Navy DDG-51 and DDG-1000 Destroyer
Programs: Background and Issues for
Congress

Ronald O'Rourke
Specialist in Naval Affairs
December 23, 2009
Congressional Research Service
7-5700
www.crs.gov
RL32109
CRS Report for Congress
P
repared for Members and Committees of Congress

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Summary
Consistent with a proposal announced by the Navy in July 2008, the Administration’s FY2010
defense budget proposed ending procurement of DDG-1000 (Zumwalt) class destroyers with the
third ship, which was authorized and partially funded in FY2009, and restarting procurement
DDG-51 (Arleigh Burke) class Aegis destroyers, which were last procured in FY2005. The
proposed FY2010 defense budget requested procurement funding to complete the cost of the third
DDG-1000 and to procure one DDG-51, and advance procurement funding for two more DDG-
51s that the Navy wants to procure in FY2011.
The Navy’s plans for destroyer procurement in FY2012 and beyond have been unclear. The Navy
since July 2008 has spoken on several occasions about a desire to build a total of 11 or 12 DDG-
51s between FY2010 and FY2015, but the Navy also testified to the Seapower subcommittee of
the Senate Armed Services Committee on June 16, 2009, that it is conducting a study on destroyer
procurement options for FY2012 and beyond that is examining design options based on either the
DDG-51 or DDG-1000 hull form. A January 2009 memorandum from the Department of Defense
acquisition executive called for such a study. A November 2009 press report stated that the study
was begun in late Spring 2009, that it was nearing completion, that it examined options for
equipping the DDG-51 and DDG-1000 designs with an improved radar, and that preliminary
findings from the study began to be briefed to “key parties on Capitol Hill and in industry” in
October 2009.
On December 7, 2009, it was reported that the Navy wants to cancel its planned CG(X) cruiser
and instead procure an improved version of the Arleigh Burke (DDG-51) class Aegis destroyer.
The improved DDG-51 that the Navy reportedly now wants to procure would be considerably
less expensive to procure than the CG(X). The improved DDG-51 would have more AAW and
BMD capability than the current DDG-51 design, but less AAW and BMD capability than what
was envisioned for the CG(X). Potential issues for Congress arising from the Navy’s reported
new plan include the following:
• Is there an adequate analytical basis for canceling the CG(X) and instead
procuring improved DDG-51s? Should an analysis of alternatives (AOA) or the
equivalent of an AOA be performed before committing to this course of action?
• Is there adequate stability in Navy planning for acquisition of surface
combatants?
• Would an improved DDG-51 be an adequate substitute for the CG(X)?
• What would be the potential operational implications of a Navy equipped with
improved DDG-51s instead of CG(X)s?
• What would be the potential industrial-base consequences of canceling the
CG(X) and instead procuring improved DDG-51s?
• What would be some potential alternatives to canceling the CG(X) and instead
procuring improved DDG-51s?


Congressional Research Service

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Contents
Introduction ................................................................................................................................ 1
Background ................................................................................................................................ 2
Navy Destroyer and Cruiser Acquisition Programs ................................................................ 2
DDG-51 Program............................................................................................................ 2
DDG-1000 Program........................................................................................................ 4
CG(X) Program .............................................................................................................. 6
Shifts in Navy Destroyer and Cruiser Acquisition Plans......................................................... 9
Rationale for 2008-2009 Shift in Destroyer Procurement Plans........................................ 9
Study of Destroyer Procurement Options for FY2012 and Beyond ................................ 12
Reported Plan to Stop CG(X) in Favor of Procuring Improved DDG-51s ...................... 15
Surface Combatant Construction Industrial Base ................................................................. 18
Shipyards...................................................................................................................... 18
Combat System Manufacturers...................................................................................... 18
Supplier Firms .............................................................................................................. 18
FY2010 Funding Request.................................................................................................... 18
DDG-51 Program.......................................................................................................... 18
DDG-1000 Program...................................................................................................... 19
CG(X) Program ............................................................................................................ 19
Issues for Congress ................................................................................................................... 19
Analytical Basis for Canceling CG(X) in Favor of Improved DDG-51s ............................... 20
Stability in Navy Surface Combatant Acquisition Planning.................................................. 21
Adequacy of Improved DDG-51 as Substitute for CG(X) .................................................... 22
Potential Operational Implications....................................................................................... 23
Potential Industrial-Base Consequences .............................................................................. 24
Radar and Combat System Makers................................................................................ 24
Shipyards...................................................................................................................... 24
Nuclear Propulsion Component Manufacturers.............................................................. 24
Potential Alternatives to Reported Navy Plan ...................................................................... 25
Continue CG(X) program.............................................................................................. 25
Procure a More Highly Modified DDG-51 .................................................................... 25
Procure a Modified DDG-1000 ..................................................................................... 25
Procure a Cost-Constrained New-Design Destroyer....................................................... 25
Backfit Existing DDG-51s with Improved Radars ......................................................... 27
FY2010 Legislative Activity ..................................................................................................... 27
Summary of Action on Funding Request ............................................................................. 27
FY2010 Defense Authorization Act (H.R. 2647/P.L. 111-84) ............................................... 28
House ........................................................................................................................... 28
Senate ........................................................................................................................... 28
Conference.................................................................................................................... 32
FY2010 DOD Appropriations Act (H.R. 3326/P.L. 111-118)................................................ 34
House ........................................................................................................................... 34
Senate ........................................................................................................................... 34
Final Version................................................................................................................. 35

Congressional Research Service

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Figures
Figure D-1. Near-Surface Bow Bulb Design for DDG-51 .......................................................... 59

Tables
Table 1. [In Navy letter to Congress] Acquisition Costs for DDG-51s and Modified DDG-
1000s ..................................................................................................................................... 10
Table 2. [In Navy Letter to Congress] Annual O & S Costs for a DDG-51 and a Modified
DDG-1000 ............................................................................................................................. 11
Table 3. Possible Approach for a Cost-Constrained New-Design Destroyer ............................... 26
Table 4. Summary of Action on FY2010 Funding Request......................................................... 27
Table C-1. DDG-1000 Capabilities Relative to DDG-51 Capabilities......................................... 50
Table D-1. DDG-1000 and DDG-51 Annual O&S Costs............................................................ 60
Table D-2. 1997 Navy Information on DDG-51 Variants ........................................................... 61

Appendixes
Appendix A. Additional Background Information on DDG-1000 Program................................. 37
Appendix B. Navy Testimony of July 31, 2008.......................................................................... 40
Appendix C. Comparisons of DDG-51 and DDG-1000 ............................................................. 45
Appendix D. Potential DDG-51 and DDG-1000 Design Variants............................................... 55

Contacts
Author Contact Information ...................................................................................................... 67

Congressional Research Service

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Introduction
Consistent with a proposal announced by the Navy in July 2008, the Administration’s FY2010
defense budget proposed ending procurement of DDG-1000 (Zumwalt) class destroyers with the
third ship, which was authorized and partially funded in FY2009, and restarting procurement
DDG-51 (Arleigh Burke) class Aegis destroyers, which were last procured in FY2005. The
proposed FY2010 defense budget requested procurement funding to complete the cost of the third
DDG-1000 and to procure one DDG-51, and advance procurement funding for two more DDG-
51s that the Navy wants to procure in FY2011.
The Navy’s plans for destroyer procurement in FY2012 and beyond have been unclear. The Navy
since July 2008 has spoken on several occasions about a desire to build a total of 11 or 12 DDG-
51s between FY2010 and FY2015, but the Navy also testified to the Seapower subcommittee of
the Senate Armed Services Committee on June 16, 2009, that it is conducting a study on destroyer
procurement options for FY2012 and beyond that is examining design options based on either the
DDG-51 or DDG-1000 hull form. A January 2009 memorandum from the Department of Defense
(DOD) acquisition executive called for such a study. A November 2009 press report stated that
the study was begun in late Spring 2009, that it was nearing completion, that it examined options
for equipping the DDG-51 and DDG-1000 designs with an improved radar, and that preliminary
findings from the study began to be briefed to “key parties on Capitol Hill and in industry” in
October 2009.1
On December 7, 2009, it was reported that the Navy wants to cancel its planned CG(X) cruiser
and instead procure an improved version of the Arleigh Burke (DDG-51) class Aegis destroyer.2
Earlier press reporting had suggested that the Navy might be heading toward such a change in
plans.3 The Navy reportedly was concerned about the projected high cost of the CG(X), and has
concluded that it does not need a ship as capable as the CG(X) to adequately perform future anti-
air warfare (AAW) and ballistic missile defense (BMD) missions. The Navy’s desire to cancel the
CG(X) and instead procure improved DDG-51s reportedly will be reflected in the Navy’s
proposed FY2011 budget, which is to be submitted to Congress in early February 2010.
Prior to this reported change in plans, the Navy had wanted to procure as many as 19 CG(X)s.
The Navy had wanted to procure the first CG(X) around FY2017 and have it enter service around
2023.4

1 Christopher P. Cavas, “Next-Generation U.S. Warship Could Be Taking Shape,” Defense News, November 2, 2009:
18, 20.
2 Christopher J. Castelli, “Draft Shipbuilding Report Reveals Navy Is Killing CG(X) Cruiser Program,” Inside the
Navy
, December 7, 2009. A November 2009 press report on a recent Navy “Hull/Radar” study suggested the Navy
wanted to procure an improved destroyer featuring a new radar. (Christopher P. Cavas, “Next-Generation U.S. Warship
Could Be Taking Shape,” Defense News, November 2, 2009: 18, 20.) Given the potential difficulty for the Navy to
finance, more or less simultaneously, the development and procurement of both an improved destroyer and the CG(X),
this press report raised the question of whether the Navy now wanted to cancel the CG(X).
3 Christopher P. Cavas, “Next-Generation U.S. Warship Could Be Taking Shape,” Defense News, November 2, 2009:
18, 20.
4 For more on the CG(X) program, see CRS Report RL34179, Navy CG(X) Cruiser Program: Background, Oversight
Issues, and Options for Congress
, by Ronald O'Rourke
Congressional Research Service
1

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

The improved DDG-51 that the Navy reportedly now wants to procure would be considerably
less expensive to procure than the CG(X). The improved DDG-51 would have more AAW and
BMD capability than the current DDG-51 design, but less AAW and BMD capability than what
was envisioned for the CG(X).
Potential issues for Congress include the following:
• Is there an adequate analytical basis for canceling the CG(X) and instead
procuring improved DDG-51s? Should an analysis of alternatives (AOA) or the
equivalent of an AOA be performed before committing to this course of action?
• Is there adequate stability in Navy planning for acquisition of surface
combatants?
• Would an improved DDG-51 be an adequate substitute for the CG(X)?
• What would be the potential operational implications of a Navy equipped with
improved DDG-51s instead of CG(X)s?
• What would be the potential industrial-base consequences of canceling the
CG(X) and instead procuring improved DDG-51s?
• What would be some potential alternatives to canceling the CG(X) and instead
procuring improved DDG-51s?
Decisions that Congress reaches about destroyer and cruiser acquisition could significantly affect
Navy capabilities and funding requirements, and the surface combatant industrial base.
Background
Navy Destroyer and Cruiser Acquisition Programs
DDG-51 Program
Program Origin
The DDG-51 (Arleigh Burke) Aegis destroyer program was initiated in the late 1970s with the
aim of developing a surface combatant to replace older destroyers and cruisers that were
projected to retire in the 1990s. The DDG-51 was conceived as an affordable complement to the
Navy’s Ticonderoga (CG-47) class Aegis cruisers.
Mission Orientation and Design Features
The DDG-51 is a multi-mission surface combatant with an emphasis on air defense (which the
Navy refers as anti-air warfare, or AAW) and blue-water (mid-ocean) operations. DDG-51s, like
CG-47s, are equipped with the Aegis combat system, an integrated ship combat system named for
the mythological shield that defended Zeus. CG-47s and DDG-51s consequently are often
referred to as Aegis cruisers and Aegis destroyers, respectively, or collectively as Aegis ships. The
current version of the DDG-51 design, called the Flight IIA version, has a full load displacement
of about 9,500 tons, which is similar to that of the CG-47.
Congressional Research Service
2

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

The DDG-51 design has been changed over time to incorporate various improvements. The Flight
IIA design, which was first procured in FY1994, was a significant change that included, among
other things, the addition of a helicopter hangar. The Aegis system installed on new DDG-51s has
been updated several times.
DDG-51s (and also some CG-47s) are being modified to receive an additional capability for
ballistic missile defense (BMD) operations. The modification for BMD operations includes,
among other things, the addition of a new software program for the Aegis combat system and the
arming of the ship with the SM-3, a version of the Navy’s Standard Missile that is designed for
BMD operations.5
Total Procured Through FY2005 and Construction Shipyards
The first DDG-51 was procured in FY1985, and a total of 62 were procured through FY2005. The
first ship entered service in 1991, a total of 54 were in service as of the end of FY2008, and the
62nd is scheduled to enter service in 2011. Of the 62 DDG-51s procured through FY2005, General
Dynamics Bath Iron Works (GD/BIW) of Bath, ME, is the builder of 34, and the Ingalls shipyard
that forms part of Northrop Grumman Shipbuilding (NGSB) is the builder of 28.6
The Navy has initiated a program for modernizing existing DDG-51s so as maintain their mission
and cost effectiveness out to the end of their projected 35-year service lives.7 In August 2008, it
was reported that the Navy had decided to expand the scope of this program to include the
installation of a BMD capability, so that every DDG-51 would eventually have a BMD
capability.8
Older CRS reports provide additional historical and background information on the DDG-51
program.9

5 For more on Navy BMD programs, CRS Report RL33745, Sea-Based Ballistic Missile Defense—Background and
Issues for Congress
, by Ronald O'Rourke.
6 In the earlier years of the DDG-51 program, when as many as four or five DDG-51s per year were being procured,
Bath Iron Works (BIW) of Bath, ME (now a part of General Dynamics) and Ingalls Shipbuilding of Pascagoula, MS
(now a part of Northrop Grumman Shipbuilding) competed on an annual basis for contracts to build DDG-51s. In
FY1994, when the annual DDG-51 procurement rate dropped to about three ships per year, the Navy ended annual
competition between the firms for the purpose of allocating DDG-51 construction contracts and began to allocate
DDG-51s between them. Two years later, in FY1996, the Navy began using Profit Related to Offer (PRO) bidding,
which granted a higher profit rate to the shipyard that submitted the lower-cost bid for its work. PRO bidding permits
the Navy to employ a degree of competition in the acquisition of DDG-51s even though DDG-51s are allocated rather
than competitively awarded to the two shipyards.
7 For more on this program, see CRS Report RS22595, Navy Aegis Cruiser and Destroyer Modernization: Background
and Issues for Congress
, by Ronald O’Rourke.
8 Otto Kreisher, “BMD Boost,” Seapower, August 2008: 12-14. Equipping all DDG-51s with a BMD capability would
substantially expand the current program of record for Navy BMD platforms, which currently calls for 15 DDG-51s
(and 3 Aegis cruisers) to be equipped for BMD operations.
9 See CRS Report 94-343, Navy DDG-51 Destroyer Procurement Rate: Issues and Options for Congress, by Ronald
O’Rourke. [April 25, 1994; out of print and available directly from the author], and CRS Report 80-205, The Navy’s
Proposed Arleigh Burke (DDG-51) Class Guided Missile Destroyer Program: A Comparison With An Equal-Cost
Force Of Ticonderoga (CG-47) Class Guided Missile Destroyers
, by Ronald O’Rourke. [November 21, 1984; out of
print and available directly from the author]
Congressional Research Service
3

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

DDG-1000 Program
Program Origin and Names
The Navy initiated the DDG-1000 (Zumwalt) destroyer program in the early 1990s under the
name DD-21, which meant destroyer for the 21st Century. In November 2001, the program was
restructured and renamed the DD(X) program, meaning a destroyer whose design was in
development. In April 2006, the program’s name was changed again, to DDG-1000, meaning a
guided missile destroyer with the hull number 1000.
Mission Orientation and Design Features
The DDG-1000 is a multi-mission destroyer with an emphasis on naval surface fire support
(NSFS) and operations in littoral (i.e., near-shore) waters. The DDG-1000 was intended in part to
replace, in a technologically more modern form, the large-caliber naval gun fire capability that
the Navy lost when it retired its Iowa-class battleships in the early 1990s.10 The DDG-1000 was
also intended to improve the Navy’s general capabilities for operating in defended littoral waters,
to introduce several new technologies that would be available for use on future Navy ships, and to
serve as the basis for the Navy’s planned CG(X) cruiser.
The DDG-1000 is to have a reduced-size crew of 142 sailors (compared to roughly 300 on the
Navy’s current destroyers and cruisers) so as reduce its operating and support (O&S) costs. The
ship is to incorporate a significant number of new technologies, including a wave-piercing,
tumblehome hull design for reduced detectability,11 a superstructure made partly of large sections
of composite (i.e., fiberglass-like) materials rather than steel or aluminum, an integrated electric-
drive propulsion system,12 a total-ship computing system for moving information about the ship,
automation technologies for the reduced-sized crew, a dual-band radar, a new kind of vertical
launch system (VLS) for storing and firing missiles, and two copies of a 155mm gun called the
Advanced Gun System (AGS). The AGS is to fire a new rocket-assisted 155mm shell, called the
Long Range Land Attack Projectile (LRLAP), to ranges of more than 60 nautical miles. The
DDG-1000 can carry 600 LRLAP rounds (300 for each gun), and additional rounds can be
brought aboard the ship while the guns are firing, creating what Navy officials call an “infinite
magazine.”
With an estimated full load displacement of 14,987 tons, the DDG-1000 design is roughly 55%
larger than the Navy’s current 9,500-ton Aegis cruisers and destroyers, and larger than any Navy
destroyer or cruiser since the nuclear-powered cruiser Long Beach (CGN-9), which was procured
in FY1957.

10 The Navy in the 1980s reactivated and modernized four Iowa (BB-61) class battleships that were originally built
during World War II. The ships reentered service between 1982 and 1988 and were removed from service between
1990 and 1992.
11 A tumblehome hull slopes inward, toward the ship’s centerline, as it rises up from the waterline, in contrast to a
conventional flared hull, which slopes outward as it rises up from the waterline.
12 For more on integrated electric-drive technology, see CRS Report RL30622, Electric-Drive Propulsion for U.S. Navy
Ships: Background and Issues for Congress
, by Ronald O’Rourke.
Congressional Research Service
4

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

When the DD-21 program was initiated, a total of 32 ships was envisaged. In subsequent years,
the planned total for the DD(X)/DDG-1000 program was reduced to 16 to 24, and then to 7.
Under the Administration’s proposed FY2010 budget, the planned total is to be reduced to three.
For additional background information on the DDG-1000 program, see Appendix A.
Estimated Costs and Prior-Year Funding
The first two DDG-1000s were procured in FY2007 and split-funded (i.e., funded with two-year
incremental funding) in FY2007-FY2008. In the FY2009 budget, the Navy estimated their
combined procurement cost at $6,324.5 million. In the FY2010 budget, the Navy estimates their
combined procurement cost at $6,634.2 million—an increase of $309.7 million, or about 4.9%.
The Navy states that this increase is not due to growth in the estimated cost to build the ships
themselves, but rather to a reallocation to the first two ships of some class-wide program-support
costs that were to have been included in the procurement costs of the fourth through seventh
ships.13 To cover this cost growth, the Navy’s proposed FY2010 budget requests $309.6 million in
procurement funding in a line item in the Navy’s shipbuilding account that requests funding to
cover cost growth on ships procured in prior fiscal years.14
The third DDG-1000 was authorized and partially funded in FY2009. The FY2009 budget
estimated the procurement cost of the third DDG-1000 at $2,652.6 million. The FY2010 budget
estimates the ship’s procurement cost at $2,738.3 million—an increase of $85.7 million, or about
3.2%. The third DDG-1000 received $149.8 million in advance procurement funding in FY2008,
and $1,504.3 million in procurement funding in FY209. The Navy’s proposed FY2010 budget
requests $1,084.2 million to complete the cost of the ship.
The DD-21/DD(X)/DDG-1000 program has received a total of about $15.3 billion in funding
from FY1995 through FY2009. This total includes about $7.4 billion in research and
development funding, and about $8.0 billion in procurement funding.
Construction Shipyards
Until July 2007, it was expected that NGSB would be the final-assembly yard for the first DDG-
1000 and that GD/BIW would be the final-assembly yard for the second. On September 25, 2007,
the Navy announced that it had decided to build the first DDG-1000 at GD/BIW, and the second
at NGSB.
On January 12, 2009, it was reported that the Navy, NGSB, and GD/BIW in the fall of 2008
began holding discussions on the idea of having GD/BIW build both the first and second DDG-
1000s, in exchange for NGSB receiving a greater share of the new DDG-51s that would be
procured under the Navy’s July 2008 proposal to stop DDG-1000 procurement and restart DDG-
51 procurement.15

13 Source: Navy briefing on DDG-1000 to CRS and Congressional Budget Office (CBO), June 10, 2009.
14 The difference between the $309.7 million figure and the $309.6 million figure appears to be a consequence of
rounding figures to the nearest tenth of a million.
15 Christopher P. Cavas, “Will Bath Build Second DDG 1000?” Defense News, January 12, 2009: 1, 6.
Congressional Research Service
5

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

On April 8, 2009, it was reported that the Navy had reached an agreement with NGSB and
GD/BIW to shift the second DDG-1000 to GD/BIW, and to have GD/BIW build all three ships.
NGSB will continue to make certain parts of the three ships, notably their composite deckhouses.
The agreement to have all three DDG-1000s built at GD/BIW was a condition that Secretary of
Defense Robert Gates set forth in an April 6, 2009, news conference on the FY2010 defense
budget for his support for continuing with the construction of all three DDG-1000s (rather than
proposing the cancellation of the second and third).
CG(X) Program
Program Origin
The CG(X) program was announced on November 1, 2001, when the Navy stated that it was
launching a Future Surface Combatant Program aimed at acquiring a family of next-generation
surface combatants. This new family of surface combatants, the Navy stated, would include three
new classes of ships:16
a destroyer called the DD(X)—later renamed the DDG-1000 or Zumwalt
class—for the precision long-range strike and naval gunfire mission,
a cruiser called the CG(X) for the AAW and BMD mission, and
a smaller combatant called the Littoral Combat Ship (LCS) to counter
submarines, small surface attack craft, and mines in heavily contested littoral
(near-shore) areas.17
The Navy wanted to procure as many as 19 CG(X)s as replacements for its 22 Ticonderoga (CG-
47) class Aegis cruisers, which are projected to reach their retirement age of 35 years between
2021 and 2029.18

16 The Future Surface Combatant Program replaced an earlier Navy surface combatant acquisition effort, begun in the
mid-1990s, called the Surface Combatant for the 21st Century (SC-21) program. The SC-21 program encompassed a
planned destroyer called DD-21 and a planned cruiser called CG-21. When the Navy announced the Future Surface
Combatant Program in 2001, development work on the DD-21 had been underway for several years, but the start of
development work on the CG-21 was still years in the future. The DD(X) program, now called the DDG-1000 or
Zumwalt-class program, is essentially a restructured continuation of the DD-21 program. The CG(X) might be
considered the successor, in planning terms, of the CG-21. After November 1, 2001, the acronym SC-21 continued for
a time to be used in the Navy’s research and development account to designate a line item (i.e., program element) that
funded development work on the DDG-1000 and CG(X).
17 For more on the LCS program, see CRS Report RL33741, Navy Littoral Combat Ship (LCS) Program: Background,
Issues, and Options for Congress
, by Ronald O'Rourke.
18 CG-47s are equipped with the Aegis combat system and are therefore referred to as Aegis cruisers. A total of 27 CG-
47s were procured for the Navy between FY1978 and FY1988; the ships entered service between 1983 and 1994. The
first five, which were built to an earlier technical standard, were judged by the Navy to be too expensive to modernize
and were removed from service in 2004-2005. The Navy is currently modernizing the remaining 22 to maintain their
mission effectiveness to age 35; for more information, see CRS Report RS22595, Navy Aegis Cruiser and Destroyer
Modernization: Background and Issues for Congress
, by Ronald O’Rourke.
Congressional Research Service
6

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Mission Orientation and Potential Design Features
The Navy’s 22 Aegis cruisers are highly capable multi-mission ships with an emphasis on AAW
and (as a more recent addition) BMD. The Navy similarly wanted the CG(X) to be a highly
capable multi-mission ship with an emphasis on AAW and BMD. BMD has emerged in recent
years as a significant new mission for the Navy. Navy surface ships in coming years may face a
threat from anti-ship ballistic missiles (ASBMs)—theater-range ballistic missiles (TBMs)
equipped with maneuvering re-entry vehicles (MaRVs) that are capable of hitting moving ships at
sea—a kind of threat the Navy has not previously faced.19 Navy BMD capabilities could also be
used to defend allied or friendly ports, airfields, cities, or forces ashore against enemy TBMs, or
to defend the United States against enemy intercontinental ballistic missiles (ICBMs).20
The CG(X) was expected to feature a new radar, called the Air and Missile Defense Radar
(AMDR), that would be larger and more powerful than the SPY-1 radar on the Navy’s current
Aegis cruisers and destroyers.21
The Navy originally intended to use the DDG-1000 hull design as the basis for the CG(X)
design.22 The potential for reusing the DDG-1000 hull design for the CG(X) was one of the
Navy’s arguments for moving ahead with the DDG-1000 program. In more recent years, however,
the Navy appeared to back away from the idea of reusing the DDG-1000 hull design as the basis
for the CG(X).23

19 For a discussion of potential MaRV-equipped TBMs capable of hitting moving ships at sea, see CRS Report
RL33153, China Naval Modernization: Implications for U.S. Navy Capabilities—Background and Issues for Congress,
by Ronald O'Rourke.
20 For further discussion of the Navy’s BMD program, CRS Report RL33745, Sea-Based Ballistic Missile Defense—
Background and Issues for Congress
, by Ronald O'Rourke.
21 The Navy testified in 2007 that the power requirement of the CG(X) combat system, including the new radar, could
be about 30 or 31 megawatts, compared with about 5 megawatts for the Aegis combat system. (Source: Spoken
testimony of Navy officials to the Seapower and Expeditionary Forces Subcommittee of the House Armed Services
Committee, March 1, 2007.) The CG(X) radar’s greater power would be intended, among other things, to give the
CG(X) more capability for BMD operations than Navy’s Aegis cruisers and destroyers.
22 For example, at an April 5, 2006, hearing, a Navy admiral in charge of shipbuilding programs, when asked what
percentage of the CG(X) design would be common to that of the DDG-1000, stated that:
[W]e haven’t defined CG(X) in a way to give you a crisp answer to that question, because there are
variations in weapons systems and sensors to go with that. But we’re operating under the belief that
the hull will fundamentally be—the hull mechanical and electrical piece of CG(X) will be the same,
identical as DD(X). So the infrastructure that supports radar and communications gear into the
integrated deckhouse would be the same fundamental structure and layout. I believe to
accommodate the kinds of technologies CG(X) is thinking about arraying, you’d probably get 60 to
70 percent of the DD(X) hull and integrated (inaudible) common between DD(X) and CG(X), with
the variation being in that last 35 percent for weapons and that sort of [thing]....
The big difference [between CG(X) and DDG-1000] will likely [be] the size of the arrays for the
radars; the numbers of communication apertures in the integrated deckhouse; a little bit of variation
in the CIC [Combat Information Center—in other words, the] command and control center; [and]
likely some variation in how many launchers of missiles you have versus the guns.
(Source: Transcript of spoken testimony of Rear Admiral Charles Hamilton II, Program Executive
Officer For Ships, Naval Sea Systems Command, before the Projection Forces Subcommittee of
House Armed Services Committee, April 5, 2006. The inaudible comment may have been a
reference to the DDG-1000’s integrated electric-drive propulsion system. Between the two
paragraphs quoted above, the questioner (Representative Gene Taylor) asked: “So the big
difference [between CG(X) and DDG-1000] will be what?”)
23 A July 2, 2008, letter from John Young, the Department of Defense (DOD) acquisition executive (the Under
(continued...)
Congressional Research Service
7

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Section 1012 of the FY2008 defense authorization act (H.R. 4986/P.L. 110-181 of January 28,
2008) makes it U.S. policy to construct the major combatant ships of the Navy, including ships
like the CG(X), with integrated nuclear power systems, unless the Secretary of Defense submits a
notification to Congress that the inclusion of an integrated nuclear power system is not in the
national interest. The Navy studied nuclear power as a design option for the CG(X), but did not
announce whether it would prefer to procure the CG(X) as a nuclear-powered ship. Some press
reports have suggested that a nuclear-powered version of the CG(X) might have a full load
displacement of more than 20,000 tons and a unit procurement cost of $5 billion or more. The
issue of nuclear power for Navy surface ships is discussed in more detail in another CRS report.24
Planned Procurement Schedule
The Navy’s FY2009 budget had called for procuring the first CG(X) in FY2011. Beginning in
late 2008, however, it was reported that the Navy had decided to defer the procurement of the first
CG(X) by several years, to about FY2017.25 Consistent with these press reports, on April 6, 2009,
Secretary of Defense Robert Gates announced—as part of a series of decisions concerning the
Department of Defense’s (DOD’s) proposed FY2010 defense budget—a decision to “delay the
CG-X next generation cruiser program to revisit both the requirements and acquisition strategy”
for the program.26 The Navy’s proposed FY2010 budget deferred procurement of the first CG(X)
beyond FY2015.

(...continued)
Secretary of Defense for Acquisition, Technology and Logistics) to Representative Gene Taylor, the chairman of the
Seapower and Expeditionary Forces subcommittee of the House Armed Services Committee, stated: “I agree that the
Navy’s preliminary design analysis for the next-generation cruiser indicates that, for the most capable radar suites
under consideration [for the CG(X)], the DDG-1000 [hull design] cannot support the radar.” In addition, it is not clear
that the DDG-1000 can accommodate one-half of the twin-reactor plant that the Navy has designed for its new Gerald
R. Ford (CVN-78) class nuclear-powered aircraft carriers. If the DDG-1000 hull cannot accommodate one-half of the
Ford-class plant, then the Navy might face a choice of either designing a new hull for the CG(X) that can accommodate
one-half of the Ford-class plant or designing a new reactor plant that can fit into the DDG-1000 hull.
24 CRS Report RL33946, Navy Nuclear-Powered Surface Ships: Background, Issues, and Options for Congress, by
Ronald O’Rourke.
25 Zachary M. Peterson, “Navy Awards Technology Company $128 Million Contract For CG(X) Work,” Inside the
Navy
, October 27, 2008. Another press report (Katherine McIntire Peters, “Navy’s Top Officer Sees Lessons in
Shipbuilding Program Failures,” GovernmentExecutive.com, September 24, 2008) quoted Admiral Gary Roughead, the
Chief of Naval Operations, as saying: “What we will be able to do is take the technology from the DDG-1000, the
capability and capacity that [will be achieved] as we build more DDG-51s, and [bring those] together around 2017 in a
replacement ship for our cruisers.” (Material in brackets in the press report.) Another press report (Zachary M.
Peterson, “Part One of Overdue CG(X) AOA Sent to OSD, Second Part Coming Soon,” Inside the Navy, September 29,
2008) quoted Vice Admiral Barry McCullough, the Deputy Chief of Naval Operations for Integration of Capabilities
and Resources, as saying that the Navy did not budget for a CG(X) hull in its proposal for the Navy’s budget under the
FY2010-FY2015 Future Years Defense Plan (FYDP) to be submitted to Congress in early 2009.
An earlier report (Christopher P. Cavas, “DDG 1000 Destroyer Program Facing Major Cuts,” DefenseNews.com, July
14, 2008) stated that the CG(X) would be delayed until FY2015 or later. See also Geoff Fein, “Navy Likely To Change
CG(X)’s Procurement Schedule, Official Says,” Defense Daily, June 24, 2008; Rebekah Gordon, “Navy Agrees CG(X)
By FY-11 Won’t Happen But Reveals Little Else,” Inside the Navy, June 30, 2008.
26 Source: Opening remarks of Secretary of Defense Robert Gates at an April 6, 2009, news conference on DOD
decisions relating to DOD’s proposed FY2010 defense budget.
Congressional Research Service
8

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Analysis of Alternatives (AOA)
The Navy assessed CG(X) design options in a study called the CG(X) Analysis of Alternatives
(AOA), known more formally as the Maritime Air and Missile Defense of Joint Forces
(MAMDJF) AOA. The CG(X) AOA was begun in mid-2006 and completed at the end of 2007.
The Navy did not publicly release the results of the CG(X) AOA .
Shifts in Navy Destroyer and Cruiser Acquisition Plans
Rationale for 2008-2009 Shift in Destroyer Procurement Plans
The Navy announced its desire to end DDG-1000 procurement and restart DDG-51 procurement
at a July 31, 2008, hearing before the Seapower and Expeditionary Forces subcommittee of the
House Armed Services Committee. (For the Navy’s prepared statement for the hearing, see
Appendix B.) In testimony at that hearing and subsequent hearings, and in other remarks since
July 2008, Navy officials have stated that they decided to propose ending DDG-1000
procurement and restarting DDG-51 procurement because of a reassessment of threats that Navy
forces are likely to face in coming years. As a result of this reassessment, Navy officials have
stated, the service wants destroyer procurement over the next several years to emphasize three
mission capabilities – area-defense AAW, BMD, and open-ocean ASW. Navy officials have also
stated that they want to maximize the number of destroyers that can be procured over the next
several years within budget constraints. Navy officials state that DDG-51s can provide the area-
defense AAW, BMD, and open-ocean ASW capabilities that the Navy wants to emphasize, and
that while the DDG-1000 design could also be configured to provide these capabilities, the Navy
could procure more DDG-51s than DDG-1000s over the next several years for the same total
amount of funding. In addition, the Navy no longer appears committed to the idea of reusing the
DDG-1000 hull as the basis for the Navy’s planned CG(X) cruiser. If the Navy had remained
committed to that idea, it might have served as a reason for continuing DDG-1000 procurement.
A May 11, 2009, letter from Admiral Gary Roughead, the Chief of Naval Operations, to Senator
Edward Kennedy, the chairman of the Seapower subcommittee of the House Armed Services
Committee, stated:
In response to your letter of October 24, 2008 concerning the Navy’s Long-Range
Shipbuilding Plan and the decision to truncate the DDG-1000 program, I stated in my letter
on January 5, 2009 that I would provide the cost estimates comparisons you requested when
they were developed in conjunction with the Fiscal Year (FY) 2010 Budget.
Specifically, you requested a comparison of “Acquisition Costs for DDG-51s and Modified
DDG-1000s” with design specifications for the Modified DDg-1000 reflecting nominally
equal capability. Table 1 provides a comparison of acquisition cost of Fiscal Year 2010 ship
and average follow ship for a DDG-51 and Modified DDG-1000 based on a multi-hull
procurement in constant FY10 dollars. The cost of 10 additional DDG-51s is less than a 7
ship class of DDG-1000s.
Congressional Research Service
9

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Table 1. [In Navy letter to Congress] Acquisition Costs for DDG-51s and Modified
DDG-1000s
(Costs in CY2010 $B)
Total FY 11 and
Avg Follow (FY11-
FY10 Out
16)
DDG-1000



RDT&E 0.14
1.76

SCN
2.73 2.55
Total 2.87

DDG 51



RDT&E 0.01
0.15

SCN
2.24 1.90
Total 2.25

* Acquisition costs reflect Rough Order of Magnitude (ROM) estimates which reflect
uncertainty in some categories of cost (e.g., amount of software reuse). The acquisition
costs do not reflect the recent DDG 1000/DDG 51 swap agreement.
It is important to discuss the assumptions used in formulating Table 1. Specifically:
• Advanced Gun Systems and associated magazines in the current DDG-1000 design
deleted and additional missile-launch tubes installed in their place.
• Ship and missile modifications as needed for the ship to successfully employ SM-2,
SM-3, and SM-6 missiles and otherwise give the ship a Ballistic Missile Defense
(BMD) and are-defense AAW capability not less than that of Flight IIA DDG-51 with
Advanced Capability 12.
• The primary system differences between the DDG-51 and DDG-1000 ships with respect
to ASW are the bow mounted sonars, the Periscope Detection Radar (PDR) planned for
DDG-1000, and the DDG-1000’s planned lower ship self noise characteristics. There is
a known performance difference at the sensor level between the hull mounted sonars on
the DDG-51 and DDG-1000 ships due to physical size and source level differences
between the ships. The DDG-51 has slightly better performance, but when factoring the
PDR and quieter self noise characteristics, the DDG-1000 could be expected to perform
as well as, or possibly better than the DDG-51 under certain scenarios and acoustic
conditions. At the campaign level when the ship is utilized in fleet ASW tactics in
conjunction with other ship and air assets the magnitude of the performance difference
is unclear. Due to the probability that the difference in performance levels at the
campaign level would be low, I will forgo the detailed analysis and assess the two ships
as equal in this area without modification.
The 10 additional DDG-51s would join an existing fleet force structure of 22 CGs and 62
DDGs. These follow-on DDG-51s build on a common hull and stable combat system
configuration incorporating advanced Integrated Air and Missile Defense (IAMD) and Anti
Submarine Warfare suite optimized for blue water sea base defense. Besides the
enhancements required to gain IAMD capability in DDG-1000, the technical risk and
acquisition costs associated with DDG-1000 are not as well defined as the known cost for the
DDG-51 hull and combat system. Therefore, the additional capacity and capability gained
through continuation of DDG-51s with lower technical risk and defined cost, couple with the
Congressional Research Service
10

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

risks associated with the DDG-1000 make the restart of the DDG-51 line the preferred
choice for affordable warfighting capability and capacity.
Table 2 provides data for your request to compare “Annual O & S Costs for a DDG-51 and a
Modified DDG-1000” in constant FY10 dollars. Although DDG-1000 requires a smaller
crew, comparing the individual element of manning costs between the two ships can be
misleading. DDG-1000 was able to decrease its crew size through increased automation and
by growing shore support primarily to complete maintenance traditionally performed by
ship’s company. Navy is committee to increasing the shore infrastructure to perform this
maintenance however; those added maintenance costs generally negate the savings generated
by the smaller crew size.
Table 2. [In Navy Letter to Congress] Annual O & S Costs for a DDG-51 and a
Modified DDG-1000
(Average O&S/Ship/Year in CY10 $M)
Cost Element
Modified DDG-
Difference (DDG-
DDG-51
1000
51 – DDG-1000)
Operating (steaming), assuming crude [oil] cost of:
$50 per barrel
$6.07
$8.42
$(2.35)
$100 per barrel
$12.14
$16.84
$(4.70)
$150 per barrel
$18.20
$25.26
$(7.05)
Maintenance $20.39 $33.39 $(13.00)
Manpower* $37.34 $17.32 $20.02
Total, Assuming crude oil cost of:
$50 per barrel
$63.80
$59.13
$4.67
$100 per barrel
$69.87
$67.55
$2.32
$150 per barrel
$75.93
$75.97
$(0.04)
Total Crew Size
254 Enlisted, 25
108 Enlisted, 15

Officers
Officers
* Does not account for increased ashore maintenance costs associated with DDG-1000s decreased crew size
Assumptions used in compiling Table 2 included:
• All costs are expressed in constant FY 2010 dollars
• Reflects average annual cost per ship, calculated on a 35 year service life basis.
Includes periodic depot maintenance and fact of life upgrades.
• Annual Fuel Usage rate of 87,373 barrels for DDG-51 and 121,233 barrels for DDG-
1000
• Crew Size is based on the following manning documents:
• DDG-51 FLT IIA Part 3 (DDG 91 – DDG 102) Final Ship Manpower Document, 9
April 2007
Congressional Research Service
11

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

• DDG-1000 Program Preliminary Ship Manpower Document, DCDRL-C.12 Rev b,
Attachment 2, 31 August 2007
• Three additional crew members added to each ship class for BMD
• Reduced manning benefits are best realized over a large class of ships such as LCS
with 55 ships.
In my role as Chief of Naval Operations, I will continue to develop a shipbuilding program
which provides affordable combat capability in sufficient capacity to maintain our position
as the dominant naval power in the world. For less cost and risk, truncating DDG-1000 and
building additional DDG-51s is the clearest path to that end.
Thank you for your continued interest in our shipbuilding program and for your unwavering
support of our Navy. If I can be of any further assistance, please let me know.27
Study of Destroyer Procurement Options for FY2012 and Beyond
The Navy wants to procure one DDG-51 in FY2010 and two more DDG-51s in FY2011. The
Navy’s plans for destroyer procurement in FY2012 and beyond have been unclear. The Navy
since July 2008 has spoken on several occasions about a desire to build a total of 11 or 12 DDG-
51s between FY2010 and FY2015, but the Navy also testified to the Seapower subcommittee of
the Senate Armed Services Committee on June 16, 2009, that it is conducting a study on destroyer
procurement options for FY2012 and beyond that is examining design options based on either the
DDG-51 or DDG-1000 hull form.28 A January 2009 memorandum from the Department of
Defense acquisition executive called for such a study.29
A September 7, 2009, press report stated:
A Navy-commissioned study slated to wrap up this month will determine the required
combination of hull form and radar to combat anti-ship ballistic missiles, a finding that could
lead to the future use of the DDG-1000 platform truncated by the service last year, according
to an August briefing slide by Rear Adm. Frank Pandolfe, the director of surface warfare.
The “DDG hull and radar study” is looking at the “required capability against emerging
threats” and proper “hull/radar combination to meet the requirement,” Pandolfe’s brief states.

27 Letter dated May 11, 2009 from Admiral Gary Roughead to Senator Edward Kennedy, posted on InsideDefense.com
(subscription required) on June 26, 2009.
28 Source: Transcript of spoken remarks of Vice Admiral Bernard McCullough at a June 16, 2009, hearing on Navy
force structure shipbuilding before the Seapower subcommittee of the Senate Armed Services Committee.
29 A January 26, 2009, memorandum for the record from John Young, the then-DOD acquisition executive, stated that
“The Navy proposed and OSD [the Office of the Secretary of Defense] agreed with modification to truncate the DDG-
1000 Program to three ships in the FY 2010 budget submission.” The memo proposed procuring one DDG-51 in
FY2010 and two more FY2011, followed by the procurement in FY2012-FY2015 (in annual quantities of 1, 2, 1, 2) of
a ship called the Future Surface Combatant (FSC) that could be based on either the DDG-51 design or the DDG-1000
design. The memorandum stated that the FSC might be equipped with a new type of radar, but the memorandum did
not otherwise specify the FSC’s capabilities. The memorandum stated that further analysis would support a decision on
whether to base the FSC on the DDG-51 design or the DDG-1000 design. (Memorandum for the record dated January
26, 2009, from John Young, Under Secretary of Defense [Acquisition, Technology and Logistics], entitled “DDG 1000
Program Way Ahead,” posted on InsideDefense.com [subscription required].)
Congressional Research Service
12

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Last summer, the Navy announced its intentions to truncate the DDG-1000 destroyer
program at three hulls and instead buy additional DDG-51 vessels—a decision Chief of
Naval Operations Adm. Gary Roughead touts in his 2010 guidance released last week.
However, in January, then-Defense Department acquisition czar John Young sent a
memorandum to senior Pentagon and Navy officials arguing the Navy’s future destroyer
fleet beyond fiscal year 2011 remained unclear.
“From FY-12 through FY-15, the [Defense Department] will procure guided-missile
destroyers based on either the DDG-51 hull or the DDG-1000 hull,” Young wrote in the Jan.
26 memo, marked “For Official Use Only—Pre-decisional” and sent to senior service and
DOD officials.
Young dubbed the undefined destroyer as the “future surface combatant.”
In June, Navy requirements chief Vice Adm. Barry McCullough told a Senate panel that a
study on future surface ship capabilities was under way, led by Johns Hopkins University.
This study is described in Pandolfe’s brief, a Navy official at the Pentagon confirmed late
last week.
“Along with the [defense secretary] and [the office of the secretary of defense], we’ve
embarked on a study that’s being led by Johns Hopkins University that’s addressing that
right now,” he said. “And from that study, we will see what capability is achievable to get us
at the heart of the threat with limited technical risk and where that best fits with respect to
hull form and then what the best path for the replacement cruiser is to come out of that
study.”
The future surface combatant is not an actual ship, McCullough explained to reporters
following the June hearing.
“When we determine what radar capability we need, then we’ll determine what’s the best
hull form” for future destroyers purchased in FY-12 and beyond, the three-star admiral said.
According to the August briefing, the study will determine the future threat of anti-ship
ballistic missiles and next-generation anti-ship cruise missiles and the required hull and radar
necessary to combat the threat. This will compare the capabilities of the DDG-51 class of
destroyers versus the DDG-1000 class.30
A November 2, 2009, press report stated:
The shape of the U.S. Navy’s next large combatant surface ship could be coming closer into
view, but a key study group working on the question isn’t quite ready to present its findings.
One issue, however, does seem decided: Support for a very large, nuclear-powered cruiser to
carry and power a new ballistic missile defense (BMD) radar may have evaporated, largely
due to its extravagant price tag.
Work on the Hull/Radar Study began in late spring. The effort, carried out under the office of
the chief of naval operations (OP-NAV), was meant to determine the maximum BMD
capability that could be put into a destroyer hull.

30 Zachary M. Peterson, “Navy Slated To Wrap Up Future Destroyer Hull And Radar Study,” Inside the Navy,
September 7, 2009. Material in brackets as in original.
Congressional Research Service
13

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Concurrent with that analysis, the Navy has tasked industry with developing concept studies
for a new radar for the ships, called the Air and Missile Defense Radar (AMDR). Northrop
Grumman, Lockheed Martin and Raytheon are the prime contenders.
The Hull/Radar Study is one of several efforts initiated earlier this year by the Navy to
examine alternatives for the next big warship, latterly called the Future Surface Combatant
and, before that, the CG(X) cruiser. The studies, including efforts by the Johns Hopkins
Advanced Physics Laboratory and the Massachusetts Institute of Technology’s Lincoln
Laboratory, are looking at ways to meet the Navy’s requirements for sea-based ballistic
missile defense, as well as traditional surface warships roles including defense of carrier and
expeditionary strike groups.
But the Hull/Radar Study has, according to sources, become the centerpiece of Chief of
Naval Operations Adm. Gary Roughead’s effort to choose a capable and affordable ship to
meet the Navy’s needs. Those same sources also caution about an internal Pentagon debate
over the various studies.
The Hull/Radar Study has, said one source, been viewed by the Navy as the “decisional
study” for the question of the next surface combatant.
But staffers working for Ashton Carter, the Pentagon’s top weapon buyer, reportedly
“believe the right answer will be from the sum of all the studies,” the source said.
Work on the AMDR, the source added, largely is being done under directives laid out by
John Young, whom Carter replaced in April.
The issue could be put to the test soon. Over the past three weeks, Navy officials have been
briefing key parties on Capitol Hill and in industry on the state of the Hull/Radar Study. No
timetable has been revealed for completion of the study, but one Pentagon source said Oct.
30, “it’s real close.” The issues at stake are complex.
The costs to design and develop a new hull are high, and Naval Sea Systems Command is
working to base future ships on as few hull designs as possible. Hull choices on which to
build the new ship are the DDG 51 destroyer hull developed in the 1980s, and the DDG 1000
hull designed over the past decade for the new Zumwalt-class destroyers.
The basic DDG 51 hull is just over 500 feet long and 67 feet wide, while the DDG 1000 hull
is 600 feet long with a beam of 81 feet. The characteristics of the DDG 51 hull are well
understood, while the tumblehome hull of the DDG 1000, meant to slice through waves
rather than ride over them, has stirred controversy in some quarters. No similar hull has been
constructed, and some engineers worry about potential stability problems, although Navy
designers maintain steadfastly that extensive computer and test-tank modeling has shown no
stability concerns.
Radar To Combat Missiles
The new radar is meant to form the basis for the next-generation combat system, intended
from the outset to combat ballistic missiles.
Northrop Grumman, Lockheed Martin and Raytheon each were awarded $9.9 million
contracts on June 26 to conduct concept stud-ies for the AMDR, but those agreements expire
in December. For the work’s next phase, the Navy on Oct. 26 posted a notice of its intent to
solicit up to three technology development contracts for the AMDR.
Congressional Research Service
14

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

The notice, posted on the Federal Business Opportunities Web site, calls the effort a “full
and open competition,” but Navy and industry sources said the three original contractors
would likely each receive a request for pro-posal for the new contract.
The new radar system is a dual-band radar system, including S-band and X-band radars and
their Radar Suite Controller (RSC). The S-band AMDR-S is to provide volume search,
tracking, BMD discrimination and missile communications. The AMDR-X will provide
horizon search, precision tracking, missile communication and terminal illumination.
The new solicitation announced Oct. 26 will cover the RSC and the AMDR-S radar.
The Hull/Radar Study’s decision to move away from the big, nuclear cruiser—dubbed
CGNX—was based on a reassessment of the threat, said one source briefed by the Navy.
“They can’t afford it, nor do they think they need it,” the Capitol Hill source said. “They
don’t think the scenarios on which the big cruiser was the answer are realistic.” Those
scenarios, the source said, envisioned “very large-sized raids of incoming missiles,” a threat
now considered less likely.
The potential price tag for such a ship—which would be the biggest surface warship built by
the U.S. Navy since World War II—is also exceptionally daunting, with unofficial estimates
running as high as $7 billion a copy, or nearly the price of an aircraft carrier.
The study so far is “strictly an analytical effort,” the source said, with “no conclusions or
recommendations yet.” As to which hull would get the go-ahead nod, another source
re-ported the study concluded that the “DDG 51 couldn’t provide the power and cooling”
capacity for a large and sensitive radar.
But the Capitol Hill source said that “both ships are equally in the running, although I think
they’re steering themselves toward the DDG 51. It’s cheaper and no less capable in a number
of dimensions—detection, intercept capability, combat system. And it’s considered less
technically risky.”31
Reported Plan to Stop CG(X) in Favor of Procuring Improved DDG-51s
On December 7, 2009, it was reported that the Navy wants to cancel the CG(X) and instead
procure improved DDG-51s. Earlier press reporting had suggested that the Navy might be
heading toward such a change in plans. The Navy reportedly was concerned about the projected
high cost of the CG(X), and has concluded that it does not need a ship as capable as the CG(X) to
adequately perform future anti-air warfare (AAW) and ballistic missile defense (BMD) missions.
The improved DDG-51 that the Navy reportedly now wants to procure would be considerably
less expensive to procure than the CG(X). The improved DDG-51 would have more AAW and
BMD capability than the current DDG-51 design, but less AAW and BMD capability than what
was envisioned for the CG(X).
A December 7, 2009, press report stated:

31 Christopher P. Cavas, “Next-Generation U.S. Warship Could Be Taking Shape,” Defense News, November 2, 2009:
18, 20.
Congressional Research Service
15

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

The Navy will kill the CG(X) cruiser program and instead develop new warships based on
the design of Arleigh Burke-class DDG-51 destroyers, according to a draft report the service
is preparing for Congress.
The long-term shipbuilding report, due to Congress in February, says unaffordable cost
estimates and immature technology doomed the CG(X) program, which was supposed to fill
a critical role in integrated air and missile defense. Inside the Navy reviewed a copy of the
draft, which is labeled “for official use only—pre-decisional information—not for release
outside the Navy.”
The Navy’s fiscal year 2009 budget plan called for buying the first CG(X) cruiser in FY-11,
but eight months ago Defense Secretary Robert Gates announced officials would delay the
program to revisit its requirements and acquisition strategy. This summer, Chief of Naval
Operations Adm. Gary Roughead asserted the Navy might still buy CG(X) cruisers.
“I would say that CG(X) could be the next surface combatant,” the admiral told reporters
June 30 after a speech in Washington, DC.
But that is not going to happen, according to the new draft report. Due to “the ship’s
projected high cost and [the] immaturity of its combat systems technology and design, the
Navy has determined that it is not in the department’s best interest to pursue CG(X)
procurement,” the report states.
“However, it will be critical to pursue the technology development and combat system
design for application on a smaller combatant such as a DDG-51 variant,” the report
continues.
The new move to kill CG(X) follows the Navy’s dramatic decision last year to truncate the
Zumwalt-class DDG-1000 destroyer program. The DDG-1000s were intended to support
integrated air and missile defense but the service decided it was more affordable and efficient
to restart the DDG-51 program.
The Navy is buying nine DDG-51s from FY-10 to FY-15 and anticipates adding an
integrated air and missile defense capability to new DDG-51s as early as FY-16, the report
states. These upgraded DDG-51s will be modifications of the current design, combining the
“best emerging technologies” aimed at further increasing integrated air and missile defense
capabilities and providing a “more effective bridge between today’s capability and what had
been planned for CG(X), the service writes.
While the Navy has “much work” to do to determine the final design, the service envisions
the DDG-51 variant having “upgrades to radar and computing performance with the
increased power-generation capacity and cooling required by these enhancements,” the
report states. The report also states procurement of a new class of DDG(X) destroyers will
begin in FY-23 “and is anticipated to be a modification to legacy ship designs.”...
Future destroyers will have upgraded radar technologies leveraging development of the
Advanced Missile Defense Radar (AMDR) that will provide increased integrated air and
missile defense capability and will be “much more capable” than today’s DDG-51s, the
report states. Northrop Grumman, Lockheed and Raytheon are the prime contractors for this
radar. The AMDR envisioned for DDG-51s will be physically smaller than the system
previously planned for CG(X), said the source.32

32 Christopher J. Castelli, “Draft Shipbuilding Report Reveals Navy Is Killing CG(X) Cruiser Program,” Inside the
(continued...)
Congressional Research Service
16

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

A December 11, 2009, press report stated:
Improved confidence in the performance of the U.S. Missile Defense Agency’s (MDA) new
midcourse tracking anti-ballistic missile satellites is allowing Navy officials to curtail
ambitious requirements for their next-generation cruiser program.
This will allow for development of a less expensive system, which is more likely to garner
support as the Pentagon is stretched to continue funding wars in Iraq and Afghanistan. In
September, MDA launched the first two Northrop Grumman Space Tracking and
Surveillance Satellites (STSS), designed to plug the persistent gap in tracking ballistic
missiles in their midcourse of flight. This is when warheads separate from their hot boosters,
which are easier to track with infrared sensors. The warheads, which are far cooler, arc
through space and begin to re-enter the atmosphere, and this phase of flight has been a
challenge for U.S. defenses.
STSS originally began as the Space-Based Infrared System Low and was renamed when it
shifted from the Air Force to MDA. Parts for the satellites had been in storage as the
program shifted hands, but MDA later threw its support behind the effort. Officials are still
checking the performance of the satellites in orbit, but expectations are high.
“MDA picked up the bucket of bolts, they put it together and they launched it,” said Vice
Adm. Barry McCullough, the Navy’s new cyber command chief, speaking last week at an
Aviation Week/Credit Suisse Aerospace & Defense Finance conference here. “I have a lot
more faith in the ability of that program to mature and produce than I did three-and-a-half
years ago.” At the time he conducted his interview with Aviation Week at the conference,
McCullough was the chief of naval operations for integration of capabilities and resources.
“When we started the [analysis of alternatives] for CG(X), we laid out as an initial condition
or assumption that it would have to operate autonomously because the STSS was in total
disarray,” McCullough said, noting the technology was “immature” for a radar sophisticated
enough to identify and track high-end targets by itself. “For us to assume we could put it into
a ship and get a radar system delivered to a ship in 2014 or 2015—it just wasn’t going to
happen,” he says. During his presentation to Wall Street analysts, McCullough noted that the
objective radar would be massive—at least 2 feet larger than the Aegis SPY-1 radar at
roughly 22 ft. in diameter. The cost for this system was estimated at $5 billion per unit.33
“Given [STSS] and given what happened with other parts of the sensor architecture, we think
we could go with a lesser sensitivity radar,” he adds.
This will call for a less costly approach and the program will be more likely to deliver ships
when needed. McCullough says Navy officials are now looking at a ship radar roughly 12-14
feet in diameter.34
For additional information on potential DDG-51 and DDG-1000 design variants, including
variants with an improved radar, see Appendix D.

(...continued)
Navy, December 7, 2009.
33 This figure appears to refer to the projected unit procurement cost of the entire CG(X), not unit procurement cost of
the CG(X) radar.
34 Amy Butler, “STSS Prompts Shift in CG(X) Plans,” Aerospace Daily & Defense Report, December 11, 2009: 1-2.
Congressional Research Service
17

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Surface Combatant Construction Industrial Base
Shipyards
All cruisers, destroyers, and frigates procured since FY1985 have been built at GD/BIW of Bath,
ME, and the Ingalls shipyard in Pascagoula, MS, that forms part of NGSB.35 Both yards have
long histories of building larger surface combatants. Construction of Navy surface combatants in
recent years has accounted for virtually all of GD/BIW’s ship-construction work and for a
significant share of Ingalls’ ship-construction work. (Ingalls also builds amphibious ships for the
Navy.) Navy surface combatants are overhauled, repaired, and modernized at GD/BIW, NGSB,
other private-sector U.S. shipyards, and government-operated naval shipyards (NSYs).
Combat System Manufacturers
Lockheed Martin and Raytheon are generally considered the two leading Navy surface combatant
radar makers and combat system integrators. Northrop Grumman is a third potential maker of
Navy surface combatant radars. Lockheed is the lead contractor for the DDG-51 combat system
(the Aegis system), while Raytheon is the lead contractor for the DDG-1000 combat system, the
core of which is called the Total Ship Computing Environment Infrastructure (TSCE-I). Lockheed
has a share of the DDG-100 combat system, and Raytheon has a share of the DDG-51 combat
system.
Supplier Firms
The surface combatant industrial base also includes hundreds of additional firms that supply
materials and components. Many of the suppliers for the DDG-1000 program are not suppliers for
the DDG-51 program, and vice versa. The financial health of Navy shipbuilding supplier firms
has been a matter of concern in recent years, particularly since some of them are the sole sources
for what they make for Navy surface combatants.
FY2010 Funding Request
DDG-51 Program
The Navy’s proposed FY2010 budget requested $1,912.3 million for the procurement of a DDG-
51. The Navy estimates the total cost of this ship at $2,240.3 million. The ship received $199.4
million in FY2009 advance procurement funding, and the Navy plans to request approval to
transfer or reprogram $128.6 million in prior-year funding to help complete the ship’s cost. The
Navy’s proposed FY2010 budget also requested $329.0 million in advance procurement funding
for two more DDG-51s to be procured in FY2011.

35 NGSB also includes the Avondale shipyard near New Orleans, Newport News Shipbuilding of Newport News, VA,
and a fourth facility, used for manufacturing ship components and structures made from composites, at Gulfport, MS.
Congressional Research Service
18

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

DDG-1000 Program
The Navy’s proposed FY2010 budget requested $1,084.2 million to complete the cost of the third
DDG-1000, and $309.6 million in additional procurement funds to cover cost growth on the first
two DDG-1000s, which were authorized in FY2007 and funded in FY2007-FY2008. The Navy
estimates the combined procurement cost of the first two DDG-1000s at $6,634.2 million, or an
average of $3,317.1 million each, and the procurement cost of the third ship at $2,738.3 million.
The Navy’s proposed FY2010 budget also requested $539.1 million in research and development
funding for the DDG-1000 program.36
CG(X) Program
The Navy’s proposed FY2010 budget requested $340.0 million in research and development
funding for the CG(X) program. Of this total, $190.0 million is for developing the CG(X)’s new
radar (the AMDR), and $150.0 million is for research and development work on the ship in
general.
Issues for Congress
Potential issues for Congress arising from the Navy’s reported desire to cancel the CG(X) and
instead procure improved DDG-51s include the following:
• Is there an adequate analytical basis for canceling the CG(X) and instead
procuring improved DDG-51s? Should an analysis of alternatives (AOA) or the
equivalent of an AOA be performed before committing to this course of action?
• Is there adequate stability in Navy planning for acquisition of surface
combatants?
• Would an improved DDG-51 be an adequate substitute for the CG(X)?
• What would be the potential operational implications of a Navy equipped with
improved DDG-51s instead of CG(X)s?
• What would be the potential industrial-base consequences of canceling the
CG(X) and instead procuring improved DDG-51s?
• What would be some potential alternatives to canceling the CG(X) and instead
procuring improved DDG-51s?
Each of these is discussed below.

36 DDG-1000 research and development funding is located in the Navy’s research and development account in Program
Element (PE) 0204202N, entitled DDG-1000. This PE is line item 135 in the Navy’s FY2010 research and
development account.
Congressional Research Service
19

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Analytical Basis for Canceling CG(X) in Favor of Improved DDG-
51s

Is there an adequate analytical basis for canceling the CG(X) and instead procuring improved
DDG-51s? Should an analysis of alternatives (AOA) or the equivalent of an AOA be performed
before committing to this course of action?

The issue of whether there is an adequate analytical basis for canceling the CG(X) and instead
procuring improved DDG-51s is somewhat similar to an issue raised by CRS several years ago as
to whether there was an adequate analytical basis for the Navy’s decision that a ship like the
LCS—a small, fast ship with modular payload packages—would be the best or most cost-
effective way to fill gaps the Navy had identified in its capabilities for countering submarines,
small surface attack craft, and mines in heavily contested littoral areas.37 The Navy eventually
acknowledged that, on the question of what would be the best approach to fill these capability
gaps, “the more rigorous analysis occurred after the decision to move to LCS.”38
Those who believe there is an adequate analytical basis for canceling the CG(X) and instead
procuring improved DDG-51s could argue that procuring improved DDG-51s would represent an
extension of the proposal debated by DOD and Congress in 2008-2009 to end procurement of
DDG-1000 destroyers and restart procurement of DDG-51 destroyers, and therefore does not
amount to the initiation of a new shipbuilding program that would require an AOA or the
equivalent of an AOA. They can also argue that the Navy’s desire to cancel the CG(X) and
instead procure improved DDG-51s reflects substantial analytical work in the form of the CG(X)
AOA, additional Navy studies that were done to support the 2008-2009 proposal to end DDG-
1000 procurement and restart DDG-51 procurement, and a recent Navy destroyer Hull/Radar
study that examined options for improving the AAW and BMD capabilities of the DDG-51 and
DDG-1000 destroyer designs through the installation of an improved radar and combat system
modifications.
Those who question whether there is an adequate analytical basis for the Navy’s reported new
plan could argue that procuring modified DDG-51s until FY2023 represents a significant change
from the plan debated in 2008-2009 to procure non-modified DDG-51s until about FY2017.
Given the scope of modifications to the DDG-51 design and the number of years that the
modified DDG-51s would be procured, they could argue, the Navy’s reported new plan amounts
to the initiation a new shipbuilding program that would require an AOA or the equivalent of an

37 See, for example, the September 5, 2002, update of CRS Report RS21305, Navy Littoral Combat Ship (LCS):
Background and Issues for Congress
, by Ronald O’Rourke, or the October 28, 2004, and the October 28, 2004, update
of CRS Report RL32109, Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress,
by Ronald O'Rourke.
38 Spoken testimony of Vice Admiral John Nathman, Deputy Chief of Naval Operations (Warfare Requirements and
Programs), at an April 3, 2003 hearing on Navy programs before the Projection Forces subcommittee of the House
Armed Services Committee. At this hearing, the chairman of the subcommittee, Representative Roscoe Bartlett, asked
the Navy witnesses about the Navy’s analytical basis for the LCS program. The witnesses defended the analytical basis
of the LCS program but acknowledged that “The more rigorous analysis occurred after the decision to move to LCS.”
See U.S. Congress, House Committee on Armed Services, Subcommittee on Projection Forces, Hearing on National
Defense Authorization Act for Fiscal Year 2004—H.R. 1588, and Oversight of Previously Authorized Programs
. 108th
Cong., 1st sess., Mar. 27, and Apr. 3, 2003, (Washington: GPO, 2003), p. 126. For an article discussing the exchange,
see Jason Ma, “Admiral: Most LCS Requirement Analysis Done After Decision To Build,” Inside the Navy, Apr. 14,
2003.
Congressional Research Service
20

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

AOA. They could also argue that the CG(X) AOA focused mainly on examining radar and hull-
design options for a cruiser with a large and powerful radar, as opposed to radar- and hull-design
options for a smaller modified destroyer with a smaller and less powerful radar, and that Navy
studies supporting its 2008-2009 proposal to stop DDG-1000 procurement and restart DDG-51
procurement were challenged by outside observers (particularly DDG-1000 supporters). They
could argue that the Navy’s recent destroyer Hull/Radar study was focused on answering a
somewhat narrowly defined question: What would be the lowest-cost option for improving the
AAW and BMD performance of a DDG-51 or DDG-1000 by a certain amount through the
installation of an improved radar and an associated modified combat system? An adequate
analytical basis for a proposed program change of this magnitude, they could argue, would
require an AOA or equivalent study that rigorously examined a broader question: Given projected
Navy roles and missions, and projected Navy and DOD capabilities to be provided by other
programs, what characteristics of all kinds (not just AAW and BMD capability) are needed in
surface combatants in coming years, and what is the most cost-effective acquisition strategy to
provide such ships?
Stability in Navy Surface Combatant Acquisition Planning
Is there adequate stability in Navy planning for acquisition of surface combatants?
Navy plans for acquisition of surface combatants have experienced multiple shifts since the mid-
1990s. The sequence can be summarized as follows:
From the mid-1990s until November 1, 2001, Navy plans called for a family of
surface combatants called SC-21 (meaning Surface Combatant for the 21st
Century) that included a new destroyer called DD-21 and a projected eventual
new cruiser called CG-21. Navy plans did not include a ship like the LCS, and
the Navy politely resisted proposals that were made starting in the late 1990s for
the service to acquire a small, fast surface ship that was called Streetfighter.
On November 1, 2001, the Navy announced a plan for a new family of ships that
included the DDG-1000 (a restructured version of the DD-21 program), the
CG(X), and the LCS. The Navy over the next several years argued strongly in
favor of stopping DDG-51 procurement and starting DDG-1000 procurement.
On July 31, 2008, the Navy essentially reversed itself by announcing that it
wanted to stop DDG-1000 procurement, which had begun in FY2007, and restart
DDG-51 procurement, which had ended in FY2005. The DDG-51s the Navy
wanted to procure would not feature significant design modifications, and they
would be procured until the start of CG(X) procurement around FY2017.
On December 2, 2009, it was reported that the Navy now wants to cancel the
CG(X) program and instead procure modified DDG-51s until FY2023.
Given the Navy’s 2008-2009 proposal to stop DDG-1000 procurement, the reported new Navy
proposal to cancel the CG(X), if implemented, would represent a change of mind by the Navy
regarding two of the three programs the Navy announced on November 1, 2001. While the Navy
remains committed to the third program announced on November 1, 2001—the LCS—that
program has experienced multiple shifts in procurement profile and acquisition strategy. The
above sequence of events, combined with the shifts that have occurred in the LCS procurement
Congressional Research Service
21

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

profile and acquisition strategy, raise a question as to whether there is adequate stability in Navy
planning for acquisition of surface combatants.
Those who believe that there is adequate stability in Navy planning for acquisition of surface
combatants could argue that changes in Navy plans since the mid-1990s were made to adapt those
plans to changing strategic and budgetary circumstances, including the identification of capability
gaps for littoral warfare (which led to the LCS program), a change in threat assessments and thus
in the kinds of mission capabilities that would need to be emphasized in future destroyers (which
led to the 2008-2009 proposal to stop DDG-1000 procurement and restart DDG-51 procurement),
and a revised understanding of what the Navy needed, and could afford, in terms of a future ship
with improved AAW and BMD capability (which led to the reported proposal to cancel the
CG(X) and instead procure modified DDG-51s). They could argue that although these changes
caused turbulence in Navy planning for acquisition of surface combatants, they were each well-
considered, and that the alternative of not implementing these changes would have led to a bigger
problem—a future surface combatant force that was both unaffordable and poorly aligned with
projected mission needs.
Those who believe that there is inadequate stability in Navy planning for acquisition of surface
combatants could argue that although there have been shifts in strategic and budgetary
circumstances since the mid-1990s, the Navy’s responses to these shifts have been unnecessarily
turbulent, in part because the Navy was slow to recognize the prospective unaffordability of its
baseline plans. They could argue that given the changes in strategic and budgetary circumstances
that have accumulated since the mid-1990s, the Navy should now step back and examine on a
holistic basis what kind of surface combatant force it needs to have in the future, and what the
most cost-effective path would be to achieve that force, before committing to any further changes
in plans.
Adequacy of Improved DDG-51 as Substitute for CG(X)
Would an improved DDG-51 be an adequate substitute for the CG(X)?
The improved DDG-51 that the Navy reportedly now wants to procure would have more AAW
and BMD capability than the current DDG-51 design, but less AAW and BMD capability than
was envisioned for the CG(X), in large part because the improved DDG-51 would be equipped
with a new radar that would have more sensitivity than the radar on current DDG-51s, but less
sensitivity than the large and powerful new radar envisioned for the CG(X). The CG(X) was also
envisioned as likely having more missile-launch tubes than the DDG-51 or improved DDG-51.
Supporters of the Navy’s reported plan to cancel the CG(X) and instead procure improved DDG-
51s could argue that a radar as large and powerful as the one envisioned for the CG(X) is no
longer needed because the projected enemy missile raid size—the number of simultaneous or
near-simultaneous enemy anti-ship missiles to be countered—has been revised downward, and
because recent improvements in the management of a U.S. program to provide a network of
space-based radars permits the Navy to now have more confidence that these space-based radars
will be available to supplement the Navy’s ship-based radars for purposes of conducting AAW
and BMD operations. (See the November 2, 2009, and December 11, 2009, press reports that are
reprinted above in the section entitled ““Shifts in Navy Destroyer and Cruiser Acquisition
Plans.”)
Congressional Research Service
22

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Skeptics of the Navy’s reported plan to cancel the CG(X) and instead procure improved DDG-51s
could argue that this plan poses potentially unacceptable risks because its provides less cushion
against the possibility of an adversary increasing missile raid size above newly projected levels
by building additional missiles, and because the plan is dependent on space-based radars and
radar-data communications links that could be vulnerable to enemy attack. Skeptics could also
argue that the improved DDG-51 the Navy reportedly is contemplating could not be fitted in the
future with a high-power directed-energy weapon (DEW), such as a laser, because the ship would
lack the electrical power such a weapon would require. Skeptics could argue that since DEWs
could be critical to the Navy’s long-term ability to affordably counter enemy anti-ship cruise
missiles (ASCMs) and anti-ship ballistic missiles (ASBMs),39 improved DDG-51s, though less
expensive to procure than CG(X)s, could lock the Navy into a DEW-less approach to AAW and
BMD that might ultimately be unaffordable for the Navy to sustain in a competition against a
wealthy and determined adversary.
An improved DDG-51 might have a larger radar cross section (i.e., be less stealthy) than a
CG(X). In a surface combatant, having a larger radar cross section can reduce the effectiveness of
ship-launched decoys that are intended to confuse the radars in the nose cones of incoming
ASCMs and ASBMs. An improved DDG-51 might also have less survivability than a CG(X) (i.e.,
less capacity for withstanding battle damage).
Potential Operational Implications
What would be the potential operational implications of a Navy equipped with improved DDG-
51s instead of CG(X)s?

Supporters of the Navy’s reported plan to cancel the CG(X) and instead procure improved DDG-
51s could argue that procuring improved DDG-51s rather than CG(X) could enhance the Navy’s
operational flexibility because the lower unit capability offered by each improved DDG-51 would
be more than offset by the higher number of improved DDG-51s that could be procured for a
given amount of funding. Skeptics could argue that the Navy’s reported plan could reduce the
Navy’s operational flexibility because the Navy would lack a ship capable of operating in certain
very high-threat locations that might be of interest, and because the Navy in general might need
to exercise greater overall caution about where and when it operates its surface combatants. In
addition, as discussed in the previous section, a fleet equipped with improved DDG-51s rather
than CG(X)s might have less operational resiliency in the event of enemy attacks on U.S. space-
based radars or radar-data communications links.
The Navy’s 22 Aegis cruisers are equipped with flag command facilities for coordinating certain
operations, and the CG(X) likely would have included an updated version of such facilities. The
current DDG-51 design does not include such facilities, and it is not clear that an improved DDG-
51 would have them, since these facilities require a certain amount of interior volume. If an

39 The cost for an adversary to build and field an additional land-based ASCM or ASBM might be much less than the
cost for the Navy to build and field an additional sea-based missile-launch tube and procure an additional interceptor
missile to place in that tube. If so, then it might become unaffordable for the Navy at some point in the future to match
each additional ASCM and ASBM that a wealthy and determined adversary might field with an additional launch tube
and interceptor missile. DEWs, if successfully developed, promise to reverse this unfavorable cost equation by
lowering the marginal cost per shot for intercepting ASCMs and ASBMs to a level well below what it costs an enemy
to build an additional ASCM or ASBM.
Congressional Research Service
23

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

improved DDG-51 does not include such facilities, then replacing the 22 Aegis cruisers with
improved DDG-51s could lead to a future surface combatant force with reduced numbers of ships
with flag command facilities for coordinating certain kinds of operations.
Potential Industrial-Base Consequences
What would be the potential industrial-base consequences of canceling the CG(X) and instead
procuring improved DDG-51s?

Radar and Combat System Makers
Procuring the CG(X) would provide an opportunity for the Navy to conduct a competition
between Lockheed and Raytheon (and perhaps other firms) to be the lead contractor on the
CG(X) combat system. Canceling the CG(X) and instead procuring improved DDG-51s would
mean that Lockheed would continue its current status as the lead contractor of Navy cruiser and
destroyer combat systems.
Procuring the CG(X) would provide the Navy with an opportunity to conduct a competition
between Lockheed, Raytheon, and Northrop to build the CG(X)’s large and powerful new radar.
Procuring an improved DDG-51 would provide the Navy with an opportunity to conduct a similar
competition between these three firms for the improved DDG-51’s somewhat smaller and less
powerful new radar.
Shipyards
Some, and perhaps much, of the shipyard work associated with building a nuclear-powered
version of the CG(X) could be assigned to Grumman Newport News (NGNN)—a shipyard in
Newport News, VA , that forms part of NGSB—because NNGN is currently the only shipyard in
the country certified to build nuclear-powered surface ships for the Navy. (NGNN builds nuclear-
powered aircraft carriers and nuclear-powered attack submarines, the latter along with General
Dynamics’ Electric Boat Division of Groton, CT, and Quonset Point, RI.) All of the shipyard
work associated with building either a conventionally powered CG(X) or an improved DDG-51
(which, like the current DDG-51, would be conventionally powered) could be performed by
GD/BIW and the Ingalls yard that forms part of NGSB.
The ultimate volume of work performed by various shipyards as a result of building either
nuclear-powered CG(X)s, conventionally powered CG(X), or improved DDG-51s would depend
in part on the numbers of such ships that the Navy could afford to procure for a given portion of
the Navy’s shipbuilding budget. Although building a single conventionally powered CG(X)
would likely provide GD/BIW and/or the Ingalls yard more work than building a single improved
DDG-51, the Navy would likely be able to procure a larger number of DDG-51s for a given
portion of the Navy’s shipbuilding budget.
Nuclear Propulsion Component Manufacturers
Procuring a nuclear-powered version of the CG(X) would provide additional work for nuclear
propulsion component manufacturers. It would increase economies of scale in the production of
Congressional Research Service
24

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

nuclear propulsion components for all Navy ships, reducing by a few or several percent the cost
of nuclear propulsion components manufactured for the Navy’s aircraft carriers and submarines.
Potential Alternatives to Reported Navy Plan
What would be some potential alternatives to canceling the CG(X) and instead procuring
improved DDG-51s?

Potential alternatives to canceling the CG(X) and instead procuring improved DDG-51s include
but are not limited to those discussed below.
Continue CG(X) program
This option would maintain the Navy’s previous plan of procuring non-modified DDG-51s until
the start of CG(X) procurement around FY2017.
Procure a More Highly Modified DDG-51
This option would cancel the CG(X) and procure a version of the DDG-51 with more substantial
modifications than what the Navy appears to be contemplating. This more highly modified DDG-
51 would have enough electrical power to support the future installation of a high-power directed
energy weapon (DEW) such as a laser. It might also include features for reducing crew size,
which would reduce the ship’s annual operating and support (O&S) cost. Installing enough
electrical power to support the future installation of a high-power DEW such as a laser might well
require lengthening the DDG-51 hull so as to provide the additional space and weight-carrying
capacity that the added electrical-generating capacity might require. As discussed in Appendix D,
the current DDG-51 hull might be lengthened by as much as 55 or 56 feet.
Procure a Modified DDG-1000
This option would cancel the CG(X) and procure a modified version of the DDG-1000 destroyer
with an improved radar and combat system modifications for improved AAW and BMD
capability. A modified DDG-1000 would have enough electrical power to support the future
installation of a high-power DEW such as a laser. The idea of a modified DDG-1000 with an
improved radar and combat system modifications for improved AAW and BMD capability is
discussed in Appendix D.
Procure a Cost-Constrained New-Design Destroyer
This option would cancel the CG(X) and procure non-modified DDG-51s while developing a
cost-constrained new-design destroyer that might begin procurement around FY2017. The new-
design destroyer would be less expensive to procure and have less AAW and BMD capability
than the CG(X), but more AAW and BMD capability than the modified DDG-51 and enough
electrical power to support the future installation of a high-power DEW such as a laser. Table 3
outlines one possible approach for developing a cost-constrained new-design destroyer.
Congressional Research Service
25

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Table 3. Possible Approach for a Cost-Constrained New-Design Destroyer
Cost or Ship Characteristic
New-Design Destroyer
Development cost
Minimize al development costs: Minimize hul -design cost by
leveraging, where possible, existing surface combatant hull designs.
Minimize combat system development cost by using a modified
version of the DDG-51 or DDG-1000 combat system. Minimize
other development costs by using no technologies not already on, or
being developed for, the DDG-51, the reported modified DDG-51,
or the DDG-1000. A possible exception would be technologies, such
as motor and power-electronics technologies, that would enable an
integrated electric drive system that is more compact than that on
the DDG-1000.
Procurement cost
Constrain unit procurement cost: Establish a unit procurement cost
target that is not more than 10% above the unit procurement cost of
the current DDG-51 design. In support of this goal, limit the new
destroyer’s ful load displacement to 10,000 to 11,000 tons
(compared to 9,500 tons for the DDG-51), and incorporate design
features (such as those employed in the DDG-1000 design) for
enhancing producibility and reducing construction cost per ton.
Annual operation and support (O&S) cost
Constrain annual O&S cost: Establish an annual O&S cost target that
is not more than, and perhaps less than, the annual O&S cost of the
current DDG-51 design. In support of this goal, incorporate design
features (such as those employed in the DDG-1000 design) to reduce
crew size.
Radar size and power, and resulting AAW
Design the ship to accommodate a radar that is larger and more
and BMD capability
powerful than what can be accommodated on the DDG-51, but
smaller and less powerful than what was envisioned for the CG(X),
so as to achieve an AAW and BMD capability greater than that of the
reported modified DDG-51, but less than that of the CG(X).
Electrical power
Design the ship with sufficient electrical power to support future
installation of a high-power directed-energy weapon (DEW), such as
a laser.
Radar cross section
Design the ship to have a radar cross section not greater than that of
DDG-51, and possibly less than that of a DDG-51, if the latter can be
achieved without increasing development and procurement cost.
Survivability (ability to withstand battle
Design the ship with a level of survivability not less than that of the
damage)
DDG-51.
Source: Prepared by CRS based on Navy data and press reports.
A cost-constrained new-design destroyer might be considered broadly analogous to the Virginia
(SSN-774) class attack submarine, which the Navy developed in the 1990s as a more affordable
successor to the Seawolf (SSN-21) attack submarine design. The Virginia-class design is smaller
and more affordable than the Seawolf class design, but more capable than the Improved Los
Angeles (Improved SSN-688 or 688I) class attack submarine that was procured prior to the
Seawolf class. Procurement of the Seawolf-class design was stopped after three ships due to the
design’s high unit procurement cost and questions about the need for such a heavily armed attack
submarine in the post-Cold War era—an assessment that might be considered somewhat similar
to the Navy’s reported concerns about the CG(X)’s projected high unit procurement cost and the
Navy’s reported new belief that it no longer needs a ship with a very high amount of autonomous
AAW and BMD capability. Following the decision to end of Seawolf procurement, the Navy,
Congressional Research Service
26

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

rather than developing and procuring improved version of the 688I design, instead developed and
procured a cost-constrained new-design attack submarine—the Virginia class.40
Backfit Existing DDG-51s with Improved Radars
This option would backfit existing DDG-51s with the improved radar and combat system
modifications that the Navy appears to be contemplating for the modified DDG-51s that it
reportedly wants to build in coming years. This option could be combined with the Navy’s
reported plan to cancel the CG(X) and procure modified DDG-51s with these same changes, or
with any of the above-described potential alternatives to that plan.
FY2010 Legislative Activity
Summary of Action on Funding Request
Table 4 summarizes action on FY2010 funding requests for the DDG-1000 and DDG-51
programs.
Table 4. Summary of Action on FY2010 Funding Request
Millions of dollars

Authorization
Appropriation
Item
Request HASC SASC conference
HAC SAC conference
Procurement funding
Procurement of third
1,084.2 1,084.2 1,084.2
1,084.2 1073.2 1,393.8a 1,382.8a
DDG-1000 in FY2010
Cost growth on first
309.6 159.6 309.6
309.6 309.6
0a
0a
two DDG-1000s
Procurement of one
1,912.3 1,912.3 1,912.3
1,912.3 1,912.3 3,650.0b 1,912.3
DDG-51 in FY2010
Advance procurement
329.0 429.0 329.0
329.0 329.0 329.0
579.0
funding for two DDG-
51s in FY2011
Research and development funding
DDG-1000 program
539.1
539.1
539.1
539.1
539.1
526.5
526.5
Sources: Bill language, committee reports, and conference reports. HASC is House Armed Services
Committee; SASC is Senate Armed Services Committee,; HAC is House Appropriations Committee,; SAC is
Senate Appropriations Committee.
a. Transfers the $309.6 million requested for cost growth on the first two DDG-1000s to the line item for
procurement of the third DDG-1000.
b. The SAC report recommends funding for the procurement of two DDG-51s.

40 For more on the Virginia-class program, see CRS Report RL32418, Navy Attack Submarine Procurement:
Background and Issues for Congress
, by Ronald O'Rourke.
Congressional Research Service
27

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

FY2010 Defense Authorization Act (H.R. 2647/P.L. 111-84)
House
In addition to the funding recommendations noted in Table 4, Section 125 of H.R. 2647 as
reported by the House Armed Services Committee (H.Rept. 111-166 of June 18, 2009) would
authorize a multiyear procurement (MYP) arrangement for the procurement of DDG-51s
beginning in FY2010.
The committee’s report states: “The committee supports the re-start of the DDG 51 class and
believes that a minimum of two of these vessels should be requested per year.” (Page 72). The
report also states:
The committee notes that the Secretary of Defense has decided to truncate the DDG 1000
program to three ships and restart the Burke class destroyer (DDG 51) program. The
committee agrees with this decision and understands the agreement reached between the
Department and the prime shipbuilding contractors for construction of the three DDG 1000
ships and the re-start of the first three DDG 51 ships will ensure industrial stability at both of
the surface combatant construction shipyards while the Department plans for future surface
combatant capability and force structure. (Pages 72-73)
The report also states:
Surface combatants
The committee will closely monitor the costs to complete the DDG 1000 class. The
committee is encouraged by the robustness of design completion prior to the start of
fabrication of the first ship. The committee expects the extra effort to complete design prior
to the start of construction and the significant investment in infrastructure at the construction
yard will set a new standard for first of class vessels in meeting target cost. However, the
committee notes that approximately $1.5 billion in research and development efforts still
need to be completed to realize the full combat capability of the ship.
The committee supports the re-start of procurement of DDG 51 class destroyers. The
committee supports the views of the Chief of Naval Operations that these vessels are
required to counter emerging ballistic missile threats and for the conduct of deep ocean
antisubmarine warfare. Therefore, the committee includes in title I of this Act, a provision
that would authorize the Secretary of the Navy to enter into a multi-year procurement
contract for additional DDG 51 destroyers. (Page 76)
Senate
In addition to the funding recommendations noted in Table 4, Section 113 of the FY2010 defense
authorization bill (S. 1390) as reported by the Senate Armed Services Committee (S.Rept. 111-35
of July 2, 2009) would, among other things, prohibit the Navy from obligating or expending
funds for surface combatants procured in FY2012 or subsequent years until certain conditions are
met. The text of Section 113 is as follows:
SEC. 113. PROCUREMENT PROGRAMS FOR FUTURE NAVAL SURFACE
COMBATANTS.
Congressional Research Service
28

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

(a) Limitation on Availability of Funds Pending Reports About Surface Combatant
Shipbuilding Programs- The Secretary of the Navy may not obligate or expend funds for the
construction of, or advanced procurement of materials for, a surface combatant to be
constructed after fiscal year 2011 until the Secretary has submitted to Congress each of the
following:
(1) An acquisition strategy for such surface combatants that has been approved by the
Department of Defense.
(2) The results of reviews by the Joint Requirements Oversight Council for an Acquisition
Category I program that supports the need for an acquisition strategy to procure surface
combatants after fiscal year 2011.
(3) A verification by an independent review panel convened by the Secretary of Defense that,
in evaluating the shipbuilding program concerned, the Secretary of the Navy considered each
of the following:
(A) Modeling and simulation, including war gaming conclusions regarding combat
effectiveness for the selected ship platforms as compared to other reasonable alternative
approaches.
(B) Assessments of platform operational availability.
(C) Life cycle costs from vessel manning levels to accomplish missions.
(4) An intelligence analysis reflecting a coordinated threat assessment of the Defense
Intelligence Agency that provides the basis for deriving the mix of platforms in the
shipbuilding program concerned when compared with the surface combatants in the 2009
shipbuilding plan.
(5) The differences in cost and schedule arising from the need to accommodate new sensors
and weapons in future surface combatants to counter the future threats referred to in
paragraph (4) when compared with the cost and schedule arising from the need to
accommodate sensors and weapons on surface combatants as contemplated by the 2009
shipbuilding plan for the vessels concerned.
(6) A verification by the commanders of the combatant commands that the shipbuilding
program for the vessels concerned would be preferable to the surface combatants included in
the 2009 shipbuilding plan for the vessels concerned in meeting all of their future mission
requirements.
(7) A joint review by the Navy and the Missile Defense Agency setting forth additional
requirements for investment in Aegis ballistic missile defense (BMD) beyond the number of
DDG-51 and CG-47 vessels planned to be equipped for this mission area in the budget of the
President for fiscal year 2010 (as submitted to Congress pursuant to section 1105 of title 31,
United States Code).
(b) Future Surface Combatant Acquisition Strategy- Not later than the date upon which
President submits to Congress the budget for fiscal year 2012 (as so submitted), the
Secretary of the Navy shall submit to the congressional defense committees a plan to provide
for full and open competition on the combat systems for surface combatants proposed in the
future-years defense program submitted to Congress under section 221 of title 10, United
States Code, together with such budget. The plan shall include specifics on the intent of the
Navy to satisfy criteria described in subsection (a) and evaluate applicable technologies
during the request for proposal and selection process.
Congressional Research Service
29

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

(c) Naval Surface Fire Support- Not later than 120 days after the enactment of this Act, the
Secretary of the Navy shall submit to the congressional defense committees an update to the
March 2006 Report to Congress on Naval Surface Fire Support. The update shall identify
how the Department of Defense intends to address any shortfalls between required naval
surface fire support capability and the plan of the Navy to provide that capability. The update
shall include addenda by the Chief of Naval Operations and Commandant of the Marine
Corps, as was the case in the 2006 report.
(d) Technology Roadmap for Future Surface Combatants and Fleet Modernization-
(1) IN GENERAL- Not later than 120 days after the date of the enactment of this Act, the
Secretary of the Navy shall develop a plan to incorporate into surface combatants constructed
after 2011, and into fleet modernization programs, the technologies developed for the DDG-
1000 destroyer and the DDG-51 and CG-47 Aegis ships, including the following:
(A) For the DDG-1000 destroyer—
(i) combat system;
(ii) multi-function and dual-band radars;
(iii) hull, mechanical and electrical systems achieving significant manpower savings; and
(iv) integrated electric propulsion technologies.
(B) For the DDG-51 and CG-47 Aegis ships—
(i) combat system, including missile defense capability;
(ii) hull, mechanical and electrical systems achieving manpower savings; and
(iii) anti-submarine warfare sensor systems designed for operating in open ocean areas.
(2) SCOPE OF PLAN- The plan required by paragraph (1) shall include sufficient detail for
systems and subsystems to ensure that the plan—
(A) avoids redundant development for common functions;
(B) reflects implementation of Navy plans for achieving an open architecture for all naval
surface combat systems; and
(C) fosters full and open competition.
(e) Definition- In this section:
(1) The term `2009 shipbuilding plan’ means the 30-year shipbuilding plan submitted to
Congress pursuant to section 231, title 10, United States Code, together with the budget of
the President for fiscal year 2009 (as submitted to Congress pursuant to section 1105 of title
31, United States Code).
(2) The term `surface combatant’ means a cruiser, a destroyer, or any naval vessel under a
program currently designated as a future surface combatant program.
Regarding Section 113, the committee’s report states:
Congressional Research Service
30

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

The committee recommends a provision [Section 113] that would prevent the Navy from
obligating any funds for building surface combatants after 2011 until the Navy conducts
particular analyses, and completes certain tasks that should be required at the beginning of
major defense acquisition programs (MDAP).
For at least the past couple of years, the Navy’s strategy for modernizing the major surface
combatants in the fleet has been in upheaval. The Navy was adamant that the next generation
cruiser had to begin construction in the 2011–2012 timeframe. After 15 years of consistent,
unequivocal support of the uniformed Navy for the fire support requirement, and for the
DDG–1000 destroyer that was intended to meet that requirement (i.e., gun fire support for
Marine Corps or Army forces ashore), the Navy leadership, in the middle of last year,
decided that they should truncate the DDG–1000 destroyer program and buy DDG–51
destroyers instead.
The Defense Department has announced that the Navy will complete construction of the
three DDG–1000 vessels and will build three DDG–51 destroyers, one in fiscal year 2010
and two in fiscal year 2011. Beyond that, the plan is less well defined, and includes building
only a notional ‘‘future surface combatant,’’ with requirements, capabilities, and costs to be
determined.
Notwithstanding Navy protests to the contrary, this was mainly due to the Navy’s
affordability concerns. The committee notes with no little irony that this sudden change of
heart on the DDG–1000 program is at odds with its own consistent testimony that
‘‘stability’’ in the shipbuilding programs is fundamental to controlling costs and protecting
the industrial base.
The Navy claims the change of heart on the DDG–1000 program was related to an emerging
need for additional missile defense capability that would be provided by DDG–51s and is
being requested by the combatant commanders, and would be used to protect carrier battle
groups against new threats.
The committee certainly believes that the services should have the ability to change course as
the long-term situation dictates. However, since we are talking about the long-term and
hundreds of billions of dollars of development and production costs for MDAPs, the
committee believes that the Defense Department should exercise greater rigor in making sure
such course corrections are made with full understanding of the alternatives and the
implications of such decisions, rather than relying on inputs from a handful of individuals.
The committee has only to look at the decision-making behind the major course correction in
Navy shipbuilding that yielded the Littoral Combat Ship (LCS) to be concerned by that
prospect.
Before deciding on a course of action regarding acquisition of surface combatants after 2011,
we collectively have time to perform the due diligence that should be and must be performed
at the beginning of any MDAP. That is what this section will ensure.
In addition, in order to deter any delaying action on conducting and completing the activities
required by this section before 2011, the committee directs that the Secretary of the Navy
obligate no more than 50 percent of the funds authorized for fiscal year 2010 in PE 24201N,
CG(X), until the Navy submits a plan for implementing the requirements of this section to
the congressional defense committees. (Pages 13-14)
Congressional Research Service
31

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Conference
In addition to the funding recommendations noted in Table 4, Section 125 of the conference
report (H.Rept. 111-288 of October 7, 2009) on the FY2010 defense authorization act (H.R.
2647/P.L. 111-84 of October 28, 2009) prohibits the Navy from obligating or expending funds for
surface combatants procured in FY2012 or subsequent years until certain conditions are met. The
text of Section 125 is as follows:
SEC. 125. PROCUREMENT PROGRAMS FOR FUTURE NAVAL SURFACE
COMBATANTS.
(a) LIMITATION ON AVAILABILITY OF FUNDS PENDING REPORTS ABOUT
SURFACE COMBATANT SHIPBUILDING PROGRAMS.—The Secretary of the Navy
may not obligate or expend funds for the construction of, or advanced procurement of
materials for, a surface combatant to be constructed after fiscal year 2011 until the Secretary
has submitted to Congress each of the following:
(1) An acquisition strategy for such surface combatants that has been approved by the Under
Secretary of Defense for Acquisition, Technology, and Logistics.
(2) Certification that the Joint Requirements Oversight Council—
(A) has been briefed on the acquisition strategy to procure such surface combatants; and
(B) has concurred that such strategy is the best preferred approach to deliver required
capabilities to address future threats, as reflected in the latest assessment by the defense
intelligence community.
(3) A verification by, and conclusions of, an independent review panel that, in evaluating the
program or programs concerned, the Secretary of the Navy considered each of the following:
(A) Modeling and simulation, including war gaming conclusions regarding combat
effectiveness for the selected ship platforms as compared to other reasonable alternative
approaches.
(B) Assessments of platform operational availability.
(C) Life cycle costs, including vessel manning levels, to accomplish missions.
(D) The differences in cost and schedule arising from the need to accommodate new sensors
and weapons in surface combatants to be constructed after fiscal year 2011 to counter the
future threats referred to in paragraph (2), when compared with the cost and schedule arising
from the need to accommodate sensors and weapons on surface combatants as contemplated
by the 2009 shipbuilding plan for the vessels concerned.
(4) The conclusions of a joint review by the Secretary of the Navy and the Director of the
Missile Defense Agency setting forth additional requirements for investment in Aegis
ballistic missile defense beyond the number of DDG–51 and CG–47 vessels planned to be
equipped for this mission area in the budget of the President for fiscal year 2010 (as
submitted to Congress pursuant to section 1105 of title 31, United States Code).
(b) FUTURE SURFACE COMBATANT ACQUISITION STRATEGY.—Not later than the
date upon which the President submits to Congress the budget for fiscal year 2012 (as so
submitted), the Secretary of the Navy shall submit to the congressional defense committees
Congressional Research Service
32

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

an update to the open architecture report to Congress that reflects the Navy’s combat systems
acquisition plans for the surface combatants to be procured in fiscal year 2012 and fiscal
years thereafter.
(c) NAVAL SURFACE FIRE SUPPORT.—Not later than 120 days after the enactment of
this Act, the Secretary of the Navy shall submit to the congressional defense committees an
update to the March 2006 Report to Congress on Naval Surface Fire Support. The update
shall identify how the Department of Defense intends to address any shortfalls between
required naval surface fire support capability and the plan of the Navy to provide that
capability. The update shall include addenda by the Chief of Naval Operations and
Commandant of the Marine Corps, as was the case in the 2006 report.
(d) TECHNOLOGY ROADMAP FOR FUTURE SURFACE COMBATANTS AND FLEET
MODERNIZATION.—
(1) IN GENERAL.—Not later than 120 days after the date of the enactment of this Act, the
Secretary of the Navy shall develop a plan to incorporate into surface combatants constructed
after 2011, and into fleet modernization programs, the technologies developed for the DDG–
1000 destroyer and the DDG–51 and CG–47 Aegis ships, including technologies and
systems designed to achieve significant manpower savings.
(2) SCOPE OF PLAN.—The plan required by paragraph (1) shall include sufficient detail
for systems and subsystems to ensure that the plan—
(A) avoids redundant development for common functions;
(B) reflects implementation of Navy plans for achieving an open architecture for all naval
surface combat systems; and
(C) fosters competition.
(e) DEFINITIONS.—In this section:
(1) The term ‘‘2009 shipbuilding plan’’ means the 30-year shipbuilding plan submitted to
Congress pursuant to section 231, title 10, United States Code, together with the budget of
the President for fiscal year 2009 (as submitted to Congress pursuant to section 1105 of title
31, United States Code).
(2) The term ‘‘surface combatant’’ means a cruiser, a destroyer, or any naval vessel,
excluding Littoral Combat Ships, under a program currently designated as a future surface
combatant program.
Regarding Section 125, the conference report states:
Procurement programs for future naval surface combatants (sec. 125)
The Senate amendment contained a provision (sec. 113) that would prevent the Navy from
obligating any funds for building surface combatants after 2011 until the Navy conducts
particular analyses, and completes certain tasks that should be required at the beginning of
major defense acquisition programs. The committee report (S. Rept. 111–35) also would
direct that the Secretary of the Navy obligate no more than 50 percent of the funds
authorized for fiscal year 2010 in PE 24201N, CG(X), until the Navy submits a plan for
implementing the requirements of this section to the congressional defense committees.
Congressional Research Service
33

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

The House bill contained no similar provision.
The House recedes with technical amendments. The conferees agree to direct that the
Secretary submit the plan for implementing the requirements of this section to the
congressional defense committees at the same time as the President submits the budget
request for fiscal year 2011. (Pages 679-680)
FY2010 DOD Appropriations Act (H.R. 3326/P.L. 111-118)
House
As shown in Table 4, the House Appropriations Committee, in its report (H.Rept. 111-230 of July
24, 2009) on H.R. 3326, recommends an $11-million reduction to the Navy’s request for
procurement funding for the DDG-1000 program. Page 164 of the report states that the
recommended reduction is for “Excess change order funding.” In addition to the funding
recommendations noted in Table 4, the committee’s report states:
SURFACE COMBATANTS
The Committee is concerned with the Navy’s apparent lack of a surface combatant
acquisition plan. In recent years, the Navy has halted production of the DDG–51 guided
missile destroyer program to start production of the DDG–1000 guided missile destroyer.
After awarding only two construction contracts for DDG–1000 class ships, the Navy
announced the termination of that program at three ships and made plans to restart the DDG–
51 production line with no clear path for future surface combatant acquisition. The
Committee is aware that surface combatants will be reviewed as part of the Quadrennial
Defense Review and directs the Navy to review, as part of the Quadrennial Defense Review,
the feasibility of using the technologies developed as part of the DDG–1000 program on
future surface combatants to ensure the taxpayers get the maximum benefit from the
significant funding that was sunk into the research and development phase of the DDG–1000
program. (Pages 165-166)
Senate
As shown in Table 4, the Senate Appropriations Committee, in its report (S.Rept. 111-74 of
September 10, 2009) on H.R. 3326, recommends funding for the procurement of two DDG-51s in
FY2010, and recommends that the $309.6 million requested to cover cost growth on the first two
DDG-1000s be transferred to the main line item for DDG-1000 procurement. (Pages 112 and
113) The committee’s report states:
DDG–51 Class Destroyer.—The fiscal year 2010 budget request included $1,912,267,000
for the construction of one DDG–51 destroyer and $328,996,000 in advance procurement
funding for two ships in fiscal year 2011. The Committee fully supports the restart of the
DDG–51 program. Therefore, in order to restart the DDG–51 program in the most efficient
and cost effective way possible, the Committee recommends an additional $1,737,733,000
for the procurement of a second DDG–51 destroyer in fiscal year 2010. The Committee
expects that the addition of a second ship in fiscal 2010 will allow the Navy to benefit from
economies of scale and improve stability the Nation’s shipbuilding industrial base....
Completion of Prior Year Shipbuilding Programs.—The fiscal year 2010 budget request
included $454,586,000 in the Completion of Prior Year Shipbuilding Programs budget line.
Congressional Research Service
34

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

The Committee understands that $309,636,000 of this request is for the DDG 1000 program
to address class-wide costs that are not specific to individual hulls but rather required to
complete all remaining ships in construction. These costs are usually budgeted across all
planned ships in construction and not in the cost to complete budget line. Therefore, the
Committee recommends transfer of $309,636,000 to the DDG 1000 new construction budget
line. Fiscal year 2011 and beyond requirements should be addressed as program shutdown
line items in future budget requests. (Pages 113 and 114)
As also shown in Table 4, the committee’s report recommends a $12.6-million reduction to the
Navy’s request for FY2010 research and development funding for the DDG-1000 program. The
report states that the reduction is for “FSST alternative initiative.” (Page 184)
Final Version
In lieu of a conference report, the House Appropriations Committee on December 15, 2009,
released an explanatory statement on a final version of H.R. 3326. This version was passed by
the House on December 16, 2009, and by the Senate on December 19, 2009, and signed into law
on December 19, 2009, as P.L. 111-118. The explanatory statement states on page 1 that it “is an
explanation of the effects of Division A [of H.R. 3326], which makes appropriations for the
Department of Defense for fiscal year 2010. As provided in Section 8124 of the consolidated bill,
this explanatory statement shall have the same effect with respect to the allocation of funds and
the implementation of this as if it were a joint explanatory statement of a committee of the
conference.”
The explanatory statement approves the Administration’s request for FY2010 procurement
funding for the DDG-51 program, increases by $250 million the Administration’s request for
FY2010 advance procurement (AP) funding for the DDG-51 program, reduces by $11 million
(for “Excess change order funding”) the Administration’s request for FY2010 procurement
funding for the DDG-1000 program, and approves the Administration’s FY2010 request for
procurement funding to cover cost growth on the first two DDG-1000s (while transferring this
funding into the DDG-1000 procurement line). (Page 166). The explanatory statement reduces
by $12.6 million (for “FSST alternative initiative”) the Administration’s FY2010 request for
research and development funding for the DDG-1000 program. (Page 278)
The explanatory statement states:
DDG-51 GUIDED MISSILE DESTROYER
The recommendation includes $578,996,000, an increase of $250,000,000 above the budget
request, for advance procurement of components for the two DDG-51 destroyers planned in
fiscal year 2011. The recommendation fully supports re-start ofthe DDG-51 program and
provides additional funding in an effort to re-start the program in a more efficient and cost
effective manner. (Page 170)
The explanatory statement also states:
SHIPBUILDING
The fiscal year 20 I0 shipbuilding budget request from the Department once again falls short
of the quantity often ships nominally required to reach and maintain the required fleet size
of313 ships. Further, the Department’s revised acquisition strategy for the Littoral Combat
Ship, solidified after the submission of the budget, has reduced the requested number of
Congressional Research Service
35

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

ships from a quantity of eight to a quantity of seven. In an effort to position the Department
to request additional ship quantities in fiscal year 2011, the recommendation includes an
additional $170,000,000 of advance procurement funding for the LHA (Replacement)
helicopter assault ship and $250,000,000 of additional advance procurement funding for the
DDG-51 Guided Missile Destroyer program. (Page 167)
Congressional Research Service
36

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Appendix A. Additional Background Information
on DDG-1000 Program

This appendix presents additional background information on the DDG-1000 program. It presents
information on the DDG-1000 program as it existed just prior to the Navy’s July 2008 change in
position on future destroyer procurement.

Program Origin
The program known today as the DDG-1000 program was announced on November 1, 2001,
when the Navy stated that it was replacing a destroyer-development effort called the DD-21
program, which the Navy had initiated in the mid-1990s, with a new Future Surface Combatant
Program aimed at developing and acquiring a family of three new classes of surface
combatants:41
a destroyer called DD(X) for the precision long-range strike and naval gunfire
mission,
a cruiser called CG(X) for the air defense and ballistic missile mission, and
a smaller combatant called the Littoral Combat Ship (LCS) to counter
submarines, small surface attack craft (also called “swarm boats”) and mines in
heavily contested littoral (near-shore) areas.42
On April 7, 2006, the Navy announced that it had redesignated the DD(X) program as the DDG-
1000 program. The Navy also confirmed in that announcement that the first ship in the class,
DDG-1000, is to be named the Zumwalt, in honor of Admiral Elmo R. Zumwalt, the Chief of
Naval operations from 1970 to 1974. The decision to name the first ship after Zumwalt was made
by the Clinton Administration in July 2000, when the program was still called the DD-21
program.43

41 The DD-21 program was part of a Navy surface combatant acquisition effort begun in the mid-1990s and called the
SC-21 (Surface Combatant for the 21st Century) program. The SC-21 program envisaged a new destroyer called DD-21
and a new cruiser called CG-21. When the Navy announced the Future Surface Combatant Program in 2001,
development work on the DD-21 had been underway for several years, while the start of development work on the CG-
21 was still years in the future. The current DDG-1000 destroyer CG(X) cruiser programs can be viewed as the
descendants, respectively, of the DD-21 and CG-21. The acronym SC-21 is still used in the Navy’s research and
development account to designate the line item (i.e., program element) that funds development work on both the DDG-
1000 and CG(X).
42 For more on the LCS program, see CRS Report RL33741, Navy Littoral Combat Ship (LCS) Program: Background,
Issues, and Options for Congress
, by Ronald O'Rourke.
43 For more on Navy ship names, see CRS Report RS22478, Navy Ship Names: Background for Congress, by Ronald
O’Rourke.
Congressional Research Service
37

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Acquisition Strategy
Navy Management
Since September 30, 2005, the Navy has managed the DDG-1000 program through a series of
separate contracts with major DDG-1000 contractors, including Northrop Grumman Shipbuilding
(NGSB), General Dynamics Bath Iron Works (GD/BIW), Raytheon, and BAE Systems (the
maker of the AGS). Under this arrangement, the Navy is acting as the overall system integrator
for the program.
Earlier Proposal for Winner-Take-All Acquisition Strategy
Under a DDG-1000 acquisition strategy approved by the Under Secretary of Defense for
Acquisition, Technology, and Logistics (USD AT&L) on February 24, 2004, the first DDG-1000
was to have been built by NGSB, the second ship was to have been built by GD/BIW, and
contracts for building the first six were to have been equally divided between NGSB and
GD/BIW.
In February 2005, Navy officials announced that they would seek approval from USD AT&L to
instead hold a one-time, winner-take-all competition between NGSB and GD/BIW to build all
DDG-1000s. On April 20, 2005, the USD AT&L issued a decision memorandum deferring this
proposal, stating in part, “at this time, I consider it premature to change the shipbuilder portion of
the acquisition strategy which I approved on February 24, 2004.”
Several Members of Congress also expressed opposition to Navy’s proposal for a winner-take-all
competition. Congress included a provision (Section 1019) in the Emergency Supplemental
Appropriations Act for 2005 (H.R. 1268/P.L. 109-13 of May 11, 2005) prohibiting a winner-take-
all competition. The provision effectively required the participation of at least one additional
shipyard in the program but did not specify the share of the program that is to go to the additional
shipyard.
On May 25, 2005, the Navy announced that, in light of Section 1019 of P.L. 109-13, it wanted to
shift to a “dual-lead-ship” acquisition strategy, under which two DDG-1000s would be procured
in FY2007, with one to be designed and built by NGSB and the other by GD/BIW.
Section 125 of the FY2006 defense authorization act (H.R. 1815/P.L. 109-163) again prohibited
the Navy from using a winner-take-all acquisition strategy for procuring its next-generation
destroyer. The provision again effectively requires the participation of at least one additional
shipyard in the program but does not specify the share of the program that is to go to the
additional shipyard.
Milestone B Approval for Dual-Lead-Ship Strategy
On November 23, 2005, the USD AT&L, granted Milestone B approval for the DDG-1000,
permitting the program to enter the System Development and Demonstration (SDD) phase. As
part of this decision, the USD AT&L approved the Navy’s proposed dual-lead-ship acquisition
strategy and a low rate initial production quantity of eight ships (one more than the Navy
subsequently planned to procure).
Congressional Research Service
38

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Contract Award For Two Lead Ships
On February 14, 2008, the Navy awarded contract modifications to GD/BIW and NGSB for the
construction of the two lead ships. The awards were modifications to existing contracts that the
Navy has with GD/BIW and NGSB for detailed design and construction of the two lead ships.
Under the modified contracts, the line item for the construction of the dual lead ships is treated as
a cost plus incentive fee (CPIF) item.
Procurement Cost Cap
Section 123 of the FY2006 defense authorization act (H.R. 1815/P.L. 109-163 of January 6,
2006), limited the procurement cost of the fifth DDG-1000 to $2.3 billion, plus adjustments for
inflation and other factors.
Congressional Research Service
39

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Appendix B. Navy Testimony of July 31, 2008
This appendix reprints in its entirety the text of the Navy’s prepared statement for the July 31,
2008, hearing on destroyer procurement before the Seapower and Expeditionary Forces
subcommittee of the House Armed Services Committee.44 The text states:
Chairman Taylor, Ranking Member Bartlett, and distinguished Members of the Seapower
and Expeditionary Forces Subcommittee, the Department is committed to executing the
Cooperative Maritime Strategy, modernizing our fleet, and building the fleet of tomorrow.
The Navy urges your support to fully fund the Department’s 2009 shipbuilding request. The
Navy requests the Committee’s support for the Navy’s recent plan to truncate the DDG 1000
program at two ships and reopen the DDG 51 line to better align our surface combatant
investment strategy with our nation’s warfighting needs. The Navy continues to address the
dynamic capability requirements of the Fleet while balancing the demands placed on limited
resources and producing a plan that provides maximum stability for the industrial base.
Modernizing the Fleet’s cruisers and destroyers and executing an affordable shipbuilding
plan are crucial to constructing and maintaining a 313 ship Navy with the capacity and
capability to meet our country’s global maritime needs. In an age of rapidly evolving threats
and fiscal constraints, we must ensure we are building only to our highest priority
requirements and that the mission sets we envision for the future represent the most likely of
those potential futures.
Surface combatants are the workhorses of our Fleet and central to our traditional Navy core
capabilities. Our cruisers, destroyers, and the new littoral combat ships bring capabilities to
the fleet, that enable us to deter our enemies, project power, deploy forward and control the
seas.
Strategic Environment
Rapidly evolving traditional and asymmetric threats continue to pose increasing challenges
to Combatant Commanders. State actors and non-state actors who, in the past, have only
posed limited threats in the littoral are expanding their reach beyond their own shores with
improved capabilities in blue water submarine operations, advanced anti-ship cruise missiles
and ballistic missiles. A number of countries who historically have only possessed regional
military capabilities are investing in their Navy to extend their reach and influence as they
compete in global markets. Our Navy will need to outpace other Navies in the blue water
ocean environment as they extend their reach. This will require us to continue to improve our
blue water anti-submarine and anti-ballistic missile capabilities in order to counter improving
anti-access strategies.
The Navy remains committed to having the capability and capacity to win our Nation’s wars
and prevent future wars. The rise of violent extremism has become a greater threat as it
rapidly evolves with diverse and adaptive capabilities. These often stateless organizations
pose further challenges with their aspirations of weapons of mass destruction development
and desire to proliferate missiles and other highly, technologically advanced weapons. All of
these threats require the Navy to have the capacity to build partnerships and continue our
efforts of investing in maritime domain awareness; intelligence, surveillance, and

44 Statement of Vice Admiral Barry McCullough, Deputy Chief of Naval Operations for Integration of Capabilities and
Resources, and Ms. Allison Stiller, Deputy Assistant Secretary of the Navy (Ship Programs), before the Subcommittee
on Seapower and Expeditionary Forces of the House Armed Services Committee, on Surface Combatant Requirements
and Acquisition Strategies, July 31, 2008, 11 pp.
Congressional Research Service
40

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

reconnaissance programs; and having both kinetic and non-kinetic effects capabilities. We
call on our surface combatants to conduct these operations and execute the Maritime Strategy
today, and we will continue to call on them to provide maritime supremacy from the
ungoverned spaces of the littorals to vast expanses of our world’s oceans.
Challenges
The challenge for the Navy is to maintain traditional core naval capabilities while
simultaneously enhancing our ability to conduct expanded core roles and missions to ensure
naval power and influence can be applied on the sea, across the littorals, and ashore. It is no
longer feasible or affordable to purchase the most capable, multi-mission platform and then
limit its use to execute tailored mission areas or focus on specific threats. As asymmetric
threats continue to evolve, so will traditional threats. The Navy must find affordable and
adaptable ways to fill current and future warfighting gaps.
Beyond addressing capability requirements, the Navy needs to have the right capacity to
remain a global deterrent and meet Combatant Commander warfighting requirements.
Combatant Commanders continue to request more surface ships and increased naval
presence to expand our cooperation with new partners in Africa, the Black Sea, the Baltic
Region, and the Indian Ocean and maintain our relationships with our allies and friends.
Therefore, we must increase surface combatant capacity in order to meet Combatant
Commander demands today for ballistic missile defense, theater security cooperation, steady
state security posture and to meet future demands as we standup Africa Command
(AFRICOM) and the FOURTH Fleet in SOUTHERN Command. The Navy also continues to
remain committed to our Ballistic Missile Defense partners around the globe, including
Japan, Korea, the Netherlands, and Spain.
Future Force
The 30 year ship building plan was designed to field the force structure to meet the
requirements of the national security strategy and the Quadrennial Defense Review meeting
the FY 2020 threat. The 313-ship force floor represents the maximum acceptable risk in
meeting the security demands of the 21st century. In the balance of capability and capacity,
the Navy has found that there are increased warfighting gaps, particularly in the area of
integrated air and missile defense capability. Capacity also matters, and capacity is capability
for the Irregular War we are in today.
The DDG 1000 program is developing a capable ship which meets the requirements for
which it was designed. The DDG 1000, with its Dual Band Radar and sonar suite design are
optimized for the littoral environment. However, in the current program of record, the DDG
1000 cannot perform area air defense; specifically, it cannot successfully employ the
Standard Missile-2 (SM-2), SM-3 or SM-6 and is incapable of conducting Ballistic Missile
Defense. Although superior in littoral ASW, the DDG 1000 lower power sonar design is less
effective in the blue water than DDG-51 capability. DDG 1000’s Advanced Gun System
(AGS) design provides enhanced Naval Fires Support capability in the littorals with
increased survivability. However, with the accelerated advancement of precision munitions
and targeting, excess fires capacity already exists from tactical aviation and organic USMC
fires. Unfortunately, the DDG 1000 design sacrifices capacity for increased capability in an
area where Navy already has, and is projected to have sufficient capacity and capability.
The DDG 51 is a proven, multi-mission guided missile destroyer. She is the Navy’s most
capable ship against ballistic missile threats and adds capacity to provide regional ballistic
missile defense. DDG 51 spirals will better bridge the ballistic missile defense gap to the
next generation Cruiser. Production costs of DDG 51s are known. The risks associated with
Congressional Research Service
41

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

re-opening the DDG 51 line are less than the risks of continuing the DDG 1000 class beyond
2 ships when balanced with the capability and capacity of pursuing the 313 ship fleet.
Current Execution
The Department is committed to executing the acquisition plan for our future force.
Acquisition Professionals and Requirements Officers are working closely to maintain the
Department’s commitment to an affordable shipbuilding and modernization plan.
DDG 51 Destroyer Program and Production Restart Assessment
The capability of DDG 51 Class ships being built today is markedly more advanced than the
initial ships of the class. The DDG 51 Class was developed in three incremental flights, with
upgraded technology and capability built into each subsequent hull. Ships are currently being
constructed at both General Dynamics (GD) Bath Iron Works (BIW) and Northrop
Grumman Shipbuilding (NGSB). 62 ships have previously been authorized and appropriated,
with the most recent procurement of three ships in FY 2005. A total of 53 ships have been
delivered to the Navy. Five ships remain under construction at GD BIW, and 4 at NGSB.
The last ship currently under construction, DDG 112, is scheduled for delivery in FY 2011.
All material for DDG 51 Class ships currently under construction has been procured, with
the majority of the long lead material purchased in an Economic Order Quantity buy in FY
2002.
DDG 51 class production has been extremely stable, with successful serial production at both
shipbuilders. Despite some setbacks, such as the impacts of Hurricane Katrina at NGSB, the
costs associated with DDG 51 class shipbuilding are well understood. The Aegis Weapon
System has been incrementally developed successfully to add increased capabilities and
transition to the use of open architecture and increased use of commercial systems.
Additionally, the DDG 51 modernization program is currently modernizing the Hull,
Mechanical, and Electrical (HM&E) and Combat Systems. These combined upgrades
support a reduction in manpower and operating costs, achieve expected service life, and
allow the class to pace the projected threat well into the 21st century.
Based upon a Navy assessment, including discussions with both current shipbuilders, to
explore any subcontractor issues, a restart of DDG 51 procurement in FY 2009 is feasible.
However, several ship and Government Furnished Equipment vendor base issues (including
configuration change issues and production line re-starts) must be addressed in order to
award and construct additional ships, which will increase ship costs above the most recently
procured ships. The most notable being the restart of the DDG 51 reduction gear production.
The Navy is confident that these issues can be resolved to support a FY 2009 restart. DDG
51 class restart beyond FY 2009 presents significant risks and therefore additional costs.
However, both shipbuilders have indicated to the Navy that these lead time challenges can be
mitigated with advance procurement and an adjusted build sequence, and that DDG 51
restart in FY 2009 is executable in both shipyards. Regarding the combat systems, the last
production contracts were awarded in 2006. The cost and ease of restarting those production
lines is a function of time, and part availability on military specification items which would
need to be addressed.
Given the truncation of the DDG 1000 program at two ships, the Navy estimate for
procurement of a single DDG 51 class ship in FY 2009 is $2.2 billion. This estimate utilizes
the latest audited Forward Pricing Rate Agreements (FPRAs) rates. Impacts for production
line restart and contractor furnished equipment/government furnished equipment
obsolescence are included. The Navy has not finalized the acquisition strategy for a FY 2009
Congressional Research Service
42

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

DDG 51 and follow-on procurements. The Navy will carefully consider stability of the
industrial base during the planning of the specific strategy.
DDG 1000 Class Destroyer Program
The Navy remains ready to begin construction of DDG 1000. A rigorous systems
engineering approach for the program has been employed to mitigate the risk involved with
building a complex lead ship surface combatant. This approach included successful building
and testing of the 10 critical technologies via Engineering Development Models. Naval
Vessel Rules were also fully incorporated prior to commencing detail design. Design of the
Mission Systems is now nearly 100 percent complete. Detail design will be approximately 85
percent complete prior to the start of fabrication, and will be more complete than any other
previous surface warship.
The systems engineering approach for DDG 1000 has been well conceived and well
executed. However, overall, the remaining program risk involved in integrating the Mission
Systems, 10 EDM’s, and the ship detail design is still moderate. Particularly, the Dual Band
Radar and Integrated Power System have further land-based testing to complete, and the
software development for the Total Ship Computing Environment continues. Careful
planning has been conducted so that where further development does continue on systems,
these have been partially tested to the point that any potential changes are not likely to affect
software or system interfaces, with a low risk of affecting either detail design or software
development.
As such, the maturity of the ship design, critical technologies, and mission systems support
commencement of production. However, it is accurate that the integration of a complex, lead
ship, surface combatant with significant new technologies always entails risk. And though
the Navy cost estimate for DDG 1000 is based on a detailed, bottoms-up approach, this
complex integration does increase the cost risk.
Truncation of the program at two ships will result in cost impacts due to program shutdown,
continuation of required class service tasks, and potential increased costs for DDG 1000 and
1001 and other programs. Additionally, the RDT&E efforts for the DDG 1000 program,
which include software development and other critical efforts, must continue in order to
deliver completed ships and in the CVN 78 Class.
Conclusion
Your Navy remains committed to building the fleet of the future and modernizing our current
fleet. The Navy’s top shipbuilding priority remains achieving a surface combatant
shipbuilding program that is equally capable of assuring peace today and access to the global
economy tomorrow regardless of the threats posed in an uncertain future. To accomplish
this, we are steadfast in our intention to not use procurement accounts for other Navy
program offsets. Procurement and R&D investments made today will serve our country and
fleet well beyond 2020 as we modernize the fleet we have and build the fleet we need.
Continuing to build DDG 51s enables us to expand warfighting capacity and capability in
areas needed by Combatant Commanders and allows us to reach the 313 ship level sooner.
Meeting evolving blue water and near-land threats that the DDG 51 can match provides less
risk to the joint warfighter. There is less risk associated with the affordability of maintaining
DDG 51 line versus continuing the DDG 1000 line. The Navy is ready to restart DDG 51
production, and is committed to successfully delivering DDG 1000 and 1001 from which, we
will inform new ship class designs. The Navy has not finalized the acquisition strategy for
FY 2009 DDG 51 and follow-on procurements, however acquisition planning is fully
underway to execute this change in the Navy’s shipbuilding requirements. The Department
urges the Committee’s support for full funding of the surface combatant procurement
Congressional Research Service
43

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

account for FY 2009 and approving our proposal regarding DDG’s. Thank you for your
continued support and commitment to our Navy. I look forward to continuing to work
closely with you to make our maritime services and nation more secure and prosperous.
Congressional Research Service
44

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Appendix C. Comparisons of DDG-51 and DDG-
1000

This appendix provides information on the capabilities and costs of the DDG-51 and DDG-1000
designs. It includes information presented by the Navy and DOD on five occasions prior to the
July 31, 2008, hearing on destroyer procurement before the Seapower and Expeditionary Forces
subcommittee of the House Armed Services Committee at which the Navy announced its change
in destroyer procurement plans:
• at a June 10, 2005, Navy briefing to CRS;
• in July 19, 2005, Navy testimony before the Projection Forces subcommittee of
the House Armed Services Committee;
• at an April 10, 2008, Navy briefing to CRS and CBO; and
• in a May 7, 2008, Navy letter to Senator Kennedy; and
• in a July 2, 2008, DOD letter to Representative Taylor.
Overview
The DDG-1000 and DDG-51 are both multimission destroyers, but they have somewhat different
mission emphases. The DDG-1000 design features a stronger emphasis on land-attack operations
and operations in littoral waters. The DDG-51 design is more oriented toward blue-water
operations.
Consistent with its larger size, higher procurement cost, and greater use of new technologies, the
DDG-1000, the Navy believes, is more capable than the DDG-51 design in several respects. The
Navy states that it designed the DDG-1000 for “full-spectrum littoral dominance” and believes
the DDG-1000 would be considerably more capable than the DDG-51 in littoral operations. The
Navy believes that because of its reduced signatures, defensive systems, number of gun shells in
its magazine, and ability to resupply gun shells while underway, the DDG-1000 would have
considerably more capability than the DDG-51 to enter defended littoral waters and conduct
sustained operations there. The Navy believes that because of its guns, aviation capabilities,
special operations forces (SOF) support capabilities, and small-boat capabilities, the DDG-1000
would be able to perform more littoral missions than the DDG-51. The Navy believes that
because of its radars and C4I/networking capabilities, replacing a DDG-51 with a DDG-1000 in a
carrier strike group would increase the strike group’s anti-air warfare (AAW) capabilities by
about 20%. The Navy believes that because of differences in their sonar capabilities, the DDG-51
has more blue-water anti-submarine warfare (ASW) capability than the DDG-1000.
June 10, 2005, Navy Briefing to CRS
The following comparison of DDG-1000 and DDG-51 capabilities is based on information
provided by the Navy to CRS at a briefing on June 1, 2005. The information has been updated in
some places to account for changes since 2005.
Congressional Research Service
45

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Growth Margin
The DDG-51 and DDG-1000 designs each have about a 10% growth margin. For the roughly
9,000-ton DDG-51, this equates to about 900 tons of growth margin, while for the 14,987-ton
DDG-1000, this equates to about 1,400 tons of growth margin.
Ship Mobility
The two designs are roughly equivalent in terms of maximum sustained speed, cruising
endurance, and seakeeping (i.e., stability in rough seas). The DDG-1000’s draft (28 feet) is
somewhat less than the DDG-51’s (31 feet). Other things held equal, this might give the DDG-
1000 an ability to operate in (or be berthed at) places where the water depth is sufficient for the
DDG-1000 but not for the DDG-51. The DDG-1000’s length (600 feet) is greater than the DDG-
51’s (505 feet). Other things held equal, this might give the DDG-51 an ability to be berthed in
spaces that are long enough for the DDG-51 but not for the DDG-1000.
Electrical Power for Weapons and Systems
The DDG-51 has 7.5 megawatts (MW) of electrical power for its weapon systems, while the
DDG-1000 design, with its integrated electric-drive system, can provide up to 78 MW for its
weapons and power systems by diverting power from propulsion to weapons and systems.
Signatures and Detectability
The DDG-1000 has a smaller radar cross-section and lower infrared, acoustic, and magnetic
signatures than the DDG-51. The two designs are roughly equivalent in terms of the detectability
of their radar and other electromagnetic emissions. The DDG-1000’s reduced signatures, DDG-
1000 supporters, will make the DDG-1000 harder to detect, localize, classify, and target, giving
the DDG-1000 a significant advantage in engagements against enemy forces.
Survivability and Damage Control
The Navy states that the DDG-1000 would be able to keep fighting after an attack like the one
that disabled the USS Cole (DDG-67) on October 12, 2000.
The two designs are roughly equivalent in terms of degree of compartmentalization and ship
stability when flooded. The DDG-1000’s vertical launch system (VLS) is more heavily armored
than the DDG-51’s. The DDG’s fire-suppression system is automated only in the engine room
and magazine, while the DDG-1000’s system is automated throughout the ship, making it safer
and more effective. The DDG-51’s flood-control system is not automated, while the DDG-1000’s
is, which the Navy believes will make it more effective. The DDG-1000’s electrical power
distribution system is an “integrated fight-through” system, meaning that it is designed to
automatically isolate damaged areas and reroute electrical power around them. All critical DDG-
1000 systems are dual-fed, meaning that if power from one source is cut off, it can be routed
through a second source. The DDG-51’s electrical power distribution system lacks these features.
Congressional Research Service
46

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

C4I/Networking Bandwidth
The C4I45 and networking systems on the DDG-1000 would have five times as much bandwidth
as those on the DDG-51. The C4I/networking capability of the DDG-1000 is equivalent to that on
the LHD-8 amphibious assault ship. In addition to improved warfighting capability, this increased
bandwidth would provide sailors aboard the DDG-1000 a better ability to “reach back” to
information sources ashore when conducting at-sea maintenance of shipboard equipment,
potentially increasing the availability rates of shipboard equipment.
Flag-Level Command Facilities
The DDG-1000 has facilities for embarking and supporting a flag-level officer and his staff, so
that they could use the ship as platform for commanding a group of ships. The DDG-51 does not
have such facilities.
Anti-Air Warfare/Ballistic Missile Defense (AAW/BMD)
The radars on the two ships are roughly equivalent in terms of dB gain (sensitivity) and target
resolution. The firm track range of the DDG-1000’s dual-band radar—the range at which it can
maintain firm tracks on targets—is 25% greater for most target types than the firm track range of
the DDG-51’s SPY-1 radar. The DDG-1000’s AAW combat system would be able to maintain
about 10 times as many tracks as the DDG-51’s Aegis system. The DDG-1000’s radar has much
more capability for resisting enemy electronic countermeasures and for detecting targets amidst
littoral “clutter.” As a result of the better performance amidst littoral clutter, the Navy believes
that ships escorted by the DDG-1000 in defended littoral waters would have three times as much
survivability as ships escorted by the DDG-51.
The two designs would use the same types of area-defense and point-defense interceptor
missiles.46 They would also use the same flares, chaff, and decoys to confuse enemy anti-ship
cruise missiles, but the Navy believes these devices would be more effective on the DDG-1000
because of the DDG-1000’s reduced signatures.
Anti-Surface Warfare/Strike Warfare
The DDG-1000 would have considerably more naval surface fire support (NSFS) capability than
the DDG-51. The DDG-51 has one 5-inch gun, while the DDG-1000 has two 155mm Advanced
Gun Systems (AGSs). The DDG-51’s gun can fire an initial salvo of 20 rounds per minute and
can subsequently fire at a sustained rate of four rounds per minute (20/4). The DDG-1000’s two
guns have a combined firing rate of 20/20. The shells currently fired by the DDG-51’s gun have a
range of 13 nm. Future shells are to have a range of up to 50 nm. The shells to be fired by the
DDG-1000’s guns are to have a range of 63 to 74 nm, and consequently could cover (at 74 nm)
more than three times as much area ashore (assuming a 25 nm standoff from shore) as a shell with
a range of 50 nm. The shells fired by the DDG-51 carry 8 pounds of explosive, while those fired

45 C4I stands for command and control, communications, computers, and intelligence.
46 As discussed earlier, the Navy, as part of its testimony at the July 31, 2008, hearing on destroyer procurement before
the Seapower and Expeditionary Forces subcommittee of the House Armed Services Committee, stated that the DDG-
1000 cannot successfully employ the SM-2 or perform area-defense AAW.
Congressional Research Service
47

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

by the DDG-1000 are to carry 24 pounds of explosive. When fired at less than maximum range,
the shells fired by the DDG-1000 can alter their flight paths so that six to eight of them can hit a
target at the same time; the shells to be fired by the DDG-51 do not have this capability. The
DDG-51 carries 600 of the 13nm-range shells or 230 of 62nm-range shells, while the DDG-1000
carries a total of 600 of its shells. It might be possible to fit the DDG-51 with one of the 155mm
guns to be carried by the DDG-1000; it would likely require the removal of both the DDG-51’s 5-
inch gun and its forward (32-cell) VLS. In this configuration, the DDG-51 might carry about 120
of the gun’s 155mm shells.
The 155mm guns on the DDG-1000 could be replaced in the future with an electromagnetic rail
gun or directed-energy weapon. The DDG-51 does not have enough electrical power to support
such weapons.
Antisubmarine Warfare (ASW)
The DDG-51’s sonar system is more capable for blue-water ASW operations, while the DDG-
1000’s system is more capable for littoral ASW operations. The DDG-1000’s bow-mounted sonar
and towed array can interact to more rapidly triangulate targets. The Flight IIA DDG-51 lacks a
towed array. The DDG-1000’s radar would have more capability than the DDG-51’s radar for
detecting submarine periscopes.
The DDG-51 has six torpedo tubes for firing lightweight (12.75-inch diameter) anti-submarine
torpedoes, while the DDG-1000 has none, but the Navy does not believe these tubes to be of
significant operational value against potential future threats. Both ships can launch lightweight
torpedoes from their helicopters or fire the Vertical Launch Antisubmarine Rocket (VLA), which
is armed with a lightweight torpedo.
The ships would use the same countermeasures for confusing enemy torpedoes, but the Navy
believes these countermeasures would be more effective on the DDG-1000 because of the DDG-
1000’s reduced signatures.
Mine Warfare (MIW)
The DDG-1000’s bow-mounted sonar includes an in-stride mine-avoidance capability; the DDG-
51’s sonar suite has less capability for detecting mines. The DDG-51 can be built to a design that
permits the ship to embark and operate the Remote Minehunting System (RMS); six ships in the
DDG-51 program (DDGs 91 to 96) have been built to this design. The Navy says that the DDG-
1000’s reduced acoustic and magnetic signatures would translate into a significantly greater
operating area in mined waters.
Missiles for Performing Above Missions
The DDG-51 has 90 missile-launching tubes in its VLS, while the DDG-1000 has 80. The DDG-
51’s VLS tubes can accommodate a missile up to 21 inches in diameter, 21 feet in length, and
about 3,000 pounds in weight. The DDG-1000’s VLS tubes can accommodate a missile up to 24
inches in diameter, 22 feet in length, and about 4,000 pounds in weight. The gas-management
(i.e., heat-management) system of the DDG-1000’s VLS tubes can accommodate a hotter-burning
missile than the gas-management system of the DDG-51’s VLS, so the DDG-1000 might be more
capable of using future missiles if they are hotter-burning.
Congressional Research Service
48

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Aviation for Performing Above Missions
The DDG-51 can embark and operate two SH-60 helicopters but does not have electronics for
launching and recovering unmanned aerial vehicles (UAVs). The DDG-1000 can embark,
operate, and provide full maintenance for two SH-60 helicopters or one SH-60 helicopter and
three UAVs. The DDG-1000’s flight deck is larger than the DDG-51’s and can accommodate all
joint rotary-wing aircraft, including the MV-22, the CH-53, and the H-47. The DDG-1000’s flight
deck is 10 feet higher off the water and can therefore be used for full flight operations in a sea
state (i.e., sea condition) that is at least one step higher (i.e., rougher) than is possible for the
flight deck on the DDG-51.
Special Operations Forces (SOF) Support
The DDG-1000 has additional berthing for 20 SOF personnel (i.e., a platoon), as well as a space
for SOF mission planning and spaces for stowing SOF gear. The DDG-51 lacks these features.
Boats
The DDG-51 can embark two seven-meter boats that are deployed and recovered with a davit.
The DDG-1000 can embark two 11-meter boats and four rubber raiding craft that are deployed
and recovered with a stern ramp, which permits faster and safer launching and recovering, and
launch/recovery operations in higher sea states.
Habitability Features for Crew
On the DDG-51, enlisted crew berthing spaces accommodate 20 to 60 sailors each. On the DDG-
1000, every sailor would have a stateroom, and each stateroom would accommodate four sailors.
The Navy believes these features would improve crew quality of life, which can improve
retention rates.
July 19, 2005, Navy Testimony
At the July 19 portion of a July 19-20, 2005, hearing before the Projection Forces subcommittee
of the House Armed Services Committee, Navy officials testified that, compared to the DDG-51
design, the DDG-1000 design’s capability improvements include, among other things,
• a threefold improvement in capability against anti-ship cruise missiles, including
significantly better radar performance in situations involving near-land radar
clutter;
• a 10-fold improvement in overall battle force defense capability, in part because
of a 5-fold improvement in networking bandwidth capacity;
• 15% more capability to defend against group attacks by enemy surface craft (i.e.,
“swarm boats”);
• a 50-fold improvement (i.e., reduction) in radar cross-section, which dramatically
enhances survivability and reduces by half the total number of missiles that need
to be fired in an intercept engagement;
Congressional Research Service
49

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

• a 10-fold increase in operating area against mines in shallow-water regions;
• three times as much naval surface fire support capability, including an ability to
answer 90% of Marine Corps calls for fire within five minutes, permitting the
ship to meet stated Marine Corps firepower requirements—a capability otherwise
unavailable in the surface fleet—giving the ship a capability roughly equivalent
to one-half of an artillery battalion, and permitting a 65% reduction in Marine
Corps artillery;
• a ship design that allows underway replenishment of gun shells, creating the
equivalent of an almost-infinite ammunition magazine and permitting nearly
continuous fire support;
• almost 10 times as much electrical capacity available for ship equipment, giving
the ship an ability to support future electromagnetic rail guns and high-energy
laser weapons; and
• features such as an automated fire-suppression system, peripheral vertical launch
system, and integrated fight-through-damage power system that significantly
increase ship survivability.47
April 10, 2008, Navy Briefing to CRS and CBO
At an April 10, 2008, briefing to CRS and CBO, Navy officials presented a briefing slide
providing a comparison of the DDG-1000 design’s capabilities relative to the DDG-51 design’s
capabilities. The briefing slide is reprinted below (with some editing changes for readability) as
Table C-1.
Table C-1. DDG-1000 Capabilities Relative to DDG-51 Capabilities
Item
DDG-1000 compared to DDG-51
Radar cross section
Significantly smaller
Ship detectability by threat aircraft
Threat must fly lower and closer to detect the ship
Firm track range on enemy anti-ship
Significant improvement, especially in land-clutter environments
cruise missiles
Performance against small boat swarm
Engage small boats at 3 times the effective range and engage 10 times
raids
more threats
Safe operating area in areas with enemy
Significantly larger
bottom mines
Land attack capability
3 times as much lethality and 40% greater range than Extended Range
Guided Munition (ERGM)a
Manning 50%
less
crew
Electrical power
Sufficient capacity for rail gun, laser weapons, and future radar upgrades

47 Source: Points taken from Statement of Admiral Vern Clark, U.S. Navy, Chief of Naval Operations, Before The
House Armed Services Committee Projection Forces Subcommittee, July 19th, 2005, and Statement of The Honorable
John J. Young, Jr., Assistant Secretary of the Navy (Research, Development and Acquisition), and RADM Charles S.
Hamilton, II, Program Executive Officer For Ships, Before the Projection Forces Subcommittee of the House Armed
Services Committee on DD(X) Shipbuilding Program, July 19, 2005.
Congressional Research Service
50

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Source: Navy briefing slide #7, entitled “Multi-Mission Combatant,” in Navy briefing to CRS and CBO, April 10,
2008. CRS has edited the words in the table to make them easier to understand.
a. ERGM was a 5-inch extended-range guided munition for the 5-inch guns on Navy cruisers and destroyers.
The Navy in 2008 canceled development of ERGM.
In addition to the information presented in Table C-1, another slide in the Navy briefing stated
that the DDG-1000’s radar cross section will be similar to that of a fishing boat.48 Navy officials
have also stated separately that the DDG-1000’s acoustic signature will be similar, at certain
speeds, to that of certain U.S. Navy submarines.49
In elaborating on the point in Table C-1 pertaining to the DDG-1000’s electrical power, Navy
officials stated at the briefing that at a speed of 20 knots, the DDG-1000 would have 58
megawatts of power available for powering non-propulsion shipboard systems. The briefing
stated that the DDG-51, by comparison, has 7.5 megawatts of power available for non-propulsion
systems.
May 7, 2008, Navy Letter to Senator Kennedy
A May 7, 2008, letter from Admiral Gary Roughead, the Chief of Naval Operations (CNO), to
Senator Edward Kennedy that was obtained by a defense trade publication and posted on its
website provided information on the comparative costs and capabilities of the DDG-1000 and
DDG-51. The letter stated:
Thank you for your letter of April 21, 2008, concerning cost estimates for the continuation of
the DDG 51 program and the DDG 1000 program.
As you indicated in your letter, without firm contracts for future ships of either class, we are
only able to provide a best estimate of the costs we would incur in either of these programs.
Since we are phasing out production of the DDG 51 class, there would be start-up costs
associated with returning this line to production. As a result, the estimated end cost to
competitively procure a lead DDG-51 (Flight IIa—essentially a repeat of the final ships
currently undergoing construction) in Fiscal Year (FY) 2009 assuming a truncation of the
DDG 1000 class after the two lead ships would be either $2.2B for a single ship or $3.5B for
two lead ships (built at competing production yards). This estimate is based on a Profit
Related to Offer (PRO) acquisition strategy. The average cost of subsequent DDG 51 Flight
IIa class ships would be about $1.8B (FY09) per ship compared to the $2.6B estimated cost
of subsequent DDG 1000 class ships. Below is the breakdown of the one and two ship FY09
DDG 51 estimates, compared to that of the DDG 1000 in the same year. DDG 1000 costs
include FY08 advanced procurement funds:

48 Navy briefing slide #8, entitled “Zumwalt Advantage,” in Navy briefing to CRS and CBO, April 10, 2008.
49 Source: Spoken testimony of Navy officials at hearing before Seapower subcommittee of Senate Armed Services
Committee on April 8, 2008.
Congressional Research Service
51

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

DDG 51
DDG 51
DDG 1000
(FY$M)
(FY09)
(FY09)
(FY09)
Qty
1 2 1
Plans/Basic
[construction]
854.4 1607.8 1393.3
Change
Orders
39.1 76.1 66.0
Government Furnished Equip
1138.2
1556.7
1126.8
Other
56.4 57.5 66.6
Total
Ship
Cost
2088.1 3298.1 2652.6
The table provided below compares the annual operations and support costs for the DDG 51
and DDG 1000 class ships.
(FY$M)
DDG 1000
DDG 51
Operating (steaming)
$18.5 $15.7
Maintenance
$10.3 $5.6
Manpower
$8.5 $19.9
Total
$37.3 $41.2
Crew Size
14 officers
24 Officers
106 enlisted
272 Enlisted
The total annual cost for the DDG 51 is a class average based on 17 years of operations and
maintenance, and does not include personnel reduction savings expected from the DDG
Modernization program. While there are cost savings associated with the DDG 1000’s
smaller crew, they are largely offset by higher estimated maintenance costs for this
significantly more complex ship.
Clearly the relative value of the DDG 1000 resides in the combat system (Dual-Band Radar,
Volume Search Radar, ASW Suite, etc) that provide this ship with superior warfighting
capability in the littoral. However, the DDG 51 can provide Ballistic Missile Defense
capability against short and medium range ballistic missiles and area Anti-Air Warfare
capability (required in an anti-access environment) where the DDG 1000 currently does not.
Upgrading the DDG 1000 combat system with this capability would incur additional cost.
The DDG 51 class also possesses better capability in active open ocean Anti-Submarine
Warfare than does the DDG 1000.
On balance, the procurement cost of a single DDG 51 is significantly less than that of a DDG
1000, and the life-cycle costs of the two classes are similar. I appreciate the opportunity to
share my perspective on these two alternatives with you. A similar letter has been sent to
Senator Martinez. As always, if I can be of further assistance, please let me know.50
On June 3, 2008, John Young, the Under Secretary of Defense for Acquisition, Technology, and
Logistics, in testimony to the Senate Armed Services Committee, questioned the accuracy of the
cost figures in the May 7 letter, stating, among other things, that he believed the annual operating

50 Source: Letter dated May 7, 2008, from Admiral G. Roughead to the Honorable Edward M. Kennedy, posted on the
Internet at InsideDefense.com (subscription required) on May 30, 2008. Emboldening in the second table as in the
original. See also Thomas Duffy, “Navy Says DDG-100, DDG-51 Annual Operating Costs Are Rated Even,” Inside the
Navy
, June 2, 2008.
Congressional Research Service
52

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

and support cost of the DDG-1000 would be about $10 million less than that of a DDG-51, and
that the procurement cost figures in the letter relied on certain assumptions that might not prove
accurate. Young’s testimony was viewed as defending the DDG-1000 more strongly than did the
CNO’s May 7, 2008, letter.51
July 2, 2008, DOD letter to Representative Taylor
A July 2, 2008, letter from John Young, the Under Secretary of Defense for Acquisition,
Technology and Logistics (i.e., the DOD acquisition executive), to Representative Gene Taylor
that was obtained by a defense trade publication and posted on its website provides additional
comments regarding the DDG-1000 and DDG-51, as well as information about the readiness of
the DDG-1000 design to enter production. The letter stated:
I agree that the Navy’s preliminary design analysis for the next generation cruiser indicates
that, for the most capable radar suites under consideration, the DDG 1000 hull cannot
support the radar. This applies just as well to the DDG 51 hull. However, it is my
understanding that engineering analysis shows that the existing DDG 1000 hull design can
support significantly more capable radar suites than the existing DDG 51 hull design.
Moreover, while it is not possible to quickly estimate the production cost of a redesigned
DDG 51 alternative, I suspect that, given the dense and complex nature of the DDG 51 hull,
as compared to that of the DDG 1000 hull, the cost of a redesigned DDG 51 very likely will
be equal to or greater than that of a DDG 1000.
Your letter also warns that cost over-runs for the DDG 1000 program might cripple the
Navy’s shipbuilding programs. I am equally concerned that restarting the DDG 51 program
would pose risk to the shipbuilding budget and inject additional cost for the following
reasons:
—Direct production hours for one DDG 1000 ship are about 2.5 times that of one DDG 51
restart ship. This validates DOD’s experience that two to three DDG 51 destroyers need to be
purchased annually to sustain the production workload base for two surface combatant
shipyards. That number of DDG 51 ships costs more per year than one DDG 1000 follow
ship. The cost per year for modified DDG 51 ships would be even higher.
—Several ship and vendor base issues, including equipment obsolescence, main reduction
gears, configuration change issues, and re-start of production lines, would need to be
resolved in order to award and construct additional DDG 51 class ships.
—The costs for the two DDG 1000 ships would increase if that program is truncated to only
two ships.
—There will be program shutdown costs for the DDG 1000 program if the program is
truncated to only two ships.
—The Research, Development, Test, & Evaluation efforts for the DDG 1000 program must
continue in order to deliver two complete lead ships and to support the Dual Band Radar for
the CVN 21 program.

51 See, for example, Emelie Rutherford, “Young Claims Inaccuracies, Assumptions In Navy Destroyer Cost
Comparison,” Defense Daily, June 5, 2008; and Dale Eisman, “Warning: Delay On Ship Will Run Up Navy’s Costs,”
Norfolk Virginian-Pilot,” June 4, 2008: D1.
Congressional Research Service
53

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

In reference to your concern that there is no Joint Requirements Oversight Council (JROC)
or U.S. Marine Corps requirement for fire support that can only be provided by the DDG
1000, the JROC validated the Operational Requirements Document (ORD) for the DDG
1000 program. The ORD includes a requirement to provide precise and sustained naval fires
at extended ranges. The DDG 1000 with its advanced Gun System firing the Long Range
Land Attack Projectile is the only ship that can achieve that validated requirement.
I remain convinced that the DDG 1000 program is poised for proper execution. Unlike DDG
51, LPD 17, and LCS, where the level of concurrent design, development, and construction
were critical flaws, leading to significant cost increases on the lead ships, the DDG 1000
program benefits from early technology maturation, and experienced design team using a
mature design tool, proven production processes, and other factors as outlined below:
—Design Drawing Status: DDG 1000 is significantly more mature in detail design than was
LPD 17 or DDG 51 at the same points in the program. For example, at the time of the Detail
Design and Construction (DD&C) contract award, DDG 1000 detail design products were 55
percent complete, compared to 0 percent for LPD 17 and DDG 51. At the start of fabrication,
DDG 1000 detail design products will be approximately 80-85 percent complete, compared
to 20 percent for DDG 51 and 20-30 percent for the two LCS designs. While design products
for the LPD 17 were also in the 80 percent complete range at the start of fabrication, this
came about only after a long delay to fix and prove the design tool during the detail design
phase, a lesson learned and avoided for the DDG 1000 program.
—Initial Module Construction: The jointly developed design of DDG 1000 is on schedule to
be more mature than any previous shipbuilding program at start of construction. The design
and build of the machinery block in advance of first ship construction completed in June
2008. This effort has been extremely beneficial as a risk reduction measure.
—Design Tool Maturity: The DDG 1000 team of contractors worked together on 3-D
modeling during preliminary and system design for 6 years in advance of the DD&C phase.
—Early Technical Product Definition: Contractor-developed technical products enabled
early development of design products (system diagrams, vendor statements of work, etc.),
which are typically developed during the early stages of detail design. DDG 1000 leveraged
these early developments to help the program reduce the risk of rework and poor quality than
undermine early-start initiatives such as those experienced on other shipbuilding programs.
—Technology Maturity: The combined DDG 1000 design team learning and use of the 3-D
Product Modeling Tool 6 years in advance of the DD&C ensures that the right quantity of
qualified human capital resources are allocated in support of the DD&C phase.
—Phase III Cost Performance: Cost performance on DDG 1000 was within 2.5 percent of
budget on the $2.7B development effort on Phase III, leading to the DD&C phase.
—Current Phase Cost Performance: The current design, development, and integration
contract is performing at an overall cost performance index of 1.02 and a schedule
performance index of 0.99 through April 2008. Detail design and transition to production are
on cost and schedule.52

52 Source: Letter dated July 2, 2008, from John J. Young, Jr., to the Honorable Gene Taylor, posted on the Internet at
InsideDefense.com (subscription required) on July 11, 2008. See also Geoff Fein, “DDG-1000 Hull Can’t Support Most
Capable Radar Planned For CG(X), Pentagon Official Says,” Defense Daily, July 11, 2008.
Congressional Research Service
54

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Appendix D. Potential DDG-51 and DDG-1000
Design Variants

This appendix presents information on potential variants of the DDG-51 and DDG-1000
destroyer designs that could reduce the O&S costs of DDG-51s procured in coming years or
improve the capabilities for AAW and BMD (which are referred to collectively in this appendix
as integrated air and missile defense, or IAMD) of DDG-51s or DDG-1000s procured in coming
years. Parts of this appendix are adapted from CRS testimony at a July 31, 2008, hearing on
destroyer procurement before the Seapower and Expeditionary Forces subcommittee of the House
Armed Services Committee.53
DDG-51 Design Variants
Introduction
The Navy has procured different versions of the DDG-51 design over time. A significant change
in the design occurred in FY1994, when the Navy shifted DDG-51 procurement to the Flight IIA
version of the ship, which included, among other things, the addition of a helicopter hangar and
the repositioning of the ship’s aft SPY-1 radar arrays. Prior to implementing the Flight IIA design,
the Navy seriously considered a version with even larger-scale changes, called the Flight III
design, that would have included, among other things, lengthening the ship’s hull to make room
for additional mission systems. The Navy and industry in the past have studied options for
lengthening the DDG-51 hull by various lengths to accommodate various capability upgrades;54
the maximum possible hull extension might be 55 or 56 feet.55
Compared to procuring additional Flight IIA DDG-51s, procuring a modified version of the
DDG-51 design would incur additional nonrecurring design and engineering costs, as well as
additional recurring production costs due to loss of learning at the shipyard associated with
changing the ship’s design and (for some of the options discussed below) the enlargement of the

53 Statement of Ronald O’Rourke, Specialist in Naval Affairs, Congressional Research Service, before the House
Armed Services Committee Subcommittee on Seapower and Expeditionary Forces hearing on Surface Combatant
Warfighting Requirements and Acquisition Strategy, July 31, 2008, 17 pp. This testimony was in turn based on
information in the Navy program of record, past briefings and other information provided by the Navy and industry to
CRS on the DDG-51 and DDG-1000 programs, industry briefings to CRS on DDG-51 and DDG-1000 design options
that were done at CRS’ request, and open-source information.
54 For example, the Navy in 1988 studied design options for a Flight III version of the DDG-51 design that included
hull extensions, in various locations along the hull, of 30 feet, 40 feet, and 46 feet. The CNO gave initial approval to a
Flight III design concept incorporating a 40-foot extension (12 feet forward and 28 feet aft), and the design was
intended to begin procurement in FY1994. (Source: Donald Ewing, Randall Fortune, Brian Rochon, and Robert Scott,
DDG 51 Flight III Design Development, Presented at the Meeting of the Chesapeake Section of The Society of Naval
Architects and Marine Engineers, December 12, 1989.) The Flight III design was canceled in late-1990/early-1991.
Subsequent studies led to the current Flight IIA design, which does not include a hull extension. A 1994 CRS report
discussed the option of lengthening the DDG-51 design by about 12 feet to increase the forward VLS battery from 32
cells to 64 cells. (See CRS Report 94-343, Navy DDG-51 Destroyer Procurement Rate: Issues and Options for
Congress
, by Ronald O’Rourke [April 25, 1994; out of print and available directly from the author]), pp. CRS-27 to
CRS-28.
55 Sources: Recent discussions with industry officials and Navy information provided to CRS in 1997.
Congressional Research Service
55

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

ship. Depending on the exact option pursued, the nonrecurring design and engineering costs could
total in the hundreds of millions of dollars.
Potential variants of the DDG-51 design that could be procured in coming years include but are
not limited to the following:
• a modified version with additional features for reducing O&S costs;
• a modified version with additional features for reducing O&S costs and
additional vertical-launch tubes;
• a modified version with additional features for reducing O&S costs and an
improved radar; and
• a modified version with additional features for reducing O&S costs, additional
vertical-launch tubes, and an improved radar.
Each of these options is discussed below.
Version with Features for Reducing O&S Costs
This option would procure Flight IIA DDG-51s that were modified to include features for
reducing the ships’ annual O&S costs. Potential features of this kind include but are not limited to
the following:
• adding automated equipment and making other changes to reduce crew size;
• adding some electric-drive equipment for interconnecting parts of the ship’s
mechanical-drive propulsion system so as to permit the system to operate more
like an integrated electric drive system; and
• installing a near-surface bow bulb above the existing sonar dome to improve
hydrodynamic efficiency.
The discussion below of how these three features could reduce DDG-51 O&S costs uses as its
starting point the table below on annual DDG-1000 and DDG-51 O&S costs, which is reprinted
from Admiral Gary Roughead’s May 7, 2008, letter to Senator Kennedy on the DDG-1000 and
DDG-51.56
(FY$M)
DDG 1000
DDG 51
Operating (steaming)
$18.5 $15.7
Maintenance
$10.3 $5.6
Manpower
$8.5 $19.9
Total
$37.3 $41.2
Crew Size
[Total 120]
[Total 296]
14 officers
24 Officers
106 enlisted
272 Enlisted
Source: Letter dated May 7, 2008, from Admiral G. Roughead to the Honorable Edward M. Kennedy, p. 2. The
figures shown in brackets for total crew size were added to the table by CRS.

56 Source: Letter dated May 7, 2008, from Admiral G. Roughead to the Honorable Edward M. Kennedy, posted on the
Internet at InsideDefense.com (subscription required) on May 30, 2008.
Congressional Research Service
56

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Reducing Crew Size
Admiral Roughead’s letter states that the above table “does not include personnel reduction
savings expected from the DDG Modernization program.” The Navy informed CRS on July 25,
2008, that the DDG-51 modernization is not expected to reduce DDG-51 crew size, but that the
size of the DDG-51 crew has, for other reasons, been reduced recently from the figure of 296
shown in the table to 278, a reduction of 18 people.57
Additional actions might permit a further reduction in DDG-51 crew size: a 2003 industry
briefing to CRS on DDG-51 modernization for reduced manning discussed various steps for
reducing crew size by about 100.58 The House Armed Services Committee’s report (H.Rept. 108-
491 of May 14, 2004) on the FY2005 defense authorization bill (H.R. 4200) similarly stated:
The committee notes that the Navy is scheduled to commence a DDG-51 modernization plan
in fiscal year 2005 with new construction and subsequently extend modernization to in-
service destroyers. The committee is aware that the foundations for DDG-51 modernization
are: increased warfighting capability, leverage of the DDG—51 shipbuilding program,
reduction of total ship ownership costs, and use of open architecture. In addition to those
factors, the committee believes that reduction in crew size from the present approximately
300 to an objective of 200 personnel should also be part of the foundation of an even more
aggressive modernization program.
According to the Navy, a DDG-51 class ship costs $25.0 million per year to operate,
including $13.0 million for the crew. The Navy estimate is that its present modernization
plan could reduce the crew cost per ship by $2.7 million per year. A larger reduction in crew
size would clearly appear to result in significant savings over the estimated 18 years of
remaining normal service life, especially noting that per capita personnel costs may be
expected to increase during that period.59
Using the figures in the table from Admiral Roughead’s May 7 letter, if additional steps can
reduce ship crew size by another 32 people, for a total reduction of 50—one-half the figure of 100
mentioned in the 2003 industry briefing and the 2004 committee report—then annual manpower
costs for the DDG-51 could be reduced from the figure of $19.9 million shown in the table to
about $16.5 million, a reduction of about 17%.
Addition of Some Electric-Drive Equipment
As discussed in two CRS reports,60 at least one maker of electric-drive propulsion equipment has
proposed increasing the planned scope of the Navy’s program for modernizing its DDG-51s to
include adding some electric-drive propulsion equipment to the ships’ existing mechanical-drive
propulsion plants. The option could also be applied to new-construction DDG-51s. The added
equipment would more fully interconnect the mechanical-drive components on each ship,
producing what the firm refers to as a hybrid propulsion plant. The firm estimates that the

57 Source: Navy information provided to CRS by telephone, July 25, 2008.
58 Source: Industry briefing to CRS on DDG-51 modernization for reduced manning, August 8, 2003.
59 H.Rept. 108-491, pp. 122-123.
60CRS Report RL33360, Navy Ship Propulsion Technologies: Options for Reducing Oil Use—Background for
Congress
, by Ronald O'Rourke, and CRS Report RS22595, Navy Aegis Cruiser and Destroyer Modernization:
Background and Issues for Congress
, by Ronald O’Rourke.
Congressional Research Service
57

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

addition of this equipment would reduce DDG-51fuel use by about 16%. This option, the firm
estimates, would have a non-recurring engineering cost of $17.1 million and a recurring cost
(including both equipment cost and installation cost) of $8.8 million per ship.61
Using the figures in the table from Admiral Roughead’s May 7 letter, reducing DDG-51 fuel use
by 16% would reduce the ship’s annual operating (steaming) cost from the figure of $15.7 million
shown in the table to about $13.2 million—a reduction of about $2.5 million. The Navy has
informed CRS that the operating (steaming) cost figures in the May 7 letter are based on fuel
costs as of February 2008 and reflect a fuel cost of $112.14 per barrel.62 If fuel in coming years
costs more than $112.14 per barrel, the dollar savings associated with a 3.9% reduction in fuel use
would be greater than $2.5 million per year. The obverse would be true if fuel in coming years
costs less than $112.14 per barrel.
Adding a Near-Surface Bow Bulb
As discussed in a CRS report,63 a study by the Navy’s David Taylor Model Basin estimated that
fitting a near-surface bow bulb—essentially a shaped piece of steel—onto a DDG-51class
destroyer could reduce its fuel use by 3.9%.64

61 Source: Briefing by the firm DRS dated December 19, 2007, with estimated percentage fuel-savings and cost figures
reconfirmed by telephone call with CRS on July 17, 2008. DRS also stated in the phone call that one Navy official had
stated that the reduction in fuel use could be greater than DRS estimates because the commanders of ships with this
equipment would likely adjust ship speeds to operate the ship more often at the hybrid system’s most-efficient speed
points (i.e., the system’s “sweet spots”).
62 Source: Navy information provided to CRS by telephone, July 25, 2008.
63CRS Report RL33360, Navy Ship Propulsion Technologies: Options for Reducing Oil Use—Background for
Congress
, by Ronald O'Rourke.
64 Dominic S. Cusanelli, “Stern Flaps and Bow Bulbs for Existing Vessels, Reducing Shipboard Fuel Consumption and
Emissions,” available online at http://www.unep.fr/ozonaction/events/military/proceedings/Presentation%20Material/
24%20-%20Cusanelli%20-%20SternFlaps.doc. The study is undated but refers to a test that was “recently completed in
Dec. 2000.” As also stated in CRS Report RL33360, Navy Ship Propulsion Technologies: Options for Reducing Oil
Use—Background for Congress
, by Ronald O'Rourke, an earlier (1994) study by the same organization estimated that
79 existing Navy cruisers and destroyers could be fitted with bow bulbs for a total development and installation cost of
less than $30 million, and that the constant-dollar life-cycle fuel savings of the 79 ships would be $250 million.
(Dominic S. Cusanelli, “Development of a Bow for a Naval Surface Combatant which Combines a Hydrodynamic Bulb
and a Sonar Dome,” paper presented at the American Society of Naval Engineers Technical Innovation Symposium,
September 1994.) DOD stated in 2000 that fitting bulbous bows onto 50 DDG-51s (a total of 62 DDG-51s have been
procured) could save $200 million in life-cycle fuel costs. (U.S. Department of Defense, Climate Change, Energy
Efficiency, and Ozone Protection, Protecting National Security and the Environment
. Washington, 2000. (Office of the
Deputy Under Secretary of Defense (Environmental Security), November 2000) p. 5. Available online at
https://www.denix.osd.mil/denix/Public/Library/Air/Climate_Change/dodclimatechange.pdf.)
Congressional Research Service
58


Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Figure D-1. Near-Surface Bow Bulb Design for DDG-51
(bulb above, existing sonar dome below)

A document from the hydromechanics department of the Naval Surface Warfare Center
Carderock Directorate summarizing efforts by that department through 1999 to improve the
hydrodynamic and operational performance of the DDG-51 similarly states that in tests of this
proposal:
Ship performance improvement was projected for the entire ship speed range across all sea
states tested, resulting in significant annual fuel savings.
Analysis of seakeeping data and extreme sea wave load tests indicate that the bow bulb had
no significant impact on ship motions or hull girder loads. Acoustic transfer function tests
data from a vibracoustic model concluded that the bow bulb should have little noticeable
impact on the sonar self-noise levels.65
Using the figures in the table from Admiral Roughead’s May 7 letter, reducing DDG-51 use by an
additional 3.9% would reduce the ship’s annual operating (steaming) cost from the figure of $15.7
million shown in the table to about $12.7 million—a reduction of $3.0 million. This savings
figure is again based on a fuel cost of $112.14 per barrel.
Summary of Potential O&S Cost Reductions
Table D-1, below, summarizes the potential reductions in annual DDG-51 O&S costs from the
three options discussed above. The total figure of $34.8 million shown in the final column of the
table is about 15% less than the figure of $41.2 million from the table in Admiral Roughead’s
May 7 letter. These figures would need to be adjusted for the options discussed later in this
statement to take into account the configuration changes of those options.

65 Document entitled “Recent Design Programs, DDG 51,” available online at http://www.nswccd.navy.mil/hyd/mul-
gal/doc-gal-1/documents/DDG51.pdf.
Congressional Research Service
59

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Table D-1. DDG-1000 and DDG-51 Annual O&S Costs
DDG 51 with
potential O&S cost
(FY$M)
DDG 1000
DDG 51
reductions
Operating
$18.5 $15.7 $12.7
(steaming)
Maintenance $10.3
$5.6
$5.6
Manpower $8.5 $19.9 $16.5
Total $37.3
$41.2
$34.8
Crew Size
120 Total:
296 Total:
246 Total
(14 officers, 106
(24 Officers, 272
enlisted)
Enlisted)
Source: Letter dated May 7, 2008, from Admiral G. Roughead to the Honorable Edward M. Kennedy, p. 2 (first
two data columns) and CRS review of Navy and industry data (third data column).
Version with Reduced O&S Costs and Additional Vertical-Launch Tubes
This version of the DDG-51 design would include additional vertical-launch tubes as well as
features for reducing O&S costs. The purpose in procuring this version would be to provide the
fleet with improved IAMD capabilities.
Additional vertical-launch tubes could be installed by lengthening the ship’s hull forward of the
deckhouse. A 1994 CRS report discussed, on the basis of Navy information, how a 12-foot
extension could permit the installation of 32 additional VLS cells.66 In 1997, to support research
that CRS was conducting into possible alternatives to the Navy’s proposed Arsenal Ship,67 the
Navy provided CRS with information on how lengthening the DDG-51 hull so as to install
additional VLS tubes might change the ship’s procurement cost. The information is summarized
in Table D-2, below. The estimated changes in procurement cost were parametric, rough order of
magnitude (ROM) estimates only, subject to further engineering evaluation, and did not include
detailed design or nonrecurring engineering costs. Although the table shows variants equipped
with Mk 41 VLS tubes (the kind currently used on Navy surface ships), adding vertical launch
tubes of a newer design may also be possible.


66 See CRS Report 94-343, Navy DDG-51 Destroyer Procurement Rate: Issues and Options for Congress, by Ronald
O’Rourke [April 25, 1994; out of print and available directly from the author]), pp. CRS-27 to CRS-28.
67 The Arsenal Ship program was aimed at acquiring a small number of relatively simple and inexpensive surface ships,
each armed with about 512 VLS tubes. The program was cancelled in 1997. For more on the program, see CRS Report
97-455, Navy/DARPA Arsenal Ship Program: Issues and Options for Congress, by Ronald O’Rourke, and CRS Report
97-1004, Navy/DARPA Maritime Fire Support Demonstrator (Arsenal Ship) Program: Issues Arising From Its
Termination
, by Ronald O’Rourke.
Congressional Research Service
60

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Table D-2. 1997 Navy Information on DDG-51 Variants
Number
of
Hull
Rough recurring
Number of Mk 41 VLS tubes (%
5-inch
extension
procurement cost
Variant
change relative to Flight IIA)
guns
(in feet)
(relative to Flight IIA)
Current Flight
96
1
0
1.00
IIA design
Option 1
128 (+ 33%)
1
12
<1.05
Option 2
160 (+ 67%)
1
30
<1.10
Option 3
192 (+100%)
1
<56
<1.15
Option 4
256 (+167%)
1
56
<1.20
Source: U.S. Navy data provided to CRS on April 9, 1997, except for the figure of 12 feet shown for the variant
with 32 additional VLS cells, which is U.S. Navy data provided for CRS Report 94-343, Navy DDG-51 Destroyer
Procurement Rate: Issues and Options for Congress, by Ronald O’Rourke [April 25, 1994; out of print and available
directly from the author]). The cost figures in the table are rough order of magnitude (ROM) estimates and do
not reflect any detailed design or engineering costs typically reflected in a lead-ship cost. The cost estimates
provided by the Navy to CRS, though ROM estimates, were more precise than shown here, and were labeled
business sensitive. They have been rendered more approximate by CRS for presentation in this table. The costs
of the options as estimated by the Navy did not differ from one another in exact increments of 5%. See also
Figure 6 on page 131 from Dean A. Rains, “Methods For Ship Military Effectiveness Analysis,” Naval Engineers
Journal, March 1994: 126-135; and Table 3 on page 26 from Dean A. Rains, “Naval Ship Affordability,” Naval
Engineers Journal, July 1996: 19-30.
As shown in the table, all these options retain the DDG-51’s 5-inch gun. If the gun is considered
not critical for the ship’s intended concept of operations, it could be eliminated from the design,
which would reduce the design’s procurement cost. Supporters of eliminating the 5-inch gun
might argue that the gun is not critical because it does not contribute to a goal of providing
improved IAMD capabilities, and because the Navy already has 106 5-inch guns on 22 existing
Aegis cruisers (two guns each) and 62 DDG-51s already in service or under construction (one
gun each). Opponents of eliminating the 5-inch gun could argue that the absence of a gun would
reduce the mission flexibility of the ship.
Version with Reduced O&S Costs and an Improved Radar
This version of the DDG-51 design would include an improved radar in the place of the DDG-
51’s current SPY-1 radar, as well as features for reducing O&S costs. The purpose in procuring
this version would be to provide the fleet with improved IAMD capabilities.
The improved radar would use active-array radar technology, as opposed to the older passive-
array technology used in the SPY-1. The active-array technology would be similar to that used,
for example, in the DDG-1000 dual band radar. Multiple industry sources have briefed CRS on
their proposals for modifying the DDG-51 design to include an active-array radar with greater
capability than the SPY-1.
If the DDG-51 hull is not lengthened, then modifying the DDG-51 design to include an improved
radar would require removing the 5-inch gun to make space and weight available for additional
equipment needed to support operations with the improved radar. Lengthening the hull might
Congressional Research Service
61

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

provide enough additional space and weight capacity to permit the 5-inch gun to be retained.68
Supporting equipment to be installed would include an additional electrical generator and
additional cooling equipment.69 The best location for the generator might be in one of the ship’s
two helicopter hangar spots, which would reduce the ship’s helicopter hangar capacity from two
helicopters to one.
Due to the higher cost of the improved radar compared with the SPY-1 and the cost for the
additional generator and cooling equipment, modifying the DDG-51 design to this configuration
would increase the recurring procurement cost of the ship. Information provided to CRS by
industry suggests that if the hull is not lengthened, the increase might be in the general range of
$100 million, or perhaps or more. If the hull were lengthened, the cost increase would be greater.
Version with Reduced O&S, Additional Tubes, and an Improved Radar
This version of the DDG-51 design would include both additional vertical-launch tubes and an
improved radar, as well as features for reducing O&S costs. The purpose in procuring this version
would be to provide the fleet with improved IAMD capabilities. This option would require the
hull to be lengthened. The resulting ship would be more expensive in all respects (nonrecurring
design and engineering costs, procurement costs, and annual O&S costs) and more capable than
the other options discussed here.70 If the ship’s hull were lengthened by 55 or 56 feet, the
resulting ship might be roughly 25% more expensive to procure than the current Flight IIA
design, or perhaps more than that.
DDG-1000 Design Variants
As with the DDG-51 design options discussed above, modifying the DDG-1000 design could
incur additional nonrecurring design and engineering costs, and could affect the estimated
procurement cost of the ship.
Procuring a modified DDG-1000 design that includes additional vertical
launch tubes rather than AGSs

This option would more closely align the DDG-1000 design with a goal of providing the fleet
with improved IAMD capabilities by removing one or both of the ship’s two AGSs and their
magazines and using the freed-up space for additional vertical launch tubes.

68 Some sources consulted by CRS believe that the 5-inch gun could be retained, even if the hull is not lengthened.
69 Some sources consulted by CRS believe that an additional electrical generator might not be needed.
70
Depending on the amount of reduction in annual O&S costs, it is possible that this ship might be comparable to, or less
expensive than, a baseline DDG-51 Flight IIA in terms of annual O&S costs.
Congressional Research Service
62

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Procuring a modified DDG-1000 design that includes additional vertical
launch tubes rather than AGSs, and also a higher-capability radar

This option, which would also more closely align the DDG-1000 design with a goal of providing
the fleet with improved IAMD capabilities, is similar to the previous option, except that the
DDG-1000 would also be equipped with a radar with more capability than the radar in the current
DDG-1000 design. (The higher-capability radar would use active-array technology, like the
current DDG-1000 radar, but would use that technology in a radar with more fully populated
arrays.) A radar with a certain amount of additional capability could be accommodated without
redesigning the DDG-1000 deck house; a radar with a greater amount of additional capability
could be accommodated through a partial redesign of the deckhouse (i.e., a redesign that would
affect the deckhouse but not require a change to the ship’s basic hull design). Due to the space
needed for the additional cooling units that would be needed to support a higher-capability radar,
this option might result in a smaller number of additional vertical launch tubes than the previous
option.
September 2008 Press Report
A September 12, 2008, press report stated:
Raytheon [RTN] has a proposal on the table with the Navy to make the emergent Zumwalt-
class DDG-1000 destroyers missile defense platforms, according to a company official.
In an interview yesterday with sister publication Space and Missile Defense Report, Taylor
Lawrence, president of Raytheon Missile Systems, noted that the Zumwalt-class destroyers
have stealth capabilities, able to move in close to enemy shores without being detected by
enemy radar.
“The good thing about Zumwalt is, it’s really the advanced ship, with the advanced combat
system, and the advanced components of missiles and everything that brings it together to
give it ... the best capability that the Navy could have for the next few years,” Lawrence
said....
“The thing we’re talking about right now is even more over and above some of the
capabilities that is in its [the Zumwalt] current requirements ... specifically about missile
defense,” Lawrence said.
“Is it a missile-defense-capable ship? And our answer—and we put proposals on the table—
is, it could be.”
A Zumwalt missile defense system would be equipped with the same family of missiles that
Raytheon built for the Aegis system, Lawrence added.
But, he added, the Zumwalt “would be a far more capable missile defense ship.”
Additionally, he said, “our proposal says let’s do some things that basically enhance the
missiles so that they’re compatible across, say, the Aegis system and the Zumwalt class and
then even our coalition partners.”
That would be accomplished, he said, by putting a data link on board the ships that “could
talk to either one ... can talk to Aegis, talk to Zumwalt, talk to our coalition partners. We
think that that’s really the future. You make the missile interoperable across all those
Congressional Research Service
63

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

configurations. If you do that, then if the Navy chooses to make Zumwalt a missile-defense-
capable ship, it becomes very easy to do—and we think very affordable.”
The Zumwalt combat system could track an enemy missile, and “the Zumwalt could be,
then, a missile-defense-capable ship, with an SM-3 [interceptor], or SM-6, by itself,” with a
dual data link on the missile.
Thus far, the Navy hasn’t accepted the Raytheon offer, deciding that the Zumwalt “is not a
missile-defense-capable ship because they’ve decided, so far, not to buy that capability,”
Lawrence said.
But the same could be said of Arleigh Burke-class destroyers until they are upgraded with
the Aegis/SM-3 ballistic missile defense capability, he said. “These are ... enhancements to
the baseline destroyers, and you can do the enhancement to either one.”
Where all that comes down is a decision as to how many of each type of ship the Navy
wishes to procure. “The big debate is, how much of either one do you want to do,” Lawrence
said. “We believe that we have a proposal on the table that would make the Zumwalt the
most capable missile defense destroyer in the fleet. But [first] you need to do a few things to
the [interceptor] missiles, you need to do a few things to the combat system, you need to buy
that incremental capability.”
As well, Zumwalts could function well in area air warfare, taking out incoming enemy air
threats, Lawrence added.
“You put the SM-2s on board, eventually SM-6s, you got a very, very capable area air
warfare defense destroyer,” he said.71
November 2009 Press Report
A November 9, 2009, press report stated:
Faced with a U.S. Navy that has moved away from the Zumwalt DDG 1000-class destroyer’s
original land-attack mission, Raytheon, prime contractor for the big destroyer’s combat
system and missiles, has presented the service with a detailed but unsolicited proposal to
upgrade the ship to perform the ballistic missile defense (BMD) mission the Navy says is
key to its future warships.
And in an attempt to sweeten the pot, the company is willing to guarantee the price of most
of the work. Raytheon says it can do the job for an additional $580 million under a fixed-
price contract. The total price, including specialized radar components, will be a bit higher,
industry sources said, but those items are dependent upon customer preferences and would
be furnished as government-supplied equipment.
“The work would involve fully populating the [SPY-4 S-band] volume-search radar with
transmit/receive modules,” the industry source said, along with “a minor tweak to the
launcher electronics to upgrade from SM-2 [Standard missiles] to handle SM-3 [BMD
missiles].” The BMD software to upgrade the ship’s computers could come from the Army’s
Theater High Altitude Area Defense (THAAD) system or the U.S. Missile Defense Agency’s

71 Dave Ahearn, “Raytheon Pitching Missile Defense Variant of DDG-1000,” Defense Daily, September 12, 2008: 2-3.
Bracketed words and stock-symbol identifiers, as well as ellipses in the interiors of paragraphs, as in the original.
Congressional Research Service
64

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

Sea-Based X-band radar (SBX), the industry source added, “and voilà, you have a BMD
version of the Zumwalt at sea six years ahead” of the CG(X) cruiser, the next-generation ship
planned to handle cruise and ballistic missile defense.
Raytheon submitted its proposal in September. And the Navy response? “Zero. Nothing
from anybody,” an informed source said Nov. 5. “Kind of surprising, but that’s the answer.”
Navy officials said they were aware of the Raytheon proposal, but said there wasn’t much
interest.
“There has been no change to the DDG 1000 program of record.” said Cmdr. Victor Chen, a
Navy spokesman.
“We don’t have a requirement for a BMD DDG 1000,” one Navy source said.
A top Raytheon official explained the idea.
“Given the current world situation, we believe it is important for decision-makers to know
that a credible BMD capability for the Zumwalt is doable and affordable, with potential
schedule advantages,” said Dan Smith, president of Raytheon’s Integrated Defense Systems,
Tewksbury, Mass. “We have not yet received a response.” The idea of converting the land-
attack destroyer to handle the increasingly important BMD mission isn’t new—particularly
after the Navy announced in summer 2008 it was “truncating” the planned seven-ship
Zumwalt class to three ships. That move, service officials said, was in response to new
threats that included ballistic missiles able to hit ships at sea and to the increasing threat from
cruise missiles. Defeating those threats, the Navy said, was not part of the DDG 1000 design.
Additionally, the Navy said the requirement to support Marines ashore with persistent,
precision fire support from the Zumwalt’s new 155mm Advanced Gun System also could be
met by other means.
What the Navy really needs, service officials say, are ships able to meet the BMD threat
now. That’s a blow for Raytheon, since the ships the Navy is buying in increasing numbers
are Arleigh Burke DDG 51-class destroyers with Lockheed Martin’s Aegis combat system,
modified to take on the BMD role.
Industry sources said the Navy asked Raytheon early in 2008 to analyze upgrading the
Zumwalts to the BMD mission. The company said few significant enhancements were
needed to the SPY-3 X-band radar—half of the ship’s dual-band radar system—but the S-
band SPY-4 volume search radar needed significant modifications. Each radar array, the
informed source said, has about 2,688 transmit/receive modules. A “fully populated” array
would have about 4,544.
Fully upgraded, the radar system would show an improvement in baseline performance of
about 16 dB, the informed source said.
The September proposal upgraded the early 2008 work and added further enhancements to
bring the system fully up to a BMD capability, the informed source said. Key modifications
would be necessary to the radar, the Mk 57 peripheral vertical launch system, and the
software. Each of the ship’s three fixed, phased radar arrays would gain about 8 metric tons
from the improvements, and the ship’s composite-structure deckhouse would need “minor
strengthening” to support the additional 24 metric tons.
But the Zumwalt design provides for future upgrades, industry sources said, and the ship has
power, cooling and stability margins available in the design specifications.
Congressional Research Service
65

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress

The modification plan “stayed within the margins,” the informed source said, and the
upgraded ship would still meet its speed requirements of better than 30 knots.
The informed source noted that underlying the proposal is a desire by Raytheon “to counter
some of the skepticism” of the DDG 1000 decision “and try to solicitate some more
engagement” in getting more use out of the design.
Raytheon’s proposal concerns only the as-yet-unnamed third ship, DDG 1002, which isn’t
scheduled to begin construction until 2011.
Construction of the first ship, DDG 1000, is about 16 percent com-plete at General
Dynamics’ Bath Iron Works shipyard in Maine, and fabrication of the second ship, the
Michael Monsoor (DDG 1001), is expected to begin next year.
Much of the BMD upgrade cost involves nonrecurring development costs, industry sources
said. Raytheon estimates the first two DDG 1000s could be upgraded for $62 million to $65
million per ship.
While the Navy has yet to respond to Raytheon’s proposal, company officials have been
briefing the idea to Navy and Pentagon parties and to key congressional committees.
Left out of those briefings, though, are the shipbuilders. General Dynamics is building the
ships, while Northrop Grumman—the original prime contractor on the DDG 1000
program—builds the composite deckhouse and other components.
Industry sources stressed that the BMD upgrade proposal was strictly a Raytheon initiative.
“There has been no external teaming or involvement with General Dynamics,” the informed
source said. “No industry partners or peers.”72
Non-combat Adjunct Ship with Powerful Radar
Another option that policymakers may consider for improving the fleet’s IAMD would be to
procure a non-combat ship equipped with a powerful radar to act as an adjunct platform for
missile defense operations and perhaps also air defense operations. The radar on the ship would
be a large, active-array radar that would be considerably more powerful, for example, than the
improved radar that could be installed on a DDG-51 or DDG-1000. The presence in the fleet of
such a radar could significantly improve the fleet’s IAMD capabilities. The ship might be similar
to the Cobra Judy Replacement ship currently under construction.73 A few or several such adjunct
ships might be procured, depending on the number of theaters to be covered, requirements for
maintaining forward deployments of such ships, and their homeporting arrangements. The ships
would have little or no self-defense capability and would need to be protected in threat situations
by other Navy ships.

72 Christopher P. Cavas, “Raytheon Pitches BMD Upgrades For Zumwalts,” Defense News, November 9, 2009: 27.
Material in brackets as in original.
73 The Cobra Judy Replacement (CJR) ship is intended to replace the missile range instrumentation ship Observation
Island (TAGM-23). Observation Island is a converted merchant ship operated by the Navy for the U.S. Air Force. The
ship is equipped with a powerful radar, called Cobra Judy, that is used for collecting technical information on foreign-
country ballistic missiles in flight. For more on the CJR program, see http://acquisition.navy.mil/programs/
information_communications/cjr.
Congressional Research Service
66

Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress


Author Contact Information

Ronald O'Rourke

Specialist in Naval Affairs
rorourke@crs.loc.gov, 7-7610


Congressional Research Service
67