Navy Littoral Combat Ship (LCS) Program: 
Background, Issues, and Options for Congress 
Ronald O'Rourke 
Specialist in Naval Affairs 
September 27, 2010 
Congressional Research Service
7-5700 
www.crs.gov 
RL33741 
CRS Report for Congress
P
  repared for Members and Committees of Congress        
Navy Littoral Combat Ship (LCS) Program 
 
Summary 
The Littoral Combat Ship (LCS) is a relatively inexpensive Navy surface combatant equipped 
with modular “plug-and-fight” mission packages. The basic version of the LCS, without any 
mission packages, is referred to as the LCS sea frame. 
The Navy wants to field a force of 55 LCSs. The first two (LCS-1 and LCS-2) were procured in 
FY2005 and FY2006 and were commissioned into service on November 8, 2008, and January 16, 
2010. Another two (LCS-3 and LCS-4) were procured in FY2009 and are under construction. 
Two more (LCS-5 and LCS-6) were procured in FY2010. 
The Navy’s FY2011-FY2015 shipbuilding plan calls for procuring 17 more LCSs in annual 
quantities of 2, 3, 4, 4, and 4. The Navy’s proposed FY2011 budget requests $1,231.0 million in 
procurement funding for the two LCSs that the Navy wants to procure in FY2011, and $278.4 
million in FY2011 advance procurement funding for the 11 LCSs that the Navy wants to procure 
in FY2012-FY2014. The Navy’s proposed FY2011 budget also requests procurement funding to 
procure LCS module weapons and LCS mission packages, and research and development funding 
for the LCS program. 
There are currently two very different LCS designs—one developed and produced by an industry 
team led by Lockheed, and another developed and produced by an industry team led by General 
Dynamics. LCS-1 and LCS-3 use the Lockheed design; LCS-2 and LCS-4 use the General 
Dynamics design. 
On September 16, 2009, the Navy announced a proposed new LCS acquisition strategy. Under 
the strategy, the Navy would hold a competition to pick a single design to which all LCSs 
procured in FY2010 and subsequent years would be built. (The process of selecting the single 
design for all future production is called a down select.) The winner of the down select would be 
awarded a contract to build 10 LCSs over the five-year period FY2010-FY2014, at a rate of two 
ships per year. The Navy would then hold a second competition—open to all bidders other than 
the shipyard building the 10 LCSs in FY2010-FY2014—to select a second shipyard to build up to 
five additional LCSs to the same design in FY2012-FY2014 (one ship in FY2012, and two ships 
per year in FY2013-FY2014). These two shipyards would then compete for contracts to build 
LCSs procured in FY2015 and subsequent years. 
Section 121(a) and (b) of the FY2010 defense authorization act (H.R. 2647/P.L. 111-84 of 
October 28, 2009) grant the Navy contracting and other authority needed to implement this new 
LCS acquisition strategy. 
The Navy had earlier planned to make the down select decision and award the contract to build 
the 10 LCSs sometime this past summer, but the decision was delayed and reportedly will now 
occur within 90 days of September 15—the date by which the two industry teams were told by 
the Navy to submit new proposal revisions. On this basis, it would appear that the decision could 
be announced as late as December 14. 
FY2011 issues for Congress include whether to approve, reject, or modify the Navy’s request for 
FY2011 procurement and advance procurement funding for the LCS program, and whether to 
provide any additional direction to the Navy regarding LCS acquisition strategy. 
 
Congressional Research Service 
Navy Littoral Combat Ship (LCS) Program 
 
Contents 
Introduction ................................................................................................................................ 1 
Background ................................................................................................................................ 2 
The LCS in General .............................................................................................................. 2 
Two Industry Teams, Each with Its Own Design.................................................................... 3 
Planned Procurement Quantities............................................................................................ 3 
Unit Procurement Cost Cap................................................................................................... 3 
Growth in Sea Frame Procurement Costs .............................................................................. 4 
2007 Program Restructuring and Ship Cancellations ............................................................. 5 
New Acquisition Strategy Announced in September 2009...................................................... 5 
FY2011 Funding Request ...................................................................................................... 6 
Issues for Congress ..................................................................................................................... 6 
New Acquisition Strategy Announced in September 2009...................................................... 6 
Enough Time for Adequate Congressional Review of Navy Proposal? ............................. 7 
Enough Time to Evaluate the Two Designs’ Operational Characteristics? ...................... 10 
Weight Given to Procurement Cost vs. Other Factors in Request for Proposals 
(RFP)......................................................................................................................... 11 
Potential Risks If First Shipyard Cannot Build Ships Within Cost.................................. 13 
Increasing LCS Combat System Commonality with Other Combat Systems .................. 13 
Navy’s Longer-Term Plans Regarding Two “Orphan” Ships .......................................... 13 
Potential Alternatives to Navy’s New Strategy............................................................... 14 
Unit Procurement Cost Cap................................................................................................. 16 
Cost Growth on LCS Sea Frames ........................................................................................ 16 
Total Program Acquisition Cost........................................................................................... 17 
Operation and Support (O&S) Cost ..................................................................................... 18 
Operational Concepts .......................................................................................................... 19 
Combat Survivability .......................................................................................................... 19 
Technical Risk .................................................................................................................... 20 
Seaframe....................................................................................................................... 20 
Mission Packages.......................................................................................................... 21 
Impact of Cancellation of NLOS-LS Missile System ........................................................... 24 
Legislative Activity for FY2011 ................................................................................................ 25 
Summary of Congressional Action on FY2011 Funding Request ......................................... 25 
FY2011 Defense Authorization Bill (H.R. 5136/S. 3454)..................................................... 26 
House ........................................................................................................................... 26 
Senate ........................................................................................................................... 27 
FY2011 DOD Appropriations Bill (S. 3800)........................................................................ 28 
Senate ........................................................................................................................... 28 
 
Tables 
Table 1. Congressional Action on FY2011 LCS Funding Request .............................................. 25 
Table C-1. Status of LCSs Funded in FY2005-FY2009.............................................................. 40 
 
Congressional Research Service 
Navy Littoral Combat Ship (LCS) Program 
 
Appendixes 
Appendix A. Summary of Congressional Action in FY2005-FY2010......................................... 30 
Appendix B. Cost Growth on LCS Sea Frames.......................................................................... 32 
Appendix C. 2007 Program Restructuring and Ship Cancellations ............................................. 38 
Appendix D. LCS Acquisition Strategy Announced in September 2009 ..................................... 41 
Appendix E. May 2010 Navy Testimony Regarding Fuel Costs as Evaluation Factor................. 45 
Appendix F. May 2010 Navy Testimony Regarding Impact of NLOS-LS Cancellation .............. 51 
Appendix G. Potential for Common Hulls.................................................................................. 53 
 
Contacts 
Author Contact Information ...................................................................................................... 58 
 
Congressional Research Service 
Navy Littoral Combat Ship (LCS) Program 
 
Introduction 
The Littoral Combat Ship (LCS) is a relatively inexpensive Navy surface combatant equipped 
with modular “plug-and-fight” mission packages. The basic version of the LCS, without any 
mission packages, is referred to as the LCS sea frame. 
The Navy wants to field a force of 55 LCSs. The first two (LCS-1 and LCS-2) were procured in 
FY2005 and FY2006 and were commissioned into service on November 8, 2008, and January 16, 
2010. Another two (LCS-3 and LCS-4) were procured in FY2009 and are under construction. 
Two more (LCS-5 and LCS-6) were procured in FY2010. 
The Navy’s FY2011-FY2015 shipbuilding plan calls for procuring 17 more LCSs in annual 
quantities of 2, 3, 4, 4, and 4. The Navy’s proposed FY2011 budget requests $1,231.0 million in 
procurement funding for the two LCSs that the Navy wants to procure in FY2011, and $278.4 
million in FY2011 advance procurement funding for the 11 LCSs that the Navy wants to procure 
in FY2012-FY2014. The Navy’s proposed FY2011 budget also requests procurement funding to 
procure LCS module weapons and LCS mission packages, and research and development funding 
for the LCS program. 
There are currently two very different LCS designs—one developed and produced by an industry 
team led by Lockheed, and another developed and produced by an industry team led by General 
Dynamics. LCS-1 and LCS-3 use the Lockheed design; LCS-2 and LCS-4 use the General 
Dynamics design. 
On September 16, 2009, the Navy announced a proposed new LCS acquisition strategy. Under 
the strategy, the Navy would hold a competition to pick a single design to which all LCSs 
procured in FY2010 and subsequent years would be built. (The process of selecting the single 
design for all future production is called a down select.) The winner of the down select would be 
awarded a contract to build 10 LCSs over the five-year period FY2010-FY2014, at a rate of two 
ships per year. The Navy would then hold a second competition—open to all bidders other than 
the shipyard building the 10 LCSs in FY2010-FY2014—to select a second shipyard to build up to 
five additional LCSs to the same design in FY2012-FY2014 (one ship in FY2012, and two ships 
per year in FY2013-FY2014). These two shipyards would then compete for contracts to build 
LCSs procured in FY2015 and subsequent years. 
Section 121(a) and (b) of the FY2010 defense authorization act (H.R. 2647/P.L. 111-84 of 
October 28, 2009) grant the Navy contracting and other authority needed to implement this new 
LCS acquisition strategy. 
The Navy had earlier planned to make the down select decision and award the contract to build 
the 10 LCSs sometime this past summer, but the decision was delayed and reportedly will now 
occur within 90 days of September 15—the date by which the two industry teams were told by 
the Navy to submit new proposal revisions. On this basis, it would appear that the decision could 
be announced as late as December 14.1 
                                                             
1 Cid Standifer and Andrew Burt, “LCS Decision May Extend To December; Senate Cuts One Ship From FY-11, 
Inside the Navy, September 20, 2010. 
Congressional Research Service 
1 
Navy Littoral Combat Ship (LCS) Program 
 
FY2011 issues for Congress include whether to approve, reject, or modify the Navy’s request for 
FY2011 procurement and advance procurement funding for the LCS program, and whether to 
provide any additional direction to the Navy regarding LCS acquisition strategy. Decisions that 
Congress makes on this issue could affect future Navy capabilities and funding requirements, and 
the shipbuilding industrial base. 
Background 
The LCS in General 
The LCS program was announced on November 1, 2001.2 The LCS is a relatively inexpensive 
Navy surface combatant that is to be equipped with modular “plug-and-fight” mission packages, 
including unmanned vehicles (UVs). Rather than being a multimission ship like the Navy’s larger 
surface combatants, the LCS is to be a focused-mission ship equipped to perform one primary 
mission at any one time. The ship’s mission orientation can be changed by changing out its 
mission packages. The basic version of the LCS, without any mission packages, is referred to as 
the LCS sea frame. 
The LCS’s primary intended missions are antisubmarine warfare (ASW), mine countermeasures 
(MCM), and surface warfare (SUW) against small boats (including so-called “swarm boats”), 
particularly in littoral (i.e., near-shore) waters. The LCS program includes the development and 
procurement of ASW, MCM, and SUW mission packages for LCS sea frames. Additional 
missions for the LCS include peacetime engagement and partnership-building operations, 
intelligence, surveillance, and reconnaissance (ISR) operations, maritime intercept operations, 
operations to support special operations forces, and homeland defense operations. 
The LCS displaces about 3,000 tons, making it about the size of a corvette (i.e., a light frigate) or 
a Coast Guard cutter. It has a maximum speed of more than 40 knots, compared to something 
more than 30 knots for the Navy cruisers and destroyers. The LCS has a shallower draft than 
Navy cruisers and destroyers, permitting it to operate in certain coastal waters and visit certain 
ports that are not accessible to Navy cruisers and destroyers. The LCS employs automation to 
achieve a reduced “core” crew of 40 sailors. Up to 35 or so additional sailors are to operate the 
ship’s embarked aircraft and mission packages, making for a total crew of about 75, compared to 
more than 200 for the Navy’s frigates and about 300 (or more) for the Navy’s current cruisers and 
destroyers. 
                                                             
2 On November 1, 2001, the Navy announced that it was launching a Future Surface Combatant Program aimed at 
acquiring a family of next-generation surface combatants. This new family of surface combatants, the Navy stated, 
would include three new classes of ships: a destroyer called the DD(X)—later redesignated the DDG-1000—for the 
precision long-range strike and naval gunfire mission; a cruiser called the CG(X) for the air defense and ballistic 
missile mission, and a smaller combatant called the Littoral Combat Ship (LCS) to counter submarines, small surface 
attack craft, and mines in heavily contested littoral (near-shore) areas. For more on the DDG-1000 program, see CRS 
Report RL32109, Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress, by 
Ronald O'Rourke. For more on the CG(X) program, see CRS Report RL34179, Navy CG(X) Cruiser Program: 
Background for Congress, by Ronald O'Rourke. 
Congressional Research Service 
2 
Navy Littoral Combat Ship (LCS) Program 
 
Two Industry Teams, Each with Its Own Design 
On May 27, 2004, the Navy awarded contracts to two industry teams—one led by Lockheed 
Martin, the other by General Dynamics (GD)—to design two versions of the LCS, with options 
for each team to build up to two LCSs each. The two teams’ LCS designs are quite different—
Lockheed’s design is based on a steel semi-planing monohull, while GD’s design is based on an 
aluminum trimaran hull. The two ships also use different combat systems (i.e., different 
collections of built-in sensors, computers, software, and tactical displays) that were designed by 
each industry team. The Navy states that both designs meet the Key Performance Parameters 
(KPPs) for the LCS program. The Lockheed team built LCS-1 and is building LCS-3 at Marinette 
Marine of Marinette, WI. The General Dynamics team built LCS-2 and is building LCS-4 at the 
Austal USA shipyard of Mobile, AL.3 
Planned Procurement Quantities 
The Navy plans to field a force of 55 LCS sea frames and 64 LCS mission packages (16 ASW, 24 
MCM, and 24 SUW). The Navy’s planned force of 55 LCSs would account for about 18% of the 
Navy’s planned force of 313 ships of all types.4 
The Navy’s five-year (FY2011-FY2015) shipbuilding plan calls for procuring 17 LCSs in annual 
quantities of 2, 3, 4, 4, and 4. The Navy’s 30-year (FY2011-FY2040) shipbuilding plan shows 
three LCSs per year for FY2016-FY2019, two per year for FY2020-FY2024, a 1-2-1-2 pattern for 
FY2025-FY2033, and two per year for FY2034-FY2040. LCSs scheduled for procurement in the 
final years of the 30-year plan would be replacements for LCSs that will have reached the end of 
their 25-year expected service lives by that time. 
Unit Procurement Cost Cap 
LCS sea frames procured in FY2010 and subsequent years are subject to a unit procurement cost 
cap. The legislative history of the cost cap is as follows: 
•  The cost cap was originally established by Section 124 of the FY2006 defense 
authorization act (H.R. 1815/P.L. 109-163 of January 6, 2006). Under this 
provision, the fifth and sixth ships in the class were to cost no more than $220 
million each, plus adjustments for inflation and other factors. 
•  The cost cap was amended by Section 125 of the FY2008 defense 
authorization act (H.R. 4986/P.L. 110-181 of January 28, 2008). This provision 
amended the cost cap to $460 million per ship, with no adjustments for inflation, 
and applied the cap to all LCSs procured in FY2008 and subsequent years. 
                                                             
3 Austal USA was created in 1999 as a joint venture between Austal Limited of Henderson, Western Australia and 
Bender Shipbuilding & Repair Company of Mobile, AL. The GD LCS team also includes GD/BIW as prime contractor 
to provide program management and planning, provide technical management, and to serve as “LCS system production 
lead.” 
4 For more on the Navy’s planned 313-ship fleet, see CRS Report RL32665, Navy Force Structure and Shipbuilding 
Plans: Background and Issues for Congress, by Ronald O'Rourke. 
Congressional Research Service 
3 
Navy Littoral Combat Ship (LCS) Program 
 
•  The cost cap was amended again by Section 122 of the FY2009 defense 
authorization act (S. 3001/P.L. 110-417 of October 14, 2008). This provision 
deferred the implementation of the cost cap by two years, applying it to all LCSs 
procured in FY2010 and subsequent years. 
•  The cost cap was amended again by Section 121(c) and (d) of the FY2010 
defense authorization act (H.R. 2647/P.L. 111-84 of October 28, 2009). The 
provision adjusted the cost cap to $480 million per ship, excluded certain costs 
from being counted against the $480 million cap, included provisions for 
adjusting that figure over time to take inflation and other events into account, and 
permitted the Secretary of the Navy to waive the cost cap under certain 
conditions.5 
Growth in Sea Frame Procurement Costs 
The Navy originally spoke of building LCS sea frames for about $220 million each in constant 
FY2005 dollars. Estimated LCS sea frame unit procurement costs have since more than doubled. 
The FY2011 budget estimates the procurement costs of LCS sea frames to be procured in 
FY2011-FY2015 at roughly $600 million each in then-year dollars. An August 2010 Government 
Accountability Office (GAO) report on the LCS program stated: 
The Navy entered contract negotiations in 2009 for fiscal year 2010 funded [LCS] seaframes 
with an incomplete understanding of LCS program costs. These contract negotiations proved 
unsuccessful, prompting the Navy to revise its acquisition strategy for the program. The 
contractors’ proposals for construction of the next three ships exceeded the approximate $1.4 
billion in funds the Navy had allocated in its fiscal year 2010 budget. In response, the Navy 
revised its strategy to construct one seaframe design instead of two for fiscal year 2010 ships 
and beyond in an effort to improve affordability. Navy cost analyses completed prior to the 
failed negotiations in 2009 lack several characteristics essential to a high-quality cost 
estimate. These characteristics include the completion of sensitivity and uncertainty analyses 
and an independent review of the cost estimate. The Navy plans to complete a more 
comprehensive cost estimate before award of additional ship contracts in 2010.6 
For a detailed discussion of cost growth on LCS sea frames from the FY2006 budget cycle 
through the FY2009 budget cycle, see Appendix B. 
                                                             
5 Section 121(d)(1) states that the Secretary of the Navy may waive the cost cap if: 
(A) the Secretary provides supporting data and certifies in writing to the congressional defense 
committees that— 
(i) the total amount obligated or expended for procurement of the vessel- 
(I) is in the best interest of the United States; and 
(II) is affordable, within the context of the annual naval vessel construction plan required 
by section 231 of title 10, United States Code; and 
(ii) the total amount obligated or expended for procurement of at least one other vessel 
authorized by subsection (a) has been or is expected to be less than $480,000,000; and 
(B) a period of not less than 30 days has expired following the date on which such certification and 
data are submitted to the congressional defense committees. 
6 Government Accountability Office, Defense Acquisitions[:] Navy’s Ability to Overcome Challenges Facing the 
Littoral Combat Ship Will Determine Eventual Capabilities, GAO-10-523, August 2010, summary page. 
Congressional Research Service 
4 
Navy Littoral Combat Ship (LCS) Program 
 
2007 Program Restructuring and Ship Cancellations 
The Navy substantially restructured the LCS program in 2007 in response to significant cost 
growth and delays in constructing the first LCS sea frames. This restructuring led to the 
cancellation of four LCSs that were funded in FY2006 and FY2007. A fifth LCS, funded in 
FY2008, was cancelled in 2008. For details on the 2007 program restructuring and the 
cancellation of the five LCSs funded in FY2006-FY2008, see Appendix C. 
New Acquisition Strategy Announced in September 2009 
On September 16, 2009, the Navy announced a proposed new LCS acquisition strategy.7 Under 
the strategy, the Navy would hold a competition to pick a single design to which all LCSs 
procured in FY2010 and subsequent years would be built. (The process of selecting the single 
design for all future production is called a down select.) The winner of the down select would be 
awarded a contract to build 10 LCSs over the five-year period FY2010-FY2014, at a rate of two 
ships per year. The Navy would then hold a second competition—open to all bidders other than 
the shipyard building the 10 LCSs in FY2010-FY2014—to select a second shipyard to build up to 
five additional LCSs to the same design in FY2012-FY2014 (one ship in FY2012, and two ships 
per year in FY2013-FY2014). These two shipyards would then compete for contracts to build 
LCSs procured in FY2015 and subsequent years. 
Section 121(a) and (b) of the FY2010 defense authorization act (H.R. 2647/P.L. 111-84 of 
October 28, 2009) grant the Navy contracting and other authority needed to implement this new 
LCS acquisition strategy. 
The Navy had earlier planned to make the down select decision and award the contract to build 
the 10 LCSs sometime this past summer, but the decision was delayed and reportedly will now 
occur within 90 days of September 15—the date by which the two industry teams were told by 
the Navy to submit new proposal revisions. On this basis, it would appear that the decision could 
be announced as late as December 14.8 An August 25, 2010, press report stated that “the Defense 
                                                             
7 Prior to the Navy’s announcement of September 16, 2009, the Navy had announced an acquisition strategy for LCSs 
to be procured in FY2009 and FY2010. Under this acquisition strategy, the Navy bundled together the two LCSs 
funded in FY2009 (LCSs 3 and 4) with the three LCSs to be requested for FY2010 into a single, five-ship solicitation. 
The Navy announced that each LCS industry team would be awarded a contract for one of the FY2009 ships, and that 
the prices that the two teams bid for both the FY2009 ships and the FY2010 ships would determine the allocation of the 
three FY2010 ships, with the winning team getting two of the FY2010 ships and the other team getting one FY2010 
ship. This strategy was intended to use the carrot of the third FY2010 ship to generate bidding pressure on the two 
industry teams for both the FY2009 ships and the FY2010 ships. 
The Navy stated that the contracts for the two FY2009 ships would be awarded by the end of January 2009. The first 
contract (for Lockheed Martin, to build LCS-3) was awarded March 23, 2009; the second contract (for General 
Dynamics, to build LCS-4) was awarded May 1, 2009. The delay in the awarding of the contracts past the end-of-
January target date may have been due in part to the challenge the Navy faced in coming to agreement with the industry 
teams on prices for the two FY2009 ships that would permit the three FY2010 ships to be built within the $460 million 
LCS unit procurement cost cap. See also Statement of RADM Victor Guillory, U.S. Navy Director of Surface Warfare, 
and RADM William E. Landay, III, Program Executive Officer Ships, and Ms. E. Anne Sandel, Program Executive 
Officer Littoral and Mine Warfare, before the Subcommittee on Seapower and Expeditionary Forces of the House 
Armed Services Committee [hearing] on the Current Status of the Littoral Combat Ship Program, March 10, 2009, pp. 
7-8. 
8 Cid Standifer and Andrew Burt, “LCS Decision May Extend To December; Senate Cuts One Ship From FY-11, 
Inside the Navy, September 20, 2010. 
Congressional Research Service 
5 
Navy Littoral Combat Ship (LCS) Program 
 
Acquisition Board now won’t meet until mid-October to give the green light to the Navy to 
proceed with the LCS contract award.”9 An August 30, 2010, press report stated: 
A Navy official said that the contract for the next batch of LCSs cannot be awarded before 
the DAB meets; however, the Navy could [nevertheless] make its downselect decision 
between the designs…. He added that the Navy hasn't determined whether it would announce 
its downselect decision at that time.10 
For additional background information on the Navy’s new acquisition strategy, see Appendix D. 
FY2011 Funding Request 
The Navy’s proposed FY2011 budget requests $1,231.0 million in procurement funding for the 
two LCSs that the Navy wants to procure in FY2011, and $278.4 million in FY2011 advance 
procurement funding for the 11 LCSs that the Navy wants to procure in FY2012-FY2014. The 
Navy’s proposed FY2011 budget estimates the procurement costs of LCS sea frames to be 
procured in FY2011-FY2015 at roughly $600 million each in then-year dollars. The Navy’s 
proposed FY2011 budget also requests $9.8 million in procurement funding to procure LCS 
module weapons, $83.0 million in procurement funding for procurement of LCS mission 
packages, and $226.3 million in research and development funding for the LCS program. 
Issues for Congress 
New Acquisition Strategy Announced in September 2009 
The new LCS acquisition strategy announced by the Navy on September 16, 2009, poses several 
potential oversight questions for Congress, including the following: 
•  Did the timing of the Navy’s September 2009 announcement of the new 
strategy—very late in the congressional process for reviewing, marking up, and 
finalizing action on the FY2010 defense budget—provide Congress with 
sufficient time to adequately review the proposal prior to finalizing its action on 
the FY2010 defense budget? 
•  Does the Navy’s proposed strategy allow the Navy enough time to adequately 
evaluate the operational characteristics of the two LCS designs before selecting 
one of those designs for all future production? 
•  Does the Navy’s proposed method for conducting the LCS down select—the 
Request for Proposals (RFP)—appropriately balance procurement cost against 
other criteria, such as life-cycle operation and support (O&S) cost and ship 
capability? 
                                                             
9 Geoff Fein, “Navy Won’t Make LCS Award Before Fall As It Awaits Additional Industry Responses,” Defense Daily, 
August 25, 2010: 4-5. See also Cid Standifer, “Navy Reopens Negotiations For LCS While Pentagon Delays DAB,” 
Inside the Navy, August 30, 2010. 
10 Cid Standifer, “Navy Reopens Negotiations For LCS While Pentagon Delays DAB,” Inside the Navy, August 30, 
2010. 
Congressional Research Service 
6 
Navy Littoral Combat Ship (LCS) Program 
 
•  What risks would the Navy face if the shipyard that wins the competition to build 
the 10 LCSs in FY2010-FY2014 cannot build them within the contracted cost? 
•  How does the Navy plan to evolve the combat system on the winning LCS design 
to a configuration that has greater commonality with one or more existing Navy 
surface ship combat systems? 
•  What are the Navy’s longer-term plans regarding the two “orphan” LCSs that are 
built to the design that is not chosen in the down select? 
•  What potential alternatives are there to the Navy’s new acquisition strategy? 
Each of these questions is discussed briefly below. 
Enough Time for Adequate Congressional Review of Navy Proposal? 
One potential issue for Congress concerning the Navy’s proposed acquisition strategy is whether 
the timing of the Navy’s September 2009 announcement of the new LCS acquisition strategy—
very late in the congressional process for reviewing, marking up, and finalizing action on the 
FY2010 defense budget—provided Congress with sufficient time to adequately review the 
proposal prior to finalizing its action on the FY2010 defense budget. The announcement of the 
Navy’s proposed acquisition strategy on September 16, 2009, came 
•  after the defense committees of Congress had held their hearings to review the 
FY2010 budget submission; 
•  after the FY2010 defense authorization bill (H.R. 2647/S. 1390) and the 
Department of Defense (DOD) appropriations bill (H.R. 3326) had been reported 
in the House and Senate; 
•  after both the House and Senate had amended and passed their versions of the 
FY2010 defense authorization bill, setting the stage for the conference on that 
bill; and 
•  after the House had passed its version of the FY2010 DOD appropriations bill. 
The timing of the Navy’s announcement was a byproduct of the fact that the Navy was not able to 
see and evaluate the industry bids for the three LCSs that the navy had originally requested for 
FY2010 until August 2009. The September 16, 2009, announcement date may have been the 
earliest possible announcement date, given the time the Navy needed to consider the situation 
created by the bids, evaluate potential courses of action, and select the newly proposed 
acquisition strategy. 
Although the Navy might not have been able to present the proposed strategy to Congress any 
sooner than September 16, the timing of the Navy’s announcement nevertheless put Congress in 
the position of being asked to approve a major proposal for the LCS program—a proposal that 
would determine the basic shape of the acquisition strategy for the program for many years into 
the future—with little or no opportunity for formal congressional review and consideration 
through hearings and committee markup activities. 
A shortage of time for formal congressional review and consideration would be a potential 
oversight issue for Congress for any large weapon acquisition program, but this might be 
especially the case for the LCS program, because it would not be the first time that the Navy has 
Congressional Research Service 
7 
Navy Littoral Combat Ship (LCS) Program 
 
put Congress in the position of having to make a significant decision about the LCS program with 
little or no opportunity for formal congressional review and consideration. As discussed in 
previous CRS reporting on the LCS program, a roughly similar situation occurred in the summer 
of 2002, after Congress had completed its budget-review hearings on the proposed FY2003 
budget, when the Navy submitted a late request for the research and development funding that 
effectively started the LCS program.11 
                                                             
11 The issue of whether Congress was given sufficient time to review and consider the merits of the LCS program in its 
early stages was discussed through multiple editions of past CRS reports covering the LCS program. The discussion in 
those reports raised the question of whether “Navy officials adopted a rapid acquisition strategy for the LCS program in 
part to limit the amount of time available to Congress to assess the merits of the LCS program and thereby effectively 
rush Congress into approving the start of LCS procurement before Congress fully understands the details of the 
program.” The discussion continued: 
With regard to the possibility of rushing Congress into a quick decision on LCS procurement, it can 
be noted that announcing the LCS program in November 2001 and subsequently proposing to start 
procurement in FY2005 resulted in a situation of Congress having only three annual budget-review 
seasons to learn about the new LCS program, assess its merits against other competing DOD 
priorities, and make a decision on whether to approve the start of procurement. These three annual 
budget-review seasons would occur in 2002, 2003, and 2004, when Congress would review the 
Navy’s proposed FY2003, FY2004, and FY2005 budgets, respectively. Congress’ opportunity to 
conduct a thorough review of the LCS program in the first two of these three years, moreover, may 
have been hampered: 
•  2002 budget-review season (for FY2003 budget). The Navy’s original FY2003 budget 
request, submitted to Congress in February 2002, contained no apparent funding for 
development of the LCS. In addition, the Navy in early 2002 had not yet announced that it 
intended to employ a rapid acquisition strategy for the LCS program. As a result, in the early 
months of 2002, there may have been little reason within Congress to view the LCS program 
as a significant FY2003 budget-review issue. In the middle of 2002, the Navy submitted an 
amended request asking for $33 million in FY2003 development funding for the LCS 
program. Navy officials explained that they did not decide until the middle of 2002 that they 
wanted to pursue a rapid acquisition strategy for the LCS program, and consequently did not 
realize until then that there was a need to request $33 million in FY2003 funding for the 
program. By the middle of 2002, however, the House and Senate Armed Services committees 
had already held their spring FY2003 budget-review hearings and marked up their respective 
versions of the FY2003 defense authorization bill. These two committees thus did not have an 
opportunity to use the spring 2002 budget-review season to review in detail the Navy’s 
accelerated acquisition plan for the LCS program or the supporting request for $33 million in 
funding. 
•  2003 budget-review season (for FY2004 budget). To support a more informed review of the 
LCS program during the spring 2003 budget-review season, the conferees on the FY2003 
defense authorization bill included a provision (Section 218) requiring the Navy to submit a 
detailed report on several aspects of the LCS program, including its acquisition strategy. In 
response to this legislation, the Navy in February 2003 submitted a report of eight pages in 
length, including a title page and a first page devoted mostly to a restatement of Section 218’s 
requirement for the report. The House and Senate Armed Services committees, in their reports 
on the FY2004 defense authorization bill, have expressed dissatisfaction with the 
thoroughness of the report as a response to the requirements of Section 218. (For details, see 
the “Legislative Activity” section of this report.) It is thus not clear whether the defense 
authorization committees were able to conduct their spring 2003 budget-review hearings on 
the FY2004 budget with as much information about the LCS program as they might have 
preferred. 
(See, for example, CRS Report RL 32109, Navy DD(X), CG(X), and LCS Ship Acquisition Programs: Oversight Issues 
and Options for Congress, by Ronald O’Rourke, updated July 29, 2005, pp. CRS-59 to CRS-60. This discussion was 
carried through multiple updates of CRS reports covering the LCS program.) 
Congressional Research Service 
8 
Navy Littoral Combat Ship (LCS) Program 
 
Supporters of the idea of approving the Navy’s proposed acquisition strategy as part of 
Congress’s work to finalize action on the FY2010 defense budget could argue one or more of the 
following: 
•  The timing of the Navy’s proposal, though not convenient for Congress, 
nevertheless represented a good-faith effort by the Navy to present the proposal 
to Congress at the earliest possible date. The Navy conducted multiple briefings 
with congressional offices starting in September 2009 to explain the proposed 
strategy. 
•  The LCS program needed to be put on a more stable long-term path as soon as 
possible, and if Congress did not approve the proposal as part of its work in 
finalizing action on the FY2010 defense budget, another year would pass before 
the LCS program could be put on a stable path approved by Congress. 
•  Although cost growth and construction problems with the LCS program can be 
viewed as a consequence of past attempts to move ahead too quickly on the LCS 
program, the Navy’s new acquisition strategy does not risk repeating this 
experience, because it does not represent another attempt to move ahead on the 
program at an imprudent speed. To the contrary, the strategy seeks to reduce 
execution risks by limiting LCS procurement to a maximum of four ships per 
year and providing a stable planning environment for LCS shipyards and 
suppliers. 
•  If the proposed strategy were not approved by Congress as part of its action on 
the FY2010 budget, the LCSs procured in FY2010 would be more expensive to 
procure, since they would not benefit from economies of scale that would come 
from awarding the FY2010 ships as part of a contract that also includes LCSs to 
be procured in FY2011-FY2014. 
Supporters of the idea of deferring a decision on the Navy’s proposed acquisition strategy until 
the FY2011 budget cycle could argue one or more of the following: 
•  Navy briefings to Congress on the proposed strategy starting in September 2009, 
though helpful, were not sufficient for Congress to fully understand the features 
and potential implications of the Navy’s proposed acquisition strategy—much 
less the relative merits of potential alternatives to that strategy. 
•  The risks of making a quick decision on the Navy’s proposed acquisition 
strategy, with little time for formal congressional review and consideration, are 
underscored by the history of the LCS program, which includes substantial cost 
growth and construction problems that can be viewed as the consequence of past 
attempts to move ahead quickly on the program, without more-extensive 
congressional review and consideration. 
•  The desire to avoid a paying a relatively high cost for LCSs procured in FY2010, 
though real, should not have been a controlling factor in this situation (i.e., 
should not have been “the tail that wags the dog”). Paying a higher cost for LCSs 
procured in FY2010, though not optimal, would be an investment to buy time for 
Congress to more fully review and consider the merits of both the Navy’s 
proposal and potential alternatives to it. Problems avoided through a full 
congressional review and consideration of the Navy’s proposal and potential 
alternatives during the FY2011 budget cycle could eventually save the Navy a lot 
Congressional Research Service 
9 
Navy Littoral Combat Ship (LCS) Program 
 
more money than the Navy hopes to save on the LCSs procured in FY2010 by 
procuring them as part of a contract that also includes LCSs to be procured in 
FY2011-FY2014. 
•  Approving the Navy’s proposed acquisition strategy at a late juncture in the 
annual congressional process for reviewing and marking up the defense budget 
would set an undesirable precedent from Congress’s standpoint regarding late 
submissions to Congress of significant proposals for large defense acquisition 
programs, and encourage DOD to do the same with other large weapon 
acquisition programs in the future in the hopes of stampeding Congress into 
making quick decisions on major proposals for those programs. 
Enough Time to Evaluate the Two Designs’ Operational Characteristics? 
Another potential issue for Congress concerning the Navy’s proposed acquisition strategy is 
whether the strategy allows the Navy enough time to adequately evaluate the operational 
characteristics of the two LCS designs before selecting one of those designs for all future 
production. Potential oversight questions for Congress include the following: 
•  Since LCS-1 as of September 2009 had been in commissioned service for less 
than a year, and LCS-2 as of that date had not yet been delivered to the Navy, 
how firm was the basis for the Navy’s determination that both LCS designs meet 
the Navy’s operational requirements for LCS?  
•  By the summer of 2010—when the Navy plans to award a contract to the winner 
of the down select—the Navy will have had only a limited time to evaluate the 
operational characteristics of LCS-1 and LCS-2 through fleet exercises and use in 
actual Navy deployments. Will the Navy at that point have a sufficient 
understanding of the two designs’ operational characteristics to appropriately 
treat the operational characteristics of the two designs in the down select? 
The Navy and its supporters could argue that the Navy has chosen a preferred design for other 
new Navy ships (such as the DDG-1000 destroyer) on the basis of paper designs only, and 
consequently that the Navy would have a firmer basis for performing the LCS down select than it 
has had on other shipbuilding programs. They can argue that the Navy has a good understanding 
of the basic differences between the ships—that the Lockheed design, for example, may have 
better features for supporting small boat operations (which are used for certain LCS missions), 
while the General Dynamics design may have better features for supporting helicopter and 
unmanned aerial vehicle (UAV) operations (which are used for certain LCS missions). 
Skeptics could argue that the Navy in the past has talked about performing an extensive 
operational review of each design prior to settling on an acquisition strategy for follow-on ships 
in the program, and that the innovative nature of the LCS—a modular ship with plug-and-fight 
mission packages and a small crew—increases the risks associated with selecting a single LCS 
design before performing such an extensive operational review. Skeptics could argue that the 
Navy is depriving itself of the opportunity to better understand, through exercises and real-world 
deployments, the implications for overall fleet operations of building all LCSs to one design or 
the other before performing the down select. 
Congressional Research Service 
10 
Navy Littoral Combat Ship (LCS) Program 
 
Weight Given to Procurement Cost vs. Other Factors in Request for Proposals 
(RFP) 
Another potential issue for Congress concerning the Navy’s proposed acquisition strategy 
concerns the criteria that the Navy will use for selecting a winning design in the down select. 
Some observers, particularly supporters of the General Dynamics LCS design, argue that the 
Navy’s proposed method for evaluating the two LCS designs in the LCS down select—set forth 
in the Request for Proposals (RFP) for the down select—focuses too much on procurement cost 
and not enough on other factors, particularly life-cycle fuel cost, other components of life-cycle 
operating and support (O&S) cost, and ship capability. Other observers, particularly supporters of 
the Lockheed LCS design, argue (as does the Navy) that the Navy’s proposed method for 
conducting the LCS down select adequately takes into account factors other than procurement 
cost. The issue is viewed as having the potential for leading to a protest of the Navy’s down select 
decision by the firm that is not selected.12 
Regarding the role of life-cycle operation and support (O&S) cost in the Navy’s down select 
decision, a February 2010 GAO report stated: 
The Navy estimated operating and support costs for LCS seaframes and mission packages in 
2009, but the estimates do not fully reflect DOD and GAO best practices for cost estimating 
and may change due to program uncertainties. GAO’s analysis of the Navy’s 2009 estimates 
showed that the operating and support costs for seaframes and mission packages could total 
$84 billion (in constant fiscal year 2009 dollars) through about 2050. However, the Navy did 
not follow some best practices for developing an estimate such as (1) analyzing the 
likelihood that the costs could be greater than estimated, (2) fully assessing how the estimate 
may change as key assumptions change, and (3) requesting an independent estimate and 
comparing it with the program estimate. The estimates may also be affected by program 
uncertainties, such as potential changes to force structure that could alter the number of ships 
and mission packages required. The costs to operate and support a weapon system can total 
70 percent of a system’s costs, and the lack of an estimate that fully reflects best practices 
could limit decision makers’ ability to identify the resources that will be needed over the 
long term to support the planned investment in LCS force structure. With a decision pending 
in 2010 on which seaframe to buy for the remainder of the program, decision makers could 
lack critical information to assess the full costs of the alternatives.13 
A February 8, 2010, press report stated that “the Navy will draw up total life-cycle cost estimates 
for both the Lockheed Martin and General Dynamics versions of the Littoral Combat Ship before 
the program goes before the Defense Acquisition Board this year for its Milestone B. review. The 
                                                             
12 For examples of articles discussing this issue, see Sean Reilly, “Loser To Fight In LCS Deal?” Mobile (AL) Press-
Register, March 28, 2010: 1; Cid Standifer, “Austal USA, GD Officials Criticize Navy’s RFP Criteria For LCS 
Award,” Inside the Navy, March 29, 2010; Zachary M. Peterson, “Navy LCS Proposal Request Seeks ‘Qualitative’ 
Total Ownership Cost Figures,” Inside the Navy, March 22, 2010; Emelie Rutherford, “Navy Stands By LCS Due Date 
As Hill Backers Of Each Bidder Swap Barbs,” Defense Daily, March 18, 2010: 2-3; Geoff Fein, “General Dynamics’ 
LCS Burns Less Fuel At Higher Speeds, Navy Documents Show,” Defense Daily, March 2, 2010: 1-2; Geoff Fein, 
“Sessions Presses Navy Over Fairness of LCS RFP Evaluation,” Defense Daily, March 1, 2010: 6-7; Geoff Fein, “USS 
Independence [LCS-2] Is The More Fuel Efficient of Two LCS Variants, Austal Official Says,” Defense Daily, 
February 24, 2010: 2-3; Geoff Fein, “LCS RFP: Greater Emphasis Placed On Ship Price, Less On Life-Cycle Cost,” 
Defense Daily, January 29, 2010: 5-7; Christopher P. Cavas, “RFP for LCS: Cost Main Factor in Winning Bid,” 
NavyTimes.com, January 28, 2010. 
13 Government Accountability Office, Littoral Combat Ship[:] Actions Needed to Improve Operating Cost Estimates 
and Mitigate Risks in Implementing New Concepts, GAO-10-257, February 2010, summary page. 
Congressional Research Service 
11 
Navy Littoral Combat Ship (LCS) Program 
 
service included the announcement in a response to a Government Accountability Office report 
that criticized LCS life-cycle estimates.”14 
At the request of Senator Jeff Sessions, the Congressional Budget Office (CBO) analyzed the 
impact of O&S cost and other types of costs on the total life-cycle costs of the LCS and (for 
purposes of comparison) four other types of Navy ships. The results of CBO’s analysis were 
released in the form of an April 28, 2010, letter to Senator Sessions. The letter states: 
CBO projected the life-cycle cost of the LCS-1 under three different assumptions about the 
average annual amount of fuel the ship will use over its 25-year life: low, moderate, and 
high. In all three scenarios, procurement costs dominate the life-cycle cost of the LCS-1, 
ranging from 58 percent to 66 percent of the total.… Personnel costs make up 14 percent to 
16 percent of the LCS-1’s total life-cycle cost in the various scenarios, and fuel costs account 
for 8 percent to 18 percent. 
The low-fuel case assumes that the LCS-1 generally operates at relatively low speeds—10 
knots or less 90 percent of the time it is under way and 30 knots or more only about 3 percent 
of the time. That speed profile is based in part on how the Navy operated the LCS-1 between 
March 2009 and March 2010. In that scenario, operation and support costs total 33 percent of 
the ship’s life-cycle cost: 16 percent for personnel costs, 8 percent for fuel costs (assuming 
that the ship consumes 25,000 barrels of fuel per year), and 9 percent for other O&S costs…. 
The moderate-fuel case—which CBO considers the most likely of the three scenarios—
assumes that the LCS-1 operates at 30 or more knots for about 5 percent of the time, at 14 
knots to 16 knots 42 percent of the time (a range that might be typical when the ship was 
traveling from its home port to a deployment location), and at less than 12 knots for the rest 
of its time under way. In that scenario, O&S costs total 34 percent of the ship’s life-cycle 
cost: 15 percent for personnel, 11 percent for fuel, and 8 percent for other O&S costs. The 
moderate speed profile would result in fuel usage of about 35,000 barrels per year, slightly 
less than the 37,600 barrels that the Navy assumed in formulating its 2011 budget request. 
By comparison, the [Navy’s] FFG-7 class frigates consumed about 31,000 barrels of fuel per 
ship in 2009. 
The high-fuel case assumes that the LCS-1 operates at 30 or more knots for about 20 percent 
of its time under way, an assumption based partly on a speed profile developed by the Naval 
Sea Systems Command for the LCS program. In that scenario, O&S costs represent about 40 
percent of the ship’s life-cycle cost—more than in the other scenarios for the LCS-1 but less 
than for any of the other types of ships considered in this analysis. Personnel costs make up 
14 percent of the life-cycle total; fuel costs, 18 percent; and other O&S costs, 8 percent. 
Projected fuel usage in this scenario is about 67,000 barrels per year. That estimate is 
unlikely to be exceeded in actual practice: It is twice the historical average for frigates and 
about 80 percent of the amount used by the Navy’s destroyers (which do not have the 
capability to speed at 40 knots, as the littoral combat ship does, but are three times larger 
than the LCS-1).15 
At a May 6, 2010, hearing on Navy shipbuilding programs before the Seapower Subcommittee of 
the Senate Armed Services Committee, Senator Sessions questioned Sean Stackley, the Navy’s 
                                                             
14 Cid Standifer, “Navy Will Project Operation Costs Of Both LCS Models for DAB Review,” Inside the Navy, 
February 8, 2010. 
15 Letter dated April 28, 2010, from Douglas W. Elmendorf, Director, CBO, to the Honorable Jeff Sessions, pp. 3-5. 
The letter is available online at http://www.cbo.gov/ftpdocs/114xx/doc11431/04-28-SessionsLetter.pdf. 
Congressional Research Service 
12 
Navy Littoral Combat Ship (LCS) Program 
 
acquisition executive (i.e., the Assistant Secretary of the Navy [Research, Development and 
Acquisition]), regarding the role of fuel costs in the Navy’s evaluation of the two LCS designs. 
For the text of this exchange, see Appendix E. 
Potential Risks If First Shipyard Cannot Build Ships Within Cost 
Another potential issue for Congress concerning the Navy’s proposed acquisition strategy 
concerns the potential risks the Navy would face if the shipyard that wins the competition to build 
the 10 LCSs in FY2010-FY2014 cannot build them within the contracted cost. The competition 
between the two existing LCS industry teams to be the winner of the down select could be intense 
enough to encourage the teams to bid unrealistically low prices for the contract to build the 10 
ships. 
The Navy and its supporters could argue that the Navy’s plan to award a fixed-price contract to 
the winner of the down select would shift the cost risk on the 10 ships from the government to the 
shipyard. They could also argue that the Navy plans to carefully evaluate the bid prices submitted 
by the two industry teams for the down select to ensure that they are realistic, and that the 
existence of the second LCS shipyard would provide the Navy with an ability to continue 
building LCSs if production at the first yard were disrupted due to financial issues. 
Skeptics could argue that even with a fixed-price contract, the Navy’s proposed strategy poses 
cost risks for the government, because a shipyard could submit an unrealistically low bid so as to 
win the down select, and then recover its losses on those 10 ships by rolling the losses into prices 
for downstream ships in the program. Alternatively, the shipyard could present the Navy with the 
prospect of going out of business and disrupting the LCS production effort unless the Navy were 
to provide a financial bailout to cover the yard’s losses on the 10 ships. Skeptics could argue that 
Navy decisions dating back to the 1970s to award multi-ship construction contracts to shipyards 
that had not yet built many ships of the kind in question sometimes led to less-than-satisfactory 
program outcomes, including substantial financial bailouts. 
Increasing LCS Combat System Commonality with Other Combat Systems 
Another potential issue for Congress regarding the Navy’s proposed acquisition strategy concerns 
the Navy’s plan to evolve the combat system on the winning LCS design to a configuration that 
has greater commonality with one or more existing Navy surface ship combat systems. The Navy 
in its September 16, 2009, announcement did not provide many details on this part of its proposed 
acquisition strategy, making it difficult to evaluate the potential costs and risks of this part of the 
strategy against potential alternatives, including an alternative (which Navy officials have 
discussed in the past) of designing a new LCS combat system that would, from the outset, be 
highly common with one or more existing Navy surface ship combat systems. 
Navy’s Longer-Term Plans Regarding Two “Orphan” Ships 
Another potential issue for Congress concerning the Navy’s proposed acquisition strategy 
concerns the Navy’s longer-term plans regarding the two “orphan” LCSs built to the design that 
was not selected in the down select. The Navy states that it plans to keep these two ships in the 
fleet because they will be capable ships and the Navy has an urgent need for LCSs. These two 
LCSs, however, will have unique logistic support needs, potentially making them relatively 
expensive to operate and support. At some point, as larger numbers of LCSs enter service, the 
Congressional Research Service 
13 
Navy Littoral Combat Ship (LCS) Program 
 
costs of operating and supporting these two ships may begin to outweigh the increasingly 
marginal addition they make to total LCS fleet capabilities. Potential alternatives to keeping the 
ships in the active-duty fleet as deployable assets include selling them to foreign buyers, 
converting them into research and development platforms, shifting them to the Naval Reserve 
Force (where they would be operated by crews consisting partially of reservists), or 
decommissioning them and placing them into preservation (i.e., “mothball”) status as potential 
mobilization assets. Potential questions for Congress include the following: 
•  Does the Navy intend to keep the two orphan LCSs in the active-duty fleet as 
deployable assets for a full 25-year service life? 
•  If so, how would be the life-cycle operation and support (O&S) costs of these 
two ships compare to those of the other LCSs? In light of these O&S costs, 
would it be cost effective to keep these two ships in the active-duty fleet as 
deployable assets for a full 25-year service life, particularly as large numbers of 
LCSs enter service? 
•  If the Navy does not intend to keep the two orphan LCSs in the active-duty fleet 
as deployable assets for a full 25-year service life, when does the Navy anticipate 
removing them from such service, and what does the Navy anticipate doing with 
them afterward? 
Potential Alternatives to Navy’s New Strategy 
Another potential issue for Congress concerning the Navy’s proposed acquisition strategy 
concerns potential alternatives to the Navy’s new acquisition strategy for acquiring LCSs 
procured in FY2010 and subsequent years. A variety of alternatives can be generated by changing 
one or more elements of the Navy’s proposed strategy. One alternative would be a strategy that 
would keep both LCS designs in production, at least for the time being. Such a strategy might 
involve the following: 
•  the use of block-buy contracts with augmented EOQ authority, as under the 
Navy’s proposed acquisition strategy, to continue producing both LCS designs, 
so as to provide stability to shipyards and suppliers involved in producing both 
LCS designs; 
•  the use of Profit Related to Offer (PRO) bidding between the builders of the two 
LCS designs, so as to generate competitive pressure between them and thereby 
restrain LCS production costs;16 and 
•  designing a new LCS combat system that would have a high degree of 
commonality with one or more existing Navy surface ship combat systems and 
be provided as government-furnished equipment (GFE) for use on both LCS 
designs—an idea that was considered by the Navy at an earlier point in the 
program. 
                                                             
16 Under PRO bidding, the two shipyards would compete not for LCS quantities (because each shipyard would know 
that it was going to build a certain number of LCSs over the term of their block-buy contracts), but rather for profit, 
with the lowest bidder receiving the higher profit margin. PRO bidding has been used in other defense acquisition 
programs where bidders do not compete for quantity. The Navy, for example, began using PRO bidding in the DDG-51 
destroyer program it in the 1990s. 
Congressional Research Service 
14 
Navy Littoral Combat Ship (LCS) Program 
 
Supporters of an alternative like the one outlined above could argue that it would 
•  provide stability to LCS shipyards and suppliers; 
•  use competition to restrain LCS production costs; 
•  permit the Navy to receive a full return on the investment the Navy made in 
creating both LCS designs; 
•  reduce the life-cycle operation and support costs associated with building two 
LCS designs by equipping all LCSs with a common combat system; 
•  allow the Navy to design an LCS combat system that is, from the outset, highly 
common with one or more of the Navy’s existing surface ship combat systems; 
•  achieve a maximum LCS procurement rate of four ships per year starting in 
FY2011 (two years earlier than under the Navy’s proposal), thus permitting more 
LCSs to enter service with the Navy sooner; 
•  build both LCS designs in substantial numbers, thereby avoiding a situation of 
having a small number of orphan LCS ships that could have potentially high 
operation and support costs; 
•  preserve a potential to neck down to a single LCS design at some point in the 
future, while permitting the Navy in the meantime to more fully evaluate the 
operational characteristics of the two designs in real-world deployments; and 
•  increase the potential for achieving foreign sales of LCSs (which can reduce 
production costs for LCSs made for the U.S. Navy) by offering potential foreign 
buyers two LCS designs with active production lines. 
Supporters of the Navy’s proposed acquisition strategy could argue that an alternative like the one 
outlined above would, compared to the Navy’s proposed strategy 
•  achieve lower economies of scale in LCS production costs by splitting 
production of LCS components between two designs; 
•  achieve, at the outset of series production of LCSs, less bidding pressure on 
shipyards, and thus higher LCS production costs, than would be achieved under 
the Navy’s proposed strategy of using a price-based competition to select a single 
design for all future LCS production; 
•  miss out on the opportunity to restrain LCS costs by using the level of efficiency 
achieved in building an LCS design at one shipyard as a directly applicable 
benchmark for gauging the level of efficiency achieved by the other shipyard in 
building the same LCS design; 
•  increase Navy LCS program-management costs and the burden on Navy 
program-management capabilities by requiring the Navy to continue managing 
the construction of two very different LCS designs; 
•  achieve lower economies of scale in LCS operation and support costs because the 
two LCS designs would still differ in their basic hull, mechanical, and electrical 
(HM&E) systems, requiring the Navy to maintain two separate HM&E logistics 
support systems; 
Congressional Research Service 
15 
Navy Littoral Combat Ship (LCS) Program 
 
•  receive only a limited return on the investment the Navy made in developing the 
two current LCS combat systems (since LCSs in the long run would not use 
either one), and require the Navy to incur the costs and the technical risks 
associated with designing a completely new LCS combat system; 
•  require the Navy to build some number of LCSs with their current combat 
systems—which are different from one another and from other Navy surface ship 
combat systems—while awaiting the development of the new LCS combat 
system, and then incur the costs associated with backfitting these earlier LCSs 
with the new system when it becomes available; 
•  send to industry a signal that is undesirable from the government’s perspective 
that if the Navy or other parts or DOD begin producing two designs for a new 
kind of weapon system, the Navy or DOD would be reluctant to neck production 
down to a single design at some point, even if government believes that doing so 
would reduce program costs while still meeting operational objectives; and 
•  miss out on the opportunity that would be present under the Navy’s proposed 
acquisition strategy to increase the potential for achieving foreign sales of LCSs 
by offering potential foreign buyers an LCS design that, through U.S. production, 
enjoys significant economies of scale for both production and operation and 
support. 
Unit Procurement Cost Cap 
Another potential oversight matter for Congress for the LCS program is where the estimated 
procurement costs of LCSs stand in relation to the unit procurement cost cap for the LCS program 
as amended by Section 121(c) and (d) of the FY2010 defense authorization act (H.R. 2647/P.L. 
111-84 of October 28, 2009). As mentioned earlier, the Navy’s proposed FY2011 budget 
estimates the procurement costs of LCS sea frames to be procured in FY2011-FY2015 at roughly 
$600 million each in then-year dollars. At first glance, this appears to be well above the $480 
million unit procurement cost cap. As also mentioned earlier, however, the cost cap excludes 
certain costs from being counted against the $480 million cap, includes provisions for adjusting 
that figure over time to take inflation and other events into account, and permits the Secretary of 
the Navy to waive the cost cap under certain conditions. 
Cost Growth on LCS Sea Frames 
Another potential oversight issue for Congress for the LCS program concerns cost growth on 
LCS sea frames. Potential questions for Congress on this issue include the following: 
•  Has the Navy taken sufficient action to prevent further cost growth on LCS sea 
frames? 
•  Has the Navy financed cost growth on LCS sea frames by reducing funding for 
the procurement of LCS mission packages? For example, is cost growth on LCS 
sea frames linked in some way to the reduction in the planned number of LCS 
mission packages from an earlier figure of 90 to 110 to the current figure of 64? 
If the Navy has financed cost growth on LCS sea frames by reducing funding for 
the procurement of LCS mission packages, how might this have affected the 
capabilities of the planned 55-ship LCS fleet? 
Congressional Research Service 
16 
Navy Littoral Combat Ship (LCS) Program 
 
•  In light of the cost growth, is the LCS program still cost-effective? What is the 
LCS sea frame unit procurement cost above which the Navy would no longer 
consider the LCS program cost-effective? 
•  If Congress had known in 2004, when it was acting on the FY2005 budget that 
contained funding to procure LCS-1, that LCS sea frame unit procurement costs 
would increase to the degree that they have, how might that have affected 
Congress’s views on the question of approving the start of LCS procurement? 
An August 2010 GAO report stated: 
The Navy faces technical, design, and construction challenges to completing the first four 
[LCS] seaframes within current cost and schedule estimates. The Navy and its shipbuilders 
have learned lessons from construction of the first two seaframes that have positioned them 
to more effectively construct future vessels. However, technical issues with the first two 
seaframes have yet to be fully resolved. Addressing these technical issues has required the 
Navy to implement design changes at the same time LCS 3 and LCS 4 are being built. 
Incorporating changes during this phase will likely require additional labor hours beyond 
current forecasts. Together, these challenges may hinder the ability of shipbuilders to apply 
lessons learned to follow-on ships and could undermine anticipated benefits from recent 
capital investments in the LCS shipyards.17 
On September 3, 2010, the Navy provided the press with a point paper responding to certain 
points made in the August 2010 GAO report.18 The point paper stated in part: 
LCS 3 and LCS 4 are in production under fixed-priced contracts. Delaying production until 
testing is complete on LCS 1 and LCS 2 would result in a significant increase in the ships’ 
costs, as it would cause a lengthy disruption in the shipbuilding workforce and vendor base 
required for ship construction. Navy’s approach to building LCS 3 and 4 is not different from 
that used in other Navy shipbuilding programs.19 
Total Program Acquisition Cost 
Another potential oversight issue for Congress for the LCS program concerns the program’s 
potential total acquisition (i.e., research and development plus procurement) cost. DOD has not 
reported a total estimated acquisition cost for the entire LCS program, including both 55 LCS sea 
frames and 64 LCS mission packages. Supporters of the LCS program could argue that 
substantial data is available in the FY2011 budget submission on annual LCS research and 
development and procurement costs for the period FY2011-FY2015. Skeptics could argue that a 
major acquisition program like the LCS program should not proceed to higher annual rates of 
production until the program’s potential total acquisition costs is reported and assessed against 
other defense spending priorities. 
                                                             
17 Government Accountability Office, Defense Acquisitions[:] Navy’s Ability to Overcome Challenges Facing the 
Littoral Combat Ship Will Determine Eventual Capabilities, GAO-10-523, August 2010, summary page. 
18 See Cid Standifer, “Navy Pushes Back Against GAO Criticism Of Littoral Combat Ship,” Inside the Navy, 
September 6, 2010. 
19 Undated Navy point paper provided to CRS by Navy Office of Legislative Affairs on September 8, 2010. 
Congressional Research Service 
17 
Navy Littoral Combat Ship (LCS) Program 
 
Operation and Support (O&S) Cost 
Another potential oversight issue for Congress for the LCS program concerns the ship’s operation 
and support (O&S) cost. At the request of Senator Jeff Sessions, the Congressional Budget Office 
(CBO) analyzed the impact of O&S cost and other types of costs on the total life-cycle costs of 
the LCS and (for purposes of comparison) four other types of Navy ships. The results of CBO’s 
analysis were released in the form of an April 28, 2010, letter to Senator Sessions.20 CBO 
estimates in the letter that LCS-1 (the Lockheed Martin LCS design) would have an O&S cost, in 
constant FY2010 dollars, of $41 million to $47 million per year, depending on how often the ship 
travels at higher speeds and consequently how much fuel the ship uses each year.21 For an excerpt 
from CBO’s letter, see the earlier section entitled “Weight Given to Procurement Cost vs. Other 
Factors in Request for Proposals (RFP).” 
A February 2010 Government Accountability Office (GAO) report stated: 
The Navy estimated operating and support costs for LCS seaframes and mission packages in 
2009, but the estimates do not fully reflect DOD and GAO best practices for cost estimating 
and may change due to program uncertainties. GAO’s analysis of the Navy’s 2009 estimates 
showed that the operating and support costs for seaframes and mission packages could total 
$84 billion (in constant fiscal year 2009 dollars) through about 2050. However, the Navy did 
not follow some best practices for developing an estimate such as (1) analyzing the 
likelihood that the costs could be greater than estimated, (2) fully assessing how the estimate 
may change as key assumptions change, and (3) requesting an independent estimate and 
comparing it with the program estimate. The estimates may also be affected by program 
uncertainties, such as potential changes to force structure that could alter the number of ships 
and mission packages required. The costs to operate and support a weapon system can total 
70 percent of a system’s costs, and the lack of an estimate that fully reflects best practices 
could limit decision makers’ ability to identify the resources that will be needed over the 
long term to support the planned investment in LCS force structure. With a decision pending 
in 2010 on which seaframe to buy for the remainder of the program, decision makers could 
lack critical information to assess the full costs of the alternatives.22 
A February 8, 2010, press report stated: 
The Navy will draw up total life-cycle cost estimates for both the Lockheed Martin and 
General Dynamics versions of the Littoral Combat Ship before the program goes before the 
Defense Acquisition Board this year for its Milestone B. review. 
The service included the announcement in a response to a Government Accountability Office 
report that criticized LCS life-cycle estimates.23 
                                                             
20 Letter dated April 28, 2010, from Douglas W. Elmendorf, Director, CBO, to the Honorable Jeff Sessions, 8 pp. The 
full text of the letter is available online at http://www.cbo.gov/ftpdocs/114xx/doc11431/04-28-SessionsLetter.pdf. 
21 Letter dated April 28, 2010, from Douglas W. Elmendorf, Director, CBO, to the Honorable Jeff Sessions, Table 1 on 
page 7. 
22 Government Accountability Office, Littoral Combat Ship[:] Actions Needed to Improve Operating Cost Estimates 
and Mitigate Risks in Implementing New Concepts, GAO-10-257, February 2010, summary page. 
23 Cid Standifer, “Navy Will Project Operation Costs Of Both LCS Models for DAB Review,” Inside the Navy, 
February 8, 2010. 
Congressional Research Service 
18 
Navy Littoral Combat Ship (LCS) Program 
 
Operational Concepts 
Another potential oversight issue for Congress for the LCS program concerns operational 
concepts for using LCSs once they enter service. The February 2010 GAO report cited above also 
stated: 
The Navy has made progress in developing operational concepts for LCS, but faces risks in 
implementing its new concepts for personnel, training, and maintenance that are necessitated 
by the small crew size. Specifically, the Navy faces risks in its ability to identify and assign 
personnel given the time needed to achieve the extensive training required. GAO’s analysis 
of a sample of LCS positions showed an average of 484 days of training is required before 
reporting to a crew, significantly more than for comparable positions on other surface ships. 
Moreover, the Navy’s maintenance concept relies heavily on distance support, with little 
maintenance performed on ship. The Navy acknowledges that there are risks in 
implementing its new concepts and has established groups to address how to implement 
them. However, these groups have not performed a risk assessment as described in the 2008 
National Defense Strategy. The Strategy describes the need to assess and mitigate risks to 
executing future missions and managing personnel, training, and maintenance. If the Navy 
cannot implement its concepts as envisioned, it may face operational limitations, have to 
reengineer its operational concepts, or have to alter the ship design. Many of the concepts 
will remain unproven until 2013 or later, when the Navy will have committed to building 
almost half the class. Having a thorough risk assessment of the new operational concepts 
would provide decision makers with information to link the effectiveness of these new 
concepts with decisions on program investment, including the pace of procurement.24 
Combat Survivability 
Another potential oversight issue for Congress for the LCS program concerns the combat 
survivability of the LCS. A December 2009 report from DOD’s Director of Operational Test and 
Evaluation stated: 
LCS was designated by the Navy as a Level I survivability combatant ship, but neither 
design is expected to achieve the degree of shock hardening as required by the CDD 
[Capabilities Development Document]. Shock hardening (ability to sustain a level of 
operations following an underwater explosive attack) is required for all mission critical 
systems, as required by a Level 1 survivability requirement. Only a few selected subsystems 
will be shock hardened, supporting only mobility to evacuate a threat area following a 
design-level shock event. Accordingly, the full, traditional rigor of Navy-mandated ship 
shock trials is not achievable, due to the damage that would be sustained by the ship and its 
many non-shock-hardened subsystems. 
The LCS LFT&E [Live Fire Test and Evaluation] program has been hampered by the Navy’s 
lack of credible modeling and simulation tools for assessing the vulnerabilities of ships 
constructed to primarily commercial standards (American Bureau of Shipping Naval Vessel 
Rules and High Speed Naval Craft Code), particularly aluminum and non-traditional hull 
forms. Legacy LFT&E models were not developed for these non-traditional factors, nor have 
they been accredited for such use. These knowledge gaps undermine the credibility of the 
modeling and simulation, and increase the amount of surrogate testing required for an 
adequate LFT&E program. 
                                                             
24 Government Accountability Office, Littoral Combat Ship[:] Actions Needed to Improve Operating Cost Estimates 
and Mitigate Risks in Implementing New Concepts, GAO-10-257, February 2010, summary page. 
Congressional Research Service 
19 
Navy Littoral Combat Ship (LCS) Program 
 
The LCS is not expected to be survivable in a hostile combat environment as evidenced by 
the limited shock hardened design and results of full scale testing of representative hull 
structures completed in December 2006.25 
Technical Risk 
Another potential oversight issue for Congress for the LCS program concerns the amount of 
technical risk in the program. The discussion below addresses this issue first with respect to the 
LCS seaframe, and then with respect to LCS mission packages. 
Seaframe 
Regarding technical risk in developing the LCS seaframe, GAO reported the following in March 
2010: 
Technology Maturity 
Seventeen of 19 critical technologies for both LCS designs are mature. For LCS 2, the 
trimaran hull and aluminum structure are nearing maturity. The Navy identified watercraft 
launch and recovery—essential to complete the LCS antisubmarine warfare and mine 
countermeasures missions—as a major risk to both seaframe designs. Watercraft launch and 
recovery systems have not been fully demonstrated for either seaframe. On the LCS 1, the 
Navy is conducting dynamic load testing, but integration with the Remote Multi-Mission 
Vehicle—a physically stressing system to launch and recover—is not scheduled to occur 
until after the ship’s shakedown cruise. For LCS 2, factory testing of the twin boom 
extensible crane revealed performance and reliability concerns that were not fully addressed 
prior to installation. In addition, program officials report the LCS 2 main propulsion diesel 
engines have not completed a required endurance test, in part due to corrosion in each 
engine’s intake valves. As an interim solution, the Navy has installed new intake valves, 
which enabled the ship to complete acceptance trials. LCS 2 has also experienced pitting and 
corrosion in its waterjet tunnels. The Navy has temporarily fixed the issue and plans to make 
weld repairs to pitted areas during a future dry dock availability. 
Design and Production Maturity 
The Navy could not provide data on completion of basic and functional drawings—a metric 
of design stability—at the start of LCS 1 and LCS 2 construction. The Navy used a 
concurrent design-build strategy for the two seaframes, which proved unsuccessful. 
Implementation of new design guidelines, delays in major equipment deliveries, and strong 
focus on achieving schedule and performance goals resulted in increased construction costs. 
LCS 1 and LCS 2 still require design changes as a result of maturing key systems. At the 
same time, shipbuilders are constructing modules for the next two ships, LCS 3 and LCS 4. 
At fabrication start for each ship, approximately 69 percent (LCS 3) and 57 percent (LCS 4) 
of basic and functional drawings were complete. Starting construction before drawings are 
complete could result in costly out-of- sequence work and rework to incorporate new design 
attributes. Incomplete designs at construction also led to weight increases for LCS 1 and 
LCS 2. According to the Navy, this weight growth contributed to a higher than desired center 
of gravity on LCS 1 that degraded the stability of that seaframe. Acceptance trials showed 
LCS 1 may not meet Navy stability requirements in a damaged condition. In response, the 
                                                             
25 Department of Defense, Director, Operation Test and Evaluation, FY 2009 Annual Report, December 2009, p. 147. 
Congressional Research Service 
20 
Navy Littoral Combat Ship (LCS) Program 
 
Navy added internal and external buoyancy tanks. For LCS 3, the contractor has incorporated 
a design change to extend the transom by four meters to improve stability. 
Other Program Issues 
In an effort to improve affordability in the LCS program, the Navy modified its acquisition 
strategy for future seaframes. The new strategy calls for selecting one seaframe design and 
awarding one prime contractor and shipyard a fixed-price incentive contract for construction 
of up to 10 ships between fiscal year 2010 and fiscal year 2014. Navy officials report that the 
earned value management systems (EVMS) in each of the LCS shipyards do not yet meet 
Defense Contract Management Agency requirements. Under the terms of the LCS 3 and LCS 
4 contracts, the shipyards must achieve EVMS certification within 28 months from the date 
of the award. Until those requirements are met, cost and schedule data reported by the prime 
contractors cannot be considered fully reliable. 
Program Office Comments 
According to the Navy, the LCS program continues to deliver vital capability with the recent 
commissioning of LCS 2. The Navy stated that LCS 1 now meets the damage stability 
requirement with the addition of external tanks on the rear of the ship. The shipbuilder 
incorporated additional stability improvements to the design for LCS 3. In the continuing 
effort to ensure the delivery of affordable LCS capability, the Navy said it revised the 
acquisition strategy in 2009 to down select to a single design in fiscal year 2010 and procure 
up to 10 ships in a block buy. The winner of this competition will also be responsible for 
developing a technical data package to support competition for a second shipbuilder to build 
up to 5 ships in fiscal year 2012-2014. Construction continues on LCS 3 and LCS 4. To 
address corrosion of the waterjet tunnels, the Navy tated that electrical isolation of 
propulsion shafts from the waterjets is being incorporated and a plan is in place to renew the 
corroded metal in the waterjet intake tunnels.26 
Mission Packages 
Regarding technical risk in developing the modular mission packages for the LCS, an April 26, 
2010, news report stated: 
The Littoral Combat Ship program lacks a ‘timely’ test program plan for the mission 
packages slated to deploy aboard the vessels, putting the effort at a ‘medium’ risk for cost 
increases … according to a new study by the Pentagon’s acquisition directorate.... 
‘The program has major integration challenges between seaframes and MPs’ [mission 
packages], the study states. ‘To address this issue, the program established an Integrated 
Product Team … the team has identified numerous deficiencies and verified corrections 
within each seaframe.’27 
An August 2010 GAO report stated: 
                                                             
26 Government Accountability Office, Defense Acquisitions[:] Assessments of Selected Weapon Programs, GAO-10-
388SP, March 2010, p. 96. 
27 Zachary M. Peterson, “DOD Report: LCS Program Faces ‘Medium Risk,’ Integration Challenges, Inside the Navy, 
April 26, 2010. Material in brackets as in original. 
Congressional Research Service 
21 
Navy Littoral Combat Ship (LCS) Program 
 
Challenges developing mission packages have delayed the timely fielding of promised 
capabilities, limiting the ships’ utility to the fleet during initial deployments. Until these 
challenges are resolved, it will be difficult for the Navy to align seaframe purchases with 
mission package procurements and execute planned tests. Key mine countermeasures and 
surface warfare systems encountered problems in operational and other testing that delayed 
their fielding. For example, four of six Non-Line-of-Sight Launch System missiles did not 
hit their intended targets in recent testing, and the Department of Defense has since canceled 
the program. Further, Navy analysis of anti-submarine warfare systems has shown the 
planned systems do not contribute significantly to the anti-submarine warfare mission. These 
combined challenges have led to procurement delays for all three mission packages. Mission 
package delays have also disrupted program test schedules—a situation exacerbated by early 
deployments of initial ships—limiting their availability for operational testing. In addition, 
these delays could disrupt program plans for simultaneously acquiring seaframes and 
mission packages. Until mission packages are proven, the Navy risks investing in a fleet of 
ships that does not deliver promised capability.28 
On September 3, 2010, the Navy provided the press with a point paper responding to certain 
points made in the August 2010 GAO report.29 The point paper stated in part: 
The original LCS Anti-Submarine Warfare (ASW) mission package was cancelled by Navy 
two years ago (POM-10)30 when analysis indicated that it did not provide a significant 
contribution to counter the ASW threat. [The] Navy immediately began exploring a new 
ASW approach for LCS. The next generation LCS ASW mission package is currently under 
development. 
Central to the next ASW mission package will be a ship-deployed variable depth sonar 
(VDS) to complement the VDS carried by the [Navy’s ship-based] MH-60R helicopter. 
[The] Navy is purchasing an advanced design model of a variable depth sonar system for 
testing and evaluation in 2012, to develop this future ASW package.31 
                                                             
28 Government Accountability Office, Defense Acquisitions[:] Navy’s Ability to Overcome Challenges Facing the 
Littoral Combat Ship Will Determine Eventual Capabilities, GAO-10-523, August 2010, summary page. 
29 See Cid Standifer, “Navy Pushes Back Against GAO Criticism Of Littoral Combat Ship,” Inside the Navy, 
September 6, 2010. 
30 This is a reference to the Program Objective Memorandum (POM) for the FY2010 budget submission. The POM is 
an internal DOD planning document that guides the preparation of a DOD budget submission. POM-10 was developed 
during 2008, to support the submission to Congress in May 2009 of the proposed FY2010 defense budget. 
31 Undated Navy point paper provided to CRS by Navy Office of Legislative Affairs on September 8, 2010. In response 
to a part of the GAO report that discussed the initial deployment of LCS-1, the point paper stated: 
Following the successful completion of Acceptance Trials, the Chief of Naval Operations directed 
the OPNAV staff, United States Fleet Forces Command, and Naval Sea Systems Command to 
evaluate the feasibility of deploying USS Freedom (LCS 1) earlier than originally scheduled. The 
intent was to employ the unique capabilities of this new class of warship as soon as practical in the 
Fleet, to gain real operational experience and to assess LCS’ minimal manning strategy. Early 
deployment retained but modified LCS 1’s testing plan. 
During her maiden deployment, two years earlier than originally planned, USS Freedom was 
outfitted with a tailored Surface Warfare Mission Package. She deployed with a Helicopter Sea 
Combat Squadron 22 detachment and a U.S. Coast Guard Law Enforcement Detachment. Freedom 
successfully conducted four drug seizures, netting more than five tons of cocaine, detained nine 
suspected drug smugglers, and disabled two “go-fast” drug vessels.  
During deployment, USS Freedom also performed integrated at-sea operations with the USS Carl 
Vinson (CVN 70) Carrier Strike Group, performed at-sea maneuvers with the former-USS 
McInerney (FFG 7), and conducted several theater security cooperation port visits in Latin 
America.  
(continued...) 
Congressional Research Service 
22 
Navy Littoral Combat Ship (LCS) Program 
 
A March 2010 GAO report stated: 
Technology Maturity 
Operation of the MCM, SUW, and ASW packages on the LCS requires a total of 22 critical 
technologies, including 11 sensors, 6 vehicles, and 5 weapons. Of these technologies, 16 are 
mature and have been demonstrated in a realistic environment. In the past year, the Navy 
removed three critical technologies from LCS mission modules due to changes in future 
ASW packages. 
The Navy has accepted delivery of two partially capable MCM mission packages; however, 
the program has delayed the procurement of the fiscal year 2009-funded package due to 
technical issues and the resulting operational test delays. Four MCM systems—the 
Unmanned Surface Vehicle (USV), Unmanned Sweep System (USS), Organic Airborne and 
Surface Influence Sweep (OASIS), and Rapid Airborne Mine Clearance System 
(RAMICS)—have not yet been demonstrated in a realistic environment, and two others—the 
Airborne Laser Mine Detection System (ALMDS) and Remote Minehunting System 
(RMS)—cannot meet system requirements. ALMDS has been unable to meet its mine 
detection requirements at its maximum depth or its mine detection and classification 
requirements at surface depths. RMS demonstrated poor system reliability, availability, and 
maintainability in a September 2008 operational assessment, and program officials report the 
system is currently undergoing a series of tests to try to improve its reliability. Program 
officials also reported that the cable used to tow certain airborne MCM systems had to be 
redesigned following test failures with two systems. 
The Navy accepted delivery of one partially capable SUW mission package in July 2008. 
This package included two engineering development models for the 30 mm gun, but did not 
                                                             
(...continued) 
Operations continued over the summer, when USS Freedom participated in the Rim of the Pacific 
exercise, returning to homeport on Aug. 10, 2010.  
Impact on Testing: 
There are no changes to the overall scope of LCS 1 testing as a result of early deployment. Given 
the deployment lasted six months, completion of the LCS 1 test program was extended by 
approximately six months. Any delays to the overall post delivery testing plan were offset by the 
extensive depth and breadth of knowledge gained during deployment. To accommodate early 
deployment, LCS developmental testing was re-sequenced. Some testing was accelerated to before 
deployment, some testing was accomplished on deployment, and some testing was deferred until 
after deployment.  
In evaluating options for deploying Freedom earlier than originally scheduled, the Navy looked at 
several key factors: ship materiel condition, test plan acceleration, ship sustainment, integrated 
support plan, and crew training and certification.  
The decision to deploy Freedom early was based on a thorough review of the required changes to 
the test plan, overseas sustainment plan, and crew certification requirements.  
Early deployment brought LCS operational issues to the forefront much sooner than under the 
original schedule, some of which would not have been learned until two years on.  
Through this process, Navy “learned by doing.” Every aspect of this ship and program is new, from 
the operational concepts, through crew training and certification processes, to the support and 
sustainment strategies. Early deployment provided a vital opportunity to collect data in real-world 
operational scenarios. This data will be invaluable in the ongoing effort to accomplish the larger 
LCS fleet integration strategy…. 
LCS is a key component of the 21st century Navy. Early deployment of LCS 1 was a tremendous 
opportunity to test the ship in a real-world environment and begin integrating this essential ship 
into our fleet. 
Congressional Research Service 
23 
Navy Littoral Combat Ship (LCS) Program 
 
include the Non-Line-of-Sight Launch System (NLOS-LS) launcher or missiles. Integration 
of the gun with LCS 1 was completed in January 2009. The gun module design appears 
stable with 100 percent of its drawings released to manufacturing. According to program 
officials, NLOS-LS was tested in August 2009, but was unable to fire due to a 
malfunctioning sensor and battery connector. The program expects delivery of the second 
SUW mission package in March 2010. It will include the 30 mm gun module and the NLOS-
LS launcher, but no missiles. 
The Navy accepted delivery of one partially capable ASW mission package in September 
2008, but plans to reconfigure the content of future packages before procuring additional 
quantities. According to Navy officials, recent warfighting analyses showed that the baseline 
ASW package did not provide sufficient capability to meet the range of threats. The current 
package will undergo developmental testing and the results will inform future configuration 
decisions. The first package underwent end-to-end testing in April 2009 and will undergo 
developmental testing in fiscal year 2010. During the 2009 end-to-end test, the Navy found 
that the USV and its associated sensors will require reliability and interface improvements to 
support sustained undersea warfare. 
Other Program Issues 
Recent changes to the LCS seaframe acquisition strategy may necessitate changes to the LCS 
mission module acquisition strategy and testing plans. For example, the new seaframe 
strategy calls for the program to select a single design in fiscal year 2010. According to 
program officials, the first mission modules will still be tested on both seaframe designs, but 
future mission modules could be tested on one or both seaframe designs. 
Program Office Comments 
The Navy stated that early packages will be delivered with partial capability, with systems 
added to the packages as they reach the level of maturity necessary for fielding. According to 
the Navy, the USV, USS, OASIS, and RAMICS have not entered production or been 
demonstrated in an operational environment. However, ALMDS and RMS have to date 
achieved a majority of their key performance requirements. The Navy stated these systems 
will be available in time to support planned retirement of legacy MCM forces. According to 
the Navy, it has initiated a program to address RMS reliability. The Navy noted that the 
program recently declared a critical Nunn-McCurdy cost breach and is under review by the 
Under Secretary of Defense (Acquisition, Technology & Logistics). Further, the Navy stated 
it has resolved technical issues related to the helicopter tow cable and the associated systems 
are ready to resume testing, while mission package acquisition and testing strategies have 
been updated to reflect seaframe acquisition strategy changes.32 
Impact of Cancellation of NLOS-LS Missile System 
Another potential oversight issue for Congress for the LCS program concerns the impact on LCS 
capabilities of the cancellation of an Army missile program known as the Non-Line of Sight 
Launch System (NLOS-LS), which the Navy had planned to use as part of the LCS surface 
warfare (SUW) mission package. In May 2010, DOD approved an Army recommendation to 
cancel NLOS-LS.33 Prior to the cancellation of NLOS-LS, the Navy planned for LCSs equipped 
                                                             
32 Government Accountability Office, Defense Acquisitions[:] Assessments of Selected Weapon Programs, GAO-10-
388SP, March 2010, p. 98. 
33 “Out of Sight,” Defense Daily, May 17, 2010: 3. See also Kate Brannen, “U.S. Army Asks to Cancel NLOS-LS,” 
(continued...) 
Congressional Research Service 
24 
Navy Littoral Combat Ship (LCS) Program 
 
with SUW mission packages to be nominally armed with three NLOS missile launchers, each 
with 15 missiles, for a total of 45 missiles per ship. The missiles could be used to counter swarm 
boats or other surface threats. 
At a May 6, 2010, hearing on Navy shipbuilding programs before the Seapower Subcommittee of 
the Senate Armed Services Committee, Senator Jack Reed questioned Sean Stackley, the Navy’s 
acquisition executive (i.e., the Assistant Secretary of the Navy [Research, Development and 
Acquisition]), and Lieutenant General George Flynn, Deputy Commandant, Combat 
Development and Integration, and Commanding General, Marine Corps Combat Development 
Command, regarding the impact the cancellation of the NLOS-LS program. For the text of this 
exchange, see Appendix F. The Navy reportedly is assessing potential alternative systems for 
fulfilling the NLOS role in the SUW mission package.34 
Legislative Activity for FY2011 
Summary of Congressional Action on FY2011 Funding Request 
Table 1 summarizes congressional action on the Navy’s FY2011 funding request for the LCS 
program. 
Table 1. Congressional Action on FY2011 LCS Funding Request 
Millions of dollars, rounded to nearest tenth; figures may not add due to rounding 
Authorization Appropriation 
 Request 
HASC SASC Conf. HAC  SAC  Conf. 
    Shipbuilding and Conversion, Navy (SCN) account, lines 12 and 13 
LCS sea frames 
1,231.0 
1,231.0 
1,231.0 
 
 
615.5 
 
    (quantity) 
(2) 
(2) 
(2) 
 
 
(1) 
 
LCS sea frames (AP) 
278.4 
278.4 
278.4 
 
 
278.4 
 
    Weapon Procurement, Navy (WPN account), line 30 
LCS module weapons 
9.8 
0.9 
9.8 
 
 
0 
 
    Other Procurement, Navy (OPN) account, line 29 
LCS modules 
83.0 
83.0 
83.0 
 
 
50.0 
 
    Research, Development, Test & Evaluation, Navy (RDT&EN) account, line 48 
LCS 226.3 
305.5 
226.3 
 
 
199.4 
 
                                                             
(...continued) 
DefenseNews.com, April 23, 2010; Jason Sherman, “Army Cancels NLOS-NS, Frees Up Billions For Other 
Procurement Needs,” Inside the Navy, April 26, 2010; Sebastian Sprenger, “NLOS-LS Seen As Effective—But To 
Pricey—In Key Army Analysis,” Inside the Navy, May 3, 2010. 
34 Zachary M. Peterson, “Navy ‘Assessing Options’ In Lieu Of Army’s Cancellation Of NLOS Missile,” Inside the 
Navy, May 3, 2010; Cid Standifer, “Industry Team Leveraging Canceled Programs To Work On Five-Inch Round,” 
Inside the Navy, May 31, 2010; Cid Standifer, “Navy Looks To Replace NLOS In LCS Surface Warfare Mission 
Module,” Inside the Navy, June 21, 2010. 
Congressional Research Service 
25 
Navy Littoral Combat Ship (LCS) Program 
 
Sources: Navy’s FY2011 budget submission, committee and conference reports, and the text of S. 3454, the 
FY2011 defense authorization bill, as reported in the Senate. 
Notes: HASC is House Armed Services Committee; SASC is Senate Armed Services Committee; HAC is 
House Appropriations Committee; SAC is Senate Appropriations Committee; Conf. is conference report; AP 
is advance procurement for ships to be procured in future years. 
FY2011 Defense Authorization Bill (H.R. 5136/S. 3454) 
House 
The House Armed Services Committee, in its report (H.Rept. 111-491 of May 21, 2010) on the 
FY2011 defense authorization bill (H.R. 5136), recommends approval of the Navy’s FY2011 
procurement and advance procurement funding requests for LCS sea frames (page 73) and LCS 
modules (page 81, line 029). The report recommends reducing by $8.9 million the Navy’s 
FY2011 procurement funding request for LCS module weapons due to termination of the NLOS-
LS program (page 68, line 030). The report recommends increasing the Navy’s FY2011 request 
for LCS research and development funding by $75.0 million for Navy NLOS-NS development, 
and by $4.25 million for axial-flow high-power-density waterjets (page 148). 
The report states: 
Littoral Combat Ship 
The Littoral Combat Ship program has failed its initial intent to build inexpensive ships with 
modular capability and field them to the fleet at a high rate. None of those goals have been 
met. The ships are expensive; the modular capability has not been tested or verified; and in 
some cases is still undergoing development; and only two of the ships have been delivered to 
the Navy. 
Last year, the committee supported the request of the Secretary of the Navy and the Chief of 
Naval Operations to revamp the acquisition strategy for these vessels and to down-select to 
one variant of the ship with the award of the fiscal year 2010 two-ship authorization. The 
new acquisition strategy is aimed at reducing overall costs by procuring 10 ships in the 
Future Years Defense Plan using a fixed price incentive contract in fiscal year 2010 with 
priced options for 8 additional ships, 2 per year, in fiscal years 2011–15. In addition, the 
government would gain all rights to the technical data package required to compete the 
winning design to a second source shipyard which would build 5 additional ships, for a total 
of 15 ships, between fiscal years 2012 and 2015. The committee supported this plan as the 
best alternative to provide needed capability to the fleet in the shortest time possible, at the 
least cost. The plan was also proposed to the committee as the best way to divorce the prime 
contractors from the program and to transition the ship’s installed combat systems to 
government furnished equipment that complimented equipment currently in use in the fleet. 
As of this report, the Navy has received the proposals from the two authorized competitors 
and is in the process of source selection leading to contract award. The committee is 
cautiously optimistic that, with a down-select to one variant and stability in the construction 
schedule, this troubled program can begin to fulfill its original purpose of providing capable 
ships, in quantity, at an affordable cost. (Pages 76-77) 
The report also states: 
Littoral Combat Ship Module weapons 
Congressional Research Service 
26 
Navy Littoral Combat Ship (LCS) Program 
 
The budget request contained $9.8 million for Littoral Combat Ship (LCS) Module 
Weapons, of which $8.9 million was requested for procurement of 45 non-line-of-sight 
launch system (NLOS–LS) missiles. 
The committee notes that the Army has terminated the NLOS-LS program, and even if it is 
continued by the Navy, an additional year of development work will be required. As a result, 
the committee does not agree with Navy procurement funding for NLOS–LS in fiscal year 
2011. In title II of this report, the committee recommends an increase in Navy research and 
development funding to support continued development work for the NLOS–LS program if 
the Navy determines that is in the best interest of the LCS program. 
The committee recommends $0.9 million, a decrease of $8.9 million, for LCS Module 
weapons. (Page 69) 
The report also states: 
Navy non-line-of-sight launch system development 
The budget request contained $226.3 million in PE 63581N35 for Littoral Combat Ship 
mission module research and development but contained no funds for the non-line-of-sight 
launch system (NLOS–LS). 
The committee notes that the Army’s termination of the NLOS–LS could leave the Navy’s 
Littoral Combat Ship (LCS) without sufficient capability to defeat small boat threats and 
unable to provide precision fire support to Marine Corps forces. The committee is informed 
that the NLOS–LS will likely require only one more year of research and development work 
to achieve threshold requirements. Therefore, in order to take advantage of the $1.5 billion in 
development funds spent to date, the committee encourages the Navy to complete 
development of the NLOS–LS system for use on the LCS. The committee also directs the 
Assistant Secretary of the Navy for Research, Development, and Acquisition to provide a 
report to the congressional defense committees by December 15, 2010, on the feasibility and 
utility of the Navy completing development of the NLOS–LS. The report should include an 
analysis of possible unit cost reduction options. 
The committee recommends $301.3 million, an increase of $75.0 million, in PE 63581N for 
research and development of the NLOS–LS for use on the LCS. (Pages 159-160) 
Senate 
The FY2011 defense authorization bill (S. 3454), as reported by the Senate Armed Services 
Committee (S.Rept. 111-201 of June 4, 2010), recommends approval of the Navy’s requests for 
FY2011 procurement and advance procurement funding for LCS sea frames (see page 677, lines 
12 and 13, of the printed bill), LCS module weapons (page 675, line 30), LCS modules (page 
680, line 29), and LCS research and development (page 732, line 48). The committee’s report 
states: 
The Littoral Combat Ship (LCS) program has made progress during the past year and the 
recent decision to move to a single design should improve affordability. The LCS fleet is 
expected to comprise 55 vessels of the Navy’s 313–ship fleet force structure. Even modest 
cost growth in this large component of the fleet magnifies the problem of achieving that 
                                                             
35 Line items in DOD research and development accounts are called program elements (PEs). 
Congressional Research Service 
27 
Navy Littoral Combat Ship (LCS) Program 
 
objective. The committee notes that the Navy’s acquisition strategy for the LCS program 
introduces competition for this class of ships and is therefore cautiously optimistic that this 
program is making progress. (Page 41) 
The committee’s report also states: 
Littoral combat ship report 
The committee has concluded that the projected ship decommissioning and construction 
schedule presented in the Navy’s program described in its “Report to Congress on Annual 
Long-Range Plan for Construction of Naval Vessels for FY 2011” could have a negative 
effect on some of the Nation’s Navy bases. This would arise because of a gap that will occur 
as a result of small surface combatants being retired years before Littoral Combat Ship 
replacements will arrive. 
The Navy’s 2010 document ‘‘Report on Strategic Plan for Homeporting the Littoral Combat 
Ship’’ provided the committee with the Navy’s notional strategic plan for stationing the 
Littoral Combat Ship through fiscal year 2020. In order to fully understand the effects of the 
Navy’s current decommissioning and shipbuilding timeline, the committee directs the 
Secretary of the Navy to submit a report to the congressional defense committees that would 
provide the timeline and detailed homeport locations for the Littoral Combat Ships that will 
be delivered through 2020. The committee directs the Secretary of the Navy to submit the 
reports at the time the President submits his fiscal year 2012 budget proposal to Congress. 
As the Navy finalizes its plans, the committee encourages the Navy to expedite delivery of 
the Littoral Combat Ship to those Navy bases that need replacement ships to mitigate 
capability gaps that will result from the retirement of smaller surface combatants. (Page 116) 
FY2011 DOD Appropriations Bill (S. 3800) 
Senate 
The Senate Appropriations Committee, in its report (S.Rept. 111-295 of September 16, 2010) on 
S. 3800, recommends $615.5 million in procurement funding for the procurement in FY2011 of 
one LCS sea frame—a reduction of $615.5 million and one LCS sea frame from the Navy’s 
request (page 86, line 12). The committee’s report states: 
Littoral Combat Ship [LCS].—The fiscal year 2011 budget request included $1,230,984,000 
for the construction of two LCS ships and $278,351,000 in advance procurement funding for 
future ships. The Committee supports the revised acquisition strategy for the LCS program 
and the decision to down-select to one variant in fiscal year 2010. The Committee, however, 
is concerned with the very aggressive construction schedule proposed in the budget request. 
Based on the historical poor cost and schedule performance of the program, including the 
current delay in the down-select decision, the Committee is concerned that the proposed 
ramp up to construct four ships in fiscal year 2011 is too aggressive and may be 
unexecutable. Therefore, the Committee recommends re-phasing the LCS construction 
schedule by reducing the budget request by $615,492,000 and one ship in fiscal year 2011. 
The Committee directs the Navy to add one LCS back into the program during the Future 
Years Defense Plan. (Page 87) 
The committee’s report also states: 
Congressional Research Service 
28 
Navy Littoral Combat Ship (LCS) Program 
 
The Secretary of Defense should be applauded for trying to gain greater control over 
runaway costs, schedule delays, and requirements creep. However, the Committee remains 
frustrated by the lack of proper control in the Defense budget process as exemplified by the 
examples listed below. The Navy should be commended for reshaping its Littoral Combat 
Ship program to down select to one contractor with the goal of reducing costs. However, the 
ensuing delay in this program has led to a schedule in which the winning contractor will not 
be able to begin constructing the second of two LCS ships requested in fiscal year 2011. 
Nonetheless, neither the Navy nor the Defense Department has suggested reducing the 
budget request even though more than $600,000,000 will not be required this fiscal year. 
(Page 7) 
The committee’s report recommends approving the Navy’s request for $278.4 million in advance 
procurement funding for LCSs to be procured in future years (page 86, line 13). 
The committee’s report recommends denying the Navy’s request for $9.8 million in procurement 
funding for the procurement of LCS weapon modules due to the termination of the NLOS-LS 
program (page 82, line 30). 
The committee’s report recommends reducing by $32.9 million the Navy’s request for 
procurement funding for the procurement of LCS modules due to unjustified growth in 
production engineering ($6 million reduction), mission package computer environment units 
requested ahead of need ($2.3 million reduction), unjustified growth in consulting services ($2 
million reduction), and AN/AQS-20A minehunting sonar equipment requested ahead of need 
($22.7 million reduction) (page 95, line 29). 
The committee’s report recommends reducing the Navy’s request for research and development 
funding for the LCS program by a net total of $26.9 million, including a reduction of $15.4 
million due to the termination of the NLOS-LS program, a reduction of $15.0 million due to 
savings from “accelerated DT” (which might be a reference to accelerated developmental 
testing), and an increase of $3.5 million for LCS axial flow high power density waterjets (page 
150, line 48). 
Congressional Research Service 
29 
Navy Littoral Combat Ship (LCS) Program 
 
Appendix A. Summary of Congressional Action in 
FY2005-FY2010 
This appendix presents a summary of congressional action on the LCS program in FY2005-
FY2010. 
FY2005 
In FY2005, Congress approved the Navy’s plan to fund the construction of the first two LCS sea 
frames using research and development funds rather than shipbuilding funds, funded the first 
construction cost of the first LCS (LCS-1), required the second LCS (LCS-2) to be built (when 
funded in FY2006) to a different design from the first, prohibited the Navy from requesting funds 
in FY2006 to build a third LCS, and required all LCSs built after the lead ships of each design to 
be funded in the SCN account rather than the Navy’s research and development account. 
FY2006 
In FY2006, Congress funded the procurement of LCSs 2, 3, and 4. (The Navy requested one LCS 
for FY2006, consistent with Congress’s FY2005 action. Congress funded that ship and provided 
funding for two additional ships.) Congress in FY2006 also established a unit procurement cost 
limit on the fifth and sixth LCS sea frames of $220 million per ship, plus adjustments for inflation 
and other factors (Section 124 of the FY2006 defense authorization bill [H.R. 1815/P.L. 109-163] 
of January 6, 2006), required an annual report on LCS mission packages and made procurement 
of more than four LCSs contingent on the Navy certifying that there exists a stable design for the 
LCS. 
FY2007 
In FY2007, Congress funded the procurement of LCSs 5 and 6. (The Navy canceled these two 
ships in 2007 before they were placed under contract for construction.) 
FY2008 
In FY2008, Congress accepted the Navy’s cancellation of LCSs 3 through 6; funded the 
procurement one additional LCS in FY2008 (which the Navy called LCS-5);36 significantly 
reduced the Navy’s FY2008 funding request for the LCS program; amended the LCS sea frame 
unit procurement cost cap to $460 million per ship for LCSs procured in FY2008 and subsequent 
years (Section 125 of the conference report [H.Rept. 110-477 of December 6, 2007] on H.R. 
1585, the FY2008 defense authorization bill, which was enacted as H.R. 4986/P.L. 110-181 of 
                                                             
36 The Navy apparently called this ship LCS-5 because the original LCS-5 and LCS-6 were canceled by the Navy 
before they were replaced under contract, leaving LCS-4 as last LCS under contract to have been canceled. In spite of 
its designation, LCS-5 would have been the third LCS in the restructured LCS program, and was the seventh to have 
been funded by Congress. 
Congressional Research Service 
30 
Navy Littoral Combat Ship (LCS) Program 
 
January 28, 2008); and required the Navy to use fixed-price-type contracts for the construction of 
LCSs procured in FY2008 and subsequent years. 
The Navy in 2007 requested that Congress amend the existing unit procurement cost cap for the 
fifth and sixth ships to $460 million, plus adjustments for inflation and other factors. Congress 
amended the cost cap to $460 million, but applied it not only to the fifth and sixth LCSs, but to all 
LCSs procured in FY2008 and subsequent years. The use of fixed-price contracts for future LCSs 
was something that the Navy had stated an intention to do as part of its plan for restructuring the 
LCS program. 
FY2009 
In FY2009, Congress delayed the implementation of the LCS sea frame unit procurement cost 
cap by two years, to ships procured in FY2010 and subsequent years (Section 122 of the FY2009 
defense authorization act [S. 3001/P.L. 110-417 of October 14, 2008]); rescinded $337 million in 
FY2008 shipbuilding funds for the LCS program, effectively canceling the funding for the LCS 
procured in FY2008 (Section 8042 of the FY2009 defense appropriations act [Division C of H.R. 
2638/P.L. 110-329 of September 30, 2008]); and funded the procurement of two LCSs at a cost of 
$1,020 million. 
FY2010 
In FY2010 Congress funded the procurement of two LCSs at a cost of $1,080 million and 
rescinded $66 million in FY2009 Other Procurement, Navy (OPN) funding for LCS mission 
modules. Section 121 of the FY2010 defense authorization act (H.R. 2647/P.L. 111-84 of October 
28, 2009) granted the Navy contracting and other authority to implement the LCS acquisition 
strategy that the Navy announced on September 16, 2009, and amended the LCS unit 
procurement cost cap. Section 122 of the act requires the LCS program to be treated as a major 
defense acquisition program (MDAP) for purposes of program management and oversight. 
Section 123 of the act requires a report on the Navy’s plan for homeporting LCSs. 
 
 
 
Congressional Research Service 
31 
Navy Littoral Combat Ship (LCS) Program 
 
Appendix B. Cost Growth on LCS Sea Frames 
This appendix presents details on cost growth on LCS sea frames from the FY2006 budget cycle 
through the FY2009 budget cycle. 
2006 
The proposed FY2007 Navy budget, submitted in February 2006, showed that: 
•  the estimate for the first LCS had increased from $215.5 million in the FY2005 
budget and $212.5 million in the FY2006 budget to $274.5 million in the 
FY2007 budget—an increase of about 27% from the FY2005 figure and about 
29% form the FY2006 figure; 
•  the estimate for the second LCS increased from $213.7 million in the FY2005 
budget and $256.5 million in the FY2006 budget to $278.1 million—an increase 
of about 30% from the FY2005 figure and about 8% from the FY2006 figure; 
and 
•  the estimate for follow-on ships scheduled for FY2009-FY2011, when the LCS 
program was to have reached a planned maximum annual procurement rate of six 
ships per year, had increased from $223.3 million in the FY2006 budget to $298 
million—an increase of about 33%. 
The Navy stated in early 2006 that the cost increase from the FY2006 budget to the FY2007 
budget was due mostly to the fact that LCS procurement costs in the FY2006 budget did not 
include items that are traditionally included in the so-called end cost—the total budgeted 
procurement cost—of a Navy shipbuilding program, such as Navy program-management costs, 
an allowance for changes, and escalation (inflation). The absence of these costs from the FY2006 
LCS budget submission raised certain potential oversight issues for Congress.37 
2007 
On January 11, 2007, the Navy reported that LCS-1 was experiencing “considerable cost 
overruns.” The Navy subsequently stated that the estimated shipyard construction cost of LCS-1 
had grown to $350 million to $375 million. This suggested that the end cost of LCS-1—which 
                                                             
37 These oversight issues included the following: 
—Why were these costs excluded? Was this a budget-preparation oversight? If so, how could such an oversight occur, 
given the many people involved in Navy budget preparation and review, and why did it occur on the LCS program but 
not other programs? Was anyone held accountable for this oversight, and if so, how? If this was not an oversight, then 
what was the reason? 
—Did the Navy believe there was no substantial risk of penalty for submitting to Congress a budget presentation for a 
shipbuilding program that, for whatever reason, significantly underestimated procurement costs? 
—Do LCS procurement costs in the budget now include all costs that, under traditional budgeting practices, should be 
included? If not, what other costs are still unacknowledged? 
—Have personnel or other resources from other Navy programs been used for the LCS program in any way? If so, have 
the costs of these personnel or other resources been fully charged to the LCS program and fully reflected in LCS 
program costs shown in the budget? 
Congressional Research Service 
32 
Navy Littoral Combat Ship (LCS) Program 
 
also includes costs for things such as Navy program-management costs and an allowance for 
changes—could be in excess of $400 million. The Navy did not publicly provide a precise cost 
overrun figure for LCS 2, but it stated that the cost overrun on LCSs 1 and 2 was somewhere 
between 50% and 75%, depending on the baseline that is used to measure the overrun. 
The Government Accountability Office (GAO) testified in July 2007 that according to its own 
analysis of Navy data, the combined cost of LCSs 1 and 2 had increased from $472 million to 
$1,075 million—an increase of 128%.38 CBO testified in July 2007 that: 
Several months ago, press reports indicated that the cost could well exceed $400 million 
each for the first two LCS sea frames. Recently, the Navy requested that the cost cap for the 
fifth and sixth sea frames be raised to $460 million, which suggests that the Navy’s estimate 
of the acquisition cost for the first two LCSs would be around $600 million apiece.... 
As of this writing, the Navy has not publicly released an estimate for the LCS program that 
incorporates the most recent cost growth, other than its request to raise the cost caps for the 
fifth and sixth ships. CBO estimates that with that growth included, the first two LCSs would 
cost about $630 million each, excluding mission modules but including outfitting, 
postdelivery, and various nonrecurring costs associated with the first ships of the class. As 
the program advances, with a settled design and higher annual rates of production, the 
average cost per ship is likely to decline. Excluding mission modules, the 55 LCSs in the 
Navy’s plan would cost an average of $450 million each, CBO estimates.39 
2008 
The proposed FY2009 budget, submitted in February 2008, showed that the estimated end costs 
of LCS-1 and LCS-2 had increased to $531 million and $507 million, respectively (or to $631 
million and $636 million, respectively, when OF/DP and FST MSSIT costs are included, or to 
$606 million and $582 million, respectively, when OF/DP costs are included, but FST MSSIT 
costs are not included). 
2009 
The proposed FY2010 budget, submitted in May 2009, showed that the estimated end costs of 
LCS-1 and LCS-2 had increased to $537 million and $575 million, respectively (or to $637 
million and $704 million, respectively, when OF/DP and FST MSSIT costs are included, or to 
$612 million and $650 million, respectively, when OF/DP costs are included, but FST MSSIT 
costs are not included). CBO reported on June 9, 2008, that: 
Historical experience indicates that cost growth in the LCS program is likely. In particular, 
using the lead ship of the FFG-7 Oliver Hazard Perry class frigate as an analogy, historical 
cost-to-weight relationships indicate that the Navy’s original cost target for the LCS of $260 
                                                             
38 Defense Acquisitions[:] Realistic Business Cases Needed to Execute Navy Shipbuilding Programs, Statement of Paul 
L. Francis, Director, Acquisition and Sourcing Management Team, Testimony Before the Subcommittee on Seapower 
and Expeditionary Forces, Committee on Armed Services, House of Representatives, July 24, 2007 (GAO-07-943T), 
pp. 4 and 22. 
39 Statement of J. Michael Gilmore, Assistant Director for National Security, and Eric J. Labs, Senior Analyst, [on] The 
Navy’s 2008 Shipbuilding Plan and Key Ship Programs, before the Subcommittee on Seapower and Expeditionary 
Forces Committee on Armed Services U.S. House of Representatives, July 24, 2007, p. 18. 
Congressional Research Service 
33 
Navy Littoral Combat Ship (LCS) Program 
 
million in 2009 dollars (or $220 million in 2005 dollars) was optimistic. The first FFG-7 cost 
about $670 million in 2009 dollars to build, or about $250 million per thousand tons, 
including combat systems. Applying that metric to the LCS program suggests that the lead 
ships would cost about $600 million apiece, including the cost of one mission module. Thus, 
in this case, the use of a historical cost-to-weight relationship produces an estimate that is 
less than the actual costs of the first LCSs to date but substantially more than the Navy’s 
original estimate. 
Based on actual costs the Navy has incurred for the LCS program, CBO estimates that the 
first two LCSs could cost about $700 million each, including outfitting and postdelivery and 
various nonrecurring costs associated with first ships of a class but excluding mission 
modules. However, as of May 1, 2008, LCS-1 was 83 percent complete and LCS-2 was 68 
percent complete. Thus, additional cost growth is possible, and CBO’s estimate reflects that 
cost risk. 
Overall, CBO estimates that the LCSs in the Navy’s plan would cost about $550 million 
each, on average, excluding mission modules. That estimate assumes that the Navy would 
select one of the two existing designs and make no changes. As the program advanced with a 
settled design and higher annual rates of production, average ship costs would probably 
decline. If the Navy decided to make changes to that design, however, the costs of building 
future ships could be higher than CBO now estimates.40 
Reasons for Cost Growth 
Various reasons have been cited for cost growth in the LCS program, including the following: 
•  Unrealistically low original estimate. Some observers believe that the original 
cost estimate of $220 million for the LCS sea frame was unrealistically low. If so, 
a potential follow-on question would be whether the LCS represents a case of 
“low-balling”—using an unrealistically low cost estimate in the early stages of a 
proposed weapon program to help the program win approval and become an 
established procurement effort. 
•  Impact of Naval Vessel Rules (NVR). Navy and industry officials have 
attributed some of the cost growth to the impact of applying new Naval Vessel 
Rules (NVR)—essentially, new rules specifying the construction standards for 
the ship—to the LCS program. The NVR issued for the LCS program 
incorporated, among other things, an increase in the survivability standard (the 
ability to withstand damage) to which LCSs were to be built.41 Building the ship 
to a higher survivability standard represented a change in requirements for the 
ship that led to many design changes, including changes that made ship more 
rugged and more complex in terms of its damage-control systems. In addition, 
Navy and industry officials have testified, the timing of the issuing of NVR 
                                                             
40 Congressional Budget Office, Resource Implications of the Navy’s Fiscal Year 2009 Shipbuilding Plan, June 8, 
2008, pp. 26-27. 
41 The LCS was earlier conceived as a ship that would be built to a survivability standard that would be sufficient, in 
the event of significant battle damage, to save the ship’s crew, but not necessarily the ship. The survivability standard 
for the LCS was increased as part of the issuing of NVR to one that would be sufficient to save not only the ship’s 
crew, but the ship as well. (Other U.S. Navy combat ships are built to a still-higher survivability standard that is 
sufficient not only to save the crew and the ship, but to permit the ship to keep fighting even though it has sustained 
damage.) 
Congressional Research Service 
34 
Navy Littoral Combat Ship (LCS) Program 
 
created a situation of concurrency between design and construction in the LCS 
program, meaning that the ship was being designed at the same time that the 
shipyard was attempting to build it—a situation long known to be a potential 
cause of cost growth. This concurrency, Navy officials testified, was a 
consequence of the compressed construction schedule for the LCS program, 
which in turn reflected an urgency about getting LCSs into the fleet to meet 
critical mission demands. 
•  Improperly manufactured reduction gear. Navy and industry officials testified 
that cost growth on LCS-1 was partly due to a main reduction gear42 that was 
incorrectly manufactured and had to be replaced, forcing a reordering of the 
construction sequence for the various major sections of the ship. 
•  Increased costs for materials. Some observers have attributed part of the cost 
growth in the program to higher-than-estimated costs for steel and other materials 
that are used in building the ships. 
•  Emphasis on meeting schedule combined with cost-plus contract. Some 
portion of cost growth on LCS-1 has been attributed to a combination of a Navy 
emphasis on meeting the ship’s aggressive construction schedule and the Navy’s 
use of a cost-plus contract to build the ship.43 
•  Shipyard Performance. Shipyard performance and supervision of the LCS 
shipyards by the LCS team leaders and the Navy has been cited as another cause 
of cost growth.44 
July 2007 GAO Testimony 
GAO testified in July 2007 that: 
We have frequently reported on the wisdom of using a solid, executable business case before 
committing resources to a new product development effort.... 
                                                             
42 A ship’s reduction gear is a large, heavy gear that reduces the high-speed revolutions of the ship’s turbine engines to 
the lower-speed revolutions of its propellers. 
43 The Senate Armed Services Committee, as part of its discussion of the LCS program in its report (S.Rept. 110-77 of 
June 5, 2007) on the FY2008 defense authorization bill (S. 1547), stated: 
Reviewing this LCS situation will undoubtedly result in a new set of “lessons learned”‘ that the 
acquisition community will dutifully try to implement. However, the committee has previously 
expressed concerns about the LCS concept and the LCS acquisition strategy. The LCS situation 
may be more a case of “lessons lost.” Long ago, we knew that we should not rush to sign a 
construction contract before we have solidified requirements. We also knew that the contractors 
will respond to incentives, and that if the incentives are focused on maintaining schedules and not 
on controlling cost, cost growth on a cost-plus contract should surprise no one. After the fact, 
everyone appears ready to agree that the original ship construction schedule for the lead ship was 
overly aggressive. (Page 98) 
44 See Katherine McIntire Peters, “Navy’s Top Officer Sees Lessons In Shipbuilding Program Failures,” 
GovermentExecutive.com, September 24, 2008; Christopher J. Castelli, “Audit Exposes Failed Management of 
Troubled Littoral Warship,” Inside the Navy, February 4, 2008; Christopher J. Castelli, “Audit Reveals Both LCS and 
Industry Teams Violated Management Rules,” Inside the Pentagon, July 10, 2008 (reprinted in essentially identical 
form, with the same headline, in the July 14, 2008, issue of sister publication Inside the Navy). 
Congressional Research Service 
35 
Navy Littoral Combat Ship (LCS) Program 
 
A sound business case would establish and resource a knowledge-based approach at the 
outset of a program. We would define such a business case as firm requirements, mature 
technologies, and an acquisition strategy that provides sufficient time and money for design 
activities before construction start. The business case is the essential first step in any 
acquisition program that sets the stage for the remaining stages of a program, namely the 
business or contracting arrangements and actual execution or performance. If the business 
case is not sound, the contract will not correct the problem and execution will be subpar. 
This does not mean that all potential problems can be eliminated and perfection achieved, but 
rather that sound business cases can get the Navy better shipbuilding outcomes and better 
return on investment. If any one element of the business case is weak, problems can be 
expected in construction. The need to meet schedule is one of the main reasons why 
programs cannot execute their business cases. This pattern was clearly evident in both the 
LPD 17 [amphibious ship] and LCS programs. In both cases, the program pushed ahead with 
production even when design problems arose or key equipment was not available when 
needed. Short cuts, such as doing technology development concurrently with design and 
construction, are taken to meet schedule. In the end, problems occur that cannot be resolved 
within compressed, optimistic schedules. Ultimately, when a schedule is set that cannot 
accommodate program scope, delivering an initial capability is delayed and higher costs are 
incurred.... 
What happens when the elements of a solid business case are not present? Unfortunately, the 
results have been all too visible in the LPD 17 and the LCS. Ship construction in these 
programs has been hampered throughout by design instability and program management 
challenges that can be traced back to flawed business cases. The Navy moved forward with 
ambitious schedules for constructing LPD 17 and LCS despite significant challenges in 
stabilizing the designs for these ships. As a result, construction work has been performed out 
of sequence and significant rework has been required, disrupting the optimal construction 
sequence and application of lessons learned for follow-on vessels in these programs.... 
In the LCS program, design instability resulted from a flawed business case as well as 
changes to Navy requirements. From the outset, the Navy sought to concurrently design and 
construct two lead ships in the LCS program in an effort to rapidly meet pressing needs in 
the mine countermeasures, antisubmarine warfare, and surface warfare mission areas. The 
Navy believed it could manage this approach, even with little margin for error, because it 
considered each LCS to be an adaptation of an existing high-speed ferry design. It has since 
been realized that transforming a high-speed ferry into a capable, networked, survivable 
warship was quite a complex venture. Implementation of new Naval Vessel Rules (design 
guidelines) further complicated the Navy’s concurrent design-build strategy for LCS. These 
rules required program officials to redesign major elements of each LCS design to meet 
enhanced survivability requirements, even after construction had begun on the first ship. 
While these requirements changes improved the robustness of LCS designs, they contributed 
to out of sequence work and rework on the lead ships. The Navy failed to fully account for 
these changes when establishing its $220 million cost target and 2-year construction cycle 
for the lead ships. 
Complicating LCS construction was a compressed and aggressive schedule. When design 
standards were clarified with the issuance of Naval Vessel Rules and major equipment 
deliveries were delayed (e.g., main reduction gears), adjustments to the schedule were not 
made. Instead, with the first LCS, the Navy and shipbuilder continued to focus on achieving 
the planned schedule, accepting the higher costs associated with out of sequence work and 
rework. This approach enabled the Navy to achieve its planned launch date for the first 
Littoral Combat Ship, but required it to sacrifice its desired level of outfitting. Program 
officials report that schedule pressures also drove low outfitting levels on the second Littoral 
Combat Ship design as well, although rework requirements have been less intensive to date. 
However, because remaining work on the first two ships will now have to be completed out-
Congressional Research Service 
36 
Navy Littoral Combat Ship (LCS) Program 
 
of-sequence, the initial schedule gains most likely will be offset by increased labor hours to 
finish these ships. 
The difficulties and costs discussed above relate to the LCS seaframe only. This program is 
unique in that the ship’s mission equipment is being developed and funded separately from 
the seaframe. The Navy faces additional challenges integrating mission packages with the 
ships, which could further increase costs and delay delivery of new antisubmarine warfare, 
mine countermeasures, and surface warfare capabilities to the fleet. These mission packages 
are required to meet a weight requirement of 180 metric tons or less and require 35 personnel 
or less to operate them. However, the Navy estimates that the mine countermeasures mission 
package may require an additional 13 metric tons of weight and seven more operator 
personnel in order to deploy the full level of promised capability. Because neither of the 
competing ship designs can accommodate these increases, the Navy may be forced to 
reevaluate its planned capabilities for LCS.45 
                                                             
45 Defense Acquisitions[:] Realistic Business Cases Needed to Execute Navy Shipbuilding Programs, Statement of Paul 
L. Francis, Director, Acquisition and Sourcing Management Team, Testimony Before the Subcommittee on Seapower 
and Expeditionary Forces, Committee on Armed Services, House of Representatives, July 24, 2007 (GAO-07-943T), 
pp. 8-11. 
Congressional Research Service 
37 
Navy Littoral Combat Ship (LCS) Program 
 
Appendix C. 2007 Program Restructuring and Ship 
Cancellations 
The Navy substantially restructured the LCS program in 2007 in response to significant cost 
growth and delays in constructing the first LCS sea frames. This restructuring led to the 
cancellation of four LCSs that were funded in FY2006 and FY2007. A fifth LCS, funded in 
FY2008, was cancelled in 2008. This appendix presents the details of the program restructuring 
and ship cancellations. 
2007 Program Restructuring 
March 2007 Navy Restructuring Plan 
In response to significant cost growth and schedule delays in the building of the first LCSs that 
first came to light in January 2007 (see next section), the Navy in March 2007 announced a plan 
for restructuring the LCS program that: 
•  canceled the two LCSs funded in FY2007 and redirected the funding for those 
two ships to pay for cost overruns on earlier LCSs; 
•  announced an intention to lift a 90-day stop-work order that the Navy had placed 
on LCS-3 in January 2007—provided that the Navy reached an agreement with 
the Lockheed-led industry team by April 12, 2007, to restructure the contract for 
building LCSs 1 and 3 from a cost-plus type contract into a fixed price incentive 
(FPI)-type contract—or terminate construction of LCS-3 if an agreement on a 
restructured contract could not be reached with the Lockheed team by April 12, 
2007; 
•  announced an intention to seek to restructure the contract with the General 
Dynamics-led industry team for building LCSs 2 and 4 into an FPI-type 
contract—if LCSs 2 and 4 experienced cost growth comparable to that of LCSs 1 
and 3—and, if such a restructuring were sought, terminate construction of LCS-4 
if an agreement on a restructured contract for LCS-2 and LCS-4 could not be 
reached; 
•  reduced the number of LCSs requested for FY2008 from three to two (for the 
same requested FY2008 procurement funding of $910.5 million), and the number 
to be requested for FY2009 from six to three; and 
•  announced an intention to conduct an operational evaluation to select a favored 
design for the LCS that would be procured in FY2010 and subsequent years, and 
to conduct a full and open follow-on competition among bidders for the right to 
build that design.46 
                                                             
46 Source: Navy briefing to CRS and Congressional Budget Office (CBO) on Navy’s proposed LCS program 
restructuring plan, March 21, 2007. 
Congressional Research Service 
38 
Navy Littoral Combat Ship (LCS) Program 
 
April 2007 Termination of LCS-3 
On April 12, 2007, the Navy announced that it had not reached an agreement with Lockheed on a 
restructured FPI-type contract for LCS-1 and LCS-3, and consequently was terminating 
construction of LCS-3.47 (The Navy subsequently began referring to the ship as having been 
partially terminated—a reference to the fact that Lockheed was allowed to continue procuring 
certain components for LCS-3, so that a complete set of these components would be on hand to 
be incorporated into the next LCS built to the Lockheed design.) (The designation LCS-3 is now 
being reused to refer to one of the two LCSs procured in FY2009.) 
November 2007 Termination of LCS-4 
In late September 2007, it was reported that the Navy on September 19 had sent a letter to 
General Dynamics to initiate negotiations on restructuring the contract for building LCSs 2 and 4 
into an FPI-type contract. The negotiations reportedly were to be completed by October 19, 
2007—30 days from September 19.48 On November 1, 2007, the Navy announced that it had not 
reached an agreement with General Dynamics on a restructured FPI-type contract for LCS-2 and 
LCS-4, and consequently was terminating construction of LCS-4.49 (The designation LCS-4 is 
now being reused to refer to one of the two LCSs procured in FY2009.) 
Cancellation of Prior-Year Ships 
Table C-1 below summarizes the status of the nine LCSs funded by Congress from FY2005 
through FY2009. As shown in the table, of the nine ships, five were later canceled, leaving four 
ships in place through FY2009—LCSs 1 and 2, and the two LCSs funded in FY2009. Ship 
designations LCS-3 and LCS-4 are being reused as the designations for the two ships funded in 
FY2009. 
                                                             
47 Department of Defense News Release No. 422-07, April 12, 2007, “Navy Terminates Littoral Combat Ship 3.” 
48 Geoff Fein, “Navy Seeking To Negotiate FPI Contract With General Dynamics,” Defense Daily, September 24, 
2007; Geoff Fein, “Navy, General Dynamics Meet To Discuss New LCS Fixed Price Structure,” Defense Daily, 
September 27, 2007; Tony Capaccio, “General Dynamics Urged To Take Fixed Price On Warship Contract,” 
Bloomberg News, September 28, 2007; Jason Sherman, “Navy, General Dynamics Discuss Fixed-Price Contract For 
LCS,” Inside the Navy, October 1, 2007. 
49 Department of Defense News Release No. 1269-07, November 1, 2007, “Navy Terminates Littoral Combat Ship 
(LCS 4) Contract.” 
Congressional Research Service 
39 
Navy Littoral Combat Ship (LCS) Program 
 
Table C-1. Status of LCSs Funded in FY2005-FY2009 
Ships  
FY  
Navy hull  
funded  funded 
designation 
Status 
1st 2005 
LCS-1 
Commissioned into service on November 8, 2008. 
2nd LCS-2 
Commissioned into service on January 16, 2010. 
3rd LCS-3 
Canceled by Navy in April 2007 after being placed under 
contract due to inability to come to agreement with contractor 
(not the same ship as LCS-3  on revised (fixed-price) contract terms for LCSs 1 and 3. 
2006 
below) 
4th 
LCS-4 
Canceled by Navy in November 2007 after being placed under 
contract due to inability to come to agreement with contractor 
(not the same ship as LCS-4  on revised (fixed-price) contract terms for LCSs 2 and 4. 
below) 
5th none 
 
Canceled by Navy in March 2007 before being placed under 
(ship canceled before being  contract as part of Navy’s LCS program restructuring; funds 
placed under contract) 
reapplied to cover other program costs. 
2007 
6th 
none  
Canceled by Navy in March 2007 before being placed under 
(ship canceled before being  contract as part of Navy’s LCS program restructuring; funds 
placed under contract) 
reapplied to cover other program costs. 
7th 
LCS-5  
Canceled by Navy following Congress’s decision in 
(for a while, at least, 
September 2008, as part of its action on the FY2009 defense 
2008 
although the ship was 
appropriations bill, to rescind the funding for the ship. 
canceled before being 
placed under contract) 
8th LCS-3 
Funded in FY2009 and Under Construction. Contract to 
build the ship awarded to Lockheed Martin on March 23, 2009. 
(not the same ship as LCS-3  Ship is currently under construction. 
above; the ship designation 
is being reused) 
2009 
9th 
LCS-4 
Funded in FY2009 and Under Construction. Contract to 
build the ship awarded to General Dynamics on May 1, 2009. 
(not the same ship as LCS-4  Ship is currently under construction. 
above; the ship designation 
is being reused) 
Source: Prepared by CRS. 
Congressional Research Service 
40 
Navy Littoral Combat Ship (LCS) Program 
 
Appendix D. LCS Acquisition Strategy Announced 
in September 2009 
This appendix presents additional background information on the LCS acquisition strategy 
announced by the Navy on September 16, 2009. 
A September 16, 2009, Department of Defense (DOD) news release on the proposed new 
acquisition strategy stated: 
The Navy announced today it will down select between the two Littoral Combat Ship (LCS) 
designs in fiscal 2010. The current LCS seaframe construction solicitation [for the FY2010 
LCSs] will be cancelled and a new solicitation will be issued. At down select, a single prime 
contractor and shipyard will be awarded a fixed price incentive contract for up to 10 ships 
with two ships in fiscal 2010 and options through fiscal 2014. This decision was reached 
after careful review of the fiscal 2010 industry bids, consideration of total program costs, and 
ongoing discussions with Congress.  
“This change to increase competition is required so we can build the LCS at an affordable 
price,” said Ray Mabus, secretary of the Navy. “LCS is vital to our Navy’s future. It must 
succeed.” 
“Both ships meet our operational requirements and we need LCS now to meet the 
warfighters’ needs,” said Adm. Gary Roughead, chief of naval operations. “Down selecting 
now will improve affordability and will allow us to build LCS at a realistic cost and not 
compromise critical warfighting capabilities.”  
The Navy cancelled the solicitation to procure up to three LCS Flight 0+ ships in fiscal 2010 
due to affordability. Based on proposals received this summer, it was not possible to execute 
the LCS program under the current acquisition strategy and given the expectation of 
constrained budgets. The new LCS acquisition strategy improves affordability by 
competitively awarding a larger number of ships across several years to one source. The 
Navy will accomplish this goal by issuing a new fixed price incentive solicitation for a down 
select to one of the two designs beginning in fiscal 2010.  
Both industry teams will have the opportunity to submit proposals for the fiscal 2010 ships 
under the new solicitation. The selected industry team will deliver a quality technical data 
package, allowing the Navy to open competition for a second source for the selected design 
beginning in fiscal 2012. The winner of the down select will be awarded a contract for up to 
10 ships from fiscal 2010 through fiscal 2014, and also provide combat systems for up to 
five additional ships provided by a second source. Delivery of LCS 2, along with 
construction of LCS 3 and LCS 4 will not be affected by the decision. This plan ensures the 
best value for the Navy, continues to fill critical warfighting gaps, reduces program 
ownership costs, and meets the spirit and intent of the Weapons System Acquisition Reform 
Act of 2009.... 
The Navy remains committed to the LCS program and the requirement for 55 of these ships 
to provide combatant commanders with the capability to defeat anti-access threats in the 
littorals, including fast surface craft, quiet submarines and various types of mines. The 
Congressional Research Service 
41 
Navy Littoral Combat Ship (LCS) Program 
 
Navy’s acquisition strategy will be guided by cost and performance of the respective designs 
as well as options for sustaining competition throughout the life of the program.50 
A September 16, 2009, e-mail from the Navy to CRS provided additional information on the 
proposed new strategy, stating: 
The Navy remains committed to a 55 ship LCS program and intends to procure these ships 
through an acquisition strategy that leverages competition, fixed price contracting and 
stability in order to meet our overarching objectives of performance and affordability. 
In the best interest of the Government, the Navy cancelled the solicitation to procure up to 
three LCS Flight 0+ ships in FY10 due to affordability. 
Based on proposals received in August, the Navy had no reasonable basis to find that the 
LCS Program would be executable going forward under the current acquisition strategy, 
given the expectation of constrained budgets. 
In the near future, and working closely with Congress, the Navy will issue a new FY10 
solicitation which downselects between the two existing designs and calls for building two 
ships in FY10 and provides options for two additional ships per year from FY11 to FY14 for 
a total of ten ships. The intent is for all of these ships to be built in one shipyard, which will 
benefit from a stable order quantity, training and production efficiencies to drive costs down. 
Both industry teams will have the opportunity to submit proposals for the FY10 ships under 
the new solicitation. 
To sustain competition throughout the life of the program and in conjunction with the 
downselect, the Navy will develop a complete Technical Data Package which will be used to 
open competition for a second source of the selected design in FY12, awarding one ship with 
options for up to four additional ships through FY14, to a new shipbuilder. 
Our FY10 solicitation will call for the prime to build an additional five combat systems to be 
delivered as government-furnished equipment for this second source shipyard. Separating the 
ship and combat systems procurement will enable bringing the LCS combat system into the 
broader Navy’s open architecture plan. 
In short, this strategy calls for two shipbuilders in continuous competition for a single LCS 
seaframe design, and a government-provided combat system. 
The revised strategy meets the full spirit and intent of the Weapon Systems Acquisition 
Reform Act of 2009 by increasing Government oversight, employing fixed price contract 
types, maximizing competition, leveraging open architecture, using Economic Order 
Quantity and Block Buy strategies, and ensuring future competition for shipbuilding as 
enabled by development of a Technical Data Package to solicit ships from a second shipyard. 
We also continue to work closely with Congress on the Navy’s LCS procurement 
intentions.... 
The Navy intends to continue with construction and delivery of LCS 3 and LCS 4, ultimately 
for use as deployable assets. We will continue to explore all avenues to ensure this is an 
affordable program.51 
                                                             
50 Department of Defense, “Littoral Combat Ship Down Select Announced,” News Release 722-09, September 16, 
2009, available online at http://www.defenselink.mil/releases/release.aspx?releaseid=12984. 
Congressional Research Service 
42 
Navy Littoral Combat Ship (LCS) Program 
 
The Navy briefed CRS and CBO about the proposed new acquisition strategy on September 22, 
2009. Points made by the Navy in the briefing included the following: 
•  The bids from the two industry teams for the three LCSs requested in the FY2010 
budget (which were submitted to the Navy in late July or early August 200952) 
were above the LCS unit procurement cost cap in “all scenarios.” 
•  Negotiations with the industry teams were deemed by the Navy to be not likely to 
result in award prices for the FY2010 ships that were acceptable to the Navy. 
•  The Navy judged that the current LCS teaming arrangements “considerably 
influenced costs” in the FY2010 bids. 
•  The Navy judged that it cannot afford more than a two-ship award in FY2010 
within the amount of funding ($1,380 million) requested for LCS sea frame 
procurement in FY2010. 
•  In response to the above points, the Navy decided to seek a new acquisition 
strategy for LCSs procured in FY2010 and subsequent years that would make the 
LCS program affordable by leveraging competition, providing stability to LCS 
shipyards and suppliers, producing LCSs at efficient rates, giving industry 
incentives to make investments that would reduce LCS production costs, and 
increase commonality in the resulting LCS fleet. 
•  Under the Navy’s proposed new strategy, the winner of the LCS down select 
would be awarded a contract to build two ships procured in FY2010, with options 
to build two more ships per year in FY2011-FY2014. The contract would be a 
block-buy contract augmented with Economic Order Quantity (EOQ) authority, 
so as to permit up-front batch purchases of long leadtime components, as would 
be the case under a multiyear procurement (MYP) contract. Unlike an MYP 
contract, however, the block buy contract would not include a termination 
liability. 
•  The winner of the down select would deliver to the Navy a technical data 
package that would permit another shipyard to build the winning LCS design. 
•  The Navy would hold a second competition to select a second LCS bidder. This 
competition would be open to all firms other than the shipyard that is building the 
10 LCSs in FY2010-FY2014. The winner of this second competition would be 
awarded a contract to build up to five LCSs in FY2012-FY2014 (one ship in 
FY2012, and two ships per year in FY2013-FY2014). 
•  The Navy would maintain competition between the two shipyards for LCSs 
procured in FY2015 and subsequent years. 
•  The prime contactor on the team that wins the LCS down select (i.e., Lockheed 
or General Dynamics) would provide the combat systems for all the LCSs to be 
                                                             
(...continued) 
51 Email from Navy Office of Legislative Affairs to CRS, entitled “LCS Way Ahead,” September 16, 2009. 
52 See, for example, Christopher P. Cavas, “LCS Bids Submitted to U.S. Navy,” DefenseNews.com, August 3, 2009, 
which states: “Lockheed Martin announced its proposal was sent to the Navy on July 31, and rival General Dynamics 
confirmed its plans were sent in by the Aug. 3 deadline.” See also Bettina H. Chavanne, “Lockheed Submits First LCS 
Proposal Under Cost Cap Regulations,” Aerospace Daily & Defense Report, August 4, 2009: 5. 
Congressional Research Service 
43 
Navy Littoral Combat Ship (LCS) Program 
 
procured in FY2010-FY2014—the 10 that would be built by the first shipyard, 
and the others that would be built by the second shipyard. 
•  The structure of the industry team that wins the down select would be altered, 
with the prime contractor on the team being separated from the shipyard (i.e., the 
shipyard building the 10 LCSs in FY2010-FY2014). The separation, which 
would occur some time between FY2010 and FY2014, would be intended in part 
to prevent an organizational conflict of interest on the part of the prime contractor 
as it provides combat systems to the two shipyards building LCSs. 
•  The current combat system used on the selected LCS design will be modified 
over time to a configuration that increases its commonality with one or more of 
the Navy’s existing surface ship combat systems. 
•  The Navy intends to complete the construction and delivery of LCS-3 and LCS-
4. 
•  The Navy believes that the proposed acquisition strategy does the following: 
maximize the use of competition in awarding contracts for LCSs procured in 
FY2010-FY2014; provide an opportunity for achieving EOQ savings with 
vendors; provide stability and efficient production quantities to the shipyards and 
vendors; provide an opportunity to move to a common combat system for the 
LCS fleet; and provide the lowest-possible total ownership cost for the Navy for 
the resulting LCS fleet, in large part because the fleet would consist primarily of 
a single LCS design with a single logistics support system. The Navy also 
believes the proposed strategy is consistent with the spirit and intent of the 
Weapon Systems Acquisition Reform Act of 2009 (S. 454/P.L. 111-23 of May 22, 
2009). 
Regarding the Navy’s ability to sustain a competition between two LCS builders for LCS 
construction contracts years from now, when the annual LCS procurement rate is projected to 
drop to 1.5 ships per year (i.e., a 1-2-1-2 pattern), Undersecretary of the Navy Robert Work 
reportedly stated: 
“We are going to be able to compete those. We will be able to compete three [ships] every 
two years and one of the yards will win two and one yard will win one. Sometimes, we’ll do 
a five multi-year [procurement contract]. We have all sorts of flexibility in here,” he said.53 
                                                             
53 Geoff Fein, “Official: Navy OK With Either LCS, New Acquisition Plan Adds Flexibility In Out Years,” Defense 
Daily, February 18, 2010: 3. 
Congressional Research Service 
44 
Navy Littoral Combat Ship (LCS) Program 
 
Appendix E. May 2010 Navy Testimony Regarding 
Fuel Costs as Evaluation Factor 
At a May 6, 2010, hearing on Navy shipbuilding programs before the Seapower Subcommittee of 
the Senate Armed Services Committee, Senator Jeff Sessions questioned Sean Stackley, the 
Navy’s acquisition executive (i.e., the Assistant Secretary of the Navy [Research, Development 
and Acquisition]), regarding the role of fuel costs in the Navy’s evaluation of the two LCS 
designs. The following is text of the exchange: 
SENATOR SESSIONS:  
Secretary Stackley, yesterday, Defense News reported that Secretary Mabus, the Navy 
secretary, in his remarks to the Navy League on May 5th, stated that “energy efficiency, both 
in the manufacturing process and in the final product would increasingly be a factor in 
judging program”—reform—"performance, as well as in the contract awards.”  
Earlier, he said, in October of last year at an energy forum, “First, we‘re going to change the 
way the Navy and the Marine Corps awards contracts, that lifetime energy costs of a building 
or a system and the fully burdened costs of fuel in powering those will be a mandatory 
evaluation factor used when awarding contracts.  
“We're going to hold industry contractually accountable for meeting energy targets and 
system efficiency requirements.” And he goes on to emphasize that more.  
And in September of ‘09, he said, “One of the drivers for me is the affordability of being 
able to operate the force. We no longer have the luxury to say it’s a good deal on price, or 
let’s buy it, we have to get our arms around the lifecycle costs.” 
Do you agree that that’s the right way to purchase a ship or anything, but—any vehicle, but a 
ship, particularly, that you want to know not only how much it costs today, but how much 
fuel it will use and how much it will cost to operate that? Is that a factor that should given 
weight in the process?  
STACKLEY:  
Sir, we—the secretary has outlined his goals for energy, and we are putting a lot of effort 
into not just meeting his goals, but building the path to get there.  
When we look at how we procure our ships, we bring total ownership cost into the equation, 
and we evaluate not just—we look at not just the procurement costs, but we look at, again, 
the ownership costs throughout the life of the program, which includes—that includes 
energy, it includes manpower, it includes maintenance and modernization considerations in 
addition to the upfront procurement cost.  
SESSIONS:  
Well, I think you said that you agree with the secretary. Is that right?  
STACKLEY:  
I would—I would always agree with the secretary, sir.  
Congressional Research Service 
45 
Navy Littoral Combat Ship (LCS) Program 
 
(LAUGHTER)  
SESSIONS:  
Well, especially when he’s correct, as he is in that statement.  
But I didn't hear you say precisely that you are at that level now. He said, we're going to—
"the first thing we're going to do is fix this energy matter.”  
So I'm asking you today, when you look at Littoral Combat Ship competition, is that 
effectively being evaluated in the bid process? It certainly seems that it should be?  
STACKLEY:  
We took a look at, inside of the—of the larger category of ownership costs, we took a look 
at—we considered it as an evaluation factor, compared the two designs, and arrived at an 
evaluation inside the technical portion of the LCS award criteria that would address 
improvements to total ownership costs, which would include energy as well as maintenance 
and modernization.  
SESSIONS:  
Well, the fact that that is a very long and complex answer makes me nervous. Because my 
analysis of it is that it does not do just what the secretary said.  
And I would offer, for the record, Mr. Chairman, a report from the Congressional Budget 
Office that’s analyzed this particular question. The way I read the report, it’s pretty clear to 
me that the Navy has not sufficiently calculated the fuel costs of this ship.  
Has the—in calculating the comparative fuel costs of the two ships, and that’s what you 
mean by those words you gave us, doesn't it? You compare the cost of one ship and its 
normal operating procedure and you compare the cost of the other. Correct? Is that what you 
mean?  
STACKLEY:  
We look at total ownership cost, which includes all the factors, including energy, yes, sir.  
SESSIONS:  
Well, let’s focus on the energy part of cost. Do you consider how much it costs to run one 
ship and you consider the cost of the other one? That’s what it means. Does it not?  
STACKLEY:  
Yes, sir.  
SESSIONS:  
And have you calculated and reduced to dollar amounts, the estimated fuel cost of operating 
these ships, each one, through the lifecycle?  
STACKLEY:  
Congressional Research Service 
46 
Navy Littoral Combat Ship (LCS) Program 
 
We've looked at the different ways in which the Navy would operate the ship—because, 
clearly, fuel costs are dependent upon how you would operate the ship—and ran the 
respective analyses for the two different designs.  
SESSIONS:  
Well, I'm well aware of that, but that's—that would be part of how you would calculate it. So 
have you calculated it to a dollar- and-cent figure, so you can compare actual cost?  
STACKLEY:  
Yes, sir. In accordance with the different ways in which we would operate the ship, inside of 
the total...  
SESSIONS:  
How much do you calculate for the LCS 1 and the LCS 2? What are the figures for each?  
STACKLEY:  
I would not provide those in an open forum because the respective figures that were used—
that we have used are proprietary. However, we have provided that information through 
other means to the CBO, in forming their report.  
SESSIONS:  
Well, as I would read the CBO report, it would conclude that Navy inadequately scored that.  
But, do I hear you saying you have an actual dollar-and-cent figure that you've used in 
evaluating the life-cycle cost, that now—that the Navy has and is applying to this ship?  
STACKLEY:  
To be exact, we took a look at the total ownership cost for the two competing designs. We 
looked at maintenance, modernization, manpower and fuel consumption. When we look at 
fuel consumption, we have to consider the different ways in which the Navy would operate 
the ship.  
And then we looked at the total ownership costs, side by side, for the two different designs, 
considering different categories for the way the Navy would...  
(CROSSTALK)  
SESSIONS:  
Surely you would have to reduce this variable speed to some sort of a factor that you could 
evaluate in terms of dollars and cents. That’s what CBO said.  
(CROSSTALK)  
SESSIONS:  
It’s been done before, hasn't it?  
Congressional Research Service 
47 
Navy Littoral Combat Ship (LCS) Program 
 
STACKLEY:  
Yes, sir. So as you read through the CBO report, what they point out is, one, there’s a range 
in terms of the percent of the total ownership cost that’s made up by fuel, and also there’s a 
range for how much of an impact the different mission type of operations have on that 
percent. And within that range, you could have one design being better than the other and 
vice versa.  
So, in fact, the outcome of the analysis for total ownership cost is highly sensitive to the way 
that the Navy would operate the ships. And depending on which...  
(CROSSTALK)  
SESSIONS:  
I couldn't agree more. But have you calculated that?  
STACKLEY:  
Yes, sir.  
SESSIONS:  
And you would agree, would you not, that if you didn't properly calculate that, then it could 
be unfair to one competitor or another? 
STACKLEY:  
What I would definitely agree to is that there is a degree of uncertainty around the estimates. 
And so within—when you say not properly calculating it, I would say that the Navy’s 
estimate is not so much of a point estimate, as it is a number plus or minus a certain 
percentage of uncertainty.  
And so, I would not—I would not suggest that we've been unfair to one or the other based on 
that calculation.  
SESSIONS:  
Mr. Stackley, I've not been able to follow those answers. It’s awfully complex to me. It 
would seem to me that you would, if you were buying an automobile, and got better gas 
mileage than another one, you would calculate over the expected life of that car, how many 
dollars you spend on fuel on each one.  
And are you saying that you have done that in this case, and—this competition—and that 
you are prepared at some point to make that public?  
STACKLEY:  
Two things. One, you say, within the competition. The analysis that you are referring to is 
not a part of the award criteria.  
SESSIONS:  
Oh. So—well, then are you going to make it a part of the award evaluation or not?  
Congressional Research Service 
48 
Navy Littoral Combat Ship (LCS) Program 
 
STACKLEY:  
No,  sir.  What  we  do  have  as  a  part  of  the  award  criteria  is  how  to  improve  upon  total 
ownership cost. When we do the analysis of total ownership cost, which includes fuel, and 
we put side by side comparison between the two designs, then the outcome of that analysis is 
entirely dependent on the assumptions you make with regards to how the Navy would 
operate the ship, where the range of operations is entirely within what the LCS will be called 
to perform.  
SESSIONS:  
Well, the CBO, faced with those circumstances, came up with a range, did they not?  
STACKLEY:  
Yes, sir.  
SESSIONS:  
And the range was something like eight to 18.  
STACKLEY:  
It was eight percent to 11 percent for a frigate-type of combatant, which would include an 
LCS.  
SESSIONS:  
And they estimated the moderate range would be 11. That was their guesstimate of—that 
was their estimate of what the...  
STACKLEY:  
Yes, sir.  
SESSIONS:  
... fuel costs should be. Have you used—do you use that figure or a different one?  
STACKLEY:  
We used the baseline figures that we have for the two designs. The other information that the 
CBO pointed toward was the operating regime of the ships, where they would nominally 
spend 95 percent of their time at 16 knots or less, 5 percent of their time north of that speed.  
So you have a range of variability of 5 percent inside of the CBO’s numbers, driven by the 
way you operate the ships, for a cost factor that’s 11 percent of the total ownership cost.  
SESSIONS:  
Well, I would—thank you, Mr. Chairman.  
Congressional Research Service 
49 
Navy Littoral Combat Ship (LCS) Program 
 
I would just say that this is a very serious matter. And I would expect—I'm not able to follow 
your answers, and my concern is that you're not adequately accounting for differences of 
fuel. And I intend to follow it.  
I hope that you conduct this correctly, but if not, I think—I think we would not have had a 
fair competition.54 
                                                             
54 Source: Transcript of hearing. 
Congressional Research Service 
50 
Navy Littoral Combat Ship (LCS) Program 
 
Appendix F. May 2010 Navy Testimony Regarding 
Impact of NLOS-LS Cancellation 
At a May 6, 2010, hearing on Navy shipbuilding programs before the Seapower Subcommittee of 
the Senate Armed Services Committee, Senator Jack Reed questioned Sean Stackley, the Navy’s 
acquisition executive (i.e., the Assistant Secretary of the Navy [Research, Development and 
Acquisition]), and Lieutenant General George Flynn, Deputy Commandant, Combat 
Development and Integration, and Commanding General, Marine Corps Combat Development 
Command, regarding the impact the cancellation of the NLOS-LS program. The following is text 
of the exchange: 
SENATOR REED: 
Let me ask a question, then yield to Senator Wicker. And I might have one more question, 
but going back to the decision about the DDG- 51 versus the DDG-1000. The DDG-1000 
was developed with the principal mission of close fire support for forcible entry, principally 
the Marine Corps.  
Then the Navy made the decision that they could do that by other means, and the more 
pressing need was missile defense, which the DDG- 51 seems more capable. Part of that 
decision, I understand, is the thought that essentially the Navy could adopt an Army system, 
the non- line of sight launch system, NLOS. But now it appears that the Army is getting 
ready to abandon the development of that system, forcing you to have no system or to adopt 
the cost of that system, rather than bootstrapping on the Army. 
So, I'm just, Admiral Blake, if NLOS is canceled, which it appears close to be, what’s your 
backup plan? But more importantly, I'd like everyone to comment on this general topic. 
What are we going to do to ensure close fire support for forcible entry of Marines?  
BLAKE:  
Well, sir, first of all, for the NLOS program, the NLOS was looked at from the Navy 
perspective to go on the LCS. It was going to be a part of the surface package, the surface 
modular package [for the LCS]. It was going to go on there.  
And it was going to be used—one of the missions it was going to be used for was for the 
swarming boat issue. What we are doing right now is because of the Army’s announcement 
that they are potentially looking at terminating the program, we have been—we are going 
back and evaluating for that particular module.  
If, in fact that program is terminated and it is decided that the Navy would not go down that 
path, then what would we have to do in order to meet the key performance parameters for 
that particular module on the LCS.  
REED:  
Thank you. That helps to clarify.  
Can I assume then, Secretary Stackley, to my comment, that the close fire support would be 
provided not by a destroyer, but by the LCS? Is that correct, the operational concept, Mr. 
Secretary?  
Congressional Research Service 
51 
Navy Littoral Combat Ship (LCS) Program 
 
STACKLEY:  
No, sir. There’s a naval surface first support capability. That requirement is met by what is 
called a triad. First, there’s organic artillery, there is air, then there’s naval surface fires. So 
that triad is intended to meet the overarching or capstone requirement.  
And we look at—you started with the DDG-1000 with the advanced con [sic: gun] system 
[the DDG-1000’s 155 mm Advanced Gun System] to [help meet] the overall requirement, 
and we look at other surface ships, basically [the] five-inch 54 [caliber gun], basically which 
is common to the DDG-51 and the [CG-47 class] cruiser. And with the NLOS, we looked at 
a capability that the LCS could further contribute to that [naval surface fire support] 
campaign problem.  
REED:  
General Flynn, since your Marines are going to have to make the forceful entry, you have the 
last word on the whole topic and NLOS, too.  
FLYNN:  
Sir, over a year ago we agreed that the solution, and this was at the same time we were 
examining the DDG-1000, we agreed to look for a joint analysis of alternatives [AOA] to 
determine the way ahead for naval surface fires. A key part of that had, as Secretary Stackley 
said, is our belief in the triad, that no single leg of the triad can meet all the demands of it. 
And we see naval surface fires as providing volume and accuracy as a key part of that triad. 
As part of the joint AOA, we looked at 71 alternatives, and we came down to the six most 
promising. One of them was the NLOS system. If it proved promising, it would have to have 
an extended range, but that was one of the alternatives. And that was one of the areas that we 
were also looking to capitalize on the Navy’s building of the LCS platform.  
If NLOS proves not to be effective, then the only other option that’s available right now is 
the development of the five-inch round, the extended range round for extended use off the 
DDG-81 and higher class [destroyer] hull forms. And that really needs to be upon 12-ish (ph) 
[sic: a POM-12 issue],55 because right now there is no [new] naval surface fire [capability], 
with the exception of the DDG-1000 in the program of record. The next promising or viable 
thing seems to be the extended five-inch range [shell]. And that would meet the 
requirement.56 
                                                             
55 The Program Objective Memorandum, or POM, is an internal DOD document used to develop DOD’s proposed 
budget. POM-12 is the POM for the proposed FY2012 budget that DOD will submit to Congress in February 2011. 
56 Source: Transcript of hearing. 
Congressional Research Service 
52 
Navy Littoral Combat Ship (LCS) Program 
 
Appendix G. Potential for Common Hulls 
Some observers, including some Members of Congress, have expressed interest in the idea of 
using common hulls for Coast Guard cutters and smaller Navy combatants, so as to improve 
economies of scale in the construction of these ships and thereby reduce their procurement costs. 
In earlier years, this interest focused on using a common hull for the LCS and the Offshore Patrol 
Cutter (OPC), a cutter displacing roughly 3,000 tons that is to be procured under the Coast 
Guard’s Deepwater acquisition program.57 More recently, this interest has focused on using a 
common hull for the LCS and the National Security Cutter (NSC), a cutter displacing about 4,300 
tons that is also being acquired under the Deepwater program. This appendix presents information 
regarding the idea of using common hulls for Coast Guard cutters and smaller Navy combatants. 
July 2009 CBO Report 
A July 2009 CBO report examines options for the Navy and Coast Guard to use common hulls for 
some of their ships. The report states that: 
some members of Congress and independent analysts have questioned whether the Navy and 
the Coast Guard need to purchase four different types of small combatants and whether—in 
spite of the services’ well-documented reservations about using similar hull designs—the 
same type of hull could be employed for certain missions. To explore that possibility, the 
Congressional Budget Office (CBO) examined three alternatives to the Navy’s and the Coast 
Guard’s current plans for acquiring littoral combat ships and deepwater cutters. 
•  Option 1 explores the feasibility of having the Coast Guard buy a variant of the Navy’s 
LCS—specifically, the semiplaning monohull—to use as its offshore patrol cutter. 
•  Option 2 examines the effects of reducing the number of LCSs the Navy would buy and 
substituting instead a naval version of the Coast Guard’s national security cutter. (The 
rationale for this option is that, according to some analysts, the NSC’s longer mission 
range and higher endurance might make it better suited than the LCS to act as a “patrol 
frigate,” which would allow the Navy to carry out certain activities—maritime security, 
engagement, and humanitarian operations—outlined in the sea services’ new maritime 
strategy.) 
•  Option 3 examines the advantages and disadvantages of having the Coast Guard buy 
more national security cutters rather than incur the costs of designing and building a 
new ship to perform the missions of an offshore patrol cutter. 
According to CBO’s estimates, all three alternatives and the services’ plans would have 
similar costs, regardless of whether they are calculated in terms of acquisition costs or total 
life-cycle costs (see Table 1).6 CBO’s analysis also indicates that the three alternative plans 
would not necessarily be more cost-effective or provide more capability than the services’ 
existing plans. Specifically, even if the options addressed individual problems that the Navy 
and Coast Guard might confront with their small combatants, it would be at the cost of 
creating new challenges. For instance, Option 1—which calls for using the LCS monohull 
for the Coast Guard’s OPC—would provide less capability for the Coast Guard from that 
                                                             
57 For more on the Deepwater program, see CRS Report RL33753, Coast Guard Deepwater Acquisition Programs: 
Background, Oversight Issues, and Options for Congress, by Ronald O’Rourke. 
Congressional Research Service 
53 
Navy Littoral Combat Ship (LCS) Program 
 
service’s perspective and at a potentially higher cost. Option 2 could provide the Navy with 
capability that, in some respects, would be superior for executing the peacetime elements of 
its maritime strategy; but that enhanced peacetime capability would sacrifice wartime 
capability and survivability. Option 3 would allow the Coast Guard to replace its aging 
cutters more quickly at a slightly higher cost but without the technical risk that is associated 
with designing and constructing a new class of ships, which the service’s existing plan 
entails. It would, however, provide fewer mission days at sea and require the Coast Guard to 
find new home ports for its much larger force of national security cutters.58 
Reported Proposal to Build Variant of NSC for Navy 
In January 2008, it was reported that Northrop Grumman, the builder of the NSC, had submitted 
an unsolicited proposal to the Navy to build a version of the NSC for the Navy as a complement 
to, rather than a replacement for, the LCS. 
January 14, 2008, Press Report 
A press report dated January 14, 2008, stated: 
The U.S. Navy is stumbling to build the ship it wants—the Littoral Combat Ship (LCS)—so 
shipbuilder Northrop Grumman is urging the service to turn to a ship it can get sooner and 
cheaper: a patrol frigate version of the Coast Guard’s National Security Cutter (NSC). 
“We have listened to what the Navy has said—to be more efficient, be innovative and 
produce affordable and capable ships,” said Phil Teel, president of Northrop’s Ship Systems 
sector. “The patrol frigate is a response to that, and to the Navy’s new National Maritime 
Strategy.” 
Northrop’s analysts have studied remarks and themes oft repeated by senior Navy leaders 
and concluded a de facto requirement exists for a frigate-size ship capable of handling a 
range of low- and mid-intensity missions. Those missions, said Eric Womble, head of Ship 
Systems’ Advanced Capabilities Group, are detailed in the Navy’s new Maritime Strategy 
and include forward presence, deterrence, sea control, maritime security, humanitarian 
assistance and disaster response. 
“You don’t want a high-end Aegis ship to handle those missions,” Womble said, “you want 
something cheaper and smaller.” 
The National Security Cutter (NSC) as configured for the Coast Guard could easily handle 
those roles, Womble said. 
The first NSC, the Bertholf, successfully carried out its initial trials in early December and 
will be commissioned this year by the Coast Guard. Womble said a Navy version would 
avoid the first-of-class issues that have plagued numerous Navy programs, including both 
designs being built for the LCS competition. 
Northrop in late December began briefing select Navy leaders on its unsolicited proposal. 
The company is taking pains to avoid presenting the ship as an LCS alternative, instead 
                                                             
58 Congressional Budget Office, Options for Combining the Navy’s and the Coast Guard’s Small Combatant Programs, 
July 2009, p. 2. 
Congressional Research Service 
54 
Navy Littoral Combat Ship (LCS) Program 
 
calling it an LCS “complement,” which is being built under a competition between Lockheed 
Martin and General Dynamics. 
Key features of Northrop’s concept are: 
—The ship is based on a proven design already under construction. 
—The NSC’s weapons, sensors and systems already have a high degree of commonality with 
Navy systems, increasing affordability. 
—While the NSC is 15 knots slower than the 45-knot LCS, the cutter can stay at sea up to 
two months, much longer than the LCS. 
The report also stated: 
Northrop is claiming it can deliver the first ship at the end of 2012 at an average cost of less 
than $400 million per ship, exclusive of government-furnished equipment, in fiscal 2007 
dollars. That’s close to the $403 million contract cost of the third NSC, which incorporates 
all current design upgrades. 
A major element of Northrop’s proposal, Womble said, is that the Navy should make no 
changes to the current Block 0 design. “That’s the only way we can deliver the ship at this 
price.” 
The design, however, has plenty of room for upgrades, Womble claimed, and Northrop is 
proposing future upgrades be handled in groups, or blocks, of ships, rather than modifying 
individual ones. Those upgrades could include non-line-of-sight missiles, SeaRAM missile 
launchers and more capabilities to handle unmanned systems. The design even has room for 
an LCS-like reconfigurable mission area under the flight deck, he claimed. 
Northrop admits the ships are deficient in one significant Navy requirement: full 
compatibility with the Naval Vessel Rules (NVR), essentially building codes developed by 
the Naval Sea Systems Command and the American Bureau of Shipping. The belated 
application of the NVR to both LCS designs was a major factor in the cost growth on those 
ships. 
Most of the NSC design already is NVR-compatible, Womble said, but upgrading the entire 
design to NVR standards would involve a fundamental redesign and eliminate the proposal’s 
cost and construction time attributes. 
“We’d need a waiver [from the NVR rules] to make this proposal work,” he said. 
The report also stated: 
Navy Response: ‘No Requirement’ 
The official response from the Navy to Northrop’s proposal so far is unenthusiastic. 
“There is currently no requirement for such a combatant,” said Lt. Clay Doss, a Navy 
spokesman at the Pentagon. The Navy’s other surface ship programs, he said, “address 
specific requirements.” 
Congressional Research Service 
55 
Navy Littoral Combat Ship (LCS) Program 
 
Doss did note that “the Navy and Coast Guard have considered a common platform for the 
LCS and the Coast Guard’s National Security Cutter. However, due to the unique mission 
requirements of each service, a common hull is not a likely course of action.” 
Problems with the LCS have caused some observers to predict the program’s demise, but the 
Navy “is completely committed to the LCS program,” Doss said. “We need 55 Littoral 
Combat Ships sooner rather than later, and we need them now to fulfill critical, urgent war-
fighting gaps.” 
Northrop however, is not alone in proposing the NSC as an LCS alternative. Coast Guard 
Capt. James Howe, writing in the current issue of the U.S. Naval Institute’s Proceedings 
magazine, is urging Navy leaders to consider the NSC. 
“I think the Navy should look at it,” he said Jan. 10. “Northrop is building a naval combatant 
here. It has standard U.S. Navy weapon systems as part of its packages. Its communications 
are interoperable. It can handle underway replenishment. If there’s a possibility it could be a 
cost saver or a good deal for the Navy, it needs to be explored.” 
Howe, who said he was unaware of Northrop’s patrol frigate proposal, agreed the NSC is 
capable of further enhancements. “There’s a lot of space on that ship,” he said. 
‘Potential Game-changer’ 
Northrop likely is facing an uphill battle with its patrol frigate, as the Navy culturally prefers 
to dictate requirements based on its own analysis. 
But the Navy is having trouble defending the affordability of its shipbuilding plan to 
Congress and bringing programs in on budget. One congressional source noted the service 
“can’t admit their plan won’t work.” An unsolicited proposal, the source said, “opens the 
way for someone else to come up with a potential game-changer.” 
Northrop’s plan, the source said, may be an unexpected opportunity. 
“Northrop is listening to the people who have been criticizing the Navy’s shipbuilding plan,” 
the source said. “They’ve gotten a sense that maybe the Navy is looking for a solution, and 
the Navy can’t produce a solution because it might be too embarrassing.” 
One more aspect that could be at work in the Northrop proposal: “I think there’s something 
coy going on here,” the source said. “They may be promoting this as an LCS complement, 
but their idea might be part of a strategic plan to replace the LCS.”59 
January 17, 2008, Press Report 
A press report dated January 17, 2008, stated: 
Northrop Grumman Corp said on Wednesday [January 16, 2008, that] a proposal to turn its 
418-foot Coast Guard cutter into a new class of Navy frigates is sparking some interest 
among U.S. Navy officials and lawmakers. 
                                                             
59 Christopher P. Cavas, “Northrop Offers NSC-Based Vessel To Fill LCS Delays,” Defense News, January 14, 2008. 
Congressional Research Service 
56 
Navy Littoral Combat Ship (LCS) Program 
 
Northrop is offering the Navy a fixed price for the new ship of under $400 million and could 
deliver the first one as early as 2012 to help out with maritime security, humanitarian aid and 
disaster response, among other things, said Eric Womble, vice president of Northrop 
Grumman Ship Systems. 
So far, the officials briefed have found Northrop’s offer “intriguing,” Womble told Reuters 
in an interview. “They like the fact that we’re putting an option on the table. No one has told 
us, ‘Go away, don’t come back, we don’t want to hear this’,” Womble said. 
At the same time, the Navy says it remains committed to another class of smaller, more agile 
ships—the Littoral Combat Ships (LCS) being built by Lockheed Martin Corp (LMT.N: 
Quote, Profile, Research) and General Dynamics Corp (GD.N: Quote, Profile, Research)—
amid huge cost overruns. 
“There currently is no requirement for a frigate,” Navy spokesman Lt. Clay Doss said. He 
said the Navy and Coast Guard had discussed a common hull during the initial stage of the 
LCS competition, but agreed that was “not a likely course of action due to the unique 
mission capabilities.” 
For now, he said the Navy was proceeding as quickly as it could with the 55-ship LCS 
program as well as design work on a new DDG-1000 destroyer, and a planned cruiser, CG-
X.... 
The report also stated: 
Virginia-based defense consultant Jim McAleese said the fixed-price offer could be good 
news for the Navy, which has typically borne the risk of cost-based shipbuilding contracts. 
“That is a potential catalyst that could have a huge impact on the way the Navy buys small- 
and mid-sized surface combatants,” McAleese said. 
Northrop says its new Coast Guard cutter also experienced some cost growth, but says that 
was mainly due to requirements added after the Sept. 11, 2001, hijacking attacks. The first of 
the new ships is due to be delivered to the Coast Guard in March, followed by one ship 
annually over the next few years. 
Northrop said it could offer the Navy a fixed price on the frigate because design work on the 
ships is already largely completed. Its price excludes government-furnished equipment that 
would still have to be put on board. 
“We’re not advocating an LCS replacement,” said spokesman Randy Belote. “But after 
listening to the Navy leadership and studying the new maritime strategy, we think we can get 
hulls and capabilities into the water at a much faster pace.” 
Womble said Northrop analysts and an outside consultant studied the Navy’s needs and 
concluded the Navy could use another ship that can operate in shallow water, be forward 
deployed, has the range and endurance to operate independently, and can work with U.S. 
allies, if needed. 
The press report also stated: 
The proposed ship can be deployed for 60 days without new supplies, has a range of 12,000 
nautical miles, and can travel at 29 knots, fast enough to keep up with other warships. That 
compares to 20 days and a range of 3,500 miles for LCS. 
Congressional Research Service 
57 
Navy Littoral Combat Ship (LCS) Program 
 
Northrop began sharing a PowerPoint presentation about the proposal with Navy officials 
and lawmakers at the end of December, and has already met with several senior officials, 
including Chief of Naval Operations Adm. Gary Roughead. 
It could deliver the first frigate by 2012, if the Navy was able to add $75 million for long 
lead procurement items into the fiscal 2009 budget proposal to be sent to Congress next 
month, Northrop said. 
The frigate is about 75 percent compliant with special requirements that apply only to U.S. 
Navy ships. Northrop said it believed it could qualify for waivers on the remaining 25 
percent because similar waivers were granted in the past.60 
 
Author Contact Information 
 
Ronald O'Rourke 
   
Specialist in Naval Affairs 
rorourke@crs.loc.gov, 7-7610 
 
 
                                                             
60 Andrea Shalal-Esa, “Northrop Offers US Navy New Ship For Fixed Price,” Reuters, January 17, 2008. 
Congressional Research Service 
58