Navy Ford (CVN-78) Class Aircraft Carrier
Program: Background and Issues for Congress

Ronald O'Rourke
Specialist in Naval Affairs
February 16, 2010
Congressional Research Service
7-5700
www.crs.gov
RS20643
CRS Report for Congress
P
repared for Members and Committees of Congress

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Summary
CVN-78, CVN-79, and CVN-80 are the first three ships in the Navy’s new Gerald R. Ford (CVN-
78) class of nuclear-powered aircraft carriers (CVNs).
CVN-78 was procured in FY2008 and is being funded with congressionally authorized four-year
incremental funding in FY2008-FY2011. The Navy’s proposed FY2011 budget estimates the
ship’s procurement cost at $11,531.0 million (i.e., about $11.5 billion) in then-year dollars, and
requests $1,731.3 million in procurement funding as the final increment to complete this
estimated procurement cost.
CVN-79 is scheduled for procurement in FY2013, and has received advance procurement funding
since FY2007. The Navy’s proposed FY2011 budget estimates the ship’s procurement cost at
$10,413.1 million (i.e., about $10.4 billion) in then-year dollars and requests $908.3 million in
advance procurement funding for the ship.
CVN-80 is scheduled for procurement in FY2018, with advance procurement funding scheduled
to begin in FY2014. The Navy’s proposed FY2011 budget estimates the ship’s procurement cost
at $13,577.0 million (i.e., about $13.6 billion) in then-year dollars.
On April 6, 2009, Secretary of Defense Robert Gates announced a number of recommendations
he was making for the FY2010 defense budget. One of these was to shift procurement of carriers
to five-year intervals. This recommendation effectively deferred the scheduled procurement of
CVN-79 from FY2012 to FY2013, and the scheduled procurement of CVN-80 from FY2016 to
FY2018. Secretary of Defense Robert Gates stated on April 6, 2009, that shifting carrier
procurement to five-year intervals would put carrier procurement on “a more fiscally sustainable
path.”
Potential oversight issues for Congress for FY2011 for the CVN-78 program include the
following:
• Did shifting carrier procurement to five-year intervals put carrier procurement on
a more fiscally sustainable path?
• Where do the estimated procurement costs of CVNs 78, 79, and 80 stand in
relation to the unit procurement cost caps for the CVN-78 program that were
established by Section 122 of the FY2007 defense authorization act (H.R.
5122/P.L. 109-364 of October 17, 2006)?
• What is the likelihood that the estimated procurement costs of CVNs 78, 79, and
80 will increase from the estimates shown in the FY2011 budget?
Congressional Research Service

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Contents
Introduction ................................................................................................................................ 1
Background ................................................................................................................................ 2
The Navy’s Aircraft Carrier Force ......................................................................................... 2
Aircraft Carrier Construction Industrial Base......................................................................... 2
Gerald R. Ford (CVN-78) Class Program .............................................................................. 2
CVN-78 .......................................................................................................................... 2
CVN-79 .......................................................................................................................... 3
CVN-80 .......................................................................................................................... 3
Procurement Funding ...................................................................................................... 4
Increase in Estimated Unit Procurement Costs................................................................. 4
Procurement Cost Cap..................................................................................................... 5
Issues for Congress ..................................................................................................................... 6
Shift to Five-Year Intervals: A More Fiscally Sustainable Path?............................................. 6
Estimated Procurement Costs in Relation to Procurement Cost Cap....................................... 9
Potential for Additional Growth in Estimated Procurement Costs .......................................... 9
Legislative Activity for FY2011 ................................................................................................ 11

Tables
Table 1. Procurement Funding for CVNs 78, 79, and 80 .............................................................. 4
Table 2. Estimated Procurement Costs of CVNs 78, 79, and 80 ................................................... 5

Appendixes
Appendix. July 16, 2009, Hearing on EMALS........................................................................... 12

Contacts
Author Contact Information ...................................................................................................... 17

Congressional Research Service

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Introduction
CVN-78, CVN-79, and CVN-80 are the first three ships in the Navy’s new Gerald R. Ford (CVN-
78) class of nuclear-powered aircraft carriers (CVNs).
CVN-78 was procured in FY2008 and is being funded with congressionally authorized four-year
incremental funding in FY2008-FY2011. The Navy’s proposed FY2011 budget estimates the
ship’s procurement cost at $11,531.0 million (i.e., about $11.5 billion) in then-year dollars, and
requests $1,731.3 million in procurement funding as the final increment to complete this
estimated procurement cost.
CVN-79 is scheduled for procurement in FY2013, and has received advance procurement funding
since FY2007. The Navy’s proposed FY2011 budget estimates the ship’s procurement cost at
$10,413.1 million (i.e., about $10.4 billion) in then-year dollars and requests $908.3 million in
advance procurement funding for the ship.
CVN-80 is scheduled for procurement in FY2018, with advance procurement funding scheduled
to begin in FY2014. The Navy’s proposed FY2011 budget estimates the ship’s procurement cost
at $13,577.0 million (i.e., about $13.6 billion) in then-year dollars.
On April 6, 2009, Secretary of Defense Robert Gates announced a number of recommendations
he was making for the FY2010 defense budget. One of these was to shift procurement of carriers
to five-year intervals. This recommendation effectively deferred the scheduled procurement of
CVN-79 from FY2012 to FY2013, and the scheduled procurement of CVN-80 from FY2016 to
FY2018. Secretary of Defense Robert Gates stated on April 6, 2009, that shifting carrier
procurement to five-year intervals would put carrier procurement on “a more fiscally sustainable
path.”1
Potential oversight issues for Congress for FY2011 for the CVN-78 program include the
following:
• Did shifting carrier procurement to five-year intervals put carrier procurement on
a more fiscally sustainable path?
• Where do the estimated procurement costs of CVNs 78, 79, and 80 stand in
relation to the unit procurement cost caps for the CVN-78 program that were
established by Section 122 of the FY2007 defense authorization act (H.R.
5122/P.L. 109-364 of October 17, 2006)?
• What is the likelihood that the estimated procurement costs of CVNs 78, 79, and
80 will increase from the estimates shown in the FY2011 budget?

1 Source: Statement of Secretary of Defense Robert Gates, at April 6, 2009, news conference on his recommendations
for the FY2010 defense budget.
Congressional Research Service
1

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Background
The Navy’s Aircraft Carrier Force
The Navy’s aircraft carrier force consists of 11 nuclear-powered ships—the one-of-a-kind
Enterprise (CVN-65) and 10 Nimitz-class ships (CVNs 68 through 77). The most recently
commissioned carrier, the George H. W. Bush (CVN-77), the final Nimitz-class ship, was
procured in FY2001 and commissioned into service on January 10, 2009.2 CVN-77 replaced the
Kitty Hawk (CV-63), which was the Navy’s last remaining conventionally powered carrier.3
Aircraft Carrier Construction Industrial Base
All U.S. aircraft carriers procured since FY1958 have been built by the Newport News, VA,
shipyard that forms part of Northrop Grumman Shipbuilding (NGSB). NGSB’s Newport News
yard is the only U.S. shipyard that can build large-deck, nuclear-powered aircraft carriers. The
aircraft carrier construction industrial base also includes hundreds of subcontractors and suppliers
in dozens of states.
Gerald R. Ford (CVN-78) Class Program
The Gerald R. Ford (CVN-78) class carrier design is the successor to the Nimitz-class carrier
design.4 Compared to the Nimitz-class design, the Ford-class design will incorporate several
improvements, including an ability to generate substantially more aircraft sorties per day and
features permitting the ship to be operated by several hundred fewer sailors than a Nimitz-class
ship, significantly reducing life-cycle operating and support costs. Navy plans call for procuring
at least three Ford-class carriers—CVN-78, CVN-79, and CVN-80.
CVN-78
CVN-78, which was named in 2007 for president Gerald R. Ford,5 was procured in FY2008 and
is being funded with congressionally authorized four-year incremental funding in FY2008-

2 Congress approved $4,053.7 million in FY2001 procurement funding to complete CVN-77’s then-estimated total
procurement cost of $4,974.9 million. Section 122 of the FY1998 defense authorization act (H.R. 1119/P.L. 105-85 of
November 18, 1997) limited the ship’s procurement cost to $4.6 billion, plus adjustments for inflation and other
factors. The Navy testified in 2006 that with these permitted adjustments, the cost cap stood at $5.357 billion. The
Navy also testified that CVN-77’s estimated construction cost had increased to $6.057 billion, or $700 million above
the adjusted cost cap. Consequently, the Navy in 2006 requested that Congress increase the cost cap to $6.057 billion.
Congress approved this request: Section 123 of the FY2007 defense authorization act (H.R. 5122/P.L. 109-364 of
October 17, 2006), increased the cost cap for CVN-77 to $6.057 billion.
3 The Kitty Hawk was decommissioned on January 31, 2009.
4 The CVN-78 class was earlier known as the CVN-21 class, which meant nuclear-powered aircraft carrier for the 21st
century.
5 Section 1012 of the FY2007 defense authorization act (H.R. 5122/P.L. 109-364 of October 17, 2006) expressed the
sense of the Congress that CVN-78 should be named for president Gerald R. Ford. On January 16, 2007, the Navy
announced that CVN-78 would be so named. CVN-78 and other carriers built to the same design will consequently be
referred to as Ford (CVN-78) class carriers. For further discussion of Navy ship names, see CRS Report RS22478,
Navy Ship Names: Background for Congress, by Ronald O’Rourke.
Congressional Research Service
2

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

FY2011.6 The Navy’s proposed FY2011 budget estimates the ship’s procurement cost at
$11,531.0 million (i.e., about $11.5 billion) in then-year dollars, and requests $1,731.3 million in
procurement funding as the final increment to complete this estimated procurement cost.
CVN-78 is scheduled to enter service as the replacement for Enterprise (CVN-65). The Navy
projects that there will be a 33-month period between the scheduled decommissioning of
Enterprise in November 2012 and the scheduled commissioning of CVN-78 in September 2015.
During this 33-month period, the Navy’s carrier force is to temporarily decline from 11 ships to
10 ships. Since 10 USC 5062(b) requires the Navy to maintain a force of at least 11 operational
carriers, the Navy asked Congress for a temporary waiver of 10 USC 5062(b) to accommodate
the 33-month period between the scheduled decommissioning of Enterprise and the scheduled
commissioning of CVN-78. Section 1023 of the FY2010 defense authorization act (H.R.
2647/P.L. 111-84 of October 28, 2009) authorizes the waiver and requires the Secretary of
Defense to submit a report on the operational risk of temporarily reducing the size of the carrier
force.
CVN-79
CVN-79 is scheduled for procurement in FY2013, and has received advance procurement funding
since FY2007. The Navy’s proposed FY2011 budget estimates the ship’s procurement cost at
$10,413.1 million (i.e., about $10.4 billion) in then-year dollars and requests $908.3 million in
advance procurement funding for the ship.
In the FY2009 budget, CVN-79 was scheduled to be procured in FY2012. On April 6, 2009,
Secretary of Defense Robert Gates announced a number of recommendations he was making for
the FY2010 defense budget. One of these was to shift procurement of carriers to five-year
intervals. Since CVN-78 was procured in FY2008, this recommendation effectively deferred the
scheduled procurement of CVN-79 from FY2012 to FY2013. Secretary of Defense Robert Gates
stated that shifting carrier procurement to five-year intervals would put carrier procurement on “a
more fiscally sustainable path.”7
CVN-80
CVN-80 is scheduled for procurement in FY2018, with advance procurement funding scheduled
to begin in FY2014. The Navy’s proposed FY2011 budget estimates the ship’s procurement cost
at $13,577.0 million (i.e., about $13.6 billion) in then-year dollars. Secretary of Defense Gates’
April 2009 recommendation to shift carrier procurement to five-year intervals (see above
discussion of CVN-79) effectively deferred the procurement of CVN-80 from FY2016 to
FY2018.

6 The use of four-year incremental funding is consistent with Section 121 of the FY2007 defense authorization act
(H.R. 5122/P.L. 109-364 of October 17, 2006), which granted the Navy the authority to use four-year incremental
funding for CVN-78, CVN-79, and CVN-80.
7 Source: Statement of Secretary of Defense Robert Gates, at April 6, 2009, news conference on his recommendations
for the FY2010 defense budget.
Congressional Research Service
3

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Procurement Funding
Table 1 shows procurement funding for CVNs 78, 79, and 80. Each ship is being procured with
several years of advance procurement funding, followed by four-year incremental procurement
funding of the remainder of the ship’s cost. The funding profile for CVN-78, for example,
includes advance procurement funding in FY2001-FY2007, followed by four years of
incremental procurement funding in FY2008-FY2011.
Table 1. Procurement Funding for CVNs 78, 79, and 80
Millions of then-year dollars, rounded to nearest tenth – figures may not add due to rounding)
FY
CVN-78 CVN-79 CVN-80 Total
FY01 21.7 0 0 21.7
FY02 135.5 0 0 135.5
FY03 395.5 0 0 395.5
FY04 1,162.9 0
0 1,162.9
FY05 623.1 0 0 623.1
FY06 618.9 0 0 618.9
FY07 735.8 52.8 0 788.6
FY08 2,685.0
123.5 0 2,808.5
FY09 2,684.6
1,210.6 0 3,895.2
FY10 737.0
482.9 0 1,219.9
FY11 (requested)
1,731.3
908.3
0
2,639.6
FY12 (projected)
0
494.8
0
494.8
FY13
(projected)
0 2,418.3 0 2,418.3
FY14
(projected) 0 3,158.5 228.1 3,386.6
FY15 (projected)
0
760.7
1,523.8
2,284.5
Source: FY2009, FY2010, and FY2011Navy budget submissions.
Increase in Estimated Unit Procurement Costs
As shown in Table 2, the estimated procurement costs of CVNs 78, 79, and 80 in the FY2011
budget submission are 10.3%, 13.3%, and 26.7% higher, respectively, than those in the FY2009
budget submission.


Congressional Research Service
4

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Table 2. Estimated Procurement Costs of CVNs 78, 79, and 80
As shown in FY2009, FY2010, and FY2011 budgets, in millions of then-year dollars
Budget CVN-78
CVN-79
CVN-80

Estimated
Scheduled
Estimated
Scheduled
Estimated
Scheduled
procurement
fiscal year of
procurement
fiscal year of
procurement
fiscal year of
cost
procurement
cost
procurement
cost
procurement
FY09
budget
10,457.9 FY08 9,191.6 FY12 10,716.8 FY16
FY10 budget
10,845.8
FY08
n/aa FY13b n/aa FY18b
FY11
budget
11,531.0 FY08 10,413.1 FY13 13,577.0 FY18
%
increase:

FY09 budget
3.7 n/a n/a
to FY10 budget
FY10 budget to
6.3 n/a n/a
FY11 budget
FY09 budget to
10.3 13.3 26.7
FY11 budget
Source: FY2009, FY2010, and FY2011Navy budget submissions.
a. n/a means not available – the FY2010 budget submission did not show estimated procurement costs for
CVNs 79 and 80.
b. The FY2010 budget submission did not show scheduled years of procurement for CVNs 79 and 80; the
dates shown here for the FY2010 budget submission are inferred from the shift to five-year intervals for
procuring carriers that was announced by Secretary of Defense Gates in his April 6, 2009, news conference
regarding recommendations for the FY2010 defense budget.
The increases in the estimated procurement costs of CVNs 78, 79, and 80 since the FY2009
budget submission have at least four potential causes:
• one additional year of inflation being incorporated into the cost of CVN-79 as a
result of its scheduled procurement being deferred from FY2012 to FY2013, and
two years of additional inflation being incorporated into the cost of CVN-80 as a
result of its scheduled procurement being deferred from FY2016 to FY2018;
• increases in projected annual rates of inflation;
• higher estimates of real (i.e., inflation-adjusted) material costs, real labor rates, or
labor hours (given a certain position on the production learning curve) for
building CVN-78 class carriers;
• increased costs due to loss of learning and reduced spreading of fixed overhead
costs resulting from shifting to five-year intervals for procuring carriers.
Procurement Cost Cap
Section 122 of the FY2007 defense authorization act (H.R. 5122/P.L. 109-364 of October 17,
2006) established a procurement cost cap for CVN-78 of $10.5 billion, plus adjustments for
inflation and other factors, and a procurement cost cap for subsequent Ford-class carriers of $8.1
billion each, plus adjustments for inflation and other factors. The conference report (H.Rept. 109-
702 of September 29, 2006) on P.L. 109-364 discusses Section 122 on pages 551-552.
Congressional Research Service
5

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Issues for Congress
Potential oversight issues for Congress for FY2011 for the CVN-78 program include the
following:
• Did shifting carrier procurement to five-year intervals put carrier procurement on
a more fiscally sustainable path?
• Where do the estimated procurement costs of CVNs 78, 79, and 80 stand in
relation to the unit procurement cost caps for the CVN-78 program that were
established by Section 122 of the FY2007 defense authorization act (H.R.
5122/P.L. 109-364 of October 17, 2006)?
• What is the likelihood that the estimated procurement cost of CVN-78, CVN-79,
or CVN-80 will increase from the estimates shown in the FY2011 budget?
Each of these issues is discussed below.
Shift to Five-Year Intervals: A More Fiscally Sustainable Path?
As mentioned earlier, when Secretary of Defense Gates announced on April 6, 2009, that he was
recommending that carrier procurement be shifted to five-year intervals, he stated that this would
put carrier procurement on “a more fiscally sustainable path.” This was interpreted as meaning
that shifting to five-year intervals (compared to a previous combination of four- and five-year
intervals in Navy 30-year shipbuilding plans) would reduce the average amount of funding
required each year for procuring carriers.
As a simplified notional example, if carriers are assumed to cost $10 billion each, then shifting
from a four-year interval to a five-year interval would reduce the average amount of carrier
procurement funding needed each year from $2.5 billion to $2.0 billion, a reduction of $500
million per year.
This simplified notional example, however, assumes that shifting from four- to five-year intervals
does not by itself cause an increase in the procurement cost of the carriers. Increasing the
procurement interval could by itself increase the procurement cost of the carriers by causing
reduced learning-curve benefits (i.e., loss of learning) from one carrier to the next, and by
reducing the spreading of fixed overhead costs at the Newport News shipyard and at supplier
firms. An increase in carrier procurement costs due to such effects would offset at least some of
the reduction in the average amount of carrier procurement funding needed each year that would
result from shifting to five-year intervals.
Shifting to five-year intervals for procuring carriers could also increase the costs of other Navy
ship programs. NGSB’s Newport News shipyard performs mid-life nuclear refueling complex
overhauls (RCOHs) on Nimitz-class carriers, and jointly builds Virginia-class nuclear-powered
attack submarines along with another shipyard (General Dynamics’ Electric Boat Division). In
addition, vendors that make nuclear-propulsion components for carriers make analogous
components for nuclear-powered submarines. A reduced spreading of fixed costs at NGSB’s
Newport News yard and at nuclear-propulsion component vendors due to the shift to five-year
intervals for carrier procurement might thus also increase costs for Nimitz-class RCOHs and
Virginia-class submarines. Increases in costs for these programs would further offset the
Congressional Research Service
6

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

reduction in the average amount of carrier procurement funding needed each year that would
result from shifting to five-year intervals for carrier procurement.
The Navy in July 2009 estimated on a preliminary basis that increasing the carrier procurement
interval to five years could increase the procurement cost of each Virginia-class submarine by $20
million to $50 million. The Navy stated:
The Navy is currently assessing the impact of the proposed shift to 5 year centers for CVN
construction, however in general the cost per ship would increase due to workload
reallocation at the Northrop Grumman Shipbuilding (NGSB) facility in Newport News, VA.
The increased cost per ship, is due to overhead reallocation for labor and materials, includes
impacts to the shipbuilder’s cost as well as the cost impact on Government Furnished
Equipment. The actual cost increase of each ship varies, and is being evaluated as part of
FY11 budget deliberations. The preliminary expected impact to individual Virginia Class
submarines varies between $20M and $50M per hull across the program.8
Since Navy plans call for procuring two Virginia-class submarines per year starting in FY2011,
the increase for the Virginia-class program might, on this basis, be $40 million to $100 million
per year in FY2011 and subsequent years.
A May 2009 Northrop Grumman Shipbuilding statement on the cost impact of shifting to five-
year intervals for procuring carriers states:
One element of the announcement by the Secretary of Defense last week was to shift from
four (4) years to five (5) years between construction start for each new Ford Class carrier.
Past Northrop Grumman Shipbuilding experience with carrier new construction has shown
that the optimum time between carrier construction is less than 4 years. This allows the most
efficient flow of the work force from one ship to the next, and facilitates a learning curve for
carriers. Moving to five (5) year intervals between starts will require the shipyard to sub-
optimize manning level sequencing and result in added trade training, loss of learning, and
added startup costs.
Increasing the time between carrier construction can have a large impact on the supplier
base, driving cost increases of 5-10 percent, or higher in some cases, above normal
escalation. Material costs of suppliers who provide similar components to other Navy
programs currently under contract will also experience cost growth. Some equipment
suppliers can be expected to exit the market as a result of the additional year with the
expense of component requalification being realized.
Finally, the decrease in production labor volume on an annual basis, created by the increase
in the time interval between carrier construction starts will increase the cost to other
programs in the yard. This applies to work already under contract, namely Virginia class
submarines (VCS) Block 2 and Block 3, and CVN 78 predominately; and for future work not
yet under contract, namely Carrier RCOH’s, CVN79 and follow-on Ford class carrier
construction, and later Blocks of VCS. The impact to work already under contract is
expected to be in the range of $100M of cost growth. We also expect cost increases for
future contracts yet to be priced. Conservative projections of the shipbuilder cost impact to

8 Navy information paper dated July 15, 2009, on the subject “5 Year Centers for CVN, Impact on VIRGINIA Class,”
provided to CRS by Navy Office of Legislative Affairs.
Congressional Research Service
7

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

CVN 79 and CVN80 for the one year delay will be on the order of a 9-15 percent cost
increase.9
Potential key oversight questions for Congress for FY2011 include the following:
• How much of the increase since the FY2009 budget submission in the estimated
procurement costs of CVNs 78, 79, and 80 (see Table 2) is due to the shift to
five-year intervals for procuring carriers?
• How do potential increases in the costs of CVN-78 class aircraft carriers, Nimitz-
class RCOHs, and Virginia-class submarines caused by the shift to five-year
intervals for procuring carriers affect the calculation of the net change in average
annual funding requirements that results from shifting carrier procurement to
five-year intervals?
Section 126 of the FY2010 defense authorization act (H.R. 2647/P.L. 111-84 of October 28,
2009) requires the Secretary of the Navy to submit a report to the congressional defense
committees on the effects of using a five-year interval for the construction of Ford-class aircraft
carriers. The text of Section 126 is as follows:
SEC. 126. FORD-CLASS AIRCRAFT CARRIER REPORT.
Not later than February 1, 2010, the Secretary of the Navy shall submit to the congressional
defense committees a report on the effects of using a five-year interval for the construction of
Ford-class aircraft carriers. The report shall include, at a minimum, an assessment of the
effects of such five-year interval on the following:
(1) With respect to the supplier base—
(A) the viability of the base, including suppliers exiting the market or other potential
reductions in competition; and
(B) cost increases to the Ford-class aircraft carrier program.
(2) Training of individuals in trades related to ship construction.
(3) Loss of expertise associated with ship construction.
(4) The costs of—
(A) any additional technical support or production planning associated with the start of
construction;
(B) material and labor;
(C) overhead; and
(D) other ship construction programs, including the costs of existing and future contracts.

9 Northrop Grumman Shipbuilding statement dated May 1, 2009, entitled “NGSB Statement Regarding Extending the
Time Interval between New Build Starts For the Ford Class of Aircraft Carriers,” provided to CRS by Northrop
Grumman.
Congressional Research Service
8

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Regarding Section 126, the conference report (H.Rept. 111-288 of October 7, 2009) on H.R.
2647/P.L. 111-84 states:
Ford-class aircraft carrier report (sec. 126)
The House bill contained a provision (sec. 122) that would require the Secretary of the Navy
to make an assessment of the cost of shifting to 5-year intervals for the construction of
aircraft carriers, including the effect of such shifting of that interval on other programs. The
House bill would have placed a limitation on the use of any funds for the aircraft carrier,
designated CVN–79, for shifting to a 5-year interval.
The Senate amendment contained no similar provision.
The Senate recedes with an amendment that would remove the limitation on the use of funds
for CVN–79.
The conferees note that a 5-year interval for aircraft carrier construction, as proposed by the
Secretary of Defense, may be the appropriate course of action for the Department of the
Navy. However, the conferees are concerned that this decision may not have been made
following a rigorous cost-benefit analysis. Therefore, the conferees expect that the Secretary
of the Navy will take no further action to preclude the ability of the Secretary to award a
construction contract for CVN–79 in fiscal year 2012 or the aircraft carrier designated CVN–
80 in fiscal year 2016, consistent with the Annual Long-Range Plan for Construction of
Naval Vessels for Fiscal Year 2009, until he completes the required assessment and fully
informs the congressional defense committees of any such a decision. (Page 680)
Estimated Procurement Costs in Relation to Procurement Cost Cap
A second potential oversight issue for Congress for the CVN-78 program concerns where the
estimated procurement costs of CVNs 78, 79, and 80 as shown in the FY2011 budget stand in
relation to the unit procurement cost caps for the CVN-78 program that were established by
Section 122 of the FY2007 defense authorization act (H.R. 5122/P.L. 109-364 of October 17,
2006). As mentioned earlier (see “Procurement Cost Cap” in the “Background” section), the cost
caps established by Section 122 can be adjusted upward to take into account inflation and other
factors.
Potential for Additional Growth in Estimated Procurement Costs
A third potential oversight issue for Congress for the CVN-78 program concerns the likelihood
that the estimated procurement costs of CVNs 78, 79, or 80 will increase from the estimates
shown in the FY2011 budget. One possible source of additional cost growth in CVN-78 is new
technologies that are being developed for the ship, particularly the electromagnetic aircraft launch
system (EMALS)—an electromagnetic (as opposed to the traditional steam-powered) aircraft
catapult. Problems in developing EMALS or other technologies could delay the ship’s completion
and increase its development and/or procurement cost. GAO reported in March 2009 that:
Nine of the CVN 21 program’s 14 critical technologies are not yet fully mature. Of these
technologies, EMALS, the advanced arresting gear, and the dual band radar present the
greatest risk to the ship’s cost and schedule. Problems during EMALS development have
already resulted in cost growth and schedule delays. In order to meet CVN 78’s delivery
date, the Navy adopted a strategy that will test, produce, and ultimately install EMALS with
Congressional Research Service
9

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

a high degree of concurrency. In September 2008, the contractor completed the first round of
high-cycle testing, gaining confidence in the performance of the generator—a source of past
problems. Contractor-led integrated land-based system testing will not be complete until the
end of fiscal year 2011—2-years later than estimated in December 2007. Assuming no
further delays, EMALS will not demonstrate full performance of a shipboard ready system
until at least 7 months after installation on CVN 78 has begun. The advanced arresting gear
has completed early verification tests that proved the system’s concept. Integrated land-based
testing with both simulated and live aircraft has slipped by one year since last year’s
assessment and is now scheduled for 2010. The Navy recently postponed delivery of the
arresting gear to the shipyard. Consequently, the shipbuilder will not install the gear prior to
laying the flight deck—a less optimal and more costly approach to building the ship. The
dual band radar—which includes the volume search and multifunction radars—is being
developed as part of the DDG 1000 program. While the multifunction radar has been tested
at sea, considerable testing remains for the volume search radar. Land-based tests of the
volume search radar prototype will not be completed until May 2009—2 years later than
planned. Upcoming land-based tests will be conducted at a lower voltage than needed to
meet requirements—and without the radome (the radar’s composite shield). Full power
output will not be tested on a complete system until 2012. Tests of carrier-specific
functionality will not conclude until shortly before shipyard delivery in 2013 leaving little
time to resolve problems before ship installation....
The program has faced challenges in maintaining its design schedule due to delays in the
receipt of technical information on EMALS and the advanced arresting gear; however, the
Navy believes this issue has been largely resolved. The shipbuilder anticipates changes to
CVN 78’s design based on the results of EMALS testing....
A February 2008 program assessment recommended a number of changes to the EMALS
program to improve performance. The Navy re-planned the test program and changed the
management approach. The CVN 21 program office is now responsible for overseeing
EMALS production and ship integration, rather than the Naval Air Systems Command. In
addition, EMALS will no longer be provided as government-purchased equipment. Instead,
the shipbuilder will purchase EMALS, giving it a more direct role in managing the
integration on CVN 78. The cost impact of this change has not been finalized.10
Navy officials testified on April 1, 2009, that they were reviewing the EMALS situation and that
“We do not see that it will have an impact on the actual schedule of the carrier at this point in
time.”11 On April 16, 2009, it was reported that the Navy had decided, based on its review of the
situation, to continue with the plan to build CVN-78 with EMALS.12

10 Government Accountability Office, Defense Acquisitions[:] Assessments of Selected Weapon Programs, GAO-09-
326SP, March 2009, pp. 68.
11 They stated that “We're looking at all options. There has been cost growth to the EMALS system. We're looking at—
at the total cost of acquisition and life cycle for EMALS and steam [catapults]. We're looking at schedule and what
does—does that do if we went back to steam [catapults] on CVN-78. What would that do to schedules? We’re in the
process of getting information from industry so that we can make an informed decision and we’ve had independent
technical looks at it within the department.” They also stated that “The technology itself is not new, but it’s the
application in the aircraft carrier [that’s new]. And so there is a lot of rigor we want to go through for component
testing so that we understand the reliability of the components as well as system testing. We are in the component
testing phase right now. We have seen minor issues in testing which we've been able to resolve. But there is some
concurrency with the schedules [for EMALS development and CVN-78 construction] and that’s one of the things we
want to evaluate going forward. Is the [EMALS] development schedule still ongoing? How do we—how do we
mitigate the risk to this carrier schedule so that that does (inaudible). Right now, we don’t see an impact to the carrier
schedule.” The Navy officials testified that they were waiting to receive an estimate from Northrop Grumman Newport
News on the potential cost impact of shifting to steam catapults for CVN-78. They stated that: “Right now, Mr.
(continued...)
Congressional Research Service
10

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

The EMALS development effort was the subject of a July 16, 2009, hearing before the Seapower
and Expeditionary Forces subcommittee of the House Armed Services Committee. Materials from
this hearing are presented in the Appendix.
Legislative Activity for FY2011
The Navy’s proposed FY2011 budget was submitted to Congress on February 1, 2010. The
budget requests $1,731.3 million in procurement funding for CVN-78 and $908.3 million in
advance procurement funding for CVN-79.

(...continued)
Chairman, the plan is—is to go to EMALS, or to continue with Electromagnetic Aircraft Launching System. That’s
going to be briefed to the CNO and the acting secretary here in the next week to 10 days.” (Source: Transcript of
spoken testimony of Allison Stiller, Deputy Assistant Secretary of the Navy [Ship Programs], and [for the final quote]
Vice Admiral Bernard McCullough, Deputy Chief of Naval Operations for Integration of Capabilities and Resources, at
an April 1, 2009, hearing on Navy shipbuilding before the Defense subcommittee of the House Appropriations
Committee. The comments by Stiller and McCullough came in response to questions on the EMALS issue posed by
Representative John Murtha, the subcommittee chairman.)
For press reports during this period discussing the EMALS issue, see Peter Frost, “Questions Swirl About New Aircraft
Catapult Systems For Next Carrier,” DailyPress.com (Newport News, VA), March 31, 2009; Emelie Rutherford and
Geoff Fein, “Navy Exploring Impact of Switching From EMALS To Steam Catapults For CVN-78,” Defense Daily,
April 2, 2009: 7-8; Rebekah Gordon, “Navy Examining Impacts of Switching to Steam Catapult on CVN-78,” Inside
the Navy
, April 6, 2009; and Christopher P. Cavas, “Next-Gen Carrier Launch System Could Be Shelved,”
DefenseNews.com, April 6, 2009.
12 A Navy spokesman stated: “This decision is based on completion of an extensive review of the EMALS program,
which included consideration of many significant factors and represents a balance between cost, schedule, technical
performance, and consideration of the risks to each.” (Andrew Tilghman, “Navy to Press on With EMALS,”
NavyTimes,com, April 16, 2009.) Another Navy spokesman stated: “To ensure the program delivers on schedule, while
limiting cost growth, the Navy is entering into detailed, fixed-price contract negotiations for procurement of
production-level equipment while implementing additional risk management efforts associated with completion of
development testing, production planning, installation and test.” (Geoff Fein, “Navy Stands By EMALS As Aircraft
Launch System For CVN-78,” Defense Daily, April 17, 2009: 3-4.)
Congressional Research Service
11

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Appendix. July 16, 2009, Hearing on EMALS
This appendix presents materials from a July 16, 2009, hearing on the EMALS development
effort before the Seapower and Expeditionary Forces subcommittee of the House Armed Services
Committee.
Chairman’s Opening Statement
The text of the opening statement of Representative Gene Taylor, the ranking member of the
subcommittee, is as follows:
The subcommittee will come to order.
Today the subcommittee meets in open session to receive testimony from officials of the
United States Navy on the current status of the Electromagnetic Aircraft Launch System, or
EMALS. The EMALS system is an electromagnetic catapult designed for use on the Ford-
class aircraft carriers. If the system delivers its full promised capability, the Ford-class
carriers will have a catapult system which is far superior to the steam catapults of the Nimitz-
class. The operational advantages are increased launch envelopes, that is, the ability to
launch both heavier and lighter aircraft than steam catapaults, higher sortie rates, reduced
weight, reduced mechanical complexity, reduced maintenance, and reduced carrier manning.
Unfortunately, what brings us together today is that the development of this program is so far
behind schedule that it threatens the delivery date for the USS Ford. For the record, I would
like to briefly summarize the history of this program and the current status:
EMALS was a core capability in the design of the next generation aircraft carrier, which the
Navy called “CVN 21” for “21th century” technology, and which eventually became the USS
Ford (CVN 78) class. In 1999 the Navy entered into technology demonstration contracts with
two different contractors; General Atomics and Northrop Grumman Marine Systems to
develop prototypes for an electromagnetic catapult. By 2004 the Navy down-selected to the
system proposed by General Atomics and entered into a System Design and Development
contract, or SDD contract, to build a full scale, ship representative prototype at the Navy test
facility in Lakehurst, New Jersey. That prototype was contracted to be completed in time for
testing to begin in 2007, testing was to have concluded after two years and presumably the
lessons learned from the test program would influence the final production system which
would be shipped to the carrier construction yard for erection into the ship. It is now July
2009 and full scale testing has yet to begin at the Lakehurst facility. The Navy is now faced
with almost complete concurrency of testing and production of the first ship-set if they are to
meet the in-yard deliver dates to keep the USS Ford on schedule. There are a number of sub-
systems to the complete EMALS system and each subsystem has different in-yard deliver
dates, but some of those dates are as early as the summer of 2011, and to meet those dates
the production of the components or at least the ordering of the material for the components
must begin now—before full scale testing of the prototype system has begun. To be fair,
some testing has already occurred. The High Cycle Test for the Energy Storage System is
well underway, as is the Highly Accelerated Life Cycle Testing of the launch motor
segments. Those tests have identified some minor redesign issues which can be incorporated
into the production components. But until a full scale catapult launch from the prototype
occurs, questions will remain on the systems overall performance.
I have been briefed, as I believe other Members of this subcommittee have been briefed, that
the issues in completing and delivering the SDD components were a result of the contractor’s
Congressional Research Service
12

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

inexperience managing a major production effort. I find that answer unsettling because it is
the Navy’s responsibility to oversee what their contractors are doing and to identify
problems before they are problems. I will note that a little over a year and a half ago, the
contractor did put in place an entirely new management and engineering team, hiring away
proven production engineers from both General Dynamics and Northrop Grumman. This
new team seems to have righted the ship, but that ship is still in very dangerous seas.
So what we have is a program that is so essential to the carrier that if it does not work, the
nation has paid billions of dollars for an unusable ship. If the system is delayed, the carrier is
automatically delayed. And every day of delay will push the cost of that carrier higher.
This is the first in what I intend to be a series of hearings on this program over the next few
years. This is too important to not have close congressional oversight. I intend to continue
close oversight of this program until it is delivered, installed, tested, and certified for
launching naval aircraft off the deck of the USS Ford.
Our witnesses today are:
• VADM David Architzel, Principle Deputy to Assistant Secretary Stackley
• CAPT Randy Mahr, Program Manager for EMALS
• CAPT Brian Antonio, Program Manager, Ford Class Aircraft Carrier
VADM Architzel is representing the Assistant Secretary as the senior acquisition executive
who is ultimately responsible for all Navy and Marine Corps acquisition programs. CAPT
Mahr, is the official whose only responsibility is this program. CAPT Antonio is responsible
for building the entire carrier—he obviously has an interest in the success of EMALS.
This year’s National Defense Authorization Act directs the Secretary of the Navy to keep
CAPT Mahr in his position until the completion of the system development testing and the
successful production of the first ship-set of components. That means the CAPT, who has
been selected to the rank of Rear Admiral, will be in place for another few years and will
have the opportunity to visit with us again on this subject.
I would now like to call on my friend from Missouri, the Ranking Member of this
subcommittee, the Honorable Todd Akin for any opening remarks he may wish to make.
Ranking Member’s Opening Statement
The text of the opening statement of Representative Todd Akin, the ranking member of the
subcommittee, is as follows:
Thank you, Mr. Chairman, and welcome to our witnesses. We appreciate your willingness to
appear before us today. As the Chairman has indicated, the Electromagnetic Launch System,
known as EMALS, is a critical part of the military’s largest and most expensive ship, the
next generation aircraft carrier. The EMALS system is important because of the capability it
delivers to the Gerald R. Ford-class carrier, allowing our Navy to increase its sortie
generation rate and the carrier to launch both heavier and lighter aircraft, in more operating
conditions, than is currently possible. This is a significant attribute, because the first of these
carriers will be in service until at least 2065, and in order to maintain its relevance, the
carrier will need to be able to launch F-35s, UAVs, and whatever else we may develop in the
meantime.
Congressional Research Service
13

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Additionally, EMALS is important because the schedule delays and cost growth experienced
by the system have put the construction and cost of the carrier in jeopardy. As this
subcommittee has noted on multiple occasions, the scale of our investment in aircraft carrier
construction means that even small increases in cost have the potential to break the bank.
Other shipbuilding programs have recently seen cost growth of close to 200 percent. If the
carrier grows by even 10 percent, the impact is in the billions of dollars per vessel. Simply
put, the EMALS program has no room for error. It must deliver on time, or put the carrier at
risk. To get there, the EMALS program must engage in con-current development and
production of the first ship set—a practice we know well from past experience is highly
risky.
But there is some good news. The contractor has been holding to schedule since the
beginning of the year and has agreed to a fixed price production contract. The Assistant
Secretary of the Navy for Research, Development, and Acquisition got personally involved
and conducted an in-depth review of the program. Secretary Stackley has elected to proceed
with the effort, a decision that I agree with, but has taken several steps to strengthen the
management of the program. One of these steps includes lengthening the tour of the current
program manager, CAPT Mahr, who is with us today. I have often noted that one of the first
lessons I learned during my time at IBM, is that for any project to succeed, you need to have
one person who is in charge. CAPT Mahr, this subcommittee has heard many good things
about you, and your colleague CAPT Brian Antonio, the CVN 21 Program Manager. But we
will be holding you to a very high standard. This is your baby and you must deliver. The
consequences for the rest of naval shipbuilding are too great to tolerate anything less.
In conclusion, I am interested in learning more today about the contract you are putting in
place with the EMALS contractor for the production ship set, and the activities required to
conclude system development and minimize risk to the CVN 21 program going forward.
Thank you again for being here. I look forward to your testimony.
Navy Statement
Chairman Taylor, Ranking Member Akin, and distinguished members of the Subcommittee,
thank you for the opportunity to appear before you today to report on the development of the
Electromagnetic Aircraft Launch System (EMALS) for Gerald R. Ford (CVN 78) class
aircraft carriers and the Department’s plan ahead for this effort.
Steam catapults will continue to deliver the minimum required aircraft launching capability
and remain the launching system on the NIMITZ-class aircraft carrier for the next fifty years.
However, the steam catapult system limits the full potential of the inherent improved
capability of the FORD-class aircraft carrier. As modern aircraft, including the Joint Strike
Fighter, grow heavier and require higher launching end speeds, and the maintenance man-
hours required to maintain the readiness of the steam catapult increases, it is imperative that
the Navy continue development of a launching system with reduced manning and increased
operational availability. In response to meeting this future need, EMALS is being developed
for the CVN 78 class to replace the steam catapult system. EMALS design requirements
support the CVN 78 sortie generation rate Key Performance Parameter (KPP) through
increased reliability and system capability. It provides a higher energy launch capability as
well as an expanded launch envelope to support future airwing capabilities. EMALS is also
projected to reduce shipboard manning requirements, improve aircraft launching system
maintainability, and provide better control and more efficient application of acceleration
forces throughout the aircraft launch cycle.
EMALS development began with a competitive prototyping effort between General Atomics
(GA) and Northrop Grumman Marine Systems in 1999. The Navy down-selected to the GA
Congressional Research Service
14

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

design in 2004 following completion of approximately 1500 launch demonstration events
conducted on both competing systems. Based on the successful prototype testing, the Navy
awarded the EMALS System Development and Demonstration (SDD) contract to GA in
2005, which is scheduled to complete in early 2012.
The EMALS program is currently executing the test portions of the SDD phase and
procuring long lead time material as it begins production of the CVN 78 ship set. Near term
events such as successful completion of High Cycle Test (HCT) Phase I and commencement
of High Cycle Test (HCT) Phase II, Highly Accelerated Life Testing (HALT), as well as
start of commissioning testing for System Functional Demonstration (SFD), will validate the
system design and enable transition into production. HCT II testing of a complete power
train, with the exception of the launch motor, is ongoing at the GA Tupelo, Mississippi site.
HALT testing of the launch motor is taking place at the Naval Air Warfare Center test site in
Lakehurst, NJ. Production Readiness Reviews (PRRs) are currently ongoing to support
release of EMALS subsystem components for production. Baseline drawing packages are
projected to complete by the end of FY 2009. Full scale, full length testing of EMALS,
including the launch of manned aircraft, is scheduled to begin at Lakehurst during the
summer of 2010.
Concurrent with testing, EMALS manufacturing and production efforts began in December
2007 with the first Long Lead Time material procurements to support CVN 78 required in
yard delivery dates and will continue through 2014 for delivery of all CVN 78 ship set
components. The Navy has placed an undefinitized contract action (UCA) with a not to
exceed value with General Atomics leading to an Advanced Acquisition Fixed Price contract
for the remaining ship set material. Definitization of this contract is targeted for later this
year. The Navy’s and GA’s support for a fixed price contract reflects our collective
confidence in the EMALS’ technology maturity and capability. The contract will be based on
the EMALS performance specification and Procurement Data Packages. Specific component
production release will be tied to Production Readiness Reviews and successful completion
of specific test events. The Production Integrated Master Schedule shows the program will
meet CVN 78 production required in yard delivery dates.
As EMALS progressed through SDD tests and began the transition to production, schedule
delays and cost overruns were experienced. A series of actions aimed at improving
management of the EMALS prime and subcontractors were taken by the Navy. In late 2007,
Navy leadership initiated a three-month independent and in-depth Production Assessment
Review (PAR). The PAR provided specific recommendations for processes and leadership
improvements, which are being implemented. Most recently, senior Navy leadership
conducted a detailed assessment of the viability of continuing with EMALS or reverting to a
legacy steam catapult system for CVN 78 based on indications that schedule and cost
performance was declining. After an extensive review, the Navy re-confirmed it’s
commitment to EMALS as the CVN 78-class aircraft launching system, while implementing
additional actions to improve performance and mitigate risk.
The production contract will ensure rigorous management and oversight. In April 2004, the
Under Secretary of Defense (Acquisition, Technology and Logistics) (USD(AT&L))
established a critical technology Integrated Product Team (IPT) to maintain oversight of all
CVN 78 critical technologies, including EMALS development. Additionally, the Navy has
implemented two detailed reviews to identify needed improvements to support better
schedule and cost performance while completing technical efforts. The review of the PAR in
2008 provided a thorough assessment of GA’s ability to transition from development to
production and to support the CVN 78 production schedule. The Navy aggressively
implemented many of the PAR recommendations including leadership changes, new
program and technical governance processes, increased involvement of the shipbuilder and a
revised test program to mitigate production schedule risks. A three-star Executive
Congressional Research Service
15

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Committee, which includes the OPNAV resource sponsor, Commanders of the Naval Sea
Systems Command and Naval Air Systems Command, and the Principal Military Deputy for
ASN RDA meet quarterly for program reviews and to provide oversight of EMALS
development. Most importantly, direct responsibility for EMALS is being executed by the
NAVAIR program manager for Aircraft Launch & Recovery Equipment (ALRE), who
reports to PEO TACAIR and COMNAVAIR to support delivery of this new program within
cost and schedule.
Issues with cost and schedule performance have created overlaps between production
component manufacturing and system level testing. Cost and schedule performance have not
been where they need to be. Recognizing this, the Navy has taken steps to better define
needed testing, improved management oversight, insisted on near term definitization of the
DCA into a fixed price contract, and increased funding to the program to cover anticipated
growth. With system level testing ongoing the potential for additional cost increases and
schedule delays remain. However, the Navy is putting additional oversight in place to
maximize performance and minimize the likelihood of overruns. Given the advantages that
EMALS is projected to afford the next generation of aircraft carriers, these actions are
essential for providing the fleet what it needs.
Component, subsystem, and system testing is identifying technical issues, retiring technical
risk, and demonstrating the capability of the EMALS. Key to the Navy’s strategy is having a
management team in place both within the Navy and at its prime contractor that is
aggressively attacking these issues and retiring risks on a schedule that supports ship
construction. We are working hard towards these ends. The management focus, review
processes and oversight that the Navy is employing are mitigating future EMALS SDD
phase technical, cost and schedule risks. The Navy will leverage management processes
established during the SDD phase by building upon these lessons learned during system
production and ship integration, including the extensive involvement of the shipbuilder in the
production and integration process. A rigorous process exists for incorporating the results of
upcoming testing in the production baseline which will mitigate cost and schedule risks of
concurrency between the SDD and production phases. The Navy has also taken steps to
include, as mentioned previously, the use of fixed price contracting where appropriate, to
control EMALS cost and schedule variances during the subsystem production phase.
Mr. Chairman, the Navy understands the concerns you and your subcommittee have
expressed, and is aggressively working to improve performance. We are implementing your
recommendations to breakout EMALS cost and performance data for separate review by
Congress, and to provide stability in the program’s key technical and management teams.
The Department is committed to delivering CVN 78 with EMALS on time and on budget.
EMALS will enable current and future generations of Naval Aviators to perform their
missions more safely, efficiently and effectively. I thank you for the opportunity to testify
and look forward to answering your questions.13


13 Statement of Vice Admiral David Architzel, USN, Principal Military Deputy, Research, Development and
Acquisition, and Captain Randy Mahr, USN, Program Manager for Aircraft Launching and Recovery Equipment
(ALRE) and Captain Brian Antonio, USN, Program Manager for Future Aircraft Carrier, Before the Seapower and
Expeditionary Warfare [sic: Forces] Subcommittee of the House Armed Services Committee [Hearing] On
Electromagnetic Aircraft Launch System (EMALS}, July 16, 2009, 43 pp.
Congressional Research Service
16

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Author Contact Information

Ronald O'Rourke

Specialist in Naval Affairs
rorourke@crs.loc.gov, 7-7610


Congressional Research Service
17