Coast Guard Deepwater Acquisition
Programs: Background, Oversight Issues, and
Options for Congress

Ronald O'Rourke
Specialist in Naval Affairs
September 29, 2010
Congressional Research Service
7-5700
www.crs.gov
RL33753
CRS Report for Congress
P
repared for Members and Committees of Congress

Coast Guard Deepwater Acquisition Programs

Summary
The term Deepwater refers to a collection of more than a dozen Coast Guard acquisition
programs for replacing and modernizing the service’s aging fleet of deepwater-capable ships and
aircraft. Until April 2007, the Coast Guard pursued these programs as a single, integrated
acquisition program that was known as the Integrated Deepwater System (IDS) program or
Deepwater program for short. The now-separated Deepwater acquisition programs include plans
for, among other things, 91 new cutters, 124 new small boats, and 247 new or modernized
airplanes, helicopters, and unmanned aerial vehicles (UAVs).
The year 2007 was a watershed year for Deepwater acquisition. The management and execution
of what was then the single, integrated Deepwater program was strongly criticized by various
observers. House and Senate committees held several oversight hearings on the program. Bills
were introduced to restructure or reform the program in various ways. Coast Guard and industry
officials acknowledged certain problems in the program’s management and execution and
defended the program’s management and execution in other respects. The Coast Guard
announced a number of reform actions that significantly altered the service’s approach to
Deepwater acquisition (and to Coast Guard acquisition in general). Among these was the change
from a single, integrated Deepwater acquisition program to a collection of separate Deepwater
acquisition programs.
The Coast Guard’s management of Deepwater acquisition programs, including implementation of
recommendations made by the Government Accountability Office (GAO), is a topic of continuing
congressional oversight. Additional oversight issues include cost growth in Deepwater acquisition
programs and the execution of individual Deepwater acquisition efforts, particularly those for
surface ships.
The Coast Guard’s proposed FY2011 budget requests $1,112.5 million in acquisition funding for
Deepwater programs, including $101.0 million for aircraft, $856.0 million for surface ships and
boats, and $155.5 million for other items.

Congressional Research Service

Coast Guard Deepwater Acquisition Programs

Contents
Introduction ................................................................................................................................ 1
Background ................................................................................................................................ 1
Deepwater Missions.............................................................................................................. 1
Origin of Deepwater Acquisition Effort ................................................................................. 2
Structure of Deepwater Acquisition Effort ............................................................................. 2
Structure Until 2007........................................................................................................ 2
Revised Structure Since 2007 .......................................................................................... 3
Deepwater Assets Planned for Acquisition............................................................................. 4
Acquisition Program Baseline ......................................................................................... 4
Fleet Mix Analysis .......................................................................................................... 5
Examples of Deepwater Deliveries and Other Milestones ...................................................... 6
Deepwater Acquisition Funding ............................................................................................ 6
Prior-Year Funding.......................................................................................................... 6
FY2011 Funding Request ................................................................................................ 7
Criticism of Deepwater Management in 2007........................................................................ 8
Coast Guard Reform Actions in 2007 .................................................................................... 9
Justice Department Investigation........................................................................................... 9
Oversight Issues for Congress ................................................................................................... 10
Management of Deepwater Programs in General ................................................................. 10
Coast Guard Perspective ............................................................................................... 10
GAO Perspective .......................................................................................................... 12
Cost Growth ....................................................................................................................... 15
Coast Guard Perspective ............................................................................................... 15
GAO Perspective .......................................................................................................... 16
Reporting of Costs and Planned Procurement Quantities ..................................................... 17
National Security Cutter (NSC)........................................................................................... 17
Coast Guard Perspective ............................................................................................... 17
GAO Perspective .......................................................................................................... 19
Sentinel Class Fast Response Cutter (FRC) ......................................................................... 20
Coast Guard Perspective ............................................................................................... 20
GAO Perspective .......................................................................................................... 22
110/123-Foot Patrol Boat Modernization............................................................................. 22
Revolving Door and Potential for Conflicts of Interest......................................................... 23
Potential Options for Congress .................................................................................................. 24
Legislative Activity in 111th Congress........................................................................................ 25
Summary of Appropriations Action on FY2011 Funding Request ........................................ 25
FY2011 DHS Appropriations Bill (S. 3607) ........................................................................ 26
Senate ........................................................................................................................... 26
Coast Guard Authorization Act of 2010 (H.R. 3619)............................................................ 29
House ........................................................................................................................... 30
Senate ........................................................................................................................... 30
Coast Guard Authorization Act for Fiscal Years 2010 and 2011 (S. 1194) ............................ 30
Senate ........................................................................................................................... 30
Coast Guard Acquisition Reform Act of 2009 (H.R. 1665) .................................................. 30
House ........................................................................................................................... 30
FY2010 DHS Appropriations Act (H.R. 2892/P.L. 111-83) .................................................. 31
Congressional Research Service

Coast Guard Deepwater Acquisition Programs

House ........................................................................................................................... 31
Senate ........................................................................................................................... 33
Conference.................................................................................................................... 36

Tables
Table 1. Deepwater Assets Planned for Acquisition ..................................................................... 4
Table 2. Prior-Year Acquisition Funding For Deepwater Programs .............................................. 7
Table 3. FY2010 and FY2011 Acquisition Funding for Deepwater Programs ............................... 8
Table 4. Action on FY2011 Deepwater Acquisition Funding Request......................................... 25

Appendixes
Appendix A. Criticism of Deepwater Management in 2007 ....................................................... 39
Appendix B. Coast Guard Reform Actions in 2007.................................................................... 43

Contacts
Author Contact Information ...................................................................................................... 46

Congressional Research Service

Coast Guard Deepwater Acquisition Programs

Introduction
The term Deepwater refers to a collection of more than a dozen Coast Guard acquisition
programs for replacing and modernizing the service’s aging fleet of deepwater-capable ships and
aircraft. Until April 2007, the Coast Guard pursued these programs as a single, integrated
acquisition program that was known as the Integrated Deepwater System (IDS) program or
Deepwater program for short. The now-separated Deepwater acquisition programs include plans
for, among other things, 91 new cutters, 124 new small boats, and 247 new or modernized
airplanes, helicopters, and unmanned aerial vehicles (UAVs).
The year 2007 was a watershed year for Deepwater acquisition. The management and execution
of what was then the single, integrated Deepwater program was strongly criticized by various
observers. House and Senate committees held several oversight hearings on the program. Bills
were introduced to restructure or reform the program in various ways. Coast Guard and industry
officials acknowledged certain problems in the program’s management and execution and
defended the program’s management and execution in other respects. The Coast Guard
announced a number of reform actions that significantly altered the service’s approach to
Deepwater acquisition (and to Coast Guard acquisition in general). Among these was the change
from a single, integrated Deepwater acquisition program to a collection of separate Deepwater
acquisition programs.
The Coast Guard’s proposed FY2011 budget requests $1,112.5 million in acquisition funding for
Deepwater programs, including $101.0 million for aircraft, $856.0 million for surface ships and
boats, and $155.5 million for other items.
The Coast Guard’s management of Deepwater acquisition programs, including implementation of
recommendations made by the Government Accountability Office (GAO), is a topic of continuing
congressional oversight. Additional oversight issues include cost growth in Deepwater acquisition
programs and the execution of individual Deepwater acquisition efforts, particularly those for
surface ships. Congress’s decision concerning Deepwater acquisition programs could affect Coast
Guard capabilities and funding requirements, Coast Guard acquisition policies and practices, and
the industrial base that produces items for Deepwater acquisition programs.
Background
Deepwater Missions
The Coast Guard performs a variety of missions in the deepwater environment, which generally
refers to waters more than 50 miles from shore. These missions include search and rescue, drug
interdiction, alien migrant interdiction, fisheries enforcement, marine pollution law enforcement,
enforcement of lightering (i.e., at-sea cargo-transfer) zones, the International Ice Patrol in
northern waters, overseas inspection of foreign vessels entering U.S. ports, overseas maritime
intercept (sanctions-enforcement) operations, overseas port security and defense, overseas
peacetime military engagement, and general defense operations in conjunction with the Navy.
Deepwater-capable assets are also used closer to shore for various operations.
Congressional Research Service
1

Coast Guard Deepwater Acquisition Programs

Origin of Deepwater Acquisition Effort
The Coast Guard initiated the Deepwater acquisition effort in the late 1990s, following a
determination by the Coast Guard that many of its existing (i.e., “legacy”) deepwater-capable
legacy assets were projected to reach their retirement ages within several years of one another.
The Coast Guard’s legacy assets at the time included 93 aging cutters and patrol boats and 207
aging aircraft. Many of these ships and aircraft are expensive to operate (in part because the
cutters require large crews), increasingly expensive to maintain, technologically obsolete, and in
some cases poorly suited for performing today’s deepwater missions.
Structure of Deepwater Acquisition Effort
Structure Until 2007
Until 2007, the Coast Guard pursued Deepwater acquisition through a single, performance-based,
system-of-systems acquisition program that used a private-sector lead system integrator (LSI):
System-of-Systems Acquisition. Rather than replacing its deepwater-capable
legacy assets through a series of individual acquisition programs, the Coast
Guard initially decided to pursue the Deepwater acquisition effort as an
integrated, system-of-systems acquisition, under which a combination of new and
modernized cutters, patrol boats, aircraft, along with associated C4ISR1 systems
and logistics support, would be procured as a single, integrated package (i.e., a
system of systems). The Coast Guard believed that a system-of-systems approach
would permit Deepwater acquisition to be optimized (i.e., made most cost
effective) at the overall Deepwater system-of-systems level, rather than
suboptimized at the level of individual Deepwater platforms and systems.
Private-Sector Lead Systems Integrator (LSI). To execute this system-of-
systems acquisition approach, the Coast Guard initially decided to use a private-
sector lead system integrator (LSI)—an industry entity responsible for designing,
building, and integrating the various elements of the package so that it met the
Coast Guard’s projected deepwater operational requirements at the lowest
possible cost.2 The Coast Guard decided to use a private-sector LSI in part
because the size and complexity of the Deepwater program was thought to be
beyond the system-integration capabilities of the Coast Guard’s then-relatively
small in-house acquisition work force.
Performance-Based Acquisition. The Coast Guard initially pursued the
Deepwater program as a performance-based acquisition, meaning that the Coast
Guard set performance requirements for the program and permitted the private-
sector LSI some latitude in determining how the various elements of the
Deepwater system would meet those requirements.

1 C4I stands for command, control, communications, computers, intelligence, surveillance, and reconnaissance.
2 For more on private-sector LSIs, see CRS Report RS22631, Defense Acquisition: Use of Lead System Integrators
(LSIs)—Background, Oversight Issues, and Options for Congress
, by Valerie Bailey Grasso.
Congressional Research Service
2

Coast Guard Deepwater Acquisition Programs

The Coast Guard conducted a competition to select the private-sector LSI for the Deepwater
program. Three industry teams competed, and on June 25, 2002, the Coast Guard awarded the
role to Integrated Coast Guard Systems (ICGS)—an industry team led by Lockheed Martin and
Northrop Grumman Ship Systems (NGSS). ICGS was awarded an indefinite delivery, indefinite
quantity (ID/IQ) contract for the Deepwater program that included a five-year baseline term that
ended in June 2007, and five potential additional award terms of up to five years (60 months)
each. On May 19, 2006, the Coast Guard announced that it was awarding ICGS a 43-month first
additional award term, reflecting good but not excellent performance by ICGS. With this
additional award term, the contract has been extended to January 2011.
Revised Structure Since 2007
In 2007, as the Coast Guard’s management and execution of the then-integrated Deepwater
program was being strongly criticized by various observers, the Coast Guard announced a number
of reform actions that significantly altered the service’s approach to Deepwater acquisition (and
to acquisition in general). As a result of these reforms, the Coast Guard, among other things,
stopped pursuing Deepwater acquisition through a single, performance-based, system-of-systems
acquisition program that used a private-sector LSI, and began pursuing Deepwater acquisition as
a collection of individual, defined-based acquisition programs, with the Coast Guard assuming
the lead role as systems integrator for each:
Individual Programs. Although Deepwater acquisition programs still appear in
the budget under the common heading IDS, the Coast Guard is now pursuing
Deepwater acquisition programs as individual programs, rather than as elements
of a single, integrated program. The Coast Guard states that it is still using a
systems approach to optimizing its acquisition programs, including the
Deepwater acquisition programs, but that the system being optimized is now the
Coast Guard as a whole, as opposed to the Deepwater subset of programs.
Coast Guard as System Integrator. The Coast Guard announced in April 2007
that, among other things, it would assume the lead role as systems integrator for
all Coast Guard Deepwater assets (as well as other major Coast Guard
acquisitions as appropriate). The Coast Guard is phasing out its reliance on ICGS
as a private-sector LSI for Deepwater acquisition, and shifting system-integration
responsibilities to itself. To support this shift, the Coast Guard is increasing its in-
house system-integration capabilities.
Defined-Based Acquisition. The Coast Guard has decided to shift from
performance-based acquisition to the use of more-detailed specifications of the
capabilities that various Deepwater assets are to have. The Coast Guard states
that although this new approach involves setting more-detailed performance
specifications, it does not represent a return to minutely-detailed specifications
such as the Military Specification (MilSpec) system once used in Department of
Defense (DOD) acquisition programs. The Coast Guard refers to its new
approach as defined-based acquisition.
Congressional Research Service
3

Coast Guard Deepwater Acquisition Programs

Deepwater Assets Planned for Acquisition3
Acquisition Program Baseline
Table 1 shows the Deepwater assets planned for acquisition under a November 2006 Deepwater
Acquisition Program Baseline (APB), and the acquisition cost of these assets in then-year dollars
as estimated at that time. As shown in the table, the total acquisition cost of these assets was
estimated at the time at $24.23 billion in then-year dollars. Acquisition funding for Deepwater
assets were scheduled at the time to be completed in FY2025, and the buildout of the assets was
scheduled at the time to be completed in 2027.
Table 1. Deepwater Assets Planned for Acquisition
(with acquisition costs in millions of then-year dollars, as estimated at the time the Acquisition Program
Baseline was published)
Qty. Item
Cost
Air assets
6
Missionized HC-130J Long Range Surveillance (LRS) aircraft (cost of missionization)
11
16
Modernized and upgraded HC-130H LRS aircraft (cost of modernization and upgrading)
610
36
New HC-144A Medium Range Surveillance (MRS) aircraft (also called Maritime Patrol Aircraft, or
1,706
MPA) based on the European Aeronautic Defence and Space Company (EADS)/CASA CN-235
Persuader MPA aircraft design
42
Modernized and upgraded MH-60T Medium Range Recovery (MRR) helicopters (cost of
451
modernization and upgrading)
102
Modernized and upgraded HH-65C Multi-Mission Cutter Helicopters (MCHs) (cost of
741
modernization and upgrading)
45
New vertical take-off unmanned aerial vehicles (VUAVs), also cal ed unmanned aircraft systems
503
(UASs)
Subtotal air assets
4,022
Surface assets
8
New National Security Cutters, or NSCs, displacing about 4,000 tons each (i.e., ships analogous to
3,450
today’s high-endurance cutters)
25
New Offshore Patrol Cutters, or OPCs, displacing about 3,200 tons each (i.e., ships analogous to
8,098
today’s medium-endurance cutters)
46
New Fast Response Cutters—Class A (FRC-As) displacing roughly 200 tons each, to replace most
2,613
of the Coast Guard’s existing 110-foot Island-class patrol boats
12
New Fast Response Cutters—Class B (FRC-Bs) displacing roughly 200 tons each, to replace the
593
rest of the Coast Guard’s existing 110-foot Island-class patrol boats
27
Medium Endurance Cutters (MECs) upgraded with a Mission Effectiveness Project (MEP) (cost of
317
upgrading)
17
Patrol boats (PBs) upgraded with a MEP (cost of upgrading)
117
124
New smal boats for Deepwater cutters, including 33 Long-Range Interceptors (LRIs) and 91 Short-
110

3 Additional background information on Deepwater acquisition programs is available at the Coast Guard’s acquisition
website at http://www.uscg.mil/acquisition/.
Congressional Research Service
4

Coast Guard Deepwater Acquisition Programs

Qty. Item
Cost
Range Prosecutors (SRPs)
8
110-foot Island-class PBs converted into 123-foot PBs (cost of conversion; program not successful
95
and halted after 8 boats)
Subtotal surface assets 15,393
C4ISR systems

Common operational picture
1,071
— Shore
systems
102
— Cutter
upgrades
180
Subtotal C4ISR systems
1,353
Integration and oversight

System engineering and oversight
1,118

Government program management
1,518

Technology obsolescence prevention
345

Logistics and infrastructure upgrades
481
Subtotal integration and oversight
3,462
TOTAL 24,230
Source: Deepwater Acquisition Program Baseline (APB) approved November 7, 2006.
Although Table 1 shows 12 FRCs and 46 FRC-Bs, the Coast Guard’s Request for Proposals
(RFP) for the FRC-B program includes options for building up to 34 FRC-Bs (which, if
exercised, would reduce the number of FRC-As to as few as 24). The Coast Guard has also stated
that if the FRC-Bs fully meet the requirements for the FRC, all 58 of the FRCs might be built to
the FRC-B design.
A version of the baseline approved by DHS in May 2007 shows some different quantities
compared to those shown above—specifically, 20 patrol boats upgraded with a MEP (rather than
the 17 shown above); a figure to be determined for an unmanned aerial system (UAS) (rather than
45 VUAVs shown above); and no 110/123-foot modernized Island class patrol boats (rather than
the 8 shown above).4
Fleet Mix Analysis
As a consequence of assuming the role of lead system integrator for Deepwater acquisition
programs, the Coast Guard is performing a fleet mix analysis to review its requirements for
Deepwater assets. The analysis could lead to changes in the planned mix of Deepwater assets.5
The results of the analysis might be released some time in 2010.

4 Government Accountability Office, Coast Guard[:] Update on Deepwater Program Management, Cost, and
Acquisition Workforce
, GAO-09-620T, April 22, 2009, p. 4.
5 Rebekah Gordon, “Coast Guard Conducting Fleet-Mix Analysis for Deepwater Assets,” Inside the Navy, April 6,
2009.
Congressional Research Service
5

Coast Guard Deepwater Acquisition Programs

Examples of Deepwater Deliveries and Other Milestones6
Examples of deliveries and other milestones for Deepwater assets include the following:
• The Coast Guard commissioned the first and second NSCs, Bertholf and
Waesche, into service on August 4, 2008, and May 7, 2010, respectively. The
third, Stratton, had its keel laying on July 20, 2009, and was 56% complete as of
September 22, 2010.
• As of September 29, 2010, the first four FRCs were 72%, 47%, 24%, and 5%
complete, respectively.
• The Navy plans to hold an industry day for the OPC on November 4, 2010. The
Coast Guard is tentatively planning to release a draft Request for Proposals
(RFP) for the program between January and March 2011, and hold a pre-
solicitation conference with industry between February and March 2011.
• The first HC-144A Ocean Sentry MPA aircraft was accepted by the Coast Guard
on March 10, 2008. On February 6, 2009, an HC-144A officially stood watch for
the first time on a scheduled operational patrol. The HC-144A achieved Initial
Operational Capability (IOC) on April 22, 2009. As of September 1, 2010, a total
of 10 had been delivered.
• The first missionized HC-130J LRS aircraft was accepted by the Coast Guard on
February 29, 2008; the sixth and final aircraft was accepted on May 18, 2010. As
of September 17, 2010, new surface search radars had been installed on 18 of 23
HC-130H aircraft.
• The first production MH-60T Jayhawk Medium Range Recovery Helicopter was
delivered on June 3, 2009, and the MH-60T achieved Initial Operational
Capability (IOC) on October 1, 2009. As of September 29, 2010, 14 had been
delivered to the Coast Guard.
• The Coast received its first MH-65C Multi-Mission Cutter Helicopter (MCH) in
October 2007. As of September 29, 2010, the Coast Guard had configured and
delivered 66 MH-65Cs and two MH-65Ds.
Deepwater Acquisition Funding
Prior-Year Funding
Table 2 below shows prior-year acquisition funding for Deepwater acquisition programs.

6 Information in this section is taken from the Coast Guard Acquisition Directorate’s web page on acquisition programs
and projects http://www.uscg.mil/acquisition/programs/acquisitionprograms.asp, and Statement of Admiral Thad W.
Allen, Commandant [of the Coast Guard], on the Coast Guard and Acquisitions before the Committee on
Appropriations Subcommittee on Homeland Security, U.S. House of Representatives, 22 April 2009.
Congressional Research Service
6

Coast Guard Deepwater Acquisition Programs

Table 2. Prior-Year Acquisition Funding For Deepwater Programs
(in millions of dollars, rounded to nearest tenth)
Priora FY02 FY03 FY04 FY05 FY06 FY07 FY08 FY09 FY10
Request
n/a 320.2
500.0
500.0 678 966.0 934.4 836.9 990.4 1,051.5
Appropriation n/a 320.2 478.0 668.2 724.0 933.1 1065.9 783.3 1034.0 1,123.0
Rescissions n/a 3.1
57.6
38.9
98.7 132.4
Transfers n/a

49.7
77.8
78.7

Supplemental
n/a
124.2
appropriations
Totalb
117.0 320.2 474.9 610.6 734.8 1036.4 1144.6 650.8 1034.0 1,123.0
Source: Prepared by CRS using Coast Guard data provided on January 29, 2007 (FY2007 and prior years),
FY2008 and FY2009 appropriations bills for FY2008 and FY2009, and (for FY2010) Coast Guard FY2011 budget
submission. Totals may not add due to rounding.
Note: n/a=not available
a. Pre-award funding prior to 2002.
b. Excludes HC-130J funding prior and airborne use-of-force funding prior to FY2007. The figure for FY2010
excludes $4.0 million funding for High Endurance Cutter sustainment and $27.3 million in funding for polar
icebreaker sustainment. Although these funds were appropriated in FY2010 under the surface category of
the Integrated Deepwater System (IDS), the Coast Guard, as part of its FY2011 budget display of its
Acquisition, Construction and Improvement (AC&I) account, shows these two line items outside the IDS
collection of line items.
FY2011 Funding Request
Table 3 shows acquisition funding requested for the Deepwater program for FY2011, along with
enacted FY2010 funding. As shown in the table, the Coast Guard for FY2011 has requested
$1,112.5 million in acquisition funding for Deepwater programs, including $101.0 million for
aircraft, $856.0 million for surface ships and boats, and $155.5 million for other items. The
$856.0 million requested for surface ships and boats includes funding for production of the fifth
NSC; continued analysis and design of the OPC; production of the FRCs numbers 9 through 12;
production of one LRI and one SRP; and operational enhancement of three Medium Endurance
Cutters at the Coast Guard Yard through the Mission Effectiveness Project.
Congressional Research Service
7

Coast Guard Deepwater Acquisition Programs

Table 3. FY2010 and FY2011 Acquisition Funding for Deepwater Programs
(in millions of dollars, rounded to nearest tenth; as shown in FY2009 budget)
Program
FY10 enacted
FY11 requested
Maritime Patrol Aircraft (MPA)
138.5
40.0
HH-60 Conversion Projects
45.9
32.0
HH-65 Conversion/Sustainment
38.0 0
Projects
HC-130H Conversion/Sustainment
45.3 25.0
Projects
HC-130J Fleet Introduction
1.3
4.0
Subtotal aircraft
269.0
101.0
National Security Cutter (NSC)
389.5
538.0
Offshore Patrol Cutter (OPC)
9.8
45.0
Fast Response Cutter (FRC)
243.0
240.0
Deepwater smal boats
3.0
3.0
Medium-endurance cutter sustainment
31.1
30.0
Patrol boats sustainment
23.0
0
Subtotal surface ships
699.4
856.0
Government program management
45.0
45.0
Systems engineering and integration
35.0
29.0
C4ISR 35.0
30.5
Deepwater logistics
37.7
50.0
Technology obsolescence prevention
1.9
1.0
Subtotal other
154.6
155.5
TOTAL 1,123.0
1,112.5
Source: Coast Guard FY2011 budget submission. C4ISR means Command and control, communications,
computers, intelligence, surveillance and reconnaissance. The total of $1,123.0 million for FY2010 excludes $4.0
million funding for High Endurance Cutter sustainment and $27.3 million in funding for polar icebreaker
sustainment. Although these funds were appropriated in FY2010 under the surface category of the Integrated
Deepwater System (IDS), the Coast Guard, as part of its FY2011 budget display of its Acquisition, Construction
and Improvement (AC&I) account, shows these two line items outside the IDS collection of line items.
Criticism of Deepwater Management in 2007
The management and execution of the then-integrated Deepwater program was strongly criticized
in 2007 by the DHS Inspector General (IG),7 GAO,8 the Defense Acquisition University (DAU)

7 See, for example, Statement of Richard L. Skinner, Inspector General, U.S. Department of Homeland Security, Before
the Committee on Transportation and Infrastructure, Subcommittee on Coast Guard and Maritime Transportation, U.S.
House of Representatives, “Deepwater: 120-Day Update,” June 12, 2007; as well as Department of Homeland Security,
Office of Inspector General, Acquisition of the National Security Cutter, OIG -07-23, January 2007 (available online at
http://www.dhs.gov/xoig/assets/mgmtrpts/OIG_07-23_Jan07.pdf); Department of Homeland Security, Office of
Inspector General, 110’/123’ Maritime Patrol Boat Modernization Project, OIG -07-27, January 2007 (available online
at http://www.dhs.gov/xoig/assets/mgmtrpts/OIG_07-27_Feb07.pdf); U.S. Department of Homeland Security, Office of
(continued...)
Congressional Research Service
8

Coast Guard Deepwater Acquisition Programs

(whose analysis was requested by the Coast Guard),9 several Members of Congress from
committees and subcommittees that oversee the Coast Guard, and other observers. House and
Senate committees held several oversight hearings on the program, at which non-Coast Guard,
non-ICGS witnesses, as well as several Members of Congress, strongly criticized the
management and execution of the program. Criticism focused on overall management of the
program, and on problems in three cutter acquisition efforts—the NSC, the modernization of the
110-foot patrol boats, and the FRC. For a more detailed discussion, see Appendix A.
Coast Guard Reform Actions in 2007
In 2007, as the Coast Guard’s management and execution of the then-integrated Deepwater
program was being strongly criticized by various observers, the Coast Guard announced a number
of reform actions that significantly altered the service’s approach to Deepwater acquisition (and
to Coast Guard acquisition in general). Among these was the change from a single, integrated
Deepwater acquisition program to a collection of separate Deepwater acquisition programs. For a
more detailed discussion, see Appendix B.
Justice Department Investigation
On April 18, 2007, it was reported that the Justice Department was conducting an investigation of
the Deepwater program. Press reports at the time stated that investigation centered on
communications systems, the conversion of the Coast Guard’s 110-foot patrol boats, and the
National Security Cutter (NSC). The Justice Department reportedly notified Lockheed, Northrop,
and certain other firms involved in the Deepwater program of the investigation on December 13,
2006, and directed the firms to preserve all documents relating to the program.10

(...continued)
Inspector General, Major Management Challenges Facing the Department of Homeland Security (Excerpts from the
FY 2006 DHS Performance and Accountability Report)
, December 2006. (OIG-07-12); and U.S. Department of
Homeland Security, Office of Inspector General. Improvements Needed in the U.S. Coast Guard’s Acquisition and
Implementation of Deepwater Information Technology Systems
, August 2006. (Office of Information Technology,
OIG-06-55).
8 See, for example, Government Accountability Office, Coast Guard[:] Challenges Affecting Deepwater Asset
Deployment and Management and Efforts to Address Them
, GAO-07-874, June 2007; Government Accountability
Office, Coast Guard[:] Status of Efforts to Improve Deepwater Program Management and Address Operational
Challenges, Statement of Stephen L. Caldwell, Acting Director Homeland Security and Justice Issues, Testimony
Before the Subcommittee on Coast Guard and Maritime Transportation, Committee on Transportation and
Infrastructure, House of Representatives
, GAO-07-575T, March 8, 2007; and Government Accountability Office,
Coast Guard[:] Coast Guard Efforts to Improve Management and Address Operational Challenges in the Deepwater
Program, Statement of Stephen L. Caldwell, Acting Director Homeland Security and Justice Issues, Testimony Before
the Subcommittee on Oceans, Atmosphere, Fisheries, and Coast Guard, Committee on Commerce, Science and
Transportation, U.S. Senate
, GAO-07-460T, February 14, 2007.
9 Defense Acquisition University, Quick Look Study, United States Coast Guard Deepwater Program, February 2007.
10 Ana Radelat, “Justice Investigating Deepwater Contractors,” NavyTimes.com, April 18, 2007; Chris Strohm,
“Deepwater Contractors Face Justice Probe” GovExec.com, April 19, 2007; Patricia Kime, “Justice Investigating
Deepwater Contract,” NavyTimes.com, April 20, 2007.
Congressional Research Service
9

Coast Guard Deepwater Acquisition Programs

Oversight Issues for Congress
The Coast Guard’s management of Deepwater acquisition programs, including implementation of
recommendations made by the Government Accountability Office (GAO), is a topic of continuing
congressional oversight. Additional oversight issues include cost growth in Deepwater
acquisition programs and the execution of individual Deepwater acquisition efforts, particularly
those for surface ships.
Management of Deepwater Programs in General
Coast Guard Perspective
The Coast Guard testified in April 2009 that:
Efforts to consolidate the Coast Guard Acquisition Directorate, assume Lead System
Integrator responsibilities, and implement the [Coast Guard’s] Blueprint for Acquisition
Reform
[document] have left us better equipped to manage costs, schedules and performance.
These business improvements have led to a number of high profile project successes.
Consider the recent award of the Fast Response Cutter (FRC) Sentinel-class patrol boat.
Initially planned as part of the Deepwater program, to be delivered through Integrated Coast
Guard Systems (ICGS), we took this project back within the Coast Guard to ensure full and
open competition and responsible program management. We have followed our reformed
acquisition processes, conducting a deliberative proposal review and award determination
with integrated participation from technical authorities and the operational community. The
FRC’s proven parentcraft design will minimize cost and schedule risk and mitigate the patrol
boat hour gap in the shortest time possible. Neither ICGS nor the Coast Guard’s pre-
modernized acquisition program could have accomplished this feat as efficiently or
effectively, and I am confident we will build on this record of advances for future
acquisitions programs as well....
Today, I am pleased to discuss our wholly reformed acquisition organization, an organization
with processes and procedures in place to ensure successful program management and
oversight. I expect further challenges, but I have the utmost confidence that the processes
now in place allow us to address those challenges head-on and facilitate delivery of assets
and systems with capabilities to meet the mission needs of today and tomorrow.
The most pointed example of the success of our reformed acquisition processes is Fast
Response Cutter Sentinel-class patrol boat. With a total potential contract value of more than
$1 billion, it was a highly competitive process, and our selection survived two post-award
protests, demonstrating that our robust acquisition process was beyond reproach.
As the yard stick by which to measure the success of our reformed acquisition enterprise, the
Sentinel project provides a number of assurances - all built on the cornerstones for successful
acquisition - for its own and future acquisition management successes, including:
• Establishment and maintenance of a direct Coast Guard relationship with the contractor,
rather than through a separate lead systems integrator;
• Development of detailed technical requirements, and firm adherence to those requirements
throughout the proposal design evaluation process and construction;
Congressional Research Service
10

Coast Guard Deepwater Acquisition Programs

• Classification of cutters to established and recognized standards (i.e., American Bureau of
Shipping and High Speed Naval Vessel Rules);
• Use of parent craft designs where applicable, with parent craft designer and builder co-
located on engineering team;
• On-site government staff at production facilities;
• Fixed price contract structure;
• Extensive involvement of technical authority throughout acquisition and delivery process;
• Independent validation (i.e., independent cost estimates and design assessments);
• Leveraging Navy and other government partnerships; and,
• Ability to re-compete thru options for data and licensing.
The Sentinel project has become the model for all current and future Coast Guard acquisition
programs. By adopting needed reforms, and guided by this Subcommittee, we’ve
demonstrated the right way to develop and manage an acquisition project. With those
reforms solidly in place, the foundation for continued success is firm....
As acquisition policy and process improvements have promoted project successes, one
persistent set of challenges has been the recruitment, development, and retention of a highly
qualified acquisition workforce. We have accomplished much in our reforms of contracting,
business and financial management, program management, systems engineering and other
key disciplines. But, like other federal agencies, we must work hard to attract and retain the
best and brightest in a highly competitive market.
In the 1990s, the level of investment in Coast Guard acquisition was approximately $200
million. In FY 2009, we were appropriated nearly $1.5 billion for our recapitalization
programs. This growth in investment has required our professional workforce to grow to
ensure adequate program management and contractor oversight and management. We have
worked hard to build capacity. Today the Acquisition Directorate has 855 military and
government civilian personnel, and is continuing to grow—including 104 added positions in
2008 and another 65 positions in 2009.
With many agencies competing for qualified acquisition professionals, it is critically
important for the Coast Guard to remain competitive in the labor market. The Coast Guard
must be able to use all hiring and workforce management tools effectively and expeditiously.
Once hired, however, another challenge is ensuring the appropriate training, skills, and
career progression for our workforce. As a government manager, I have an obligation to
properly equip my personnel with the skills and tools they need to accomplish their missions.
One of the areas where we have placed enormous pressure is on our training and certification
programs. A couple of years ago we had a lot of people who might have had the right
experience but had not completed required training or certification, so it was difficult to see
standardized skills across projects. We have addressed this challenge. Today, of the 14 Level
I investments in our acquisition portfolio (valued at greater than $1 billion total life cycle
cost), 100 percent are led by DHS Level III (the highest level) certified program managers.
Congressional Research Service
11

Coast Guard Deepwater Acquisition Programs

We have also developed a new Human Capital Strategic Plan that outlines several goals
aimed at improving the skills of our workforce. An overarching objective is to raise the
profile of Coast Guard acquisition as a profession with well-defined career paths for both
uniformed and civilian employees. That strategy sets goals for training and educational
opportunities, using internal resources as well as reaching out to third parties, such as the
Defense Acquisition University and the Naval Postgraduate School, to provide additional
support.
The goal in these efforts is to improve the career path that can be followed by uniformed and
civilian employees, ultimately narrowing the gap between the complexity of acquisition tasks
and the availability of skilled workers to accomplish them....
With acquisition reform firmly taking root, the future of Coast Guard acquisition is bright.
We have learned from the past, but our focus remains on the future. Reformed processes
have already led to acquisition success, but I am confident our greatest successes lay ahead,
if we remain committed to the foundational principles and acquisition cornerstones that have
driven our reforms. As the Coast Guard’s mission support organization is established fully,
those principles will become further engrained in our mission support and acquisition
culture.
The future will see new requirements for ever new assets and systems. In fact, we will soon
begin the largest single acquisition project in our history—the Off-Shore Patrol Cutter. Now
that our reforms are in place, I am confident that this and other future projects will be
managed effectively and efficiently.11
GAO Perspective
GAO for several years has been assessing, providing reports and testimony on, and making
recommendations for Coast Guard management of Deepwater acquisition. The Coast Guard has
implemented many of GAO’s recommendations. The extent to which the Coast Guard has
implemented GAO recommendations has been a topic of continuing congressional oversight for
Deepwater acquisition.
A July 2010 GAO report states:
DHS has revised its approach to managing and overseeing Deepwater by making the
program subject to its recently finalized acquisition directive, which establishes a number of
review points to provide insight into such key documents as baselines and test reports. DHS
has also increased the number of its reviews of individual Deepwater assets. The Coast
Guard’s own management policies are generally aligned with DHS directives, although
operational testing policies are still being revised, and it has developed additional guidance
on completion of key requirements documents. In taking on the systems integrator role, the
Coast Guard is also decreasing its dependence on ICGS by planning for alternate vendors on
some of the assets already in production, as well as awarding and managing work outside of
the ICGS contract for other assets….
The Coast Guard continues to take steps to address its acquisition workforce needs as it
assumes the role of system integrator. For example, it is using a workforce planning model

11 Statement of Admiral Thad W. Allen, Commandant [of the Coast Guard], on the Coast Guard and Acquisitions
before the Committee on Appropriations Subcommittee on Homeland Security, U.S. House of Representatives, 22
April 2009, pp. 2-3, 8-11.
Congressional Research Service
12

Coast Guard Deepwater Acquisition Programs

to estimate current and future needs for key acquisition personnel. The Coast Guard has also
begun to implement initiatives such as promoting career growth for acquisition professionals.
External limitations on the availability of acquisition personnel, coupled with 100 new
positions authorized in fiscal year 2010, place the Coast Guard’s acquisition directorate
vacancy rate at about 20 percent. While it is using contractors in support roles, the Coast
Guard has released guidance regarding the roles of government staff in overseeing
contractors.12
GAO testified in February 2010 that:
the Coast Guard has also had several acquisition management challenges throughout the
history of [the Deepwater] program and some of those challenges remain. To address some
of these past acquisition management challenges, in April 2007, the Coast Guard assumed
the role of systems integrator for the Deepwater Program, reduced the scope of the work by
the former systems integrator (or prime contractor), Integrated Coast Guard Systems (ICGS),
and assigned these functions to Coast Guard stakeholders. Additionally, the Coast Guard has
improved and begun to apply the disciplined management process contained in its Major
Systems Acquisition Manual (MSAM) for individual assets, although it did not meet its goal
of adhering to this process for all Deepwater assets by March 2009. In addition, we reported
in July 2009 that the MSAM does not appear to be consistent with DHS policy that requires
entities responsible for operational testing to be independent of the system’s users. The Coast
Guard concurred with our recommendation to consult with DHS on policies regarding the
independent operational test authority....
Problems in Deepwater management and oversight have led to delivery delays and other
operational challenges for certain assets, as our prior work has identified, particularly (1)
patrol boats and their anticipated replacements, the Fast Response Cutters and (2) the
National Security Cutter. Specifically, we reported in June 2008 that conversion of the first
eight 110-foot patrol boats was unsuccessful, and subsequently, the Coast Guard decided to
remove these vessels from service and accelerate the design and delivery of the replacement
Fast Response Cutters. The removal from service of the eight converted patrol boats in
November 2006 created operational challenges by reducing potential patrol boat availability
by 16 percent or 20,000 annual operational hours. To mitigate the loss of these eight patrol
boats and the associated 2,500 operational hours per patrol boat in the near term, the Coast
Guard implemented a number of strategies beginning in fiscal year 2007. For example, the
Coast Guard began using the crews from the eight patrol boats removed from service to
augment the crews of eight other patrol boats so that these assets could operate for longer
duration, yet still met crew rest requirements. To help fill the longer-term patrol boat
operational gap, Coast Guard officials continue to pursue the acquisition of a commercially
available Fast Response Cutter. The Coast Guard reports that the first of these cutters, the
Sentinel, will commence operations in Miami, Florida in fiscal year 2011. While the contract
is for the design and production of up to 34 cutters, the Coast Guard intends to acquire a total
of 12 by fiscal year 2011 to assess the capabilities of these first 12 before exercising options
for additional cutters. Coast Guard officials noted that they plan to assess the capabilities of
the new cutter through operational test and evaluation before exercising options for
additional cutters.
Regarding the National Security Cutters, delays in the delivery of National Security Cutters
and the support assets of unmanned aircraft and small boats have created operational gaps
for the Coast Guard that include the projected loss of thousands of days in National Security

12 Government Accountability Office, COAST GUARD[:] Deepwater Requirements, Quantities, and Cost Require
Revalidation to Reflect Knowledge Gained
, GAO-10-790, July 2010, summary page.
Congressional Research Service
13

Coast Guard Deepwater Acquisition Programs

Cutter availability for conducting missions until 2018, as we reported in July 2009. The first
vessel (USCGC Bertholf, see figure 1) was initially projected for delivery in 2006 but was
not delivered to the Coast Guard until May 2008. We reported in July 2009 that this first
vessel was undergoing final trials as the Coast Guard prepared it for full operational service
in the fourth quarter of fiscal year 2010. The Coast Guard deployed this first National
Security Cutter without its planned support assets. Given the delivery delays, the Coast
Guard must continue to rely on High Endurance Cutters that are becoming increasingly
unreliable. Coast Guard officials said that the first National Security Cutter capabilities will
be greater than those of a High Endurance Cutter; however, the Coast Guard cannot
determine the extent to which the National Security Cutters’ capabilities will exceed those of
the High Endurance Cutter until the National Security Cutters’ support assets are operational,
which will take several years. To mitigate these operational gaps, the Coast Guard is
considering extending the service life of some of its High Endurance Cutters and is using
existing aircraft and small boats until unmanned aircraft and new small boats are operational.
However, because the High Endurance Cutters are increasingly unreliable, the Coast Guard
planned to perform a series of upgrades and maintenance procedures on selected vessels.
Before this work could begin, the Coast Guard conducted an analysis on the condition of the
High Endurance Cutters and this resulted in the plan to decommission 4 High Endurance
Cutters by fiscal year 2011, which could further negatively impact the Coast Guard’s ability
to more effectively conduct missions.
Looking forward, Coast Guard officials stated that they must review and continuously re-
validate whether assumptions used to determine the original fleet mix (i.e., types and number
of vessels and aircraft) of Deepwater assets are still reflective of mission demands and
operational requirements. For example, the Coast Guard is conducting an updated review to
determine whether it will continue with the contractor’s original 2001 baseline mix of 8
National Security Cutters, 25 Offshore Patrol Cutters, and 58 Fast Response Cutters. From
2005 to 2006, the Coast Guard worked to rebaseline the Deepwater program to reflect its
post-September 11 mission. In April 2006, we reported on this baseline, looking at key
changes in asset numbers and capabilities between the original (2001) and revised (2005 and
2006) Deepwater baseline implementation plans. At that time, we found that the Coast
Guard’s analytical methods were appropriate for determining if the revised asset mix would
provide greater mission performance and whether the mix was appropriate for meeting
Deepwater missions. In May 2007, the DHS approved the Deepwater Acquisition Program
Baseline, which reflects the revised 2005 to 2006 implementations plans. Since that time, as
the Coast Guard has taken over the acquisition and management responsibilities for the
Deepwater program from the contractor, it has realized that its knowledge of how the various
proposed assets would work together to help meet mission needs were limited because the
contractor, in certain cases, had developed the plans for these assets without using all of the
input from the Coast Guard. Coast Guard officials stated that as part of the on-going process
to review the original work completed by the contractor, and in light of technology advances,
the Department’s maturation, program oversight, and new assets coming online, the Coast
Guard has initiated an analysis of the capabilities, number, and mix of assets it needs to
fulfill its Deepwater missions by undertaking a new fleet mix analysis. The Coast Guard
expects that this fleet mix analysis will assist in determining capability-capacity-performance
sensitivities and serve as one tool, among many, in making future capability requirements
determinations, including future fleet mix decisions. The results of this study were originally
expected in the summer of 2009, but U.S. Coast Guard officials told us that, as of February
2010, the finalization of this study is not expected for a few more months, at which time
Coast Guard leadership is to assess the results and plan for future asset procurement
decisions. According to Coast Guard officials, the Coast Guard plans to update this fleet mix
analysis every 4 years and use it as a basis to update the numbers and types of assets needed
Congressional Research Service
14

Coast Guard Deepwater Acquisition Programs

for the Deepwater program. At this time, it is too soon to determine the extent to which the
fleet mix analysis will inform the Coast Guard’s future Deepwater investment decisions.13
Cost Growth
Coast Guard Perspective
An August 30, 2010, press report quoted Admiral Robert Papp, the Commandant of the Coast
Guard, as acknowledging that the Coast Guard’s ability to acquire Deepwater assets within
budgeted costs will depend in part on factors that the Coast Guard does not control:
“We can't control the ups and downs of the economy, the price of steel and other things, so
there could be [added] costs that occur,” he said. “A lot of acquisition pricing depends upon
a steady stream of funding. If you delay a ship or you delay the award of a contract for a year
or if you don't get the funding through Congress, it adds costs in the out years ... Maybe the
whole project doesn’t fit within that original advertised cost. We'll be working very hard to
bring it in within cost.”14
A July 2009 news report stated: “The total cost of the Coast Guard’s beleaguered Deepwater
acquisition program is a ‘moving target’ that could rise beyond the latest $26.3 billion price tag,
but the completion date for the purchases could come sooner than projected, the service’s top
officer testified last week.”15
The Coast Guard testified in April 2009 that:
[a] persistent challenge is controlling costs in complex, multiple-year projects – especially
those costs driven by economic factors outside the Coast Guard’s control, more specifically,
those types of cost increases recently impacting the National Security Cutter and Maritime
Patrol Aircraft projects. Current economic conditions have seen a steady six-month decline
in the cost of commodities such as nickel, steel and copper. However, when we award
production contracts, our contract price reflects commodity prices at the time of award.
In the case of the National Security Cutter we are executing production contracts for NSCs
two and three and the long lead time materials contract for NSC four that were priced based
on historically high commodity and fuel prices in effect during the summer of 2008.
Likewise, when current NSC and MPA contracts were awarded, the value of the U.S. dollar
was at a record low when compared to other foreign currencies, meaning all foreign
components necessary for production were more expensive.
While the government will never be able to eliminate these types of cost changes completely,
we have taken steps to minimize their impact within Coast Guard acquisitions. Once again,
by building on the cornerstones for acquisition success, we have established a firm

13 Government Accountability Office, Coast Guard[:] Observations on the Requested Fiscal Year 2011 Budget, Past
Performance, and Current Challenges, GAO-10-411T, February 25, 2010 (Testimony before the Subcommittee on
Coast Guard and Maritime Transportation, Committee on Transportation and Infrastructure, U.S. House of
Representatives), pp. 12-17.
14 Cid Standifer, “Papp: Deepwater Cost Increases May Be Out Of Coast Guard’s Control,” Inside the Navy, August 30,
2010. Ellipses and bracketed material as in original.
15 Rebekah Gordon, “Coast Guard Commandant: Deepwater Price Tag A ‘Moving Target,’” Inside the Navy, July 13,
2009.
Congressional Research Service
15

Coast Guard Deepwater Acquisition Programs

commitment to independent cost estimates within each project to validate projected program
costs. We have initiated more rigorous government oversight of contractor performance and
cost accounting, including renewed emphasis on Earned Value Management data. And we
continue to work with industry to balance risk and ensure affordable acquisition programs at
best value for the government.16
GAO Perspective
A July 2010 GAO report states:
Currently, the Deepwater Program exceeds the 2007 cost and schedule baselines, and given
revisions to performance parameters for certain assets, it is unlikely to meet system-level
performance baselines. The asset-specific baselines that have been approved to date, while
providing greater insight into asset-level capabilities, place the total cost of Deepwater at
roughly $28 billion, or $3.8 billion over the $24.2 billion 2007 baseline. The revised
baselines also present life-cycle costs, which encompass the acquisition cost as well as costs
for operations and maintenance. While the revised baselines show a significant decrease in
life-cycle costs, due to changes to assumptions like shorter service lives for assets, the Coast
Guard’s understanding of them continues to evolve as the agency revisits its assumptions and
produces new cost estimates. Costs could continue to grow as four assets currently lack
revised cost baselines; among them is the largest cost driver in the Deepwater Program, the
Offshore Patrol Cutter. The asset-level baselines also indicate that schedules for some assets
are expected to be delayed by several years. Regarding system-level performance, the 2007
baseline may not be achievable, as the Coast Guard has redefined or eliminated key
performance indicators for many individual assets, while significant uncertainties surround
other assets. Further, a planned analysis to reassess the overall fleet mix for Deepwater was
not completed as planned, and a new analysis will include surface assets only. In the
meantime, the Coast Guard and DHS are proceeding with acquisition decisions on individual
assets.17
GAO testified in February 2010 that:
The Coast Guard has also made other improvements to its oversight and management of the
Deepwater program. Due in part to the Coast Guard’s increased insight into its purchases, the
anticipated cost, schedules, and capabilities of many Deepwater assets have changed since
the $24.2 billion baseline was established in 2007. Coast Guard officials have stated that this
baseline reflected not a traditional cost estimate, but rather the anticipated contract costs as
determined by ICGS. As the Coast Guard developed its own cost baselines for some assets,
as of July 2009, it has become apparent that some of the assets it is procuring will likely cost
up to $2.7 billion more than anticipated. This represents about a 39 percent cost growth for
the assets under the revised cost estimates. According to Coast Guard, as more cost baselines
are developed and approved, further cost growth is likely. Updated baselines also indicate
that schedules have slipped for delivery of several of the assets. 18

16 Statement of Admiral Thad W. Allen, Commandant [of the Coast Guard], on the Coast Guard and Acquisitions
before the Committee on Appropriations Subcommittee on Homeland Security, U.S. House of Representatives, 22
April 2009, pp. 17-18.
17 Government Accountability Office, COAST GUARD[:] Deepwater Requirements, Quantities, and Cost Require
Revalidation to Reflect Knowledge Gained
, GAO-10-790, July 2010, summary page.
18 Government Accountability Office, Coast Guard[:] Observations on the Requested Fiscal Year 2011 Budget, Past
Performance, and Current Challenges, GAO-10-411T, February 25, 2010 (Testimony before the Subcommittee on
Coast Guard and Maritime Transportation, Committee on Transportation and Infrastructure, U.S. House of
Representatives), pp. 13-14.
Congressional Research Service
16

Coast Guard Deepwater Acquisition Programs

Reporting of Costs and Planned Procurement Quantities
Regarding Coast Guard reporting of costs and planned procurement quantities for Deepwater
acquisition programs, a July 2009 GAO report stated:
The Coast Guard’s budget submission, as currently structured, limits Congress’s
understanding of details at the asset level in so far as it does not include key information
such as assets’ total acquisition costs or, for the majority of assets, the total quantities
planned. For example, while the justification of the NSC request includes a detailed
description of expected capabilities and how these capabilities link to the Coast Guard’s
missions and activities funded by past appropriations, it does not include estimates of total
program cost, future award or delivery dates of remaining assets, or even the total number of
assets to be procured.
Our past work has emphasized that one key to a successful capital acquisition, such as the
multibillion-dollar ships and aircraft the Coast Guard is procuring, is budget submissions that
clearly communicate needs.11 An important part of this communication is to provide
decision makers with information about cost estimates, risks, and the scope of a planned
project before substantial resources are committed. Good budgeting also requires that the full
costs of a project be considered upfront when decisions are made. Other federal agencies that
acquire systems similar to those of the Coast Guard, such as the Department of Defense,
capture these elements in justifications of their budget requests....
While the Coast Guard’s asset-level Quarterly Acquisition Reports to Congress and the
annual Deepwater Program Expenditure Report include some information on total costs and
quantities, these documents are provided only to the appropriations committees, and they
contain selected information that is restricted due to acquisition sensitive material. The
budget justification prepared by the Coast Guard is a tool that Congress uses in its budget
and appropriations deliberations. Presentation of information on the full costs and quantities
of Deepwater assets in the Coast Guard’s budget submission can provide Congress greater
insights in fulfilling its roles of providing funding and conducting oversight.19
National Security Cutter (NSC)
Oversight issues concerning the NSC program have included whether the original design for the
NSC was rugged enough to ensure that the ships could be operated for their full 30-year intended
service lives; whether the electronic systems on the ship met technical standards (including some
referred to as TEMPEST) for information assurance (or IA—the ability of the ship’s various
electronic systems to protect classified data); and cost growth in building the ships.
Coast Guard Perspective
The Coast Guard testified in April 2009 that:
We have been actively running Bertholf through her paces during the operational test and
evaluation process now underway and have received very positive feedback from her crew
and the Coast Guard’s operational community. Of particular note, Bertholf has conducted her
first operational patrols and completed flight deck dynamic interface testing and attained

19 Government Accountability Office, Coast Guard[:]As Deepwater Systems Integrator, Coast Guard Is Reassessing
Costs and Capabilities but Lags in Applying Its Disciplined Acquisition Approach
, GAO-09-682, July 2009, pp. 21-22.
Congressional Research Service
17

Coast Guard Deepwater Acquisition Programs

interim flight deck certification. Additionally, Bertholf recently conducted towing exercises
with CGC [Coast Guard cutter] Morgenthau, a fueling at sea evolution with USNS [U.S.
naval ship] Kaiser, and testing of the 57mm deck gun and close-in weapon system against
high-speed maneuvering surface targets and unmanned aerial vehicles....
We continue to see real progress in the areas of Information Assurance, which includes
TEMPEST, on the NSC. Our technical authority, with support from the Command, Control,
Communications, Computers, Intelligence, Surveillance and Reconnaissance (C4ISR) and
NSC project managers, conducted TEMPEST certification inspections prior to preliminary
acceptance of Bertholf in May 2008. Those pre-delivery inspections have contributed to
building a TEMPEST baseline, which will serve as a reference point for all future
TEMPEST-related activities. Using the test-fix-test methodology, we now have resolved all
122 visual TEMPEST discrepancies identified during that pre-acceptance process. We are
conducting additional instrumented TEMPEST surveys using a National Security Agency
(NSA) approved contractor to prepare for final TEMPEST testing, which is scheduled to be
conducted by SPAWAR [the Navy’s Space and Naval Warfare Systems Command] and in
April 2009.
We continue to build on lessons learned and are making some significant improvements to
the Stratton, including construction process efficiencies, enhanced functionality and better
hull design. One of the most notable process improvements is a significant reduction in the
number of grand blocks—multiple units stacked together in large assembly halls away from
the waterfront—used to assemble the ships hull. We used 29 grand blocks to assemble
Bertholf, but expect to use as few as 14 to assemble Stratton. This will enable more sub-
assembly work in each grand block in a controlled environment and potentially lead to fewer
construction hours compared to the process for Bertholf.
Other improvements include an enhanced replenishment at sea station, which incorporates a
redesigned refueling area that will be more efficient and ergonomic for cutter personnel. We
are also improving the gas turbine removal route, which will make it easier to remove and
repair the gas turbine modules that power the cutter. And we have enhanced the hull fatigue
design on Stratton, ensuring she will achieve a 30-year fatigue life.
We are currently working toward production award for the fourth NSC, Hamilton. In line
with accomplished acquisition reforms and our efforts to become the lead systems integrator,
the production award for Hamilton will occur outside the Integrated Coast Guard Systems
(ICGS) LSI construct and include a fixed price contract structure.20
The Coast Guard also testified in April 2009 that:
our reform efforts are facilitating the successful resolution of past and current project
challenges.
One such challenge is the fatigue lifespan of the National Security Cutter—which the Coast
Guard insists be at least 30 years—meaning at least 30 years before the onset of major
repairs due to normal mission use. In 2007, in accordance with the acquisition success
cornerstones and working through our technical authority for engineering and logistics, the
Coast Guard arranged to work with the Navy’s Naval Surface Warfare Center, Carderock
Division to provide independent third party analysis of fatigue design solutions developed by

20 Statement of Admiral Thad W. Allen, Commandant [of the Coast Guard], on the Coast Guard and Acquisitions
before the Committee on Appropriations Subcommittee on Homeland Security, U.S. House of Representatives, 22
April 2009, pp. 13-14.
Congressional Research Service
18

Coast Guard Deepwater Acquisition Programs

Coast Guard naval engineers. Using the newest available computer fatigue modeling
software, Carderock reached two main conclusions in its final report, presented to the Coast
Guard earlier this year.
First, Carderock determined Coast Guard-developed design fatigue enhancements for the
hulls of NSCs three through eight will achieve the desired 30-year fatigue life, while also
recommending monitoring of localized stress in several structural details. Second, the report
identifies major improvements with fatigue life after completing identified modifications to
hulls one and two, but the Carderock transmittal letter recommends more data be gathered
for several areas which are still modeling a less-than 30-year fatigue life.
We agree with Carderock’s assessments. In fact, we have already outfitted CGC Bertholf
with strain gauge sensors to measure actual encountered stresses and collect data to enable
more precise design modeling. Our technical authority is also reviewing each area identified
by Carderock, based on Coast Guard missions and the planned operational profile of the
NSC, and will develop a plan to address those concerns prior to implementing any related
design fix. Plans are to gather data and modify design enhancements over a span of multiple
years, even after NSCs one and two transition to full operations, as the upgrades are
completed over potentially several future yard availabilities. We plan to continue to
collaborate with Carderock to conduct further analysis, including possible re-validation of
changes to the proposed design as a result of the recommendations in their report.
Another persistent challenge is controlling costs in complex, multiple-year projects –
especially those costs driven by economic factors outside the Coast Guard’s control, more
specifically, those types of cost increases recently impacting the National Security Cutter and
Maritime Patrol Aircraft projects. Current economic conditions have seen a steady six-month
decline in the cost of commodities such as nickel, steel and copper. However, when we
award production contracts, our contract price reflects commodity prices at the time of
award.
In the case of the National Security Cutter we are executing production contracts for NSCs
two and three and the long lead time materials contract for NSC four that were priced based
on historically high commodity and fuel prices in effect during the summer of 2008.
Likewise, when current NSC and MPA contracts were awarded, the value of the U.S. dollar
was at a record low when compared to other foreign currencies, meaning all foreign
components necessary for production were more expensive.21
GAO Perspective
A July 2009 GAO report states that the cost of the NSC program was estimated in June 2009 at
$4,749 million in then-year dollars—an increase of $1,299 million, or about 38%, from the 2007
baseline estimate of $3,450 million.22 The report states that the Coast Guard has

21 Statement of Admiral Thad W. Allen, Commandant [of the Coast Guard], on the Coast Guard and Acquisitions
before the Committee on Appropriations Subcommittee on Homeland Security, U.S. House of Representatives, 22
April 2009, pp. 17-18. See also Calvin Biesecker, “Coast Guard’s NSC Fleet Cost Estimates Rise Due To Labor,
Commodity Issues,” Defense Daily, February 6, 2009: 2-3; Bettina H. Chavanne, “National Security Cutter Hulls
Below Fatigue Life Requirements,” Aerospace Daily & Defense Report, February 10, 2009: 1-2; Rebekah Gordon,
“First Two National Security Cutters Still Face Fatigue-Life Issues,” Inside the Navy, February 9, 2009.
22 Government Accountability Office, Coast Guard[:]As Deepwater Systems Integrator, Coast Guard Is Reassessing
Costs and Capabilities but Lags in Applying Its Disciplined Acquisition Approach
, GAO-09-682, July 2009, p. 18.
Congressional Research Service
19

Coast Guard Deepwater Acquisition Programs

made a significant investment in the NSC program before completing operational testing to
demonstrate that the capabilities it is buying meet Coast Guard needs. While some testing of
the NSC has already taken place, the tests conducted to date do not substitute for the
complete scope of operational testing that should be the basis for further investment. For
example, COMOPTEVFOR completed an operational assessment of the NSC in 2007 to
identify risks to the program’s successful completion of operational testing. Before the first
NSC was delivered, it also underwent acceptance trials, conducted by the U.S. Navy Board
of Inspection and Survey, to determine compliance with contract requirements and to test
system capabilities. Since delivery of the first NSC, the Coast Guard has also conducted
flight deck and combat system certifications with the assistance of the Navy. While these
demonstrations and certifications provide evidence that the first NSC functions as intended,
they do not fully demonstrate the suitability and effectiveness of the ship for Coast Guard
operations. According to officials, a test plan to demonstrate these capabilities is expected to
be approved in July 2009, and COMOPTEVFOR may begin operational testing in March
2010. However, by the time full operational testing is scheduled to be completed in 2011, the
Coast Guard plans to have six of eight NSCs either built or under contract.23
Sentinel Class Fast Response Cutter (FRC)
On March 14, 2007, the Coast Guard announced that it intended to procure the 12 FRC-B cutters,
also known as the Sentinel class, directly from the manufacturer, rather than through ICGS.24 On
June 22, 2007, the Coast Guard issued a Request for Proposals (RFP) for the FRC-B, with
submissions from industry due November 19, 2007. In February 2008, it was reported that the
contract to be awarded by the Coast Guard could be valued at up to $1.7 billion for 34 FRC-Bs, if
all options are executed.25 On September 26, 2008, the Coast Guard announced that it had
awarded an $88-million contract to Bollinger Shipyards for the design and construction of the
FRC-B, which the Coast Guard now refers to as the Sentinel class. On October 7, 2008, the
shipbuilding firm Marinette Marine filed a protest with GAO of the Coast Guard’s contract award
to Bollinger.26 On January 12, 2009, GAO denied the protest.27 On February 9, 2009, Marinette
Marine notified the Justice Department of its intent to file a second protest, but on February 17,
2009, it was reported that Marinette had withdrawn the second protest.28
Coast Guard Perspective
The Coast Guard testified in April 2009 that:

23 Government Accountability Office, Coast Guard[:]As Deepwater Systems Integrator, Coast Guard Is Reassessing
Costs and Capabilities but Lags in Applying Its Disciplined Acquisition Approach
, GAO-09-682, July 2009, pp. 14-15.
24 Coast Guard press release, “Coast Guard Reassigns Deepwater Replacement Patrol Boast Acquisition Project,”
March 14, 2007; Calvin Biesecker, “Coast Guard Strips FRC-B Patrol Boat Acquisition From ICGS,” Defense Daily,
March 15, 2007; Renae Merle, “Coast Guard Cancels Contract,” Washington Post, March 15, 2007; and David Stout,
“Coast Guard Cancels Contract For Vessel,” New York Times, March 15, 2007.
25 Andrea Shalal-Esa, “US Cost Guard Sees Patrol Boat Award in May or June,” Reuters, February 11, 2008. See also
Stew Magnuson, “Not So Fast on Fast Response Cutters, Coast Guard Says,” National Defense Magazine, February
2008.
26 Rebekah Gordon, “Marinette Marine Files Protest Over Coast Guard’s FRC Award,” Inside the Navy, October 13,
2009.
27 Rebekah Gordon, “GAO Denies Protest of Coast Guard Award to Bollinger for FRC,” Inside the Navy, January 19,
2009.
28 Amy McCullough, “Marinette Withdraws Patrol Boast Protest,” NavyTimes.com, February 17, 2009.
Congressional Research Service
20

Coast Guard Deepwater Acquisition Programs

business improvements have led to a number of high profile project successes. Consider the
recent award of the Fast Response Cutter (FRC) Sentinel-class patrol boat. Initially planned
as part of the Deepwater program, to be delivered through Integrated Coast Guard Systems
(ICGS), we took this project back within the Coast Guard to ensure full and open
competition and responsible program management. We have followed our reformed
acquisition processes, conducting a deliberative proposal review and award determination
with integrated participation from technical authorities and the operational community. The
FRC’s proven parentcraft design will minimize cost and schedule risk and mitigate the patrol
boat hour gap in the shortest time possible. Neither ICGS nor the Coast Guard’s pre-
modernized acquisition program could have accomplished this feat as efficiently or
effectively, and I am confident we will build on this record of advances for future
acquisitions programs as well....
The most pointed example of the success of our reformed acquisition processes is Fast
Response Cutter Sentinel-class patrol boat. With a total potential contract value of more than
$1 billion, it was a highly competitive process, and our selection survived two post-award
protests, demonstrating that our robust acquisition process was beyond reproach.
As the yard stick by which to measure the success of our reformed acquisition enterprise, the
Sentinel project provides a number of assurances - all built on the cornerstones for successful
acquisition - for its own and future acquisition management successes, including:
• Establishment and maintenance of a direct Coast Guard relationship with the contractor,
rather than through a separate lead systems integrator;
• Development of detailed technical requirements, and firm adherence to those requirements
throughout the proposal design evaluation process and construction;
• Classification of cutters to established and recognized standards (i.e., American Bureau of
Shipping and High Speed Naval Vessel Rules);
• Use of parent craft designs where applicable, with parent craft designer and builder co-
located on engineering team;
• On-site government staff at production facilities;
• Fixed price contract structure;
• Extensive involvement of technical authority throughout acquisition and delivery process;
• Independent validation (i.e., independent cost estimates and design assessments);
• Leveraging Navy and other government partnerships; and,
• Ability to re-compete thru options for data and licensing.
The Sentinel project has become the model for all current and future Coast Guard acquisition
programs.29

29 Statement of Admiral Thad W. Allen, Commandant [of the Coast Guard], on the Coast Guard and Acquisitions
before the Committee on Appropriations Subcommittee on Homeland Security, U.S. House of Representatives, 22
April 2009, pp. 2-3, 8-9.
Congressional Research Service
21

Coast Guard Deepwater Acquisition Programs

The Coast Guard also testified in April 2009 that:
our reform efforts are directly measured in the recent contract award for the critically needed
Fast Response Cutter Sentinel-class patrol boat. Initially planned as part of the Deepwater
program, to be delivered through Integrated Coast Guard Systems, we took this project back
within the Coast Guard to ensure full and open competition and responsible program
management. We have abided strictly to our reformed acquisition processes, conducting a
deliberative proposal review and award determination with integrated participation from
technical authorities and the operational community. Based on the cornerstones for
successful acquisition, this project also adheres to MSAM guidelines, full reporting,
independent assessment and validation, leveraging internal and external partnerships, and
robust departmental oversight.30
GAO Perspective
A July 2009 GAO report stated:
Based on its determination that the need for the capabilities to be provided by the Fast
Response Cutter and C4ISR is pressing, the Coast Guard has contracted for these capabilities
without having in place all acquisition documentation required by the MSAM. This situation
puts the Coast Guard at risk for cost overruns and schedule slips if it turns out that what it is
buying does not meet its requirements. For example, in September 2008, after conducting a
full and open competition, the Coast Guard awarded an $88.2 million contract to Bollinger
Shipyards, Inc. for the design and construction of a lead Fast Response Cutter. Prior to the
award, however, the Coast Guard did not have an approved operational requirements
document or test plan for this asset as required by the MSAM process. Recognizing the risks
inherent in this approach, the Coast Guard developed a basic requirements document and an
acquisition strategy based on procuring a proven design. These documents were reviewed
and approved by the Coast Guard’s capabilities directorate, the engineering and logistics
directorate, and chief of staff before the procurement began. The Coast Guard’s next
acquisition decision event is scheduled for the first quarter of fiscal year 2010 to obtain DHS
approval for low-rate initial production. According to officials, the Coast Guard intends to
submit an operational requirements document and test plan to DHS for this acquisition
decision event. With plans to exercise contract options for hulls 2 through 8 in fiscal year
2010, the Coast Guard’s aggressive schedule leaves little room for unforeseen problems.
Program risks are compounded by the fact that the Coast Guard plans to have at least 12
cutters either delivered or under contract prior to the scheduled completion of operational
testing in fiscal year 2012, before it has certainty that what it is buying meets Coast Guard
needs.31
110/123-Foot Patrol Boat Modernization
As an earlier part of the Deepwater program, the Coast Guard initiated an effort to modernize its
existing 110-foot Island class patrol boats, so that they could remain in service pending the
delivery of replacement Deepwater craft. Among other things, the modernization increased the

30 Statement of Admiral Thad W. Allen, Commandant [of the Coast Guard], on the Coast Guard and Acquisitions
before the Committee on Appropriations Subcommittee on Homeland Security, U.S. House of Representatives, 22
April 2009, pp. 15-16.
31 Government Accountability Office, Coast Guard[:]As Deepwater Systems Integrator, Coast Guard Is Reassessing
Costs and Capabilities but Lags in Applying Its Disciplined Acquisition Approach
, GAO-09-682, July 2009, p. 15.
Congressional Research Service
22

Coast Guard Deepwater Acquisition Programs

length of the boats to 123 feet. The effort is thus referred to variously as the 110-foot
modernization program, the 123-foot modernization program, or the 110/123-foot modernization
program.
The initial eight boats in the program began to develop significant structural problems soon after
completing their modernizations. The Coast Guard removed the boats from service and canceled
the program, having spent close to $100 million on it. On May 17, 2007, the Coast Guard issued a
letter to ICGS revoking its previous acceptance of the eight modernized boats—an action
intended to facilitate Coast Guard attempts to recover from ICGS funds that were spent on the
eight converted boats.32 On January 7 and 8, 2008, it was reported that the Coast Guard was
seeking a repayment of $96.1 million from ICGS for the patrol boats and had sent a letter to
ICGS on December 28, 2007, inviting ICGS to a negotiation for a settlement of the issue.33 Some
observers questioned the strength of the government’s legal case, and thus its prospects for
recovering the $96.1 million or some figure close to that.34
The Coast Guard testified in April 2009 that:
With regard to the 123-foot patrol boats, the Department of Justice and the DHS-OIG [the
DHS Office of the Inspector General] continue their investigation into the project. The qui
tam [legal] action involving the patrol boats is still on-going. The Department of Justice has
not yet made yet made a determination whether it will intervene in that action. The Coast
Guard continues its support of the DOJ and DHS-OIG investigation.
Simultaneous to our support of the DOJ investigation, we have also undertaken an
independent engineering analysis through the Navy’s Naval Sea Systems Command, which
we expect to be completed sometime this summer. Additionally, we are working with the
Department of Justice to release five of the eight patrol boats to salvage systems, equipment
and parts still of value to the Coast Guard. The remaining three cutters would remain
untouched for evidence purposes in support of the ongoing investigations.35
Revolving Door and Potential for Conflicts of Interest
The so-called revolving door, which refers to the movement of officials between positions in
government and industry, can create benefits for government and industry in terms of allowing
each side to understand the other’s needs and concerns, and in terms of spreading best practices
from one sector to the other. At the same time, some observers have long been concerned that the

32 Dan Caterinicchia, “Coast Guard Wants Refund For Ships,” Associated Press, May 17, 2007; Renae Merle, “Coast
Guard Seeks Deepwater Refund,” Washington Post, May 18, 2007: D3.
33 See Andrea Shalal-Esa, “Lockheed, Northrop Asked To Pay $96 Mln For Bad Boats,” Reuters, January 7, 2008;
Geoff Fein, “Coast Guard Invites ICGS To Negotiate A Settlement Over 123-Foot Boat Issue,” Defense Daily, January
8, 2008; Dan Caterinicchia, “Gov’t Wants $96M Refund For Faulty Ships,” Business Week, January 8, 2008. See also
Emelie Rutherford, “Coast Guard Wants $96 Million From Deepwater Team For Bad Ships,” Inside the Navy, January
14, 2008.
34 See, for example, Geoff Fein, “Coast Guard Invites ICGS To Negotiate A Settlement Over 123-Foot Boat Issue,”
Defense Daily, January 8, 2008. See also Geoff Fein, “Rep. Taylor Chides Coast Guard Over Effort To Recoup Cutter
Conversion Funds,” Defense Daily, February 27, 2008.
35 Statement of Admiral Thad W. Allen, Commandant [of the Coast Guard], on the Coast Guard and Acquisitions
before the Committee on Appropriations Subcommittee on Homeland Security, U.S. House of Representatives, 22
April 2009, p. 18. See also Bettina H. Chavanne, “Lawmakers Still Pressing USCG On Patrol Boat Conversion,”
Aerospace Daily & Defense Report, March 25, 2009: 3.
Congressional Research Service
23

Coast Guard Deepwater Acquisition Programs

revolving door might create conflicts of interest for officials carrying out their duties while in
government positions. A March 25, 2007, news article stated in part:
Four of the seven top U.S. Coast Guard officers who retired since 1998 took positions with
private firms involved in the Coast Guard’s troubled $24 billion fleet replacement program,
an effort that government investigators have criticized for putting contractors’ interests ahead
of taxpayers’.
They weren’t the only officials to oversee one of the federal government’s most complex
experiments at privatization, known as Deepwater, who had past or subsequent business ties
to the contract consortium led by industry giants Northrop Grumman and Lockheed Martin.
The secretary of transportation, Norman Y. Mineta, whose department included the Coast
Guard when the contract was awarded in 2002, was a former Lockheed executive. Two
deputy secretaries of the Department of Homeland Security, which the Coast Guard became
part of in 2003, were former Lockheed executives, and a third later served on its board.
Washington’s revolving-door laws have long allowed officials from industry giants such as
Lockheed, the nation’s largest defense contractor, to spend parts of their careers working for
U.S. security agencies that make huge purchases from those companies, though there are
limits.
But Deepwater dramatizes a new concern, current and former U.S. officials said: how
dwindling competition in the private sector, mushrooming federal defense spending and the
government’s diminished contract management skills raise the stakes for potential conflicts
of interest.
Deepwater also illustrates how federal ethics rules carve out loopholes for senior
policymakers to oversee decisions that may benefit former or prospective employers. These
include outsourcing strategies under which taxpayers bear most of the risks for failure,
analysts said.
There is no sign that any of the retired admirals or former Lockheed officials did anything
illegal.
But the connections between the agencies and the contractors have drawn the attention of the
DHS inspector general, Richard L. Skinner. “That is on our radar screen,” he said. “It’s
something we are very sensitive to.”36
Potential Options for Congress
In addition to approving or modifying the Coast Guard’s requests for FY2011 acquisition funding
Deepwater programs, potential options for Congress regarding the Deepwater program include
but are not limited to the following:
• continue to track the Coast Guard’s management and execution of Deepwater
acquisition programs, including implementation of reform actions announced by
the Coast Guard itself or recommended by GAO;

36 Spencer S. Hsu and Renae Merle, “Coast Guard’s Purchasing Raises Conflict-Of-Interest Flags,” Washington Post,
March 25, 2007.
Congressional Research Service
24

Coast Guard Deepwater Acquisition Programs

• modify reporting requirements for Deepwater acquisition programs;
• prohibit the obligation or expenditure of some or all FY2011 funding for
Deepwater acquisition programs until the Coast Guard or DHS takes certain
actions or makes certain certifications regarding the Deepwater program; and
• pass legislation to codify acquisition reforms for Deepwater programs that the
Coast Guard has already announced, or to change acquisition policies and
practices for Deepwater acquisition programs in other ways.
Legislative Activity in 111th Congress
Summary of Appropriations Action on FY2011 Funding Request
The Coast Guard’s proposed FY2011 budget requests $1,112.5 million in acquisition funding for
Deepwater programs, including $101.0 million for aircraft, $856.0 million for surface ships and
boats, and $155.5 million for other items. Table 4 summarizes appropriations action on this
funding request.
Table 4. Action on FY2011 Deepwater Acquisition Funding Request
(in millions of dollars, rounded to nearest tenth)
Appropriations
Program Request
HAC
SAC
conference
Maritime Patrol Aircraft (MPA)
40.0

49.0

HH-60 Conversion Projects
32.0

32.0

HH-65 Conversion/Sustainment Projects
0

0

HC-130H Conversion/Sustainment
25.0
25.0
Projects
HC-130J Fleet Introduction
4.0

4.0

Unmanned Aircraft Systems
0

2.0

Subtotal aircraft
101.0

112.0

National Security Cutter (NSC)
538.0

648.0

Offshore Patrol Cutter (OPC)
45.0

45.0

Fast Response Cutter (FRC)
240.0

240.0

Deepwater smal boats
3.0

3.0

Medium-endurance cutter sustainment
30.0

30.0

Patrol boats sustainment
0

0

Subtotal surface ships
856.0

966.0

Government program management
45.0

45.0

Systems engineering and integration
29.0

29.0

C4ISRa 30.5

30.5

Logistics 50.0

50.0

Technology obsolescence prevention
1

1.0

Subtotal other
155.5

155.5

TOTAL 1,112.5

1,233.5

Sources: FY2011 Coast Guard budget submission and SAC report (S.Rept. 111-222 of July 19, 2010) on the
FY2011 DHS appropriations bill (S. 3607).
Note: HAC is House Appropriations Committee; SAC is Senate Appropriations Committee.
a. Command and control, communications, computers, intelligence, surveillance and reconnaissance.
Congressional Research Service
25

Coast Guard Deepwater Acquisition Programs

FY2011 DHS Appropriations Bill (S. 3607)
Senate
As shown in Table 4, the Senate Appropriations Committee, in its report (S.Rept. 111-222 of July
19, 2010) on S. 3607, recommends a total of $1,233.5 million in the Coast Guard’s AC&I account
for Deepwater acquisition programs. The report states:
DEEPWATER FUNDING
The Committee recommends $1,233,502,000 for Deepwater, $121,000,000 above the
amount requested and $79,222,000 above the fiscal year 2010 level. Details of major
procurements under this program and other acquisitions are provided below.
MARITIME PATROL AIRCRAFT
The Committee recommends $49,000,000 for the Maritime Patrol Aircraft [MPA],
$9,000,000 above the budget request. Funds are recommended for the acquisition of one
aircraft (#15), which will provide an additional 1,200 hours to address the Coast Guard’s
MPA flight-hour gap. The amount above the request funds an additional mission system
pallet [MSP] and sparing. The Coast Guard is behind schedule in producing MSPs for its
fleet of MPAs. Closing this gap will accelerate the deployment of fully missionized aircraft
to the field.
UNMANNED AIRCRAFT SYSTEMS
In addition to funding included for the ship-based Unmanned Aircraft Systems [UAS]
project in the Committee’s recommendation for “Research, Development, Test, and
Evaluation,” the Committee includes $2,000,000 in this account to accelerate pre-acquisition
activities in accordance with the Coast Guard’s Major Systems Acquisition Manual
“Analyze/Select” Phase for the ship-based UAS.
NATIONAL SECURITY CUTTER
The recommendation includes $648,002,000 for the National Security Cutter [NSC]
acquisition, $110,000,000 above the budget request. The Committee disagrees with the
administration’s decision to delay funding for the 6th NSC. The NSC program, which is
already 2 years behind schedule, will be further delayed without additional funds. The 12
legacy cutters the NSC will replace are frequently out of service due to unscheduled
maintenance requirements. These 12 cutters lose an average of 250 operational days per year
due to unplanned maintenance, which is directly impacting the Coast Guard’s ability to
perform its many missions. Funds are provided to complete production of NSC #5, as
requested, and for long lead-time materials for NSC #6, which avoids additional project costs
and recapitalization delays associated with a break in NSC production. Funding long lead-
time material for NSC #6 in conjunction with production funding for NSC #5 is consistent
with the Department of Homeland Security’s approved Acquisition Program Baseline for the
NSC program.
The Committee strongly supports the procurement of one National Security Cutter per year
until all eight planned ships are procured. The continuation of production without a break
will ensure that these ships, which are vital to the Coast Guard’s mission, are procured at the
lowest cost, and that they enter the Coast Guard fleet as soon as possible.
Congressional Research Service
26

Coast Guard Deepwater Acquisition Programs

FAST RESPONSE CUTTER
The Committee recommends $240,000,000 for the Coast Guard’s Fast Response Cutter
[FRC], as requested. This funding will allow the Coast Guard to acquire four FRC hulls (9-
12). The first FRC is scheduled for delivery in fiscal year 2011 and will be fully operational
in fiscal year 2012. The Committee expects the Coast Guard to continue quarterly briefings
to the Committee on the status of this procurement, including critical decision points and
dates; status of service life extensions of the existing 110-foot patrol boats; and patrol boat
operational metrics.
MEDIUM ENDURANCE CUTTER SUSTAINMENT
The recommendation includes $30,000,000 for the Medium Endurance Cutter [WMEC]
Sustainment Project, as requested. Funding will complete sustainment work on three 270-
foot cutters. This funding is intended to improve mission effectiveness of these vessels to
allow them to meet their goals for program availability through the remainder of their service
lives. This program has been successful in significantly reducing the number of major
equipment failures on these vessels resulting in a much higher percentage of time they are
fully mission capable. The Committee is concerned that the total funding in the fiscal year
2011-15 Capital Investment Plan for the WMEC Sustainment project is $20,700,000 less
than the project’s approved Acquisition Program Baseline cost estimate. Work items will be
scaled back and the last two 270-foot WMECs will not undergo the sustainment project.
Given the success of this program in mitigating fleet equipment failures and delays in
fielding a replacement asset (Offshore Patrol Cutter), the Committee encourages the Coast
Guard to reconsider this decision as it develops its fiscal year 2012 budget request.
PATROL BOAT SUSTAINMENT
No funding is identified in the fiscal year 2011-15 Capital Investment Plan for patrol boat
sustainment due to the administration’s decision to de-scope the project. This decision
means that 17 instead of 20 patrol boats will undergo sustainment. While the Coast Guard is
in the process of acquiring 58 FRCs to replace the legacy patrol fleet (which has well
surpassed its expected service life), only 22 are expected to be delivered by the end of fiscal
year 2015. This should reinforce the need to sustain the legacy fleet until replacements are
deployed. The Committee encourages the Coast Guard to reconsider this decision as it
develops its fiscal year 2012 budget request.
OFFSHORE PATROL CUTTER
The recommendation includes $45,000,000 for the Offshore Patrol Cutter [OPC], as
requested. Funding provides for pre-acquisition activities. The Committee expects the Coast
Guard to provide quarterly briefings to the Committee on the status of this procurement,
including critical decision points and dates. Further, in accordance with section 511 of this
act, no funds may be used in contravention of the Buy American Act, including the
procurement of main propulsion engines for the OPC….
DEEPWATER EXPENDITURE PLAN
The Coast Guard is directed to brief the Committee on its fiscal year 2011 Deepwater
expenditure plan no later than 60 days after the date of enactment of this act. The briefing
Congressional Research Service
27

Coast Guard Deepwater Acquisition Programs

shall be consistent with the Deepwater expenditure plan requirements set forth in Public Law
110–329.37
QUARTERLY ACQUISITION REPORTS
The Commandant is directed to continue to submit to the Committee quarterly acquisition
and mission emphasis reports consistent with deadlines articulated under section 360 of
division I of Public Law 108–7.38 The Coast Guard shall continue submitting these reports

37 P.L. 110-329, a consolidated security, disaster assistance, and continuing appropriations act for FY2009, states, in the
paragraph that makes appropriations for the Coast Guard’s AC&I account, that the funds are made available, provided,
among other things,
That $350,000,000 of the funds provided for the Integrated Deepwater Systems program may not
be obligated until the Committees on Appropriations of the Senate and the House of
Representatives receive directly from the Coast Guard and approve a plan for expenditure that—
(1) defines activities, milestones, yearly costs, and life cycle costs for each new procurement of a
major asset, including an independent cost estimate for each;
(2) identifies life cycle staffing and training needs of Coast Guard project managers and
procurement and contract staff;
(3) identifies competition to be conducted in, and summarizes the approved acquisition strategy for,
each procurement;
(4) includes a certification by the Chief Human Capital Officer of the Department of Homeland
Security that current human capital capabilities are sufficient to execute the expenditure plan;
(5) includes an explanation of each procurement that involves an indefinite delivery/indefinite
quantity contract and explains the need for such contract;
(6) identifies individual project balances by fiscal year, including planned carryover into fiscal year
2010 by project;
(7) identifies operational gaps by asset and explains how funds provided in this Act address the
shortfalls between current operational capabilities and requirements;
(8) includes a listing of all open Government Accountability Office and Office of Inspector General
recommendations related to the program and the status of Coast Guard actions to address the
recommendations, including milestones for fully addressing them;
(9) includes a certification by the Chief Procurement Officer of the Department that the program
has been reviewed and approved in accordance with the investment management process of the
Department, and that the process fulfills all capital planning and investment control requirements
and reviews established by the Office of Management and Budget, including Circular A-11, part 7;
(10) identifies use of the Defense Contract Audit Agency;
(11) includes a certification by the head of contracting activity for the Coast Guard and the Chief
Procurement Officer of the Department that the plans for the program comply with the Federal
acquisition rules, requirements, guidelines, and practices, and a description of the actions being
taken to address areas of non-compliance, the risks associated with them along with plans for
addressing these risks, and the status of their implementation;
(12) identifies the use of independent validation and verification; and
(13) is reviewed by the Government Accountability Office….
38 Section 360 of Division I of P.L. 108-7, a consolidated appropriations resolution for FY2003, states:
SEC. 360. None of the funds provided in this Act or prior Appropriations Acts for Coast Guard
`Acquisition, construction, and improvements’ shall be available after the fifteenth day of any
quarter of any fiscal year, unless the Commandant of the Coast Guard first submits to the House
and Senate Committees on Appropriations a quarterly report on the agency’s mission hour
emphasis and a quarterly report on all major Coast Guard acquisition projects including projects
executed for the Coast Guard by the United States Navy and vessel traffic service projects:
Provided, That such acquisition reports shall include an acquisition schedule, estimated current and
year funding requirements, and a schedule of anticipated obligations and outlays for each major
acquisition project: Provided further, That such acquisition reports shall rate on a relative scale the
(continued...)
Congressional Research Service
28

Coast Guard Deepwater Acquisition Programs

in the same format as required in fiscal year 2010. In addition, for each asset covered, the
reports should present the objective for operational hours the Coast Guard expects to
achieve, the gap between that objective and current capabilities, and how the acquisition of
the specific asset closes the gap. The information should include a discussion of how the
Coast Guard calculated the operational hours, an explanation on risks to mission
performance associated with the current shortfall, and the operational strategy to mitigate
such risks.
GAO DEEPWATER REVIEW
The GAO is directed to continue its oversight of the Deepwater program, including a
continued focus on acquisitions nearing critical decision points and Coast Guard progress in
functioning as the systems integrator. GAO has informed the Committee that the Coast
Guard has not completed its planned fleet mix analysis that was intended to revalidate the
quantities of assets needed to meet mission needs. The Coast Guard is to complete this
analysis and submit the results no later than 120 days after the date of enactment of this act.
GAO shall provide an assessment of the report as part of its annual review of the Deepwater
program. (Pages 84-87; material in brackets as in original)
The report also states:
The Committee understands a review of the Coast Guard’s Deepwater cutter fleet
recapitalization program is being conducted by the Office of the Chief Financial Officer’s
Program Analysis and Evaluation Division [PA&E]. PA&E shall brief the Committee on this
effort no later than 90 days after the date of enactment of this act. (Page 21; material in
brackets as in original)
The report also states:
REPORTING REQUIREMENTS WITHOLDING
In an effort to encourage timely submissions to the Committees of materials necessary for
robust and informed oversight, the Committee withholds $75,000,000 from obligation from
the Coast Guard’s “Headquarters Directorates” until the Quarterly Acquisition Report for
the second quarter of fiscal year 2011, Revised Deepwater Implementation Plan, and a
comprehensive 5-year Capital Investment Plan for fiscal years 2012-2016 have been
submitted. (Pages 80-81)
Coast Guard Authorization Act of 2010 (H.R. 3619)
H.R. 3619 was passed by the House on October 23, 2009, and by the Senate on May 7, 2010. The
Senate-passed version substitutes the text of S. 1194 (see below), with modifications.

(...continued)
cost risk, schedule risk, and technical risk associated with each acquisition project and include a
table detailing unobligated balances to date and anticipated unobligated balances at the close of the
fiscal year and the close of the following fiscal year should the Administration’s pending budget
request for the acquisition, construction, and improvements account be fully funded: Provided
further, That such acquisition reports shall also provide abbreviated information on the status of
shore facility construction and renovation projects: Provided further, That all information submitted
in such mission hour emphasis and acquisition reports shall be current as of the last day of the
preceding quarter.
Congressional Research Service
29

Coast Guard Deepwater Acquisition Programs

House
In H.R. 3619 as reported by the House Transportation and Infrastructure Committee (H.Rept.
111-303 [Part 1] of October 16, 2009), Section 101(2)(b) would authorize $1,194.78 million in
Acquisition, Construction, and Improvements (AC&I) funding for Deepwater acquisition
programs. Section 1316 requires an assessment of needs for additional Coast Guard presence in
high-latitude regions, including, among other things, “an assessment of the high latitude operating
capabilities of all current Coast Guard assets, including assets acquired under the Deepwater
program.” Title V would reform Coast Guard acquisition, including Deepwater acquisition.
H.Rept. 111-303 (Part 1) discusses Title V on pages 86-90.
Senate
On May 7, 2010, the Senate passed S.Amdt. 3912, which amended H.R. 3619 by substituting the
text of S. 1194 as reported by the Senate Commerce, Science, and Transportation Committee (see
below), with modifications. The Senate then passed H.R. 3619 the same day.
Coast Guard Authorization Act for Fiscal Years 2010 and 2011 (S.
1194)

Senate
In S. 1194 as reported by the Senate Commerce, Science, and Transportation Committee S.Rept.
111-95 of October 30, 2009), Section 101(2) would authorize $1,383.98 million for the Coast
Guard’s Acquisition, Construction, and Improvements (AC&I) account, which funds both
Deepwater acquisition programs and other Coast Guard acquisition programs. Title V would
reform Coast Guard acquisition, including Deepwater acquisition. S.Rept. 111-95 discusses
Deepwater acquisition programs in general on pages 3-5, and Title V on pages 18-23.
On May 7, 2010, the Senate passed S.Amdt. 3912, which amended H.R. 3619 (see above) by
substituting the text of S. 1194 as reported by the Senate Commerce, Science, and Transportation
Committee, with modifications. The Senate then passed H.R. 3619 the same day.
Coast Guard Acquisition Reform Act of 2009 (H.R. 1665)
House
H.R. 1665, which was passed by the House on July 29, 2009, would reform Coast Guard
acquisition, including Deepwater acquisition. The House Transportation and Infrastructure
Committee’s report on the bill (H.Rept. 111-215 of July 20, 2009) discusses the Deepwater
program on pages 1-8.
Congressional Research Service
30

Coast Guard Deepwater Acquisition Programs

FY2010 DHS Appropriations Act (H.R. 2892/P.L. 111-83)
House
In addition to making funding recommendations for FY2010, the House Appropriations
Committee’s report (H.Rept. 111-157 of June 16, 2009) on H.R. 2892 stated the following
regarding Deepwater acquisition programs:
QUARTERLY REPORTS ON ACQUISITION PROJECTS AND MISSION
EMPHASIS
The Committee continues to find Coast Guard’s quarterly acquisition reports and mission
emphasis reports extremely useful, and as such, directs Coast Guard to continue submitting
these comprehensive reports in a timely fashion. The Coast Guard is directed to continue to
include in the acquisition reports information on small boat purchases and leases made
within the Operating Expenses appropriation.
STATUTORY REPORTING REQUIREMENTS
The Committee is frustrated that the Coast Guard failed to provide several reports required in
law that were to accompany the 2010 budget request. Specifically, P.L. 110–329 requires the
Coast Guard to submit a Deepwater expenditure plan and a capital investment plan, yet
neither was received. While these are not simple documents, these are not new requests. The
Coast Guard has been required to submit a capital investment plan every year since the
agency moved to DHS. Similarly, the Coast Guard has been required to submit an annual
expenditure plan using the fiscal year 2006 revised Deepwater Implementation Plan as the
base document since fiscal year 2007. These reports are critical because they provide the
Committee with needed data to assess the effectiveness of one of the country’s largest annual
investments in homeland security. The explanation provided in the budget justification for
the lack of data from a Capital Investment Plan is wholly inadequate in satisfying the
requirement. Although the Committee had chosen not to carry a withholding provision in the
bill this year out of consideration for possible dislocations in the reporting process due to the
transition of administrations, these documents should be provided to the Committee
immediately, or there is little question that the question of withholdings will be revisited.
DEEPWATER
The Committee recommends $1,014,980,000 for Deepwater, $36,500,000 below the amount
requested and $19,014,000 below the amount provided in fiscal year 2009.
MARITIME PATROL AIRCRAFT
The Maritime Patrol Aircraft (MPA) serves as the Coast Guard’s lead fixed-wing extended
surveillance and quick response platform. The Committee recommends $138,500,000 for
two additional MPAs, mission pallets, spares, and logistics support as requested. The
Committee does not include $36,500,000 requested for accelerating the purchase of a MPA
flight simulator ahead of its original schedule.
MARITIME SURVEILLANCE
The Committee has consistently voiced its concerns over the gap between the Coast Guard’s
stated mission hour needs for maritime surveillance and available resource hours of
surveillance assets. These concerns are based upon the Coast Guard’s quantitative analysis of
Congressional Research Service
31

Coast Guard Deepwater Acquisition Programs

mission requirements and repeated testimony by operational personnel and security experts
on the need for increased maritime surveillance capabilities, especially in the source and
transit zones of the eastern Pacific Ocean and the Caribbean basin. The Committee is pleased
the fiscal year 2010 budget request partially addresses this issue through funding for aircraft
acquisition, conversion and sustainment. However, the Committee is concerned by the
absence of requested funding to support operational testing and evaluation of either land-
based or cutter-based unmanned aerial systems (UAS) in fiscal year 2010 given the
unrealized potential of such assets for enhanced maritime surveillance. Furthermore, the
Committee notes that even with these additional surveillance resources requested for fiscal
year 2010, the Coast Guard’s available maritime surveillance hours will only be at
approximately 65 percent of stated mission needs. The Coast Guard is directed to report to
the Committee no later than November 1, 2009, on its planned efforts to leverage available
interagency resources and other temporary surveillance capabilities, including the
operational testing and evaluation of UAS, in fiscal year 2010 to address the maritime
surveillance mission hour gap.
NATIONAL SECURITY CUTTER
The National Security Cutter (NSC) is the replacement for the 378-foot High Endurance
Cutter, and as such, is capable of worldwide operations, extended on-scene presence, long
transit and forward deployments. The Committee recommends $281,480,000 for the NSC as
requested, $72,220,000 below the amount provided in fiscal year 2009. The Committee does
this despite persistent concerns regarding cost controls and the production schedule for this
class of cutter. These concerns are predicated on the fact that the cost of the fourth NSC is
more than $73,700,000 and fourteen percent higher than the previous two cutters in this class
and that the Coast Guard’s current schedule delays the award for the fifth NSC until 2011.
The Committee is troubled by a projected production schedule for the remaining NSCs that
delays fulfillment of known operational needs and appears to enable further cost growth and
delays in cutter delivery. These concerns are exacerbated by the absence of requested
funding for known, immediate maintenance needs of the legacy high endurance cutters
(HECs) in fiscal year 2010. The Committee views the confluence of the NSC’s extended
production schedule with the uncertain long-term availability of the legacy HEC fleet as a
detriment to offshore maritime security operations and directs the Coast Guard to: prioritize
maintenance needs of the HEC fleet, as addressed elsewhere in this report, and inform the
Committee no later than July 1, 2009, of its efforts to put in place a contractual structure for
the remaining NSCs that will provide expeditious delivery at the least cost and risk to the
taxpayer.
OFFSHORE PATROL CUTTER
The Offshore Patrol Cutter (OPC) is the replacement vessel for the current 210-foot and 270-
foot Medium Endurance cutters. The Committee provides the requested $9,800,000 to
complete alternatives analysis and required acquisition documentation for the OPC, as well
as beginning Phase I of preliminary design. The Committee understands from the Coast
Guard that this approach will help reduce the risk of program cost growth. Given that such
cost growth was behind the decision to stop work on the initial OPC, the Coast Guard is
directed to brief the Committee on the result of the requirements analysis prior to initiating
Phase I work on the new OPC.
FAST RESPONSE CUTTER
The Fast Response Cutter (FRC) is the more capable replacement for the Coast Guard’s
legacy 110-foot patrol boats. The Committee provides the requested $243,000,000 for full-
rate production of four FRCs, $127,700,000 above the amount provided in fiscal year 2009.
The Coast Guard is expected to take delivery of the first FRC in fiscal year 2010. The
Congressional Research Service
32

Coast Guard Deepwater Acquisition Programs

Committee directs the Coast Guard to include in its quarterly briefings to the Committee on
the FRC’s progress information on the effectiveness of its various efforts to control cost
growth.
LEGACY CUTTER SUSTAINMENT
The Committee continues to be concerned about legacy cutter sustainment as new vessels are
being slowly brought into service. The Committee understands that the funding level in the
request for cutter sustainment allows for these programs to continue on schedule, with the
shipyards working at optimal capacity. The Committee is pleased by the increases in vessel
availability resulting from the sustainment programs in place for patrol boats and Medium-
Endurance Cutters. Coast Guard reporting indicates that the Medium Endurance Cutter
Sustainment Program has increased the fully-capable mission availability of 270-foot cutters
by 62 percent, and 210-foot cutters by 75 percent. Also, the Committee notes that attention to
critical maintenance needs in the 378-foot High Endurance Cutter fleet has resulted in more
marginal improvements in availability, and urges the Coast Guard to move ahead on a more
robust sustainment option for the High Endurance Cutter.
DEEPWATER REVIEW AND CAPITAL INVESTMENT PLAN
The Committee notes that neither the Secretary’s review of the Revised Deepwater
Implementation Plan nor the future-years capital investment plan mandated in P.L. 110–329
were provided with the budget request. The Committee strongly urges the Department to
produce those items expeditiously, and make sure that similar mandates carried in this
legislation are met. (Pages 81-84)
Senate
In addition to making funding recommendations for FY2010, the Senate Appropriations
Committee’s report (S.Rept. 111-31 of June 18, 2009) on the FY2010 DHS appropriations bill (S.
1298) stated the following regarding Deepwater acquisition programs:
DEEPWATER FUNDING
The Committee recommends $1,194,780,000 for Deepwater, $143,300,000 above the
amount requested and $160,786,000 above the fiscal year 2009 level. Details of major
procurements under this program and changes to the request are provided below.
MARITIME PATROL AIRCRAFT
The Committee recommends $175,000,000 for the Maritime Patrol Aircraft [MPA], the same
level as proposed in the budget request. This funding will allow the Coast Guard to acquire 2
aircraft (13 and 14), mission systems, and a flight simulator. The funds will address the
Coast Guard’s MPA flight-hour gap by providing 2,400 additional MPA hours every year.
NATIONAL SECURITY CUTTER
The recommendation includes $389,480,000 for the National Security Cutter [NSC]
acquisition, $108,000,000 above the budget request. The Committee disagrees with the
administration’s decision to delay funding for the 5th NSC. The NSC program, which is
already 2 years behind schedule, will be further delayed without additional funds. The 12
legacy cutters the NSC will replace are frequently out of service due to unscheduled
maintenance requirements. These 12 cutters lose an average of 250 operational days per year
due to unplanned maintenance, which is directly impacting the Coast Guard’s ability to
Congressional Research Service
33

Coast Guard Deepwater Acquisition Programs

perform its many missions. Funds are provided to complete production of NSC #4 and for
long-lead time materials for NSC #5, which ensures the Coast Guard is properly positioned
to negotiate a best-value, fixed-price contract for NSC #4 and avoids additional project costs
and recapitalization delays associated with a break in NSC production.
The Committee strongly supports the procurement of one National Security Cutter per year
until all eight planned ships are procured. The continuation of production without a break
will ensure that these ships, which are vital to the Coast Guard’s mission, are procured at the
lowest cost, and that they enter the Coast Guard fleet as soon as possible.
FAST RESPONSE CUTTER
The Committee recommends $243,000,000 for the Coast Guard’s ‘‘Fast Response Cutter’’
[FRC–B], the same level as proposed in the budget request. This funding will allow the
Coast Guard to acquire four FRC–B hulls (5–8). The first FRC–B is scheduled for delivery
in the third quarter of fiscal year 2011 and will be fully operational in fiscal year 2012. The
Committee expects the Coast Guard to continue quarterly briefings on the status of this
procurement, including critical decision points and dates, planned service life extensions of
the existing 110-foot patrol boats, and patrol boat operational metrics.
MISSION EFFECTIVENESS PROJECT
The recommendation includes $54,100,000 for the Mission Effectiveness Project, the same
level as proposed in the budget request. Of this amount, $31,100,000 is for sustainment of
three 270-foot and two 210-foot medium endurance cutters, and $23,000,000 is for
sustainment of three 110-foot legacy patrol boats. This funding is intended to improve
mission effectiveness of these vessels to allow them to meet their goals for program
availability through the remainder of their service lives. This program has been successful in
significantly reducing the number of major equipment casualties on these vessels resulting in
a much higher percentage of time they are fully mission capable.
OFFSHORE PATROL CUTTER
The recommendation includes $9,800,000 for the Offshore Patrol Cutter [OPC], the same
level as proposed in the budget request. The Committee directs the Coast Guard to brief the
Committee by April 30, 2010, on the results of the alternatives analysis for the OPC....
POLAR ICEBREAKER SUSTAINMENT
The Committee recommends $32,500,000 above the budget request to complete the
reactivation and service life extension of Coast Guard Cutter Polar Star. Of this amount,
$5,200,000 is funded in the AC&I direct personnel costs PPA. Returning Polar Star to
operational status is vital to ensuring the U.S. Government has the ability to project U.S.
sovereignty and protect the broad range of security, economic, and environmental interests in
the Arctic and Antarctic. Within this amount, the Coast Guard shall begin survey and design
and conduct a business case analysis for either a new heavy polar icebreaker class or a major
service life extension project for existing heavy icebreakers. The only existing heavy polar
class icebreaker, the Polar Sea, has only 7 years remaining in its useful life....
HIGH ENDURANCE CUTTER SUSTAINMENT
Delays in the planned delivery of National Security Cutters have created a sustainment
problem for the Coast Guard in maintaining its fleet of legacy High Endurance Cutters. The
Committee is aware of efforts to assess the need and scope for a maintenance plan for the
378-foot High Endurance Cutter fleet. The Committee includes $8,000,000 above the request
Congressional Research Service
34

Coast Guard Deepwater Acquisition Programs

for pre-acquisition survey and design to determine the requirements for a maintenance
effectiveness project. A similar program for the Medium Endurance Cutter fleet has been
highly successful in increasing its fully-capable mission availability. The Coast Guard shall
brief the Committee no later than 60 days after the date of enactment of this act on
preliminary plans for this effort.
AC&I PERSONNEL
The Committee provides $105,200,000 for personnel and related support, $5,200,000 above
the budget request. These additional FTEs are necessary for the Coast Guard to perform the
systems integrator role for the Deepwater Program and to execute traditional acquisition
projects. This amount also includes personnel related costs to reactivate the Polar Star.
The Committee is well aware of the limited pool of certified and experienced acquisition
professionals. Therefore, the Committee encourages the Coast Guard to work with the
appropriate authorizing committees to ensure that its hiring authorities are on par with those
of the other armed services.
According to recent testimony by the Government Accountability Office, “there are
approximately 200 contractor employees in support of the acquisition directorate—
representing 24 percent of its total acquisition workforce.” Some of these contractors are
performing core Government acquisition functions. The Coast Guard shall brief the
Committee no later than 60 days after the date of enactment of this act on efforts to reduce
reliance on contractors performing inherently governmental work....
DEEPWATER EXPENDITURE PLAN
The Coast Guard is directed to brief the Committee on its fiscal year 2010 deepwater
expenditure plan not later than 60 days after the date of enactment of this act. The briefing
shall be consistent with the Deepwater expenditure plan requirements set forth in Public Law
110–329.
QUARTERLY ACQUISITION REPORTS
The Commandant is directed to continue to submit quarterly acquisition and mission
emphasis reports consistent with deadlines articulated under section 360 of division I of
Public Law 108–7 and the fiscal year 2008 joint explanatory statement. The Committee notes
that the Coast Guard has adopted the practice of comparing cost, schedule, and performance
estimates against the most recently approved baseline. This approach provides an incomplete
assessment of an acquisition’s progress against the original baseline. Therefore, the report
shall compare current estimates against the original baseline and the most recent baseline, if
available. This method is consistent with Department of Defense acquisition reporting policy
and is recommended by the Government Accountability Office. When reporting on “key
project documents,” it should be noted if approved documentation differs from that required
by the Major Systems Acquisition Manual or the Department’s Acquisition Review
guidance. The reports should also indicate if a test and evaluation master plan has been
approved for an asset. Finally, the acquisition reports shall include a “stoplight chart” that
tracks key performance parameters of each asset through developmental and operational
testing. Because the Coast Guard consistently fails to meet quarterly submission deadlines,
the Committee withholds $30,000,000 from Headquarter Directorates until the second
quarter report is submitted.
Congressional Research Service
35

Coast Guard Deepwater Acquisition Programs

GAO DEEPWATER REVIEW
The GAO is directed to continue its oversight of the Deepwater program. GAO’s focus shall
include an assessment of the Coast Guard’s conversion projects for the HH–60 and HH–65
platforms. The Committee is concerned with the schedule for both programs. According to
the Coast Guard’s quarterly acquisition reports, the schedule for the HH–60 program is at
“significant risk” and is not expected to meet projected milestones. The same reports show a
moderate schedule risk for the HH–65 conversion program. Delays in the HH–65 conversion
program have resulted in an unobligated balance in excess of $100,000,000 and the Coast
Guard expects to carryover $58,729,000 into fiscal year 2010. (Pages 77-80)
Conference
In H.R. 2892/P.L. 111-83 of October 28, 2009 as reported by the conference committee (H.Rept.
111-298 of October 13, 2009), the paragraph that appropriates funds for the Coast Guard’s
Operating Expenses (OE) account states:
That of the funds provided under this heading, $50,000,000 shall be withheld from obligation
for Headquarters Directorates until: (1) the fiscal year 2010 second quarter acquisition report
required by Public Law 108–7 and the fiscal year 2008 joint explanatory statement
accompanying Public Law 110–161; (2) the Revised Deepwater Implementation Plan; and
(3) the future-years capital investment plan for fiscal years 2011–2015 are received by the
Committees on Appropriations of the Senate and the House of Representatives....
The paragraph that appropriates funs for the Coast Guard’s Acquisition, Construction, and
Improvements (AC&I) account appropriated $1,154.28 million for Deepwater acquisition
programs,
Provided, That of the funds made available for the Integrated Deepwater Systems program,
$269,000,000 is for aircraft and $730,680,000 is for surface ships: Provided further, That the
Secretary of Homeland Security shall submit to the Committees on Appropriations of the
Senate and the House of Representatives, in conjunction with the President’s fiscal year 2011
budget, a review of the Revised Deepwater Implementation Plan that identifies any changes
to the plan for the fiscal year; an annual performance comparison of Integrated Deepwater
Systems program assets to pre-Deepwater legacy assets; a status report of such legacy assets;
a detailed explanation of how the costs of such legacy assets are being accounted for within
the Integrated Deepwater Systems program; and the earned value management system gold
card data for each Integrated Deepwater Systems program asset: Provided further, That the
Secretary shall submit to the Committees on Appropriations of the Senate and the House of
Representatives, in conjunction with the fiscal year 2011 budget request, a comprehensive
review of the Revised Deepwater Implementation Plan, and every 5 years thereafter, that
includes a complete projection of the acquisition costs and schedule for the duration of the
plan.
In addition appropriating funding for Deepwater acquisition programs for FY2010, the
conference report states the following regarding Deepwater acquisition programs:
Comprehensive Review of the Revised Deepwater Implementation Plan
The conferees note with emphasis the legislative requirement for the Secretary to submit a
comprehensive review of the Revised Deepwater Implementation Plan (RDIP). The
longstanding requirements for this review are specific: a complete projection of the
acquisition costs and schedule for the duration of the RDIP. The conferees expect this review
Congressional Research Service
36

Coast Guard Deepwater Acquisition Programs

to update the original RDIP estimated total cost of $24.2 billion and projected completion by
fiscal year 2027. Furthermore, the review should clearly and comprehensively display the
types and quantities of operational assets covered by the RDIP and the costs and schedule, by
fiscal year and by asset, for the replacement or phase-out of legacy assets through
refurbishment or acquisition. Since the recapitalization of the Coast Guard’s cutters, aircraft,
and C4ISR systems is a complex, multiyear, and integrated program, the conferees believe it
is imperative to evaluate the complete acquisition program baseline, by asset, through the
duration of the RDIP. Given that this RDIP review has been mandated in every annual
appropriations Act for DHS since the first RDIP was established in November 2006, the
conferees cannot foresee any justification for undue delay from DHS and the Coast Guard in
submitting a review that fully complies with the specified requirements, including complete
baseline costs. As noted previously in this statement, $50,000,000 is withheld from
obligation from Coast Guard Headquarters Directorates until this RDIP review is submitted
to the Committees, along with the Capital Investment Plan for fiscal years 2011–2015 and
the Quarterly Acquisition Report for the second quarter of fiscal year 2010....
Maritime Patrol Aircraft
The conference agreement provides $138,500,000 for the Maritime Patrol Aircraft
acquisition as proposed by the House instead of $175,000,000 as proposed by the Senate.
Funds are available for maritime patrol aircraft, mission pallets, simulator, and associated
project costs. The Coast Guard is to brief the Committees no later than 30 days after the date
of enactment of this Act on the planned distribution of these funds.
National Security Cutter
The conference agreement provides $389,480,000 for the National Security Cutter (NSC)
acquisition as proposed by the Senate instead of $281,480,000 as proposed by the House.
These funds are to complete production of NSC #4 and for long lead-time materials for NSC
#5. The conferees direct the Coast Guard to finalize the integrated logistics plan for the NSC
and to brief the Committees on it within 60 days of the date of enactment of this Act.
Offshore Patrol Cutter
The conferees direct the Coast Guard to brief the Committees by March 15, 2010, on the
progress of its ongoing preliminary acquisition work on the Offshore Patrol Cutter, including
the results of the requirements and alternatives analyses.
Fast Response Cutter
The conferees expect the Coast Guard to continue quarterly briefings on the status of the Fast
Response Cutter procurement as outlined in the Senate report, including information on the
effectiveness of its efforts to control cost growth in the program.
Polar Icebreaker Sustainment
The conference agreement provides an additional $32,500,000 to complete the reactivation
and service life extension of the Coast Guard Cutter POLAR STAR as proposed by the
Senate. No additional funding for this activity was proposed by the House. Of this amount,
$5,200,000 is provided in the Acquisition, Construction, and Improvements direct personnel
costs PPA. Funds shall be applied as specified in the Senate report. The conferees believe
returning POLAR STAR to operational status is vital to national interests in the polar
regions. According to the Coast Guard the only existing operational heavy icebreaker, the
POLAR SEA, has only five years of service life remaining. The absence of requested
funding to complete fiscal year 2009 efforts to reactivate POLAR STAR, combined with the
Congressional Research Service
37

Coast Guard Deepwater Acquisition Programs

lack of compliance with standing Congressional direction on the polar icebreaking budget,
implies a broader lack of commitment to sustaining polar capabilities and achieving
longterm, strategic objectives in the Arctic. The conferees direct the Coast Guard to brief the
Committees no later than December 15, 2009, on the program execution plan for reactivation
of POLAR STAR and the status of resources required to achieve mission requirements for
polar operations.
High Endurance Cutter Sustainment
The conference agreement provides $4,000,000 above the request for pre-acquisition survey
and design to determine the requirements for a maintenance effectiveness project for the
High Endurance Cutter, instead of the $8,000,000 as proposed by the Senate. No additional
funding for this activity was proposed by the House. The conferees direct the Coast Guard to
brief the Committees no later than 60 days after the date of enactment of this Act on
preliminary plans for this effort, as proposed by the Senate. (Pages 88-89)
The conference report also states:
Reporting Requirements Withholding
The conferees note that despite legislative mandates the Coast Guard has failed to produce an
expenditure plan for the Integrated Deepwater Systems program, a Capital Investment Plan,
or Quarterly Acquisition Reports in time to be of use during the fiscal year 2010
appropriations process. In an effort to encourage timely submissions to the Committees of
materials necessary for robust and informed oversight, the conference report withholds
$50,000,000 from obligation from the Coast Guard’s Headquarters Directorates PPA
[program, project, or activity] until the Revised Deepwater Implementation Plan, a
comprehensive five-year Capital Investment Plan for fiscal years 2011–2015, and the
Quarterly Acquisition Report for the second quarter of fiscal year 2010 have been submitted
to the Committees. (Page 83)
The conference report also states:
Government Accountability Office Reviews
The conferees direct the GAO to continue its oversight of the Deepwater Program. In
addition to the programs highlighted in the Senate report, GAO should focus on programs
nearing critical decision points, such as the Fast Response Cutter, Maritime Patrol Aircraft,
and C4ISR, as well as continuing its ongoing work reviewing the acquisition of the NSC and
changes made to acquisition processes and policies at both the component and Departmental
level that will affect how the Coast Guard functions as systems integrator. The conferees
expect GAO to review Coast Guard expenditure plans once they are transmitted to the
Committees. (Pages 90-91)

Congressional Research Service
38

Coast Guard Deepwater Acquisition Programs

Appendix A. Criticism of Deepwater Management
in 2007

Overall Management of Program
Many observers in 2007 believed the problems experienced in the three Deepwater cutter
acquisition efforts were the product of broader problems in the Coast Guard’s overall
management of the Deepwater program. Reports and testimony in 2007 and prior years from the
DHS IG and GAO, as well as a February 2007 DAU “quick look study” requested by the Coast
Guard39 expressed serious concerns about the Coast Guard’s overall management of the
Deepwater program.
Some observers expressed the view that using a private-sector LSI to implement the Deepwater
program made a complex program more complex, and set the stage for waste, fraud, and abuse by
effectively outsourcing oversight of the program to the private sector and by creating a conflict of
interest for the private sector in executing the program. Other observers, including GAO and the
DAU, expressed the view that using a private-sector LSI is a basically valid approach, but that the
contract the Coast Guard used to implement the approach for the Deepwater program was flawed
in various ways, undermining the Coast Guard’s ability to assess contractor performance, control
costs, ensure accountability, and conduct general oversight of the program.
Observers raised various issues about the Deepwater contract. Among other things, they
expressed concern that the contract was an indefinite delivery, indefinite quantity (ID/IQ)
contract, which, they said, can be an inappropriate kind of contract for a program like the
Deepwater program. Observers also expressed concern that the contract
• transferred too much authority to the private-sector LSI for defining performance
specifications, for subsequently modifying them, and for making technical
judgements;
• permitted the private-sector LSI to certify that certain performance goals had
been met—so-called self-certification, which, critics argue, can equate to no
meaningful certification;
• provided the Coast Guard with insufficient authority over the private-sector LSI
for resolving technical disputes between the Coast Guard and the private-sector
LSI;
• was vaguely worded with regard to certain operational requirements and
technical specifications, reducing the Coast Guard’s ability to assess performance
and ensure that the program would achieve Coast Guard goals;
• permitted the firms making up the private-sector LSI to make little use of
competition between suppliers in selecting products to be used in the Deepwater
program, to tailor requirements to fit their own products, and consequently to rely
too much on their own products, as opposed to products available from other
manufacturers;

39 Defense Acquisition University, Quick Look Study, United States Coast Guard Deepwater Program, February 2007.
Congressional Research Service
39

Coast Guard Deepwater Acquisition Programs

• permitted the private-sector LSI’s performance during the first five-year period to
be scored in a way that did not sufficiently take into account recent problems in
the cutter acquisition efforts;
• permitted award fees and incentive fees (i.e., bonuses) to be paid to the private-
sector LSI on the basis of “attitude and effort” rather than successful outcomes;
and
• lacked sufficient penalties and exit clauses.
Observers also expressed concern that the Coast Guard did not have enough in-house staff and in-
house expertise in areas such as program management, financial management, and system
integration to properly oversee and manage an acquisition effort as large and complex as the
Deepwater program, and that the Coast Guard did not make sufficient use of the Navy or other
third-party, independent sources of technical expertise, advice, and assessments. They also
expressed concern that the Coast Guard, in implementing the Deepwater program, placed a higher
priority on meeting a schedule as opposed to ensuring performance.
In response to criticisms of the management and execution of the Deepwater program, Coast
Guard and industry officials acknowledged certain problems in the program’s management and
execution and defended the program’s management execution in other respects.40
National Security Cutter (NSC)
A DHS IG report released in January 2007 strongly criticized the NSC program, citing design
flaws in the ship and the Coast Guard’s decision to start construction of NSCs in spite of early
internal notifications about these flaws. The design flaws involved, among other things, areas in
the hull with insufficient fatigue life—that is, with insufficient strength to withstand the stresses
of at-sea operations for a full 30-year service life. The DHS IG report also noted considerable
growth in the cost to build the first two NSCs, and other issues.41
Observers in 2007 stated that the Coast Guard failed to report problems about the NSC effort to
Congress on a timely basis, resisted efforts by the DHS IG to investigate the NSC effort, and
appeared to have altered briefing slides on the NSC effort so as to downplay the design flaws to
certain audiences. On May 17, 2007, the DHS IG testified that the Coast Guard’s cooperation
with the DHS IG had substantially improved (though some issues remained), but that Deepwater

40 For examples of Coast Guard testimony, see Department of Homeland Security, U.S. Coast Guard, Statement of
Admiral Thad W. Allen, Commandant, on Deepwater: 120-Days Later, Before the Subcommittee on Coast Guard &
Maritime Transportation, Committee on Transportation & Infrastructure, U.S. House of Representatives, June 12,
2007; and Department of Homeland Security, U.S. Coast Guard, Statement of Rear Admiral Gary T. Blore and Captain
Steven Baynes on Deepwater: Charting a Course For Safer Waters, Before the Committee on Homeland Security, U.S.
House of Representatives, Subcommittees on Management, Investigations, and Oversight and Border, Maritime and
Global Counterterrorism, May 17, 2007.
For examples of industry testimony, see Statement for the Record, Mr. James E. Anton, Vice President Deepwater
Program, Northrop Grumman Ship Systems (NGSS), Testimony Before: The House Maritime and Global Counter-
Terrorism Subcommittee And The House Management, Investigations and Oversight Subcommittee, May 17, 2007;
and Testimony of Fred P. Moosally, President, Lockheed Martin Maritime Systems and Sensors, to The House
Committee on Homeland Security Subcommittee on Border, Maritime and Global Counterterrorism, May 17, 2007.
41 Department of Homeland Security, Office of Inspector General, Acquisition of the National Security Cutter, OIG -
07-23, January 2007. The report is available online at http://www.dhs.gov/xoig/assets/mgmtrpts/OIG_07-23_Jan07.pdf.
Congressional Research Service
40

Coast Guard Deepwater Acquisition Programs

contractors had establishing unacceptable conditions for DHS IG to interview contractor
personnel about the program.
110-Foot Patrol Boat Modernization
The Coast Guard originally planned to modernize and lengthen its 49 existing Island-class 110-
foot patrol boats so as to improve their capabilities and extend their lives until their planned
eventual replacement with FRCs starting in 2018. The work lengthened the boats to 123 feet. The
program consequently is referred to as the 110-foot or 123-foot or 110/123 modernization
program.
Eight of the boats were modernized at a total cost of about $96 million. The first of the eight
modernized boats was delivered in March 2004. Structural problems were soon discovered in
them. In June 2005, the Coast Guard stopped the modernization effort at eight boats after
determining that they lacked capabilities needed for meeting post-9/11 Coast Guard operational
requirements.
In August 2006, a former Lockheed engineer posted on the Internet a video alleging four other
problems with the 110-foot patrol boat modernization effort.42 The engineer had previously
presented these problems to the DHS IG, and a February 2007 report from the DHS IG confirmed
two of the four problems.43
On November 30, 2006, the Coast Guard announced that it was suspending operations of the
eight modernized boats (which were assigned to Coast Guard Sector Key West, FL) because of
the discovery of additional structural damage to their hulls. The suspension prompted expressions
of concern that the action could reduce the Coast Guard’s border-enforcement capabilities in the
Caribbean. The Coast Guard said it was exploring options for addressing operational gaps
resulting from the decision.44
On April 17, 2007, the Coast Guard announced that it would permanently decommission the eight
converted boats and strip them of equipment and components that might be reused on other Coast
Guard platforms.45 The Coast Guard acknowledged in 2007 that the program was a failure.

42 Patricia Kime, “Video Alleges Security Problems With Converted U.S. Coast Guard Cutters,” DefenseNews.com,
August 7, 2006. See also Griff Witte, “On YouTube, Charges Of Security Flaws,” Washington Post, August 29, 2006.
The video is posted on the Internet at http://www.youtube.com/watch?v=qd3VV8Za04g.
43 Department of Homeland Security, Office of Inspector General, 110’/123’ Maritime Patrol Boat Modernization
Project
, OIG -07-27, January 2007. The report is available online at http://www.dhs.gov/xoig/assets/mgmtrpts/
OIG_07-27_Feb07.pdf.
44 “Coast Guard Statement on Suspension of Converted Patrol Boat Operations,” InsideDefense.com, November 30,
2006; Patricia Kime, “U.S. Coast Guard Pulls 123s Out of Service,” DefenseNews.com, November 30, 2006; Calvin
Biesecker, “Coast Guard Suspends 123-Foot Patrol Boat Operations,” DefenseDaily, December 1, 2006; Robert Block,
“Coast Guard Fleet Cuts Could Hurt Border Patrols,” Wall Street Journal, December 1, 2006; Renae Merle, “Coast
Guard Finds Flaws In Converted Patrol Boats,” Washington Post, December 2, 2006; Renae Merle and Spencer S. Hsu,
“Costly Fleet Update Falters,” Washington Post, December 8, 2006.
45 Coast Guard Press Release dated April 17, 2007, entitled “Statement by Adm. Thad Allen on the Converted 123-Foot
Patrol Boats and Changes to the Deepwater Acquisition Program.” See also Geoff Fein, “Coast Guard Nixes 123-Foot
Patrol Boat, Assumes Lead of Deepwater Effort,” Defense Daily, April 18, 2007; Patricia Kime, “Coast Guard To
Decommission Troubled 123s,” NavyTimes.com, April 18, 2007.
Congressional Research Service
41

Coast Guard Deepwater Acquisition Programs

Fast Response Cutter (FRC)
As a result of the problems in the 110-foot patrol boat modernization project, the Coast Guard
accelerated the FRC design and construction effort by 10 years. Problems, however, were
discovered in the FRC design. The Coast Guard suspended work on the design in February 2006,
and then divided the FRC effort into two classes—the FRC-Bs, which are to be procured in the
near term, using an existing patrol boat design (which the Coast Guard calls a “parent craft”
design), and the subsequent FRC-As, which are to be based on a fixed version of the new FRC
design.
As mentioned earlier, although the November 2006 Deepwater APB calls for 12 FRCs and 46
FRC-Bs, the Coast Guard’s Request for Proposals (RFP) for the FRC-B program includes options
for building up to 34 FRC-Bs (which, if exercised, would reduce the number of FRC-As to as few
as 24). The Coast Guard has also stated that if the FRC-Bs fully meet the requirements for the
FRC, all 58 of the FRCs might be built to the FRC-B design.
Congressional Research Service
42

Coast Guard Deepwater Acquisition Programs

Appendix B. Coast Guard Reform Actions in 2007
Actions Announced in April 2007
On April 17, 2007, the Coast Guard announced six changes intended to reform management of
the Deepwater program. In announcing the actions, Admiral Thad Allen, the Commandant of the
Coast Guard, stated in part:
Working together with industry, the Coast Guard will make the following six [6]
fundamental changes in the management of our Deepwater program:
[1] The Coast Guard will assume the lead role as systems integrator for all Coast Guard
Deepwater assets, as well as other major acquisitions as appropriate....
[2] The Coast Guard will take full responsibility for leading the management of all life cycle
logistics functions within the Deepwater program under a an improved logistics architecture
established with the new mission support organization.
[3] The Coast Guard will expand the role of the American Bureau of Shipping, or other
third-parties as appropriate, for Deepwater vessels to increase assurances that Deepwater
assets are properly designed and constructed in accordance with established standards.
[4] The Coast Guard will work collaboratively with Integrated Coast Guard Systems to
identify and implement an expeditious resolution to all outstanding issues regarding the
national security cutters.
[5] The Coast Guard will consider placing contract responsibilities for continued production
of an asset class on a case-by-case basis directly with the prime vendor consistent with
competition requirements if: (1) deemed to be in the best interest of the government and (2)
only after we verify lead asset performance with established mission requirements.
[6] Finally, I will meet no less than quarterly with my counterparts from industry until any
and all Deepwater program issues are fully adjudicated and resolved. Our next meeting is to
be scheduled within a month.
These improvements in program management and oversight going forward will change the
course of Deepwater.
By redefining our roles and responsibilities, redefining our relationships with our industry
partners, and redefining how we assess the success of government and industry management
and performance, the Deepwater program of tomorrow will be fundamentally better than the
Deepwater program of today....
As many of you know, I have directed a number of significant organizational changes [to the
Coast Guard], embedded within direction and orders, to better prepare the Coast Guard to
meet and sustain mission performance long into the future as we confront a broad range of
converging threats and challenges to the safety, security and stewardship of America’s vital
maritime interests.
What’s important to understand here is that these proposed changes in organizational
structure, alignment and business processes, intended to make the Coast Guard more
Congressional Research Service
43

Coast Guard Deepwater Acquisition Programs

adaptive, responsive and accountable, are not separate and distinct from what we have been
doing over the past year to improve Deepwater.
In fact, many of these initiatives can be traced directly to challenges we’ve faced, in part, in
our Deepwater program. Consequently, we will be better organized, better trained, and better
equipped to manage large, complex acquisitions like Deepwater in the coming days, weeks,
months and years as we complete these service-wide enhancements to our mission support
systems, specifically our acquisition, financial and logistics functions. That is the future of
the Coast Guard, and that is the future of Deepwater.
To be frank, I am tired of looking in the rearview mirror - conducting what has been the
equivalent of an archaeological dig into Deepwater. We already understand all too well what
has been ailing us within Deepwater in the past five years:
We’ve relied too much on contractors to do the work of government as a result of tightening
AC&I budgets, a dearth of contracting personnel in the federal government, and a loss of
focus on critical governmental roles and responsibilities in the management and oversight of
the program.
We struggle with balancing the benefits of innovation and technology offered through the
private sector against the government’s fundamental reliance on robust competition.
Both industry and government have failed to fully understand each other’s needs and
requirements, all too often resulting in both organizations operating at counter-odds to one
another that have benefited neither industry nor government.
And both industry and government have failed to accurately predict and control costs.
While we can—and are—certainly learning from the past, we ought to be about the business
of looking forward—with binoculars even—as we seek to see what is out over the horizon so
we can better prepare to anticipate challenges and develop solutions with full transparency
and accountability. That is the business of government. And it’s the same principle that
needs to govern business as well.
And it’s precisely what I intend to do: with the changes in management and oversight I
outlined for you here today, with the changes we are making in the terms and conditions of
the Deepwater contract, and with the changes we will make in our acquisition and logistics
support systems throughout the Coast Guard. If we do, I have no doubt in my mind that we
will exceed all expectations for Deepwater....
The Deepwater program of tomorrow will be fundamentally better than the Deepwater
program of today.
The Coast Guard has a long history of demonstrating exceptional stewardship and care of the
ships, aircraft and resources provided it by the public, routinely extending the life of our
assets far beyond original design specifications to meet the vital maritime safety, security
and stewardship needs of the nation....
Knowing that to be the case, I am personally committed to ensuring that our newest ships,
aircraft and systems acquired through the Coast Guard’s Integrated Deepwater System are
capable of meeting our mission requirements from the moment they enter service until they
are taken out of service many, many years into the future....
Congressional Research Service
44

Coast Guard Deepwater Acquisition Programs

As I’ve said many times in the past, the safety and security of all Americans depends on a
ready and capable Coast Guard, and the Coast Guard depends on our Deepwater program to
keep us ready long into the future.
The changes to Deepwater management and oversight I outlined here for you today reflect a
significant change in the course of Deepwater. I will vigorously implement these and other
changes that may be necessary to ensure that our Coast Guard men and women have the
most capable fleet of ships, aircraft and systems they need to do the job I ask them to do each
and every day on behalf of the American people.46
Other Actions Announced in 2007
The Coast Guard in 2007 also did the following:
• announced a reorganization of certain Coast Guard commands—including the
creation of a unified Coast Guard acquisition office—that is intended in part to
strengthen the Coast Guard’s ability to manage acquisition projects, including the
Deepwater program;
• stated that would alter the terms of the Deepwater contract for the 43-month
award term that commenced in June 2007 so as to address concerns raised about
the current Deepwater contract;
• announced that it intended to procure the 12 FRC-B cutters directly from the
manufacturer, rather than through ICGS;
• stated that it was hiring additional people with acquisition experience, so as to
strengthen its in-house capability for managing the Deepwater program and other
Coast Guard acquisition efforts;
• stated that it concurred with many of the recommendations made in the DHS IG
reports, and was moving to implement them;
• stated that it was weighing the recommendations of the DAU quick look study;
and
• stated that it had also implemented many recommendations regarding Deepwater
program management that have been made by GAO.


46 Coast Guard Press Release dated April 17, 2007, entitled “Statement by Adm. Thad Allen on the Converted 123-Foot
Patrol Boats and Changes to the Deepwater Acquisition Program.”
Congressional Research Service
45

Coast Guard Deepwater Acquisition Programs

Author Contact Information

Ronald O'Rourke

Specialist in Naval Affairs
rorourke@crs.loc.gov, 7-7610


Congressional Research Service
46