Navy Littoral Combat Ship (LCS) Program:
Background, Issues, and Options for Congress

Ronald O'Rourke
Specialist in Naval Affairs
April 18, 2011
Congressional Research Service
7-5700
www.crs.gov
RL33741
CRS Report for Congress
P
repared for Members and Committees of Congress

Navy Littoral Combat Ship (LCS) Program

Summary
The Littoral Combat Ship (LCS) is a relatively inexpensive Navy surface combatant equipped
with modular “plug-and-fight” mission packages. The Navy wants to field a force of 55 LCSs.
The first two LCSs (LCS-1 and LCS-2) were procured in FY2005 and FY2006 and were
commissioned into service on November 8, 2008, and January 16, 2010. Another two (LCS-3 and
LCS-4) were procured in FY2009 and are under construction. Two more (LCS-5 and LCS-6)
were procured in FY2010 and are under contract. The Navy’s proposed FY2011 budget requested
funding to procure an additional two (LCS-7 and LCS-8). Although the Navy’s FY2011 funding
has not yet been fully determined, the Navy announced on March 17 that it had brought these two
ships under contract. The Navy’s proposed FY2012 budget requests funding to procure four more
(LCSs 9 through 12). Navy plans call for procuring an additional 15 LCSs in FY2013-FY2016 in
annual quantities of 4-4-4-3.
There are two very different LCS designs—one developed and produced by an industry team led
by Lockheed, and another developed and produced by an industry team led by General Dynamics.
The Lockheed design is built at the Marinette Marine shipyard at Marinette, WI; the General
Dynamics design is built at the Austal USA shipyard at Mobile, AL.
On November 3, 2010, the Navy notified congressional offices that it was prepared to implement
a dual-award acquisition strategy under which the Navy would award each LCS builder a 10-ship
contract for the six-year period FY2010-FY2015. The Navy stated that, compared to an earlier
down select strategy that the Navy had announced in September 2009, the dual-award strategy
would reduce LCS procurement costs by hundreds of millions of dollars. The Navy needed
additional legislative authority from Congress to implement the dual-award strategy. Congress
granted the authority in Section 150 of H.R. 3082/P.L. 111-322 of December 22, 2010, an act that,
among other things, funded federal government operations through March 4, 2011. On December
29, 2010, the Navy implemented the dual-award strategy, awarding a 10-ship, fixed-price
incentive (FPI) block-buy contract to Lockheed, and another 10-ship, FPI block-buy contract to
Austal USA. LCSs 5 through 8 are the first four LCSs executed under the two block-buy
contracts.
Current issues for Congress concerning the LCS program include the Navy’s lack of economic
order quantity (EOQ) authority for executing the two block-buy contracts, changes or potential
changes to the composition of LCS mission modules announced by the Navy in January 2011, the
combat survivability of the LCS, and hull cracking on LCS-1.

Congressional Research Service

Navy Littoral Combat Ship (LCS) Program

Contents
Introduction ................................................................................................................................ 1
Background ................................................................................................................................ 1
The Program in General ........................................................................................................ 1
The LCS in Brief............................................................................................................. 1
Planned Procurement Quantities...................................................................................... 2
Two LCS Designs ........................................................................................................... 2
Two LCS Shipyards ........................................................................................................ 4
Unit Procurement Cost Cap............................................................................................. 5
Estimated Acquisition Cost ............................................................................................. 6
Estimated Operation and Support (O&S) Cost................................................................. 6
Manning and Deployment Concept ................................................................................. 7
Major Program Developments............................................................................................... 8
Growth in Sea Frame Procurement Costs ........................................................................ 8
2007 Program Restructuring and Ship Cancellations ....................................................... 8
2009 Down Select Acquisition Strategy (Not Implemented) ............................................ 8
2010 Dual-Award Acquisition Strategy (Implemented) .................................................... 9
2011 Announced Changes in Mission Module Equipment ............................................. 10
FY2011 Funding Request .................................................................................................... 12
FY2012 Funding Request.................................................................................................... 13
Issues for Congress ................................................................................................................... 13
Lack of Economic Order Quantity (EOQ) Authority for Executing the Block-Buy
Contracts ......................................................................................................................... 13
Announced Changes in Mission Module Equipment............................................................ 13
Combat Survivability .......................................................................................................... 14
Hull Cracking on LCS-1 ..................................................................................................... 16
Technical Risk .................................................................................................................... 18
Sea Frame..................................................................................................................... 18
Mission Packages.......................................................................................................... 19
Total Program Acquisition Cost........................................................................................... 21
Separate SAR Reporting of Sea Frame and Mission Module Costs ...................................... 21
Operational Concepts .......................................................................................................... 22
Legislative Activity for FY2012 ................................................................................................ 24
FY2012 Funding Request.................................................................................................... 24

Figures
Figure 1. Lockheed LCS Design (Top) and General Dynamics LCS Design (Bottom).................. 3

Tables
Table 1. Construction Status of LCSs .......................................................................................... 5
Table A-1. Congressional Action on FY2011 Funding Request .................................................. 27
Table D-1. Status of LCSs Funded in FY2005-FY2009 ............................................................. 43
Congressional Research Service

Navy Littoral Combat Ship (LCS) Program

Table F-1. Navy and CBO Estimates of Ship Procurement Costs Through FY2015 Under
Down Select and Dual-Award Strategies ................................................................................ 63

Appendixes
Appendix A. Legislative Activity for FY2011............................................................................ 25
Appendix B. Summary of Congressional Action in FY2005-FY2010......................................... 33
Appendix C. Cost Growth on LCS Sea Frames in FY2007-FY2012 Budgets ............................. 35
Appendix D. 2007 Program Restructuring and Ship Cancellations............................................. 41
Appendix E. Down Select Acquisition Strategy Announced in September 2009 ......................... 44
Appendix F. Dual-Award Acquisition Strategy Announced in November 2010........................... 58

Contacts
Author Contact Information ...................................................................................................... 67

Congressional Research Service

Navy Littoral Combat Ship (LCS) Program

Introduction
This report provides background information and potential issues for Congress on the Littoral
Combat Ship (LCS), a relatively inexpensive Navy surface combatant equipped with modular
“plug-and-fight” mission packages. The Navy’s proposed FY2012 budget requests funding for the
procurement of four LCSs.
Current issues for Congress concerning the LCS program include changes or potential changes to
the composition of LCS mission modules announced by the Navy in January 2011, the combat
survivability of the LCS, and hull cracking on LCS-1. Congress’s decisions on the LCS program
could affect Navy capabilities and funding requirements, and the shipbuilding industrial base.
Background
The Program in General
The LCS in Brief
The LCS program was announced on November 1, 2001.1 The LCS is a relatively inexpensive
Navy surface combatant that is to be equipped with modular “plug-and-fight” mission packages,
including unmanned vehicles (UVs). Rather than being a multimission ship like the Navy’s larger
surface combatants, the LCS is to be a focused-mission ship, meaning a ship equipped to perform
one primary mission at any given time. The ship’s mission orientation can be changed by
changing out its mission packages. The basic version of the LCS, without any mission packages,
is referred to as the LCS sea frame.
The LCS’s primary intended missions are antisubmarine warfare (ASW), mine countermeasures
(MCM), and surface warfare (SUW) against small boats (including so-called “swarm boats”),
particularly in littoral (i.e., near-shore) waters. The LCS program includes the development and
procurement of ASW, MCM, and SUW mission packages for LCS sea frames. The LCS’s
permanently built-in gun gives it some ability to perform the SUW mission even without an SUW
module.
Additional missions for the LCS include peacetime engagement and partnership-building
operations, intelligence, surveillance, and reconnaissance (ISR) operations, maritime intercept
operations, operations to support special operations forces, and homeland defense operations. An
LCS might perform these missions at any time, regardless of its installed mission module,

1 On November 1, 2001, the Navy announced that it was launching a Future Surface Combatant Program aimed at
acquiring a family of next-generation surface combatants. This new family of surface combatants, the Navy stated,
would include three new classes of ships: a destroyer called the DD(X)—later redesignated the DDG-1000—for the
precision long-range strike and naval gunfire mission; a cruiser called the CG(X) for the air defense and ballistic
missile mission, and a smaller combatant called the Littoral Combat Ship (LCS) to counter submarines, small surface
attack craft, and mines in heavily contested littoral (near-shore) areas. For more on the DDG-1000 program, see CRS
Report RL32109, Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress, by
Ronald O'Rourke. For more on the CG(X) program, see CRS Report RL34179, Navy CG(X) Cruiser Program:
Background for Congress
, by Ronald O'Rourke.
Congressional Research Service
1

Navy Littoral Combat Ship (LCS) Program

although an installed mission module might enhance an LCS’s ability to perform some of these
missions.
The LCS displaces about 3,000 tons, making it about the size of a corvette (i.e., a light frigate) or
a Coast Guard cutter. It has a maximum speed of more than 40 knots, compared to something
more than 30 knots for the Navy cruisers and destroyers. The LCS has a shallower draft than
Navy cruisers and destroyers, permitting it to operate in certain coastal waters and visit certain
ports that are not accessible to Navy cruisers and destroyers. The LCS employs automation to
achieve a reduced “core” crew of 40 sailors. Up to 35 or so additional sailors are to operate the
ship’s embarked aircraft and mission packages, making for a total crew of about 75, compared to
more than 200 for the Navy’s frigates and about 300 (or more) for the Navy’s current cruisers and
destroyers.
Planned Procurement Quantities
The Navy plans to field a force of 55 LCS sea frames and 64 LCS mission packages (16 ASW, 24
MCM, and 24 SUW). The Navy’s planned force of 55 LCSs would account for about one-sixth of
the Navy’s planned fleet of more than 300 ships of all types.2
Navy plans call for procuring 19 LCSs in the five-year period FY2012-FY2016, in annual
quantities of 4-4-4-4-3. These 19 ships account for more than one-third of the 55 battle force
ships in the Navy’s FY2012-FY2016 shipbuilding plan. The Navy’s FY2011-FY2040 30-year
shipbuilding plan, submitted to Congress in February 2010 in conjunction with the FY2011
budget, shows three LCSs per year for FY2016-FY2019, two per year for FY2020-FY2024, a 1-
2-1-2 pattern for FY2025-FY2033, and two per year for FY2034-FY2040. LCSs scheduled for
procurement in the final years of the 30-year plan would be replacements for LCSs that will have
reached the end of their 25-year expected service lives by that time.
Two LCS Designs
On May 27, 2004, the Navy awarded contracts to two industry teams—one led by Lockheed
Martin, the other by General Dynamics (GD)—to design two versions of the LCS, with options
for each team to build up to two LCSs each. The LCS designs developed by the two teams are
quite different—the Lockheed team’s design is based on a steel semi-planing monohull, while GD
team’s design is based on an aluminum trimaran hull (see Figure 1). The two ships also use
different built-in combat systems (i.e., different collections of built-in sensors, computers,
software, and tactical displays) that were designed by each industry team. The Navy states that
both LCS designs meet the Key Performance Parameters (KPPs) for the LCS program.

2 For more on the Navy’s planned fleet, see CRS Report RL32665, Navy Force Structure and Shipbuilding Plans:
Background and Issues for Congress
, by Ronald O'Rourke.
Congressional Research Service
2





Navy Littoral Combat Ship (LCS) Program

Figure 1. Lockheed LCS Design (Top) and General Dynamics LCS Design (Bottom)

Source: Source: U.S. Navy file photo accessed by CRS at http://www.navy.mil/list_all.asp?id=57917 on January 6,
2010.
Congressional Research Service
3

Navy Littoral Combat Ship (LCS) Program

Two LCS Shipyards
The Lockheed LCS design is built at the Marinette Marine shipyard at Marinette, WI.3 The GD
LCS design is built at the Austal USA shipyard at Mobile, AL.4 Odd-numbered LCSs (i.e., LCS-
1, LCS-3, LCS-5, and so on) use the Lockheed design; even numbered LCSs (i.e., LCS-2, LCS-4,
LCS-6, and so on) use the GD design.
Table 1 shows the construction status of the first eight LCSs.5 The Navy’s proposed FY2011
budget requested funding to procure two LCSs (LCS-7 and LCS-8). Although the Navy’s FY2011
funding as of mid-March 2011 had not yet been fully determined, the Navy announced on March
17 that it had brought the two FY2011 LCSs under contract.6 LCSs 5 through 8 are the first four
LCSs executed under the two LCS block-buy contracts that are described later in this report (see
“2010 Dual-Award Acquisition Strategy (Implemented)”).

3 Marinette Marine is a division of the Fincantieri Marine Group, an Italian shipbuilding firm. In 2009, Fincantieri
purchased Manitowoc Marine Group, the owner of Marinette Marine and two other shipyards. Lockheed is a minority
investor in Marinette Marine.
4 Austal USA was created in 1999 as a joint venture between Austal Limited of Henderson, Western Australia, and
Bender Shipbuilding & Repair Company of Mobile, AL, with Austal Limited as the majority owner.
5 Table 1 excludes five LCSs that were funded in FY2006-FY2008 but later canceled by the Navy; these five canceled
LCSs are shown in Table D-1 in Appendix D.
6 “Fiscal year 2011 Littoral Combat Ship Contract Awards Announced,” Navy News Service, March 17, 2011,
accessed online at http://www.navy.mil/search/display.asp?story_id=59150. The Navy states that it “is able to make
these awards [i.e., bring LCS-7 and LCS-8 under contract] under the Continuing Resolution because the construction
contracts for the [two] FY 2011 ships and associated Government Furnished Equipment (GFE) and programmatics
were appropriated within the Continuing Resolution Authority constraints which are based on FY 2010 funding
controls.” (Source: Navy Office of Legislative Affairs e-mail to CRS, March 18, 2011.) In other words, the Navy
determined that it was able to bring LCS-7 and LCS-8 under contract, even though the Navy’s final FY2011 funding
level had not yet been determined as of mid-March 2011, because the two ships could be funded within an amount of
money equal to the FY2010 funding level in the Shipbuilding and Conversion, Navy (SCN) appropriation account for
the LCS program, and the Navy judged that the final FY2011 SCN funding level for the LCS program would likely be
at least equal to the FY2010 SCN funding level. The Navy’s requested FY2011 SCN funding level for the LCS
program was greater than the FY2010 funding level for the program, but the higher amount of funding requested for
FY2011 did not reflect the reduction in LCS procurement costs achieved through the Navy’s use of block-buy
contracting for the LCS program.
Congressional Research Service
4

Navy Littoral Combat Ship (LCS) Program

Table 1. Construction Status of LCSs
FY
Navy hull
funded designation
Shipyard Status
2005 LCS-1 Marinette
Marine
Commissioned into service November 8, 2008.
2006 LCS-2
Austal
USA Commissioned into service January 16, 2010.
LCS-3 Marinette
Marine Under
construction.
Delivery scheduled for February 2012.
2009
LCS-4 Austal
USA Under
construction.
Delivery scheduled for June 2012.
LCS-5 Marinette
Marine Under
contract. Delivery scheduled for September 2014.
2010
LCS-6 Austal
USA Under
contract.
Delivery scheduled for July 2014.
LCS-7 Marinette
Marine Under
contract.
Delivery scheduled for October 2013 or
April 2014.
2011
LCS-8 Austal
USA Under
contract.
Delivery scheduled for December 2013 or
June 2014.
Source: Prepared by CRS based on FY2012 Navy budget submission.
Notes: (1) Table excludes five LCSs funded in FY2006-FY2008 but later canceled by the Navy; these five
canceled LCSs are shown in Table D-1 in Appendix D.
(2) CRS on March 18, 2011, asked the Navy to confirm or correct the scheduled delivery dates shown for LCSs
5 through 8, because the dates shown for LCS-5 and LCS-6, are later than those shown for LCS-7 and LCS-8,
respectively. In addition, Navy budget documents (pages 11-1 and 11-4 of the FY2012 justification book for the
SCN account) also provide two different delivery dates for LCS-7 and LCS-8.
Unit Procurement Cost Cap
LCS sea frames procured in FY2010 and subsequent years are subject to a unit procurement cost
cap. The legislative history of the cost cap is as follows:
• The cost cap was originally established by Section 124 of the FY2006 defense
authorization act (H.R. 1815/P.L. 109-163 of January 6, 2006). Under this
provision, the fifth and sixth ships in the class were to cost no more than $220
million each, plus adjustments for inflation and other factors.
• The cost cap was amended by Section 125 of the FY2008 defense
authorization act (H.R. 4986/P.L. 110-181 of January 28, 2008). This provision
amended the cost cap to $460 million per ship, with no adjustments for inflation,
and applied the cap to all LCSs procured in FY2008 and subsequent years.
• The cost cap was amended again by Section 122 of the FY2009 defense
authorization act (S. 3001/P.L. 110-417 of October 14, 2008). This provision
deferred the implementation of the cost cap by two years, applying it to all LCSs
procured in FY2010 and subsequent years.
• The cost cap was amended again by Section 121(c) and (d) of the FY2010
defense authorization act (H.R. 2647/P.L. 111-84 of October 28, 2009). The
provision adjusted the cost cap to $480 million per ship, excluded certain costs
from being counted against the $480 million cap, included provisions for
adjusting the $480 million figure over time to take inflation and other events into
account, and permitted the Secretary of the Navy to waive the cost cap under
Congressional Research Service
5

Navy Littoral Combat Ship (LCS) Program

certain conditions.7 The Navy states that after taking inflation into account, the
$480 million figure equates, as of December 2010, to $538 million.
Estimated Acquisition Cost
The Department of Defense’s (DOD’s) December 31, 2010, Selected Acquisition Report (SAR)
for the LCS program, which was released in mid-April 2011, estimates the total acquisition cost
for 55 LCS sea frames at $37,438.8 million (i.e., about $37.4 billion) in then-year dollars. This
figure includes $3,481.7 million in research and development costs (including funds for the
construction of LCS-1 and LCS-2), $33,720.5 million in procurement costs for LCSs 3 through
55, and $236.6 million in military construction (MilCon) costs. The SAR reports that, in constant
FY2010 dollars, these figures become $31,996.8 million, including $3,426.8 million in research
and development costs, $28,364.0 million in procurement costs, and $206.0 million in MilCon
costs, respectively.8
The December 31, 2010, SAR does not contain estimated acquisition costs for the planned total
of 64 LCS mission packages. The SAR states:
On February 18, 2011, USD(AT&L)9 conducted a Milestone B (MS B) Defense Acquisition
Board (DAB) for the seaframe portion of the LCS program. The decision of the DAB was to
separate the program into two separate and distinct programs with separate reporting
requirements. The Seaframe portion of the program is reported in this SAR as approved at
MS B. The Mission Module portion of the program will begin reporting when it receives its
Milestone B decision.10
Estimated Operation and Support (O&S) Cost
DOD’s December 31, 2010, SAR for the sea frame portion of the LCS program estimates the total
life-cycle operation and support (O&S) cost for 55 sea frames, each operated for 25 years, at
$87,089.3 million (i.e., about $87.1 billion) in then-year dollars, or $50,479.0 million in constant
FY2010 dollars. The SAR estimates the annual O&S cost of a single LCS sea frame at $36.6
million in constant FY2010 dollars.11 (Dividing the figure of $50,479.0 million by 55 ships and
25 years per ship produces a figure of $36.7 million per ship per year.) The SAR states that these

7 Section 121(d)(1) states that the Secretary of the Navy may waive the cost cap if:
(A) the Secretary provides supporting data and certifies in writing to the congressional defense
committees that—
(i) the total amount obligated or expended for procurement of the vessel-
(I) is in the best interest of the United States; and
(II) is affordable, within the context of the annual naval vessel construction plan required
by section 231 of title 10, United States Code; and
(ii) the total amount obligated or expended for procurement of at least one other vessel
authorized by subsection (a) has been or is expected to be less than $480,000,000; and
(B) a period of not less than 30 days has expired following the date on which such certification and
data are submitted to the congressional defense committees.
8 Department of Defense, Selected Acquisition Report (SAR), LCS, as of December 31, 2010, p. 14.
9 The Under Secretary of Defense (Acquisition, Technology, and Logistics) – DOD’s acquisition executive.
10 Department of Defense, Selected Acquisition Report (SAR), LCS, as of December 31, 2010, p. 4.
11 Department of Defense, Selected Acquisition Report (SAR), LCS, as of December 31, 2010, p. 37.
Congressional Research Service
6

Navy Littoral Combat Ship (LCS) Program

estimates are based on certain assumptions, including an average Defense Energy Support Center
(DESC) price of fuel of $117.60 per barrel in constant FY2010 dollars. The SAR states that the
“source of [the] estimate is the Navy Service Cost Position and OSD Independent Cost Estimate
developed and approved in support of LCS Seaframe Milestone B decision February, 2011.” The
estimated O&S costs in the SAR appear to be for the 55 LCS sea frames only; they do not appear
to include O&S costs (including associated personnel costs) for LCS mission modules.
The Congressional Budget Office (CBO) estimated O&S costs for LCS sea frames in an April 28,
2010, letter.12 A February 2010 Government Accountability Office (GAO) report commented on a
2009 Navy estimate of LCS O&S costs.13
Manning and Deployment Concept
The Navy plans to maintain three LCS crews for each two LCSs, and to keep one of those two
LCSs continuously underway—a plan Navy officials sometimes refer to as “3-2-1.” Under the 3-
2-1 plan, LCSs are to be deployed for 16 months at a time, and crews are to rotate on and off
deployed ships at four-month intervals.14 The 3-2-1 plan will permit the Navy to maintain a
greater percentage of the LCS force in deployed status at any given time than would be possible
under the traditional approach of maintaining one crew for each LCS and deploying LCSs for six
or seven months at a time.

12 Letter dated April 28, 2010, from Douglas W. Elmendorf, Director, CBO, to the Honorable Jeff Sessions, 8 pp. The
full text of the letter is available online at http://www.cbo.gov/ftpdocs/114xx/doc11431/04-28-SessionsLetter.pdf.
13 The GAO report stated:
The Navy estimated operating and support costs for LCS seaframes and mission packages in 2009,
but the estimates do not fully reflect DOD and GAO best practices for cost estimating and may
change due to program uncertainties. GAO’s analysis of the Navy’s 2009 estimates showed that the
operating and support costs for seaframes and mission packages could total $84 billion (in constant
fiscal year 2009 dollars) through about 2050. However, the Navy did not follow some best
practices for developing an estimate such as (1) analyzing the likelihood that the costs could be
greater than estimated, (2) fully assessing how the estimate may change as key assumptions change,
and (3) requesting an independent estimate and comparing it with the program estimate. The
estimates may also be affected by program uncertainties, such as potential changes to force
structure that could alter the number of ships and mission packages required. The costs to operate
and support a weapon system can total 70 percent of a system’s costs, and the lack of an estimate
that fully reflects best practices could limit decision makers’ ability to identify the resources that
will be needed over the long term to support the planned investment in LCS force structure. With a
decision pending in 2010 on which seaframe to buy for the remainder of the program, decision
makers could lack critical information to assess the full costs of the alternatives.
(Government Accountability Office, Littoral Combat Ship[:] Actions Needed to Improve Operating
Cost Estimates and Mitigate Risks in Implementing New Concepts
, GAO-10-257, February 2010,
summary page.)
14 See, for example, Grace Jean, “Buying Two Littoral Combat Ship Designs Saves the Navy $600 Million, Official
Says,” NationalDefenseMagazine.org, January 12, 2011.
Congressional Research Service
7

Navy Littoral Combat Ship (LCS) Program

Major Program Developments
Growth in Sea Frame Procurement Costs
The Navy originally spoke of building LCS sea frames for about $220 million each in constant
FY2005 dollars. Costs for the first few LCSs subsequently more than doubled. For a detailed
discussion of cost growth on the first few LCS sea frames from the FY2007 budget through the
FY2012 budget, see Appendix C.
2007 Program Restructuring and Ship Cancellations
The Navy substantially restructured the LCS program in 2007 in response to significant cost
growth and delays in constructing the first LCS sea frames. This restructuring led to the
cancellation of four LCSs that were funded in FY2006 and FY2007. A fifth LCS, funded in
FY2008, was cancelled in 2008. For details on the 2007 program restructuring and the
cancellation of the five LCSs funded in FY2006-FY2008, see Appendix D.
2009 Down Select Acquisition Strategy (Not Implemented)
On September 16, 2009, the Navy announced a proposed acquisition strategy under which the
Navy would hold a competition to pick a single design to which all LCSs procured in FY2010
and subsequent years would be built (i.e., carry out a design “down select”).15 Section 121(a) and
(b) of the FY2010 defense authorization act (H.R. 2647/P.L. 111-84 of October 28, 2009)
provided the Navy authority to implement this down select strategy. The Navy’s down select
decision was expected to be announced by December 14, 2010, the date when the two LCS
bidders’ bid prices would expire.16 The down select strategy was not implemented; it was

15 The winner of the down select would be awarded a contract to build 10 LCSs over the five-year period FY2010-
FY2014, at a rate of two ships per year. The Navy would then hold a second competition—open to all bidders other
than the shipyard building the 10 LCSs in FY2010-FY2014—to select a second shipyard to build up to five additional
LCSs to the same design in FY2012-FY2014 (one ship in FY2012, and two ships per year in FY2013-FY2014). These
two shipyards would then compete for contracts to build LCSs procured in FY2015 and subsequent years.
Prior to the Navy’s announcement of September 16, 2009, the Navy had announced an acquisition strategy for LCSs to
be procured in FY2009 and FY2010. Under this acquisition strategy, the Navy bundled together the two LCSs funded
in FY2009 (LCSs 3 and 4) with the three LCSs to be requested for FY2010 into a single, five-ship solicitation. The
Navy announced that each LCS industry team would be awarded a contract for one of the FY2009 ships, and that the
prices that the two teams bid for both the FY2009 ships and the FY2010 ships would determine the allocation of the
three FY2010 ships, with the winning team getting two of the FY2010 ships and the other team getting one FY2010
ship. This strategy was intended to use the carrot of the third FY2010 ship to generate bidding pressure on the two
industry teams for both the FY2009 ships and the FY2010 ships.
The Navy stated that the contracts for the two FY2009 ships would be awarded by the end of January 2009. The first
contract (for Lockheed Martin, to build LCS-3) was awarded March 23, 2009; the second contract (for General
Dynamics, to build LCS-4) was awarded May 1, 2009. The delay in the awarding of the contracts past the end-of-
January target date may have been due in part to the challenge the Navy faced in coming to agreement with the industry
teams on prices for the two FY2009 ships that would permit the three FY2010 ships to be built within the $460 million
LCS unit procurement cost cap. See also Statement of RADM Victor Guillory, U.S. Navy Director of Surface Warfare,
and RADM William E. Landay, III, Program Executive Officer Ships, and Ms. E. Anne Sandel, Program Executive
Officer Littoral and Mine Warfare, before the Subcommittee on Seapower and Expeditionary Forces of the House
Armed Services Committee [hearing] on the Current Status of the Littoral Combat Ship Program, March 10, 2009, pp.
7-8.
16 The Navy had earlier planned to make the down select decision and award the contract to build the 10 LCSs in the
(continued...)
Congressional Research Service
8

Navy Littoral Combat Ship (LCS) Program

superseded in late-December 2010 by the current dual-award acquisition strategy (see next
section). For additional background information on the down select strategy, see Appendix E.
2010 Dual-Award Acquisition Strategy (Implemented)
On November 3, 2010, while observers were awaiting the Navy’s decision under the down select
strategy (see previous section), the Navy notified congressional offices that it was prepared to
implement an alternative dual-award acquisition strategy under which the Navy would forego
making a down select decision and instead award each LCS bidder a 10-ship contract for the six-
year period FY2010-FY2015, in annual quantities of 1-1-2-2-2-2. The Navy stated that, compared
to the down select strategy, the dual-award strategy would reduce LCS procurement costs by
hundreds of millions of dollars. The Navy needed additional legislative authority from Congress
to implement the dual-award strategy. The Navy stated that if the additional authority were not
granted by December 14, the Navy would proceed to announce its down select decision under the
acquisition strategy announced on September 16, 2009. On December 13, it was reported that the
two LCS bidders, at the Navy’s request, had extended the prices in their bids to December 30,
effectively giving Congress until December 30 to decide whether to grant the Navy the authority
needed for the dual-award strategy.
The Navy’s November 3 proposal of a dual-award strategy posed an issue for Congress of
whether this strategy would be preferable to the down select strategy, and whether Congress
should grant the Navy, by December 30, the additional legislative authority the Navy would need
to implement the dual-award strategy. On December 14, 2010, the Senate Armed Services
Committee held a hearing to review the proposed dual-award strategy. Congress granted the Navy
authority to implement the dual-award strategy in Section 150 of H.R. 3082/P.L. 111-322 of
December 22, 2010, an act that, among other things, funded federal government operations
through March 4, 2011.
On December 29, 2010, using the authority granted in H.R. 3082/P.L. 111-322, the Navy
implemented the dual-award strategy, awarding a 10-ship, fixed-price incentive (FPI) block-buy
contract to Lockheed, and another 10-ship, FPI block-buy contract to Austal USA. In awarding
the contracts, the Navy stated that LCSs to be acquired under the two contracts are to have an
average unit cost of about $440 million, a figure well below the program’s adjusted unit
procurement cost cap (as of December 2010) of $538 million (see “Unit Procurement Cost Cap”).
The 20 ships to be acquired under the two contracts have a target cost and a higher ceiling cost.
Any cost growth above the target cost and up to the ceiling cost would be shared between the
contractor and the Navy according to an agreed apportionment (i.e., a “share line”). Any cost
growth above the ceiling cost would be borne entirely by the contractor. The Navy stated that, as
a worst case, if the costs of the 20 ships under the two FPI contracts grew to the ceiling figure and
all change orders were expended, the average cost of the ships would increase by about $20
million, to about $460 million, a figure still well below the adjusted cost cap figure of $538
million.17

(...continued)
summer of 2010, but the decision was delayed to as late as December 14. (The final bids submitted by the two LCS
contractors were submitted on about September 15, and were valid for another 90 days, or until December 14.)
17 Source: Contract-award information provided to CRS by navy office of Legislative Affairs, December 29, 2010.
Congressional Research Service
9

Navy Littoral Combat Ship (LCS) Program

The Navy on December 29 technically awarded only two LCSs (one to each contractor). These
ships (LCS-5 and LCS-6) are the two LCSs funded in FY2010. Awards of additional ships under
the two contracts are subject to congressional authorization and appropriations. The Navy states
that if authorization or sufficient funding for any ship covered under the contracts is not provided,
or if the Navy is not satisfied with the performance of a contractor, the Navy is not obliged to
award additional ships covered under contracts. The Navy states that it can do this without paying
a penalty to the contractor, because the two block-buy contracts, unlike a typical multiyear
procurement (MYP) contract, do not include a provision requiring the government to pay the
contractor a contract cancellation penalty.18
The Navy’s proposed dual-award strategy is broadly similar to a notional dual-award approach
that was presented in this CRS report as an option for Congress (see Appendix E) since
September 27, 2009, when the report was updated to incorporate the Navy’s September 16, 2009,
announcement of its proposed down select strategy.
For additional background information on the dual-award strategy, see Appendix F.
2011 Announced Changes in Mission Module Equipment
The Navy in January 2011 announced changes or potential changes to the composition of LCS
mission modules; the sections below summarize these changes.
SUW Module: Griffin Selected as Recommended Replacement for N-LOS
The Navy had planned to use an Army missile program known as the Non-Line of Sight Launch
System (NLOS-LS) as part of the LCS surface warfare (SUW) mission package. The Navy
planned for LCSs equipped with SUW mission packages to be nominally armed with three NLOS
missile launchers, each with 15 missiles, for a total of 45 missiles per ship. The missiles could be
used to counter swarm boats or other surface threats.
In May 2010, DOD approved an Army recommendation to cancel NLOS-LS.19 Following the
cancellation of NLOS-LS, the Navy assessed potential alternative systems for fulfilling the NLOS
role in the SUW mission package. On January 11, 2011, the Navy announced that it had selected
the Griffin missile as its recommended replacement for NLOS-LS. The Navy stated that Griffin
will be about half as expensive as NLOS-LS, and that it could be delivered about as soon as
NLOS. The Navy stated that an initial version of the Griffin would be ready by 2014 or 2015, and
that a follow-on, longer-ranged version would be ready by 2016 or 2017.20 One press report

18 Source: Navy briefing to CRS and the Congressional Budget Office (CBO) on December 15, 2010. For a press
article on this issue, see Cid Standifer, “FY-11 LCS Contracts On Hold Because Of Continuing Resolution,” Inside the
Navy
, March 14, 2011.
19 “Out of Sight,” Defense Daily, May 17, 2010: 3. See also Kate Brannen, “U.S. Army Asks to Cancel NLOS-LS,”
DefenseNews.com, April 23, 2010; Jason Sherman, “Army Cancels NLOS-NS, Frees Up Billions For Other
Procurement Needs,” Inside the Navy, April 26, 2010; Sebastian Sprenger, “NLOS-LS Seen As Effective—But To
Pricey—In Key Army Analysis,” Inside the Navy, May 3, 2010.
20 Grace Jean, “Buying Two Littoral Combat Ship Designs Saves the Navy $600 Million, Official Says,”
NationalDefenseMagazine.org, January 12, 2011; Carlo Munoz, “Navy Pushing Griffin For NLOS-LS Replacement,”
Defense Daily, January 13, 2011; Michael Fabey, “U.S. Navy Identifies New LCS Modules,” Aerospace Daily &
Defense Report
, January 14, 2011: 3; Cid Standifer, “Raytheon’s Griffin System To Replace NLOS In LCS Mission
Package,” Inside the Navy, January 17, 2011; David Wichner, “New Navy Ships May Use Small Raytheon Missile,”
(continued...)
Congressional Research Service
10

Navy Littoral Combat Ship (LCS) Program

quoted an official from Raytheon, the maker of the Griffin, as stating that the Griffin’s current
range is less than 5 kilometers (i.e., less than about 2.7 nautical miles).21 Another press report
stated: “The Griffin’s range has not been officially disclosed, though industry experts have
reported a range of about 3.5 miles when surface-launched and about nine miles when launched
from the air. The NLOS missile had a range of about 25 miles.”22
ASW Module: Shift to Systems With “In Stride” Capability
The Navy in January 2011 provided information on changes it has decided to make to the systems
making up the ASW module. A January 14, 2011, press report stated that the Navy
discovered that while its [originally planned] LCS ASW module was able to do the mission,
the equipment package proved unsatisfactory because the ship would actually have to stop in
the water to deploy the equipment. “The ship could not do it in stride,” says Capt. John
Ailes, Navy mission module program office manager….
As for its ASW defense, the Navy plans to deploy a module that will include three parts: a
variable-depth sonar; a multi-functional towed array; and a lightweight towed array, Ailes
says. The Navy will be testing the ASW module package throughout this and the coming
year, he says, with an eye toward initial operational capability in 2017.23
A January 12, 2011, press report stated:
For the anti-submarine warfare package, the Navy in 2012 expects to receive from Thales a
low frequency sonar under development for demonstration and testing purposes. The towed
array will provide sailors with a mobile anti-submarine capability. In the meantime, officials
are moving ahead with other sensors, including the multifunction towed array for passive
detection and the lightweight tow for torpedo countermeasures and non-acoustic rounds. The
intent is to be able to counter enemy diesel submarines in the littorals. “You shift capabilities
of the ship from a stationary anti-submarine warfare buried-in system to an in-stride littoral
and open-ocean capability when you need it. That puts sensors and sound sources in the fleet
in numbers,” said [Rear Admiral Frank C. Pandolfe, director of the Navy’s surface warfare
division].24
MCM Module: Possible Replacement of RAMICS by Modified ALMDS
A January 13, 2011, press report stated:
The Navy is looking to terminate an underperforming anti-mine system from the LCS
mission package being designed for that mission.

(...continued)
Arizona Daily Star (Tucson), January 18, 2011.
21 Cid Standifer, “Raytheon’s Griffin System To Replace NLOS In LCS Mission Package,” Inside the Navy, January
17, 2011.
22 David Wichner, “New Navy Ships May Use Small Raytheon Missile,” Arizona Daily Star (Tucson), January 18,
2011.
23 Michael Fabey, “U.S. Navy Identifies New LCS Modules,” Aerospace Daily & Defense Report, January 14, 2011: 3.
24 Grace Jean, “Buying Two Littoral Combat Ship Designs Saves the Navy $600 Million, Official Says,”
NationalDefenseMagazine.org, January 12, 2011.
Congressional Research Service
11

Navy Littoral Combat Ship (LCS) Program

Service acquisition officials have become increasingly frustrated with the testing results of
the Rapid Airborne Mine Clearance System (RAMCS), Rear Adm. Frank Pandolfe, head of
the Navy’s surface warfare directorate, said this week.
While testing is still underway on the Northrop Grumman [NOC] system, which is to locate
and destroy mines in shallow waters, the results have fallen short of service expectations, he
said during a Jan. 11 speech at the Surface Navy Association’s annual conference in
Arlington, Va.
To remedy the situation, Pandolfe said program officials are looking to modify the Airborne
Laser Mine Detection System (ALMDS) to carry out the RAMCS mission.
Also manufactured by Northrop Grumman, the ALMDS uses directed energy system
mounted on board a MH-60R helicopter to detect mines at the same shallow depth the
RAMCS was designed to destroy.
If the modification is successful, Navy decisionmakers plan to ax the RAMCS platform and
use the ALMDS variant, Pandolfe said.
The surface warfare chief did not go into specifics regarding what kind of development work
would be necessary to make such a transition, but he did note the move would also trim costs
on the growing costs on the LCS anti-mine package.
However, Pandolfe reiterated that if the Navy opts to go with the ALMDS approach, the
mission package itself would be delivered on time.
“They will be where they need to be when they need to be there,” he said.25
FY2011 Funding Request
The Navy’s proposed FY2011 budget requested $1,231.0 million in procurement funding for the
two LCSs that the Navy wants to procure in FY2011, and $278.4 million in FY2011 advance
procurement funding for 11 LCSs that the Navy wanted, under the FY2011 budget submission, to
procure in FY2012-FY2014. (The Navy now wants, under the dual-award strategy, to procure 12
LCSs in FY2012-FY2014.) The Navy’s proposed FY2011 budget also requested $9.8 million in

25 Carlo Munoz, “Navy Looks To Cut Anti-Mine System From LCS Mission Package,” Defense Daily, January 13,
2011. Material in brackets as in original. A January 12, 2011, press report similarly stated that
A key technology [for the MCM module], the remote mine hunting vehicle, a diesel-powered semi-
submersible that will tow the AQS-20 sonar, is behind schedule.
“Reliability of the system is about 80 percent of where we need to be,” [Rear Admiral Frank C.
Pandolfe, director of the Navy’s surface warfare division] said. But he remains confident that the
system will pull through. The rapid airborne mine clearance system, or RAMICS, a cannon
designed to destroy mines floating below the surface in deep water, is not performing well in tests.
Navy officials are looking to adapt the airborne mine neutralization system, which kills mines at the
bottom of the ocean, for the mission. Preliminary testing is showing promise, and if it works, then
the Navy may not need RAMICS, Pandolfe said.
“That would allow us to streamline the program, save money and go to a single kill vehicle,” he
said. When the legacy mine sweeping force starts leaving the fleet in 2017, the Navy will be ready
to introduce the LCS systems, he said.
(Grace Jean, “Buying Two Littoral Combat Ship Designs Saves the Navy $600 Million, Official
Says,” NationalDefenseMagazine.org, January 12, 2011.)
Congressional Research Service
12

Navy Littoral Combat Ship (LCS) Program

procurement funding to procure LCS module weapons, $83.0 million in procurement funding for
procurement of LCS mission packages, and $226.3 million in research and development funding
for the LCS program.
FY2012 Funding Request
Under Navy budget plans, the four LCSs that the Navy wants to procure in FY2012 are to receive
$79.5 million in prior-year advance procurement (AP) funding. Navy’s proposed FY2012 budget
requests $1,802.1 million in FY2012 procurement funding to complete the four ships’ combined
estimated procurement cost of $1,881.6 million. The Navy’s proposed FY2012 budget also
requests $79.6 million procurement funding for procurement of LCS mission packages, and
$286.8 million in research and development funding for the LCS program.
Issues for Congress
Lack of Economic Order Quantity (EOQ) Authority for Executing
the Block-Buy Contracts

The provision that granted the Navy the authority to implement a dual-award acquisition strategy
for the LCS program—Section 150 of the Continuing Appropriations and Surface Transportation
Extensions Act, 2011 (H.R. 3082/P.L. 111-322)—did not include wording explicitly permitting
the Navy to use economic order quantity (EOQ) purchasing in procuring the 20 LCSs covered
under the two 10-ship LCS block-buy contracts. (EOQ authority comes automatically with grants
of authority for multiyear procurement [MYP] arrangements,26 but needs to be explicitly included
in provisions that grant authority for block-buy contracts.)
One option for Congress, in marking up the Navy’s proposed FY2012 budget, would be to
include a provision explicitly permitting the Navy to use EOQ purchasing in procuring the 20
LCSs covered under the two 10-ship block-buy contracts. Granting the Navy EOQ authority for
the two LCS block-buy contracts would permit the Navy to bring forward certain long-leadtime
components of many of these 20 LCSs and procure them all at once, in batch fashion (i.e., order
them in an economic quantity), during the earlier years of the block-buy contracts. This could
reduce the production costs of these components and thereby reduce the total procurement costs
of many of these 20 LCSs. Since EOQ purchasing would shift the procurement of certain LCS
sea frame components from later years of the two block-buy contracts to earlier years, funding
these EOQ purchases would increase LCS sea frame procurement funding requirements in the
earlier years of the two block-buy contracts, and reduce (by an even larger amount) LCS sea
frame procurement funding requirements in the later years of the two LCS block-buy contracts.
Announced Changes in Mission Module Equipment
One potential oversight question for Congress concerns the changes and potential changes in LCS
mission module equipment announced by the Navy in January 2011 (see “2011 Announced

26 EOQ authority is included in 10 USC 2306b, the law governing MYP arrangements.
Congressional Research Service
13

Navy Littoral Combat Ship (LCS) Program

Changes in Mission Module Equipment” in “Background”). Potential oversight questions for
Congress include the following:
• How will the announced changes in the equipment making up the SUW and
ASW modules affect the Initial Operational Capability (IOC) dates of these
modules?
• How would the replacement of the NLOS-LS missile by the Griffin missile in the
SUW module affect the SUW capability of the LCS, particularly in light of the
range of the Griffin missile compared to that of the NLOS-LS missile?
• When does the Navy anticipate announcing its decision on whether to keep the
Rapid Airborne Mine Clearance System (RAMICS) in the MCM module or
replace it with a modified version of the Airborne Laser Mine Detection System
(ALMDS)? If RAMICS were replaced by a modified version of ALMDS, how
would that affect the IOC date of the MCM module and the MCM capability of
the LCS?
Combat Survivability
Another potential oversight issue for Congress for the LCS program concerns the combat
survivability of the LCS. A December 2010 report from DOD’s Director of Operational Test and
Evaluation stated:
[On LCS-1,] Critical ship control systems essential to support the crew have performed well
in testing; however, several systems required for self-defense and mission package support
have demonstrated early reliability problems….
LCS is not expected to be survivable in terms of maintaining a mission capability in a hostile
combat environment. This assessment is based primarily on a review of the LCS design
requirements. The Navy designated LCS a Survivability Level 1 ship; the design of the ship
just allows for crew evacuation. Consequently, its design is not required to include
survivability features necessary to conduct sustained operations in a combat environment.
The results of early live fire testing using modeling and simulation, while not conclusive,
have raised concerns about the effects weapons will have on the crew and critical equipment.
Additional live fire testing and analysis is needed to fully assess the survivability of the LCS
class of ships. Additional information is available in the classified LCS 1 Early Fielding
Report.27
At a March 9, 2011, hearing on the Navy’s proposed FY2012 budget before the Defense
subcommittee of the House Appropriations Committee, the following exchange took place
concerning LCS survivability:
REPRESENTATIVE JAMES MORAN: I’d like to ask questions about the Littoral Combat
Ship and the Aegis Combat System. Perhaps the best directive that Admiral Roughead—
either of our other distinguished witnesses may want to chime in as well—we know that the
LCS is designed to fight in littoral waters, where larger surface and subsurface ships can’t
safely navigate.

27 Department of Defense, Director, Operation Test and Evaluation, FY 2010 Annual Report, December 2010, pp. 144-
145.
Congressional Research Service
14

Navy Littoral Combat Ship (LCS) Program

But according to the Pentagon’s (inaudible) report that just came out in the last two or three
months, the Department of Operational Tests and Evaluations, and I quote, “The LCS design
is not required to include survivability features necessary to conduct sustained operations in
the combat environment.”
So I have to ask, why are we buying 55 of these surface combatants if they’re not designed
to survive in a hostile combat environment? I don’t understand how we can justify that. What
other warfighter need does the LCS program satisfy if the ships are not designed to survive
in a combat environment? Admiral?
CHIEF OF NAVAL OEPRATIONS ADMIRAL GARY ROUGHEAD: Yes, sir. And I
would submit that as you look at the levels of survivability that we have in our ships today,
that the Littoral Combat Ship is not as hard and tough a ship, for example, as one of our
guided missile destroyers. But it still possesses levels of survivability and redundancy that
allow it to go into hostile environments. And so, there are varying degrees as to how we
grade them. And LCS, in concert with the rest of the fleet, I believe is going to be a very key
component of our ability to operate in the military.28
At a March 9, 2011, hearing on Navy shipbuilding programs before the Seapower and Projection
Forces subcommittee of the House Armed Services Committee, the following exchange took
place concerning LCS survivability:
REPRESENTATIVE HANK JOHNSON: I’m concerned that we may be prioritizing
quantity at the expense of quality particularly given our short-term focus on light ships
designed for use in coastal waters. I’m concerned about unresolved questions regarding
survivability of the LCS.…
Secretary Stackley, for years the Director of Operational Testing and Evaluation has raised
serious concerns regarding survivability of the littoral combat ship and whether the LCS
meets its Level 1 survivability requirement, why are LCS full ship shock tests not scheduled
until Fiscal Year ‘14 when we will already have produced 10 or 12 ships? And why would
we begin full-scale production of the ship if there are serious outstanding concerns regarding
its survivability?
ASSISTANT SECRETARY OF THE NAVY FOR RESEARCH DEVELOPMENT AND
ACQUISITION SEAN STACKLEY: Yes, sir. Let me first by describing LCSs. LCS-1 and 2
are both designed to Level 1 level of survivability. And all the analysis and testing to date
supports the determination that they in fact meet their survivability requirements. The
scheduling of the full ship shock trial on LCS in 2014 is about right compared to all other
shipbuilding programs.
In fact, typically, in a major shipbuilding program, you don’t shock the lead ship, you end up
shocking one of the first follow ships. So, for example, the last major shipbuilding program
that we conducted shock trials on, the DDG-51, the first ship to be shocked was DDG-53,
which wasn't delivered until two years after the 51. And by the time she was shocked, we
had about 20 DDG 51s under contract in a full rate production.
The nature of the beast in shipbuilding is that you have such a large capital intense structure
that’s building these ships, that you cannot afford to stop construction and wait for the lead

28 Source: Transcript of hearing. For a press article discussing this exchange, see Andrew Burt, “CNO Defends Littoral
Combat Ship’s Role In Fleet Despite Low Survivability,” Inside the Navy, March 14, 2011.
Congressional Research Service
15

Navy Littoral Combat Ship (LCS) Program

ship to be built, tested, and then get around to a full ship shock before you start construction
again.
So what we do is we address to the extent possible through analysis and surrogate testing and
developmental testing, proof out the design so that by the time we get to the shock trial, the
risk has been retired.
And in fact, if you go back and look at the results from prior full ship shock trials, the change
activity that’s driven into those ship’s designs is relatively minimal because we have in fact
spent so much time on the front end of the design to retire that risk. And we see the same
case here for LCS.29
Hull Cracking on LCS-1
Another potential oversight issue for Congress for the LCS program concerns hull cracking on
LCS-1. A March 18, 2011, press report states that LCS-1
developed a crack as long as six inches through its hull during sea trials, prompting a U.S.
Navy investigation of the design.
The Navy is analyzing the crack to determine if changes are required for future Lockheed
Martin hulls, Naval Sea Systems Command spokesman Christopher Johnson said yesterday
in an e-mail. This includes reviewing “the design, construction drawings and welding
procedures,” he said.
During a heavy-weather ocean trial on the USS Freedom in mid-February, he said, sailors
discovered a six-inch horizontal hull crack below the waterline that leaked five gallons an
hour. Inside the hull the crack measured three inches. It originated in a weld seam between
two steel plates.
The ship returned to its home port in San Diego, avoiding rough seas, after the commanding
officer judged the leak rate “manageable,” Johnson said.
Smaller cracks that indicated welding “defects” showed up in the welds of the vessel’s
aluminum structure during sea trials last year, Johnson said in his e-mail.
Initial analysis of the second Lockheed-built vessel, the USS Independence, showed
improved welding, he said.
A spokesman for Lockheed Martin, Keith Little, said the company “is working closely with
the Navy to confirm the root cause” and has made all necessary repairs to the ship. “We are
also supporting the Navy in additional testing along the hull to confirm this crack was an
isolated anomaly,” Little said….
Johnson said in his e-mail that repair of the hull crack was completed March 12….
Johnson said that several years ago the Navy conducted an “early fatigue analysis” on the
Freedom that “identified high-stress areas” in the aluminum superstructure. The areas were
fitted with instruments to collect data and to monitor for cracks.

29 Source: Transcript of hearing.
Congressional Research Service
16

Navy Littoral Combat Ship (LCS) Program

Cracks showed up late last year in the predicted areas. The measuring instruments remain in
place, and the Navy implemented some design changes to the superstructure “to correct high
stress and fatigue issues,” Johnson said.30
An April 12, 2011, press report states:
Navy officials looking into an incident in which cracking developed on portions of the
Lockheed Martin [LMT]-version of the Littoral Combat Ship have ruled out design flaws as
a cause, according to a senior company official.
Program officials were notified by Naval Sea Systems Command “a couple of weeks” ago
that the LCS design of the Lockheed Martin variant was not to blame for the cracks, Joe
North, vice president of the company’s Littoral Ship Systems, said during an April 8 briefing
with reporters at the company’s offices in Arlington, Va. Navy review of structural cracks on
the USS Freedom (LCS-1) is still under review, he added.
“It certainly is not design,” he said regarding the Navy review. “So, now we are looking at
was it [caused] by stresses under the way [the Navy] went through the heavy sea testing, or
was it potentially a flaw in the weld that got through.”
North added, “It could be [caused] from ... a workmanship issue. You can [just] imagine the
number of miles of welds on a ship.”
In February, the Navy was forced to suspend heavy sea trials on the LCS-1 after a three- to
six-inch crack in the ship’s hull developed during the trials. In addition to the hull cracks,
structural anomalies were also found in the ship’s main superstructure, according to North.
Since the suspension of sea tests for LCS-1, service officials have been reviewing the
incident, with Lockheed Martin officials supporting the investigation by supplying the Navy
with technical information, North said.
“What we have done, basically, is re-run our models and fed them the data, the engineering
basis for everything we have looked at,” he said. “So, they are taking that, plus their own
assessments and they are controlling the overall assessment of the ship.”
He could not comment on when the Navy review of the incident will be complete, but noted
that company officials have already begun to address some of the issues that led to the
cracking on LCS-1 on the new LCS-3 ship, which is now under construction at Marinette
Marine shipyards in Wisconsin.
“What we have done on [LCS]-3 ... from a producability standpoint, is [ask] how can we
make this better, the second time around,” North said.
To that end, North acknowledged that in “some very small areas” on LCS-1 where program
officials found it difficult to get a “full-penetration weld” employees would “be forced to try
and get a hand in” and get a solid weld.
“So we corrected those [areas] in [LCS]-3 going forward, so that we get full capability ... and
completely make sure up front that everything is done,” he said.

30 Tony Capaccio, “Lockheed NMartin’s First Littoral Combat Ship Cracks, Navy Says,” Bloomberg News, march 18,
2011.
Congressional Research Service
17

Navy Littoral Combat Ship (LCS) Program

While the hull cracking took Navy and Lockheed Martin officials by surprise, the cracks on
the boat’s superstructure “were predicted,” North said, adding they are “more of a nuisance
issue that occurs.” The superstructure on board LCS-3 has also been corrected to address the
flaws in LCS-1.31
Technical Risk
Another potential oversight issue for Congress concerns the amount of technical risk in the
program. The discussion below addresses this issue first with respect to the LCS sea frame, and
then with respect to LCS mission packages.
Sea Frame
Regarding technical risk in developing and building the LCS sea frame, a March 2011 GAO
report stated:
Technology Maturity
Sixteen of 19 critical technologies for both LCS designs are mature. Three technologies—
LCS 1’s overhead launch and retrieval system and LCS 2’s trimaran hull and aluminum
structure—are nearing maturity. Further, launch, handling, and recovery systems, which are
essential to the LCS antisubmarine warfare and mine countermeasures missions, are still
being refined for both designs. For LCS 1, Navy simulations have identified risks in safely
launching and recovering mission systems that experience pendulous motion during
handling—such as the remote multimission vehicle and unmanned surface vehicle systems.
These operations may be complicated by unacceptably high water levels intruding into the
ship’s launch bay during high sea states. On LCS 2, the twin boom extensible crane
system—designed to launch, handle, and recover watercraft—contains unproven elements.
The Navy reports recent progress on these systems including (1) successful operation and
movement of an embarked 11-meter rigid-hull inflatable boat onboard LCS 1 in March 2010,
(2) synthetic lift lines on LCS 2 successfully completing a 200 percent lift test, and (3)
routine usage of a straddle carrier to move an 11-meter rigid-hull inflatable boat (with
stowage cradle) and berthing modules around the LCS 2 mission bay. Navy officials also
report that testing of LCS 2’s twin-boom extensible crane is progressing.
Design and Production Maturity
The Navy provided historical data on design completeness that was inconsistent with data it
provided to GAO last year, but officials did not respond to requests for clarification. The
data provided by the Navy last year indicated that the LCS 3 and LCS 4 began fabrication
with only 69 percent and 57 percent of basic and functional drawings complete, respectively.
The Navy also could not provide this data for the LCS 1 and LCS 2. GAO’s work on
shipbuilding best practices has found that leading commercial firms assess a ship design as
stable when 100 percent of these drawings are complete. By delaying construction start until
basic and functional design is completed and a stable design is achieved, shipbuilders

31 Carlo Munoz, “Lockheed Martin: Navy Rules Out Design Flaws As cause For LCS Cracks,” Defense Daily, April
12, 2011. See also Cid Standifer, “Lockheed: LCS-1 Crack Caused By Faulty Welding, Not A Design Flaw,” Inside the
Navy
, April 11, 2011, and Michael Fabey, “Welds Implicated In LCS Cracks,” Aerospace Daily & Defense Report,
April 11, 2011: 3.
Congressional Research Service
18

Navy Littoral Combat Ship (LCS) Program

minimize the risk of design changes and the subsequent costly rework and out-of-sequence
work these changes can drive.
The Navy used a concurrent design-build strategy for LCS 1 and LCS 2 seaframes, which
proved unsuccessful. Implementation of new design guidelines, delays in major equipment
deliveries, and strong focus on achieving schedule and performance goals resulted in
increased construction costs. The Navy’s ongoing efforts to resolve technical issues affecting
LCS 1 and LCS 2, implement cost reduction measures, and increase mission capability have
led to design changes for LCS 3 and LCS 4. These changes are significant and have affected
the configuration of several major ship systems including propulsion, communications,
electrical, and navigation….
Program Office Comments
According to the Navy, two industry teams (1) have each designed, built, and delivered to
the Navy a lead ship meeting the LCS performance requirements and (2) are currently
building their second ships, with lessons learned from the lead ships incorporated into the
designs. The Navy states that both designs are stable, with LCS 3 and LCS 4 having
experienced minimal design changes to-date, and cites impressive learning and investment
by both shipbuilders as well as significant improvement in cost and schedule performance.
According to the Navy, LCS 3 launched on December 4, 2010, at over 80 percent complete.
This level of completeness at launch, and the improvement in cost and schedule performance
by both shipbuilders, provides the Navy confidence that risk of design change and out-of-
sequence work is minimal. The Navy also provided technical comments, which were
incorporated as appropriate.32
Mission Packages
Regarding technical risk in developing the modular mission packages for the LCS, a March 2011
GAO report stated:
Technology Maturity
At its full baseline capability, operation of the MCM, SUW, and ASW packages on LCS
requires a total of 21 critical technologies, including 11 sensors, 6 vehicles, and 4 weapons.
Of these technologies, 18 are mature and have been demonstrated in a realistic environment.
The Navy has accepted delivery of two partially capable MCM mission packages. According
to program officials, in 2010 the MCM mission package completed end-to-end testing, and
two MCM systems—the AN/AQS-20A sonar and Airborne Laser Mine Detection System—
have completed developmental testing in separate test events. Two other systems—the
Unmanned Surface Vehicle (USV) and Unmanned Surface Sweep System—have not yet
been demonstrated in a realistic environment, and a third—the Remote Minehunting System
(RMS)—has been delayed because of poor reliability. Program officials report that the Navy
is assessing alternative USV designs because the current system does not meet power output
requirements necessary to support the towed surface sweep system. The RMS, which is its
own major defense acquisition program, experienced a Nunn-McCurdy unit cost breach of
the critical threshold in December 2009, due to cost increases resulting from a 51 percent
reduction in quantity and efforts to improve reliability. In June 2010, the Office of the

32 Government Accountability Office, Defense Acquisitions[:] Assessments of Selected Weapon Programs, GAO-11-
233SP, March 2011, p. 98.
Congressional Research Service
19

Navy Littoral Combat Ship (LCS) Program

Secretary of Defense completed its review and certified RMS for continuation. According to
Director, Operational Test and Evaluation, officials, RMS reliability has improved from 7.9
hours to nearly 45 hours between failures. According to program officials, the Navy plans to
recommence RMS production in fiscal year 2015. Further, program officials report that the
Rapid Airborne Mine Clearance System has been removed from the package while the Navy
evaluates more cost-effective alternatives for meeting desired capability delivery time
frames.
The Navy has accepted delivery of two partially capable SUW mission packages and expects
to accept delivery of a third mission package in fiscal year 2011. The Navy will resume
procuring SUW packages in fiscal year 2012. The 30 millimeter gun was test-fired from LCS
1 in September 2009 and according to program officials, integrated with the LCS 1 combat
system and demonstrated at sea in April 2010. In May 2010, DOD cancelled the Non-Line-
of-Sight Launch System due to cost and technical challenges. Officials note the Navy is
evaluating other alternatives and expects to complete evaluation by the second quarter of
fiscal year 2011.
The Navy accepted delivery of one partially capable ASW mission package in September
2008. However, program officials stated that the Navy plans to introduce new mission
systems and classified capabilities before procuring additional ASW packages. Program
officials report that the Navy has completed development and testing of the first ASW
mission package to evaluate operational concepts and refine requirements.
Other Program Issues
The Navy plans to purchase 18 ships and 13 mission packages between fiscal years 2011 and
2015, but developmental delays in key mission package systems mean the Navy will acquire
significant numbers of seaframes before mission packages are proven. GAO has reported
since 2007 on challenges developing systems constituting LCS mission packages and
integrating them with their host platforms. These challenges have delayed the planned
delivery of baseline capability by several years. Until mission package performance is
proven, the Navy risks investing in a fleet of ships that does not deliver its promised
capability and is largely constrained to self-defense as opposed to mission-related tasks.
Program Office Comments
The Navy stated that recent testing has been comprehensive, operationally relevant, and
successful. According to the Navy, the SUW mission package supported early deployment of
LCS 1, providing a counter–illicit trafficking capability. Further, the Navy stated that from
program inception, the acquisition strategy for mission package has employed an incremental
approach and remained stable, fielding systems as they achieve the required level of
maturity. According to the Navy, those few systems experiencing issues (NLOS-LS and
RMS) are either being replaced with alternative systems or are targets of increased focus and
attention. According to the Navy, the results have been positive in all cases. In addition, the
Navy provided technical comments, which were incorporated as appropriate.33
An April 26, 2010, news report stated:

33 Government Accountability Office, Defense Acquisitions[:] Assessments of Selected Weapon Programs, GAO-11-
233SP, March 2011, p. 100.
Congressional Research Service
20

Navy Littoral Combat Ship (LCS) Program

The Littoral Combat Ship program lacks a “timely” test program plan for the mission
packages slated to deploy aboard the vessels, putting the effort at a “medium” risk for cost
increases … according to a new study by the Pentagon’s acquisition directorate....
“The program has major integration challenges between seaframes and MPs’ [mission
packages],” the study states. “To address this issue, the program established an Integrated
Product Team … the team has identified numerous deficiencies and verified corrections
within each seaframe.”34
Total Program Acquisition Cost
Another potential oversight issue for Congress for the LCS program concerns the lack of an
official DOD estimate of the program’s total acquisition (i.e., research and development plus
procurement) cost. Although DOD’s December 31, 2010, SAR for the LCS program provides an
estimated total acquisition cost for 55 LCS sea frames (see “Estimated Acquisition Cost” in
“Background”), DOD has not reported a total estimated acquisition cost for the entire LCS
program, including costs for both 55 LCS sea frames and 64 LCS mission packages.
Supporters of the LCS program could argue that substantial data is available in the Navy’s annual
budget submission on annual LCS research and development and procurement costs for the five-
year period covered by the Future Years Defense Program (FYDP). Skeptics could argue that a
major acquisition program like the LCS program should not proceed to higher annual rates of
production until the program’s potential total acquisition cost is reported and assessed against
other defense spending priorities.
Separate SAR Reporting of Sea Frame and Mission Module Costs
Another potential oversight issue for Congress is whether DOD should report LCS sea frame
costs and LCS mission module costs in separate SARs, or together in the same SAR. As
mentioned earlier (see “Estimated Acquisition Cost” in “Background”), DOD in its December 31,
2010, SAR for the LCS program stated that DOD has decided to “to separate the [LCS] program
into two separate and distinct programs with separate reporting requirements. The Seaframe
portion of the program is reported in this SAR as approved at MS [Milestone] B. The Mission
Module portion of the program will begin reporting when it receives its Milestone B decision.”
Supporters of publishing these two sets of costs in separate SARs could argue that it will facilitate
congressional oversight of the program by helping Congress differentiate sea frame costs from
mission module costs. Supporters of publishing these two sets of costs together in the same SAR
could argue that publishing them in separate SARs could complicate congressional oversight of
the program by making the total cost of the LCS program as a whole (including costs for both sea
frames and mission modules) less visible to Congress, and by making costs in the LCS sea frame
SAR less easily comparable to costs reported in SARs for other Navy shipbuilding programs.

34 Zachary M. Peterson, “DOD Report: LCS Program Faces ‘Medium Risk,’ Integration Challenges, Inside the Navy,
April 26, 2010. Material in brackets as in original.
Congressional Research Service
21

Navy Littoral Combat Ship (LCS) Program

Operational Concepts
Another potential oversight issue for Congress for the LCS program concerns operational
concepts for using LCSs once they enter service. A February 2010 GAO report stated:
The Navy has made progress in developing operational concepts for LCS, but faces risks in
implementing its new concepts for personnel, training, and maintenance that are necessitated
by the small crew size. Specifically, the Navy faces risks in its ability to identify and assign
personnel given the time needed to achieve the extensive training required. GAO’s analysis
of a sample of LCS positions showed an average of 484 days of training is required before
reporting to a crew, significantly more than for comparable positions on other surface ships.
Moreover, the Navy’s maintenance concept relies heavily on distance support, with little
maintenance performed on ship. The Navy acknowledges that there are risks in
implementing its new concepts and has established groups to address how to implement
them. However, these groups have not performed a risk assessment as described in the 2008
National Defense Strategy. The Strategy describes the need to assess and mitigate risks to
executing future missions and managing personnel, training, and maintenance. If the Navy
cannot implement its concepts as envisioned, it may face operational limitations, have to
reengineer its operational concepts, or have to alter the ship design. Many of the concepts
will remain unproven until 2013 or later, when the Navy will have committed to building
almost half the class. Having a thorough risk assessment of the new operational concepts
would provide decision makers with information to link the effectiveness of these new
concepts with decisions on program investment, including the pace of procurement.35
An April 2011 news analysis article states:
The Navy promises this ship will be ideal for going after fast, swarming small craft like
those operated by the Iranian Pasdaran, or Revolutionary Guards, and for chasing pirates.
With speeds in excess of 40 knots, “it’s great for a knife fight,” some like to say. But the
speed currently touted as a great war-fighting quality was originally meant for transit. You
would perform your mine-hunting mission at the top of the Persian Gulf, for example, zip
back to Bahrain or somewhere, change out the mission module in two or three hours, and
zoom back to be on station by morning with a surface or anti-submarine warfare module
installed, ready for action. But it gradually became apparent the modules couldn’t be
swapped out that fast—two or three days is more like it—and the transit speed requirement
diminished in value. Even though the original requirement is gone, the speed remains—at the
cost of endurance and other factors—and the Navy has found other ways to describe its
usefulness.
Another remarkable characteristic of the program is that the 20 ships just contracted or
issued options for—on a fixed-price incentive basis—are the same basic designs already
being built. Yet no true operational experience has been gained with the first ships, and the
new ships show only a handful of modifications.
Apart from the Navy’s inability to properly forecast how fast these ships could be built,
fielded and paid for, there is a similar tone-deafness to how they will be employed. The
service has done its best to estimate how the ships will be manned, supported, deployed and
used, but at this point—eight years after the program started—it’s still mostly conjecture.

35 Government Accountability Office, Littoral Combat Ship[:] Actions Needed to Improve Operating Cost Estimates
and Mitigate Risks in Implementing New Concepts
, GAO-10-257, February 2010, summary page.
Congressional Research Service
22

Navy Littoral Combat Ship (LCS) Program

It’s one thing to develop a new class of destroyer or submarine or strike fighter. While new
designs have updated and different features and capabilities, it is conceptually understood
how to support and operate them. But that is not the case with the LCS. Just about everyone
involved with the new type will have to learn how to support, operate and use them…
Although nearly half the planned LCS fleet is now built, under contract or with contract
options, there is no demonstrable example of exactly how this LCS concept is going to work.
Consider:

LCS has no proven concept of operations. Tactical commanders with on-scene and area
responsibilities so far have no experience in deploying these ships and experiencing what
they can do.

Command-and-control questions on the ships themselves remain. Who, for example,
should have weapons release authority—the ship’s commanding officer or the officer in
charge of the mission detachment?

Are the ships best operated in small numbers or in groups? What sorts of groups work
best with each kind of mission? In what roles might they be effective on their own?

What are the best mission sets for the ships? Already, Adm. John Harvey, head of U.S.
Fleet Forces command, is urging the fleet not to use them in ways for which they are not
intended—and that was after only one ship was in service. Do people understand what these
ships are for and what they can do?

The ships have no area air defense capability. Who will protect them and how will that
be coordinated?
• No other surface ship has been designed to operate as many offboard vehicles as the
LCS. How will each ship coordinate its own offboard systems, including unmanned air,
surface and underwater vehicles? Should different ships take responsibility for particular
dimensions—i.e., should one ship control all the underwater vehicles, or should that be left
to each CO or OIC? Should one ship take on all those particular vehicles, or can each ship
deploy its own?

Are these ships well-suited to a “knife fight” with high-speed small craft, as some have
urged, or would a better tactic be to stand off and fight with the 57mm gun and offboard
systems such as armed helicopters or drones?

Is the high speed really necessary? Should more fuel be added at the expense of speed?

The ships are not patrol boats and do not have long endurance, despite proclamations
that they are great for anti-piracy work. Do they need a redesign if that’s the mission?
• Is it better to fit a ship with a single mission module for longer periods, or better to
frequently swap out the modules?
• Can all the necessary personnel be accommodated? The ships are limited to 75 or 76
berths—no room for extra riders, such as special operations forces, or more likely, technical
representatives for the multiplicity of vehicles each ship will eventually carry.

Will the mission modules prove effective? The mine module already has lost several
major components. Will it prove the equal of the fleet’s mine countermeasures ships the LCS
is set to replace? Will the anti-submarine warfare module really prove effective? Already, the
Congressional Research Service
23

Navy Littoral Combat Ship (LCS) Program

Navy has classified the cost of the system, along with component details, so it has gotten
harder to make this assessment. However, reports abound that the system is ineffective.

Will the unique support systems for the ships prove their effectiveness? The tiny crew of
40 needs an exceptionally high level of pier support—will they get it? Will the needs of parts
and maintenance supply be met routinely?

Will future managers accept that both kinds of LCS have entirely separate and unique
combat system suites? With dozens of different systems on each design, sailors qualified to
serve on one LCS or the other are no more qualified to serve on the other LCS class than an
amphibious sailor. Will that stand? At some point down the road, will some future CNO or
Navy secretary decide that the fleet can’t afford both types of combat systems and order the
premature disposal of all of one of the types long before the end of their service life? Those
are just some of the issues facing the development of the LCS.
Perhaps the only sure thing is that the Navy has tried its best to come up with possible
answers to these questions. The thing to do now is not to promise that solutions are at hand
but to put the LCS in the hands of young sailors and let them go out, get hands-on experience
with the ships in multiple scenarios, find out how they’ll work best, and adapt.
The 1930s were exciting times for sailors and aviators living through the great age of naval
aviation experimentation and making believers out of doubters. The 2010s and 2020s could
prove just as rewarding for today’s LCS sailors, headed on courses both known and
unknown.36
A report by the Center for Strategic and Budgetary Assessments (CSBA) provides additional
discussion of possible operational concepts for the LCS.37
Legislative Activity for FY2012
FY2012 Funding Request
Under Navy budget plans, the four LCSs that the Navy wants to procure in FY2012 are to receive
$79.5 million in prior-year advance procurement (AP) funding. Navy’s proposed FY2012 budget
requests $1,802.1 million in FY2012 procurement funding to complete the four ships’ combined
estimated procurement cost of $1,881.6 million. The Navy’s proposed FY2012 budget also
requests $79.6 million procurement funding for procurement of LCS mission packages, and
$286.8 million in research and development funding for the LCS program.


36 Christopher P. Cavas, “Past Imperfect[:] Like First Carriers, Littoral Combat Ship Enters Age of Experimentation,”
Armed Forces Journal, April 2011 (accessed at http://www.armedforcesjournal.com/2011/04/5848053).
37 Martin M. Murphy, Littoral Combat Ship[:] An Examination of its Possible Concepts of Operation, Washington,
Center for Strategic and Budgetary Assessments, 2010, 71 pp.
Congressional Research Service
24

Navy Littoral Combat Ship (LCS) Program

Appendix A. Legislative Activity for FY2011
Legislation to Provide Authority for Dual-Award Strategy
Continuing Appropriations and Surface Transportation Extensions Act, 2011
(H.R. 3082/P.L. 111-322)38

On December 21, 2010, the Senate and House passed H.R. 3082, a bill that, among other things,
funds federal government operations through March 4, 2011. Section 150 of the bill provides the
Navy authority to implement a dual-award strategy. H.R. 3082 was signed into law as P.L. 111-
322 of December 22, 2010. The text of Section 150 is as follows:
SEC. 150. Subject to the availability of appropriations, the Secretary of the Navy may award
a contract or contracts for up to 20 Littoral Combat Ships (LCS). 39
A Bill to Amend the FY2010 Defense Authorization Act (H.R. 6494)
H.R. 6494 would provide legislative authority for the Navy to implement a dual-award
acquisition strategy for the LCS program. The bill was passed by the House on December 15,
2010. The text of H.R. 6494 is as follows:
SECTION 1. LITTORAL COMBAT SHIP PROGRAM.
(a) Contract Authority- Subsection (a) of section 121 of the National Defense Authorization
Act for Fiscal Year 2010 (P.L. 111-84; 123 Stat. 2211) is amended—
(1) in paragraph (1)—
(A) by striking `ten Littoral Combat Ships and 15 Littoral Combat Ship ship control and
weapon systems’ and inserting `20 Littoral Combat Ships, including any ship control and
weapon systems the Secretary determines necessary for such ships,’; and
(B) by striking `a contract’ and inserting `one or more contracts’; and

38 H.R. 3082 was originally the FY2010 military construction, the Department of Veterans Affairs, and related agencies
appropriations bill.
39 H.R. 3082 became a continuing resolution that funds federal government operations through March 4, 2011 through
the adoption in the Senate of S.Amdt. 4885, which was proposed on December 19, 2010.
An earlier version of H.R. 3082 in the House was a full-year continuing appropriations bill for FY2011. Section 2314
of this version of H.R. 3082 would provide legislative authority for the Navy to implement a dual-award acquisition
strategy for the LCS program. The text of Section 2314 was as follows:
SEC. 2314. The Secretary of the Navy may award a contract or contracts for up to 20 Littoral
Combat Ships subject to the availability of appropriated funds for such purpose.
An earlier version of H.R. 3082 in the Senate was a consolidated appropriations bill for FY2011. Section 8123 of this
version of H.R. 3082 would provide legislative authority for the Navy to implement a dual-award acquisition strategy
for the LCS program. The text of Section 8123 was as follows:
SEC. 8123. Subject to the availability of appropriations, the Secretary of the Navy may award a
contract or contracts for up to 20 Littoral Combat Ships (LCS).
Congressional Research Service
25

Navy Littoral Combat Ship (LCS) Program

(2) in paragraph (2), by striking `liability to’ and inserting `liability of’.
(b) Technical Data Package- Subsection (b)(2)(A) of such section is amended by striking `a
second shipyard, as soon as practicable’ and inserting `another shipyard to build a design
specification for that Littoral Combat Ship’.
(c) Limitation of Costs- Subsection (c)(1) of such section is amended by striking `awarded to
a contractor selected as part of a procurement’ and inserting `under a contract’.
Senate Amendment 4741 (S.Amdt. 4741) to FY2011 Defense Authorization Bill
(S. 3454)

Senate Amendment (S.Amdt. 4741) to the FY2011 Defense Authorization Bill (S. 3454),
submitted on December 8, 2010, would, among other things, provide legislative authority to the
Navy to implement a dual-award acquisition strategy for the LCS program. The text of the first
part of S.Amdt. 4741—the part relating to the LCS program—is as follows:
At the end of subtitle C of title I [of S. 3454], add the following:
SEC. 126. ADDITIONAL COMBAT SHIP MATTERS.
(a) Modifications to Littoral Combat Ship Program Authority.—Section 121 of the National
Defense Authorization Act for Fiscal Year 2010 (P.L. 111-84; 123 Stat. 2211) is amended—
(1) in subsection (a)—
(A) in paragraph (1)—
(i) by striking ``ten Littoral Combat Ships and 15 Littoral Combat Ship ship control and
weapon systems” and inserting ``20 Littoral Combat Ships (LCS), including ship control and
weapon systems,”; and
(ii) by striking ``a contract” and inserting ``one or more contracts”; and
(B) in paragraph (2)—
(i) by striking ``A contract” and inserting ``Any contract”; and
(ii) by striking ``liability to” and inserting ``liability of”;
(2) in subsection (b)—
(A) in paragraph (1), by striking ``a procurement” and inserting ``any contract”; and
(B) in paragraph (2)—
(i) by striking ``a Littoral” and inserting ``any Littoral”; and
(ii) in subparagraph (A), by striking ``a second shipyard, as soon as practicable” and
inserting ``another shipyard to build to a design specification for that Littoral Combat Ship”;
and
Congressional Research Service
26

Navy Littoral Combat Ship (LCS) Program

(3) in subsection (c)(1), by striking ``awarded to a contractor selected as part of a
procurement” and inserting ``under any contract”….
Legislation Relating to FY2011 Funding and Other Aspects of
Program

FY2011 Funding Request
The Navy’s proposed FY2011 budget requested $1,231.0 million in procurement funding for the
two LCSs that the Navy wants to procure in FY2011, and $278.4 million in FY2011 advance
procurement funding for 11 LCSs that the Navy wanted, under the FY2011 budget submission, to
procure in FY2012-FY2014. (The Navy now wants, under the dual-award strategy, to procure 12
LCSs in FY2012-FY2014.) The Navy’s proposed FY2011 budget also requested $9.8 million in
procurement funding to procure LCS module weapons, $83.0 million in procurement funding for
procurement of LCS mission packages, and $226.3 million in research and development funding
for the LCS program.
Summary of Congressional Action on FY2011 Funding Request
Table A-1 summarizes congressional action on the Navy’s FY2011 funding request for the LCS
program.
Table A-1. Congressional Action on FY2011 Funding Request
Millions of dollars, rounded to nearest tenth
Authorization Appropriation
Request
HASC SASC Conf. HACa SAC FInal
Shipbuilding and Conversion, Navy (SCN) account, lines 12 and 13
LCS sea frames
1,231.0
1,231.0
1,231.0
1,231.0
n/aa 615.5 1,169.0
(quantity)
(2)
(2)
(2)
(2)
n/aa (1) (2)
LCS sea frames (AP)
278.4
278.4
278.4
278.4
n/aa 278.4 190.4
Weapon Procurement, Navy (WPN account), line 30
LCS module weapons
9.8
0.9
9.8
not clear
n/aa 0 0
Other Procurement, Navy (OPN) account, line 29
LCS modules
83.0
83.0
83.0
not clear
n/aa 50.0 41.4
Research, Development, Test & Evaluation, Navy (RDT&EN) account, line 48
LCS 226.3
305.5
226.3
not
clear
n/aa 199.4 189.6
Sources: Table prepared by CRS based on Navy’s FY2011 budget submission, committee reports, the text of S.
3454, the FY2011 defense authorization bill, as reported in the Senate, the joint explanatory statement of the
House and Senate Armed Services Committees on H.R. 6523 (for authorization conference), and funding tables
posted by the House Rules Committee for H.R. 1473 of the 112th Congress (for appropriation final). The joint
explanatory statement for S. 3454 includes tables with recommended funding levels for ful appropriation
accounts, but not for line items within those accounts. The statement showed no recommended change to the
requested total amount for the SCN account, but recommended changes to the requested total amounts for the
WPN, OPN, and RDT&EN accounts.
Notes: HASC is House Armed Services Committee; SASC is Senate Armed Services Committee; HAC is
House Appropriations Committee; SAC is Senate Appropriations Committee; Conf. is conference report; Final
is final version of the appropriations bill (H.R. 1473 of the 112th Congress); AP is advance procurement for ships
to be procured in future years.
a. The full House Appropriations Committee did not file an official, numbered committee report for the
FY2011 DOD appropriations act.
Congressional Research Service
27

Navy Littoral Combat Ship (LCS) Program

FY2011 DOD and Full-Year Continuing Appropriations Act (H.R. 1473)
According to line-item funding tables posted by the House Rules Committee,40 the FY2011
Department of Defense and Full-Year Continuing Appropriations Act (H.R. 1473 of the 112th
Congress, introduced on April 11, 2011):
• reduces the Navy’s FY2011 procurement funding request in the SCN account for
LCS sea frames by $62.0 million, with the reduction being for “Cost Savings”;
• reduces the Navy’s FY2011 advance procurement (AP) funding request in the
SCN account for LCS sea frames by $88.0 million, with the reduction being for
“Program Reduction”;
• rejects the Navy’s FY2011 procurement funding request in the WPN account for
LCS module weapons, with the reduction to zero being for “NLOS Program
Termination”;
• reduces the Navy’s FY2011 procurement funding request in the OPN account for
LCS modules by $41.582 million, including $6.0 million for “MCM Module
Production Support Growth,” $3.064 million for “Consulting Services Growth,”
$7.6 million for “Excess Remote Multi-Mission Vehicle Funding,” $2.268
million for “Mission Package Computer Environment Units Ahead of Need,” and
$22.65 million for “AN/AQS-20A – Ahead of Need”; and
• reduces the Navy’s FY2011 research and development funding request in the
RDT&EN account for the LCS program by a net total of $36.7 million, including
• reductions of $15.8 million for “LCS-2 post shakedown availability delay,”
$0.5 million for “LCS-1 post shakedown availability planning funding
excess,” $15.4 million for “NLOS missile termination,” $2.0 million for
“Navy requested transfer to [RDT&EN account] line 49 [“Combat System
Integration”] for Automatic Test and Re-Test,” and $15 million for “Savings
from accelerated DT,” and
• increases of $4.0 million for “Program Increase – Mine Warfare Testing
Disruption” and $8.0 million for “Program Increase – Small Business
Technology Insertion (Mine Warfare Modules).
FY2011 DOD Appropriations Bill (S. 3800)
Senate
The Senate Appropriations Committee, in its report (S.Rept. 111-295 of September 16, 2010) on
S. 3800 of the 111th Congress, recommends $615.5 million in procurement funding for the
procurement in FY2011 of one LCS sea frame—a reduction of $615.5 million and one LCS sea
frame from the Navy’s request (page 86, line 12). The committee’s report states:

40 The funding tables were posted at http://rules.house.gov/Legislation/legislationDetails.aspx?NewsID=244.

Congressional Research Service
28

Navy Littoral Combat Ship (LCS) Program

Littoral Combat Ship [LCS].—The fiscal year 2011 budget request included $1,230,984,000
for the construction of two LCS ships and $278,351,000 in advance procurement funding for
future ships. The Committee supports the revised acquisition strategy for the LCS program
and the decision to down-select to one variant in fiscal year 2010. The Committee, however,
is concerned with the very aggressive construction schedule proposed in the budget request.
Based on the historical poor cost and schedule performance of the program, including the
current delay in the down-select decision, the Committee is concerned that the proposed
ramp up to construct four ships in fiscal year 2011 is too aggressive and may be
unexecutable. Therefore, the Committee recommends re-phasing the LCS construction
schedule by reducing the budget request by $615,492,000 and one ship in fiscal year 2011.
The Committee directs the Navy to add one LCS back into the program during the Future
Years Defense Plan. (Page 87)
The committee’s report also states:
The Secretary of Defense should be applauded for trying to gain greater control over
runaway costs, schedule delays, and requirements creep. However, the Committee remains
frustrated by the lack of proper control in the Defense budget process as exemplified by the
examples listed below. The Navy should be commended for reshaping its Littoral Combat
Ship program to down select to one contractor with the goal of reducing costs. However, the
ensuing delay in this program has led to a schedule in which the winning contractor will not
be able to begin constructing the second of two LCS ships requested in fiscal year 2011.
Nonetheless, neither the Navy nor the Defense Department has suggested reducing the
budget request even though more than $600,000,000 will not be required this fiscal year.
(Page 7)
The committee’s report recommends approving the Navy’s request for $278.4 million in advance
procurement funding for LCSs to be procured in future years (page 86, line 13).
The committee’s report recommends denying the Navy’s request for $9.8 million in procurement
funding for the procurement of LCS weapon modules due to the termination of the NLOS-LS
program (page 82, line 30).
The committee’s report recommends reducing by $32.9 million the Navy’s request for
procurement funding for the procurement of LCS modules due to unjustified growth in
production engineering ($6 million reduction), mission package computer environment units
requested ahead of need ($2.3 million reduction), unjustified growth in consulting services ($2
million reduction), and AN/AQS-20A minehunting sonar equipment requested ahead of need
($22.7 million reduction) (page 95, line 29).
The committee’s report recommends reducing the Navy’s request for research and development
funding for the LCS program by a net total of $26.9 million, including a reduction of $15.4
million due to the termination of the NLOS-LS program, a reduction of $15.0 million due to
savings from “accelerated DT” (which might be a reference to accelerated developmental
testing), and an increase of $3.5 million for LCS axial flow high power density waterjets (page
150, line 48).
Congressional Research Service
29

Navy Littoral Combat Ship (LCS) Program

FY2011 Defense Authorization Act (H.R. 6523/P.L. 111-383)
House (H.R. 5136)
The House Armed Services Committee, in its report (H.Rept. 111-491 of May 21, 2010) on the
FY2011 defense authorization bill (H.R. 5136), recommends approval of the Navy’s FY2011
procurement and advance procurement funding requests for LCS sea frames (page 73) and LCS
modules (page 81, line 029). The report recommends reducing by $8.9 million the Navy’s
FY2011 procurement funding request for LCS module weapons due to termination of the NLOS-
LS program (page 68, line 030). The report recommends increasing the Navy’s FY2011 request
for LCS research and development funding by $75.0 million for Navy NLOS-NS development,
and by $4.25 million for axial-flow high-power-density waterjets (page 148).
The report states:
Littoral Combat Ship
The Littoral Combat Ship program has failed its initial intent to build inexpensive ships with
modular capability and field them to the fleet at a high rate. None of those goals have been
met. The ships are expensive; the modular capability has not been tested or verified; and in
some cases is still undergoing development; and only two of the ships have been delivered to
the Navy.
Last year, the committee supported the request of the Secretary of the Navy and the Chief of
Naval Operations to revamp the acquisition strategy for these vessels and to down-select to
one variant of the ship with the award of the fiscal year 2010 two-ship authorization. The
new acquisition strategy is aimed at reducing overall costs by procuring 10 ships in the
Future Years Defense Plan using a fixed price incentive contract in fiscal year 2010 with
priced options for 8 additional ships, 2 per year, in fiscal years 2011–15. In addition, the
government would gain all rights to the technical data package required to compete the
winning design to a second source shipyard which would build 5 additional ships, for a total
of 15 ships, between fiscal years 2012 and 2015. The committee supported this plan as the
best alternative to provide needed capability to the fleet in the shortest time possible, at the
least cost. The plan was also proposed to the committee as the best way to divorce the prime
contractors from the program and to transition the ship’s installed combat systems to
government furnished equipment that complimented equipment currently in use in the fleet.
As of this report, the Navy has received the proposals from the two authorized competitors
and is in the process of source selection leading to contract award. The committee is
cautiously optimistic that, with a down-select to one variant and stability in the construction
schedule, this troubled program can begin to fulfill its original purpose of providing capable
ships, in quantity, at an affordable cost. (Pages 76-77)
The report also states:
Littoral Combat Ship Module weapons
The budget request contained $9.8 million for Littoral Combat Ship (LCS) Module
Weapons, of which $8.9 million was requested for procurement of 45 non-line-of-sight
launch system (NLOS–LS) missiles.
The committee notes that the Army has terminated the NLOS-LS program, and even if it is
continued by the Navy, an additional year of development work will be required. As a result,
Congressional Research Service
30

Navy Littoral Combat Ship (LCS) Program

the committee does not agree with Navy procurement funding for NLOS–LS in fiscal year
2011. In title II of this report, the committee recommends an increase in Navy research and
development funding to support continued development work for the NLOS–LS program if
the Navy determines that is in the best interest of the LCS program.
The committee recommends $0.9 million, a decrease of $8.9 million, for LCS Module
weapons. (Page 69)
The report also states:
Navy non-line-of-sight launch system development
The budget request contained $226.3 million in PE 63581N41 for Littoral Combat Ship
mission module research and development but contained no funds for the non-line-of-sight
launch system (NLOS–LS).
The committee notes that the Army’s termination of the NLOS–LS could leave the Navy’s
Littoral Combat Ship (LCS) without sufficient capability to defeat small boat threats and
unable to provide precision fire support to Marine Corps forces. The committee is informed
that the NLOS–LS will likely require only one more year of research and development work
to achieve threshold requirements. Therefore, in order to take advantage of the $1.5 billion in
development funds spent to date, the committee encourages the Navy to complete
development of the NLOS–LS system for use on the LCS. The committee also directs the
Assistant Secretary of the Navy for Research, Development, and Acquisition to provide a
report to the congressional defense committees by December 15, 2010, on the feasibility and
utility of the Navy completing development of the NLOS–LS. The report should include an
analysis of possible unit cost reduction options.
The committee recommends $301.3 million, an increase of $75.0 million, in PE 63581N for
research and development of the NLOS–LS for use on the LCS. (Pages 159-160)
Senate (S. 3454)
The FY2011 defense authorization bill (S. 3454), as reported by the Senate Armed Services
Committee (S.Rept. 111-201 of June 4, 2010), recommends approval of the Navy’s requests for
FY2011 procurement and advance procurement funding for LCS sea frames (see page 677, lines
12 and 13, of the printed bill), LCS module weapons (page 675, line 30), LCS modules (page
680, line 29), and LCS research and development (page 732, line 48). The committee’s report
states:
The Littoral Combat Ship (LCS) program has made progress during the past year and the
recent decision to move to a single design should improve affordability. The LCS fleet is
expected to comprise 55 vessels of the Navy’s 313–ship fleet force structure. Even modest
cost growth in this large component of the fleet magnifies the problem of achieving that
objective. The committee notes that the Navy’s acquisition strategy for the LCS program
introduces competition for this class of ships and is therefore cautiously optimistic that this
program is making progress. (Page 41)
The committee’s report also states:

41 Line items in DOD research and development accounts are called program elements (PEs).
Congressional Research Service
31

Navy Littoral Combat Ship (LCS) Program

Littoral combat ship report
The committee has concluded that the projected ship decommissioning and construction
schedule presented in the Navy’s program described in its “Report to Congress on Annual
Long-Range Plan for Construction of Naval Vessels for FY 2011” could have a negative
effect on some of the Nation’s Navy bases. This would arise because of a gap that will occur
as a result of small surface combatants being retired years before Littoral Combat Ship
replacements will arrive.
The Navy’s 2010 document ‘‘Report on Strategic Plan for Homeporting the Littoral Combat
Ship’’ provided the committee with the Navy’s notional strategic plan for stationing the
Littoral Combat Ship through fiscal year 2020. In order to fully understand the effects of the
Navy’s current decommissioning and shipbuilding timeline, the committee directs the
Secretary of the Navy to submit a report to the congressional defense committees that would
provide the timeline and detailed homeport locations for the Littoral Combat Ships that will
be delivered through 2020. The committee directs the Secretary of the Navy to submit the
reports at the time the President submits his fiscal year 2012 budget proposal to Congress.
As the Navy finalizes its plans, the committee encourages the Navy to expedite delivery of
the Littoral Combat Ship to those Navy bases that need replacement ships to mitigate
capability gaps that will result from the retirement of smaller surface combatants. (Page 116)
Final Version (H.R. 6523/P.L. 111-383)
H.R. 6523/P.L. 111-383 of January 7, 2011, does not appear to include any provisions relating
specifically to the LCS program. The joint explanatory statement of the House and Senate Armed
Services Committees on H.R. 6523 does not discuss the program.
Congressional Research Service
32

Navy Littoral Combat Ship (LCS) Program

Appendix B. Summary of Congressional Action in
FY2005-FY2010

This appendix presents a summary of congressional action on the LCS program in FY2005-
FY2010.
FY2005
In FY2005, Congress approved the Navy’s plan to fund the construction of the first two LCS sea
frames using research and development funds rather than shipbuilding funds, funded the first
construction cost of the first LCS (LCS-1), required the second LCS (LCS-2) to be built (when
funded in FY2006) to a different design from the first, prohibited the Navy from requesting funds
in FY2006 to build a third LCS, and required all LCSs built after the lead ships of each design to
be funded in the SCN account rather than the Navy’s research and development account.
FY2006
In FY2006, Congress funded the procurement of LCSs 2, 3, and 4. (The Navy requested one LCS
for FY2006, consistent with Congress’s FY2005 action. Congress funded that ship and provided
funding for two additional ships.) Congress in FY2006 also established a unit procurement cost
limit on the fifth and sixth LCS sea frames of $220 million per ship, plus adjustments for inflation
and other factors (Section 124 of the FY2006 defense authorization bill [H.R. 1815/P.L. 109-163]
of January 6, 2006), required an annual report on LCS mission packages and made procurement
of more than four LCSs contingent on the Navy certifying that there exists a stable design for the
LCS.
FY2007
In FY2007, Congress funded the procurement of LCSs 5 and 6. (The Navy canceled these two
ships in 2007 before they were placed under contract for construction.)
FY2008
In FY2008, Congress accepted the Navy’s cancellation of LCSs 3 through 6; funded the
procurement one additional LCS in FY2008 (which the Navy called LCS-5);42 significantly
reduced the Navy’s FY2008 funding request for the LCS program; amended the LCS sea frame
unit procurement cost cap to $460 million per ship for LCSs procured in FY2008 and subsequent
years (Section 125 of the conference report [H.Rept. 110-477 of December 6, 2007] on H.R.
1585, the FY2008 defense authorization bill, which was enacted as H.R. 4986/P.L. 110-181 of

42 The Navy apparently called this ship LCS-5 because the original LCS-5 and LCS-6 were canceled by the Navy
before they were replaced under contract, leaving LCS-4 as last LCS under contract to have been canceled. In spite of
its designation, LCS-5 would have been the third LCS in the restructured LCS program, and was the seventh to have
been funded by Congress.
Congressional Research Service
33

Navy Littoral Combat Ship (LCS) Program

January 28, 2008); and required the Navy to use fixed-price-type contracts for the construction of
LCSs procured in FY2008 and subsequent years.
The Navy in 2007 requested that Congress amend the existing unit procurement cost cap for the
fifth and sixth ships to $460 million, plus adjustments for inflation and other factors. Congress
amended the cost cap to $460 million, but applied it not only to the fifth and sixth LCSs, but to all
LCSs procured in FY2008 and subsequent years. The use of fixed-price contracts for future LCSs
was something that the Navy had stated an intention to do as part of its plan for restructuring the
LCS program.
FY2009
In FY2009, Congress delayed the implementation of the LCS sea frame unit procurement cost
cap by two years, to ships procured in FY2010 and subsequent years (Section 122 of the FY2009
defense authorization act [S. 3001/P.L. 110-417 of October 14, 2008]); rescinded $337 million in
FY2008 shipbuilding funds for the LCS program, effectively canceling the funding for the LCS
procured in FY2008 (Section 8042 of the FY2009 defense appropriations act [Division C of H.R.
2638/P.L. 110-329 of September 30, 2008]); and funded the procurement of two LCSs at a cost of
$1,020 million.
FY2010
In FY2010 Congress funded the procurement of two LCSs at a cost of $1,080 million and
rescinded $66 million in FY2009 Other Procurement, Navy (OPN) funding for LCS mission
modules. Section 121 of the FY2010 defense authorization act (H.R. 2647/P.L. 111-84 of October
28, 2009) granted the Navy contracting and other authority to implement the LCS acquisition
strategy that the Navy announced on September 16, 2009, and amended the LCS unit
procurement cost cap. Section 122 of the act requires the LCS program to be treated as a major
defense acquisition program (MDAP) for purposes of program management and oversight.
Section 123 of the act required a report on the Navy’s plan for homeporting LCSs.

Congressional Research Service
34

Navy Littoral Combat Ship (LCS) Program

Appendix C. Cost Growth on LCS Sea Frames in
FY2007-FY2012 Budgets

This appendix presents details on cost growth on the first few LCS sea frames in the FY2007-
FY2012 budget submissions.
FY2007 Budget
The proposed FY2007 Navy budget, submitted in February 2006, showed that:
• the estimate for the first LCS had increased from $215.5 million in the FY2005
budget and $212.5 million in the FY2006 budget to $274.5 million in the
FY2007 budget—an increase of about 27% from the FY2005 figure and about
29% form the FY2006 figure;
• the estimate for the second LCS increased from $213.7 million in the FY2005
budget and $256.5 million in the FY2006 budget to $278.1 million—an increase
of about 30% from the FY2005 figure and about 8% from the FY2006 figure;
and
• the estimate for follow-on ships scheduled for FY2009-FY2011, when the LCS
program was to have reached a planned maximum annual procurement rate of six
ships per year, had increased from $223.3 million in the FY2006 budget to $298
million—an increase of about 33%.
The Navy stated in early 2006 that the cost increase from the FY2006 budget to the FY2007
budget was due mostly to the fact that LCS procurement costs in the FY2006 budget did not
include items that are traditionally included in the so-called end cost—the total budgeted
procurement cost—of a Navy shipbuilding program, such as Navy program-management costs,
an allowance for changes, and escalation (inflation). The absence of these costs from the FY2006
LCS budget submission raised certain potential oversight issues for Congress.43

43 These oversight issues included the following:
—Why were these costs excluded? Was this a budget-preparation oversight? If so, how could such an oversight occur,
given the many people involved in Navy budget preparation and review, and why did it occur on the LCS program but
not other programs? Was anyone held accountable for this oversight, and if so, how? If this was not an oversight, then
what was the reason?
—Did the Navy believe there was no substantial risk of penalty for submitting to Congress a budget presentation for a
shipbuilding program that, for whatever reason, significantly underestimated procurement costs?
—Do LCS procurement costs in the budget now include all costs that, under traditional budgeting practices, should be
included? If not, what other costs are still unacknowledged?
—Have personnel or other resources from other Navy programs been used for the LCS program in any way? If so, have
the costs of these personnel or other resources been fully charged to the LCS program and fully reflected in LCS
program costs shown in the budget?
Congressional Research Service
35

Navy Littoral Combat Ship (LCS) Program

FY2008 Budget
On January 11, 2007, the Navy reported that LCS-1 was experiencing “considerable cost
overruns.” The Navy subsequently stated that the estimated shipyard construction cost of LCS-1
had grown to $350 million to $375 million. This suggested that the end cost of LCS-1—which
also includes costs for things such as Navy program-management costs and an allowance for
changes—could be in excess of $400 million. The Navy did not publicly provide a precise cost
overrun figure for LCS 2, but it stated that the cost overrun on LCSs 1 and 2 was somewhere
between 50% and 75%, depending on the baseline that is used to measure the overrun.
GAO testified in July 2007 that according to its own analysis of Navy data, the combined cost of
LCSs 1 and 2 had increased from $472 million to $1,075 million—an increase of 128%.44 CBO
testified in July 2007 that:
Several months ago, press reports indicated that the cost could well exceed $400 million
each for the first two LCS sea frames. Recently, the Navy requested that the cost cap for the
fifth and sixth sea frames be raised to $460 million, which suggests that the Navy’s estimate
of the acquisition cost for the first two LCSs would be around $600 million apiece....
As of this writing, the Navy has not publicly released an estimate for the LCS program that
incorporates the most recent cost growth, other than its request to raise the cost caps for the
fifth and sixth ships. CBO estimates that with that growth included, the first two LCSs would
cost about $630 million each, excluding mission modules but including outfitting,
postdelivery, and various nonrecurring costs associated with the first ships of the class. As
the program advances, with a settled design and higher annual rates of production, the
average cost per ship is likely to decline. Excluding mission modules, the 55 LCSs in the
Navy’s plan would cost an average of $450 million each, CBO estimates.45
FY2009 Budget
The proposed FY2009 budget, submitted in February 2008, showed that the estimated end costs
of LCS-1 and LCS-2 had increased to $531 million and $507 million, respectively (or to $631
million and $636 million, respectively, when OF/DP and FST MSSIT costs are included, or to
$606 million and $582 million, respectively, when OF/DP costs are included, but FST MSSIT
costs are not included).
FY2010 Budget
The proposed FY2010 budget, submitted in May 2009, showed that the estimated end costs of
LCS-1 and LCS-2 had increased to $537 million and $575 million, respectively (or to $637
million and $704 million, respectively, when OF/DP and FST MSSIT costs are included, or to

44 Defense Acquisitions[:] Realistic Business Cases Needed to Execute Navy Shipbuilding Programs, Statement of Paul
L. Francis, Director, Acquisition and Sourcing Management Team, Testimony Before the Subcommittee on Seapower
and Expeditionary Forces, Committee on Armed Services, House of Representatives, July 24, 2007 (GAO-07-943T),
pp. 4 and 22.
45 Statement of J. Michael Gilmore, Assistant Director for National Security, and Eric J. Labs, Senior Analyst, [on] The
Navy’s 2008 Shipbuilding Plan and Key Ship Programs, before the Subcommittee on Seapower and Expeditionary
Forces Committee on Armed Services U.S. House of Representatives, July 24, 2007, p. 18.
Congressional Research Service
36

Navy Littoral Combat Ship (LCS) Program

$612 million and $650 million, respectively, when OF/DP costs are included, but FST MSSIT
costs are not included). CBO reported on June 9, 2008, that:
Historical experience indicates that cost growth in the LCS program is likely. In particular,
using the lead ship of the FFG-7 Oliver Hazard Perry class frigate as an analogy, historical
cost-to-weight relationships indicate that the Navy’s original cost target for the LCS of $260
million in 2009 dollars (or $220 million in 2005 dollars) was optimistic. The first FFG-7 cost
about $670 million in 2009 dollars to build, or about $250 million per thousand tons,
including combat systems. Applying that metric to the LCS program suggests that the lead
ships would cost about $600 million apiece, including the cost of one mission module. Thus,
in this case, the use of a historical cost-to-weight relationship produces an estimate that is
less than the actual costs of the first LCSs to date but substantially more than the Navy’s
original estimate.
Based on actual costs the Navy has incurred for the LCS program, CBO estimates that the
first two LCSs could cost about $700 million each, including outfitting and postdelivery and
various nonrecurring costs associated with first ships of a class but excluding mission
modules. However, as of May 1, 2008, LCS-1 was 83 percent complete and LCS-2 was 68
percent complete. Thus, additional cost growth is possible, and CBO’s estimate reflects that
cost risk.
Overall, CBO estimates that the LCSs in the Navy’s plan would cost about $550 million
each, on average, excluding mission modules. That estimate assumes that the Navy would
select one of the two existing designs and make no changes. As the program advanced with a
settled design and higher annual rates of production, average ship costs would probably
decline. If the Navy decided to make changes to that design, however, the costs of building
future ships could be higher than CBO now estimates.46
FY2011 Budget
The proposed FY2011 budget, submitted in February 2010, showed that the estimated end cost of
LCS-1 remained unchanged from the previous year at $537 million, and that the estimated end
cost of LCS-2 had increased to $607 million. These two figures become $656 million and $736
million, respectively, when OF/DP and FST MSSIT costs are included, or $631 million and $682
million, respectively, when OF/DP costs are included, but FST MSSIT costs are not included. The
Navy’s FY2011 budget submission states that OF/DP and FST MSSIT costs are non-end cost
items, and that FSD MSSIT costs for LCS-1 and LCS-2 “are not true construction costs and are
[instead] costs associated with design completion.”47
FY2012 Budget
The proposed FY2012 budget, submitted in February 2011, showed that the estimated end cost of
LCS-1 remained unchanged from the previous year at $537 million, and that the estimated end
cost of LCS-2 had increased to $653 million. These two figures become $670.4 million and

46 Congressional Budget Office, Resource Implications of the Navy’s Fiscal Year 2009 Shipbuilding Plan, June 8,
2008, pp. 26-27.
47 Source: Department of Navy, Department of the Navy Fiscal Year (FY) 2011 Budget Estimates, February 2010,
Justification of Estimates, Research, Development, Test & Evaluation, Navy, Budget Activity 4
, Exhibit R-2A, RDT&E
Project Justification, PE 0603581N: Littoral Combat Ship (LCS), pages 34-35 of 46 (pdf pages 552-553 of 1054).
Congressional Research Service
37

Navy Littoral Combat Ship (LCS) Program

$808.8 million, respectively, when OF/DP and FST MSSIT costs are included, or $645.4 million
and $754.8 million, respectively, when OF/DP costs are included, but FST MSSIT costs are not
included. The Navy’s FY2011 budget submission states that OF/DP and FST MSSIT costs are
non-end cost items, and that FSD MSSIT costs for LCS-1 and LCS-2 “are not true construction
costs and are [instead] costs associated with design completion.”48
Reasons for Cost Growth
Various reasons have been cited for cost growth in the LCS program, including the following:
Unrealistically low original estimate. Some observers believe that the original
cost estimate of $220 million for the LCS sea frame was unrealistically low. If so,
a potential follow-on question would be whether the LCS represents a case of
“low-balling”—using an unrealistically low cost estimate in the early stages of a
proposed weapon program to help the program win approval and become an
established procurement effort.
Impact of Naval Vessel Rules (NVR). Navy and industry officials have
attributed some of the cost growth to the impact of applying new Naval Vessel
Rules (NVR)—essentially, new rules specifying the construction standards for
the ship—to the LCS program. The NVR issued for the LCS program
incorporated, among other things, an increase in the survivability standard (the
ability to withstand damage) to which LCSs were to be built. Building the ship to
a higher survivability standard represented a change in requirements for the ship
that led to many design changes, including changes that made ship more rugged
and more complex in terms of its damage-control systems. In addition, Navy and
industry officials have testified, the timing of the issuing of NVR created a
situation of concurrency between design and construction in the LCS program,
meaning that the ship was being designed at the same time that the shipyard was
attempting to build it—a situation long known to be a potential cause of cost
growth. This concurrency, Navy officials testified, was a consequence of the
compressed construction schedule for the LCS program, which in turn reflected
an urgency about getting LCSs into the fleet to meet critical mission demands.
Improperly manufactured reduction gear. Navy and industry officials testified
that cost growth on LCS-1 was partly due to a main reduction gear49 that was
incorrectly manufactured and had to be replaced, forcing a reordering of the
construction sequence for the various major sections of the ship.
Increased costs for materials. Some observers have attributed part of the cost
growth in the program to higher-than-estimated costs for steel and other materials
that are used in building the ships.
Emphasis on meeting schedule combined with cost-plus contract. Some
portion of cost growth on LCS-1 has been attributed to a combination of a Navy

48 Source: Department of Defense, Department of Defense Fiscal Year (FY) 2012 Budget Estimates, February 2011,
Navy Justification Book Volume 2, Research, Development, Test & Evaluation, Navy, Budget Activity 4
, Exhibit R-2A,
RDT&E Project Justification, PE 0603581N: Littoral Combat Ship (LCS), page 33 of 42 (pdf page 469 of 888).
49 A ship’s reduction gear is a large, heavy gear that reduces the high-speed revolutions of the ship’s turbine engines to
the lower-speed revolutions of its propellers.
Congressional Research Service
38

Navy Littoral Combat Ship (LCS) Program

emphasis on meeting the ship’s aggressive construction schedule and the Navy’s
use of a cost-plus contract to build the ship.50
Shipyard Performance. Shipyard performance and supervision of the LCS
shipyards by the LCS team leaders and the Navy has been cited as another cause
of cost growth.51
July 2007 GAO Testimony
GAO testified in July 2007 that:
We have frequently reported on the wisdom of using a solid, executable business case before
committing resources to a new product development effort....
A sound business case would establish and resource a knowledge-based approach at the
outset of a program. We would define such a business case as firm requirements, mature
technologies, and an acquisition strategy that provides sufficient time and money for design
activities before construction start. The business case is the essential first step in any
acquisition program that sets the stage for the remaining stages of a program, namely the
business or contracting arrangements and actual execution or performance. If the business
case is not sound, the contract will not correct the problem and execution will be subpar.
This does not mean that all potential problems can be eliminated and perfection achieved, but
rather that sound business cases can get the Navy better shipbuilding outcomes and better
return on investment. If any one element of the business case is weak, problems can be
expected in construction. The need to meet schedule is one of the main reasons why
programs cannot execute their business cases. This pattern was clearly evident in both the
LPD 17 [amphibious ship] and LCS programs. In both cases, the program pushed ahead with
production even when design problems arose or key equipment was not available when
needed. Short cuts, such as doing technology development concurrently with design and
construction, are taken to meet schedule. In the end, problems occur that cannot be resolved
within compressed, optimistic schedules. Ultimately, when a schedule is set that cannot
accommodate program scope, delivering an initial capability is delayed and higher costs are
incurred....
What happens when the elements of a solid business case are not present? Unfortunately, the
results have been all too visible in the LPD 17 and the LCS. Ship construction in these
programs has been hampered throughout by design instability and program management

50 The Senate Armed Services Committee, as part of its discussion of the LCS program in its report (S.Rept. 110-77 of
June 5, 2007) on the FY2008 defense authorization bill (S. 1547), stated:
Reviewing this LCS situation will undoubtedly result in a new set of “lessons learned”‘ that the
acquisition community will dutifully try to implement. However, the committee has previously
expressed concerns about the LCS concept and the LCS acquisition strategy. The LCS situation
may be more a case of “lessons lost.” Long ago, we knew that we should not rush to sign a
construction contract before we have solidified requirements. We also knew that the contractors
will respond to incentives, and that if the incentives are focused on maintaining schedules and not
on controlling cost, cost growth on a cost-plus contract should surprise no one. After the fact,
everyone appears ready to agree that the original ship construction schedule for the lead ship was
overly aggressive. (Page 98)
51 See Katherine McIntire Peters, “Navy’s Top Officer Sees Lessons In Shipbuilding Program Failures,”
GovermentExecutive.com, September 24, 2008; Christopher J. Castelli, “Audit Exposes Failed Management of
Troubled Littoral Warship,” Inside the Navy, February 4, 2008; Christopher J. Castelli, “Audit Reveals Both LCS and
Industry Teams Violated Management Rules,” Inside the Pentagon, July 10, 2008 (reprinted in essentially identical
form, with the same headline, in the July 14, 2008, issue of sister publication Inside the Navy).
Congressional Research Service
39

Navy Littoral Combat Ship (LCS) Program

challenges that can be traced back to flawed business cases. The Navy moved forward with
ambitious schedules for constructing LPD 17 and LCS despite significant challenges in
stabilizing the designs for these ships. As a result, construction work has been performed out
of sequence and significant rework has been required, disrupting the optimal construction
sequence and application of lessons learned for follow-on vessels in these programs....
In the LCS program, design instability resulted from a flawed business case as well as
changes to Navy requirements. From the outset, the Navy sought to concurrently design and
construct two lead ships in the LCS program in an effort to rapidly meet pressing needs in
the mine countermeasures, antisubmarine warfare, and surface warfare mission areas. The
Navy believed it could manage this approach, even with little margin for error, because it
considered each LCS to be an adaptation of an existing high-speed ferry design. It has since
been realized that transforming a high-speed ferry into a capable, networked, survivable
warship was quite a complex venture. Implementation of new Naval Vessel Rules (design
guidelines) further complicated the Navy’s concurrent design-build strategy for LCS. These
rules required program officials to redesign major elements of each LCS design to meet
enhanced survivability requirements, even after construction had begun on the first ship.
While these requirements changes improved the robustness of LCS designs, they contributed
to out of sequence work and rework on the lead ships. The Navy failed to fully account for
these changes when establishing its $220 million cost target and 2-year construction cycle
for the lead ships.
Complicating LCS construction was a compressed and aggressive schedule. When design
standards were clarified with the issuance of Naval Vessel Rules and major equipment
deliveries were delayed (e.g., main reduction gears), adjustments to the schedule were not
made. Instead, with the first LCS, the Navy and shipbuilder continued to focus on achieving
the planned schedule, accepting the higher costs associated with out of sequence work and
rework. This approach enabled the Navy to achieve its planned launch date for the first
Littoral Combat Ship, but required it to sacrifice its desired level of outfitting. Program
officials report that schedule pressures also drove low outfitting levels on the second Littoral
Combat Ship design as well, although rework requirements have been less intensive to date.
However, because remaining work on the first two ships will now have to be completed out-
of-sequence, the initial schedule gains most likely will be offset by increased labor hours to
finish these ships.
The difficulties and costs discussed above relate to the LCS seaframe only. This program is
unique in that the ship’s mission equipment is being developed and funded separately from
the seaframe. The Navy faces additional challenges integrating mission packages with the
ships, which could further increase costs and delay delivery of new antisubmarine warfare,
mine countermeasures, and surface warfare capabilities to the fleet. These mission packages
are required to meet a weight requirement of 180 metric tons or less and require 35 personnel
or less to operate them. However, the Navy estimates that the mine countermeasures mission
package may require an additional 13 metric tons of weight and seven more operator
personnel in order to deploy the full level of promised capability. Because neither of the
competing ship designs can accommodate these increases, the Navy may be forced to
reevaluate its planned capabilities for LCS.52

52 Defense Acquisitions[:] Realistic Business Cases Needed to Execute Navy Shipbuilding Programs, Statement of Paul
L. Francis, Director, Acquisition and Sourcing Management Team, Testimony Before the Subcommittee on Seapower
and Expeditionary Forces, Committee on Armed Services, House of Representatives, July 24, 2007 (GAO-07-943T),
pp. 8-11.
Congressional Research Service
40

Navy Littoral Combat Ship (LCS) Program

Appendix D. 2007 Program Restructuring and Ship
Cancellations

The Navy substantially restructured the LCS program in 2007 in response to significant cost
growth and delays in constructing the first LCS sea frames. This restructuring led to the
cancellation of four LCSs that were funded in FY2006 and FY2007. A fifth LCS, funded in
FY2008, was cancelled in 2008. This appendix presents the details of the program restructuring
and ship cancellations.
2007 Program Restructuring
March 2007 Navy Restructuring Plan
In response to significant cost growth and schedule delays in the building of the first LCSs that
first came to light in January 2007 (see next section), the Navy in March 2007 announced a plan
for restructuring the LCS program that:
• canceled the two LCSs funded in FY2007 and redirected the funding for those
two ships to pay for cost overruns on earlier LCSs;
• announced an intention to lift a 90-day stop-work order that the Navy had placed
on LCS-3 in January 2007—provided that the Navy reached an agreement with
the Lockheed-led industry team by April 12, 2007, to restructure the contract for
building LCSs 1 and 3 from a cost-plus type contract into a fixed price incentive
(FPI)-type contract—or terminate construction of LCS-3 if an agreement on a
restructured contract could not be reached with the Lockheed team by April 12,
2007;
• announced an intention to seek to restructure the contract with the General
Dynamics-led industry team for building LCSs 2 and 4 into an FPI-type
contract—if LCSs 2 and 4 experienced cost growth comparable to that of LCSs 1
and 3—and, if such a restructuring were sought, terminate construction of LCS-4
if an agreement on a restructured contract for LCS-2 and LCS-4 could not be
reached;
• reduced the number of LCSs requested for FY2008 from three to two (for the
same requested FY2008 procurement funding of $910.5 million), and the number
to be requested for FY2009 from six to three; and
• announced an intention to conduct an operational evaluation to select a favored
design for the LCS that would be procured in FY2010 and subsequent years, and
to conduct a full and open follow-on competition among bidders for the right to
build that design.53

53 Source: Navy briefing to CRS and Congressional Budget Office (CBO) on Navy’s proposed LCS program
restructuring plan, March 21, 2007.
Congressional Research Service
41

Navy Littoral Combat Ship (LCS) Program

April 2007 Termination of LCS-3
On April 12, 2007, the Navy announced that it had not reached an agreement with Lockheed on a
restructured FPI-type contract for LCS-1 and LCS-3, and consequently was terminating
construction of LCS-3.54 (The Navy subsequently began referring to the ship as having been
partially terminated—a reference to the fact that Lockheed was allowed to continue procuring
certain components for LCS-3, so that a complete set of these components would be on hand to
be incorporated into the next LCS built to the Lockheed design.) (The designation LCS-3 is now
being reused to refer to one of the two LCSs procured in FY2009.)
November 2007 Termination of LCS-4
In late September 2007, it was reported that the Navy on September 19 had sent a letter to
General Dynamics to initiate negotiations on restructuring the contract for building LCSs 2 and 4
into an FPI-type contract. The negotiations reportedly were to be completed by October 19,
2007—30 days from September 19.55 On November 1, 2007, the Navy announced that it had not
reached an agreement with General Dynamics on a restructured FPI-type contract for LCS-2 and
LCS-4, and consequently was terminating construction of LCS-4.56 (The designation LCS-4 is
now being reused to refer to one of the two LCSs procured in FY2009.)
Cancellation of Prior-Year Ships
Table D-1 below summarizes the status of the nine LCSs funded by Congress from FY2005
through FY2009. As shown in the table, of the nine ships, five were later canceled, leaving four
ships in place through FY2009—LCSs 1 and 2, and the two LCSs funded in FY2009. Ship
designations LCS-3 and LCS-4 are being reused as the designations for the two ships funded in
FY2009.

54 Department of Defense News Release No. 422-07, April 12, 2007, “Navy Terminates Littoral Combat Ship 3.”
55 Geoff Fein, “Navy Seeking To Negotiate FPI Contract With General Dynamics,” Defense Daily, September 24,
2007; Geoff Fein, “Navy, General Dynamics Meet To Discuss New LCS Fixed Price Structure,” Defense Daily,
September 27, 2007; Tony Capaccio, “General Dynamics Urged To Take Fixed Price On Warship Contract,”
Bloomberg News, September 28, 2007; Jason Sherman, “Navy, General Dynamics Discuss Fixed-Price Contract For
LCS,” Inside the Navy, October 1, 2007.
56 Department of Defense News Release No. 1269-07, November 1, 2007, “Navy Terminates Littoral Combat Ship
(LCS 4) Contract.”
Congressional Research Service
42

Navy Littoral Combat Ship (LCS) Program

Table D-1. Status of LCSs Funded in FY2005-FY2009
FY
Navy hull
funded
designation
Status
2005
LCS-1
Commissioned into service on November 8, 2008. This ship
is included in Table 1.
LCS-2
Commissioned into service on January 16, 2010. This ship is
included in Table 1.
LCS-3
Canceled by Navy in April 2007 after being placed under
contract due to inability to come to agreement with contractor
(not the same ship as LCS-3 below)
on revised (fixed-price) contract terms for LCSs 1 and 3. This
2006
ship is not included in Table 1.
LCS-4
Canceled by Navy in November 2007 after being placed under
contract due to inability to come to agreement with contractor
(not the same ship as LCS-4 below)
on revised (fixed-price) contract terms for LCSs 2 and 4. This
ship is not included in Table 1.
none
Canceled by Navy in March 2007 before being placed under
(ship canceled before being placed
contract as part of Navy’s LCS program restructuring; funds
under contract)
reapplied to cover other program costs. This ship is not
included in Table 1.
2007
none
Canceled by Navy in March 2007 before being placed under
(ship canceled before being placed
contract as part of Navy’s LCS program restructuring; funds
under contract)
reapplied to cover other program costs. This ship is not
included in Table 1.
LCS-5
Canceled by Navy following Congress’s decision in
(for a while, at least, although the ship September 2008, as part of its action on the FY2009 defense
2008
was canceled before being placed
appropriations bill, to rescind the funding for the ship. This ship
under contract; the ship designation is is not included in Table 1.
now being used for the first of the two
ships funded in FY2010)
LCS-3
Under construction. This ship is included in Table 1.
(not the same ship as LCS-3 above; the
ship designation is being reused)
2009
LCS-4
Under construction. This ship is included in Table 1.
(not the same ship as LCS-4 above; the
ship designation is being reused)
Source: Prepared by CRS.
Congressional Research Service
43

Navy Littoral Combat Ship (LCS) Program

Appendix E. Down Select Acquisition Strategy
Announced in September 2009

This appendix presents additional background information on the down select acquisition strategy
announced by the Navy on September 16, 2009.
DOD and Navy Background Information
A September 16, 2009, Department of Defense (DOD) news release on the proposed down select
strategy stated:
The Navy announced today it will down select between the two Littoral Combat Ship (LCS)
designs in fiscal 2010. The current LCS seaframe construction solicitation [for the FY2010
LCSs] will be cancelled and a new solicitation will be issued. At down select, a single prime
contractor and shipyard will be awarded a fixed price incentive contract for up to 10 ships
with two ships in fiscal 2010 and options through fiscal 2014. This decision was reached
after careful review of the fiscal 2010 industry bids, consideration of total program costs, and
ongoing discussions with Congress.
“This change to increase competition is required so we can build the LCS at an affordable
price,” said Ray Mabus, secretary of the Navy. “LCS is vital to our Navy’s future. It must
succeed.”
“Both ships meet our operational requirements and we need LCS now to meet the
warfighters’ needs,” said Adm. Gary Roughead, chief of naval operations. “Down selecting
now will improve affordability and will allow us to build LCS at a realistic cost and not
compromise critical warfighting capabilities.”
The Navy cancelled the solicitation to procure up to three LCS Flight 0+ ships in fiscal 2010
due to affordability. Based on proposals received this summer, it was not possible to execute
the LCS program under the current acquisition strategy and given the expectation of
constrained budgets. The new LCS acquisition strategy improves affordability by
competitively awarding a larger number of ships across several years to one source. The
Navy will accomplish this goal by issuing a new fixed price incentive solicitation for a down
select to one of the two designs beginning in fiscal 2010.
Both industry teams will have the opportunity to submit proposals for the fiscal 2010 ships
under the new solicitation. The selected industry team will deliver a quality technical data
package, allowing the Navy to open competition for a second source for the selected design
beginning in fiscal 2012. The winner of the down select will be awarded a contract for up to
10 ships from fiscal 2010 through fiscal 2014, and also provide combat systems for up to
five additional ships provided by a second source. Delivery of LCS 2, along with
construction of LCS 3 and LCS 4 will not be affected by the decision. This plan ensures the
best value for the Navy, continues to fill critical warfighting gaps, reduces program
ownership costs, and meets the spirit and intent of the Weapons System Acquisition Reform
Act of 2009....
The Navy remains committed to the LCS program and the requirement for 55 of these ships
to provide combatant commanders with the capability to defeat anti-access threats in the
littorals, including fast surface craft, quiet submarines and various types of mines. The
Congressional Research Service
44

Navy Littoral Combat Ship (LCS) Program

Navy’s acquisition strategy will be guided by cost and performance of the respective designs
as well as options for sustaining competition throughout the life of the program.57
A September 16, 2009, e-mail from the Navy to CRS provided additional information on the
proposed down select strategy, stating:
The Navy remains committed to a 55 ship LCS program and intends to procure these ships
through an acquisition strategy that leverages competition, fixed price contracting and
stability in order to meet our overarching objectives of performance and affordability.
In the best interest of the Government, the Navy cancelled the solicitation to procure up to
three LCS Flight 0+ ships in FY10 due to affordability.
Based on proposals received in August, the Navy had no reasonable basis to find that the
LCS Program would be executable going forward under the current acquisition strategy,
given the expectation of constrained budgets.
In the near future, and working closely with Congress, the Navy will issue a new FY10
solicitation which downselects between the two existing designs and calls for building two
ships in FY10 and provides options for two additional ships per year from FY11 to FY14 for
a total of ten ships. The intent is for all of these ships to be built in one shipyard, which will
benefit from a stable order quantity, training and production efficiencies to drive costs down.
Both industry teams will have the opportunity to submit proposals for the FY10 ships under
the new solicitation.
To sustain competition throughout the life of the program and in conjunction with the
downselect, the Navy will develop a complete Technical Data Package which will be used to
open competition for a second source of the selected design in FY12, awarding one ship with
options for up to four additional ships through FY14, to a new shipbuilder.
Our FY10 solicitation will call for the prime to build an additional five combat systems to be
delivered as government-furnished equipment for this second source shipyard. Separating
the ship and combat systems procurement will enable bringing the LCS combat system into
the broader Navy’s open architecture plan.
In short, this strategy calls for two shipbuilders in continuous competition for a single LCS
seaframe design, and a government-provided combat system.
The revised strategy meets the full spirit and intent of the Weapon Systems Acquisition
Reform Act of 2009 by increasing Government oversight, employing fixed price contract
types, maximizing competition, leveraging open architecture, using Economic Order
Quantity and Block Buy strategies, and ensuring future competition for shipbuilding as
enabled by development of a Technical Data Package to solicit ships from a second shipyard.
We also continue to work closely with Congress on the Navy’s LCS procurement
intentions....
The Navy intends to continue with construction and delivery of LCS 3 and LCS 4, ultimately
for use as deployable assets. We will continue to explore all avenues to ensure this is an
affordable program.58

57 Department of Defense, “Littoral Combat Ship Down Select Announced,” News Release 722-09, September 16,
2009, available online at http://www.defenselink.mil/releases/release.aspx?releaseid=12984.
Congressional Research Service
45

Navy Littoral Combat Ship (LCS) Program

The Navy briefed CRS and CBO about the proposed down select strategy on September 22, 2009.
Points made by the Navy in the briefing included the following:
• The bids from the two industry teams for the three LCSs requested in the FY2010
budget (which were submitted to the Navy in late July or early August 200959)
were above the LCS unit procurement cost cap in “all scenarios.”
• Negotiations with the industry teams were deemed by the Navy to be not likely to
result in award prices for the FY2010 ships that were acceptable to the Navy.
• The Navy judged that the current LCS teaming arrangements “considerably
influenced costs” in the FY2010 bids.
• The Navy judged that it cannot afford more than a two-ship award in FY2010
within the amount of funding ($1,380 million) requested for LCS sea frame
procurement in FY2010.
• In response to the above points, the Navy decided to seek a new acquisition
strategy for LCSs procured in FY2010 and subsequent years that would make the
LCS program affordable by leveraging competition, providing stability to LCS
shipyards and suppliers, producing LCSs at efficient rates, giving industry
incentives to make investments that would reduce LCS production costs, and
increase commonality in the resulting LCS fleet.
• Under the Navy’s proposed strategy, the winner of the LCS down select would be
awarded a contract to build two ships procured in FY2010, with options to build
two more ships per year in FY2011-FY2014. The contract would be a block-buy
contract augmented with Economic Order Quantity (EOQ) authority, so as to
permit up-front batch purchases of long leadtime components, as would be the
case under a multiyear procurement (MYP) contract. Unlike an MYP contract,
however, the block buy contract would not include a termination liability.
• The winner of the down select would deliver to the Navy a technical data
package that would permit another shipyard to build the winning LCS design.
• The Navy would hold a second competition to select a second LCS bidder. This
competition would be open to all firms other than the shipyard that is building the
10 LCSs in FY2010-FY2014. The winner of this second competition would be
awarded a contract to build up to five LCSs in FY2012-FY2014 (one ship in
FY2012, and two ships per year in FY2013-FY2014).
• The Navy would maintain competition between the two shipyards for LCSs
procured in FY2015 and subsequent years.
• The prime contactor on the team that wins the LCS down select (i.e., Lockheed
or General Dynamics) would provide the combat systems for all the LCSs to be

(...continued)
58 Email from Navy Office of Legislative Affairs to CRS, entitled “LCS Way Ahead,” September 16, 2009.
59 See, for example, Christopher P. Cavas, “LCS Bids Submitted to U.S. Navy,” DefenseNews.com, August 3, 2009,
which states: “Lockheed Martin announced its proposal was sent to the Navy on July 31, and rival General Dynamics
confirmed its plans were sent in by the Aug. 3 deadline.” See also Bettina H. Chavanne, “Lockheed Submits First LCS
Proposal Under Cost Cap Regulations,” Aerospace Daily & Defense Report, August 4, 2009: 5.
Congressional Research Service
46

Navy Littoral Combat Ship (LCS) Program

procured in FY2010-FY2014—the 10 that would be built by the first shipyard,
and the others that would be built by the second shipyard.
• The structure of the industry team that wins the down select would be altered,
with the prime contractor on the team being separated from the shipyard (i.e., the
shipyard building the 10 LCSs in FY2010-FY2014). The separation, which
would occur some time between FY2010 and FY2014, would be intended in part
to prevent an organizational conflict of interest on the part of the prime contractor
as it provides combat systems to the two shipyards building LCSs.
• The current combat system used on the selected LCS design will be modified
over time to a configuration that increases its commonality with one or more of
the Navy’s existing surface ship combat systems.
• The Navy intends to complete the construction and delivery of LCS-3 and LCS-
4.
• The Navy believes that the proposed acquisition strategy does the following:
maximize the use of competition in awarding contracts for LCSs procured in
FY2010-FY2014; provide an opportunity for achieving EOQ savings with
vendors; provide stability and efficient production quantities to the shipyards and
vendors; provide an opportunity to move to a common combat system for the
LCS fleet; and provide the lowest-possible total ownership cost for the Navy for
the resulting LCS fleet, in large part because the fleet would consist primarily of
a single LCS design with a single logistics support system. The Navy also
believes the proposed strategy is consistent with the spirit and intent of the
Weapon Systems Acquisition Reform Act of 2009 (S. 454/P.L. 111-23 of May 22,
2009).
Regarding the Navy’s ability to sustain a competition between two LCS builders for LCS
construction contracts years from now, when the annual LCS procurement rate is projected to
drop to 1.5 ships per year (i.e., a 1-2-1-2 pattern), Under Secretary of the Navy Robert Work
reportedly stated:
“We are going to be able to compete those. We will be able to compete three [ships] every
two years and one of the yards will win two and one yard will win one. Sometimes, we’ll do
a five multi-year [procurement contract]. We have all sorts of flexibility in here,” he said.60
Potential Oversight Questions for Congress
Prior to the Navy’s November 3, 2010, proposal for a dual-award acquisition strategy, the
proposed down select strategy posed several potential oversight questions for Congress, including
the following:
• Did the timing of the Navy’s September 2009 announcement of the strategy—
very late in the congressional process for reviewing, marking up, and finalizing
action on the FY2010 defense budget—provide Congress with sufficient time to

60 Geoff Fein, “Official: Navy OK With Either LCS, New Acquisition Plan Adds Flexibility In Out Years,” Defense
Daily
, February 18, 2010: 3.
Congressional Research Service
47

Navy Littoral Combat Ship (LCS) Program

adequately review the proposal prior to finalizing its action on the FY2010
defense budget?
• Does the Navy’s proposed strategy allow the Navy enough time to adequately
evaluate the operational characteristics of the two LCS designs before selecting
one of those designs for all future production?
• Does the Navy’s proposed method for conducting the LCS down select—the
Request for Proposals (RFP)—appropriately balance procurement cost against
other criteria, such as life-cycle operation and support (O&S) cost and ship
capability?
• What risks would the Navy face if the shipyard that wins the competition to build
the 10 LCSs in FY2010-FY2014 cannot build them within the contracted cost?
• How does the Navy plan to evolve the combat system on the winning LCS design
to a configuration that has greater commonality with one or more existing Navy
surface ship combat systems?
• What are the Navy’s longer-term plans regarding the two “orphan” LCSs that are
built to the design that is not chosen in the down select?
• What potential alternatives are there to this acquisition strategy?
Each of these questions is discussed briefly below.
Enough Time for Adequate Congressional Review of Navy Proposal?
One potential issue for Congress concerning the proposed down select strategy was whether the
timing of the Navy’s September 2009 announcement of the strategy—very late in the
congressional process for reviewing, marking up, and finalizing action on the FY2010 defense
budget—provided Congress with sufficient time to adequately review the proposal prior to
finalizing its action on the FY2010 defense budget. The announcement of the Navy’s proposed
acquisition strategy on September 16, 2009, came
• after the defense committees of Congress had held their hearings to review the
FY2010 budget submission;
• after the FY2010 defense authorization bill (H.R. 2647/S. 1390) and the
Department of Defense (DOD) appropriations bill (H.R. 3326) had been reported
in the House and Senate;
• after both the House and Senate had amended and passed their versions of the
FY2010 defense authorization bill, setting the stage for the conference on that
bill; and
• after the House had passed its version of the FY2010 DOD appropriations bill.
The timing of the Navy’s announcement was a byproduct of the fact that the Navy was not able to
see and evaluate the industry bids for the three LCSs that the Navy had originally requested for
FY2010 until August 2009. The September 16, 2009, announcement date may have been the
earliest possible announcement date, given the time the Navy needed to consider the situation
created by the bids, evaluate potential courses of action, and select the proposed acquisition
strategy.
Congressional Research Service
48

Navy Littoral Combat Ship (LCS) Program

Although the Navy might not have been able to present the proposed down select strategy to
Congress any sooner than September 16, the timing of the Navy’s announcement nevertheless put
Congress in the position of being asked to approve a major proposal for the LCS program—a
proposal that would determine the basic shape of the acquisition strategy for the program for
many years into the future—with little or no opportunity for formal congressional review and
consideration through hearings and committee markup activities.
A shortage of time for formal congressional review and consideration would be a potential
oversight issue for Congress for any large weapon acquisition program, but this might have been
especially the case for the LCS program, because it was not be the first time that the Navy put
Congress in the position of having to make a significant decision about the LCS program with
little or no opportunity for formal congressional review and consideration. As discussed in
previous CRS reporting on the LCS program, a roughly similar situation occurred in the summer
of 2002, after Congress had completed its budget-review hearings on the proposed FY2003
budget, when the Navy submitted a late request for the research and development funding that
effectively started the LCS program.61

61 The issue of whether Congress was given sufficient time to review and consider the merits of the LCS program in its
early stages was discussed through multiple editions of past CRS reports covering the LCS program. The discussion in
those reports raised the question of whether “Navy officials adopted a rapid acquisition strategy for the LCS program in
part to limit the amount of time available to Congress to assess the merits of the LCS program and thereby effectively
rush Congress into approving the start of LCS procurement before Congress fully understands the details of the
program.” The discussion continued:
With regard to the possibility of rushing Congress into a quick decision on LCS procurement, it can
be noted that announcing the LCS program in November 2001 and subsequently proposing to start
procurement in FY2005 resulted in a situation of Congress having only three annual budget-review
seasons to learn about the new LCS program, assess its merits against other competing DOD
priorities, and make a decision on whether to approve the start of procurement. These three annual
budget-review seasons would occur in 2002, 2003, and 2004, when Congress would review the
Navy’s proposed FY2003, FY2004, and FY2005 budgets, respectively. Congress’ opportunity to
conduct a thorough review of the LCS program in the first two of these three years, moreover, may
have been hampered:
2002 budget-review season (for FY2003 budget). The Navy’s original FY2003 budget
request, submitted to Congress in February 2002, contained no apparent funding for
development of the LCS. In addition, the Navy in early 2002 had not yet announced that it
intended to employ a rapid acquisition strategy for the LCS program. As a result, in the early
months of 2002, there may have been little reason within Congress to view the LCS program
as a significant FY2003 budget-review issue. In the middle of 2002, the Navy submitted an
amended request asking for $33 million in FY2003 development funding for the LCS
program. Navy officials explained that they did not decide until the middle of 2002 that they
wanted to pursue a rapid acquisition strategy for the LCS program, and consequently did not
realize until then that there was a need to request $33 million in FY2003 funding for the
program. By the middle of 2002, however, the House and Senate Armed Services committees
had already held their spring FY2003 budget-review hearings and marked up their respective
versions of the FY2003 defense authorization bill. These two committees thus did not have an
opportunity to use the spring 2002 budget-review season to review in detail the Navy’s
accelerated acquisition plan for the LCS program or the supporting request for $33 million in
funding.
2003 budget-review season (for FY2004 budget). To support a more informed review of the
LCS program during the spring 2003 budget-review season, the conferees on the FY2003
defense authorization bill included a provision (Section 218) requiring the Navy to submit a
detailed report on several aspects of the LCS program, including its acquisition strategy. In
response to this legislation, the Navy in February 2003 submitted a report of eight pages in
length, including a title page and a first page devoted mostly to a restatement of Section 218’s
requirement for the report. The House and Senate Armed Services committees, in their reports
(continued...)
Congressional Research Service
49

Navy Littoral Combat Ship (LCS) Program

Supporters of the idea of approving the Navy’s proposed down select strategy as part of
Congress’s work to finalize action on the FY2010 defense budget could argue one or more of the
following:
• The timing of the Navy’s proposal, though not convenient for Congress,
nevertheless represented a good-faith effort by the Navy to present the proposal
to Congress at the earliest possible date. The Navy conducted multiple briefings
with congressional offices starting in September 2009 to explain the proposed
strategy.
• The LCS program needed to be put on a more stable long-term path as soon as
possible, and if Congress did not approve the proposal as part of its work in
finalizing action on the FY2010 defense budget, another year would pass before
the LCS program could be put on a stable path approved by Congress.
• Although cost growth and construction problems with the LCS program can be
viewed as a consequence of past attempts to move ahead too quickly on the LCS
program, the Navy’s acquisition strategy does not risk repeating this experience,
because it does not represent another attempt to move ahead on the program at an
imprudent speed. To the contrary, the strategy seeks to reduce execution risks by
limiting LCS procurement to a maximum of four ships per year and providing a
stable planning environment for LCS shipyards and suppliers.
• If the proposed strategy were not approved by Congress as part of its action on
the FY2010 budget, the LCSs procured in FY2010 would be more expensive to
procure, since they would not benefit from economies of scale that would come
from awarding the FY2010 ships as part of a contract that also includes LCSs to
be procured in FY2011-FY2014.
Supporters of the idea of deferring a decision on the Navy’s proposed down select strategy until
the FY2011 budget cycle could argue one or more of the following:
• Navy briefings to Congress on the proposed strategy starting in September 2009,
though helpful, were not sufficient for Congress to fully understand the features
and potential implications of the Navy’s proposed acquisition strategy—much
less the relative merits of potential alternatives to that strategy.
• The risks of making a quick decision on the Navy’s proposed acquisition
strategy, with little time for formal congressional review and consideration, are
underscored by the history of the LCS program, which includes substantial cost
growth and construction problems that can be viewed as the consequence of past

(...continued)
on the FY2004 defense authorization bill, have expressed dissatisfaction with the
thoroughness of the report as a response to the requirements of Section 218. (For details, see
the “Legislative Activity” section of this report.) It is thus not clear whether the defense
authorization committees were able to conduct their spring 2003 budget-review hearings on
the FY2004 budget with as much information about the LCS program as they might have
preferred.
(See, for example, CRS Report RL 32109, Navy DD(X), CG(X), and LCS Ship Acquisition Programs: Oversight Issues
and Options for Congress
, by Ronald O’Rourke, updated July 29, 2005, pp. CRS-59 to CRS-60. This discussion was
carried through multiple updates of CRS reports covering the LCS program.)
Congressional Research Service
50

Navy Littoral Combat Ship (LCS) Program

attempts to move ahead quickly on the program, without more-extensive
congressional review and consideration.
• The desire to avoid paying a relatively high cost for LCSs procured in FY2010,
though real, should not have been a controlling factor in this situation (i.e.,
should not have been “the tail that wags the dog”). Paying a higher cost for LCSs
procured in FY2010, though not optimal, would be an investment to buy time for
Congress to more fully review and consider the merits of both the Navy’s
proposal and potential alternatives to it. Problems avoided through a full
congressional review and consideration of the Navy’s proposal and potential
alternatives during the FY2011 budget cycle could eventually save the Navy a lot
more money than the Navy hopes to save on the LCSs procured in FY2010 by
procuring them as part of a contract that also includes LCSs to be procured in
FY2011-FY2014.
• Approving the Navy’s proposed acquisition strategy at a late juncture in the
annual congressional process for reviewing and marking up the defense budget
would set an undesirable precedent from Congress’s standpoint regarding late
submissions to Congress of significant proposals for large defense acquisition
programs, and encourage DOD to do the same with other large weapon
acquisition programs in the future in the hopes of stampeding Congress into
making quick decisions on major proposals for those programs.
Enough Time to Evaluate the Two Designs’ Operational Characteristics?
Another potential issue for Congress concerning the Navy’s down select strategy was whether the
strategy allowed the Navy enough time to adequately evaluate the operational characteristics of
the two LCS designs before selecting one of those designs for all future production. Potential
oversight questions for Congress included the following:
• Since LCS-1 as of September 2009 had been in commissioned service for less
than a year, and LCS-2 as of that date had not yet been delivered to the Navy,
how firm was the basis for the Navy’s determination that both LCS designs meet
the Navy’s operational requirements for LCS?
• By the summer of 2010—when the Navy plans to award a contract to the winner
of the down select—the Navy will have had only a limited time to evaluate the
operational characteristics of LCS-1 and LCS-2 through fleet exercises and use in
actual Navy deployments. Will the Navy at that point have a sufficient
understanding of the two designs’ operational characteristics to appropriately
treat the operational characteristics of the two designs in the down select?
The Navy and its supporters could argue that the Navy has chosen a preferred design for other
new Navy ships (such as the DDG-1000 destroyer) on the basis of paper designs only, and
consequently that the Navy would have a firmer basis for performing the LCS down select than it
has had on other shipbuilding programs. They can argue that the Navy has a good understanding
of the basic differences between the ships—that the Lockheed design, for example, may have
better features for supporting small boat operations (which are used for certain LCS missions),
while the General Dynamics design may have better features for supporting helicopter and
unmanned aerial vehicle (UAV) operations (which are used for certain LCS missions).
Congressional Research Service
51

Navy Littoral Combat Ship (LCS) Program

Skeptics could argue that the Navy in the past has talked about performing an extensive
operational review of each design prior to settling on an acquisition strategy for follow-on ships
in the program, and that the innovative nature of the LCS—a modular ship with plug-and-fight
mission packages and a small crew—increases the risks associated with selecting a single LCS
design before performing such an extensive operational review. Skeptics could argue that the
Navy is depriving itself of the opportunity to better understand, through exercises and real-world
deployments, the implications for overall fleet operations of building all LCSs to one design or
the other before performing the down select.
Weight Given to Procurement Cost vs. Other Factors in Request for Proposals
(RFP)

Another potential issue for Congress concerning the Navy’s down select strategy concerned the
criteria that the Navy will use for selecting a winning design in the down select. Some observers,
particularly supporters of the General Dynamics LCS design, argued that the Navy’s proposed
method for evaluating the two LCS designs in the LCS down select—set forth in the Request for
Proposals (RFP) for the down select—focused too much on procurement cost and not enough on
other factors, particularly life-cycle fuel cost, other components of life-cycle operating and
support (O&S) cost, and ship capability. Other observers, particularly supporters of the Lockheed
LCS design, argued (as did the Navy) that the Navy’s proposed method for conducting the LCS
down select adequately took into account factors other than procurement cost. The issue was
viewed as having the potential for leading to a protest of the Navy’s down select decision by the
firm that is not selected.62
Regarding the role of life-cycle operation and support (O&S) cost in the Navy’s down select
decision, a February 2010 GAO report stated:
The Navy estimated operating and support costs for LCS seaframes and mission packages in
2009, but the estimates do not fully reflect DOD and GAO best practices for cost estimating
and may change due to program uncertainties. GAO’s analysis of the Navy’s 2009 estimates
showed that the operating and support costs for seaframes and mission packages could total
$84 billion (in constant fiscal year 2009 dollars) through about 2050. However, the Navy did
not follow some best practices for developing an estimate such as (1) analyzing the
likelihood that the costs could be greater than estimated, (2) fully assessing how the estimate
may change as key assumptions change, and (3) requesting an independent estimate and
comparing it with the program estimate. The estimates may also be affected by program
uncertainties, such as potential changes to force structure that could alter the number of ships
and mission packages required. The costs to operate and support a weapon system can total
70 percent of a system’s costs, and the lack of an estimate that fully reflects best practices

62 For examples of articles discussing this issue, see Sean Reilly, “Loser To Fight In LCS Deal?” Mobile (AL) Press-
Register
, March 28, 2010: 1; Cid Standifer, “Austal USA, GD Officials Criticize Navy’s RFP Criteria For LCS
Award,” Inside the Navy, March 29, 2010; Zachary M. Peterson, “Navy LCS Proposal Request Seeks ‘Qualitative’
Total Ownership Cost Figures,” Inside the Navy, March 22, 2010; Emelie Rutherford, “Navy Stands By LCS Due Date
As Hill Backers Of Each Bidder Swap Barbs,” Defense Daily, March 18, 2010: 2-3; Geoff Fein, “General Dynamics’
LCS Burns Less Fuel At Higher Speeds, Navy Documents Show,” Defense Daily, March 2, 2010: 1-2; Geoff Fein,
“Sessions Presses Navy Over Fairness of LCS RFP Evaluation,” Defense Daily, March 1, 2010: 6-7; Geoff Fein, “USS
Independence [LCS-2] Is The More Fuel Efficient of Two LCS Variants, Austal Official Says,” Defense Daily,
February 24, 2010: 2-3; Geoff Fein, “LCS RFP: Greater Emphasis Placed On Ship Price, Less On Life-Cycle Cost,”
Defense Daily, January 29, 2010: 5-7; Christopher P. Cavas, “RFP for LCS: Cost Main Factor in Winning Bid,”
NavyTimes.com, January 28, 2010.
Congressional Research Service
52

Navy Littoral Combat Ship (LCS) Program

could limit decision makers’ ability to identify the resources that will be needed over the
long term to support the planned investment in LCS force structure. With a decision pending
in 2010 on which seaframe to buy for the remainder of the program, decision makers could
lack critical information to assess the full costs of the alternatives.63
A February 8, 2010, press report stated that “the Navy will draw up total life-cycle cost estimates
for both the Lockheed Martin and General Dynamics versions of the Littoral Combat Ship before
the program goes before the Defense Acquisition Board this year for its Milestone B. review. The
service included the announcement in a response to a Government Accountability Office report
that criticized LCS life-cycle estimates.”64
At the request of Senator Jeff Sessions, the CBO analyzed the impact of O&S cost and other
types of costs on the total life-cycle costs of the LCS and (for purposes of comparison) four other
types of Navy ships. The results of CBO’s analysis were released in the form of an April 28,
2010, letter to Senator Sessions. The letter states:
CBO projected the life-cycle cost of the LCS-1 under three different assumptions about the
average annual amount of fuel the ship will use over its 25-year life: low, moderate, and
high. In all three scenarios, procurement costs dominate the life-cycle cost of the LCS-1,
ranging from 58 percent to 66 percent of the total.… Personnel costs make up 14 percent to
16 percent of the LCS-1’s total life-cycle cost in the various scenarios, and fuel costs account
for 8 percent to 18 percent.
The low-fuel case assumes that the LCS-1 generally operates at relatively low speeds—10
knots or less 90 percent of the time it is under way and 30 knots or more only about 3 percent
of the time. That speed profile is based in part on how the Navy operated the LCS-1 between
March 2009 and March 2010. In that scenario, operation and support costs total 33 percent of
the ship’s life-cycle cost: 16 percent for personnel costs, 8 percent for fuel costs (assuming
that the ship consumes 25,000 barrels of fuel per year), and 9 percent for other O&S costs….
The moderate-fuel case—which CBO considers the most likely of the three scenarios—
assumes that the LCS-1 operates at 30 or more knots for about 5 percent of the time, at 14
knots to 16 knots 42 percent of the time (a range that might be typical when the ship was
traveling from its home port to a deployment location), and at less than 12 knots for the rest
of its time under way. In that scenario, O&S costs total 34 percent of the ship’s life-cycle
cost: 15 percent for personnel, 11 percent for fuel, and 8 percent for other O&S costs. The
moderate speed profile would result in fuel usage of about 35,000 barrels per year, slightly
less than the 37,600 barrels that the Navy assumed in formulating its 2011 budget request.
By comparison, the [Navy’s] FFG-7 class frigates consumed about 31,000 barrels of fuel per
ship in 2009.
The high-fuel case assumes that the LCS-1 operates at 30 or more knots for about 20 percent
of its time under way, an assumption based partly on a speed profile developed by the Naval
Sea Systems Command for the LCS program. In that scenario, O&S costs represent about 40
percent of the ship’s life-cycle cost—more than in the other scenarios for the LCS-1 but less
than for any of the other types of ships considered in this analysis. Personnel costs make up
14 percent of the life-cycle total; fuel costs, 18 percent; and other O&S costs, 8 percent.

63 Government Accountability Office, Littoral Combat Ship[:] Actions Needed to Improve Operating Cost Estimates
and Mitigate Risks in Implementing New Concepts
, GAO-10-257, February 2010, summary page.
64 Cid Standifer, “Navy Will Project Operation Costs Of Both LCS Models for DAB Review,” Inside the Navy,
February 8, 2010.
Congressional Research Service
53

Navy Littoral Combat Ship (LCS) Program

Projected fuel usage in this scenario is about 67,000 barrels per year. That estimate is
unlikely to be exceeded in actual practice: It is twice the historical average for frigates and
about 80 percent of the amount used by the Navy’s destroyers (which do not have the
capability to speed at 40 knots, as the littoral combat ship does, but are three times larger
than the LCS-1).65
At a May 6, 2010, hearing on Navy shipbuilding programs before the Seapower Subcommittee of
the Senate Armed Services Committee, Senator Sessions questioned Sean Stackley, the Navy’s
acquisition executive (i.e., the Assistant Secretary of the Navy [Research, Development and
Acquisition]), regarding the role of fuel costs in the Navy’s evaluation of the two LCS designs.
Potential Risks If First Shipyard Cannot Build Ships Within Cost
Another potential issue for Congress concerning the Navy’s down select strategy concerned the
potential risks the Navy would face if the shipyard that wins the competition to build the 10 LCSs
in FY2010-FY2014 cannot build them within the contracted cost. The competition between the
two existing LCS industry teams to be the winner of the down select could be intense enough to
encourage the teams to bid unrealistically low prices for the contract to build the 10 ships.
The Navy and its supporters could argue that the Navy’s plan to award a fixed-price contract to
the winner of the down select would shift the cost risk on the 10 ships from the government to the
shipyard. They could also argue that the Navy plans to carefully evaluate the bid prices submitted
by the two industry teams for the down select to ensure that they are realistic, and that the
existence of the second LCS shipyard would provide the Navy with an ability to continue
building LCSs if production at the first yard were disrupted due to financial issues.
Skeptics could argue that even with a fixed-price contract, the Navy’s proposed strategy poses
cost risks for the government, because a shipyard could submit an unrealistically low bid so as to
win the down select, and then recover its losses on those 10 ships by rolling the losses into prices
for downstream ships in the program. Alternatively, the shipyard could present the Navy with the
prospect of going out of business and disrupting the LCS production effort unless the Navy were
to provide a financial bailout to cover the yard’s losses on the 10 ships. Skeptics could argue that
Navy decisions dating back to the 1970s to award multi-ship construction contracts to shipyards
that had not yet built many ships of the kind in question sometimes led to less-than-satisfactory
program outcomes, including substantial financial bailouts.
Increasing LCS Combat System Commonality with Other Combat Systems
Another potential issue for Congress regarding the Navy’s down select strategy concerned the
Navy’s plan to evolve the combat system on the winning LCS design to a configuration that has
greater commonality with one or more existing Navy surface ship combat systems. The Navy in
its September 16, 2009, announcement did not provide many details on this part of its proposed
acquisition strategy, making it difficult to evaluate the potential costs and risks of this part of the
strategy against potential alternatives, including an alternative (which Navy officials have
discussed in the past) of designing a new LCS combat system that would, from the outset, be
highly common with one or more existing Navy surface ship combat systems.

65 Letter dated April 28, 2010, from Douglas W. Elmendorf, Director, CBO, to the Honorable Jeff Sessions, pp. 3-5.
The letter is available online at http://www.cbo.gov/ftpdocs/114xx/doc11431/04-28-SessionsLetter.pdf.
Congressional Research Service
54

Navy Littoral Combat Ship (LCS) Program

Navy’s Longer-Term Plans Regarding Two “Orphan” Ships
Another potential issue for Congress concerning the Navy’s down select strategy concerned the
Navy’s longer-term plans regarding the two “orphan” LCSs built to the design that was not
selected in the down select. The Navy stated that it planned to keep these two ships in the fleet
because they will be capable ships and the Navy has an urgent need for LCSs. These two LCSs,
however, will have unique logistic support needs, potentially making them relatively expensive to
operate and support. At some point, as larger numbers of LCSs enter service, the costs of
operating and supporting these two ships may begin to outweigh the increasingly marginal
addition they make to total LCS fleet capabilities. Potential alternatives to keeping the ships in the
active-duty fleet as deployable assets include selling them to foreign buyers, converting them into
research and development platforms, shifting them to the Naval Reserve Force (where they would
be operated by crews consisting partially of reservists), or decommissioning them and placing
them into preservation (i.e., “mothball”) status as potential mobilization assets. Potential
questions for Congress included the following:
• Does the Navy intend to keep the two orphan LCSs in the active-duty fleet as
deployable assets for a full 25-year service life?
• If so, how would be the life-cycle operation and support (O&S) costs of these
two ships compare to those of the other LCSs? In light of these O&S costs,
would it be cost effective to keep these two ships in the active-duty fleet as
deployable assets for a full 25-year service life, particularly as large numbers of
LCSs enter service?
• If the Navy does not intend to keep the two orphan LCSs in the active-duty fleet
as deployable assets for a full 25-year service life, when does the Navy anticipate
removing them from such service, and what does the Navy anticipate doing with
them afterward?
Potential Alternatives to Navy’s September 2009 Strategy
Another potential issue for Congress concerning the Navy’s down select strategy concerned
potential alternatives to that strategy. A variety of alternatives can be generated by changing one
or more elements of the Navy’s proposed strategy. One alternative would be a strategy that would
keep both LCS designs in production, at least for the time being. Such a strategy might involve
the following:
• the use of block-buy contracts with augmented EOQ authority, as under the
Navy’s proposed acquisition strategy, to continue producing both LCS designs,
so as to provide stability to shipyards and suppliers involved in producing both
LCS designs;
• the use of Profit Related to Offer (PRO) bidding between the builders of the two
LCS designs, so as to generate competitive pressure between them and thereby
restrain LCS production costs;66 and

66 Under PRO bidding, the two shipyards would compete not for LCS quantities (because each shipyard would know
that it was going to build a certain number of LCSs over the term of their block-buy contracts), but rather for profit,
with the lowest bidder receiving the higher profit margin. PRO bidding has been used in other defense acquisition
programs where bidders do not compete for quantity. The Navy, for example, began using PRO bidding in the DDG-51
(continued...)
Congressional Research Service
55

Navy Littoral Combat Ship (LCS) Program

• designing a new LCS combat system that would have a high degree of
commonality with one or more existing Navy surface ship combat systems and
be provided as government-furnished equipment (GFE) for use on both LCS
designs—an idea that was considered by the Navy at an earlier point in the
program.
The Navy’s November 3, 2010, proposal for a dual-award LCS acquisition strategy is broadly
similar to the notional dual-award approach outlined above. This notional dual-award approach
has been presented in this CRS report as an option for Congress since September 27, 2009, when
the report was updated to incorporate the Navy’s September 16, 2009, announcement of its
proposed down select strategy. The discussion below concerns the notional dual-award approach
outlined above.
Supporters of an alternative like the one outlined above could argue that it would
• provide stability to LCS shipyards and suppliers;
• use competition to restrain LCS production costs;
• permit the Navy to receive a full return on the investment the Navy made in
creating both LCS designs;
• reduce the life-cycle operation and support costs associated with building two
LCS designs by equipping all LCSs with a common combat system;
• allow the Navy to design an LCS combat system that is, from the outset, highly
common with one or more of the Navy’s existing surface ship combat systems;
• achieve a maximum LCS procurement rate of four ships per year starting in
FY2011 (two years earlier than under the Navy’s proposal), thus permitting more
LCSs to enter service with the Navy sooner;
• build both LCS designs in substantial numbers, thereby avoiding a situation of
having a small number of orphan LCS ships that could have potentially high
operation and support costs;
• preserve a potential to neck down to a single LCS design at some point in the
future, while permitting the Navy in the meantime to more fully evaluate the
operational characteristics of the two designs in real-world deployments; and
• increase the potential for achieving foreign sales of LCSs (which can reduce
production costs for LCSs made for the U.S. Navy) by offering potential foreign
buyers two LCS designs with active production lines.
Supporters of the Navy’s proposed acquisition strategy could argue that an alternative like the one
outlined above would, compared to the Navy’s proposed strategy
• achieve lower economies of scale in LCS production costs by splitting
production of LCS components between two designs;

(...continued)
destroyer program it in the 1990s.
Congressional Research Service
56

Navy Littoral Combat Ship (LCS) Program

• achieve, at the outset of series production of LCSs, less bidding pressure on
shipyards, and thus higher LCS production costs, than would be achieved under
the Navy’s proposed strategy of using a price-based competition to select a single
design for all future LCS production;
• miss out on the opportunity to restrain LCS costs by using the level of efficiency
achieved in building an LCS design at one shipyard as a directly applicable
benchmark for gauging the level of efficiency achieved by the other shipyard in
building the same LCS design;
• increase Navy LCS program-management costs and the burden on Navy
program-management capabilities by requiring the Navy to continue managing
the construction of two very different LCS designs;
• achieve lower economies of scale in LCS operation and support costs because the
two LCS designs would still differ in their basic hull, mechanical, and electrical
(HM&E) systems, requiring the Navy to maintain two separate HM&E logistics
support systems;
• receive only a limited return on the investment the Navy made in developing the
two current LCS combat systems (since LCSs in the long run would not use
either one), and require the Navy to incur the costs and the technical risks
associated with designing a completely new LCS combat system;
• require the Navy to build some number of LCSs with their current combat
systems—which are different from one another and from other Navy surface ship
combat systems—while awaiting the development of the new LCS combat
system, and then incur the costs associated with backfitting these earlier LCSs
with the new system when it becomes available;
• send to industry a signal that is undesirable from the government’s perspective
that if the Navy or other parts or DOD begin producing two designs for a new
kind of weapon system, the Navy or DOD would be reluctant to neck production
down to a single design at some point, even if government believes that doing so
would reduce program costs while still meeting operational objectives; and
• miss out on the opportunity that would be present under the Navy’s proposed
acquisition strategy to increase the potential for achieving foreign sales of LCSs
by offering potential foreign buyers an LCS design that, through U.S. production,
enjoys significant economies of scale for both production and operation and
support.

Congressional Research Service
57

Navy Littoral Combat Ship (LCS) Program

Appendix F. Dual-Award Acquisition Strategy
Announced in November 2010

This appendix presents additional background information on the dual-award acquisition strategy
announced by the Navy on November 3, 2009.
November 4, 2010, Navy Point Paper
A November 4, 2010, Navy point paper on the dual-award strategy proposed on November 3,
2010, stated the following (this is the full text of the point paper):67
Littoral Combat Ship Proposed Revised Acquisition
Dual Ten Ship Awards
• In summer 2009 Navy received bids for three FY10 ships from Lockheed
Martin/Marinette Marine/Bollinger and General Dynamics Bath Iron Works/Austal
USA industry teams. These bids did not reflect competitive pricing and well exceeded
the Congressional Cost Cap. In order to reverse cost trends on the program, the
acquisition strategy was revised to the current down select strategy.
• The Navy’s Littoral Combat Ship acquisition strategy to down select to a single design
has resulted in a highly effective competition between the industry bidders. Navy is on
the path to down select in accordance with the terms of the current solicitation.
• The industry response to the competitive acquisition strategy has resulted in has resulted
in reduction in cost for the LCS ships relative to the previous bids. These competitive
bids, coupled with Navy’s desires to increase ship procurement rates to support
operational requirements, has created an opportunity to award each bidder a fixed price
ten-ship block buy – a total of 20 ships from Fiscal Year 2010 to Fiscal Year 2015. A
comparison between the two strategies of which ships are included in a down
select/second source versus dual 10 ship block buy appears in the table below.
• The current NDAA [national defense authorization act] language permits the Navy to
procure up to 10 ships in a block buy. In order to execute a dual ten ship award, Navy
believes Congressional authorization is required.
• If Congressional support for this approach is granted, Navy will work with industry to
revise the ship procurement schedules within current proposal pricing (FY10 – FY15
vice FY10 – FY14).
• Navy is continuing on the path to down select and absent authorization, we will proceed
to down select by mid-December 2010.
• There are numerous benefits to this approach including stabilizing the LCS program and
the industrial base with award of 20 ships; increasing ship procurement rate to support

67 Source: Navy point paper on proposed alternative LCS acquisition strategy dated November 4, 2010.
Congressional Research Service
58

Navy Littoral Combat Ship (LCS) Program

operational requirements; sustaining competition through the program; and enhancing
Foreign Military Sales opportunities.
• The Navy intends to procure the Technical Data Package for both designs and if
necessary a second source for either or both designs could be brought into the program.
• Either approach will ensure the Navy procures affordably priced ships.

FY10
FY11
FY12
FY13
FY14
FY15
TOTAL
Winner
2
2
2
2
2
4
Downselect
Second Source
1
2
2
19
TOTAL
2
2
3
4
4
4
Contractor A
1
1
2
2
2
2
Dual Award
Contractor B
1
1
2
2
2
2
20
TOTAL
2
2
4
4
4
4

Near-Term Issue for Congress
The Navy’s proposed dual-award strategy posed a near-term issue for Congress of whether this
strategy would be preferable to the down select strategy, and whether Congress should grant the
Navy, by December 30, the additional legislative authority the Navy would need to implement the
dual-award strategy.
December 14 Senate Armed Services Committee Hearing
On December 14, 2010, the Senate Armed Services Committee held a hearing to review the
Navy’s proposed dual-award strategy. The witnesses at the hearing included Navy leaders and
representatives from CBO, GAO, and CRS. The committee’s web page for the hearing68 contains
links to the prepared statements of the GAO and CRS witnesses, and states that the Navy and
CBO witnesses did not submit their prepared statements in electronic form. (The CBO witness
asked in his opening remarks that CBO’s December 10, 2010, letter report on the relative costs of
the down select and dual-award strategies69 be entered into the record for the hearing. CBO’s
letter report is available from the CBO website.) The committee’s web page for the hearing also
contains a link to the transcript of the hearing.
Some General Observations
General observations that could be made on the Navy’s proposed dual-award strategy included
but are not limited to the following:

68 http://armed-services.senate.gov/testimony.cfm?wit_id=9812&id=4897.
69 Congressional Budget Office, letter report to Senator John McCain on LCS acquisition strategies dated December 10,
2010, 7 pp.
Congressional Research Service
59

Navy Littoral Combat Ship (LCS) Program

• The dual-award strategy would avoid, at least for now, the possibility of a
contract protest being filed against a Navy down select decision.
• Although the dual-award strategy includes the possibility of the Navy at some
point bringing a second source into the program for either or both LCS designs,
the dual-award strategy does not include the guaranteed opportunity present in
the down select strategy for shipyards not currently involved in building LCSs to
compete for the right to become the second LCS builder.
• The Navy’s November 4, 2010, point paper on the dual-award strategy does not
outline the Navy’s intentions regarding the currently different combat systems
(i.e., the built-in collections of sensors, weapons, displays, and software) on the
two LCS designs.
• The dual-award strategy would require each LCS contractor to build 10 ships
over a period of six years (FY2010-FY2015) rather than five years (FY2010-
FY2014), but at the same price that was bid for the five-year schedule. In
addition, LCSs built under the dual-award strategy would incorporate combat
systems that would be built by combat system manufacturers in smaller annual
quantities than would be the case under the down select strategy, possibly
increasing the costs of these combat systems. Factors such as these could, at the
margin, alter the profitability for each contractor of building its respective group
of 10 ships.
It could also be noted that the Navy’s proposed dual-award strategy is broadly similar to a
notional dual-award approach that was presented in this CRS report as an option for Congress
(see Appendix E) since September 27, 2009, when the report was updated to incorporate the
Navy’s September 16, 2009, announcement of its proposed down select strategy.
Potential Oversight Questions for Congress
Potential oversight questions for Congress in assessing whether the proposed dual-award strategy
would be preferable to the down select strategy, and whether to grant the Navy, by December 30,
the additional legislative authority the Navy would need to implement a dual-award strategy,
included but were not limited to the following:
• Did the timing of the Navy’s proposal provide Congress with enough time to
adequately assess the relative merits of the down select strategy and the dual-
award strategy? Given that the contractors submitted their bids by about
September 15, could the Navy have notified Congress of the proposed dual-
award strategy sooner than November 3, giving Congress more time to seek
information on and evaluate the proposal? Should the Navy have asked the
contractors to extend their bid prices for another, say, 30 or 60 or 90 days beyond
the original December 14 expiration date, so as to provide more time for
congressional review of the Navy’s proposal?70 (As mentioned earlier, on

70 A December 6, 2010, press report states: “Lockheed officials have indicated that they could extend the pricing in
their proposal for a short while beyond Dec. 14, to allow time for Congress to approve the change. Lockheed Chief
Financial Officer Bruce Tanner told an investment conference last week that Lockheed could extend the prices it
offered for a day or two, but not indefinitely…. Analysts said they expected both companies to show some flexibility
on the expiration of their pricing, given that each firm stood to win a contract valued at around $5 billion.” (Andrea
(continued...)
Congressional Research Service
60

Navy Littoral Combat Ship (LCS) Program

December 13, it was reported that the two LCS bidders, at the Navy’s request,
had extended the prices in their bids for 16 days, to December 30. At the
December 14 hearing, Navy witnesses expressed strong doubts about the
willingness of the bidders to extend their bid prices for any significant additional
amount of time, since agreements with their parts suppliers and other
arrangements on which the bids are based would no longer be valid.)
• What role, if any, did a desire by the Navy to avoid a potential contract protest
against the Navy’s down select decision play in the Navy’s decision to propose
the alternate dual-award strategy? For example, how concerned, if at all, was the
Navy that the announcement of an LCS down select decision might lead to a
contract protest and controversy somewhat like what has been experienced in the
Air Force’s KC-X aerial refueling tanker acquisition program?71 A December 13,
2010, press report on the LCS program stated: “One high-level Navy source
recently said that without the dual-ship approach, ‘there is 100 percent chance of
a protest.’”72
• What are the potential relative costs of the down select and dual-award
acquisition strategies, including development costs, procurement costs, and life-
cycle operation and support (O&S) costs? Did the Navy fully and accurately
estimated these costs—including potential costs for developing, procuring, and
installing a common combat system for both LCS designs—and reported all
these potential costs to Congress?
• What are the potential relative risks of the down select and dual-award
acquisition strategies, including development risks, production cost risks,
production schedule risks, and life-cycle O&S risks? Did the Navy fully and
accurately estimated these risks, and reported all these potential risks to
Congress?
• What are the Navy’s intentions, under the proposed dual-award acquisition
strategy, regarding the currently different combat systems on the two LCS
designs? Does the Navy intend to leave them unchanged, adopt one of the
combat systems as the common system for both designs, or develop a new
combat system for both designs? If the Navy intends to pursue the second or third
of these paths, what is the Navy’s plan (including schedule) for doing so? If the
Navy does not have a definite plan regarding the combat systems for the ships,
how well can the potential costs and risks of the dual-award strategy be estimated
and compared to those of the down select strategy?
• What are the potential industrial-base impacts of the dual-award strategy,
including impacts on the two LCS contractors, on shipyards that could, under the

(...continued)
Shalal-Esa, “U.S. Navy Hopeful Congress Will Approve Ship Buys,” Reuters.com, December 6, 2010.) Another
December 6, 2010, press report that was posted online on December 3, 2010, stated: “Theoretically, Lockheed Martin
and Austal could likely agree to extend the price deadline, but the Navy has not asked them to do so yet, [Navy
spokeswoman Captain Cate] Mueller said.” (Cid Standifer, “Stand-Alone Bill May Be Needed To Approve LCS Dual
Block Buy Plan,” Inside the Navy, December 6, 2010.)
71 For more on the KC-X program, see CRS Report RL34398, Air Force KC-46A Tanker Aircraft Program:
Background and Issues for Congress
, by Jeremiah Gertler.
72 Christopher P. Cavas, “Deadline Looms For U.S. Navy’s LCS,” Defense News, December 13, 2010: 1.
Congressional Research Service
61

Navy Littoral Combat Ship (LCS) Program

down select strategy, bid for the right to become the second LCS builder, and on
combat system manufacturers?
• What impact, if any, might the Navy’s proposal to shift from its down select
strategy to the dual-award strategy have on the ability of the Department of
Defense (DOD) to implement down select strategies for other acquisition
programs? For example, will the Navy’s proposal to shift to the dual-award
strategy cause contractors bidding for other acquisition programs to treat with
increased skepticism stated DOD intentions to carry out down selects? If so,
could that reduce the benefits of competition that DOD might hope to achieve
through the use of down select strategies?
Enough Time for Adequate Congressional Review of Navy
Proposal?

Regarding whether the timing of the Navy’s proposal provides Congress with enough time to
adequately assess the relative merits of the down select strategy and the dual-award strategy, it
can be noted that this was the third time in the history of the LCS program that the Navy
presented Congress with an important choice about the future of the LCS program late in the
congressional budget-review cycle, after Congress had completed its spring budget-review
hearings and some of its committee markups. The first instance was in mid-2002, when the Navy
submitted an amended request to Congress for FY2003 funding to get the LCS program started
using a rapid acquisition strategy.73 The second was in September 2009, when the Navy
announced its proposed down select strategy for the LCS program (see the discussion of this issue
in following section on the down select strategy).
In light of the third instance—the Navy’s proposal of November 3, 2010, for using a dual-award
strategy rather than a down select strategy—a potential issue for Congress are the implications for
the LCS program and congressional oversight of defense acquisition programs in general of
proceeding with the LCS program in part on the basis of policies originally presented as
proposals to Congress late in the congressional budget-review cycle, after Congress had
completed its spring budget-review hearings and some of its committee markups. The Navy’s
November 3, 2010, notification to Congress of the proposed dual-award strategy, combined with
a request by the Navy that Congress act on that proposal by December 30, provided relatively
little time for Congress to collect cost and other information from the Navy (including
information that Navy might not offer in initial briefings to individual congressional offices), for
Congress to solicit cost and other information from independent sources such as CBO and GAO,

73 The Navy’s original FY2003 budget request, submitted to Congress in February 2002, contained no apparent funding
for development of the LCS. In addition, the Navy in early 2002 had not yet announced that it intended to employ a
rapid acquisition strategy for the LCS program. As a result, in the early months of 2002, there may have been little
reason within Congress to view the LCS program as a significant FY2003 budget-review issue. In the middle of 2002,
the Navy submitted an amended request asking for $33 million in FY2003 development funding for the LCS program.
Navy officials explained that they did not decide until the middle of 2002 that they wanted to pursue a rapid acquisition
strategy for the LCS program, and consequently did not realize until then that there was a need to request $33 million in
FY2003 funding for the program. By the middle of 2002, however, the House and Senate Armed Services committees
had already held their spring FY2003 budget-review hearings and marked up their respective versions of the FY2003
defense authorization bill. These two committees thus did not have an opportunity to use the spring 2002 budget-review
season to review in detail the Navy’s accelerated acquisition plan for the LCS program or the supporting request for
$33 million in funding.
Congressional Research Service
62

Navy Littoral Combat Ship (LCS) Program

for CBO and GAO to develop such information and provide it to Congress, for Congress to hold
hearings at which all this information might be discussed in a group setting, with multiple parties
present, and for congressional offices to then form their evaluations of the Navy’s proposal.
Relative Costs
Regarding the relative costs of the down select and dual-award acquisition strategies, there were
at least three significant cost elements to consider: ship procurement costs; costs for possibly
modifying the combat systems on LCSs so as to achieve more commonality in combat system
equipment among all LCSs, and between LCSs and other Navy ships; and operational and
support (O&S) costs.
Ship Procurement Costs
Regarding ship procurement costs, the Navy estimated that procuring LCSs under the dual-award
strategy would cost $1 billion less through FY2016, and $600 million less through FY2015, than
procuring them under the down select strategy. The Navy states that the $1 billion in savings
through FY2016 translates to $910 million in net present value terms, and that the $600 million in
savings through FY2015 translates to $496 million in net present value terms.74
CBO, in contrast, estimates in its December 10, 2010, letter report that procuring LCSs under the
dual-award strategy would cost $740 million more through FY2015) than procuring them under
the down select strategy. CBO’s letter report included several cautionary statements about its
estimates relating to limits on the information available to CBO in developing its estimates. The
Navy and CBO estimates of ship procurement costs through FY2015 are summarized in Table
F-1
.
Table F-1. Navy and CBO Estimates of Ship Procurement Costs Through FY2015
Under Down Select and Dual-Award Strategies
For the period FY2010-FY2015, in current (i.e., then-year) dollars
Acquisition approaches
Estimated Cost
Navy estimate
19-ship down-select plan
10,400 million
20-ship dual-award plan
9,800 million
Difference between two plans
Dual-award plan costs $600 million less


CBO estimate
19-ship down-select plan
11,080 million
20-ship dual-award plan
11,820 million
Difference between two plans
Dual-award plan costs $740 million more

74 Source for $496 million figure: Navy briefing to CRS and CBO, March 30, 2011.
Congressional Research Service
63

Navy Littoral Combat Ship (LCS) Program

Source: Table prepared by CRS based on data presented in Congressional Budget Office, letter report to
Senator John McCain on LCS acquisition strategies dated December 10, 2010, Table 2 on page 5.
At the December 14 hearing, the Navy witnesses defended the Navy’s estimate, stating that it was
based on actual bid data from the two LCS bidders, and that CBO’s estimate did not reflect full
exposure to this bid data, because the data is proprietary and being closely held by the Navy
pending a potential announcement by the Navy of a down select decision (if the dual-award
strategy is not pursued).
Under the down select strategy, shipyards competing to become the second LCS builder could
include yards that currently build other ships for the Navy, such as, possibly, General Dynamics’
Bath Iron Works (GD/BIW) of Bath, ME, Northrop Grumman’s Ingalls shipyard of Pascagoula,
MS, or General Dynamics’ National Steel and Shipbuilding Company (NASSCO) of San Diego,
CA. If such a yard were to be selected under the down select strategy to become the second LCS
builder, it could reduce the cost of other Navy ships being built at that yard by more fully
spreading the fixed overhead costs of that yard. The Navy and CBO estimates in Table F-1 do not
account for possible changes in the costs of other Navy ships that might be occur as a
consequence of changes in the spreading of shipyard fixed overhead costs.
Combat System Modification Costs
Any savings the dual-award strategy might realize relative to the down select strategy in terms of
costs for procuring LCSs could be offset by potential additional costs under the dual-award
strategy for modifying the combat systems on LCSs so as to achieve more commonality in
combat system equipment among all LCSs, and between LCSs and other Navy ships. Prior to its
September 2009 announcement of its proposed down select strategy, Navy officials on some
occasions had spoken about the possibility of modifying the combat systems of one or both LCS
designs so as to achieve more commonality in combat system equipment among all LCSs, and
between LCSs and other Navy ships. 75
A November 29, 2010, press report stated that “the Navy intends to keep separate the combat
systems of the Lockheed and Austal USA versions of the Littoral Combat Ships for its dual buy
strategy, but will ‘procure the tech data package to allow for consideration of [a] common combat
system in the future,’ according to Navy spokeswoman Capt. Cate Mueller.” The report also
quoted an industry official as saying that the Navy is likely “still strategizing as to how they’re
going to single up on a combat system.”76
At the December 14 hearing, the Navy stated the following regarding the issue of potential
combat system modification costs:
The current [LCS] acquisition strategy does not call for the changeout of the [LCS] combat
system.

75 See, for example, Christopher P. Cavas, “Two LCS Designs, One Big Dilemma,” Defense News, December 13,
2010: 22.
76 Andrew Burt, “Navy Open To Combining Combat Systems On Both Littoral Combat Ships,” Inside the Navy,
November 29, 2010. Material in brackets as in original. The Austal USA version of the LCS is the version developed
by the General Dynamics-led LCS industry team.
Congressional Research Service
64

Navy Littoral Combat Ship (LCS) Program

Let me describe some characteristics of the combat system. As it was mentioned earlier, the
total cost for the [LCS] combat system is on the order of about $70 million. When we think
of the combat system, we break it down into a couple key components – weapons, sensors,
and command and control [aka command and decision, or C and D] system. We have in fact,
on the weapons side of the combat system, commonality [between the two LCS designs].
Both ships’ 57-millimeter Bofors guns, both ships we’re looking at RAM–CRAM [sic: RAM
or SEARAM] weapons systems. So the weapon system is already common both between
them and also with other ships in the inventory.
Now, on the sensor side, we have contemplated moving towards a common sensor, and
inside of this solicitation the Navy asked for priced bids for a new sensor to consider for the
future. In total, the cost for bringing a new sensor—that’s both common for LCS and with
the rest of the fleet—is about $20 million nonrecurring and about $2 million a ship
difference.
So weapons are common. If the Navy chose to go to a common system for performance
reasons, the cost impact would be about $20 million nonrecurring and a couple million
dollars a ship.
Then on the C and D side, which is largely the software system and displays and processors,
the Navy does not have a drive right now to go towards common C and D for this class either
in the down-select or dual-award. It is something that we could consider in the future.77
A January 17, 2011, press report stated:
“The median class size in the Navy is about 12 to 14 ships, so we have a lot of 12-ship
classes that have their own combat system,” [Rear Admiral David Lewis, the Navy’s
program executive officer for ships,] said, “so we have no plans on changing the combat
system on the ships. They're effective. At this point, they meet the requirements, and so I
don't see any appetite in the Navy for changing those.”…
Lewis admitted that the business case could change after the two 10-ship contracts have run
their course, but said he was skeptical it would make more sense to change combat systems
then than now.78
Life-Cycle Operation and Support (O&S) Costs
Any savings the dual-award strategy might realize relative to the down select strategy in terms of
costs for procuring LCSs could also be offset by potential additional life-cycle operation and
support (O&S) costs of operating significant numbers of two different LCS designs. A December
8, 2010, GAO report states: “According to the Navy, [estimated savings in LCS procurement
costs under the dual-award strategy] would be offset, in part, by an additional $842 million in
total ownership costs, which the Navy equates to a net present value of $295 million.”79 The
Navy confirmed this figure at the December 14 hearing, and stated that this estimate was
carefully prepared and consistent with past Navy analyses on this question.

77 Transcript of spoken testimony of Sean J. Stackley, Assistant Secretary of Navy for Research, Development, and
Acquisition.
78 Cid Standifer, “Rear Adm. Lewis: Navy Has ‘No Appetite’ To Change LCS Combat System,” Inside the Navy,
January 17, 2011.
79 Government Accountability Office, Navy’s Proposed Dual Award Acquisition Strategy for the Littoral Combat Ship
Program
, GAO-11-249R, December 8, 2010, Table 1 on page 3.
Congressional Research Service
65

Navy Littoral Combat Ship (LCS) Program

GAO’s December 8 report states:
Navy officials expressed confidence that their cost estimate supporting the dual award
provides details on the costs to operate and support both designs. However, since little actual
LCS operating and support data are available to date, the Navy’s estimates for these costs are
currently based on data from other ships and could change as actual cost data become more
available. These estimates are also based on new operational concepts for personnel, training,
and maintenance that have not been fully developed, tested, and implemented. For example,
the Navy has not yet implemented a comprehensive training plan, and it is possible that the
plan could cost more or less than the training costs currently accounted for by the Navy. 80
CBO’s December 10 letter report states:
Operating and maintaining two types of ships would probably be more expensive, however.
The Navy has stated that the differences in costs are small (and more than offset by
procurement savings), but there is considerable uncertainty about how to estimate those
differences because the Navy does not yet have much experience in operating such ships.81
Resulting Net Costs
Using the above information, it appears that the Navy estimates that, compared to the down select
strategy, the dual award strategy might save a net total of $615 million (net present value) through
FY2016, or $201 million (net present value) through FY2015. This figure includes $910 million
(net present value) in savings in ship procurement costs through FY2016, or $496 million (net
present value) in ship procurement costs through FY2015, less $295 million (net present value) in
additional ship O&S costs.
This figure does not account for possible changes in the costs of other Navy ships that might be
occur as a consequence of changes in the spreading of shipyard fixed overhead costs. The
estimated net savings of $615 million (net present value) through FY2016 ($201 million [net
present value] through FY2015) would be reduced by any LCS combat system modification
costs. Navy testimony at the December 14 hearing suggests that combat system modification
costs might range from zero (no modifications) to a few tens of millions of dollars (changing the
radar on the ships).
Using CBO’s estimate rather than the Navy’s estimate for relative ship procurement costs (see
Table F-1) would make the dual-award strategy more expensive than the down select strategy. As
mentioned earlier, the Navy witnesses at the December 14 hearing defended the Navy’s estimate
of ship procurement costs, stating that it was based on actual bid data from the two LCS bidders,
and that CBO’s estimate did not reflect full exposure to this bid data, because the data is
proprietary and being closely held by the Navy pending a potential announcement by the Navy of
a down select decision (if the dual-award strategy is not pursued).

80 Government Accountability Office, Navy’s Proposed Dual Award Acquisition Strategy for the Littoral Combat Ship
Program
, GAO-11-249R, December 8, 2010, p. 6.
81 Congressional Budget Office, letter report to Senator John McCain on LCS acquisition strategies dated December 10,
2010, p. 3.
Congressional Research Service
66

Navy Littoral Combat Ship (LCS) Program

Relative Risks
Regarding the potential relative risks of the down select and dual-award acquisition strategies, the
December 8 GAO report states that “a second ship design and source provided under the dual
award strategy could provide the Navy an additional hedge against risk, should one design prove
problematic.”82 It might also be argued that the dual-award strategy avoids the construction risks
present under the down select strategy of having LCSs built by a shipyard that has not previously
built LCSs.
On the other hand, it might be argued that if there is a substantial risk of an LCS design proving
problematic, then the LCS program should not be put into series production in the first place, and
that if there is not a substantial risk of an LCS design proving problematic, then the value of
hedging against that risk would be negligible. It might also be argued that managing the
construction of two very different LCS designs could place increased demands on overall Navy
program management capacities and on the Navy’s Supervisor of Shipbuilding (SUPSHIP)
capabilities for on-site monitoring of the construction of Navy ships—factors that might increase
the chances of program-management challenges in the LCS program or of the Navy not detecting
in a timely manner construction-quality problems that might occur in one or both LCS designs.83

Author Contact Information

Ronald O'Rourke

Specialist in Naval Affairs
rorourke@crs.loc.gov, 7-7610



82 Government Accountability Office, Navy’s Proposed Dual Award Acquisition Strategy for the Littoral Combat Ship
Program
, GAO-11-249R, December 8, 2010, p. 4.
83 Limits on Navy SUPSHIP capacities may have been a factor in the delayed discovery by the Navy of construction
quality problems on Navy San Antonio (LPD-17) class amphibious ships. For a discussion of LPD-17 class
construction quality problems, CRS Report RL34476, Navy LPD-17 Amphibious Ship Procurement: Background,
Issues, and Options for Congress
, by Ronald O'Rourke.
Congressional Research Service