Navy Ford (CVN-78) Class Aircraft Carrier
Program: Background and Issues for Congress

Ronald O'Rourke
Specialist in Naval Affairs
January 21, 2011
Congressional Research Service
7-5700
www.crs.gov
RS20643
CRS Report for Congress
P
repared for Members and Committees of Congress

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Summary
CVN-78, CVN-79, and CVN-80 are the first three ships in the Navy’s new Gerald R. Ford (CVN-
78) class of nuclear-powered aircraft carriers (CVNs).
CVN-78 was procured in FY2008 and is being funded with congressionally authorized four-year
incremental funding in FY2008-FY2011. The Navy’s proposed FY2011 budget estimated the
ship’s procurement cost at $11,531.0 million (i.e., about $11.5 billion) in then-year dollars, and
requested $1,731.3 million in procurement funding as the final increment to complete this
estimated procurement cost.
CVN-79 is scheduled for procurement in FY2013, and has received advance procurement funding
since FY2007. The Navy’s proposed FY2011 budget estimated the ship’s procurement cost at
$10,413.1 million (i.e., about $10.4 billion) in then-year dollars and requested $908.3 million in
advance procurement funding for the ship.
CVN-80 is scheduled for procurement in FY2018, with advance procurement funding scheduled
to begin in FY2014. The Navy’s proposed FY2011 budget estimated the ship’s procurement cost
at $13,577.0 million (i.e., about $13.6 billion) in then-year dollars.
On April 6, 2009, Secretary of Defense Robert Gates announced a number of recommendations
he was making for the FY2010 defense budget. One of these was to shift procurement of carriers
to five-year intervals. This recommendation effectively deferred the scheduled procurement of
CVN-79 from FY2012 to FY2013, and the scheduled procurement of CVN-80 from FY2016 to
FY2018. Secretary of Defense Robert Gates stated on April 6, 2009, that shifting carrier
procurement to five-year intervals would put carrier procurement on “a more fiscally sustainable
path.”
Potential oversight issues for Congress for the CVN-78 program include the following:
• Did shifting carrier procurement to five-year intervals put carrier procurement on
a more fiscally sustainable path?
• What is the likelihood that the estimated procurement costs of CVNs 78, 79, and
80 will increase from current estimates?
Congressional Research Service

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Contents
Introduction ................................................................................................................................ 1
Background ................................................................................................................................ 1
The Navy’s Aircraft Carrier Force ......................................................................................... 1
Aircraft Carrier Construction Industrial Base......................................................................... 2
Gerald R. Ford (CVN-78) Class Program .............................................................................. 2
CVN-78 .......................................................................................................................... 2
CVN-79 .......................................................................................................................... 3
CVN-80 .......................................................................................................................... 3
Procurement Funding ...................................................................................................... 3
Increase in Estimated Unit Procurement Costs................................................................. 4
Procurement Cost Cap..................................................................................................... 6
Issues for Congress ..................................................................................................................... 6
Shift to Five-Year Intervals: A More Fiscally Sustainable Path?............................................. 6
May 2009 Northrop Grumman Shipbuilding Statement ................................................... 7
March 2010 GAO Report ................................................................................................ 8
March 2010 Navy Report Required by Section 126 ......................................................... 8
June 30, 2010, Selected Acquisition Report (SAR) .......................................................... 9
Navy Data Provided to CRS and CBO on June 24, 2010................................................ 10
Potential for Additional Growth in Estimated Procurement Costs ........................................ 11
June 30, 2010, Selected Acquisition Report ................................................................... 11
May 2010 CBO Report ................................................................................................. 11
March 2010 GAO Report .............................................................................................. 12
Technical and Design Issues—December 2010 DOT&E Report .......................................... 13
Legislative Activity for FY2012 ................................................................................................ 14

Tables
Table 1. Procurement Funding for CVNs 78, 79, and 80 .............................................................. 4
Table 2. Estimated Procurement Costs of CVNs 78, 79, and 80 ................................................... 5
Table 3. Cost Impact of Shifting to Five-year Intervals .............................................................. 10

Appendixes
Appendix A. Legislative Activity for FY2011............................................................................ 15
Appendix B. Text of Navy Report on Effects of Shifting to Five-Year Intervals ......................... 17
Appendix C. July 16, 2009, Hearing on EMALS ....................................................................... 21

Contacts
Author Contact Information ...................................................................................................... 26
Congressional Research Service

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Introduction
CVN-78, CVN-79, and CVN-80 are the first three ships in the Navy’s new Gerald R. Ford (CVN-
78) class of nuclear-powered aircraft carriers (CVNs).
CVN-78 was procured in FY2008 and is being funded with congressionally authorized four-year
incremental funding in FY2008-FY2011. The Navy’s proposed FY2011 budget estimated the
ship’s procurement cost at $11,531.0 million (i.e., about $11.5 billion) in then-year dollars, and
requested $1,731.3 million in procurement funding as the final increment to complete this
estimated procurement cost.
CVN-79 is scheduled for procurement in FY2013, and has received advance procurement funding
since FY2007. The Navy’s proposed FY2011 budget estimated the ship’s procurement cost at
$10,413.1 million (i.e., about $10.4 billion) in then-year dollars and requested $908.3 million in
advance procurement funding for the ship.
CVN-80 is scheduled for procurement in FY2018, with advance procurement funding scheduled
to begin in FY2014. The Navy’s proposed FY2011 budget estimated the ship’s procurement cost
at $13,577.0 million (i.e., about $13.6 billion) in then-year dollars.
On April 6, 2009, Secretary of Defense Robert Gates announced a number of recommendations
he was making for the FY2010 defense budget. One of these was to shift procurement of carriers
to five-year intervals. This recommendation effectively deferred the scheduled procurement of
CVN-79 from FY2012 to FY2013, and the scheduled procurement of CVN-80 from FY2016 to
FY2018. Secretary of Defense Robert Gates stated on April 6, 2009, that shifting carrier
procurement to five-year intervals would put carrier procurement on “a more fiscally sustainable
path.”1
Potential oversight issues for Congress for the CVN-78 program include the following:
• Did shifting carrier procurement to five-year intervals put carrier procurement on
a more fiscally sustainable path?
• What is the likelihood that the estimated procurement costs of CVNs 78, 79, and
80 will increase from current estimates?
Background
The Navy’s Aircraft Carrier Force
The Navy’s aircraft carrier force consists of 11 nuclear-powered ships—the one-of-a-kind
Enterprise (CVN-65) and 10 Nimitz-class ships (CVNs 68 through 77). The most recently
commissioned carrier, the George H. W. Bush (CVN-77), the final Nimitz-class ship, was

1 Source: Statement of Secretary of Defense Robert Gates, at April 6, 2009, news conference on his recommendations
for the FY2010 defense budget.
Congressional Research Service
1

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

procured in FY2001 and commissioned into service on January 10, 2009.2 CVN-77 replaced the
Kitty Hawk (CV-63), which was the Navy’s last remaining conventionally powered carrier.3
Aircraft Carrier Construction Industrial Base
All U.S. aircraft carriers procured since FY1958 have been built by the Newport News, VA,
shipyard that forms part of Northrop Grumman Shipbuilding (NGSB). NGSB’s Newport News
yard is the only U.S. shipyard that can build large-deck, nuclear-powered aircraft carriers. The
aircraft carrier construction industrial base also includes hundreds of subcontractors and suppliers
in dozens of states.
Gerald R. Ford (CVN-78) Class Program
The Gerald R. Ford (CVN-78) class carrier design is the successor to the Nimitz-class carrier
design.4 Compared to the Nimitz-class design, the Ford-class design will incorporate several
improvements, including an ability to generate substantially more aircraft sorties per day and
features permitting the ship to be operated by several hundred fewer sailors than a Nimitz-class
ship, significantly reducing life-cycle operating and support costs. Navy plans call for procuring
at least three Ford-class carriers—CVN-78, CVN-79, and CVN-80.
CVN-78
CVN-78, which was named in 2007 for President Gerald R. Ford,5 was procured in FY2008 and
is being funded with congressionally authorized four-year incremental funding in FY2008-
FY2011.6 The Navy’s proposed FY2011 budget estimated the ship’s procurement cost at
$11,531.0 million (i.e., about $11.5 billion) in then-year dollars, and requested $1,731.3 million in
procurement funding as the final increment to complete this estimated procurement cost.
CVN-78 is scheduled to enter service as the replacement for Enterprise (CVN-65). The Navy
projects that there will be a 33-month period between the scheduled decommissioning of

2 Congress approved $4,053.7 million in FY2001 procurement funding to complete CVN-77’s then-estimated total
procurement cost of $4,974.9 million. Section 122 of the FY1998 defense authorization act (H.R. 1119/P.L. 105-85 of
November 18, 1997) limited the ship’s procurement cost to $4.6 billion, plus adjustments for inflation and other
factors. The Navy testified in 2006 that with these permitted adjustments, the cost cap stood at $5.357 billion. The
Navy also testified that CVN-77’s estimated construction cost had increased to $6.057 billion, or $700 million above
the adjusted cost cap. Consequently, the Navy in 2006 requested that Congress increase the cost cap to $6.057 billion.
Congress approved this request: Section 123 of the FY2007 defense authorization act (H.R. 5122/P.L. 109-364 of
October 17, 2006), increased the cost cap for CVN-77 to $6.057 billion.
3 The Kitty Hawk was decommissioned on January 31, 2009.
4 The CVN-78 class was earlier known as the CVN-21 class, which meant nuclear-powered aircraft carrier for the 21st
century.
5 Section 1012 of the FY2007 defense authorization act (H.R. 5122/P.L. 109-364 of October 17, 2006) expressed the
sense of the Congress that CVN-78 should be named for President Gerald R. Ford. On January 16, 2007, the Navy
announced that CVN-78 would be so named. CVN-78 and other carriers built to the same design will consequently be
referred to as Ford (CVN-78) class carriers. For further discussion of Navy ship names, see CRS Report RS22478,
Navy Ship Names: Background for Congress, by Ronald O’Rourke.
6 Section 121 of the FY2007 defense authorization act (H.R. 5122/P.L. 109-364 of October 17, 2006) granted the Navy
the authority to use four-year incremental funding for CVN-78, CVN-79, and CVN-80.
Congressional Research Service
2

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Enterprise in November 2012 and the scheduled commissioning of CVN-78 in September 2015.
During this 33-month period, the Navy’s carrier force is to temporarily decline from 11 ships to
10 ships. Since 10 USC 5062(b) requires the Navy to maintain a force of at least 11 operational
carriers, the Navy asked Congress for a temporary waiver of 10 USC 5062(b) to accommodate
the 33-month period between the scheduled decommissioning of Enterprise and the scheduled
commissioning of CVN-78. Section 1023 of the FY2010 defense authorization act (H.R.
2647/P.L. 111-84 of October 28, 2009) authorizes the waiver and requires the Secretary of
Defense to submit a report on the operational risk of temporarily reducing the size of the carrier
force.
CVN-79
CVN-79 is scheduled for procurement in FY2013, and has received advance procurement funding
since FY2007. The Navy’s proposed FY2011 budget estimated the ship’s procurement cost at
$10,413.1 million (i.e., about $10.4 billion) in then-year dollars and requested $908.3 million in
advance procurement funding for the ship.
In the FY2009 budget, CVN-79 was scheduled to be procured in FY2012. On April 6, 2009,
Secretary of Defense Robert Gates announced a number of recommendations he was making for
the FY2010 defense budget. One of these was to shift procurement of carriers to five-year
intervals. Since CVN-78 was procured in FY2008, this recommendation effectively deferred the
scheduled procurement of CVN-79 from FY2012 to FY2013. Secretary of Defense Robert Gates
stated that shifting carrier procurement to five-year intervals would put carrier procurement on “a
more fiscally sustainable path.”7
CVN-80
CVN-80 is scheduled for procurement in FY2018, with advance procurement funding scheduled
to begin in FY2014. The Navy’s proposed FY2011 budget estimated the ship’s procurement cost
at $13,577.0 million (i.e., about $13.6 billion) in then-year dollars. Secretary of Defense Gates’
April 2009 recommendation to shift carrier procurement to five-year intervals (see above
discussion of CVN-79) effectively deferred the procurement of CVN-80 from FY2016 to
FY2018.
Procurement Funding
Table 1 shows procurement funding for CVNs 78, 79, and 80. Each ship is being procured with
several years of advance procurement funding, followed by four-year incremental procurement
funding of the remainder of the ship’s cost.8 The funding profile for CVN-78, for example,
includes advance procurement funding in FY2001-FY2007, followed by four years of
incremental procurement funding in FY2008-FY2011.

7 Source: Statement of Secretary of Defense Robert Gates, at April 6, 2009, news conference on his recommendations
for the FY2010 defense budget.
8 As mentioned earlier, Section 121 of the FY2007 defense authorization act (H.R. 5122/P.L. 109-364 of October 17,
2006) granted the Navy the authority to use four-year incremental funding for CVN-78, CVN-79, and CVN-80.
Congressional Research Service
3

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Table 1. Procurement Funding for CVNs 78, 79, and 80
(Millions of then-year dollars, rounded to nearest tenth)
FY
CVN-78 CVN-79 CVN-80 Total
FY01 21.7 0 0 21.7
FY02 135.3 0 0 135.3
FY03 395.5 0 0 395.5
FY04 1,162.9 0
0 1,162.9
FY05 623.1 0 0 623.1
FY06 618.9 0 0 618.9
FY07 735.8 52.8 0 788.6
FY08 2,685.0
123.5 0 2,808.6
FY09 2,684.6
1,210.6 0 3,895.1
FY10 737.0
482.9 0 1,219.9
FY11 (requested)
1,731.3
908.3
0
2,639.6
FY12 (projected)
0
494.8
0
494.8
FY13
(projected)
0 2,418.3 0 2,418.3
FY14
(projected) 0 3,158.5 228.1 3,386.6
FY15 (projected)
0
760.7
1,523.8
2,284.5
Source: FY2009, FY2010, and FY2011Navy budget submissions.
Note: Figures may not add due to rounding.
Increase in Estimated Unit Procurement Costs
As shown in Table 2, the estimated procurement costs of CVNs 78, 79, and 80 in the FY2011
budget submission are 10.3%, 13.3%, and 26.7% higher, respectively, in then-year dollars than
those in the FY2009 budget submission.9

9 CBO in 2008 and the Government Accountability Office (GAO) in 2007 questioned the accuracy of the Navy’s cost
estimate for CVN-78. CBO reported in June 2008 that it estimated that CVN-78 would cost $11.2 billion in constant
FY2009 dollars, or about $900 million more than the Navy’s estimate of $10.3 billion in constant FY2009 dollars, and
that if “CVN-78 experienced cost growth similar to that of other lead ships that the Navy has purchased in the past 10
years, costs could be much higher still.” CBO also reported that, although the Navy publicly expressed confidence in its
cost estimate for CVN-78, the Navy had assigned a confidence level of less than 50% to its estimate, meaning that the
Navy believed there was more than a 50% chance that the estimate would be exceeded. (Congressional Budget Office,
Resource Implications of the Navy’s Fiscal Year 2009 Shipbuilding Plan, June 9, 2008, p. 20.) GAO reported in August
2007 that:
Costs for CVN 78 will likely exceed the budget for several reasons. First, the Navy’s cost estimate,
which underpins the budget, is optimistic. For example, the Navy assumes that CVN 78 will be
built with fewer labor hours than were needed for the previous two carriers. Second, the Navy’s
target cost for ship construction may not be achievable. The shipbuilder’s initial cost estimate for
construction was 22 percent higher than the Navy’s cost target, which was based on the budget.
Although the Navy and the shipbuilder are working on ways to reduce costs, the actual costs to
build the ship will likely increase above the Navy’s target. Third, the Navy’s ability to manage
issues that affect cost suffers from insufficient cost surveillance. Without effective cost
surveillance, the Navy will not be able to identify early signs of cost growth and take necessary
(continued...)
Congressional Research Service
4

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Table 2. Estimated Procurement Costs of CVNs 78, 79, and 80
(As shown in FY2009, FY2010, and FY2011 budgets, in millions of then-year dollars)
Budget CVN-78
CVN-79
CVN-80
Estimated
Scheduled
Estimated
Scheduled
Estimated
Scheduled
procurement
fiscal year of
procurement
fiscal year of
procurement
fiscal year of

cost
procurement
cost
procurement
cost
procurement
FY09
budget
10,457.9 FY08 9,191.6 FY12 10,716.8 FY16
FY10 budget
10,845.8
FY08
n/aa FY13b n/aa FY18b
FY11
budget
11,531.0 FY08 10,413.1 FY13 13,577.0 FY18
%
increase:

FY09 budget
3.7 n/a n/a
to FY10 budget
FY10 budget to
6.3 n/a n/a
FY11 budget
FY09 budget to
10.3 13.3 26.7
FY11 budget
Source: FY2009, FY2010, and FY2011Navy budget submissions.
a. n/a means not available; the FY2010 budget submission did not show estimated procurement costs for
CVNs 79 and 80.
b. The FY2010 budget submission did not show scheduled years of procurement for CVNs 79 and 80; the
dates shown here for the FY2010 budget submission are inferred from the shift to five-year intervals for
procuring carriers that was announced by Secretary of Defense Gates in his April 6, 2009, news conference
regarding recommendations for the FY2010 defense budget.
The increases in the estimated procurement costs of CVNs 78, 79, and 80 since the FY2009
budget submission have at least four potential causes:
• one additional year of inflation being incorporated into the cost of CVN-79 as a
result of its scheduled procurement being deferred from FY2012 to FY2013, and
two years of additional inflation being incorporated into the cost of CVN-80 as a
result of its scheduled procurement being deferred from FY2016 to FY2018;
• increases in projected annual rates of inflation;

(...continued)
corrective action.
(Government Accountability Office, Defense Acquisitions[:] Navy Faces Challenges Constructing
the Aircraft Carrier Gerald R. Ford within Budget, GAO-07-866, August 2007, summary page. See
also Government Accountability Office, Defense Acquisitions[:] Realistic Business Cases Needed
to Execute Navy Shipbuilding Programs, Statement of Paul L. Francis, Director, Acquisition and
Sourcing Management Team, Testimony Before the Subcommittee on Seapower and Expeditionary
Forces, Committee on Armed Services, House of Representatives, July 24, 2007 (GAO-07-943T),
p. 15.)
Congressional Research Service
5

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

• higher estimates of real (i.e., inflation-adjusted) material costs, real labor rates, or
labor hours (given a certain position on the production learning curve) for
building CVN-78 class carriers; and
• increased costs due to loss of learning and reduced spreading of fixed overhead
costs resulting from shifting to five-year intervals for procuring carriers.
Procurement Cost Cap
Section 122 of the FY2007 defense authorization act (H.R. 5122/P.L. 109-364 of October 17,
2006) established a procurement cost cap for CVN-78 of $10.5 billion, plus adjustments for
inflation and other factors, and a procurement cost cap for subsequent Ford-class carriers of $8.1
billion each, plus adjustments for inflation and other factors. The conference report (H.Rept. 109-
702 of September 29, 2006) on P.L. 109-364 discusses Section 122 on pages 551-552.
The Navy on February 19, 2010, notified the congressional defense committees that, after making
permitted adjustments in the cost cap for inflation and other factors, the estimated cost of CVN-
78 is $224 million below the cost cap for that ship.10 The Navy on April 19, 2010, informed CRS
and the Congressional Budget Office (CBO) that, after making permitted adjustments in the cost
cap for inflation and other factors, the estimated costs of CVN-79 and CVN-80 each remain
several hundred million dollars below the cost cap for those ships.11
Issues for Congress
Potential oversight issues for Congress for the CVN-78 program include the following:
• Did shifting carrier procurement to five-year intervals put carrier procurement on
a more fiscally sustainable path?
• What is the likelihood that the estimated procurement cost of CVN-78, CVN-79,
or CVN-80 will increase from current estimates?
Each of these issues is discussed below.
Shift to Five-Year Intervals: A More Fiscally Sustainable Path?
As mentioned earlier, when Secretary of Defense Gates announced on April 6, 2009, that he was
recommending that carrier procurement be shifted to five-year intervals, he stated that this would
put carrier procurement on “a more fiscally sustainable path.” This was interpreted as meaning
that shifting to five-year intervals (compared to a combination of four- and five-year intervals in
previous Navy 30-year shipbuilding plans) would reduce the average amount of funding required
each year for procuring carriers.

10 Source: Letter dated February 19, 2010, from Secretary of the Navy Ray Mabus to the chairmen of the House and
Senate Armed Services committees and the Defense subcommittees of the House and Senate Appropriations
Committees. Copy of letter provided by the Navy to CRS and the Congressional Budget Office (CBO) on April 19,
2010.
11 Source: April 19, 2010, Navy briefing on the CVN-78 program to CRS and CBO.
Congressional Research Service
6

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

As a simplified notional example, if carriers are assumed to cost $10 billion each, then shifting
from a four-year interval to a five-year interval would reduce the average amount of carrier
procurement funding needed each year from $2.5 billion to $2.0 billion, a reduction of $500
million per year.
This simplified notional example, however, assumes that shifting from four- to five-year intervals
does not by itself cause an increase in the real (i.e., inflation-adjusted) procurement cost of the
carriers. Increasing the procurement interval could by itself cause an increase in the real
procurement cost of the carriers by reducing learning-curve benefits (i.e., causing a loss of
learning) from one carrier to the next, and by reducing the spreading of fixed overhead costs at
the Newport News shipyard and at supplier firms. A real increase in carrier procurement costs due
to such effects would offset at least some of the reduction in the average amount of carrier
procurement funding needed each year that would result from shifting to five-year intervals.
Shifting to five-year intervals for procuring carriers could also increase the costs of other Navy
ship programs. NGSB’s Newport News shipyard performs mid-life nuclear refueling complex
overhauls (RCOHs) on Nimitz-class carriers, and jointly builds Virginia-class nuclear-powered
attack submarines along with another shipyard (General Dynamics’ Electric Boat Division). In
addition, vendors that make nuclear-propulsion components for carriers make analogous
components for nuclear-powered submarines. A reduced spreading of fixed costs at NGSB’s
Newport News yard and at nuclear-propulsion component vendors due to the shift to five-year
intervals for carrier procurement might thus also increase costs for Nimitz-class RCOHs and
Virginia-class submarines. Increases in costs for these programs would further offset the
reduction in the average amount of carrier procurement funding needed each year that would
result from shifting to five-year intervals for carrier procurement.
Potential key oversight questions for Congress for FY2011 include the following:
• How much of the increase since the FY2009 budget submission in the estimated
procurement costs of CVNs 78, 79, and 80 (see Table 2) is due to the shift to
five-year intervals for procuring carriers?
• How do potential increases in the costs of CVN-78 class aircraft carriers, Nimitz-
class RCOHs, and Virginia-class submarines caused by the shift to five-year
intervals for procuring carriers affect the calculation of the net change in average
annual funding requirements that results from shifting carrier procurement to
five-year intervals?
May 2009 Northrop Grumman Shipbuilding Statement
A May 2009 Northrop Grumman Shipbuilding statement on the cost impact of shifting to five-
year intervals for procuring carriers states:
One element of the announcement by the Secretary of Defense last week was to shift from
four (4) years to five (5) years between construction start for each new Ford Class carrier.
Past Northrop Grumman Shipbuilding experience with carrier new construction has shown
that the optimum time between carrier construction is less than 4 years. This allows the most
efficient flow of the work force from one ship to the next, and facilitates a learning curve for
carriers. Moving to five (5) year intervals between starts will require the shipyard to sub-
optimize manning level sequencing and result in added trade training, loss of learning, and
added startup costs.
Congressional Research Service
7

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Increasing the time between carrier construction can have a large impact on the supplier
base, driving cost increases of 5-10 percent, or higher in some cases, above normal
escalation. Material costs of suppliers who provide similar components to other Navy
programs currently under contract will also experience cost growth. Some equipment
suppliers can be expected to exit the market as a result of the additional year with the
expense of component requalification being realized.
Finally, the decrease in production labor volume on an annual basis, created by the increase
in the time interval between carrier construction starts will increase the cost to other
programs in the yard. This applies to work already under contract, namely Virginia class
submarines (VCS) Block 2 and Block 3, and CVN 78 predominately; and for future work not
yet under contract, namely Carrier RCOH’s, CVN79 and follow-on Ford class carrier
construction, and later Blocks of VCS. The impact to work already under contract is
expected to be in the range of $100M of cost growth. We also expect cost increases for
future contracts yet to be priced. Conservative projections of the shipbuilder cost impact to
CVN 79 and CVN80 for the one year delay will be on the order of a 9-15 percent cost
increase.12
March 2010 GAO Report
A March 2010 Government Accountability Office (GAO) report stated that if carrier procurement
were shifted to five-year intervals, “the fabrication start date for CVN 80 will be delayed by 2
years, which will increase the amount of shipyard overhead costs paid under the CVN 79
contract.”13
March 2010 Navy Report Required by Section 126
Section 126 of the FY2010 defense authorization act (H.R. 2647/P.L. 111-84 of October 28,
2009) required the Secretary of the Navy to submit a report to the congressional defense
committees on the effects of using a five-year interval for the construction of Ford-class aircraft
carriers. The conference report (H.Rept. 111-288 of October 7, 2009) on H.R. 2647/P.L. 111-84
stated the following regarding Section 126:
The conferees note that a 5-year interval for aircraft carrier construction, as proposed by the
Secretary of Defense, may be the appropriate course of action for the Department of the
Navy. However, the conferees are concerned that this decision may not have been made
following a rigorous cost-benefit analysis. Therefore, the conferees expect that the Secretary
of the Navy will take no further action to preclude the ability of the Secretary to award a
construction contract for CVN–79 in fiscal year 2012 or the aircraft carrier designated CVN–
80 in fiscal year 2016, consistent with the Annual Long-Range Plan for Construction of
Naval Vessels for Fiscal Year 2009, until he completes the required assessment and fully
informs the congressional defense committees of any such a decision. (Page 680)
The Navy submitted the report on March 4, 2010.14 The report states, among other things, that

12 Northrop Grumman Shipbuilding statement dated May 1, 2009, entitled “NGSB Statement Regarding Extending the
Time Interval between New Build Starts For the Ford Class of Aircraft Carriers,” provided to CRS by Northrop
Grumman.
13 Government Accountability Office, Defense Acquisitions[:] Assessments of Selected Weapon Programs, GAO-10-
388SP, March 2010, p. 54.
14 This is the date of the cover letters to the congressional recipients. The report itself has a cover date of February
(continued...)
Congressional Research Service
8

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

• “It is reasonable to assume that some vendor base inefficiencies, in addition to
inflation may occur by increasing CVN build intervals to five years.”
• “While a five-year interval between carrier construction starts will result in
potential inefficiencies and gaps for specific carrier construction trade skills, the
Navy plans to closely manage the transition to 5-year centers to minimize the
impact of this change on training of individuals required to support ship
construction.”
• “The Navy estimated that a four-year build interval would maximize the
opportunity to achieve labor efficiencies due to learning. A five-year build
interval reduces this opportunity; however, the overall impact for loss of learning
associated with a shift to five-year centers is manageable through Advance
Procurement and Advance Construction.”
• “The Navy assessed the NIMITZ Class cost returns for shipbuilder labor and
material and GFE to determine the correlation between these cost elements and
the number of years between carrier awards. The Navy estimates that impact to
Basic Construction is around 1.0% for CVN 79 and CVN 80.”
• “The change to five-year build intervals results in an overhead decrease in direct
labor workload for aircraft carrier construction, thereby causing the overhead
rates to increase proportionately. The Navy estimates the construction portion
increase is less than 1% each for CVN 78, CVN 79 and CVN 80.”
• “The impact of changing the interval between carrier awards to the VIRGINIA
Class submarine current Block II and Block III contracts is estimated to be $30-
50 million per hull.”15
The report does not provide an overall dollar calculation of how much of the increase since the
FY2009 budget submission in the estimated procurement costs of CVNs 78, 79, and 80 is due to
the shift to five-year intervals for procuring carriers. Virginia-class submarines are scheduled to
be procured at a rate of two ships per year starting FY2011. If the cost increase of $30 million to
$50 million for each Virginia-class boat cited in the Navy’s report holds for Virginia-class boats
procured in FY2011 and subsequent years, then the shift to five-year intervals for procuring
carriers would increase Virginia-class procurement costs by $60 million to $100 million per year.
For the text of the Navy’s report, see Appendix B.
June 30, 2010, Selected Acquisition Report (SAR)
The Department of Defense’s (DOD’s) June 30, 2010, Selected Acquisition Report (SAR) for the
CVN-78 program states that the estimated increase in Ford-class procurement costs resulting
from shifting to five-year intervals for procuring carriers is $1,798.0 million in then-year dollars,
consisting of $521.0 million for CVN-79 and $1,277.0 million for CVN-80.16 The June 30, 2010,
SAR states that these two figures are a “clarification” of figures presented in the December 31,

(...continued)
2010.
15 Department of the Navy, Report to Congress on Effects of Five-year Build Intervals for Force Class Aircraft
Carriers
, February 2010, 5 pp. Copy provided to CRS by Navy Office of legislative Affairs on April 8, 2010.
16 Department of Defense, Selected Acquisition Report (SAR), CVN-78, As of June 30, 2010, p. 26.
Congressional Research Service
9

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

2009, SAR. The December 31, 2009, SAR estimated the increase at $4,131.2 million in then-year
dollars, consisting of $1,131.4 million for CVN-79 and $2,999.8 million CVN-80, but also stated
that these figures were “overstated, and will be corrected in the June 2010 SAR.”17 The difference
between the June 30, 2010, SAR, and the December 31, 2009, SAR regarding the estimated
increase in procurement costs resulting from shifting to five-year intervals for procuring carriers
(i.e., $4,131.2 million minus $1,798.0 million) is $2,333.2 million. The June 30, 2010, SAR re-
attributes a net total of $2,333.2 million in estimated cost increases to factors other than shifting
to five-year intervals for procuring carriers, and reports total estimated procurement costs for
CVN-79 and CVN-80 that are the same as those reported in the December 31, 2009, SAR.
Neither the June 30, 2010, SAR nor the December 31, 2009, SAR shows an estimated increase in
the procurement cost for CVN-78 resulting from shifting to five-year intervals for procuring
carriers. The figures in the June 30, 2010, SAR are consistent with the Navy-provided figures
presented in Table 3.
Navy Data Provided to CRS and CBO on June 24, 2010
On April 19, 2010, following a Navy briefing to CRS and CBO on the CVN-78 program, CRS
asked the Navy to provide the procurement costs of CVNs 78, 79, and 80 in constant FY2011
dollars as in the proposed FY2011 budget, and what these costs would have been in the proposed
FY2011 budget if there had been no shift to five-year intervals for carrier procurement (i.e., if
CVN-79 were procured in FY2012 and CVN-80 were procured in FY2016). The Navy provided
the figures (in both then-year and constant FY2011 dollars) to CRS and CBO on June 24, 2010.
Table 3 shows the figures.
Table 3. Cost Impact of Shifting to Five-year Intervals
(Millions of dollars, rounded to nearest tenth)
CVN-78
CVN-79
CVN-80
Then-year dollars
Cost in FY2011 budget
11,531.0
10,413.1
13,577.0
What the figure would have been in FY2011 budget if
11,531.0 9,892.1 12,300.0
there had been no shift to five-year intervals
Difference (dollars)
0
521.0
1,277.0
Difference (%)
0
5.3%
10.4%
Constant FY2011 dollars
Cost in FY2011 budget
11,875.9
9,742.3
11,628.5
What the figure would have been in FY2011 budget if
11,875.9 9,396.7 10,872.2
there had been no shift to five-year intervals
Difference (dollars)
0
345.6
756.3
Difference (%)
0
3.7%
7.0%
Source: Briefing slide entitled “CVN 78 Class CBO/CRS Data Request,” dated June 24, 2010, and provided as
an attachment to a Navy information paper dated May 19, 2010. The May 19, 2010, information paper and the
June 24, 2010, attachment were provided to CRS and CBO on June 24, 2010.

17 Department of Defense, Selected Acquisition Report (SAR), CVN-78, As of December 31, 2009, pp. 4 and 25.
Congressional Research Service
10

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Notes: In the scenario assuming there had been no shift to five-year intervals for carrier procurement, CVN-79
would be procured in FY2012 and CVN-80 would be procured in FY2016. The Navy converted then-year dol ars
to constant FY2011 dol ars using a January 2010 SCN (i.e., shipbuilding budget) deflator. FY2011 budget figures
for CVN-80 reflect a CVN-78 program estimate pending official approval from the Naval Sea Systems Command
(NAVSEA).
Potential for Additional Growth in Estimated Procurement Costs
A second potential oversight issue for Congress for the CVN-78 program concerns the likelihood
that the estimated procurement costs of CVNs 78, 79, or 80 will increase from current estimates.
One possible source of additional cost growth in CVN-78 is new technologies that are being
developed for the ship, particularly the electromagnetic aircraft launch system (EMALS)—an
electromagnetic (as opposed to the traditional steam-powered) aircraft catapult. Problems in
developing EMALS or other technologies could delay the ship’s completion and increase its
development and/or procurement cost.
June 30, 2010, Selected Acquisition Report
DOD’s June 30, 2010, Selected Acquisition Report (SAR) for the CVN-78 program states:
Electromagnetic Aircraft Launch System component production remains on schedule to
support CVN 78 construction with subsystems deliveries meeting Required In-Yard Dates.
The first two, of three, phases of the High Cycle Testing are complete. The third phase is
scheduled for completion in September 2010. The first of two phases of the Highly
Accelerated Life Testing is complete. The second phase is planned for a September 2011
completion. System Functional Demonstration is scheduled to begin in September 2010,
with live aircraft launching planned for Late Fall 2010.18
May 2010 CBO Report
A May 2010 CBO report on the potential cost of the Navy’s FY2011 30-year shipbuilding plan
states:
The Navy’s projected cost of the lead ship of the CVN-78 class grew by 10 percent between
the President’s 2008 and 2011 budget requests. The Navy now expects the lead ship’s cost to
be about $11.7 billion (about what CBO estimated in its analysis of the Navy’s 2009 plan).
Yet further increases appear likely. The CVN-78 is only about 10 percent complete, and cost
growth in shipbuilding programs typically occurs when a ship is more than half finished—
particularly in the later stages of construction, when all of a ship’s systems must be installed
and integrated.
To estimate the cost of the lead ship of the CVN-78 class, CBO used the actual costs of the
previous carrier—the CVN-77—and then adjusted them for higher costs for government-
furnished equipment and for more than $3 billion in costs for nonrecurring engineering and
detail design (the plans, drawings, and other one-time items associated with the first ship of a
new class). As a result, CBO estimates that the lead CVN-78 will cost about $12.5 billion
once it is completed. Subsequent ships of the class will not require as much funding for one-
time items; however, on the basis of higher projected inflation in shipbuilding costs, CBO

18 Department of Defense, Selected Acquisition Report (SAR), CVN-78, As of June 30, 2010, p. 7.
Congressional Research Service
11

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

estimates the average cost of the six carriers in the 2011 plan at $12.4 billion, whereas the
Navy estimates their average cost at $10.6 billion….
There are several reasons to believe that the final cost of the CVN-78 could be even higher
than CBO’s estimate. First, most lead ships built in the past 20 years have experienced cost
growth of more than 40 percent. (CBO’s estimate for the lead CVN-78 already accounts for
some of that historical cost growth.) Second, Navy officials have told CBO that there is a 60
percent probability that the final cost of the CVN-78 will exceed the service’s estimate,
compared with a 40 percent probability that the final cost will be less than that estimate.
Third, a number of critical technologies that are supposed to be incorporated into the ship,
such as a new electromagnetic catapult system for launching aircraft, remain under
development. Difficulties in completing their development could arise and increase costs,
which would affect the costs for subsequent ships of the class.19
March 2010 GAO Report
GAO reported the following in March 2010 regarding the status of the CVN-78 program,
including the potential for cost growth:
Technology Maturity
The CVN 21 program has consistently demonstrated the maturity of its critical technologies
later than recommended by best practices. Only 4 of the program’s 19 critical technologies
were mature when the construction preparation contract was awarded in 2004. Of the
program’s 13 current critical technologies, 8 have not been demonstrated in a realistic
environment. Three of these technologies—EMALS, advanced arresting gear, and dual band
radar-present the greatest risk to the ship’s cost and schedule. While CVN 21 program
officials stated that the EMALS program is on schedule to deliver material to the shipyard
when it is needed for construction, concurrent EMALS testing and ship construction
continue to present cost and schedule risks to the program. The Navy completed a second
phase of testing for the EMALS generator—an area of prior concern—and the first phase of
testing for the EMALS launch motor in 2009. As a result of the tests, the program identified
design changes that are necessary to improve the performance of EMALS, but add cost and
schedule risk to the program. The Navy plans to test EMALS with actual aircraft in summer
2010. The advanced arresting gear includes seven major subsystems. Programs officials
expect that six of the subsystems will be mature after analyzing data from a recent reliability
test. The remaining subsystem—control system software—will remain immature until
integrated land-based testing with actual aircraft occurs in fiscal year 2012. This testing will
overlap with the first arresting gear deliveries to the shipyard. Testing of carrier specific dual
band radar functionality is scheduled to conclude in fiscal year 2012. Dual band radar
equipment will be delivered incrementally from fiscal years 2012 through 2014.
Design Maturity
The CVN 78 began construction in September 2008 without a complete product model. The
program began production with approximately 76 percent of the 3D product model complete.
In November 2009, the contractor completed the detail phase in the 3D product model.
However, program officials reported that while the 3D product model is complete, some
product model work will continue up to and after delivery of CVN 78. This additional work

19 Congressional Budget Office, An Analysis of the Navy’s Fiscal Year 2011 Shipbuilding Plan, May 2010, pp. 11-13.
Congressional Research Service
12

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

includes making design adjustments for planned just-in-time technology insertions or for
unplanned delays in contractor or government furnished information.
Production Maturity
The Navy awarded the contract for CVN 78 construction in September 2008. Construction of
approximately 50 percent of the ship’s units are complete. According to program officials,
these units are low on the ship and only account for 9 percent of the ship’s production hours.
The Navy awarded a not-to-exceed fixed-price production contract to General Atomics for
EMALS and the advanced arresting gear in 2009. At the time of award, the contract price
had not been finalized. The Navy expects to finalize the price of this contract in March 2010.
Other Program Issues
The Navy plans to use the dual band radar on both CVN 21 carriers and DDG 1000
destroyers. Given the recent decision to truncate the DDG 1000 program, CVN 21 program
officials stated that the dual band radar production line may be idle for up to 4 years before
production begins for CVN 79. The cost of the CVN 79 dual band radar could increase due
to the costs associated with restarting the production line. In addition, the fiscal year 2010
President’s Budget recommends moving the carrier to a 5-year build cycle. If adopted, the
fabrication start date for CVN 80 will be delayed by 2 years, which will increase the amount
of shipyard overhead costs paid under the CVN 79 contract.
Program Office Comments
The program office generally concurs with the assessment that concurrent technology
development, particularly regarding EMALS, the advanced arresting gear, and the dual-band
radar system, presents the highest programmatic risk. Officials stated that all critical
technologies are being aggressively managed through established processes to mitigate cost,
schedule, and development risk and remain on track to meet required shipbuilder in-yard
need dates.20
The EMALS development effort was the subject of a July 16, 2009, hearing before the Seapower
and Expeditionary Forces subcommittee of the House Armed Services Committee. Materials from
this hearing are presented in the Appendix C.
Technical and Design Issues—December 2010 DOT&E Report
A December 2010 report on various DOD acquisition programs from DOD’s Director,
Operational Test and Evaluation (DOT&E)—DOT&E’s annual report for FY2010—stated, in its
section on the CVN-78 program, that
The CVN 78 program continues to have challenges with F-35 Joint Strike Fighter (JSF)
integration. The thermal footprint from the main engine exhaust, shipboard noise levels, and
information technology requirements need work. Design changes may be required for the jet
blast deflectors, and active cooling may be required in the flight deck just forward of the jet
blast deflector….
Numerous integrated warfare system items are of concern, including:

20 Government Accountability Office, Defense Acquisitions[:] Assessments of Selected Weapon Programs, GAO-10-
388SP, March 2010, p. 54.
Congressional Research Service
13

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

• The ship-self-defense combat systems on aircraft carriers have historically had
reliability and weapon system integration shortcomings. While the Navy has made
efforts, it has not yet developed a detailed plan to address these concerns on CVN 78.
• The Navy lags in developing a new anti-ship ballistic missile target and in obtaining a
capability to launch four simultaneous supersonic sea-skimming targets. Both are
required to assess effectiveness of ship self-defense….
EMALS experienced two notable hardware/software incidents that caused test delays at the
SFD [System Functional Design] test site at Lakehurst [NJ]. One incident involved an un-
commanded armature retraction due to a software anomaly in the asset protection module.
The second anomaly involved the loss of an encoder from the catapult armature during a
dead-load test. Both anomalies have been resolved. EMALS has started performance
verification with dead loads at the SFD site, and [the] AAG [Advanced Arresting Gear] is
nearing the start of Jet Car Track Site dead load testing. Required In Yard Date (RIYD) for
these systems continues to drive the development schedule; however, to date development
and testing remains on track.21
Legislative Activity for FY2012
The Administration is expected to submit its proposed FY2012 defense budget to Congress on or
about February 14, 2011.

21 Director, Operational Test and Evaluation, FY 2010 Annual Report, December 2010, p. 112.
Congressional Research Service
14

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Appendix A. Legislative Activity for FY2011
FY2011 Funding Request
The Navy’s proposed FY2011 budget was submitted to Congress on February 1, 2010. The
budget requested $1,731.3 million in procurement funding for CVN-78 and $908.3 million in
advance procurement funding for CVN-79.
FY2011 Continuing Appropriations and Surface Transportation
Extensions Act (H.R. 3082/P.L. 111-322)

H.R. 3082/P.L. 111-322 of December 22, 2010, generally funds government programs through
March 4, 2011, at FY2010 funding levels, which in the case of the CVN-78 program are
considerably lower than those requested for FY2011 (see Table 1). It is possible that the Navy
might seek to use CVN-78 program funding that is made available through March 4, 2011, under
H.R. 3082/P.L. 111-322 to support, as much as possible, activities consistent with the Navy’s
planned FY2011 schedule for the CVN-78 program while awaiting further congressional action
next year on funding for the remainder of FY2011.
FY2011 DOD Appropriations Bill (S. 3800)
Senate
The Senate Appropriations Committee, in its report (S.Rept. 111-295 of September 16, 2010) on
S. 3800, recommended approval of the Navy’s request for FY2011 procurement and advance
procurement funding for CVN-78 and CVN-79 (page 86).
FY2011 Defense Authorization Act (H.R. 6523/P.L. 111-383)
House (H.R. 5136)
The House Armed Services Committee, in its report (H.Rept. 111-491 of May 21, 2010) on the
FY2011 defense authorization bill (H.R. 5136), recommended approval of the Navy’s request for
FY2011 procurement and advance procurement funding for CVN-78 and CVN-79 (page 73).
Section 1021 of H.R. 5136 as reported by the committee would amend the law (10 USC 231) that
requires the Department of Defense to annually submit a 30-year Navy shipbuilding plan. The
amendment would, among other things, require that the Secretary of the Navy, in submitting each
30-year plan, “ensure that such plan—(1) is in accordance with section 5062(b) of this title [i.e.,
10 USC 5062(b), which requires the Navy to maintain a force of at least 11 operational carriers];
and (2) phases the construction of new aircraft carriers during the periods covered by such plan in
a manner that minimizes the total cost for procurement for such vessels.”
The committee’s report states:
Congressional Research Service
15

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Aircraft carriers
The committee is concerned that the decision by the Secretary of Defense in April 2009,
prior to the completion of the congressionally mandated analysis of the Quadrennial Defense
Review, to shift aircraft carrier construction to five-year centers for the stated purpose of “a
more fiscally sustainable path” was shortsighted. The committee has recently learned via
receipt of Department of Defense Selected Acquisition Reports that the cost to construct the
next three Ford-class aircraft carriers is likely to increase by up to $4.0 billion because of the
change in construction centers. The committee notes that the current 30-year shipbuilding
plan would not maintain a force of 11 operational aircraft carriers past fiscal year 2040 and
therefore does not conform to the requirement in section 5062b of title 10, United States
Code, to maintain an operational fleet of 11 aircraft carriers.
The committee expects that subsequent plans will conform to current law, or the Secretary of
the Navy will request a change to statute commensurate with detailed analysis of the effect a
reduction to 10 operational aircraft carriers will have on the national military strategy. In title
I [sic: Title X – Section 1021] of this Act, the committee directs the Secretary of Defense to
phase the construction of aircraft carriers to minimize the total cost for procurement of the
vessels. (Page 75)
Senate (S. 3454)
The FY2011 defense authorization bill (S. 3454), as reported by the Senate Armed Services
Committee (S.Rept. 111-201 of June 4, 2010), recommended approval of the Navy’s request for
FY2011 procurement and advance procurement funding for CVN-78 and CVN-79 (see page 677
of the printed bill).
Final Version (H.R. 6523/P.L. 111-383)
Section 102(a)(3) of H.R. 6523/P.L. 111-383 of January 7, 2011, authorized FY2011 funding for
the Navy’s entire shipbuilding account at the requested amount. H.R. 6523 contains no provisions
relating specifically to procurement of aircraft carriers. The joint explanatory statement of the
House and Senate Armed Services Committees on H.R. 6523 does not discuss procurement of
aircraft carriers.
Congressional Research Service
16

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Appendix B. Text of Navy Report on Effects of
Shifting to Five-Year Intervals

The following is the text of the Navy’s report on the effects of shifting to five-year intervals for
procuring carriers.22
I . REPORT REQUIREMENTS
Section 126 of the National Defense Authorization Act for Fiscal Year 2010, P.L. 111-84,
(hereinafter “Section 126”) requires that a report be submitted to Congress no later than
February 1, 2010 assessing the effects of using a five-year interval for the construction of
Gerald R. Ford Class aircraft carriers. The assessment shall include impacts with respect to
four specified areas resulting from this change in acquisition strategy. This report fulfills the
Navy’s reporting obligation pursuant to Section 126. The language of this section is as
follows:
“Not later than February 1, 2010, the Secretary of the Navy shall submit to the congressional
defense committees a report on the effects of using a five-year interval for the construction of
FORD Class aircraft carriers. The report shall include, at a minimum, an assessment of the
effects of such five-year interval on the following:
(1) With respect to the supplier base-
(A) the viability of the base, including suppliers exiting the market or other potential
reductions in competition; and
(B) cost increases to the Ford Class aircraft carrier program.
(2) Training of individuals in trades related to ship construction.
(3) Loss of expertise associated with ship construction.
(4) The costs of—
(A) any additional technical support or production planning associated with the start of
construction;
(B) material and labor;
(C) overhead; and
(D) other ship construction programs, including the costs of existing and future contracts.”
II. ASSESSMENT DISCUSSION
On April 6, 2009, Secretary of Defense announced within a Defense Budget
Recommendation Statement that the Navy’s CVN 21 aircraft carrier program (Ford Class)

22 Department of the Navy, Report to Congress on Effects of Five-year Build Intervals for Force Class Aircraft
Carriers
, February 2010, 5 pp. The cover letters sent with the report are dated March 4, 2010. Copy of report provided
to CRS by Navy Office of legislative Affairs on April 8, 2010.
Congressional Research Service
17

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

would shift from a four-year to a five-year build cycle, thereby placing the program on a
more fiscally sustainable path. This will result in 10 aircraft carriers after 2040. The five-year
build cycle allows for a balance between carrier build-rate and inventory, and a more
effective use of overall Shipbuilding and Conversion, Navy funding between carrier
programs and other ship, submarine, support, and amphibious ship recapitalization plans.
1. IMPACT TO SUPPLIER BASE
It has been the Navy’s experience that longstanding aircraft carrier suppliers have generally
responded to ship construction schedule shifts and extended workload gaps without
widespread disruption or loss of continuity for critical products from most vendors. For
example, the interval between procurement of CVN 77 and CVN 78 was originally planned
to be five years, but grew to seven years. There was no significant impact on the
shipbuilder’s procurement of components to support ship construction.
In addition, for a 2009 Navy-funded RAND Corporation study, RAND sought comments
from 46 major suppliers regarding the impact of moving the CVN 79 award date to Fiscal
Year 2013. The suppliers chosen were those deemed critical to aircraft carrier construction
by the shipbuilder. The majority of the 18 major suppliers who responded indicated that less
than 20% of their total annual revenues were from aircraft carrier construction, and nearly all
responding vendors indicated they provide services to other Navy ship platforms including
submarines, surface combatants, and aircraft carrier Refueling and Complex Overhauls
(RCOH). It is reasonable to assume that some vendor base inefficiencies, in addition to
inflation may occur by increasing CVN build intervals to five years. Efforts by the Navy to
drive cross-platform commonality of parts and proactively manage obsolescence also
mitigate the risk of economic dependence. As a result, economic dependence on Ford Class
aircraft carrier order frequency for the majority of the vendor industrial base is projected to
be low. The Navy plans to continue to closely manage this industrial base to minimize
impacts and costs.
2-3. IMPACT TO TRAINING AND EXPERTISE
The construction start of the Ford Class coincides with an overall ramp-up in shipyard
production efforts in the Fiscal Year 2010-Fiscal Year 2013 timeframe due to an increase to
two per year VIRGINIA Class submarines, more consistent carrier build frequencies,
sustained NIMITZ Class RCOH program, and the start of CVN 65 inactivation. While a five-
year interval between carrier construction starts will result in potential inefficiencies and
gaps for specific carrier construction trade skills, the Navy plans to closely manage the
transition to 5- year centers to minimize the impact of this change on training of individuals
required to support ship construction.
The Navy estimated that a four-year build interval would maximize the opportunity to
achieve labor efficiencies due to learning. A five-year build interval reduces this opportunity;
however, the overall impact for loss of learning associated with a shift to five-year centers is
manageable through Advance Procurement and Advance Construction.
4. COST IMPACTS
There are three primary sources of cost impact associated with increasing the intervals
between carrier construction starts - inflation, inefficiencies, and overhead impacts. The
effects of these are addressed in paragraphs 4A, 4B, and 4C for CVN 79 and CVN 80. For
other work at the shipyard, the collective impacts of the three sources are provided in
paragraph 4D.
Congressional Research Service
18

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

A. Cost of any Additional Technical Support or Production Planning Associated with the
Start of Construction
Since CVN 79 advance planning and procurement commenced prior to the five-year build
interval decision, CVN 79 technical support and production planning will be adjusted for the
five-year interval. The Construction Preparation contract will be extended by one year to
meet the construction award shift from Fiscal Year 2012 to Fiscal Year 2013. With the
exception of costs associated with an additional year of planning amounting to about 1%,
there should be no other fiscal implications with this extension.
B. Cost of Material and Labor
A five-year build interval imposes one additional year of inflation on the CVN 79 and two
additional years on CVN 80. The Navy estimates a 3% impact on the Basic Construction
Cost and Government Furnished Equipment (GFE) for CVN 79 and an 8% impact to CVN
80. This inflation impact will be addressed in the budget request for these two ships.
The Navy assessed the NIMITZ Class cost returns for shipbuilder labor and material and
GFE to determine the correlation between these cost elements and the number of years
between carrier awards. The Navy estimates that impact to Basic Construction is around
1.0% for CVN 79 and CVN 80.
C. Cost of Overhead
Overhead rates (percentage of direct labor) at the shipbuilder and major suppliers are directly
correlated to the projected direct labor workload. The change to five-year build intervals
results in an overall decrease in direct labor workload for aircraft carrier construction,
thereby causing the overhead rates to increase proportionally. The Navy estimates the
construction portion increase is less than 1% each for CVN 78, CVN 79 and CVN 80. The
Navy will be working with the shipbuilder on managing overhead in the shipyard.
D. Costs of Other Ship Construction Programs, Including the Costs of Existing and Future
Contracts
The impact of changing the interval between carrier awards to the VIRGINIA Class
submarine current Block II and Block III contracts is estimated to be $30-50 million per hull.
The increase in costs is associated with workload reallocatjon in the shipbuilding industrial
base.
III. REPORT SUMMARY
This report, as required by Section 126 of P.L. 111-84, assesses the impacts resulting from
the shift of the acquisition schedule to five-year intervals for Ford Class aircraft carriers. A
review of available information indicates there will be a minimal impact on the supplier base
if closely managed. Since the shipyard has ample opportunity to plan for five-year intervals,
any impacts to worker training or trade skill inefficiencies, and workload planning is
assessed to be manageable.
The change from a four-year to a five-year build interval will result in a unit cost increase to
the Ford Class carriers that have funding requirements in the Future Years Defense Program.
The Navy is continuing to refine the estimated impacts and will adjust future budget
submissions. These increases are due primarily to inflation, inefficiencies, and overhead
adjustments that will be factored into the overall budget request for each ship. Despite the
inflation adjusted costs per ship, the change in build interval allows carrier annual funding
requirements to be spread over longer periods of time, maintains a steady state 11 carrier
Congressional Research Service
19

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

force structure until after 2040, and facilitates a reduced average annual aircraft carrier
funding requirement.
Congressional Research Service
20

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Appendix C. July 16, 2009, Hearing on EMALS
This appendix presents materials from a July 16, 2009, hearing on the EMALS development
effort before the Seapower and Expeditionary Forces subcommittee of the House Armed Services
Committee.
Chairman’s Opening Statement
The text of the opening statement of Representative Gene Taylor, the ranking member of the
subcommittee, is as follows:
The subcommittee will come to order.
Today the subcommittee meets in open session to receive testimony from officials of the
United States Navy on the current status of the Electromagnetic Aircraft Launch System, or
EMALS. The EMALS system is an electromagnetic catapult designed for use on the Ford-
class aircraft carriers. If the system delivers its full promised capability, the Ford-class
carriers will have a catapult system which is far superior to the steam catapults of the Nimitz-
class. The operational advantages are increased launch envelopes, that is, the ability to
launch both heavier and lighter aircraft than steam catapaults, higher sortie rates, reduced
weight, reduced mechanical complexity, reduced maintenance, and reduced carrier manning.
Unfortunately, what brings us together today is that the development of this program is so far
behind schedule that it threatens the delivery date for the USS Ford. For the record, I would
like to briefly summarize the history of this program and the current status:
EMALS was a core capability in the design of the next generation aircraft carrier, which the
Navy called “CVN 21” for “21th century” technology, and which eventually became the USS
Ford (CVN 78) class. In 1999 the Navy entered into technology demonstration contracts with
two different contractors; General Atomics and Northrop Grumman Marine Systems to
develop prototypes for an electromagnetic catapult. By 2004 the Navy down-selected to the
system proposed by General Atomics and entered into a System Design and Development
contract, or SDD contract, to build a full scale, ship representative prototype at the Navy test
facility in Lakehurst, New Jersey. That prototype was contracted to be completed in time for
testing to begin in 2007, testing was to have concluded after two years and presumably the
lessons learned from the test program would influence the final production system which
would be shipped to the carrier construction yard for erection into the ship. It is now July
2009 and full scale testing has yet to begin at the Lakehurst facility. The Navy is now faced
with almost complete concurrency of testing and production of the first ship-set if they are to
meet the in-yard deliver dates to keep the USS Ford on schedule. There are a number of sub-
systems to the complete EMALS system and each subsystem has different in-yard deliver
dates, but some of those dates are as early as the summer of 2011, and to meet those dates
the production of the components or at least the ordering of the material for the components
must begin now—before full scale testing of the prototype system has begun. To be fair,
some testing has already occurred. The High Cycle Test for the Energy Storage System is
well underway, as is the Highly Accelerated Life Cycle Testing of the launch motor
segments. Those tests have identified some minor redesign issues which can be incorporated
into the production components. But until a full scale catapult launch from the prototype
occurs, questions will remain on the systems overall performance.
I have been briefed, as I believe other Members of this subcommittee have been briefed, that
the issues in completing and delivering the SDD components were a result of the contractor’s
Congressional Research Service
21

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

inexperience managing a major production effort. I find that answer unsettling because it is
the Navy’s responsibility to oversee what their contractors are doing and to identify
problems before they are problems. I will note that a little over a year and a half ago, the
contractor did put in place an entirely new management and engineering team, hiring away
proven production engineers from both General Dynamics and Northrop Grumman. This
new team seems to have righted the ship, but that ship is still in very dangerous seas.
So what we have is a program that is so essential to the carrier that if it does not work, the
nation has paid billions of dollars for an unusable ship. If the system is delayed, the carrier is
automatically delayed. And every day of delay will push the cost of that carrier higher.
This is the first in what I intend to be a series of hearings on this program over the next few
years. This is too important to not have close congressional oversight. I intend to continue
close oversight of this program until it is delivered, installed, tested, and certified for
launching naval aircraft off the deck of the USS Ford.
Our witnesses today are:
• VADM David Architzel, Principle Deputy to Assistant Secretary Stackley
• CAPT Randy Mahr, Program Manager for EMALS
• CAPT Brian Antonio, Program Manager, Ford Class Aircraft Carrier
VADM Architzel is representing the Assistant Secretary as the senior acquisition executive
who is ultimately responsible for all Navy and Marine Corps acquisition programs. CAPT
Mahr, is the official whose only responsibility is this program. CAPT Antonio is responsible
for building the entire carrier—he obviously has an interest in the success of EMALS.
This year’s National Defense Authorization Act directs the Secretary of the Navy to keep
CAPT Mahr in his position until the completion of the system development testing and the
successful production of the first ship-set of components. That means the CAPT, who has
been selected to the rank of Rear Admiral, will be in place for another few years and will
have the opportunity to visit with us again on this subject.
I would now like to call on my friend from Missouri, the Ranking Member of this
subcommittee, the Honorable Todd Akin for any opening remarks he may wish to make.
Ranking Member’s Opening Statement
The text of the opening statement of Representative Todd Akin, the ranking member of the
subcommittee, is as follows:
Thank you, Mr. Chairman, and welcome to our witnesses. We appreciate your willingness to
appear before us today. As the Chairman has indicated, the Electromagnetic Launch System,
known as EMALS, is a critical part of the military’s largest and most expensive ship, the
next generation aircraft carrier. The EMALS system is important because of the capability it
delivers to the Gerald R. Ford-class carrier, allowing our Navy to increase its sortie
generation rate and the carrier to launch both heavier and lighter aircraft, in more operating
conditions, than is currently possible. This is a significant attribute, because the first of these
carriers will be in service until at least 2065, and in order to maintain its relevance, the
carrier will need to be able to launch F-35s, UAVs, and whatever else we may develop in the
meantime.
Congressional Research Service
22

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Additionally, EMALS is important because the schedule delays and cost growth experienced
by the system have put the construction and cost of the carrier in jeopardy. As this
subcommittee has noted on multiple occasions, the scale of our investment in aircraft carrier
construction means that even small increases in cost have the potential to break the bank.
Other shipbuilding programs have recently seen cost growth of close to 200 percent. If the
carrier grows by even 10 percent, the impact is in the billions of dollars per vessel. Simply
put, the EMALS program has no room for error. It must deliver on time, or put the carrier at
risk. To get there, the EMALS program must engage in con-current development and
production of the first ship set—a practice we know well from past experience is highly
risky.
But there is some good news. The contractor has been holding to schedule since the
beginning of the year and has agreed to a fixed price production contract. The Assistant
Secretary of the Navy for Research, Development, and Acquisition got personally involved
and conducted an in-depth review of the program. Secretary Stackley has elected to proceed
with the effort, a decision that I agree with, but has taken several steps to strengthen the
management of the program. One of these steps includes lengthening the tour of the current
program manager, CAPT Mahr, who is with us today. I have often noted that one of the first
lessons I learned during my time at IBM, is that for any project to succeed, you need to have
one person who is in charge. CAPT Mahr, this subcommittee has heard many good things
about you, and your colleague CAPT Brian Antonio, the CVN 21 Program Manager. But we
will be holding you to a very high standard. This is your baby and you must deliver. The
consequences for the rest of naval shipbuilding are too great to tolerate anything less.
In conclusion, I am interested in learning more today about the contract you are putting in
place with the EMALS contractor for the production ship set, and the activities required to
conclude system development and minimize risk to the CVN 21 program going forward.
Thank you again for being here. I look forward to your testimony.
Navy Statement
Chairman Taylor, Ranking Member Akin, and distinguished members of the Subcommittee,
thank you for the opportunity to appear before you today to report on the development of the
Electromagnetic Aircraft Launch System (EMALS) for Gerald R. Ford (CVN 78) class
aircraft carriers and the Department’s plan ahead for this effort.
Steam catapults will continue to deliver the minimum required aircraft launching capability
and remain the launching system on the NIMITZ-class aircraft carrier for the next fifty years.
However, the steam catapult system limits the full potential of the inherent improved
capability of the FORD-class aircraft carrier. As modern aircraft, including the Joint Strike
Fighter, grow heavier and require higher launching end speeds, and the maintenance man-
hours required to maintain the readiness of the steam catapult increases, it is imperative that
the Navy continue development of a launching system with reduced manning and increased
operational availability. In response to meeting this future need, EMALS is being developed
for the CVN 78 class to replace the steam catapult system. EMALS design requirements
support the CVN 78 sortie generation rate Key Performance Parameter (KPP) through
increased reliability and system capability. It provides a higher energy launch capability as
well as an expanded launch envelope to support future airwing capabilities. EMALS is also
projected to reduce shipboard manning requirements, improve aircraft launching system
maintainability, and provide better control and more efficient application of acceleration
forces throughout the aircraft launch cycle.
EMALS development began with a competitive prototyping effort between General Atomics
(GA) and Northrop Grumman Marine Systems in 1999. The Navy down-selected to the GA
Congressional Research Service
23

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

design in 2004 following completion of approximately 1500 launch demonstration events
conducted on both competing systems. Based on the successful prototype testing, the Navy
awarded the EMALS System Development and Demonstration (SDD) contract to GA in
2005, which is scheduled to complete in early 2012.
The EMALS program is currently executing the test portions of the SDD phase and
procuring long lead time material as it begins production of the CVN 78 ship set. Near term
events such as successful completion of High Cycle Test (HCT) Phase I and commencement
of High Cycle Test (HCT) Phase II, Highly Accelerated Life Testing (HALT), as well as
start of commissioning testing for System Functional Demonstration (SFD), will validate the
system design and enable transition into production. HCT II testing of a complete power
train, with the exception of the launch motor, is ongoing at the GA Tupelo, Mississippi site.
HALT testing of the launch motor is taking place at the Naval Air Warfare Center test site in
Lakehurst, NJ. Production Readiness Reviews (PRRs) are currently ongoing to support
release of EMALS subsystem components for production. Baseline drawing packages are
projected to complete by the end of FY 2009. Full scale, full length testing of EMALS,
including the launch of manned aircraft, is scheduled to begin at Lakehurst during the
summer of 2010.
Concurrent with testing, EMALS manufacturing and production efforts began in December
2007 with the first Long Lead Time material procurements to support CVN 78 required in
yard delivery dates and will continue through 2014 for delivery of all CVN 78 ship set
components. The Navy has placed an undefinitized contract action (UCA) with a not to
exceed value with General Atomics leading to an Advanced Acquisition Fixed Price contract
for the remaining ship set material. Definitization of this contract is targeted for later this
year. The Navy’s and GA’s support for a fixed price contract reflects our collective
confidence in the EMALS’ technology maturity and capability. The contract will be based on
the EMALS performance specification and Procurement Data Packages. Specific component
production release will be tied to Production Readiness Reviews and successful completion
of specific test events. The Production Integrated Master Schedule shows the program will
meet CVN 78 production required in yard delivery dates.
As EMALS progressed through SDD tests and began the transition to production, schedule
delays and cost overruns were experienced. A series of actions aimed at improving
management of the EMALS prime and subcontractors were taken by the Navy. In late 2007,
Navy leadership initiated a three-month independent and in-depth Production Assessment
Review (PAR). The PAR provided specific recommendations for processes and leadership
improvements, which are being implemented. Most recently, senior Navy leadership
conducted a detailed assessment of the viability of continuing with EMALS or reverting to a
legacy steam catapult system for CVN 78 based on indications that schedule and cost
performance was declining. After an extensive review, the Navy re-confirmed it’s
commitment to EMALS as the CVN 78-class aircraft launching system, while implementing
additional actions to improve performance and mitigate risk.
The production contract will ensure rigorous management and oversight. In April 2004, the
Under Secretary of Defense (Acquisition, Technology and Logistics) (USD(AT&L))
established a critical technology Integrated Product Team (IPT) to maintain oversight of all
CVN 78 critical technologies, including EMALS development. Additionally, the Navy has
implemented two detailed reviews to identify needed improvements to support better
schedule and cost performance while completing technical efforts. The review of the PAR in
2008 provided a thorough assessment of GA’s ability to transition from development to
production and to support the CVN 78 production schedule. The Navy aggressively
implemented many of the PAR recommendations including leadership changes, new
program and technical governance processes, increased involvement of the shipbuilder and a
revised test program to mitigate production schedule risks. A three-star Executive
Congressional Research Service
24

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Committee, which includes the OPNAV resource sponsor, Commanders of the Naval Sea
Systems Command and Naval Air Systems Command, and the Principal Military Deputy for
ASN RDA meet quarterly for program reviews and to provide oversight of EMALS
development. Most importantly, direct responsibility for EMALS is being executed by the
NAVAIR program manager for Aircraft Launch & Recovery Equipment (ALRE), who
reports to PEO TACAIR and COMNAVAIR to support delivery of this new program within
cost and schedule.
Issues with cost and schedule performance have created overlaps between production
component manufacturing and system level testing. Cost and schedule performance have not
been where they need to be. Recognizing this, the Navy has taken steps to better define
needed testing, improved management oversight, insisted on near term definitization of the
DCA into a fixed price contract, and increased funding to the program to cover anticipated
growth. With system level testing ongoing the potential for additional cost increases and
schedule delays remain. However, the Navy is putting additional oversight in place to
maximize performance and minimize the likelihood of overruns. Given the advantages that
EMALS is projected to afford the next generation of aircraft carriers, these actions are
essential for providing the fleet what it needs.
Component, subsystem, and system testing is identifying technical issues, retiring technical
risk, and demonstrating the capability of the EMALS. Key to the Navy’s strategy is having a
management team in place both within the Navy and at its prime contractor that is
aggressively attacking these issues and retiring risks on a schedule that supports ship
construction. We are working hard towards these ends. The management focus, review
processes and oversight that the Navy is employing are mitigating future EMALS SDD
phase technical, cost and schedule risks. The Navy will leverage management processes
established during the SDD phase by building upon these lessons learned during system
production and ship integration, including the extensive involvement of the shipbuilder in the
production and integration process. A rigorous process exists for incorporating the results of
upcoming testing in the production baseline which will mitigate cost and schedule risks of
concurrency between the SDD and production phases. The Navy has also taken steps to
include, as mentioned previously, the use of fixed price contracting where appropriate, to
control EMALS cost and schedule variances during the subsystem production phase.
Mr. Chairman, the Navy understands the concerns you and your subcommittee have
expressed, and is aggressively working to improve performance. We are implementing your
recommendations to breakout EMALS cost and performance data for separate review by
Congress, and to provide stability in the program’s key technical and management teams.
The Department is committed to delivering CVN 78 with EMALS on time and on budget.
EMALS will enable current and future generations of Naval Aviators to perform their
missions more safely, efficiently and effectively. I thank you for the opportunity to testify
and look forward to answering your questions.23


23 Statement of Vice Admiral David Architzel, USN, Principal Military Deputy, Research, Development and
Acquisition, and Captain Randy Mahr, USN, Program Manager for Aircraft Launching and Recovery Equipment
(ALRE) and Captain Brian Antonio, USN, Program Manager for Future Aircraft Carrier, Before the Seapower and
Expeditionary Warfare [sic: Forces] Subcommittee of the House Armed Services Committee [Hearing] On
Electromagnetic Aircraft Launch System (EMALS}, July 16, 2009, 43 pp.
Congressional Research Service
25

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Author Contact Information

Ronald O'Rourke

Specialist in Naval Affairs
rorourke@crs.loc.gov, 7-7610


Congressional Research Service
26