Contract Types: An Overview of the Legal
Requirements and Issues

Kate M. Manuel
Legislative Attorney
October 1, 2010
Congressional Research Service
7-5700
www.crs.gov
R41168
CRS Report for Congress
P
repared for Members and Committees of Congress

Contract Types: An Overview of the Legal Requirements and Issues

Summary
Federal procurement contracts are commonly divided into two main types—fixed-price and cost-
reimbursement—that primarily differ as to whether the government or the contractor assumes the
risk of increases in performance costs (e.g., wages, materials). With a fixed-price contract, the
contractor assumes this risk because it agrees to provide goods or services to the government for a
certain price established at the time of contracting. If the performance costs exceed this price, the
contractor generally cannot, absent a price adjustment clause, recover more money from the
government. Rather, it must perform the contract at a loss, or default on the contract. In contrast,
with a cost-reimbursement contract, the government assumes the risk of increases in performance
costs because it agrees to repay the contractor for the allowable costs of performing certain work
up to a total cost specified in the contract. Additionally, under certain types of cost-reimbursement
contracts, the contractor may be entitled to profit in the form of fixed fees or incentive or award
fees. Contracts can also be divided into other types, including incentive contracts, letter contracts,
indefinite-delivery/indefinite-quantity (ID/IQ) contracts, and time-and-materials (T&M)
contracts. Particular contracts can display features of various types (e.g., pricing on both fixed-
price and cost-reimbursement bases for different line items) and can often be of multiple types
(e.g., an ID/IQ T&M letter contract). Determining the type of a particular contract is a question of
law, and contract language stating that a contract is of a certain type is not dispositive.
The use of certain contract types is prohibited or required in certain circumstances: (1) cost-plus-
a-percentage-of-cost contracts are absolutely prohibited; (2) cost-reimbursement contracts cannot
be used to acquire commercial items; and (3) contracts resulting from sealed bidding must be
firm-fixed-price or fixed-price with an economic price adjustment. Outside of these restrictions,
however, selection of the contract type for a particular procurement is generally within the
contracting officer’s discretion. The contracting officer typically decides on the contract type
prior to issuing a solicitation. However, particularly in negotiated procurements, selection of the
contract type can be “a matter for negotiation” between the procuring activity and the contactor.
Current congressional and public interest in contract types is, in part, an outgrowth of the reported
increase in the use of cost-reimbursement contracts during the George W. Bush Administration
and the Obama Administration’s proposal to reduce by at least 10% the funds obligated in
FY2010 by “high risk-contracting authorities,” such as cost-reimbursement, time-and-materials,
and labor-hour contracts. The Department of Defense’s (DOD’s) budget request for FY2011
similarly proposed a 17% reduction in the use of time-and-materials and labor-hour contracts.
Additionally, the Office of Management and Budget (OMB) has called for agencies to include
“specific actions and goals” to reduce their reliance on cost-reimbursement and time-and-
materials contracts in their FY2012 budget submissions. This call is part of a broader proposal to
cut agencies’ discretionary spending by 5%, among other things.
The 111th Congress has enacted or proposed several bills that address use of various types of
contracts, including P.L. 111-5, P.L. 111-23, P.L. 111-84, P.L. 111-118, H.R. 1665, H.R. 2269,
H.R. 3619, H.R. 4983, H.R. 5013, H.R. 5136, S. 920, S. 1194, S. 2901, S. 2971, S. 3454, S. 3455,
S. 3607, S. 3611, and S. 3676.

Congressional Research Service

Contract Types: An Overview of the Legal Requirements and Issues

Contents
Introduction ................................................................................................................................ 1
Selecting the Contract Type......................................................................................................... 1
Types of Contracts ...................................................................................................................... 3
Contracts Under Part 16 of the FAR ...................................................................................... 5
Fixed-Price Contracts...................................................................................................... 5
Cost-Reimbursement Contracts ....................................................................................... 8
Incentive Contracts ....................................................................................................... 10
Time-and-Materials and Labor-Hour Contracts.............................................................. 11
Indefinite-Delivery Contracts ........................................................................................ 13
Other Agreements Under Part 16 of the FAR ....................................................................... 15
Letter Contracts ............................................................................................................ 15
Agreements................................................................................................................... 17
Recently Enacted and Proposed Legislation............................................................................... 17
Executive Branch Initiatives...................................................................................................... 19
Obama Memorandum of March 4, 2009 .............................................................................. 19
OMB Memorandum of July 29, 2009 .................................................................................. 20
OMB Memorandum of October 27, 2009 ............................................................................ 20
Effectiveness of These Initiatives Presently Unknown ......................................................... 22

Tables
Table 1. Types of Fixed-Price Contracts ...................................................................................... 5
Table 2. Types of Cost-Reimbursement Contracts........................................................................ 8
Table 3. OMB Guidance on “Appropriate Use and Oversight” of Contract Types....................... 21

Appendixes
Appendix. Chronology of Developments Regarding Contract Types, 107th-110th
Congresses............................................................................................................................. 23

Contacts
Author Contact Information ...................................................................................................... 26
Acknowledgments .................................................................................................................... 26

Congressional Research Service

Contract Types: An Overview of the Legal Requirements and Issues

Introduction
This report provides an overview of the various contract types (e.g., fixed-price, cost-
reimbursement) used in federal procurement and the legal requirements and issues pertaining to
each. Current congressional and public interest in contract types is, in part, an outgrowth of the
reported increase in the use of cost-reimbursement contracts during the George W. Bush
Administration1 and the Obama Administration’s proposal to reduce by at least 10% the funds
obligated in FY2010 by “high risk-contracting authorities,” such as cost-reimbursement, time-
and-materials, and labor-hour contracts.2 The Department of Defense’s (DOD’s) budget request
for FY2011 similarly proposes a 17% reduction in the use of time-and-materials and labor-hour
contracts.3 Additionally, the Office of Management and Budget (OMB) has called for agencies to
include “specific actions and goals” to reduce their reliance on cost-reimbursement and time-and-
materials contracts in their FY2012 budget submissions.4 This call is part of a broader proposal to
cut agencies’ discretionary spending by 5%, among other things.
Selecting the Contract Type
The use of certain contract types may be prohibited or required, at least in certain circumstances.
Cost-plus-a-percentage-of-cost contracts, under which the government reimburses contractors’
costs and pays them a percentage of these costs as an allowance for profit, are absolutely
prohibited,5 and agency prime contracts must generally prohibit cost-plus-a-percentage-of-cost

1 In FY2008, 60% of federal contract dollars ($315.7 billion) was reportedly obligated through fixed-price contracts;
25% ($135.4 billion) through cost-reimbursement contracts; and 5% ($27.5 billion) through time-and-materials and
labor-hour contracts). See Contract Data for FY2008 Show Continued Reliance on Cost-Reimbursement Contracts,
Fed. Cont. Daily, Apr. 6, 2009. The amount obligated through cost-reimbursement contracts has increased since
FY2000, although the extent of this increase is unclear. See id. (reporting that only $71 billion was obligated by cost-
reimbursement contracts in 2000); Grant Thornton, 14th Annual Government Contractor Industry Highlights Book 8
(2009), available at http://www.grantthornton.com/staticfiles//GTCom/files/Industries/Government%20contractor/
14th_Gov_Con_Highlights_011409small.pdf (noting that cost-reimbursement contracts represented 28% of federal
contracts in its 11th survey, 39% in its 12th survey, 40% in its 13th survey, and 45% in the current survey); Center for
Strategic and International Studies, Defense Industrial Initiatives Group, Structure and Dynamics of the U.S. Federal
Professional Services Industrial Base, 1995-2007
16 (2009) (suggesting that the dollar amount obligated through fixed-
price contracts has declined faster than usage of fixed-price contracts per se).
2 Executive Office of the President, Office of Management and Budget, Improving Government Acquisition, July 29,
2009, at 2, available at http://www.whitehouse.gov/omb/assets/memoranda_fy2009/m-09-25.pdf.
3 See, e.g., Geoffrey Emeigh, DOD Requests $548.9 B for FY2011, Aims to Reduce T&M/LH Contracts by 17 Percent,
Fed. Cont. Daily, Feb. 2, 2010. The Panel on Contracting Integrity’s 2009 report to Congress also included among its
FY2010 goals studying DOD’s letter contracts for possible abuse, reviewing use of time-and-materials and labor-hour
contracts, and possibly developing doctrine for the selection of contract types for research and development. Dep't of
Defense, Office of the Under Secretary of Defense for Acquisition, Technology & Logistics, Panel on Contracting
Integrity 2009 Report to Congress, available at http://www.acq.osd.mil/dpap/cpic/cp/docs/
Panel_on_Contracting_Integrity_2009_to_Congress.pdf.
4 Exec. Office of the President, Office of Mgmt. & Budget, Fiscal Year 2012 Budget Guidance, June 8, 2010, available
at
http://www.whitehouse.gov/sites/default/files/omb/assets/memoranda_2010/m10-19.pdf. DOD has reportedly placed
similar emphasis on using the “proper” contract type for particular procurements and phasing out time-and-materials
and single-award indefinite-delivery/indefinite-quantity contracts in its efforts to increase its warfighting capabilities by
2 to 3% annually without increasing spending. See Jeff Kinney, Carter Tells Defense Industry Officials DOD Must
Receive More Value for Its Money, 94 Fed. Cont. Rep. 5 (July 6, 2010).
5 P.L. 81-152, § 304(b), 63 Stat. 395 (June 30, 1949) (codified, as amended, at 41 U.S.C. § 254(b)) (procurements of
civilian agencies); P.L. 84-508, § 2306(a), 70A Stat. 130 (May 9, 1956) (codified, as amended, at 10 U.S.C. § 2306(a))
(continued...)
Congressional Research Service
1

Contract Types: An Overview of the Legal Requirements and Issues

subcontracts.6 The use of cost-reimbursement contracts to acquire commercial items is similarly
prohibited.7 Contracts for commercial items must instead be firm-fixed-price or fixed-price with
economic price adjustment contracts,8 or of other types (e.g., time-and-materials, ID/IQ) that
price goods or services on a firm-fixed-price or fixed-price-with-an-economic-price-adjustment
basis.9 Contracts that result from sealed bidding must also be firm-fixed-price or fixed-price with
an economic price adjustment.10
Aside from these restrictions, however, selection of the contract type for a particular procurement
is generally within the contracting officer’s discretion.11 The contracting officer typically decides

(...continued)
(procurements of defense agencies); 48 C.F.R. § 16.102(c). Despite this prohibition, agencies sometimes inadvertently
enter cost-plus-a-percentage-of-cost contracts, which are void because they are unlawful. See, e.g., Urban Data Sys.,
Inc. v. United States, 699 F.2d 1147 (Fed. Cir. 1983), aff'g Urban Data Sys., Inc., GSBCA 5545, 81-2 BCA ¶ 15,254
(1981) (finding that two contracts whose price adjustment clauses provided for item or unit prices to be audited after
performance, with the contract prices adjusted by 5 to 10% based upon the audit findings, constituted cost-plus-a-
percentage-of-cost systems of contracting).
6 48 C.F.R. § 16.102(c). The clause prohibiting cost-plus-a-percentage-of-cost subcontracts may be excluded only when
the prime contract is a firm-fixed-price contract. Id.
7 48 C.F.R. § 16.301-3(b). For purposes of federal procurements, a “commercial item” is
… [a]ny item, other than real property, that is of a type customarily used by the general public or
by non-governmental entities for purposes other than governmental purposes, and (i) [h]as been
sold, leased, or licensed to the general public; or (ii) [h]as been offered for sale, lease, or license to
the general public ... [including] installation services, maintenance services, repair services, training
services, and other services if (i) [s]uch services are procured for support of [a commercial item],
regardless of whether such services are provided by the same source or at the same time as the
item; and (ii) [t]he source of such services provides similar services contemporaneously to the
general public under terms and conditions similar to those offered to the Federal Government; [or]
… [s]ervices of a type offered and sold competitively in substantial quantities in the commercial
marketplace based on established catalog or market prices for specific tasks performed or specific
outcomes to be achieved and use standard commercial terms and conditions. 48 C.F.R. § 2.101.
This definition is controversial, in part because it includes the phrase “of a type” when referring to services as well as
goods, while the statutory definition of commercial services on which it is based does not. Compare id. (regulatory
definition of “commercial services”) with 41 U.S.C. § 403(12)(F) (statutory definition of “commercial services”). See,
e.g.
, Report of the Acquisition Advisory Panel to the Office of Federal Procurement Policy and the United States
Congress
95-96 (2007), available at https://www.acquisition.gov/comp/aap/24102_GSA.pdf.
8 48 C.F.R. § 16.201.
9 The Services Acquisition Reform Act (SARA) of 2003 explicitly authorized agencies to use time-and-materials and
labor-hour contracts to acquire commercial items. See P.L. 108-136, § 1432, 117 Stat. 1672 (Nov. 24, 2003). Before
SARA was enacted, the FAR prohibited the use of contracts that were not fixed-price to acquire commercial items. See
48 C.F.R. § 12.207 (2002) (“Agencies shall use firm-fixed-price contracts or fixed-price contracts with economic price
adjustment for the acquisition of commercial items…. Use of any other contract type to acquire commercial items is
prohibited.”).
10 48 C.F.R. § 16.102(a). Sealed bidding is one of two main source-selection methods used by the federal government.
In sealed bidding, the procuring activity awards the contract to the lowest-priced, qualified, responsible bidder without
conducting negotiations with the bidders. This is in contrast to the other main source-selection method, negotiated
procurement, wherein the procuring activity bargains with offerors after receiving proposals, and awards the contract to
the offeror whose proposal rates most highly on evaluation criteria that include, but are not limited to, cost or price. In
the case of negotiated procurements, any type or combination of types of contracts allowed under Subpart 16 of the
FAR may be used. 48 C.F.R. § 16.102(b).
11 See, e.g., Am. Tel. & Tel. Co. v. United States, 307 F.3d 1374, 1379 (Fed. Cir. 2002) (“[T]he regulations entrust the
contracting officer with especially great discretion, extending even to his application of procurement regulations.”);
Master Sec., Inc., Comp. Gen. Dec. B-232263 (Nov. 7, 1988) (denying a protest that alleged the contracting officer’s
proposed use of a firm-fixed-price contract for three years of work was improper because it would impose an inordinate
risk of high labor costs on the contractor).
Congressional Research Service
2

Contract Types: An Overview of the Legal Requirements and Issues

on the contract type prior to issuing a solicitation. This decision is made after considering a range
of factors including the degree of price competition in the procurement, the type and complexity
of the requirements, the urgency of the requirements, the period of performance or length of the
production run, and the history of the acquisition.12 These factors can cut in various ways in any
given procurement. For example, while the requirements might be simple enough for a fixed-
price contract, the procuring activity’s need for them might be urgent, a circumstance which can
justify use of cost-reimbursement contracts. However, particularly in negotiated procurements,
selection of the contract type can be “a matter for negotiation” between the procuring activity and
the contactor.13 Most reports by the Government Accountability Office or agency inspectors
general discussing agencies’ use of particular types of contracts allege not that the type used was
unlawful but that it was imprudent because it left the government vulnerable to paying too much,
especially if agency oversight of contractor performance was inadequate.14
Provided they do not unilaterally modify particular contracts, procuring activities may generally
change the type of contract used in the course of an acquisition program, a series of contracts for
recurring requirements, or a single long-term contract, so as to shift more risk to the contractor as
the uncertainties associated with the procurement are reduced.15
Types of Contracts
Federal procurement contracts are commonly divided into two main types—fixed-price and cost-
reimbursement—that primarily differ as to whether the government or the contractor bears the
risk of increases in performance costs (e.g., wages, materials). With a fixed-price contract, the
contractor agrees to supply certain goods or services to the government at a predetermined price.
This means that, absent a price adjustment clause in the contract, the contractor assumes the risk
that the performance costs will exceed the contract price.16 In contrast, with a cost-reimbursement
contract, the government agrees to pay certain costs that the contractor incurs in providing the
goods or services. While payment may only be made for costs allowed under the contract up to a
total cost specified in the contract,17 the government assumes the risk that performance costs will

12 48 C.F.R. § 16.104(a)-(k).
13 48 C.F.R. § 16.103(a). A “procuring activity” is any component of an executive agency with significant acquisition
functions that is designated as such by the head of the agency. 48 C.F.R. § 2.101.
14 See, e.g., Treasury Inspector General for Tax Administration, Current Practices Might Be Preventing Use of the Most
Advantageous Contractual Methods to Acquire Goods and Services, Feb. 10, 2009, at 2-3, available at
http://www.treas.gov/tigta/auditreports/2009reports/200910037fr.html (reporting that 33 of 40 contracts reviewed were
cost-reimbursement, time-and-materials, or labor-hour, but finding that the contracts were not improper based on the
associated statements of works); Gov't Accountability Office, Troubled Asset Relief Program: Additional Actions
Needed to Better Ensure Integrity, Accountability, & Transparency, GAO-90-161, Dec. 2008, at 36-37, available at
http://www.gao.gov/new.items/d09161.pdf (noting extensive use of time-and-materials contracts and suggesting that
there needs to be close government supervision to ensure that costs are contained).
15 See, e.g., 48 C.F.R. § 16.103(c); Gov't Accountability Office, Troubled Asset Relief Program: Status of Efforts to
Address Transparency and Accountability Issues, GAO-09-417T, Feb. 24, 2009, at 3 & 10, available at
http://www.gao.gov/new.items/d09296.pdf (recommending that agencies shift toward fixed-price contracts as program
requirements are better defined).
16 See, e.g., Cleveland Telecomm. Corp. v. United States, 39 Fed. Cl. 649 (1997) (contractor not entitled to
reimbursement for unforeseen premium wage payments); D.W. Clark, Inc., ASBCA 45562, 94-3 BCA ¶ 27,132 (1994)
(contractor solely responsible for increases in material costs absent an economic price adjustment clause in the
contract).
17 48 C.F.R. § 52.216-7 (allowable costs and payment); 48 C.F.R. § 52.232-20(a) (limitation on costs).
Congressional Research Service
3

Contract Types: An Overview of the Legal Requirements and Issues

increase over the term of the contract. While shifting as much risk as possible from the
government to the contractor might seem like a good idea,18 the FAR instructs contracting officers
to use contract types that result in “reasonable contractor risks,”19 in part because contractors who
are forced to assume excessive risk may cease to be available as contracting partners for the
government.20 Contracts can also be divided into other types, including incentive contracts, letter
contracts, indefinite-delivery/indefinite-quantity (ID/IQ) contracts, and time-and-materials
(T&M) contracts. Particular contracts can display features of various types (e.g., pricing on both
fixed-price and cost-reimbursement bases for different line items) and can often be of multiple
types (e.g., an ID/IQ T&M letter contract).21
This report focuses on the “contract types” included in Part 16 of the Federal Acquisition
Regulation (FAR). Some of these types are legally binding contracts; others are agreements that,
while not themselves legally binding, spell out terms and conditions of future binding contracts.
The report does not discuss other “types” in terms of which federal procurement contracts can
also be described (e.g., performance-based, share-in-savings, interagency, multiyear).22 The report
also does not directly address orders or options because they are not types of contracts.23
Determining the type of a particular contract is a question of law,24 and contract language stating
that a contract is of a certain type is not dispositive.25

18 See, e.g., Firm-Fixed-Price Contract Awards Require Discipline on DOD’s Part, Comptroller Says, Fed. Cont. Daily,
Mar. 20, 2009 (quoting some who would place all risk of cost overruns on the contractors).
19 48 C.F.R. § 16.103(a).
20 See, e.g., John Cibinic, Jr. & Ralph C. Nash, Jr., Formation of Government Contracts 1080 (3d ed. 1998).
21 See, e.g., J.A. Jones Constr. Co., ASBCA 43344, 96-2 BCA ¶ 28,517 (1996) (contract displaying elements of firm-
fixed price and cost-sharing contracts); Ben Bain, DHS Procurement Office Eyes Contract Hybrids, Wash. Tech., Dec.
3, 2009, available at http://washingtontechnology.com/Articles/2009/12/07/WEEK-DHS-contracting-eagle.aspx. A
“hybrid contract” is one that displays features of multiple types.
22 The report also does not discuss task order/delivery order (TO/DO) contracts or multiple-award task-order contracts
(MATOCs) as distinct types. As the FAR explains, requirements contracts and ID/IQ contracts can also be described as
TO/DO contracts. 48 C.F.R § 16.501-2(a). Similarly, any type of indefinite-delivery contract could be a MATOC. 48
C.F.R. § 16.500(a).
23 An order is a request for delivery of goods or provision of services issued to a vendor currently holding a contract.
The work under the order must be within the scope of the contract under which the order is issued, or the procuring
activity must solicit a new contract. An option is a unilateral right in a contract under which the government may, for a
specified period, purchase additional supplies or services, or otherwise extend the contract. Federal contracts are
generally for one year but can potentially be extended to five years through agencies’ use of options. 48 C.F.R. §
17.204(e).
24 See, e.g., Coastal Gov't Servs., Inc., ASBCA 49625, 97-1 BCA ¶ 28,888 (1997) (“The determination of the contract
type is a matter of law, … and we are not bound either by what the contract is called or by the label attached to it by the
parties.”).
25 See, e.g., LSI Serv. Corp. v. United States, 422 F.2d 1334 (Ct. Cl. 1970) (finding that a contract titled “Cost
Reimbursement Contract” was a fixed-price contract because it contained a clause limiting the maximum total cost,
including the contractor’s fee, to a stated amount); Franklin Co., ASBCA 9750, 65-1 BCA ¶ 4,767 (1965), aff'd
Franklin Co. v. United States, 381 F.2d 416 (Ct. Cl. 1967) (finding that the contracts in question were not requirements
contracts, despite being designated as such, because they provided for the supply of the same kind of services in the
same place, and there cannot be two simultaneous requirements contracts for the same services in the same place).
Congressional Research Service
4

Contract Types: An Overview of the Legal Requirements and Issues

Contracts Under Part 16 of the FAR
Fixed-Price Contracts
The various types of fixed-price contracts, described in Table 1, provide for the contractor to
receive a specified (i.e., fixed) price for supplying certain goods or services to the government.
With some types of fixed-price contracts, the price is fixed without the possibility of change,
absent modifications by the government or defective performance by the contractor, at the time of
contracting (e.g., firm-fixed-price contracts). With others, the price is fixed at the time of
contracting but could later change depending upon changes in circumstances (e.g., fixed-price
contracts with economic price adjustments,26 fixed price contracts with prospective price
redetermination, fixed-ceiling price contracts with retroactive price redetermination27). The extent
of possible changes in price is sometimes restricted at the time of contracting (e.g., fixed-ceiling-
price contracts with retroactive price redetermination). At other times, it may be left open (e.g.,
fixed-price contracts with economic price adjustments). Fixed-price contracts are generally for
the provision of specified quantities of goods or services. However, some provide a specified fee
in return for the contractor’s expending a specified level of effort, regardless of whether particular
objectives are realized (e.g., firm-fixed-price, level-of-effort term contracts).
Table 1. Types of Fixed-Price Contracts
Type
Description
Use
Conditions on Use
Firm-fixed-price
Contractor agrees to provide
Used when acquiring
n/a
contracts
supplies or services to the
commercial items or other
procuring activity for a
goods and services when

specified price
there are reasonably definite
specifications, and fair and
reasonable prices can be
established at the outset
Fixed-price
Contractor agrees to provide
Used when the stability of
Contracting officer must
contracts with
supplies or services to the
market or labor conditions
determine that a price
economic price
procuring activity for a
throughout the period of
adjustment clause is necessary
adjustmentsa
specified price that could be
performance is uncertain, and
to protect the contractor or
adjusted if certain economic
contingencies otherwise
government against significant
conditions change during
included in the contract price
fluctuations in costs or
performance of the contract
can be identified and
provide for price adjustments
separately addressed in the
in the event of changes in the
contract
contractor’s established prices

26 Contracting officers have substantial discretion in determining whether to include an economic price adjustment
clause in a fixed-price contract, and their determinations about whether to include such a clause generally will not be
reversed by judicial or administrative tribunals. See, e.g., B&P Refuse Disposal, Inc., Comp. Gen. Dec. B-253661
(Sept. 16, 1993); Master Security, Inc., Comp. Gen. Dec. B-232262 (Nov. 30, 1988); Sentinel Elecs., Inc., Comp. Gen.
Dec. B-212770 (Dec. 20, 1983).
27 Some commentators have suggested that fixed-price contracts with retroactive price redetermination are really cost-
plus-a-percentage-of-cost contracts because profit is computed based on a percentage of the costs after performance.
See, e.g., 2-19 Gov't Cont.: L., Admin. & Proc. § 19.40. The courts, however, have historically rejected this argument
on the grounds that Congress explicitly prohibited cost-plus-a-percentage-of-cost contracts but has permitted fixed-
price contracts with retroactive price redetermination. See Nat’l Elec. Labs., Inc. v. United States, 180 F. Supp. 337,
340 (Ct. Cl. 1960) (“There probably is some difference but not enough, we think, to justify us in treating the latter
[retroactive] type of price provisions as illegal.”).
Congressional Research Service
5

Contract Types: An Overview of the Legal Requirements and Issues

Type
Description
Use
Conditions on Use
Fixed-price
Contractor receives a firm
Used to acquire quantity
Negotiations have shown
contract with
fixed price for a specified
production or services when
firm-fixed-price and incentive
prospective
initial period of performance,
it is possible to negotiate a fair contracts are not suitable;
price
with the price for later
and reasonable price for the
contractor’s accounting
redetermination
periods revised in an equitable initial period but not for later
system is adequate;
manner based on variables
ones
accounting system can be
agreed upon by the partiesb
made to conform to the price
periods; there is reasonable
assurance redetermination
will take place as scheduled
Fixed-ceiling-
Contractor receives no more
Used for research and
Contractor’s accounting
price contracts
than a fixed ceiling price that
development contracts whose
system is adequate for price
with retroactive
was agreed upon when the
anticipated value is less than
redetermination; there is
price
contract was formed;
$150,000 when other fixed-
reasonable assurance
redetermination
determination of actual price
price contracts cannot be
redetermination will take
occurs after the contract is
used
place as scheduled; the head
performed based on variables
of procuring activity approves
previously agreed upon
use of this contract
Firm-fixed-price, Contractor receives a fixed
Used for research and
Required level of effort is
level-of-effort
amount for providing a certain development contracts whose
identified, agreed upon in
term contracts
level of effort over a certain
anticipated value is less than
advance; there is reasonable
period of time on work that
$150,000; general y yields a
assurance that the intended
“can only be stated in general
report describing the R&D
result cannot be achieved by
terms”
results
expending less effort
Source: Congressional Research Service, based on Subpart 16.2 of the FAR.
a. Economic price adjustment clauses themselves can be of three types, depending upon whether the
adjustment is made based upon (1) established prices, (2) the actual costs of labor or material, or (3) indexes of
labor or material. 48 C.F.R. § 16.203-1(a).
b. The initial performance period must be the longest possible period allowing for a “fair and reasonable firm
fixed price,” and the later performance periods must be a minimum of 12 months. 48 C.F.R. § 16.205-2(a).
Fixed-price contracts are generally favored by policy makers because the contractor, not the
government, assumes the risk of increases in performance costs.28 The government’s liability is
typically limited to the contract price, so long as the contract does not have a price adjustment
clause and the government has not actually or constructively modified the contract.29 If the costs
of labor or materials increase during performance of the contract, the contractor must absorb
these costs, even if doing so means choosing between performing the contract at a loss and
breaching the contract. Additionally, the government can generally rely on the contractor to
finance performance under a fixed-price contract.30 Unless the government agrees to provide
financing in the form of progress payments, it pays only for completed or delivered work.31 With

28 See, e.g., Formation of Government Contracts, supra note 20, at 1061.
29 See, e.g., McDonnell Douglas Corp. v. United States, 37 Fed. Cl. 295 (1997) (when the government orders changes,
the contractor is no longer required to deliver at the contract price, regardless of increases in performance costs, so long
as the increases resulted from the government’s changes); Martin-Copeland Co., ASBCA 26551, 83-2 BCA ¶ 16,752
(1983) (contractor not entitled to relief when the price of gold increased by 350% because it had assumed the risk that
the price would not increase beyond the 10% provided for in the price adjustment clause).
30 See, e.g., Formation of Government Contracts, supra note 20, at 1061.
31 Id. Progress payments made on the basis of percentage of completion to construction contractors and architect-
engineers are considered invoice payments. 48 C.F.R. § 32.903. Progress payments made on the basis of performance
milestones are considered financing payments. 48 C.F.R. §§ 32.503-8—32.503.9. Any other progress payments based
(continued...)
Congressional Research Service
6

Contract Types: An Overview of the Legal Requirements and Issues

cost-reimbursement contracts, in contrast, the contractor needs to provide only a minimal amount
of financing because its costs are reimbursed on a regular basis.32 Further, fixed-price contracts
are generally simpler for the government to administer because there is typically no need to audit
the contactor’s books or determine whether particular costs are allowable under the contract.33
Rather, the government can pay the agreed-upon price upon acceptance of the goods or services
or as otherwise scheduled under the contract.34
Fixed-price contracts are not without their drawbacks, however, as some commentators have
noted.35 Regardless of the type of fixed-price contract used, the government runs the risk of
overpaying for goods and services, especially if it overestimates its requirements.36 It is not
entitled to a price reduction if the contractor’s actual costs are less than anticipated,37 and certain
payments may be recoverable under cost-reimbursement contracts but not under fixed-price
contracts.38 With firm-fixed-price contracts, in particular, the government could also (1) pay
higher prices than would have been paid under cost-reimbursement contracts;39 (2) have to
convert the contract to another type to obtain completion of performance; 40 or (3) defend lawsuits
filed by contractors attempting to recover increases in performance costs by alleging that the
government constructively modified the contract.41 Similarly, with fixed-price contracts with
economic price adjustment clauses, the government could be vulnerable to “significant and
unanticipated price increases,” especially if the clauses do not adequately protect the
government’s interests.42 However, refusal to use economic price adjustment clauses where

(...continued)
on costs are “unusual” and may be made only in exceptional cases. 48 C.F.R. §§ 32.501-1—32.501-2.
32 See, e.g., Formation of Government Contracts, supra note 20, at 1061.
33 See, e.g., 2-19 Gov't Cont.: L., Admin. & Proc. § 19.20 (2009).
34 Acceptance occurs when an authorized representative of the government assumes ownership of identified supplies
tendered or approves specific services rendered as partial or complete performance of the contract. See 48 C.F.R. §
46.101.
35 See, e.g., Formation of Government Contracts, supra note 20, at 1080.
36 North Chicago Disposal Co., ASBCA 25535, 82-1 BCA ¶ 15,488 (1981) (government could not recover when it
contracted for removal of “wet garbage” from galleys at the Great Lakes Naval Base and then did not use the service
because the galley personnel were unaware of it and disposed of the garbage in-house); Rolligon Corp., ASBCA 8812,
65-2 BCA ¶ 15,488 (1965) (government liable for the full contract price when it leased two experimental vehicles from
the contractor for a one-year testing-and-evaluation period and then discontinued testing after one month).
37 Penker Constr. Co. v. United States, 96 Ct. Cl. 1 (1942) (government could not deduct payments from a fixed-price
contract when the number of yards of materials excavated was less than the government had estimated it would be).
38 Gould, Inc., ASBCA 46759, 97-2 BCA ¶ 29,254 (1997), reaff’d on recons. 98-1 BCA ¶ 29,469 (1998) (when the
contractor over-funded pension accounts because of incorrect actuarial assumptions, the government was entitled to a
credit on costs billed to cost-recovery contracts, but not on costs billed to firm-fixed-price contracts).
39 See, e.g., Commission on Army Acquisition and Program Management in Expeditionary Operations, Urgent Reform
Required: Army Expeditionary Contracting
38 (2007) (reporting that contractors had to price firm-fixed-price contracts
higher in order to cover possible risks of performing in war zones).
40 See, e.g., General Dynamics Corp. v. United States, 671 F.2d 474 (Ct. Cl. 1982) (government converting a firm-
fixed-price contract into a cost-reimbursement contract in order to obtain completion of the work); Ball Bros. Research
Group, NASABCA 1277-6, 80-2 BCA ¶ 14,562 (1980) (same).
41 See, e.g., McDonnell Douglas Corp. v. United States, 37 Fed. Cl. 295 (1997) (when the government orders changes,
the contractor is no longer required to deliver at the contract price, regardless of increases in performance costs, so long
as the increases resulted from the government’s changes). In one case, Northrop Grumman reportedly sued to recover
$14 million due to alleged modifications to the fixed-price portions of a $26 million contract to develop a prototype
communications system. See, e.g., Northrop Grumman May Sue for Overrun on $26 Million Prototype Contract, COFC
Rules, 70 Fed. Cont. Rep. 417 (Oct. 26, 1998).
42 Office of the Under Secretary of Defense, Acquisition, Technology & Logistics, Follow-on Actions in Response to
(continued...)
Congressional Research Service
7

Contract Types: An Overview of the Legal Requirements and Issues

significant economic fluctuations are possible could result in the government paying higher prices
because fewer contractors will compete for such contracts.43
Cost-Reimbursement Contracts
The various cost-reimbursement contracts, described in Table 2, provide for the government to
pay the contractor, at a minimum, allowable costs incurred in performing the contract up to a total
cost specified in the contract. As used here, “costs” do not necessarily include all expenses that
the contractor incurred in performing the contract. Rather, costs are expenses that are allocable to
the contract and reimbursable by the government under the terms of the contract.44 The types of
cost-reimbursement contracts differ in whether the contractor recovers only costs (e.g., cost
contracts, cost-sharing contracts) or whether there is some allowance for profit (e.g., cost-plus-
fixed-fee contracts, cost-plus-a-percentage-of-cost contracts). Some contracts are with vendors
that are nonprofits (e.g., cost contracts) or that at least are not expecting to profit from the
contract (e.g., cost-sharing contracts). Others are with contractors who anticipate making a profit
(cost-plus-fixed-fee contracts). Cost-plus-a-percentage-of-cost contracts are absolutely
prohibited,45 and no cost-reimbursement contract may be used to acquire commercial items.46
Table 2. Types of Cost-Reimbursement Contracts
Type
Description
Use
Cost contracts
Contractor reimbursed for allowable costs up
Used for research and development projects,
to a specified total cost; no allowance for
especially those involving nonprofits (e.g.,
profit
colleges and universities)
Cost-sharing
Contractor is reimbursed for some allowable
Used when the contractor expects “substantial
contracts
costs; pays the other costs itself
compensating benefits” (e.g., commercializing
the results of R&D)
Cost-plus-fixed-
Contractor is reimbursed for allowable costs
Used when other contract types cannot be
fee contracts
up to the specified total cost and receives a
used (e.g., requirements for research, study or
negotiated fixed fee for its effortsa
preliminary exploration involving a level of
effort that is presently unknown, or
development or testing under circumstances
where the use of a cost-plus-incentive-fee
contract is impractical)
Cost-plus-a-
Contractor is reimbursed for its costs and
Absolutely prohibited, even as a subcontract
percentage-of-
receives a certain percentage of these costs as
under most types of federal prime contracts
cost contracts
an allowance for profit
Source: Congressional Research Service, based on Subpart 16.3 of the FAR.

(...continued)
OIG Report Notification: “Effect of Payments into Boeing Pension Funds on Economic Price Adjustment Clauses in
DoD Contracts,” Sept. 9, 2009, available at http://www.acq.osd.mil/dpap/policy/policyvault/USA005087-09-
DPAP.pdf (reporting $1.9 billion in price increases on contracts for the C-17 Globemaster aircraft, F/A-18 E/F Super
Hornet aircraft, and AH-64D Apache Longbow helicopter).
43 See, e.g., Formation of Government Contracts, supra note 20, at 1083.
44 48 C.F.R. § 31.201-2 (allowable costs); 48 C.F.R. § 31.201-4 (allocable costs). This means that “costs” can vary by
contract, making it impossible to discuss, in the abstract, which costs may properly be reimbursed.
45 See supra notes 5-6 and accompanying text.
46 48 C.F.R. § 16.301-3(b).
Congressional Research Service
8

Contract Types: An Overview of the Legal Requirements and Issues

a. The fixed fee is independent of actual costs and is adjusted only if the procuring activity changes the work
to be performed under the contract. 48 C.F.R. § 16.306(a).
As commentators have noted, cost-reimbursement contracts can be “high risk” for the
government because the contractor has little incentive to keep the performance costs down given
that the government will ultimately pay these costs.47 These risks are even greater when the
contractor is assured of not only recovery of its costs, but also profit based on a percentage of the
costs (i.e., cost-plus-a-percentage-of-cost contracts).48 Cost-reimbursement contracts also impose
certain administrative demands upon procuring activities that are generally not present with fixed-
price contracts. Among other things, procuring activities must (1) ensure that the contractor’s
accounting system is adequate for determining the costs applicable to the contract and (2) conduct
“appropriate … surveillance” of the contractor during performance.49 Further, cost-
reimbursement contracts can give rise to disputes between the parties over whether particular
costs are allowable under or allocable to the contract.50
However, the alleged risks of cost-reimbursement contracts can be lessened with effective
government oversight of contractor performance,51 and the contracts themselves contain certain
protections for the government. Key among these protections are limitations on allowable costs
and total costs.52 The government is only required to reimburse the contractor for costs that are
allowable under and allocable to the contract, and the maximum total cost that the government
must potentially reimburse is fixed at the time of contracting. Under the terms of the contract, the
contractor must notify the government when costs approach or exceed this total. The government
then has the right—but not the obligation—to approve additional costs.53 If the government
approves additional costs, the contractor must continue working until the funds are spent or
performance is completed. However, if the government does not approve the additional costs, the
contractor is expected to cease performance. If it does not cease performance, it generally cannot
recover any further costs from the government.54 Cost-plus-fixed-fee contracts are also subject to
limitations on the amount of the fixed fee, which generally cannot exceed 10% of the estimated
cost (6% for architectural and engineering work; 15% for experimental, research or development
work).55

47 See, e.g., Improving Government Acquisition, supra note 2.
48 Muschany v. United States, 324 U.S. 49, 61-62 (1944) (“The evil of such contracts is that the profit of the other party
to the contract increases in proportion to that other party’s costs expended in the performance.”).
49 48 C.F.R. § 16.301-3.
50 See, e.g., 2-19 Gov't Cont.: L., Admin. & Proc. § 19.20.
51 See, e.g., Geoffrey Emeigh, DOD Acquisition Experts Chime in on SASC Weapon Systems Acquisition Reform
Agenda, Fed. Cont. Daily, Mar. 4, 2009 (quoting Jacques Gansler, former Under Secretary of Defense for Acquisition,
Technology & Logistics, as stating that the government has not been using cost-type contracts as effectively as it
could).
52 48 C.F.R. § 52.216-7 (allowable costs and payment); 48 C.F.R. § 52.232-20(a) (limitation on costs).
53 See, e.g., Eyler Assocs., ASBCA 16804, 75-1 BCA ¶ 11,320 (1975) (contracting officer has substantial discretion in
determining whether to fund an overrun); ARINC Research Corp., ASBCA 15861, 72-2 BCA ¶ 9,721 (1972) (same).
54 However, in certain circumstances, the government’s failure to fund a cost overrun could constitute an abuse of
discretion. See, e.g., Gen. Elec. Co. v. United States, 440 F.2d 420 (Ct. Cl. 1971) (government abused its discretion in
failing to fund a cost overrun when the circumstances were such that the contractor could not have known of the
overrun).
55 48 C.F.R. § 15.404-4(c)(4)(i). The FAR authorizes payment of this fixed fee either (1) upon completion and delivery
of a specified end product or (2) after the contractor has worked at a specified level of effort for an agreed upon period
of time. 48 C.F.R. § 16.306(d)(1)-(2). Payment upon completion is preferred and must be used “whenever the work …
can be defined well enough to permit development of estimates within which the contractor can be expected to
(continued...)
Congressional Research Service
9

Contract Types: An Overview of the Legal Requirements and Issues

Incentive Contracts
The various types of incentive contracts—fixed-price incentive contracts, cost-plus-incentive-fee
contracts, and cost-plus-award-fee contracts—are often characterized as occupying a “middle
ground” between fixed-price and cost-reimbursement contracts because the parties share the risk
by basing the contractor’s profits, in part, on the cost or quality of its performance.56 The various
types of incentive contracts are alike in that they provide for the contractor to get (1) a specified
base fee and (2) the opportunity to earn additional fees (i.e., incentive or award fees) based upon
its performance in meeting cost, schedule, or technical goals under the contract.57 They differ in
the basis upon which the additional fee is determined and, in the case of incentive-fee contracts,
the circumstances in which they can be used.
With cost-plus-award-fee contracts, the award fee is entirely separate from the base fee58 and is
determined based on the procuring activity’s subjective evaluation of the contractor’s
performance.59 Such determinations are generally final and are not subject to the “disputes
clause” of the contract, which otherwise permits the contractor to contest certain matters with the
government.60 However, in Burnside-Ott Aviation Training Center v. Dalton, the U.S. Court of
Appeals for the Federal Circuit held that such unilateral determinations by the government are
subject to dispute when they are arbitrary and capricious.61
With fixed-price incentive contracts and cost-plus-incentive-fee contracts, in contrast, the
incentive fee is determined based upon formulaic adjustments of the base fee.62 The formula for
fixed-price incentive contracts focuses upon “the relationship of total final negotiated cost to total
target cost”63 and can include either (1) the target cost, the target profit, and the price ceiling, in
the case of firm-target incentives64 or (2) the initial target cost, the initial target profit, the ceiling
price, and the initial profit adjustment formula that is used at an agreed-upon point during
performance to establish the target profit, in the case of successive-target incentives.65 The
formula for cost-plus-incentive-fee contracts focuses upon “the relationship of total allowable

(...continued)
complete the work.” 48 C.F.R. § 16.306(d)(3). Payment based upon work at a specific level of effort for an agreed upon
period of time may be used only when the contract requires the contractor “to provide a specific level of effort within a
definite time period.” 48 C.F.R. § 16.306(d)(4).
56 See, e.g., Formation of Government Contracts, supra note 20, at 1061.
57 Because exclusive focus upon meeting delivery or technical performance goals can result in excessive costs, any
contract including delivery or technical performance goals must also include cost goals. 48 C.F.R. § 16.403(a); 48
C.F.R. § 16.405-1(a); 48 C.F.R. § 16.405-2.
58 48 C.F.R. § 16.405-2.
59 48 C.F.R. § 16.401(e)(2). The FAR requires that cost-plus-award-fee contracts include award-fee plans, specifying
the procedures that the procuring activity will use when evaluating the contractor’s performance to determine award
fees. 48 C.F.R. § 16.401(e)(3). Among other things, these plans provide for “evaluation period(s) to be conducted at
stated intervals during the contract period … so that the contractor will periodically be informed of the quality of its
performance and the areas in which improvement is expected.” Id.
60 41 U.S.C. §§ 601-613 (codification of the Contract Disputes Act); 48 C.F.R. § 52.233-1 (standard disputes clause).
61 107 F.3d 854 (Fed. Cir. 1997), aff’g Burnside-Ott Aviation Training Center, ASBCA 43184, 96-1 BCA ¶ 28,102
(1996). See also Textron Defense Sys., A Div. of AVCO Corp., ASBCA 47352, 47950, 96-2 BCA ¶ 28,332 (1996).
62 48 C.F.R. § 16.403(a); 48 C.F.R. § 16.405-1(a).
63 48 C.F.R. § 16.403(a).
64 48 C.F.R. § 16.403-1(a).
65 48 C.F.R. § 16.403-2(a)(1).
Congressional Research Service
10

Contract Types: An Overview of the Legal Requirements and Issues

costs to total target cost”66 and includes the target cost, the target fee, the minimum fee, and the
maximum fee as components.67 The FAR contemplates that cost-plus-incentive-fee contracts will
be used more narrowly than fixed-price incentive contracts (i.e., for research and development
projects).68
Contractors who fail to meet incentive-related goals often also fail to meet other terms of the
contract, which could carry different penalties. For example, failure to meet a technical
performance goal could constitute failure to meet a specification requirement. However, the
penalty for the former is a reduction in profits or fees, while the penalties for the latter could
involve rejection of the work by the contracting officer, redoing the work so that it meets the
specifications, or termination for default. Most contracts reportedly do not make clear that the
government is not entitled to a “double remedy” in these situations,69 but courts and boards of
contract appeals sometimes construe them to such an effect.70
Time-and-Materials and Labor-Hour Contracts
In a time-and-materials contract, the contractor is paid a fixed hourly rate71 for direct labor
expended during the contract’s performance (e.g., wages, overhead, general and administrative
expenses, profit72), as well as the actual cost of materials.73 The materials covered by a time-and-
materials contract can include direct materials, subcontracts for supplies or incidental services,
other direct costs, and applicable indirect costs.74 However, the FAR specifies that material
handling costs, which include “all appropriate indirect costs allocated to direct materials,” may be
part of the materials cost only if they are not part of the labor-hourly rate.75 It imposes this
requirement to ensure that material handling costs are not “paid twice” in a way that could result
in a prohibited cost-plus-percentage-of-cost system of contracting.76 A labor-hour contract is

66 48 C.F.R. § 16.405-1(a).
67 Id.
68 The FAR states that cost-plus-incentive-fee contracts are “appropriate” for “services or development and test
programs.” 48 C.F.R. § 16.405-1(b)(1). Additionally, cost-plus-incentive-fee contracts, like other cost-reimbursement
contracts, cannot be used to acquire commercial items. 48 C.F.R. § 301-3(b).
69 Formation of Government Contracts, supra note 20, at 1145.
70 See, e.g., North Am. Aviation, Inc., ASBCA 11603, 68-1 BCA ¶ 6,998 (1968); Gen. Precision, Inc., ASBCA 11071,
66-2 BCA ¶ 5,904 (1966).
71 The FAR defines “hourly rate” as “the rate(s) prescribed in the contract for payment for labor that meets the labor
category qualification of a labor category specified in the contract that are – (1) [p]erformed by the contractor; (2)
[p]erformed by the subcontractors; or (3) [t]ransferred between divisions, subsidiaries, or affiliates of the contractor
under a common control.” 48 C.F.R. § 16.601(a). See 48 C.F.R. § 16.601(c)(2) for the detailed requirements for fixed
hourly rates.
72 48 C.F.R. § 16.601(c)(2)(i).
73 48 C.F.R. § 16.601(b).
74 48 C.F.R. § 16.601(a). “Direct materials” are “those materials that enter directly into the end product, or that are used
or consumed directly in connection with the furnishing of the end product or service.” Id.
75 48 C.F.R. § 16.601(c)(3).
76 See, e.g., Gen. Eng'g & Mach. Works v. O’Keefe, 991 F.2d 775 (Fed. Cir. 1993) (affirming a board holding that
recovery of a separate material handling charge and inclusion of material handling costs in the hourly rate of a time-
and-materials contract violated the prohibition on cost-plus-a-percentage-of-cost contracts because it allowed a “double
recovery”).
Congressional Research Service
11

Contract Types: An Overview of the Legal Requirements and Issues

similar to a time-and-materials contract, except the contractor supplies only direct labor, not
materials.77
Subpart 16 of the FAR addresses procuring activities’ use of time-and-materials and labor-hour
contracts in general. It authorizes agencies to use such contracts only when
• the parties cannot accurately estimate the extent or duration of the contract’s work, or
reasonably estimate the costs of the contract, at the time of contracting;78
• the contracting officer prepares a determination and findings (D&F) that “no other
contract is suitable”;79 and
• the contract includes a ceiling price that the contractor exceeds at its own risk.80
Subpart 12 of the FAR imposes additional requirements upon use of time-and-materials and
labor-hours contracts to acquire commercial services.81 Under Subpart 12, agencies may use time-
and-materials and labor-hour contracts to acquire commercial services only under contracts or
orders that were “competitively” awarded.82 Additionally, under Subpart 12, D&Fs must not only
conclude that “no other contract is suitable” but must also: (1) include a description of the market
research that was conducted to reach this conclusion; (2) establish that it is not possible at the
time of contracting or ordering to accurately estimate the extent or duration of the work or
anticipate the costs; (3) establish that the requirement has been structured to maximize use of
firm-fixed-price or fixed-price with economic price adjustment contracts in future acquisitions for
the same requirements (e.g., limiting the length of the contract); and (4) describe plans to
maximize the use of firm-fixed-price or fixed-price with economic price adjustment contracts in
future acquisitions.83

77 48 C.F.R. § 16.602.
78 48 C.F.R. § 16.601(c).
79 48 C.F.R. § 16.601(d)(1)(i). Additionally, the head of the contracting activity must approve the D&F “prior to the
execution of the base period when the base period plus any option periods exceeds three years.” 48 C.F.R. §
16.601(d)(1)(ii).
80 48 C.F.R. § 16.601(d)(1). The contractor must document any subsequent changes in the ceiling price. 48 C.F.R. §
16.601(d)(2).
81 There is, however, presently some uncertainty as to whether purchases under the Federal Supply Schedules, which
list commercial items, are subject to the requirements of Subpart 12 or just those of Subpart 16. The General Services
Administration reportedly has taken the position that the Federal Supply Schedules are not subject to Subpart 12
because the Federal Acquisition Streamlining Act (FASA) of 1994, not the Services Acquisition Reform Act (SARA)
of 2003, authorized use of time-and-materials and labor-hour contracts under the Federal Supply Schedules, and
SARA, not FASA, is the basis for the requirements in Subpart 12. See Gov't Accountability Office, Contract
Management: Minimal Compliance with New Safeguards for Time-and-Materials Contracts for Commercial Services
and Safeguards Have Not Been Applied to GSA Schedules Program, GAO-09-579, June 24, 2009, available at
http://www.gao.gov/new.items/d09579.pdf.
82 48 C.F.R. § 12.207(b)(1)(i). For purposes of Subpart 12.2, this means (1) contracts awarded using competitive
procedures or procedures for other than full and open competition, provided that the procuring activity received offers
from two or more responsible offerors, or (2) orders issued under a multiple-award ID/IQ using the “fair opportunity”
procedures described below. 48 C.F.R. § 12.207(b)(1)(i)(A)-(C). See infra note 104 and accompanying text for more
information on the “fair opportunity” procedures.
83 48 C.F.R. § 12.207(b)(2)(i)-(iv). Subpart 12 similarly limits agencies’ authority to use ID/IQ contracts to acquire
commercial services. See 48 C.F.R. § 12.207(c).
Congressional Research Service
12

Contract Types: An Overview of the Legal Requirements and Issues

Indefinite-Delivery Contracts
The three types of indefinite-delivery contracts—definite-quantity, requirements, and indefinite-
delivery/indefinite-quantity (ID/IQ) contracts—are alike in that they provide for the contractor to
deliver goods or services to the procuring activity at future dates unspecified at the time of
contracting. They differ in the quantity of goods or services that the procuring activity must order
and, thus, in the circumstances in which they are generally used. Definite-quantity contracts
provide for the procuring activity to order a fixed quantity of goods or services from the
contractor over the term of the contract.84 Such contracts are used when the procuring activity
knows that it will require a specific quantity of goods or services that are regularly available or
will be available after a short lead time.85 Requirements contracts, in contrast, provide for the
procuring activity to order all its “requirements” for goods or services of the type provided for in
the contract from the contractor during the term of the contract.86 If the procuring activity has no
requirements for these goods or services, it generally “owes” the contractor no orders.87 However,
if the procuring activity has requirements and purchases them from another vendor88 or, in some
cases, develops additional in-house capabilities to perform the work,89 it could potentially
terminate the contract for convenience or even breach it.90 Requirements contracts are used when

84 48 C.F.R. § 16.501-2(b)(1).
85 48 C.F.R. § 16.502(b).
86 48 C.F.R. § 16.503(a) (“A requirements contract provides for filling all actual purchase requirements of designated
Government activities for supplies or services during a specified contract period.”).
87 See, e.g., G.T. Folge & Co. v. United States, 135 F.2d 117 (4th Cir. 1943) (government not liable for failure to order
if it has no requirements for the goods or services). Any estimates of quantity contained in the solicitation or the
contract are nonbinding. See, e.g., Franklin Co. v. United States, 381 F.2d 416 (Ct. Cl. 1967) (government not obligated
to furnish work orders up to the estimated amount); Kasehagen Sec. Servs., Inc., ASBCA 25629, 86-2 BCA ¶ 18,797
(1986) (contractor must fill orders above the estimate). However, the government could potentially be liable to the
contractor if the estimate was negligently prepared. See, e.g., Alert Care Ambulance Serv., VACAB 2844, 90-3 BCA ¶
22,945 (1990) (government failed to exercise due care in preparing the estimates because it did not consider historical
data regarding prior years’ requirements); Pied Piper Ice Cream, Inc., ASBCA 20605, 76-2 BCA ¶ 12,148 (1976)
(same). If feasible, the contract should specify a maximum quantity of goods or services, orders in excess of which the
contractor is generally not required to meet. 48 C.F.R. § 16.503(a)(2).
88 See, e.g., Rumsfeld v. Applied Cos., Inc., 325 F.3d 1328, 1339 (Fed. Cir. 2003) (“[T]he government breaches a
requirements contract when it has requirements for contract items or services, but diverts business from the contractor
and does not use the contractor to satisfy those requirements.”); Ready-Mix Concrete Co. Ltd. v. United States, 158 F.
Supp. 571 (Ct. Cl. 1958) (contractor entitled to an equitable adjustment if the government purchases the needed
supplies or services from any other source during the contract period).
89 Contract language stating that the contractor is entitled to supply those items “required to be purchased by the
government” will generally be construed to allow the procuring activity to develop additional in-house capacity during
the term of the contract. See, e.g., Export Packing & Crating Co., Inc., ASBCA 16133, 73-2 BCA ¶ 10,066 (1973);
Applied Painting & Decorating Co., ASBCA 15919, 73-2 BCA ¶ 10,358 (1973). However, language stating that the
contractor is entitled to supply items “in excess of the quantities which the activity may itself furnish with its own
capabilities” generally will not be so construed because it is read as referring to the procuring activity’s capabilities at
the time of contracting. See, e.g., Kozak Micro Sys., Inc., GSBCA 10519, 91-1 BCA ¶ 23,342 (1991) (“Where the
contract demands that the contractor provide all the required supplies or services of a named Government activity ‘in
excess of the quantities which the activity may itself furnish with its own capabilities,’ the document is understood to
refer to the capabilities in existence at the time the contract is awarded. The government may not develop and use
additional capabilities to eliminate a part of work that the contractor raised every expectation of receiving, and thereby
prevent the contractor from recovering its costs.”); Maya Transit Co., ASBCA 20186, 75-2 BCA ¶ 11,552 (1975)
(government not permitted to reorder its budget priorities and redistribute its capabilities to assume more bus routes for
its own drivers when the contract provided for the contractor to furnish bus services “in excess of the quantities which
the activity may itself furnish within its own capabilities”).
90 Courts often treat governmental failures to comply with the terms of procurement contracts as constructive
terminations of the contract. See, e.g., Nesbitt v. United States, 543 F.2d 583 (Ct. Cl. 1965); Integrity Mgmt. Int’l, Inc.,
(continued...)
Congressional Research Service
13

Contract Types: An Overview of the Legal Requirements and Issues

the government anticipates recurring requirements but cannot predetermine the precise quantities
needed.91 ID/IQ contracts are also used when the government anticipates recurring needs but
cannot specify the quantity needed.92 However, an ID/IQ contract does not entitle the contractor
to fill all the procuring activity’s requirements for certain goods or services. Rather, the contractor
is assured of orders for only the “minimum quantity” of goods or services specified in the
contract.93 This quantity must be a “more than nominal amount,”94 but recent recommendations
by the Government Accountability Office suggest that $500 can be used as the guaranteed
minimum, regardless of the maximum ordering limitations or total contract value, in the absence
of reliable historical data suggesting otherwise.95
Under indefinite-delivery contracts, the procuring activity issues task or delivery orders to the
contractor when it requires supplies or services, a process which is generally not subject to the
Competition in Contracting Act. However, Congress has imposed certain competition
requirements upon agencies issuing orders under requirements and ID/IQ contracts, in particular.
The Federal Acquisition Streamlining Act (FASA) of 1994 established a “preference” for
multiple-award contracts by requiring agencies to use them, instead of single-award contracts, “to
the maximum extent possible.” 96 A multiple-award contract is one held by several vendors, all of
whom can receive orders under it, while a single-award contract is one held by one vendor, who
is the only vendor who can receive orders under it.97 This preference applies to ID/IQ contracts98
and, potentially, to requirements contracts.99 FASA also requires agencies using multiple-award

(...continued)
ASBCA 18289, 75-1 BCA ¶ 11,235 (1975). However, they will generally not convert failure to order under a
requirements contract into a termination for convenience when the failure was in bad faith or based on circumstances
known to the government at the time of contracting. See, e.g., Torncello v. United States, 681 F.2d 756 (Fed. Cl. 1982)
(termination based on the contractor’s prices, which were known to the government at the time of contracting); Kalvar
Corp. v. United States, 543 F.2d 1298 (Ct. Cl. 1976) (termination in bad faith).
91 48 C.F.R. § 16.503(b)(1).
92 48 C.F.R. § 16.504(b).
93 See, e.g., 48 C.F.R. § 16.504(a)(1); Peter J. Brandon, AGBCA 91-186-1, 92-1 BCA ¶ 24,648 (1991). Provided the
minimum quantity is ordered, the government is not liable for ordering similar goods and services from other
contractors; failing to order any estimated quantities, even if those estimates were negligently prepared; or any costs
that the contractor incurs due to lack of orders. See, e.g., Bliss Co. v. United States, 74 Ct. Cl. 14 (1932) (government
not liable for losses due to the contractor’s plant being idled for lack of orders); Crown Laundry & Dry Cleaners,
ASBCA 39982, 90-3 BCA ¶ 22,993 (1990) (“[W]e do not examine the reasonableness of the estimates in indefinite
quantity contracts.”); Alta Constr. Co., PSCBA 1395, 87-2 BCA ¶ 19,720 (1987) (government’s awarding work orders
to a competitor of the contractor does not give rise to a breach of contract claim). An ID/IQ contract may also contain a
maximum quantity, orders in excess of which the contractor generally need not fill. 48 C.F.R. § 16.504(a)(3).
94 Goldwasser v. United States, 325 F.2d 722 (Ct. Cl. 1963) (contract with a minimum quantity of $100 compared to
estimated price of $40,000 “would have been a one-sided bargain, bordering upon lack of mutuality”); Tennessee Soap
Co. v. United States, 126 F. Supp. 439 (Ct. Cl. 1954) (a $10 minimum order was nominal and thus insufficient).
95 Library of Congress, Comp. Gen. Dec. B-318046 (July 7, 2009).
96 P.L. 103-355, § 1004, 108 Stat. 3249-54 (Oct. 13, 1994) (codified at 10 U.S.C. § 2304a(d)(3)) (procurements of
defense agencies); id. at § 1054, 108 Stat. 3261-65 (codified at 41 U.S.C. § 253h(d)(3)) (procurements of civilian
agencies).
97 A single-award ID/IQ contract differs from a requirements contract in that the procuring activity has not committed
to purchasing all its requirements for particular goods and services from that contractor and is free to contract with
other vendors for the same goods and services.
98 See, e.g., 48 C.F.R. § 16.500(a) (“This subpart prescribes policies and procedures for making awards of indefinite-
delivery contracts and establishes a preference for making multiple awards of indefinite-quantity contracts.”).
99 See, e.g., Formation of Government Contracts, supra note 20, at 1191 (raising the question of whether single-award
requirements contracts violate FASA). See also Nations, Inc., Comp. Gen. Dec. B-272455 (Nov. 5, 1996) (finding such
(continued...)
Congressional Research Service
14

Contract Types: An Overview of the Legal Requirements and Issues

contracts to provide contractors “a fair opportunity to be considered” when issuing task or
delivery orders in excess of $3,000 unless certain conditions apply.100 The National Defense
Authorization Act for FY2008 (NDAA ‘08) and regulations promulgated under its authority
further strengthened the competition requirements for orders under requirements and ID/IQ
contracts by prohibiting agencies from using single-award contracts whose anticipated value
exceeds $103 million, including options, unless the agency head makes certain determinations in
writing.101 The NDAA ‘08 also defined what constitutes a “fair opportunity to be considered” for
orders in excess of $5.5 million under multiple-award contracts.102 Also, in the interests of
promoting competition, agencies are likewise prohibited from awarding requirements contracts
for “advisory and assistance services”103 in excess of three years and $12.5 million, including
options, unless certain conditions are met.104
Other Agreements Under Part 16 of the FAR
Letter Contracts
There are times when an agency’s need for a contractor’s goods or services is so pressing that the
agency cannot wait for the execution of a formal (i.e., definitized) contract. However, contractors

(...continued)
a violation when the procuring activity proposed to issue a single requirements contract whose anticipated value was
over $10 million).
100 10 U.S.C. § 2304c(b)(1)-(4); 41 U.S.C. § 253j(b)(1). For an agency to issue an order without providing contractors
“a fair opportunity to be considered,” the following conditions must be satisfied: (1) the agency’s need for the goods or
services is of “unusual urgency;” (2) only one contractor is capable of providing the goods or services; (3) the order
should be issued on a sole-source basis in the interests of economy and efficiency because it is “a logical follow-on” to
an order issued on a competitive basis; or (4) the order must be placed with a particular contractor to satisfy a minimum
guarantee under an ID/IQ.
101 P.L. 110-181, § 843, 122 Stat. 236-39 (Oct. 14, 2008). Before using a single-award contract, the agency head must
find that (1) the orders expected under the contract are “so integrally related” that only a single source can reasonably
perform them; (2) the contract provides for only firm-fixed-price orders for goods or services whose prices are
established in the contract; (3) only one source is qualified and capable of performing the work at a reasonable price; or
(4) because of exceptional circumstances, it is “necessary in the public interest” to award the contract to a single
source. Id. Agency heads must notify also Congress within 30 days after making a determination to award a single-
award contract in excess of $103 million. P.L. 110-181 applies to the requirements and ID/IQ contracts of both defense
and civilian agencies. An earlier law had imposed similar restrictions on DOD’s requirements and ID/IQ contracts, but
this provision was subsequently repealed because it was redundant. See National Defense Authorization Act for
FY2009, P.L. 110-417, § 863(f), 122 Stat. 4548 (Oct. 14, 2008) (repealing defense-specific requirements); National
Defense Authorization Act for FY2002, P.L. 107-107, § 803, 115 Stat. 1179 (Dec. 28, 2001) (establishing defense-
specific requirements).
102 P.L. 110-181, § 843. Under the NDAA, for contractors to have a fair opportunity to be considered, agencies must
provide them with (1) a notice of the task or delivery order that includes a clear statement of the agency’s requirements;
(2) a reasonable period of time to provide a proposal in response to the notice; (3) disclosure of the significant factors
and subfactors that the agency expects to consider in evaluating proposals and their relative importance; (4) a written
statement documenting the basis for the award and the relative importance of quality and price or cost factors, if the
award is to be made on a best-value basis; and (5) an opportunity for post-award debriefing. Id.
103 As used here, “advisory and assistance services” include “those services provided under contract by
nongovernmental sources to support or improve: organizational policy development; decision-making; management
and administration; program and/or project management and administration; or R&D activities.” 48 C.F.R. § 2.101.
104 Before issuing a solicitation for such a contract, the contracting officer or other designated official must determine
in writing that the services are “so unique or highly specialized that it is not practicable to make multiple awards.” 48
C.F.R. § 16.503(d)(1)-(2).
Congressional Research Service
15

Contract Types: An Overview of the Legal Requirements and Issues

recognize that performing in the absence of a legal commitment binding the government to
compensate them is risky and could result in their “being called a mere volunteer and ...
recover[ing] nothing.”105 As a result, the government developed letter contracts (also known as
undefinitized contracts).106 These are temporary contracts intended to “authorize immediate
commencement of … work” prior to the execution of the final contract.107 Letter contracts
typically state that a formal contract will be executed at a later date and incorporate certain terms
and conditions by reference.108 When letter contracts are used, they are subject to numerous
requirements,109 including a requirement that the contract cannot “[c]ommit the Government to a
definitive contract in excess of the funds available at the time the letter contract is executed.”110 In
the event that a definitive contract cannot be negotiated because of failure to reach agreement as
to price or fee after reasonable efforts, the contractor must proceed with the work, and the
contracting officer may determine a reasonable price or fee with the approval of the head of the
procuring activity.111
Courts may or may not consider letter contracts to be legally binding, depending upon the
language contained in the contracts. If, for example, the document contains a clear and
unconditional acceptance of the offer, then the government will generally be found to have been
bound as of the date it was issued.112 However, if the government’s acceptance is conditioned
upon execution of a formal contract, the document will generally be found not to be legally
binding.113
Letter contracts are of particular concern to Congress because of the potential for agencies to
commit themselves to spending in excess of appropriations.114 Because letter contracts only
contain general terms, many terms and conditions, including price, often have not been negotiated

105 2-19 Gov't Cont.: L., Admin. & Proc. § 19.160 [1]. See also Baltimore & Ohio R.R. v. United States, 261 U.S. 592
(1923).
106 2-19 Gov't Cont.: L., Admin. & Proc. § 19.160 [1].
107 Id.; 48 C.F.R. § 16.603-1.
108 See Briggs & Turivas v. United States, 83 Ct. Cl. 664 (1936). The FAR requires contracting officers to include
within the letter contract the standard contract clauses for the type of contract that is contemplated by the letter contract.
48 C.F.R. § 16.603-4(a).
109 See 48 C.F.R. §§ 16.603-2—16.603-3.
110 48 C.F.R. § 16.603(a)-(b).
111 48 C.F.R. § 16.603-2(c). The contractor is required to continue work under the standard contract clause found at 48
C.F.R. § 52.216-25. However, because of the lack of detailed terms in the letter contract, litigation can result if the
letter is not converted into a detailed contract. See, e.g., Chrysler Corp., ASBCA 4749, 60-2 BCA ¶ 2,669 (1960).
112 See, e.g., Secretary of Navy, Comp. Gen. Dec. B-22324 (Dec. 15, 1941). So long as the letter is sufficiently clear
that the contractor can proceed with the work and the government can make substantial payments on the account,
courts will generally hold that a contract was created and therefore allow a contractor to sue, despite the absence of a
formal contract. Bass & Assocs. v. United States, 205 F.2d 1386 (Ct. Cl. 1974). However, the FAR requires that
contractors satisfy three requirements to recover pre-contract costs: (1) the costs must be incurred prior to
definitization; (2) the costs must have been incurred directly pursuant to negotiations with the procuring activity; and
(3) the costs would have been allowable if incurred after definitization. See Integrated Logistics Support Sys. v. United
States, 47 Fed. Cl. 248, 256 (2000). The Government’s maximum liability for pre-contract costs is “the estimated
amount necessary to cover the contractor’s requirements for funds before definitization” but cannot exceed 50% of the
estimated costs of the definitized contract unless approved in advance by the authorizing official. See, e.g., General
Servs. Admin., 33 Comp. Gen. 291 (1954).
113 See, e.g., Secretary of Commerce, Comp. Gen. Dec. B-21873 (Dec. 22, 1941).
114 For example, Congress has passed significant restrictions on the use of letter contracts in defense procurements. See
10 U.S.C. § 2326.
Congressional Research Service
16

Contract Types: An Overview of the Legal Requirements and Issues

and agreed upon.115 As a result, the cost of the definite contract cannot easily be predicted.
Additionally, the Comptroller General once expressed concern that letter contracts may violate
the prohibition upon cost-plus-a-percentage-of-cost contracts when the definitive contract is not
executed until the work is finished.116 However, letter contracts are now generally accepted.
Agreements
Although they are included in Part 16 of the FAR, the two types of agreements—basic
agreements and basic ordering agreements—are not contracts.117 Rather, they are written
instruments of understanding, negotiated between procuring activities and contractors, that
contain terms applicable to future contracts118 or orders119 between the parties. Basic agreements
and basic order agreements are used in different circumstances. Basic agreements are used when
the procuring activity anticipates awarding a “substantial number” of contracts to a contractor
with whom it has experienced “significant recurring negotiating problems;”120 while basic
ordering agreements are used when the procuring activity anticipates acquiring a substantial, but
presently unknown, quantities of goods or services.121 However, the two types of agreements are
alike in that they must be reviewed annually before the anniversary of their effective dates.122
Additionally, their terms may be changed only by modifications of the agreement, not by any
contracts incorporating the agreement or orders issued under it.123
Recently Enacted and Proposed Legislation
Like its recent predecessors (see Appendix), the 111th Congress has enacted several statutes that
promote use of fixed-price contracts or limit use of other types of contracts. The American
Recovery and Reinvestment Act (ARRA) of 2009 required that “[t]o the maximum extent
possible, contracts funded under this Act shall be awarded as fixed-price contracts through the use
of competitive procedures.”124 The Weapon Systems Acquisition Reform Act of 2009 did not

115 2-19 Gov't Cont.: L., Admin. & Proc. § 19.160 [1].
116 See General Servs. Admin., 33 Comp. Gen. 291 (1954).
117 48 C.F.R. § 16.702(a) (basic agreement); 48 C.F.R. § 16.703(a) (basic ordering agreement). However, an agreement
could potentially be a contract when consideration and mutuality of assent are present. See, e.g., Almar Indus. Inc. v.
United States, 16 Cl. Ct. 243 (1989); 2-19 Gov't Cont.: L., Admin. & Proc. § 19.170.
118 See 48 C.F.R. § 16.702(b)(1) (basic agreements). These terms must include (1) the clauses required for negotiated
contracts by statute, executive order, and the FAR and (2) any other clauses prescribed by the FAR or agency
regulations that the parties agree to include. Id.
119 See 48 C.F.R. § 16.703(c)(1) (basic ordering agreements). These terms must (1) describe the method for determining
prices to be paid to the contractor for supplies or services; (2) include delivery terms or conditions, or specify how they
will be determined; (3) list one or more procuring activities authorized to issue orders under the agreement; (4) specify
the point at which an order becomes a binding contract (e.g., issuance, acceptance); (5) provide that failure to reach
agreement on price for any order issued before price is established is a dispute under the “disputes clause;” and (6)
include any special data required when “fast payment” procedures will apply to orders. Id.
120 48 C.F.R. § 16.702(a).
121 48 C.F.R. § 16.703(b).
122 48 C.F.R. § 16.702(b)(3) (basic agreements); 48 C.F.R. § 16.703(c)(2) (basic ordering agreements).
123 Id.
124 P.L. 111-5, § 1554, 123 Stat. 302 (Feb. 17, 2009). ARRA further required that agencies post a summary of each
contract that is not fixed-price or competitively awarded on Recovery.gov (http://www.recovery.gov). Id.
Congressional Research Service
17

Contract Types: An Overview of the Legal Requirements and Issues

itself directly address the types of contracts used in major defense acquisition programs,125 but its
sponsors reportedly characterized the act as “push[ing]” DOD to award more fixed-price
contracts for weapon systems by “eliminating” certain risks inherent in such programs.126 The
National Defense Authorization Act for FY2010 similarly expressed the sense of Congress that
the Navy can undertake other measures to acquire new ships and maintain the current fleet with
greater efficiency, including increased use of fixed-price contracts.127 This act also required the
Secretary of Defense to revise the Defense Federal Acquisition Regulation Supplement to ensure
that it reflects all applicable limitations on reimbursement of costs and payment of profits or fees
with respect to costs incurred prior to definitization of letter contracts.128 Additionally, the
Department of Defense Appropriations Act, 2010,129 continued the prohibition on obligating more
than 35% of the funds appropriated under the act for environmental remediation under ID/IQ
contracts valued at $130 million or higher that had appeared in prior appropriations acts.130
The 111th Congress is also considering additional legislation targeting the types of contracts used
by federal agencies. Many bills would promote the use of firm-fixed-price contracts, or limit the
use of other types of contracts, either in general or in particular circumstances. For example, the
Implementing Management for Performance and Related Reforms to Obtain Value in Every
Acquisition Act of 2010 (H.R. 5013) would require the Secretary of Defense to ensure that
contracts for the acquisition of military-purpose nondevelopmental items are firm-fixed-price,131
while the Intelligence Authorization Act for FY2010 (S. 3611) would require the Director of
National Intelligence to conduct and submit to the congressional intelligence committees an
initial vulnerability assessment for each major system and significant items of supply prior to
obligating funds for contracts in excess of $40 million that are not firm-fixed-price.132 Other bills

125 P.L. 111-23, 123 Stat. 1704 (May 22, 2009). A major defense acquisition program is any program that (1) will
exceed $300 million for research, development, testing, and evaluation, or $1.8 billion for total procurement, or (2) is
designated as such by the Secretary of Defense. 10 U.S.C. § 2430.
126 See, e.g., Weapon Systems Acquisition Reform Bill to Back Fixed-Cost Awards, Alter Nunn-McCurdy Related
Terms, Fed. Cont. Daily, Feb. 25, 2009 (quoting Senator Carl Levin).
127 P.L. 111-84, § 1021, 123 Stat. 2444 (Oct. 23, 2009).
128 Id., at § 812, 123 Stat. 2406. This includes, but is not limited to, the requirements in Section 809 of the National
Defense Authorization Act for FY2008 (P.L. 110-181) and 48 C.F.R. § 52-216.26.
129 P.L. 111-118, § 8098, 123 Stat. 3450 (Dec. 19, 2009).
130 See, e.g., Consolidated Security, Disaster Assistance & Continuing Appropriations Act, 2009, P.L. 110-329, § 8103,
122 Stat. 3644 (Sept. 30, 2008); Department of Defense Appropriations Act, 2008, P.L. 110-116, § 8110, 121 Stat.
1339 (Nov. 13, 2007); Department of Defense, Emergency Supplemental Appropriations to Address Hurricanes in the
Gulf of Mexico, and Pandemic Influenza Act, 2006, P.L. 109-148, § 8051, 119 Stat. 2709 (Dec. 30, 2005).
131 H.R. 5013, § 108.
132 S. 3611, § 321. See also Gulf Coast Civil Works Act, H.R. 2269, § 2 (limiting use of cost-reimbursement contracts
in certain construction projects); Improving Management for Performance and Related Reforms to Obtain Value in
Every Acquisition Act of 2010, H.R. 5013, § 408 (establishing an “acquisition savings program” that targets ID/IQ
contracts); National Defense Authorization Act for FY2011, H.R. 5136, § 408 (same); id. at § 832 (requiring
contractors submitting proposals for energy-savings contracts to use firm-fixed-price contracts); Information
Technology (IT) Investment Oversight Enhancement and Waste Prevention Act, S. 920, § 4 (requiring that agencies
whose information technology investment projects vary at least 40% from their original baselines in terms of cost,
schedule, or performance examine use of firm-firm-price contracts for certain requirements); Coast Guard
Authorization Act for FY2010 and 2011, S. 1194, § 502 (limiting the Coast Guard’s authority to enter into letter
contracts); Coast Guard Acquisition Reform Act of 2009, H.R. 1665, § 207 (same); Coast Guard Authorization Act of
2010, H.R. 3619, § 527 (same); National Defense Authorization Act for FY2011, S. 3454, § 841 (establishing certain
requirements for the “business systems” of contractors holding cost-reimbursement, incentive, time-and-materials, and
labor-hour contracts); Department of Defense Authorization Act for FY2011, S. 3455, § 841 (same); id. at § 511
(including capabilities acquired under firm-fixed-price contracts among those eligible for the new acquisition process
for the rapid fielding of capabilities in response to urgent operational needs).
Congressional Research Service
18

Contract Types: An Overview of the Legal Requirements and Issues

would limit agencies’ authority to award fees under incentive contracts by, for example,
prohibiting the award of fees when contractors engage in undesirable conduct (e.g., jeopardizing
the health or safety of government personnel)133 or fail to engage in desired conduct (e.g.,
reporting information into databases on Afghanistan and Iraq contracts).134 Yet other bills would
require additional training (e.g., on formation and administration of cost-reimbursement, time-
and-materials, and ID/IQ contracts ),135 or reporting (e.g., requiring that information on the
amount and nature of the “profit incentive” offered to contractors for achieving or exceeding
specified goals under incentive contracts be reported on USASpending.gov).136 However, in one
case, the proposed legislation (S. 3676) would remove an existing restriction on the use of a
specific contract type by exempting the U.S. Agency for International Development from
compliance with the “fair opportunity” procedures when issuing an order under an ID/IQ to a
small or disadvantaged business.137
Executive Branch Initiatives
Agencies arguably began paying more attention to contract types toward the end of the George W.
Bush Administration (see Appendix). For example, on September 29, 2008, the Department of
Defense announced that it would conduct peer reviews of certain service contracts,138 a process
that includes an evaluation of whether the “[a]ppropriate contract type” was used.139 However,
this attention increased during the Obama Administration, in part because use of fixed-price
contracts is one of the key components of President Obama’s proposals to reform government
contracting.
Obama Memorandum of March 4, 2009
On March 4, 2009, President Obama issued a memorandum on government contracting that
identified use of cost-reimbursement contracts, along with noncompetitive contracts, as
potentially inconsistent with obtaining the “best value” for taxpayers:

133 National Defense Authorization Act for FY2011, S. 3454, § 843 S. 3454 would also limit award fees to private
security contractors (PSCs) operating in areas of combat operations who fail to comply with regulations governing the
conduct of PSCs. Id. at § 831. Similar provisions are included in S. 3455, the Department of Defense Authorization Act
for FY2011. See S. 3455, §§ 842-843.
134 National Defense Authorization Act for FY2011, § 852. See also Department of Homeland Security Appropriations
Act, 2011, S. 3607, § 532 (requiring that all contracts entered into by the Department of Homeland Security that
provide award fees link the fees to successful acquisition outcomes, as specified in terms of cost, schedule or
performance); id., § 552 (prohibiting the use of funds appropriated under the act to pay award or incentive fees to
contractors whose work was judged below satisfactory or that does not meet the basic requirements of the contract).
135 Acquisition Workforce Improvement Act of 2009, S. 2901, § 2 (establishing a government-wide acquisition
management fellows program).
136 Transparency in Government Act of 2010, H.R. 4983, § 501.
137 Department of State, Foreign Operations, and Related Programs Appropriations Act, 2011, S. 3676, § 7034.
138 Office of the Under Secretary of Defense, Acquisition, Technology & Logistics, Peer Reviews of Contracts for
Supplies and Services, Sept. 28, 2008, available at http://www.acq.osd.mil/dpap/policy/policyvault/USA000820-08-
DPAP.pdf.
139 Office of the Under Secretary of Defense, Acquisition, Technology & Logistics, Review Criteria for the Acquisition
of Services, Feb. 18, 2009, available at http://www.acq.osd.mil/dpap/policy/policyvault/USA002735-08-DPAP.pdf.
Congressional Research Service
19

Contract Types: An Overview of the Legal Requirements and Issues

Excessive reliance by executive agencies on sole-source contracts (or contracts with a
limited number of sources) and cost-reimbursement contracts creates a risk that taxpayer
funds will be spent on contracts that are wasteful, inefficient, subject to misuse, or otherwise
not well designed to serve the needs of the Federal Government or the interests of the
American taxpayer.140
The memorandum articulated a “preference for fixed-price type contracts,” with cost-
reimbursement contracts used “only when circumstances do not allow the agency to define its
requirements sufficiently to allow for a fixed-price type contract.”141 It also predicted that
increased use of fixed-price contracts could save taxpayers “billions of dollars” a year142 and
directed the Office of Management and Budget (OMB) to issue guidance on “the appropriate use
and oversight of all contract types” by September 30, 2009.143
OMB Memorandum of July 29, 2009
President Obama’s March 4, 2009 memorandum also called for OMB to issue guidance to assist
agencies in “identify[ing] contracts that are wasteful, inefficient, or not otherwise likely to meet
[their] needs.”144 Although OMB was not required to address contract types when providing this
guidance, it did so in its July 29, 2009, memorandum on “Improving Government Acquisition.”
The July memorandum noted that cost-reimbursement and time-and-materials and labor-hour
contracts “pose special risks of overspending” because “they provide no direct incentive to the
contractor for cost control” and “are often used without an appropriate basis or sufficient
management and oversight to limit taxpayer risk.”145 The memorandum instructed agencies to
“aim to reduce” by at least 10% the funds obligated by “high risk-contracting authorities,” such as
cost-reimbursement, time-and-materials, and labor-hour contracts, in FY2010.146 This 10%
reduction is in addition to the requirement that agencies develop a plan to save 7% of “baseline”
(FY2008) contract spending by the end of FY2011.147
OMB Memorandum of October 27, 2009
On October 27, 2009, OMB issued the guidance on the appropriate use and oversight of various
contract types called for in President Obama’s March 4, 2009, memorandum. The October
memorandum provided a framework organized around three “key questions,” illustrated in Table
3
, for selecting the best contract type for particular acquisitions and, if necessary, transitioning
recurring or follow-on work to “lower-risk” contract types.148 It reiterated that agencies are to

140 The White House, Office of the Press Secretary, Government Contracting, Mar. 4, 2009, at ¶ 3, available at
http://www.whitehouse.gov/the_press_office/Memorandum-for-the-Heads-of-Executive-Departments-and-Agencies-
Subject-Government.
141 Id. at ¶ 8.
142 Id. at ¶ 2.
143 Id. at ¶ 10.
144 Id. at ¶ 8.
145 Improving Government Acquisition, supra note 2, at 2.
146 Id.
147 Id. at 1. Agencies were to submit by November 2, 2009, plans to achieve 7% of baseline spending by FY2011 and
reduce their use of “high risk” contract types. See OMB Official Defends Moves to Reform Federal Procurement
System, Fed. Cont. Daily, Oct. 30, 2009.
148 Executive Office of the President, Office of Management and Budget, Increasing Competition and Structuring
(continued...)
Congressional Research Service
20

Contract Types: An Overview of the Legal Requirements and Issues

reduce by at least 10% the funds obligated by new contracts that are cost-reimbursement, time-
and-materials, or labor-hour contracts, among other things, in FY2010.149 It also stated that the
Office of Federal Procurement Policy (OFPP) within OMB will review agencies’ progress vis-à-
vis this target on a semiannual basis in FY2010 and require corrective action plans where
necessary.150 OFPP will set new targets for FY2011 and later years, as well as “work with
agencies to identify best practices, new techniques and strategies, areas in need of additional
guidance or policy, and measures and benchmarks.”151
Table 3. OMB Guidance on “Appropriate Use and Oversight” of Contract Types
Key Question
Considerations
How is the agency
• Determine the level of uncertainty
choosing the best
contract type for
• Use incentives to motivate lower costs with improved delivery or technical performance
the acquisition?
and discourage contractor inefficiency and waste
How is the agency
• Ensure contractor costs are reasonable and the contractor is making progress in
mitigating the risk
accordance with the contract’s performance schedule (e.g., determine the contractor’s
when cost-
accounting system is adequate, have in place appropriate government surveillance to provide
reimbursement or
reasonable assurance that efficient methods and effective costs controls are in place)
time-and-materials/
labor-hour
• Link payment to performance on cost-plus-award-fee contracts (e.g., determine an award-
contracts are used? fee contract is appropriate; tie fees to cost, timeliness, and the quality of the contractor’s
performance; fol ow prescribed standards for differentiating between levels of performance
and the corresponding percentage of available award fee that can be earned; prohibit “roll
over” of award fees and payment of award fees for unsatisfactory performance)
• Determine the appropriateness of time-and-materials or labor-hour contracts in
commercial acquisitions (i.e., ensure sufficient analysis underlies the decision, including an
explanation of why a fixed-price contract is unsuitable)
• Provide for the necessary skills and capacity in the acquisition workforce to award and
manage a cost-type contract
How is the agency
• Use appropriate mechanisms, such as contract review boards, peer reviews, or contract
creating
type advocates to bring additional expertise to bear in determining the best contract type
opportunities to
transition to
• Award contracts that al ow the agency to choose between a fixed-price, cost-
“lower risk”
reimbursement, or time-and-materials or labor-hour basis for the payment of different
contracts?
contract requirements
Source: Congressional Research Service, based on “Increasing Competition and Structuring Contracts for the
Best Results,” http://www.whitehouse.gov/sites/default/files/omb/assets/procurement_gov_contracting/
increasing_competition_10272009.pdf.

(...continued)
Contracts for Best Results, Oct. 27, 2009, at Attachment, pp. 2-11, available at http://www.whitehouse.gov/omb/assets/
procurement_gov_contracting/increasing_competition_10272009.pdf.
149 Id. at 1.
150 Id. at 2. In December 2009, OMB reported that agencies are generally “on track” to achieve this 10% reduction in
FY2010. See Acquisition and Contracting Improvement Plans and Pilots: Saving Money and Improving Government,
Dec. 2009, available at http://www.whitehouse.gov/omb/assets/reports/
2009_acquisition_contracting_improvement.pdf.
151 Id.
Congressional Research Service
21

Contract Types: An Overview of the Legal Requirements and Issues

Effectiveness of These Initiatives Presently Unknown
It remains to be seen how effective the Obama Administration’s initiatives will be in curtailing
use of cost-reimbursement and other allegedly “high risk” types of contracts.152 Some
commentators expect agencies to award more fixed-price contracts, in keeping with President
Obama’s contracting agenda.153 This view may be supported by certain recent, high-profile
contract actions, such as the Air Force’s proposal to award a fixed-price incentive contract for its
KC-X aerial refueling tanker recapitalization program.154 However, other commentators suggest
that focusing upon contract types is unlikely to lead to the reforms necessary to improve federal
contracting or make it more cost-effective.155 The persistence of cost-reimbursement contracts
under the ARRA may support this latter view. When enacting ARRA, Congress required that
agencies use fixed-price contracts “[t]o the maximum extent possible.”156 However, as of
February 2010, $9.3 billion in ARRA funds had reportedly been obligated by non-fixed-price
contracts, while $11.1 billion had been obligated by fixed-price contracts.157

152 Preliminary reports from OMB suggest that agencies’ use of new cost-reimbursement, time-and-materials, and
labor-hour contracts was lower in the first half of FY2010 than it was in the first half of FY2009. See Office of Mgmt.
& Budget, Cutting Waste and Saving Money through Contracting Reform, July 7, 2010, available at
http://www.whitehouse.gov/omb/assets/blog/Update_on_Contracting _Reforms.pdf. Additionally, many agencies have
reportedly undertaken initiatives to improve their acquisition workforce’s capability to manage “high risk” contract
types. See Office of Mgmt. & Budget, Acquisition and Contracting Improvement Plans and Pilots: Saving Money and
Improving Government, Dec. 2009, available at http://www.whitehouse.gov/sites/default/files/omb/assets/reports/
2009_acquisition_contracting_improvement.pdf.
153 See, e.g., Firm-Fixed Price Contract Awards Require Discipline on DOD’s Part, Comptroller Says, Fed. Cont.
Daily
, Mar. 20, 2009.
154 See, e.g., Northrop May Opt Out of Tanker Competition if DOD Does Not Modify Solicitation Language, Fed.
Cont. Daily
, Dec. 3, 2009.
155 See, e.g., Steve Kelman & Steve Schooner, Achieving Effective Reform, Fed. Times, Apr. 13, 2009, at 23 (“Most
contracting experts … would put [the reforms proposed in Obama’s March 4 memorandum] low on the priority list of
the myriad targets of opportunity for improving the procurement system.”); Matthew Weigelt, Contractors Wary of
Procurement Proposals, Wash. Tech., Mar. 27, 2009, available at http://washingtontechnology.com/articles/2009/03/
30/procurement-contract-reform.aspx (“From what they heard, many information technology companies contracting
with the government didn’t consider Obama’s proposed procurement reforms as anything approaching a sea change.…
For instance, contracting regulations already favor fixed-price contracts as the safe and preferred method instead of
cost-reimbursement and especially time-and-materials contracts. Many experts doubted that new guidance would
improve on that.”); New Nonprofit Organization Will Work to Promote Acquisition Reform, Innovation, Fed. Cont.
Daily
, Apr. 27, 2009 (quoting the newly formed Federal Acquisition and Reform Institute as expressing the view that
the discussion needs to be “elevated” from “tactics, such as types of contracts, to a more strategic one”).
156 P.L. 111-5, § 1554, 123 Stat. 302.
157 See, e.g., Deborah Billings, Obama Highlights Transparency of Recovery Act Implementation, 93 Fed. Cont. Rep.
133 (Feb. 23, 2010). See also Gov't Accountability Office, Recovery Act: Contract Oversight Activities of the
Recovery Accountability and Transparency Board and Observations on Contract Spending in Selected States, GAO-10-
216R, Nov. 30, 2009, at 7-8, available at http://www.gao.gov/new.items/d10216r.pdf (noting that, although state
officials reported that 73% of federally funded contracts under ARRA were awarded using fixed-price contracts, some
officials identified contracts as fixed-price when there was a fixed price per unit but the total quantities were
undefined).
Congressional Research Service
22

Contract Types: An Overview of the Legal Requirements and Issues

Appendix. Chronology of Developments Regarding
Contract Types, 107th-110th Congresses

Dec. 28,
National Defense Authorization Act for FY2002 (P.L. 107-107, §§ 802-803158) set as an “objective” for DOD
2001
to achieve savings in expenditures for services by using “appropriate” competition of task orders under
service contracts. Also required DOD to award orders in excess of $100,000159 issued under multiple-award
contracts on a competitive basis160 unless certain circumstances apply.161
Nov. 24, National Defense Authorization Act for FY2004 (P.L. 108-163, §§ 847 and 1432) made firm-fixed-price or
2003
fixed-price with economic price adjustment contracts or subcontracts for certain weapons-related prototype
projects valued at less than $50 million eligible for a pilot program for follow-on contracting for the
production of items or processes. Also authorized use of time-and materials or labor-hour contracts to
purchase commercial services that are (1) commonly sold to the general public through such contracts and
(2) purchased on a competitive basis.
Jan. 6,
National Defense Authorization Act (P.L. 109-163, § 817) established a joint training program on contingency
2006
contracting, including the appropriate use of letter contracts, ID/IQ task orders, and letter contracts.
July 11,
Coast Guard & Maritime Transportation Act of 2006 (P.L. 109-241, § 205) authorized the use of “one-step
2006
turn-key selection procedures” in contracting for construction projects. Such procedures are “used for the
selection of a contractor on the basis of price and other evaluation criteria to perform, in accordance with
the provisions of a firm fixed-price contract, both the design and construction of a facility.”
Oct. 4,
Department of Homeland Security Appropriations Act, 2007 (P.L. 109-295, § 692) general y prohibited
2006
contractors holding cost-reimbursement contracts or task or delivery orders for disaster or emergency
response or recovery valued at over $100,000 from subcontracting more than 65% of the cost of the
contract or order.162
Oct. 17,
John Warner National Defense Authorization Act for FY2007 (P.L. 109-364) required the Departments of
2006
Defense and State and the U.S. Agency for International Development to identify the types of contracts used
in Iraq and Afghanistan (§ 854).163 Also required various entities to perform “comprehensive and detailed
cost analyses” of the Joint Strike Fighter engine program covering, among other things, an alternative under
which the programs executes a one-time firm-fixed price contract for a selected propulsion system for the
lifecycle of the aircraft fol owing the Initial Service Release of the propulsion system in FY2008 (§ 211).
Authorized the Milestone Decision Authority for a major defense acquisition program to approve use of a
cost-type contract for a development program only upon a written determination that (1) the program is so

158 Section 803 was repealed by the National Defense Authorization Act for FY2009 because it was “redundant” after
Congress imposed identical restrictions on all agencies. See P.L. 110-417, § 863(f), 122 Stat. 4548 (Oct. 14, 2008).
159 The values contained in this chronology are those given in the statute as it was enacted. They do not reflect any
subsequent adjustments made for inflation.
160 For purposes of Section 803, an award is made on a competitive basis if it is made pursuant to procedures that: (1)
require that fair notice of the intent to make a purchase is provided to all contractors offering such services under the
contract and (2) afford all contractors responding to that notice a fair opportunity to make an offer and have that offer
considered. However, notice may be provided to fewer than all contractors offering the service so long as notice is
provided to “as many contractors as is practicable.” If notice is not provided to all contractors, a purchase may not be
made unless either (1) offers were received from at least three qualified contractors or (2) the contracting officer
determines in writing that no additional qualified contractors could be identified despite reasonable efforts to do so.
161 A purchase need not be made on a competitive basis if the contracting officer waives this requirement based upon a
determination, justified in writing, that (1) the agency’s need for the requirements is of “unusual urgency;” (2) only one
contractor is capable of providing the goods or services at the required “level of quality;” (3) the order should be issued
on a sole-source basis in the interests of economy and efficiency because it is a “logical follow-on” to an order that was
competitively issued; or (4) the order must be placed with a particular contractor to satisfy a minimum guarantee.
162 This prohibition does not apply if the Secretary of Homeland Security determines that it is “not feasible or
practicable.”
163 A similar requirement was later included in the National Defense Authorization Act for FY2008. See P.L. 110-181,
§ 861(b), 122 Stat. 253 (Jan. 28, 2008).
Congressional Research Service
23

Contract Types: An Overview of the Legal Requirements and Issues

complex and technical y chal enging that it would not be practicable to reduce program risk to a level that
would permit use of a fixed-price contract and (2) the complexity and technical chal enge of the program is
not the result of a failure to meet the requirements established in 10 U.S.C. 2366a (§ 818).164 Exempted firm-
fixed price contracts, subcontracts, or task or delivery orders awarded on the basis of adequate price
competition or for the acquisition of commercial items from the regulatory provisions proscribing pass-
through charges on DOD contracts that are “excessive” in relation to the cost of work performed by the
contractor or subcontractor (§ 852). Required the Secretary of Defense to issue guidance on the linking of
award and incentive fees to acquisition outcomes (§ 814).165
May 25,
U.S. Troop Readiness, Veterans’ Care, Katrina Recovery & Iraq Accountability Appropriations Act, 2007 (P.L.
2007
110-28, § 6402) prohibited obligation of certain funds appropriated for the Integrated Deepwater Systems
program until the House and Senate Appropriations committees receive and approve a plan for expenditure
that contains “very limited ID/IQ contracts” and explains the need for any ID/IQ contracts.166
Dec. 4,
The Office of Federal Procurement Policy issued a memorandum167 calling on top federal acquisition officials
2007
to (1) review their agencies’ policies on incentive fee contracting to ensure that the fees paid to contractors
are linked to acquisition outcomes; (2) ensure that incentive fees are not earned if the contractor’s
performance is judged to be below satisfactory or does not meet the basic contract requirements; (3)
examine incentive fee contracts as part of the program management review process for agency internal
audits; (4) conduct risk-benefit analyses to determine whether to use incentive fee contracts and (5) develop
guidance indicating that rollover of unearned fees is “not preferred.”
Jan. 28,
National Defense Authorization Act for FY2008 (P.L. 110-181, §§ 805 and 809) restricted DOD’s use of
2008
time-and-materials and labor-hour contracts for commercial item acquisitions to (1) services procured for
support of a commercial item; (2) emergency repair services; or (3) other services to the extent that the
agency head approves certain determinations in writing.168 Also required that the Defense Federal
Acquisition Regulation Supplement (DFARS) be amended to include certain requirements pertaining to the
use of letter contracts.169

(...continued)
164 Section 818 repeals Section 807 of the National Defense Authorization Act for FY1989, which prohibited the use of
firm-fixed-price contracts in excess of $10 million for the development of major systems or subsystems unless the
Secretary of Defense determined in writing that the program risk had been reduced to the extent that realistic pricing
can occur and the contract type permits an “equitable and sensible” allocation of risk between the contracting parties.
See P.L. 100-456, § 807, 102 Stat. 2011 (Sept. 29, 1988).
165 Among other things, this guidance must (1) ensure all that new contracts using award fees link fees to program cost,
schedule, and performance outcomes; (2) identify circumstances in which contractor performance may be judged
“excellent” or “superior” and the percentage of the available award fee that the contractor should be paid for such
performance; (3) establish standards for determining what percentage of an award fee, if any, should be paid for
performance judged “acceptable,” “expected,” “good,” or “satisfactory;” (4) ensure no award fee is paid to contractors
for performance that is less than satisfactory or does not meet basic contract requirements; and (5) provide “specific
direction” on any circumstances in which award fees not earned during one award fee period may be rolled over to
subsequent award fee periods.
166 Identical language was later included in the Consolidated Appropriations Act, 2008. P.L. 110-161, 121 Stat. 2055
(Dec. 26, 2007).
167 Executive Office of the President, Office of Management and Budget, Appropriate Use of Incentive Contracts,
available at http://www.whitehouse.gov/omb/procurement/memo/incentive_contracts_120407.pdf.
168 These determinations must find (1) that the services to be acquired are commercial services; (2) the offeror of the
services has submitted sufficient information under 41 U.S.C. § 403(12)(F)(b); (3) similar services are commonly sold
to the general public through the use of time-and-materials or labor-hour contracts; and (4) the use of a time-and-
materials or labor-hour contract is in the best interest of the government.
169 These requirements must include, at a minimum, the circumstances in which it is appropriate to use letter contracts;
approval requirements for use of letter contracts; procedures for ensuring that timelines for definitization are met;
procedures for ensuring compliance with limitations on the obligation of funds pursuant to letter contracts; procedures
for ensuring compliance with limitations on profits or fees with respect to costs incurred prior to definitization; and
reporting requirements for letter contracts that fail to meet timelines or comply with limitations on obligation of funds
or profits or fees.
Congressional Research Service
24

Contract Types: An Overview of the Legal Requirements and Issues

Mar. 20,
DOD issued a memorandum reminding senior contracting officials that time-and-materials contracts “are the
2008
least preferred contract type.”170
Apr. 23,
DOD proposes a rule171 that would require certain determinations and findings for non-commercial time-
2008
and-materials contracts, including (1) “sufficient facts and rationale to justify that no other contract type is
suitable;” (2) a description of the market research conducted; (3) information establishing that it is not
possible at the time of placing the contract or order to estimate with accuracy the extent or duration of the
work to be performed or to anticipate the costs with any reasonable degree of accuracy; (4) information
establishing that the requirement has been structured to minimize the use of time-and-materials
requirements; and (5) a description of the actions planned to minimize the use of time-and-materials
contracts on future acquisitions for the same requirements. Rule would also require that contracting officers
structure ID/IQ contracts that authorize time-and-materials orders to also authorize orders on other bases,
to the maximum extent practicable and execute determinations and findings for each order placed on a time-
and-materials basis, if the contract allows other types of orders, or for the underlying contract, if it
authorizes only time-and-materials orders.
July 14,
DOD issued memorandum172 reminding contracting officers that they are to prepare quality assurance plans
2008
along with the statement of work or objectives when using time-and-materials or labor-hour contracts and
noting that the contracting officer’s representative’s surveillance functions should correspond with the dollar
value and complexity of the contract.
Oct. 14,
Duncan Hunter National Defense Authorization Act for FY2009 (P.L. 110-417) subjected non-defense
2008
agencies to the competition requirements pertaining to the issuance of orders in excess of $100,000 under
multiple-award ID/IQ contracts that defense agencies had been subject to under the National Defense
Authorization Act for FY2002, as wel as required public notice of all sole-source orders placed against a
multiple-award contract except in cases involving “extraordinary circumstances” or classified orders (§ 863).
Required that the FAR be amended to include certain guidance on the use of cost-reimbursement
contracts173 and required the inspectors general of certain agencies174 and the Director of OMB to produce
reports regarding use of cost-reimbursement contracts and, in the case of OMB, task and delivery orders
(§864).175 Imposed limitations on tiering of subcontractors on cost-reimbursement contracts or task or
delivery orders issued by non-defense agencies176 in order to “ensure that neither a contractor nor a
subcontractor receives indirect costs or profit on work performed by a lower-tier subcontractor to which
the higher-tier contractor or subcontractor adds no, or negligible, value” (§ 866).177 Also required that the
FAR be amended to provide non-defense agencies with guidance on the appropriate use of award and

170 Office of the Under Secretary of Defense, Acquisition, Technology & Logistics, Proper Use of Time-and-Materials
Contract Types, Mar. 20, 2008, available at http://www.acq.osd.mil/dpap/policy/policyvault/2008-0173-DPAP.pdf.
171 Dep't of Defense, DFARS Case 2007-D021: Limitations on DoD Non-Commercial Time-and-Materials Contracts,
73 Fed. Reg. 21891 (Apr. 23, 2008). The final rule was promulgated on November 24, 2008. See 73 Fed. Reg. 70912.
172 Office of the Under Secretary of Defense, Acquisition, Technology & Logistics, Management of Contractor
Performance under Time & Material and Labor Hour Contracts for Services, July 14, 2008, available at
http://www.acq.osd.mil/dpap/policy/policyvault/2008-0320-DPAP.pdf.
173 This guidance must include, at a minimum, (1) when and under what circumstances cost-reimbursement contracts
are appropriate; (2) the acquisition plan findings necessary to support the decision to use a cost-reimbursement
contract; and (3) the acquisition workforce resources necessary to award and manage cost-reimbursement contracts.
174 This reporting requirement applies only to agencies that awarded contracts or issued orders totaling at least $1
billion in the prior fiscal year. For these agencies, the inspectors general are to report on the results of their view of the
agency’s compliance with the new FAR provisions in their next semiannual report.
175 OMB is to submit an annual report to Congress on the total number and value of contracts awarded during the
covered fiscal year, the total number and value of cost-reimbursement contracts and orders issued during that year; and
an assessment of the effectiveness of the new FAR provisions in ensuring appropriate use of cost-reimbursement
contracts.
176 Section 866 explicitly provided that defense agencies are to remain subject to the limitations on tiering of
subcontractors contained in Section 852 of the John Warner National Defense Authorization Act of Fiscal Year 2007,
P.L. 109-364 120 Stat. 2340.
177 This provision does not apply to charges for indirect costs or profit based on the direct costs of managing lower-tier
subcontracts.
Congressional Research Service
25

Contract Types: An Overview of the Legal Requirements and Issues

incentive fees like that required for defense agencies under P.L. 109-364 (§ 867).178


Author Contact Information

Kate M. Manuel

Legislative Attorney
kmanuel@crs.loc.gov, 7-4477


Acknowledgments
CRS Legislative Attorney Carol J. Toland contributed to an earlier version of this report.



(...continued)
178 Among other things, this guidance must (1) ensure that all new contracts using award fees link such fees to
acquisition outcomes; (2) establish standards for identifying the appropriate level of officials authorized to approve the
use of award and incentive fees in new contracts; (3) identify circumstances in which contractor performance may be
judged “excellent” or “superior” and the percentage of the award fee that the contractor should be paid for such
performance; (4) establish standards for determining the percentage of the available award fee, if any, which
contractors should be paid for performance that is judged to be “acceptable,” “average,” “expected,” “good,” or
“satisfactory;” (5) ensure that no award fee may be paid for contractor performance that is judged to be below
satisfactory performance or performance that does not meet the basic requirements of the contract; (6) provide “specific
direction” on any circumstances in which it may be appropriate to roll over award fees that are not earned in one award
fee period to subsequent award fee periods; and (7) include performance measures to evaluate the effectiveness of
award and incentive fees as a tool for improving contractor performance and achieving desired program outcomes.
Congressional Research Service
26