 and $3.0 billion below that enacted for FY2011. Much of that reduction came from military base closure accounts. Initiated in late 2005, the current base realignment and closure (BRAC) round is expected to conclude in September 2011. Funding needed in FY2010 and FY2011 for construction and movement of organizations will not be needed in FY2012 and subsequent years. In addition, the President requested less regular military construction for FY2012 than in earlier years. Finally, funding for construction supporting Overseas Contingency Operations (OCO, or active military operations in Iraq and Afghanistan), appropriations for which totaled $1.4 billion in FY2010 and $1.3 billion in FY2011, has been virtually eliminated, with only $217 million in the regular FY2012 appropriation requested for construction within U.S. Central Command (CENTCOM). The first military construction bill (H.R. 2055) was passed by the House on June 14, 2011.

Construction issues within the United States center on relocations associated with BRAC movements; the proposed transfer of a nuclear-powered aircraft carrier from Norfolk, VA, to Mayport, FL; the potential to move detainees from Naval Station Guantanamo; and the possible expansion of the Army's Piñon Canyon Maneuver Site.

In the Pacific region, topics of major interest include planned relocations of U.S. Marine forces within the Japanese Prefecture of Okinawa and from Okinawa to the U.S. Territory of Guam; movement of U.S. garrisons in the Republic of Korea; and normalization of duty there, which will lengthen tours and bring many more military families to Korea.

Troops are also moving within Europe and redeploying to the United States. Active duty military personnel stationed in Europe now number only one-quarter of the force present in 1980, and garrisons in Germany are being concentrated into two large military communities near Landstuhl and Vilseck. At least one major combat formation scheduled to move to the United States during the past few years has been retained at its garrison in Germany pending a military basing review.

Military responsibility for much of Africa is now exercised by U.S. Africa Command (AFRICOM). Though headquartered in Germany, AFRICOM has one enduring military garrison site on the continent, at Camp Lemonier, Djibouti. Press accounts have indicated that a new permanent home for AFRICOM headquarters might be located in southeastern Virginia.

Southwest Asia, the area of responsibility for CENTCOM, has seen ongoing military operations for almost a decade. Since FY2004, Congress has given DOD special authority to use some operations and maintenance funds for military construction outside of the normal appropriations process. Both House and Senate versions of the National Defense Authorization Act for 2012 would extend that authority into FY2012. Funds for military construction had been provided through special emergency supplemental appropriations, but beginning in FY2010, these funds were folded into the base budget—though still categorized separately from normal construction requests. CENTCOM construction has fallen with the FY2012 request.


Military Construction: Analysis of the FY2012 Appropriation and Authorization

Military Construction Funding Trends, FY2010-FY2012

Appropriations Overview

On February 14, 2011, President Barack Obama submitted to Congress his request for military construction appropriations to support federal government operations during FY2012, which will begin on October 1, 2011 (see Table 1). The timing of his request was unusual because it overlapped the congressional process of appropriating for government operations during FY2011. A full-year continuing appropriations bill (H.R. 1473, P.L. 112-10) that included military construction was enacted on April 15, 2011.

The House Committee on Appropriations introduced its Military Construction, Veterans Affairs, and Related Agencies Appropriations Act for 2012 (H.R. 2055) on May 31. The House began debate on June 2 and passed the bill on June 14, 2011. Debate and amendment on the House floor encompassed several provisions that could affect the cost of and competition for military construction projects. One debate centered on Section 415, which was eventually stricken by recorded vote, 204-203 (H.Amdt. 411, Roll no. 413). The section would have barred the use of military construction funds to enforce Executive Order 13502 (41 U.S.C. 251 note). This order permits executive agencies to specify that "project labor agreements" (PLA) be used on construction costing $25 million or more. These PLAs are pre-hire collective bargaining agreements with labor organizations that establish the terms and conditions of employment on specific construction projects.1 Another amendment, proposed on the floor, would have barred the imposition of Davis-Bacon prevailing wage standards on military construction projects. The motion was defeated in a recorded vote, 178-232 (H.Amdt. 413, Roll no. 414).2

The Senate received H.R. 2055 on June 15 and referred it to the Committee on Appropriations. The committee reported H.R. 2055 with an amendment in the form of a substitute on June 30, 2011. The bill was placed on the Senate Legislative Calendar under General Orders (Calendar N. 31). On July 11, a motion to proceed to consideration of the measure was made (Congressional Record, S4478), along with a cloture motion. With unanimous consent, the cloture motion was accepted and the motion to consider H.R. 2055 was withdrawn.

Table 1. Military Construction Appropriations Accounts by Title, FY2010-FY2012

(total budget authority in thousands of dollars)

Account

FY2010 Enacted
(P.L. 111-117)

FY2011 Full-Year Continuing Appropriation
(P.L. 112-10, Div B, Title X)

FY2012 Request

FY2012 House Bill (H.R. 2055)

FY2012 House Bill (H.R. 2055)

Grand Total, Title I

23,279,950

16,587,773

14,766,047

14,165,347

13,717,382

Grand Total, Title IV

1,398,984

1,222,852

Grand Total

24,678,934

17,810,625

14,766,047

14,165,347

13,717,382

Source: CRS calculation based on data appearing in Table A-1 and Table A-2.

Note: Appropriations figures portray total budget authority made available under the relevant bills. This includes New Budget Authority and rescinded appropriations and may differ from tables produced by others.

FY2012 Military Construction Authorization and Appropriations

Section 114 of Title 10, United States Code, requires that Congress authorize the appropriation of funding to the Department of Defense for certain purposes, including military construction, as part of the annual appropriations cycle. This authorization is effected through the enactment of the annual National Defense Authorization Act (NDAA), of which one division constitutes the Military Construction Authorization Act. The NDAA for FY2012 (H.R. 1540) was introduced in the House on April 14, 2011. The House Committee on Armed Services reported its amendment of the bill on May 17 (H.Rept. 112-78, with a supplemental report, H.Rept. 112-78, Part 2, submitted on May 23). The House passed the bill by recorded vote, 322-96 (Roll no. 375), on May 26, and the Senate received it on June 6, 2011, referring it to the Committee on Armed Services. The Senate Committee on Armed Services reported its version of the NDAA (S. 1253) on June 22.

In addition to authorizing military construction appropriations, the act provides additional authorities related to military construction and family housing. It routinely authorizes specific construction projects and land acquisitions, property improvements, and the like. It can also forbid various actions. For example, Section 2307 of the House version of H.R. 1540 would prohibit the disestablishment, closure, or realignment of any element of the Air Force's Air and Space Operations Center until the Department of the Air Force takes certain specified actions.3

The military construction appropriation, Title I of the Military Construction, Veterans Affairs, and Related Agencies Appropriations Act, pays for the building of new military facilities required for new weapons systems, including aircraft and naval vessels; the redeployment of military forces to new locations; the improvement of military living and working conditions; the reduction of facility operating costs; and the improvement of military productivity at both active and reserve component facilities. Military construction funds also pay for construction and movement of organizations mandated in base closure and realignment actions, and for the environmental remediation required for the disposal of defense real property as required by the base closure acts of 1988 and 1990, as amended.4

Another appropriation within the bill provides funding for the North Atlantic Treaty Organization (NATO) Security Investment Program (NSIP), which constitutes the U.S. contribution to a 28-nation collective account for the acquisition and construction of international collective defense facilities within the North Atlantic Treaty Area.

Other subaccounts finance costs associated with construction, improvement, operation, and leasing of all government-provided military family housing. The Family Housing Improvement Fund (FHIP) finances the DOD portion of the various public-private partnerships resulting from the privatization of much of the inventory of domestic military family housing under the Military Housing Privatization Initiative (MHPI) begun during the late 1990s. A separate account, the Unaccompanied Housing Improvement Fund, performs the same function for the barracks or dormitories that house single service members or those whose families do not relocate with a change of duty stations. The Homeowners Assistance Fund (HAF) was created during the mid-1960s to assist DOD family homeowners who are forced to sell their houses in markets depressed by base closures, but eligibility to apply for such assistance was temporarily expanded to include military members who purchased homes during the so-called "housing bubble" and who were ordered to change duty stations during the subsequent "housing crisis." The Secretary of Defense terminated this temporary eligibility late in 2010, as permitted under the enabling statute.

A final subaccount funds the construction of facilities at several chemical munitions depots. These munitions, such as nerve gases, have been banned from use in warfare by international treaty, and highly sophisticated industrial plants at select depots have been constructed to demilitarize (render non-lethal) and safely dispose of U.S. chemical munitions stockpiles. Construction for this program is nearing completion.

Titles II and III of the bill fund the benefits programs and operations of the Department of Veterans Affairs and several federal agencies, including the American Battle Monuments Commission, the Armed Forces Retirement Home, the U.S. Court of Appeals for Veterans Claims, and Arlington National Cemetery. These titles are not addressed in this report.5

Title IV was a temporary appropriation provision dedicated to military construction supporting "overseas contingency operations" (OCO), such as the ongoing ground force deployments to U.S. Central Command (CENTCOM). During the first years of active military engagement in CENTCOM, such construction was paid for through a series of emergency supplemental appropriations. In recent years, the Obama Administration has moved this funding into the regular appropriations process, designating it as "Title IV (OCO)" military construction. FY2012 marks the first year when no funds have been requested to fund OCO construction.6

On June 2, 2011, the House took up H.R. 2055, its version of the Military Construction, Veterans Affairs, and Related Agencies Appropriations Act for FY2012, passing an amended version on June 14. This bill would appropriate $14.2 billion in new budget authority for military construction and family housing. This would be a reduction of $0.6 billion (4.1%) below the presidential request, but this figure does not count $237.1 million in budget authority from previous appropriations that would be rescinded, effectively recycling funding into the new fiscal year. Therefore, the total military construction and family housing appropriation that would be enacted in this bill would come to $14.4 billion—$14.2 billion in new budget authority and $0.2 billion in unexpired, unobligated funds reclaimed from previous fiscal years.

The Senate received H.R. 2055 on June 15 and referred it to the Committee on Appropriations. On June 30, the committee reported the bill with an amendment in the form of a substitute, along with its written report (S.Rept. 112-29). The bill was introduced to the Senate on July 11 through a motion to consider that was accompanied by a cloture motion. The motion to consider was then withdrawn. The Senate amendment would appropriate $13.7 billion in new budget authority for military construction and family housing, $1.0 billion (7.1%) below the President's request.

Military Construction Funding Levels, FY2010-FY2012

As FY2010 expired at the end of September of that year, Congress passed the first of what would become eight continuing appropriations bills to fund FY2011.7 The initial continuing appropriation, while allowing for spending on military construction at a rate equal to that enacted for FY2010, barred DOD from initiating any new construction projects. Section 101 of the act permitted the continuation of projects that were provided for in the FY2010 appropriation, but Section 102 stated that no funds provided under the appropriation could be used to initiate any project "for which appropriations, funds, or other authority were not available during fiscal year 2010." This restriction was not lifted until the enactment of the Department of Defense and Full-Year Continuing Appropriations Act, 2011 (P.L. 112-10) on April 15, 2011, more than halfway into FY2011. The forced moratorium allowed Congress to reclaim some FY2011 funding through the rescission process and apply it to the FY2012 appropriation. The House began debate on the Military Construction Appropriations Act for FY2012 (H.R. 2055), on June 2, and passed the bill in its amended form on June 14, 2011.

Funding enacted for FY2010 and FY2011, the President's request for FY2012, and H.R. 2055 are laid out in Table 2. The amounts shown are "new budget authority" (NBA), the new appropriations needed to fund the various accounts for the years indicated. NBA is the total appropriation amount required for a given year minus reductions and rescissions mandated by subsequent legislation. A more detailed comparison, which includes these additional details, may be found in the Appendix in Table A-1 and Table A-2.

Table 2. Military Construction Appropriations Accounts, FY2010-FY2012

(new budget authority, thousands of dollars)

Account

FY2010 Enacted
(P.L. 111-117)

FY2011 Full-Year Continuing Appropriation (P.L. 112-10, Div B, Title X)

FY2012 Request

FY2012
House Bill (H.R. 2055)

FY2012 Senate Bill (H.R. 2055)

Military Construction, Army

3,456,419

3,517,023

3,235,991

3,041,491

3,066,891

Military Construction, Navy and Marine Corps

3,482,535

3,235,954

2,461,547

2,436,547

2,187,622

Military Construction, Air Force

1,255,567

983,081

1,364,858

1,247,358

1,227,058

Military Construction, Defense-wide

2,942,519

2,718,816

3,848,757

3,533,757

3,380,917

Total, Active Components

11,137,040

10,454,874

10,911,153

10,259,153

9,862,488

Military Construction, Army National Guard

549,056

871,917

773,592

773,592

773,592

Military Construction, Air National Guard

364,226

194,596

116,246

116,246

116,246

Military Construction, Army Reserve

431,566

317,539

280,549

280,549

280,549

Military Construction, Navy Reserve

125,874

61,434

26,299

26,299

26,299

Military Construction, Air Force Reserve

112,269

7,816

33,620

33,620

33,620

Total, Reserve Components

1,582,991

1,453,302

1,230,306

1,230,306

1,230,306

Total, Military Construction

12,720,031

11,908,176

12,141,459

11,489,459

11,092,794

NATO Security Investment Program

197,414

258,366

272,611

272,611

272,611

Family Housing Construction, Army

273,236

92,184

186,897

186,897

186,897

Family Housing Ops and Debt, Army

523,418

517,104

494,858

494,858

494,858

Family Housing Construction, Navy and Marine Corps

146,569

186,071

100,972

100,972

100,972

Family Housing Ops and Debt, Navy and Marine Corps

368,540

365,613

367,863

367,863

367,863

Family Housing Construction, Air Force

66,101

77,869

84,804

84,804

84,804

Family Housing Ops and Debt, Air Force

502,936

512,764

404,761

404,761

404,761

Family Housing Construction, Defense-wide

2,859

Family Housing Ops and Debt, Defense-wide

49,214

50,363

50,723

50,723

50,723

DOD Family Housing Improvement Fund

2,600

1,094

2,184

2,184

2,184

Homeowners Assistance Fund

323,225

16,482

1,284

1,284

1,284

Total, Family Housing

2,258,698

1,819,544

1,694,346

1,694,346

1,694,346

Chemical Demilitarization Construction, Defense-wide

151,541

124,721

75,312

75,312

75,312

Base Realignment and Closure

7,952,266

2,476,996

582,319

482,319

582,319

Total, Title Ia

23,279,950

16,587,773

14,766,047

14,014,047

13,717,382

Total, Title IVb

1,398,984

1,222,852

Grand Total

24,678,934

17,810,625

14,766,047

14,014,447

13,717,382

Source: H.Rept. 111-366; P.L. 112-10; DOD Budget Justification Material, FY2012; H.R. 2055; S.Rept. 112-29.

a. Title I funds normal military construction and family housing projects.

b. Title IV was a temporary funding classification that replaced the separate emergency supplemental funding of previous years for Overseas Contingency Operations, primarily in areas of active military operations.

Regional Command Construction Issues

Northern Command (NORTHCOM)

The geographic land area comprising U.S. Northern Command includes the contiguous United States, Alaska, Canada, and Mexico.

The principal military construction issues within Northern Command center on the relocation of personnel and organizations within the continental United States and the redeployment of troops from garrisons overseas to domestic duty stations.

The largest portion of domestic relocation was required by the 2005 Defense Base Closure and Realignment Commission (also known as the BRAC Commission). Over the past six years, the defense agencies and military departments have carried out a highly complex—and often contentious—program of construction and movement mandated by the commission that required the appropriation of approximately $35 billion. The 2005 BRAC round, save for environmental cleanup and disposal of surplus property, is scheduled to be completed not later than September 15, 2011. Nevertheless, perceiving military service inability to fully implement some of the more complex commission recommendations by the statutorily mandated deadline, Section 2704 of H.R. 1540, the NDAA for FY2012, would permit the Secretary of Defense to extend the completion of as many as seven recommendations for up to a year.8

Another section of the bill, Section 2707, would prevent the use of more than 1,000 parking spaces at the site of BRAC Commission Recommendation 133 until the Secretary of Defense takes certain actions, including the completion of a number of traffic mitigation projects. BRAC 133, as it is called, will move a large number of defense workers to newly constructed facilities at the Mark Center in Arlington, VA. Congress has questioned the ability of that site to absorb the expected increase in surface traffic generated by the transfers and has written provisions similar to this into previous versions of the NDAA.

Associated with the domestic BRAC, and funded through the BRAC appropriation, is the construction needed to house units repositioned to the United States as part of the parallel Integrated Global Presence and Basing Strategy (IGPBS), later renamed the Global Defense Posture Realignment (GDPR).

Separate from the 2005 BRAC round, DOD announced plans to permanently move one of the Navy's aircraft carriers from its home port of Norfolk, VA, to a new duty station in Mayport, FL. The announced reasoning for the move is strategic. Currently, the naval station at Norfolk is the sole Navy facility along the nation's eastern or southern coasts with the needed facilities and capacity to service a nuclear-powered aircraft carrier.9 The Navy became concerned that stationing all Atlantic Fleet carriers at a single port facility could offer a vulnerability to potential adversaries and decided to build a second facility at Mayport, estimating the cost of the project at $580 million. Thus far, Congress has not appropriated the necessary construction funds, although the budget request includes some ancillary items that would support future facility construction.10 The FY2012 request does not include funding to build the needed facilities, though there is a $15.0 million request for "Massey Avenue Corridor Improvements" and a like amount for planning and design that are seen as supporting the eventual construction of a carrier home port. Section 2204 of H.R. 1540 (NDAA for FY2012) would bar the use of any appropriations for FY2012 for "architectural and engineering services and construction design of any military construction project necessary to establish a homeport for a nuclear-powered aircraft carrier at Naval Station Mayport, Florida."11

A provision in H.R. 2055, Section 412 of the House version of the military construction appropriation, would prevent the use of funds for any construction in the United States to house any Guantanamo detainees. Section 128 would forbid the use of funds to support "any action that relates to or promotes the expansion of the boundaries or size of the Piñon Canyon Maneuver Site, Colorado." This prohibition stems from an attempt several years ago by the Army to request authorization to begin exploring the expansion of the maneuver area. Stiff local resistance led to the insertion of this language into the annual military construction appropriation.

Pacific Command (PACOM)

U.S. Pacific Command (PACOM) is geographically the largest of the combatant commands, holding within its area of responsibility most of the Pacific and Arctic Oceans; the People's Republic of China; Mongolia; the Democratic People's Republic of Korea (North Korea); the Republic of Korea (South Korea); Japan and the Philippines; Indonesia; the countries of Southeast Asia; the southern Asian, Oceanic, and Australian landmasses to the western border of India; and the corresponding sea areas of the Indian Ocean. Three major force movements and their associated construction are imminent or underway in the Pacific region.

GAO recently completed an analysis of the costs associated with changes in the U.S. military posture in Asia, finding that

DOD's posture planning guidance does not require the U.S. Pacific Command to include comprehensive cost data in its theater posture plan, and as a result, DOD lacks critical information that could be used by decision makers as they deliberate on posture requirements and affordability.... Without comprehensive and routine reporting of posture costs, DOD decision makers will not have the full fiscal context in which to develop posture plans and requirements, and congressional committees will lack a full understanding of the potential funding requirements associated with DOD budget requests.12

MCAS Futenma Replacement

As the result of intergovernmental agreements, Japan has undertaken the construction of a new air facility in the Prefecture of Okinawa for the use of U.S. Marine Corps aviation units now operating from Marine Corps Air Station (MCAS) Futenma, near the prefecture capital of Naha. Upon completion of the new station, the existing facility is to be returned to sole Japanese control.

The selection of a new site for the Futenma Replacement Facility (FRF) and other Japanese domestic political considerations have delayed initiation of construction of the new facility.13 Nevertheless, the Japanese press recently announced agreement between the two national governments on a potential site and runway configuration.14 These plans were formalized at a joint U.S.–Japan ministerial meeting on June 21, 2011, though both governments concluded that adherence to the original 2014 completion date would be impossible, announcing afterward that the FRF would be completed "at the earliest possible date after 2014."15 Nevertheless, the Senate Committee on Armed Services, in their report on the NDAA for 2012, has expressed considerable concern, stating that the "committee believes that the proposed plan for the relocation of Marine Corps Air Station (MCAS) Futenma, located on the island of Okinawa, has become untenable and must be resolved sooner and more economically than the current plan will allow," estimating that "even under the most reasonable circumstances, the FRF ... would likely take at least 7 to 10 years to complete at a cost to the Government of Japan of approximately $5.0–10.0 billion dollars."16 That committee would direct the Secretary of Defense to report on the feasibility of relocating Marine aviation assets from MCAS Futenma to the nearby Kadena Air Base instead of to the projected new facility. In addition, Section 1079 of S. 1253, the Senate's version of the NDAA, would create an independent panel to assess U.S. force posture in East Asia and the Pacific Region, emphasizing examination of the current plans for force realignments on Okinawa and Guam.

Guam Redeployment

The two governments have also agreed to move approximately 8,000 Marines from their present garrisons in Okinawa to facilities in the U.S. Territory of Guam, approximately 1,400 miles to the east. Japan has pledged to provide approximately $6 billion of the estimated $10 billion needed for the relocation.17

Congress has criticized the pace of DOD planning for the move. During consideration of FY2011 appropriations, the Senate Committee on Appropriations recommended deferring $464.6 million in requested construction funding from overseas projects in Guam, Europe, Korea, and other locations pending the completion of a DOD review of its global posture.18 Nevertheless, the redeployment is inextricably linked to the FRF project. DOD is awaiting "tangible progress" on the part of the Japanese in constructing the FRF before commencing the construction necessary to house the Marines relocating from Okinawa.19

While noting that official DOD plans continue to adhere to a 2014 deadline for completion of the Guam redeployment, the House Committee on Appropriations stated, "The Committee remains supportive of the realignment of Marine Corps forces from Okinawa to Guam. At the same time, the Committee has serious concerns about the Department of Defense's (DOD) ability to adequately fund and complete construction on time and within budget."20 In its report on H.R. 2055, the FY2012 military construction appropriation bill, the Senate Committee on Appropriations reiterated its concerns, stating that

Due to the lack of verifiable cost estimates for the Guam buildup, the failure of DOD to submit to the congressional defense committees a comprehensive master plan for the initiative, and continuing uncertainty over the ability of the Government of Japan to fulfill its commitment to relocate United States troops on Okinawa, the Committee has deferred funding for fiscal year 2012 military construction projects associated with the relocation of United States Marines to Guam.21

This included two major Navy projects, a $77.2 million improvement of water utility services to the planned cantonment area at Finegayan and a $78.6 million increment for the development of utility services to the north ramp area on Andersen Air Force Base, a site used by the Navy and planned to host Marine aviation units moved from Japan. The Senate version of the NDAA would also strike the requested funding for these construction projects.

The House version of the NDAA, H.R. 1540, authorizes full funding of both construction projects. Nevertheless, Section 2208 of S. 1253, the Senate's version of the NDAA for 2012, would bar the obligation or expenditure of any appropriated funds or funds provided to the United States by the Government of Japan to implement the Marine relocation to Guam until the Commandant of the Marine Corps provides to the congressional defense committees his "preferred force lay-down" in the Pacific Region and the Secretary of Defense provides a master construction plan supporting that lay-down, certifies that "tangible progress" has been made on the relocation of MCAS Futenma, and provides an interagency plan for the work necessary on Guam's non-military facilities to prepare for the relocation.

At the end of bilateral consultations between the Secretary of State, the Secretary of Defense, and their Japanese counterparts on June 21, 2011, the Department of State issued a press release stating, in part, "The Ministers noted that completion of the FRF and the Marine relocation will not meet the previously targeted date of 2014 and confirmed their commitment to complete the above projects at the earliest possible date after 2014 in order to avoid the indefinite use of the Marine Corps Air Station (MCAS) Futenma, while maintaining Alliance capabilities."22

Korea Transformation

Since the Armistice on the Korean Peninsula ended combat in 1954, U.S. ground forces have been concentrated in a number of forward bases distributed along the demarcation line between South Korea and North Korea, with a major headquarters complex at Yongsan, adjacent to the capital of Seoul.

Following agreements between South Korea and the United States, the headquarters of U.S. Forces, Korea (USFK) and U.S. Army and Air Force units are being concentrated into two large military communities centered on Osan Air Base and Camp Humphreys, south of the capital. Additionally, tours of duty for military personnel are being lengthened, and servicemembers will soon be permitted to bring their families with them, significantly increasing the size of those communities. In its May 2011 report on the military posture in Asia, the GAO noted that they

obtained DOD cost estimates that total $17.6 billion through 2020 for initiatives in South Korea, but DOD cost estimates are incomplete. One initiative, to extend the tour length of military service members and move thousands of dependents to South Korea ... could cost DOD $5 billion by 2020 and $22 billion or more through 2050, but this initiative was not supported by a business case analysis that would have considered alternative courses of action and their associated costs and benefits. As a result, DOD is unable to demonstrate that tour normalization is the most cost-effective approach to meeting its strategic objectives. This omission raises concerns about the investments being made in a $13 billion construction program at Camp Humphreys, where tour normalization is largely being implemented.23

The House Committee on Appropriations expressed its views on the issue of "tour normalization" in its report on the military construction appropriations bill, stating

The Department of Defense has taken on an arduous and expensive task to normalize deployments to Korea by establishing a two-year tour for single members of the service and three-year tours for married servicemembers to include their families. The task will require great investment in military construction for schools, family housing and child development centers just to name a few. The Committee is concerned that this investment may be an expense that the United States should not incur. The Committee directs the Secretary of Defense to report to the Committee on Appropriations within 60 days of enactment of this Act the total cost and plan for Tour Normalization in Korea.24

The Senate Committee on Appropriations voiced its concerns with both tour normalization and the redeployment of U.S. forces on the peninsula in its report on H.R. 2055.

This lack of a business case analysis ... raises concerns about the investments being made in a $13,000,000,000 construction program at Camp Humphreys, Korea, to accommodate the relocation of United States troops south of Seoul and the first phase of tour normalization. Full tour normalization would require additional land, housing, schools and other facilities at Camp Humphreys, which would require a revised master plan for the base and would likely require changes to the current construction program. Given the extent of construction currently underway at Camp Humphreys, any substantive change in the plan could impact efficiency and drive up costs considerably. ... No funding was requested in the fiscal year 2012 budget for military construction related to tour normalization in Korea, but the Committee will expect detailed cost information and a completed business case analysis, approved by the Secretary of Defense, for the strategic objectives that to this point have driven the decision to implement tour normalization, before approving any funding requests in future years. This business case analysis should clearly articulate the strategic objectives, identify and evaluate alternative courses of action to achieve those objectives, and recommend the most cost-effective alternative.25

Finally, the Senate Committee on Armed Services included Section 2113 into S. 1253, their version of the NDAA for FY2012, that would bar any funds from being obligated or expended in support of tour normalization until DOD's Director of Cost Assessment and Program Evaluation (CAPE) conducts an appropriate analysis of alternatives to the program being pursued by the Army, the Secretary of the Army submits a master plan detailing the schedule and costs for the needed facility and infrastructure construction, and subsequent legislation authorizes such obligation.

European Command (EUCOM)

U.S. European Command (EUCOM) encompasses the countries in Europe, Russia, Israel, Greenland, and Iceland. The EUCOM commander simultaneously serves as NATO's Supreme Allied Commander, Europe (SACEUR). Because Europe was long considered the front line during the Cold War, the bulk of U.S. forces permanently garrisoned overseas was stationed within the EUCOM area of responsibility. In 1980, more than 331,000 servicemembers were on duty in the countries of Western and Southern Europe and afloat on adjacent seas. Of these, more than 244,000, along with their families and associated civilian employees, were stationed in what was then West Germany.

With the end of the Cold War, these garrisons saw significant reductions in their size. By 1999, Europe and adjacent waters hosted approximately 116,200 U.S. servicemembers, with 65,000 of those located in Germany. As of September 30, 2010, the number in and around Europe had fallen to 79,000, with 53,900 located in Germany, 9,600 in Italy, and 9,200 in the United Kingdom.26

As part of the GDPR mentioned earlier, Army and Air Force personnel in the Federal Republic of Germany are being consolidated into two large military communities centered at Kaiserslautern (known to many servicemembers as "K-Town") in the country's southwest near Frankfurt, and Grafenwöhr-Vilseck in eastern Bavaria near the Czech border. For the past several years, military construction supporting this relocation has concentrated in these areas.

A significant portion of the combat power remaining in the Army portion of EUCOM was scheduled to redeploy to new posts in the southwestern United States as part of the GDPR, but the Secretary of Defense agreed to reconsider the movement of two brigade combat teams after the most recent Quadrennial Defense Review reviewed the U.S. interest in supporting NATO.27

The President's FY2012 request includes $563 million for construction in Germany. It includes $249 million for Army construction of the relocated European Army and Air Force Exchange Central Distribution Facility (later not supported by the House), various training and communications facilities, barracks, and family housing. The DOD Education Agency (DODEA) is requesting $207 million to build, expand, or replace elementary, middle, and high schools at several locations. The Tricare Management Agency plans to replace the military medical center at Rhine Ordnance Barracks at a total cost of $1.2 billion and is requesting $71 million for the first increment of funding.28 The Air Force is asking for $35 million to build a new airman's dormitory at Ramstein Air Base, and the Defense Information Systems Agency (DISA) is asking for $2.4 million to upgrade its facility serving U.S. Army, Europe, headquarters near Stuttgart.

The Senate Committee on Appropriations took note of the potential impact of efficiency initiatives announced by the Secretary of Defense during August of 2010 when it wrote

The Committee remains concerned with the United States Army transformation and realignment plans in Europe. This year, DOD announced the restructuring of headquarters commands in Europe from four-star to three-star staff billets to reduce overhead as part of the Secretary of Defense's efficiency initiative. Subsequently, the Army announced its decision to reduce Army Brigade Combat Teams [BCTs] in Europe from four to three after 2015. In light of these developments, the Army continues to have challenges articulating its long term plans and justification for its forces and installations in Europe. ... In order to better understand future requirements for military construction in Germany, the Committee directs that no later than 90 days after enactment of this act, the Army and European Command provide a report on installations and properties in Germany that they intend to return to the host nation.29

Africa Command (AFRICOM)

Until U.S. Africa Command (AFRICOM) was activated in 2008, military affairs on the continent were the responsibility of EUCOM. With creation of AFRICOM headquarters, much of that responsibility shifted to the new command (Egypt, though, did not transfer to AFRICOM).

Funds for the construction of two headquarters buildings at Camp Lemonier, Djibouti, were requested in FY2011. One of these was intended for Camp Lemonier itself, while the other was planned for the use of Combined Joint Task Force-Horn of Africa (CJTF-HOA). While the task force comprises the majority of personnel assigned to the installation, Camp Lemonier is limited in size. In its report on the military construction appropriation for FY2011, the Senate Committee on Appropriations noted that DOD had not submitted a requested report on plans for future operations of both Camp Lemonier and CJTF-HOA and recommended that funds for a separate task force headquarters be denied.30 The President's request for FY2012 includes $43.5 million for construction of housing at the camp and $46.0 million for facility improvements at the adjoining airfield.

The House version of H.R. 2055 fully funded this request, as does the version of the bill reported by the Senate Committee on Appropriations. Nevertheless, the committee noted in its report that it

remains concerned about the long range mission of AFRICOM at Camp Lemonier and the planned development and security of the installation. ... Although it is a Navy installation, its primary mission is to support the Combined Joint Task Force– Horn of Africa [CJTF–HOA], which is focused on anti-terrorism and capacity building in East Africa. DOD has designated Camp Lemonier as an enduring location, but by DOD definition, joint task forces are temporary in nature, designed to address specific, limited objectives, and are normally dissolved when their mission has been achieved or is no longer required. ... The Committee therefore directs the Secretary of the Navy to submit a comprehensive master plan for Camp Lemonier that can serve as a baseline to measure progress, total costs, and total funding requirements for all current and future projects associated with Camp Lemonier.31

Since its creation, AFRICOM headquarters has been located in Germany. Press reports have mentioned discussions concerning its potential movement to the Norfolk, VA, area.32 In its report on the NDAA for FY2012, the House Committee on Armed Services noted that Commander, U.S. Africa Command, has studied various alternatives for moving his headquarters to the United States and directed the Secretary of Defense to report the conclusions of that study not later than April 1, 2012.33

Central Command (CENTCOM)

The area of responsibility assigned to U.S. Central Command (CENTCOM) includes Egypt, the Arabian Peninsula, and much of South and Southwestern Asia. CENTCOM has been the primary focal point of U.S. military operations since early 2002.

While considerable construction in the CENTCOM area has been funded in previous years, the FY2012 request for appropriations includes only $80 million for a new entry control point and phases (slices) of funding for a barracks and drainage system at Bagram Air Base in Afghanistan and $137.2 million for three construction projects in Qatar and Bahrain Island. The House versions of both military construction appropriations and authorization support that funding. The Senate versions would strike the funding of the two projects on Bahrain Island, with Senate authorizers citing concerns that the Navy could not execute them during the fiscal year.34

Nevertheless, since FY2004, Congress has annually renewed a temporary authority permitting the Secretary of Defense to use operations and maintenance (O&M) funding in the defense appropriation for military construction in support of overseas contingency operations. This discretion, referred to as "Section 2808 authority" for the provision originally granting it in the FY2004 National Defense Authorization Act (P.L. 108-136), has varied over the years in the amount of funding available and the locations where it may be used, rising as high as $500 million for FY2009. Section 2804 of the Ike Skelton National Defense Authorization Act, 2011 (P.L. 111-383) limited funding to $100 million and restricted its use to Afghanistan. Section 2805 of the House version of the FY2012 NDAA would reauthorize this authority for an additional year, through September 30, 2012, as would Section 2802 of the Senate's version of the bill.

Legislative language used by congressional appropriators and authorizers has sought to distinguish between construction intended to support short-term expeditionary military operations and permanent garrisoning of troops in either Iraq or Afghanistan. That language has prevented funds from being used for the "permanent stationing" of forces and stressed that construction is to support "operational requirements of a temporary nature."

Nevertheless, this stance has softened somewhat in recent years. Section 2806 of P.L. 110-417, the Duncan Hunter National Defense Authorization Act for FY2009, exempted construction in Afghanistan from the existing ban on the use of O&M funds "deemed as supporting a long-term presence."

A detailed discussion of war-related construction funding may be found in CRS Report R41232, FY2010 Supplemental for Wars, Disaster Assistance, Haiti Relief, and Other Programs, coordinated by [author name scrubbed].

FY2011 Continuing Appropriations

Federal funding for FY2011 was provided through a series of eight continuing appropriations of varying lengths.35 Normally, a continuing appropriation permits government agencies to operate at the same rate as experienced in the most recent full-year appropriation—in this case FY2010—for the duration of the appropriation.

The first bill of the series, the Continuing Appropriations Act, 2011 (P.L. 111-242), was enacted on September 30, 2010, and provided funding through December 3, 2010. This original act, rather than merely extending existing appropriations into the new year, adjusted the amounts available to several appropriations accounts from their prorated FY2010 levels. The most substantial adjustment to military construction accounts was the reduction of the BRAC 2005 account from the $8.0 billion needed near the height of BRAC construction in FY2010 to $2.4 billion. Nevertheless, the act also contained the following text:

Sec. 102. (a) No appropriation or funds made available or authority granted pursuant to section 101 for the Department of Defense shall be used for (1) the new production of items not funded for production in fiscal year 2010 or prior years; (2) the increase in production rates above those sustained with fiscal year 2010 funds; or (3) the initiation, resumption, or continuation of any project, activity, operation, or organization (defined as any project, subproject, activity, budget activity, program element, and subprogram within a program element, and for any investment items defined as a P-1 line item in a budget activity within an appropriation account and an R-1 line item that includes a program element and subprogram element within an appropriation account) for which appropriations, funds, or other authority were not available during fiscal year 2010.

This section, therefore, did not permit the initiation of any new FY2011 construction projects. None of the subsequent enacted appropriations altered this language until the enactment of the Full-Year Continuing Appropriation Act for FY2011 (P.L. 112-10) on April 15, 2011.

FY2012 Appropriations

The President submitted his FY2012 appropriation request for military construction and family housing to Congress on February 14, 2011, and the House passed its version of the Military Construction, Veterans Affairs, and Related Agencies Appropriations Act (H.R. 2055) on June 14, 2011. The overall level of funding in the President's request represents a 17.1% ($3.0 billion) reduction below the combined Title I (military construction) and Title IV (Overseas Contingency Operations construction) amount enacted for FY2011. The House version of H.R. 2055 funding levels in New Budget Authority represent a 20.5% ($3.6 billion) reduction from FY2011 enacted amounts.

The major portion of that reduction comes from the $2.1 billion less in BRAC 2005 funding needed to support the first post-implementation year of that program. The President's FY2012 request is less than one-quarter of the amount needed during the last year of BRAC construction and movement. The President also requested no funds for the Overseas Contingency Operations construction account. This represented $1.2 billion in the FY2011 appropriation. Even though the FY2012 base budget request includes $80 million in construction for Afghanistan, plus another $137 million elsewhere in Central Command, this marks a substantial reduction in construction activity in the area of the most intense U.S. military operations.

The House passed its version of a military construction appropriations bill (H.R. 2055) on June 14, 2011. The Senate Committee on Appropriations reported its amendment to H.R. 2055 on June 30, and the chamber may take up the measure in the near future.

Questions for Congress

As Members of Congress and the defense committees consider the President's request for FY2012, a number of questions may suggest themselves:

Appendix. Detailed Military Construction Appropriations Tables

Table A-1. Title I Military Construction Appropriations Accounts, FY2010-FY2012

(budget authority in thousands of dollars)

Account

FY2010 Enacted
(P.L. 111-117)

FY2011 Full-Year Continuing Appropriation
(P.L. 112-10, Div B, Title X)

FY2012 Request

FY2012 House Bill (H.R. 2055)

FY2012 Senate Bill (H.R. 2055)

Military Construction, Army

3,719,419

3,787,598

3,235,991

3,141,491

3,066,891

Rescissions

-33,000

-263,000

-100,000

Reduction

-230,000

-7,575

Total New BA

3,456,419

3,517,023

3,235,991

3,041,491

3,066,891

Military Construction, Navy and Marine Corps

3,769,003

3,303,611

2,461,547

2,461,547

2,187,622

Rescissions

-51,468

-61,050

-25,000

Reduction

-235,000

-6,607

Total New BA

3,482,535

3,235,954

2,461,547

2,436,547

2,187,622

Military Construction, Air Force

1,450,426

1,106,995

1,364,858

1,279,358

1,227,058

Rescissions

-130,768

-121,700

-32,000

Reduction

-2,214

Total New BA

1,255,567

983,081

1,364,858

1,247,358

1,227,058

Military Construction, Defense-wide

3,093,679

2,873,062

3,848,757

3,665,157

3,380,917

Rescissions

-151,160

-148,500

-131,400

Reduction

-5,746

Total New BA

2,942,519

2,718,816

3,848,757

3,533,757

3,380,917

Total, Active Components

11,137,040

10,454,874

10,911,153

10,259,153

9,862,488

Military Construction, Army National Guard

582,056

873,664

773,592

773,592

773,592

Rescissions

-33,000

Reduction

-1,747

Total New BA

549,056

871,917

773,592

773,592

773,592

Military Construction, Air National Guard

371,226

194,986

116,246

116,246

116,246

Rescissions

-7,000

Reduction

-390

Total New BA

364,226

194,596

116,246

116,246

116,246

Military Construction, Army Reserve

431,566

318,175

280,549

280,549

280,549

Reduction

-636

Total New BA

431,566

317,539

280,549

280,549

280,549

Military Construction, Navy Reserve

125,874

61,557

26,299

26,299

26,299

Reduction

-123

Total New BA

125,874

61,434

26,299

26,299

26,299

Military Construction, Air Force Reserve

112,269

7,832

33,620

33,620

33,620

Reduction

-16

Total New BA

112,269

7,816

33,620

33,620

33,620

Total, Reserve Components

1,582,991

1,453,302

1,230,306

1,230,306

1,230,306

Total, Military Construction

12,720,031

11,908,176

12,141,459

11,489,459

11,092,794

(Appropriations)

13,655,518

12,527,480

12,141,459

11,777,859

11,092,794

(Rescissions)

-406,396

-594,250

-288,400

(Reductions)

-529,091

-25,054

NATO Security Investment Program

197,414

258,884

272,611

272,611

272,611

Reduction

-518

Total New BA

197,414

258,366

272,611

272,611

272,611

Family Housing Construction, Army

273,236

92,369

186,897

186,897

186,897

Reduction

-185

Total New BA

273,236

92,184

186,897

186,897

186,897

Family Housing Ops and Debt, Army

523,418

518,140

494,858

494,858

494,858

Reduction

-1,036

Total New BA

523,418

517,104

494,858

494,858

494,858

Family Housing Construction, Navy and Marine Corps

146,569

186,444

100,972

100,972

100,972

Reduction

-373

Total New BA

146,569

186,071

100,972

100,972

100,972

Family Housing Ops and Debt, Navy and Marine Corps

368,540

366,346

367,863

367,863

367,863

Reduction

-733

Total New BA

368,540

365,613

367,863

367,863

367,863

Family Housing Construction, Air Force

66,101

78,025

84,804

84,804

84,804

Reduction

-156

Total New BA

66,101

77,869

84,804

84,804

84,804

Family Housing Ops and Debt, Air Force

502,936

513,792

404,761

404,761

404,761

Reduction

-1,028

Total New BA

502,936

512,764

404,761

404,761

404,761

Family Housing Construction, Defense-Wide

2,859

Family Housing Ops and Debt, Defense-Wide

49,214

50,464

50,723

50,723

50,723

Reduction

-101

Total New BA

49,214

50,363

50,723

50,723

50,723

DOD Family Housing Improvement Fund

2,600

1,096

2,184

2,184

2,184

Reduction

-2

Total New BA

2,600

1,094

2,184

2,184

2,184

Homeowners Assistance Fund

323,225

16,515

1,284

1,284

1,284

Reduction

-33

Total New BA

323,225

16,482

1,284

1,284

1,284

Total, Family Housing

2,258,698

1,819,544

1,694,346

1,694,346

1,694,346

(Appropriations)

2,258,698

1,823,191

1,694,346

1,694,346

1,694,346

(Reductions)

0

-3,647

0

0

0

Chemical Demilitarization Construction, Defense-wide

151,541

124,971

75,312

75,312

75,312

Reduction

-250

Total New BA

151,541

124,721

75,312

75,312

75,312

Base Realignment and Closure

 

 

 

 

 

BRAC,1990

496,768

360,474

323,543

323,543

323,543

Rescissions

-100,000

Reduction

-721

Total New BA

496,768

359,753

323,543

223,543

323,543

BRAC,2005

7,455,498

2,354,285

258,776

258,776

258,776

Rescissions

-232,363

Reduction

-4,709

Total New BA

7,455,498

2,117,213

258,776

258,776

258,776

Total, BRAC

7,952,266

2,476,966

582,319

482,319

582,319

(Appropriations)

7,952,266

2,714,759

582,319

582,319

582,319

(Rescissions)

-232,363

-100,000

(Reductions)

-5,430

Grand Total, Title I

23,279,950

16587,773

14,766,047

14,014,047

13,717,382

(Appropriations)

24,215,437

17,449,285

14,766,047

14,402,447

13,717,382

(Rescissions)

-406,396

-826,613

-388,400

(Reductions)

-529,091

-34,899

Source: H.Rept. 111-366; P.L. 112-10; DOD Budget Justification Material, FY2012; H.R. 2055; S.Rept. 112-29.

Table A-2. OCO Military Construction Appropriations Act Counts, FY2010-FY2012

(budget authority in thousands of dollars)

Account

FY2010 Enacted
(P.L. 111-117)

FY2011 Full-Year Continuing Appropriation
(P.L. 112-10, Div B, Title X)

FY2012 Request

FY2012 House Bill (H.R. 2055)

FY2012 Senate Bill (H.R. 2055)

Military Construction, Army

924,484

981,346

Military Construction, Army (Emergency)

Military Construction, Air Force

474,500

195,006

Military Construction, Air Force (Emergency)

Military Construction, Defense-wide

46,500

Military Construction, Defense-wide (Emergency)

Grand Total, Title IV

1,398,984

1,222,852

Source: H.Rept. 111-366; P.L. 112-10; DOD Budget Justification Material, FY2012; H.R. 2055; S.Rept. 112-29.

Footnotes

1.

For more information on project labor agreements, see CRS Report R41310, Project Labor Agreements, by [author name scrubbed].

2.

Broader discussions of the use of Davis-Bacon wage rates can be found in CRS Report R40663, The Davis-Bacon Act and Changes in Prevailing Wage Rates, 2000 to 2008, by [author name scrubbed], (pdf) and CRS Report 94-408, The Davis-Bacon Act: Institutional Evolution and Public Policy, by [author name scrubbed].

3.

More information on the National Defense Authorization Act for FY2012 may be found in CRS Report R41861, Defense: FY2012 Budget Request, Authorization and Appropriations, by [author name scrubbed].

4.

These acts were the Defense Authorization Amendments and Base Closure and Realignment Act, 1988 (P.L. 100-526, Div A, Title XII, Part D, § 1231(17), 101 Stat. 1161), and the Defense Base Closure and Realignment Act, 1990 (P.L. 101-510, Div B, Title XXIX, Part A, § 2911, 104 Stat. 1819). A number of CRS products have addressed various aspects of military installation closures. Current products include CRS Report RS22147, Military Base Closures: Socioeconomic Impacts, by [author name scrubbed] and [author name scrubbed]; CRS Report RL34709, Economic Development Assistance for Communities Affected by Employment Changes Due to Military Base Closures (BRAC), by [author name scrubbed]; and CRS Report R40476, Base Realignment and Closure (BRAC): Transfer and Disposal of Military Property, by [author name scrubbed]. Examples of other products include CRS Report RS22184, Military Base Closures: Redevelopment Assistance Programs, by [author name scrubbed]; CRS Report RL32963, The Availability of Judicial Review Regarding Military Base Closures and Realignments, by [author name scrubbed]; and CRS Report RL33137, Military Base Closures and the Impact Aid Program for Education, by [author name scrubbed].

5.

Detailed discussions of veterans affairs appropriations may be found in CRS Report R41343, Veterans Medical Care: FY2011 Appropriations, by [author name scrubbed]; and CRS Report R41688, Veterans Affairs: A Preliminary Analysis of the FY2012 Appropriations Request , by [author name scrubbed] and [author name scrubbed].

6.

Nevertheless, the President's request did include $80 million for military construction in Afghanistan at Bagram Air Base, $100 million for work in Bahrain, and $37 million for construction in Qatar.

7.

The continuing appropriations for FY2011 were, in chronological order, H.R. 3081 (P.L. 111-242, October 1–December 3, 2010), H.J.Res. 101 (P.L. 111-290, December 4–December 18, 2010), H.J.Res. 105 (P.L. 111-317, December 19–December 21, 2010), H.R. 3082 (P.L. 111-322, December 22, 2010–March 4, 2011), H.J.Res. 44 (P.L. 112-4, March 5–March 18, 2011), H.J.Res. 48 (P.L. 112-6, March 19–April 8, 2011), H.R. 1363 (P.L. 112-8, April 9–April 15, 2011), and H.R. 1473 (P.L. 112-10, April 16–September 30, 2011). For additional information on continuing appropriations, see CRS Report RL30343, Continuing Resolutions: Latest Action and Brief Overview of Recent Practices, by [author name scrubbed]; CRS Report R41771, FY2011 Appropriations in Budgetary Context, by [author name scrubbed] and [author name scrubbed]; and the Congressional Budget Office website, Continuing Resolutions for FY2011, http://www.cbo.gov/publications/collections/collections.cfm?collect=17.

8.

The recommendations to be selected by the Secretary have not been publicly identified.

9.

The USS John F. Kennedy, the Navy's last conventionally fueled aircraft carrier, was decommissioned on August 1, 2007. All active aircraft carriers are now nuclear powered.

10.

For a much more extensive examination of the Mayport carrier issue, see CRS Report R40248, Navy Nuclear Aircraft Carrier (CVN) Homeporting at Mayport: Background and Issues for Congress, by [author name scrubbed].

11.

For more information regarding the proposed relocation to Mayport, see CRS Report R41254, Defense: FY2011 Authorization and Appropriations, coordinated by [author name scrubbed].

12.

U.S. Government Accountability Office, Defense Management: Comprehensive Cost Information and Analysis of Alternatives Needed to Assess Military Posture in Asia, GAO-11-316, May 25, 2011, frontispiece.

13.

For additional information and analysis of U.S.-Japanese security relations, see CRS Report RL33436, Japan-U.S. Relations: Issues for Congress, coordinated by [author name scrubbed].

14.

"Minister Tells Okinawa Gov. of Plan to Proceed with Futenma Relocation," Kyodo News, June 13, 2011, posted online at 01:17.

15.

William Wan, "U.S., Japan Agree to Delay Relocation of Air Base on Okinawa," The Washington Post, June 22, 2011, p. A9.

16.

U.S. Congress, Senate Committee on Armed Services, National Defense Authorization Act for Fiscal Year 2012, report to accompany S. 1253, 112th Cong., 1st sess., June 22, 2011, S.Rept. 112-26, p. 241.

17.

Of this sum, the Government of Japan has committed to provide $2.8 billion in cash, with the remainder taking the form of recoverable financial instruments.

18.

U.S. Congress, Senate Committee on Appropriations, Subcommittee on Military Construction and Veterans Affairs, and Related Agencies, Military Construction and Veterans Affairs, and Related Agencies Appropriations Bill, 2010, Report to accompany S. 3615, 111th Cong., 2nd sess., July 19, 2010, S.Rept. 111-226, p. 9.

19.

Additional information on and analysis of the Marine relocation can be found in CRS Report RS22570, Guam: U.S. Defense Deployments, by [author name scrubbed].

20.

U.S. Congress, House Committee on Appropriations, Subcommittee on Military Construction, Veterans Affairs, and Related Agencies, Military Construction, Veterans Affairs, and Related Agencies Appropriations Bill, 2012, report, together with Minority Views, to accompany H.R. 2055, 112th Cong., 1st sess., May 31, 2011, H.Rept. 112-94 (Washington: GPO, 2011), p. 15.

21.

U.S. Congress, Senate Committee on Appropriations, Subcommittee on Military Construction and Veterans Affairs, and Related Agencies, Military Construction and Veterans Affairs, and Related Agencies Appropriation Bill, 2012, report to accompany H.R. 2055, 112th Cong., 1st sess., June 30, 2011, S.Rept. 112-29 (Washington: GPO, 2011), p. 9.

22.

"Security Consultative Committee Document Progress on the Realignment of US Forces in Japan," Department of State Press Release, June 21, 2011.

23.

GAO-11-316, frontispiece. Additional details on the relocation of U.S. forces on the Korean Peninsula may be found in CRS Report R41481, U.S.-South Korea Relations, coordinated by [author name scrubbed].

24.

H.Rept. 112-94, p. 21-22.

25.

S.Rept. 112-29, p. 8, 10.

26.

U.S. military manpower levels are regularly reported by the Defense Manpower Data Center. Its military personnel figures can be accessed at http://siadapp.dmdc.osd.mil/personnel/MILITARY/miltop.htm.

27.

Jason Sherman, "QDR Reconsidering Plan to Move Two Brigades from Europe to U.S.," Inside the Pentagon, August 13, 2009, vol. 25, no. 32.

28.

Rhine Ordnance Barracks, part of the Kaiserslautern Military Community, is a major deployment terminus for U.S. forces stationed in the European Central Region. Located adjacent to Ramstein Air Base and near major ammunition storage sites, the barracks will act as a major outfitting and processing station for any unit being deployed from the region on a military operation.

29.

S.Rept. 112-29, p. 14.

30.

S.Rept. 111-226, p. 16.

31.

Ibid., p. 11-12.

32.

Robert McCabe, "JFCOM Downsizing to be Complete by March 2012," The Virginian Pilot & Ledger Star, February 10, 2011, p. A1.

33.

U.S. Congress, House Committee on Armed Services, National Defense Authorization Act for Fiscal Year 2012, Report of the Committee on Armed Services House of Representatives on H.R. 1540 together with additional views [including cost estimate of the Congressional Budget Office], 112th Cong., 1st sess., May 17, 2011, H.Rept. 112-78 (Washington: GPO, 2011), p. 288.

34.

S.Rept. 112-26, p. 239.

35.

For detailed information on these continuing appropriations, see CRS Report RL30343, Continuing Resolutions: Latest Action and Brief Overview of Recent Practices, by [author name scrubbed].