Navy Attack Submarine Procurement:
Background and Issues for Congress

Ronald O'Rourke
Specialist in Naval Affairs
October 21, 2009
Congressional Research Service
7-5700
www.crs.gov
RL32418
CRS Report for Congress
P
repared for Members and Committees of Congress

Navy Attack Submarine Procurement: Background and Issues for Congress

Summary
The Navy has been procuring Virginia (SSN-774) class nuclear-powered attack submarines
(SSNs) at a rate of one per year for the past several years. The procurement rate is scheduled to
increase to two boats per year starting in FY2011. A total of 11 boats have been procured through
FY2009. The eight Virginia-class submarines to be procured in the five-year period FY2009-
FY2013 (boats 11 through 18) are being procured under a multiyear procurement (MYP)
arrangement.
The Navy’s proposed FY2010 budget requests $1,964.3 million in procurement funding to
complete the procurement cost of a 12th Virginia-class boat. The FY2010 budget estimates the
procurement cost of this boat at $2,756.7 million, and the ship has received a total of $792.4
million in prior-year funding. The Navy’s proposed FY2010 budget also requests $1,346.4
million in advance procurement (AP) funding for Virginia-class boats to be procured in future
years, and $613.3 million in additional AP funding for Economic Order Quantity (EOQ)
purchases of long-leadtime items for Virginia-class boats to be procured under the FY2009-
FY2013 MYP arrangement.
The House and Senate Appropriations Committees, in their reports (H.Rept. 111-230 of July 24,
2009 and S.Rept. 111-74 of September 10, 2009, respectively) on the FY2010 Department of
Defense (DOD) appropriations bill (H.R. 3326), both recommend approving the Administration’s
FY2010 request for procurement and advance procurement funding for the Virginia-class
submarine program.

Congressional Research Service

Navy Attack Submarine Procurement: Background and Issues for Congress

Contents
Introduction ................................................................................................................................ 1
Background ................................................................................................................................ 1
Submarines in the U.S. Navy................................................................................................. 1
Types of Submarines ....................................................................................................... 1
Roles and Missions ......................................................................................................... 1
Attack Submarine Force Levels............................................................................................. 3
Force-Level Goal ............................................................................................................ 3
Historical Force Levels ................................................................................................... 3
Force Level As of End Of FY2008 .................................................................................. 3
Virginia (SSN-774) Class Program........................................................................................ 4
General ........................................................................................................................... 4
Past and Planned Procurement......................................................................................... 4
Changes in Planned Procurement Rates........................................................................... 4
Multiyear Procurement (MYP)........................................................................................ 5
Joint Production Arrangement ......................................................................................... 6
Cost-Reduction Effort ..................................................................................................... 6
Submarine Construction Industrial Base ................................................................................ 7
General ........................................................................................................................... 7
Design and Engineering Portion ...................................................................................... 8
Projected SSN Shortfall ........................................................................................................ 8
Size and Timing of Shortfall............................................................................................ 8
Navy Study On Options For Mitigating Projected Shortfall ............................................. 9
Issues for Congress ................................................................................................................... 11
48-Boat Force-Level Goal and Planned SSN Procurement................................................... 11
Virginia-Class Technology Insertion.................................................................................... 12
Potential Options for Congress .................................................................................................. 13
Legislative Activity For FY2010 ............................................................................................... 13
FY2010 Funding Request.................................................................................................... 13
FY2010 Defense Authorization Bill (H.R. 2647/S. 1390) .................................................... 13
House ........................................................................................................................... 13
Senate ........................................................................................................................... 14
Conference.................................................................................................................... 15
FY2010 DOD Appropriations Bill (H.R. 3326).................................................................... 15
House ........................................................................................................................... 15
Senate ........................................................................................................................... 15

Tables
Table 1. Past and Planned Virginia-Class Procurement................................................................. 4
Table 2. Planned Virginia-Class Procurement in Various FYDPs.................................................. 5
Table 3. SSN Force Level, 2009-2038 (Navy Projection)............................................................. 9

Congressional Research Service

Navy Attack Submarine Procurement: Background and Issues for Congress

Appendixes
Appendix A. Past SSN Force-Level Goals ................................................................................. 16
Appendix B. Views Regarding 48-Boat SSN Force-Level Goal ................................................. 18
Appendix C. Options for Funding SSNs .................................................................................... 20
Appendix D. Maintaining Submarine Design and Engineering Base .......................................... 23

Contacts
Author Contact Information ...................................................................................................... 24

Congressional Research Service

Navy Attack Submarine Procurement: Background and Issues for Congress

Introduction
The Navy has been procuring Virginia (SSN-774) class nuclear-powered attack submarines
(SSNs) at a rate of one per year for the past several years. The procurement rate is scheduled to
increase to two boats per year starting in FY2011. A total of 11 boats have been procured through
FY2009. The eight Virginia-class submarines to be procured in the five-year period FY2009-
FY2013 (boats 11 through 18) are being procured under a multiyear procurement (MYP)
arrangement.
The Navy’s proposed FY2010 budget requests $1,964.3 million in procurement funding to
complete the procurement cost of a 12th Virginia-class boat. The FY2010 budget estimates the
procurement cost of this boat at $2,756.7 million, and the ship has received a total of $792.4
million in prior-year funding. The Navy’s proposed FY2010 budget also requests $1,346.4
million in advance procurement (AP) funding for Virginia-class boats to be procured in future
years, and $613.3 million in additional AP funding for Economic Order Quantity (EOQ)
purchases of long-leadtime items for Virginia-class boats to be procured under the FY2009-
FY2013 MYP arrangement.
Background
Submarines in the U.S. Navy
Types of Submarines
Submarines are one of four principal categories of combat ships that traditionally have helped
define the size and structure of the U.S. Navy. The other three are aircraft carriers, surface
combatants (e.g., cruisers, destroyers, frigates, and Littoral Combat Ships), and amphibious ships.
(The Navy also includes mine warfare ships and a variety of auxiliary and support ships.)
Submarines can be powered by either nuclear reactors or non-nuclear power sources such as
diesel engines or fuel cells. All U.S. Navy submarines are nuclear-powered. A submarine’s use of
nuclear or non-nuclear power as its energy source is not an indication of whether it is armed with
nuclear weapons—a nuclear-powered submarine can lack nuclear weapons, and a non-nuclear-
powered submarine can be armed with nuclear weapons.
Roles and Missions
U.S. Navy submarines fall into three types—nuclear-powered ballistic missile submarines
(SSBNs), nuclear-powered cruise missile submarines (SSGNs), and nuclear-powered attack
submarines (SSNs).1

1 In the designations SSBN, SSGN, and SSN, SS stands for submarine, N stands for nuclear-powered, B stands for
ballistic missile, and G stands for guided missile (such as a cruise missile).
Congressional Research Service
1

Navy Attack Submarine Procurement: Background and Issues for Congress

SSBNs
The SSBNs’ basic mission is to remain hidden at sea with their nuclear-armed submarine-
launched ballistic missiles (SLBMs) and thereby deter a strategic nuclear attack on the United
States.2 As of the end of FY2008, the Navy included 14 Ohio (SSBN-726) class SSBNs, which
are commonly called Trident submarines because they carry Trident SLBMs. Each Trident SSBN
can carry 24 Trident SLBMs.
SSGNs
The Navy’s four SSGNs, which are a recent addition to the fleet, are former Trident SSBNs that
have been converted (i.e., modified) to carry Tomahawk cruise missiles and special operations
forces (SOF) rather than SLBMs. Although the SSGNs differ somewhat from SSNs in terms of
mission orientation (with the SSGNs being strongly oriented toward Tomahawk strikes and SOF
support, while the SSNs are more general-purpose in orientation), SSGNs can perform other
submarine missions and are sometimes included in counts of the projected total number of Navy
attack submarines. The Navy’s SSGNs are discussed in another CRS report.3
SSNs
The SSNs—the focus of this report—are general-purpose submarines that perform a variety of
peacetime and wartime missions, including the following:
• covert intelligence, surveillance, and reconnaissance (ISR), much of it done for
national-level (as opposed to purely Navy) purposes;
• covert insertion and recovery of SOF (on a smaller scale than possible with the
SSGNs);
• covert strikes against land targets with the Tomahawk cruise missiles (again on a
smaller scale than possible with the SSGNs);
• covert offensive and defensive mine warfare;
• anti-submarine warfare (ASW); and
• anti-surface ship warfare.
During the Cold War, ASW against the Soviet submarine force was the primary stated mission of
U.S. SSNs, although covert ISR and covert SOF insertion/recovery operations were reportedly
important on a day-to-day basis as well.4 In the post-Cold War era, although anti-submarine

2 Although this mission is often associated with the Cold War-era nuclear competition between the United States and the
Soviet Union, it has continued, with some modifications, in the post-Cold War era. For a discussion of U.S. strategic nuclear
weapons policy and force structure, see CRS Report RL31623, U.S. Nuclear Weapons: Changes in Policy and Force
Structure
, by Amy F. Woolf.
3 CRS Report RS21007, Navy Trident Submarine Conversion (SSGN) Program: Background and Issues for Congress,
by Ronald O’Rourke.
4 For an account of certain U.S. submarine surveillance and intelligence-collection operations during the Cold War, see
Sherry Sontag and Christopher Drew with Annette Lawrence Drew, Blind Man’s Bluff (New York: Public Affairs,
1998).
Congressional Research Service
2

Navy Attack Submarine Procurement: Background and Issues for Congress

warfare remains a mission, the SSN force has focused more on performing the other missions
noted on the list above.
Attack Submarine Force Levels
Force-Level Goal
In February 2006, the Navy proposed achieving and maintaining in coming years a fleet with a
total of 313 ships, including 48 SSNs (and 4 SSGNs). For a review of SSN force level goals since
the Reagan Administration, see Appendix A.
Historical Force Levels
The SSN force included more than 90 boats during most of the 1980s, peaked at 98 boats at the
end of FY1987, and then began to decline. The force included 85 to 88 boats during the early
1990s, 79 boats at the end of FY1996, 65 boats at the end of FY1998, 57 boats at the end of
FY1999, and 56 boats at the end of FY2000. It has since numbered 53 to 56 boats. The decline in
the number of SSNs since the late 1980s has roughly paralleled the decline in the total size of the
Navy over the same time period.
Force Level As of End Of FY2008
The 53 SSNs in service at the end of FY2008 included the following:
• 45 Los Angeles (SSN-688) class boats;
• 3 Seawolf (SSN-21) class boats; and
• 5 Virginia (SSN-774) class boats.
Los Angeles (SSN-688) Class SSNs
A total of 62 Los Angeles-class submarines, commonly called 688s, were procured between
FY1970 and FY1990 and entered service between 1976 and 1996. They are equipped with four
21-inch diameter torpedo tubes and can carry a total of 26 torpedoes or Tomahawk cruise missiles
in their torpedo tubes and internal magazines. The final 31 boats in the class (SSN-719 and
higher) are equipped with an additional 12 vertical launch system (VLS) tubes in their bows for
carrying and launching another 12 Tomahawk cruise missiles. The final 23 boats in the class
(SSN-751 and higher) incorporate further improvements and are referred to as Improved Los
Angeles class boats or 688Is. As of the end of FY2008, 17 of the 62 boats in the class had been
retired.
Seawolf (SSN-21) Class SSNs
The Seawolf class was originally intended to include about 30 boats, but Seawolf-class
procurement was stopped after three boats as a result of the end of the Cold War and associated
changes in military requirements. The three Seawolf-class submarines are the Seawolf (SSN-21),
the Connecticut (SSN-22), and the Jimmy Carter (SSN-23). SSN-21 and SSN-22 were procured
in FY1989 and FY1991 and entered service in 1997 and 1998, respectively. SSN-23, which was
Congressional Research Service
3

Navy Attack Submarine Procurement: Background and Issues for Congress

built to a lengthened configuration compared to the other two ships in the class, was originally
procured in FY1992. Its procurement was suspended in 1992 and then reinstated in FY1996. It
entered service in 2005. Seawolf-class submarines are larger than Los Angeles-class boats or
previous U.S. Navy SSNs.5 They are equipped with eight 30-inch-diameter torpedo tubes and can
carry a total of 50 torpedoes or cruise missiles.
Virginia (SSN-774) Class Program
General
The Virginia-class attack submarine was designed to be less expensive and better optimized for
post-Cold War submarine missions than the Seawolf-class design. The Virginia-class design is
slightly larger than the Los Angeles-class design,6 but incorporates newer technologies. Virginia-
class boats currently cost about $2.8 billion each to procure. The first Virginia-class boat entered
service in October 2004.
Past and Planned Procurement
As shown in Table 1, 11 Virginia-class boats have been procured through FY2009, and 7 more
are planned for procurement during the period FY2010-FY2013 as part of a multiyear
procurement (MYP) arrangement for procuring a total of eight boats during the period FY2009-
FY2013.
Table 1. Past and Planned Virginia-Class Procurement
FY98 FY99 FY00 FY01 FY02 FY03 FY04 FY05
1 1 0 1 1 1 1 1
FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13
1 1 1 1 1 2 2 2
Source: Prepared by CRS based on U.S. navy data, including multiyear procurement (MYP) arrangement for
procuring Virginia-class boats in FY2009-FY2013.
Changes in Planned Procurement Rates
When Virginia-class procurement began in the 1990s, DOD originally projected that the
procurement rate would increase to two boats per year in FY2002. (The originally envisaged
procurement profile for the Virginia-class program for the years FY1998-FY2002 was 1-0-1-0-2.)
In subsequent budgets, the date for starting two-per-year procurement was progressively pushed
back. Table 2 shows planned Virginia-class procurement in FYDPs submitted since the mid-
1990s.


5 Los Angeles-class boats have a beam (i.e., diameter) of 33 feet and a submerged displacement of about 7,150 tons.
Seawolf-class boats have a beam of 40 feet. SSN-21 and SSN-22 have a submerged displacement of about 9,150 tons.
SSN-23 is 100 feet longer than SSN-21 and SSN-22 and has a submerged displacement of 12,158 tons.
6 Virginia-class boats have a beam of 34 feet and a submerged displacement of 7,800 tons.
Congressional Research Service
4

Navy Attack Submarine Procurement: Background and Issues for Congress

Table 2. Planned Virginia-Class Procurement in Various FYDPs
FYDP (date
submitted)
98 99 00 01 02 03 04 05 06 07 08 09 10 11 12 13
FY95-99 (2/94)
1
0

FY96-01
(2/95)
1 0 1 0

FY97-01 (3/96)
1
1a 1 1a

FY98-03
(2/97)
1 1 0 1 1 0

FY99-03
(2/98)
1 0 1 1 0

FY00-05
(2/99)

0 1 1 1 1 1

FY01-05
(2/00)

1 1 1 1 1

FY2002 (6/01)b
1

FY03-07
(2/02)

1 1 1 1 1

FY04-09
(2/03)

1 1 1 2 2 2

FY05-09
(2/04)

1 1 1 1 2

FY06-11
(2/05)

1 1 1 1 1 1

FY07-11
(2/06)

1 1 1 1 1

FY08-13
(2/07)

1 1 1 1 2 2
FY09-13
(2/08)

1 1 2 2 2
FY2010 (5/09)c


1
[2]
[2]
[2]
Source: Prepared by CRS using Navy data.
a. Included at Congressional direction, but not funded in the plan.
b. Submission for FY2002 budget only; no FYDP for FY2002-FY2007 submitted. This was the first year of the
George W. Bush Administration. The boat proposed for procurement in FY2002 was the final boat
procured under a block-buy arrangement that included four boats in the period FY1998-FY2002.
c. Submission for FY2010 budget only; no FYDP for FY2010-FY2015 submitted. This was the first year of the
Obama Administration. The boat proposed for procurement in FY2010 is the second of eight boats to be
procured under a multiyear procurement (MYP) arrangement approved by Congress that includes a total of
eight boats in the period FY2009-FY2013, in annual quantities of 1, 1, 2, 2, and 2, respectively. The figures of
two boats per year shown in brackets for the years FY2011-FY2013 reflect the annual quantities for those
years under the MYP arrangement.
Multiyear Procurement (MYP)
Under a multiyear procurement (MYP) arrangement requested by the Navy and approved by
Congress in FY2008 and FY2009,7 a total of eight Virginia-class boats (boats 11 through 18 in the

7 Section 8011 of the compromise version of the FY2009 defense appropriations act (Division C of H.R. 2638/P.L.
110-329 of September 30, 2008) granted authority for using FY2009 funds for an MYP arrangement for the Virginia-
class program. Section 122 of the compromise version of the FY2009 defense authorization bill (S. 3001/P.L. 110-417
of October 14, 2008) modified the authority to use an MYP arrangement for Virginia-class boats to be procured in
FY2009-FY2013 that was granted to the Secretary of the Navy by Section 121 of FY2008 defense authorization act
(H.R. 4986/P.L. 110-181 of January 28, 2008). The modification additionally permits the Secretary to enter into one or
more contracts for advance procurement and advance construction of components for the boats procured under the
MYP arrangement.
Congressional Research Service
5

Navy Attack Submarine Procurement: Background and Issues for Congress

program) are to be procured in the period FY2009-FY2013, in annual quantities of 1, 1, 2, 2, and
2, respectively.
The five Virginia-class boats procured in FY2004-FY2008 were also procured under a multiyear
procurement (MYP) arrangement. The four boats procured in FY1998-FY2002 were procured
under a somewhat similar arrangement called a block buy. The boat procured in FY2003 fell
between the FY1998-FY2002 block buy and the FY2004-FY2008 MYP.
Joint Production Arrangement
Virginia-class boats are built jointly by General Dynamics’ Electric Boat Division (GD/EB) of
Groton, CT, and Quonset Point, RI, and the Newport News, VA, shipyard that forms part of
Northrop Grumman Shipbuilding (NGSB).8 Under the arrangement, GD/EB builds certain parts
of each boat, Newport News builds certain other parts of each boat, and the yards take turns
building the reactor compartments and performing final assembly of the boats. GD/EB is building
the reactor compartments and performing final assembly on boats 1, 3, and so on, while Newport
News is doing so on boats 2, 4, and so on. The arrangement results in a roughly 50-50 division of
Virginia-class profits between the two yards and preserves both yards’ ability to build submarine
reactor compartments (a key capability for a submarine-construction yard) and perform
submarine final-assembly work.
The joint production arrangement is a departure from past U.S. submarine construction practices,
under which complete submarines were built in individual yards. The joint production
arrangement is the product of a debate over the Virginia-class acquisition strategy within
Congress, and between Congress and DOD, that occurred in 1995-1997 (i.e., during the markup
of the FY1996-FY1998 defense budgets). The goal of the arrangement is to keep both GD/EB
and Newport News involved in building nuclear-powered submarines, and thereby maintain two
U.S. shipyards capable of building nuclear-powered submarines, while minimizing the cost
penalties of using two yards rather than one to build a submarine design that is being procured at
a relatively low annual rate.
Cost-Reduction Effort
The Navy states that it has achieved a goal of reducing the cost of Virginia-class submarines so
that two boats can be procured in FY2012 for combined cost of $4.0 billion in FY2005 dollars—a
goal referred to as “2 for 4 in 12.” Achieving this goal involved removing about $400 million (in
FY2005 dollars) from the cost of each submarine. (The Navy calculates that the unit target cost of
$2.0 billion in FY2005 dollars for each submarine translates into about $2.6 billion for a boat
procured in FY2012, and about $2.7 billion for a boat procured in FY2013.)
The Navy says that, in constant FY2005 dollars, about $200 million of the $400 million in the
sought-after cost reductions were accomplished simply through the improved economies of scale
(e.g., better spreading of shipyard fixed costs and improved learning rates) of producing two
submarines per year rather than one per year. The remaining $200 million in sought-after cost
reductions, the Navy says, was accomplished through changes in the ship’s design (which will

8 GD/EB and the Newport News shipyard are the only two shipyards in the country capable of building nuclear-
powered ships. GD/EB builds submarines only, while the Newport News shipyard also builds nuclear-powered aircraft
carriers and is capable of building other types of surface ships.
Congressional Research Service
6

Navy Attack Submarine Procurement: Background and Issues for Congress

contribute roughly $100 million toward the cost-reduction goal) and changes in the shipyard
production process (which will contribute the remaining $100 million or so toward the goal).
Some of the design changes will be introduced to Virginia-class boats procured prior to FY2012,
but the Navy says the full set of design changes will not be ready for implementation until the
FY2012 procurement.
Changes in the shipyard production process are aimed in large part at reducing the total shipyard
construction time of a Virginia-class submarine from 72 months to 60 months. (If the ship spends
less total time in the shipyard being built, its construction cost will incorporate a smaller amount
of shipyard fixed overhead costs.) The principal change involved in reducing shipyard
construction time to 60 months involves increasing the size of the modules that form each
submarine, so that each submarine can be built out of a smaller number of modules. The Navy
says that the goal of reducing shipyard construction time to 60 months is a medium-risk goal,
meaning that the Navy believes that there is a moderate (as opposed to low or high) risk that the
goal will not be achieved.
Because the full set of design changes and the reduction in construction time to 60 months will
not be achieved until FY2012, the Navy says that the $2.0 billion goal cannot be fully met for
boats procured prior to FY2012, even if those boats are procured at a rate of two per year.
The Navy earlier stated that if improved economies of scale and changes in the ship’s design and
in the shipyard production process are not sufficient to achieve the $2.0-billion target, the Navy
might consider reducing the capabilities of the Virginia class in certain areas until the target is
achieved.9
The Navy’s goal to reduce the cost of each Virginia-class boat to $2.0 billion in constant FY2005
dollars is a goal that the Navy has set for itself. While Congress may take this goal into account, it
need not control congressional action.
Submarine Construction Industrial Base
General
In addition to GD/EB and Newport News, the submarine construction industrial base includes
scores of supplier firms, as well as laboratories and research facilities, in numerous states. About
80% of the total material procured from supplier firms for the construction of submarines
(measured in dollars rather than pieces, parts, or purchase orders) comes from single or sole
source suppliers. Observers in recent years have expressed concern for the continued survival of
many of these firms. For nuclear-propulsion component suppliers, an additional source of

9 For more on the Navy’s plan for reducing the procurement cost of the Virginia-class design, see Statement of Ms.
Allison Stiller, Deputy Assistant Secretary of the Navy (Ship Programs) and RDML [Rear Admiral] William Hilarides,
Program Executive Officer for Submarines, Before the Seapower and Expeditionary Forces Subcommittee of the
House Armed Services Committee [hearing on] Force Structure Requirements and Alternative Funding Strategies for
the United States Submarine Fleet, March 8, 2007; Richard R. Burgess, “Sub Force Innovation,”Seapower, February
2008: 16-19; Dave Johnson and Dustin Muniz, “More for Less,” Undersea Warfare, Winter 2007: 22-23, 28; and
William Hilarides, “2 For 4 in 2012, The Virginia-Class Road Ahead,” U.S. Naval Institute Proceedings, June 2006:
68-69.
Congressional Research Service
7

Navy Attack Submarine Procurement: Background and Issues for Congress

stabilizing work is the Navy’s nuclear-powered aircraft carrier construction program.10 In terms of
work provided to these firms, a carrier nuclear propulsion plant is roughly equivalent to five
submarine propulsion plants.
Design and Engineering Portion
Earlier in this decade, some observers expressed concern about the design and engineering
portion of the submarine construction industrial base. Much of the design and engineering portion
is resident at GD/EB and Newport News. (A small portion is resident at a some of the component
makers.) With Virginia-class design work winding down and no other submarine-design projects
underway, the submarine design and engineering base faced the near-term prospect, for the first
time in about 50 years, of having no major submarine-design project on which to work. Navy and
industry officials, Members of Congress, and other observers were concerned that unless a major
submarine-design project is begun soon, the submarine design and engineering base would begin
to atrophy through the departure of experienced personnel. Rebuilding an atrophied submarine
design and engineering base, Navy and industry officials believe, could be time-consuming,
adding time and cost to the task of the next submarine-design effort, whenever it might begin.
Concern about this possibility among some Navy and industry officials was strengthened by the
UK’s difficulties a few years ago in designing its new Astute-class SSN. The UK submarine
design and engineering base atrophied for lack of work, and the subsequent Astute-class design
effort experienced considerable delays and cost overruns. Submarine designers and engineers
from GD/EB were assigned to the Astute-class project to help the UK overcome these problems.11
The issue of maintaining the submarine design and engineering base appears to have been
addressed by bringing forward, to FY2010, the start of design work on the next-generation SSBN.
Under a more traditional schedule for designing the next-generation SSBN, design work on that
ship might not have begun for another few years. For further discussion, see Appendix D.
Projected SSN Shortfall
Size and Timing of Shortfall
The Navy’s 30-year SSN procurement plan, if implemented, would not be sufficient to maintain a
force of 48 SSNs consistently over the long run. As shown in Table 3, the Navy in 2008 projected
that the SSN force will fall below 48 boats during the 12-year period 2022-2033, reaching a
minimum of 41 boats in 2028-2029. Since the Navy plans to retire the four SSGNs by 2028
without procuring any replacements for them, no SSGNs would be available in 2028 and
subsequent years to help compensate for a drop in SSN force level below 48 boats.

10 For more on this program, see CRS Report RS20643, Navy Ford (CVN-78) Class Aircraft Carrier Program:
Background and Issues for Congress
, by Ronald O’Rourke.
11 See, for example, Andrew Chuter, “U.K. Spending Mounts for U.S. Help on Sub,” Defense News, September 13,
2005: 4; Richard Scott, “Electric Boat Provides Project Director for Astute Class,” Jane’s Navy International, May
2004: 33; Richard Scott, “Astute Sets Out on the Long Road to Recovery,” Jane’s Navy International, December 2003,
pp. 28-30; Richard Scott, “Recovery Plan Shapes Up for Astute Submarines,” Jane’s Defence Weekly, November 19,
2003, p. 26.
Congressional Research Service
8

Navy Attack Submarine Procurement: Background and Issues for Congress

Table 3. SSN Force Level, 2009-2038 (Navy Projection)
09 10 11 12 13 14 15 16 17 18 19 20 21 22 23
53 52 52 53 54 51 51 49 50 49 50 48 48 47 47
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
46 45 44 43 41 41 42 44 45 47 49 50 52 53 53
Source: Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2009, p. 8.
The potential for the Navy’s long-range SSN procurement plan to produce a shortfall in the SSN
force over the long run has been discussed by CRS since 1995, in the form of testimony to
Congress in 1995, 1997, 1999, 2000, 2002, 2004, 2006, and 2007, a 1997 CRS presentation to a
Defense Science Board task force on the submarine of the future, which issued its report in
1998;12 a 1999-2000 CRS report,13 a 2002 CRS report,14 and this report since its inception in
2004.
Navy Study On Options For Mitigating Projected Shortfall
The Navy in 2006 initiated a study on options for mitigating the projected SSN shortfall. The
study was completed in early 2007 and briefed to CRS and the Congressional Budget Office
(CBO) on May 22, 2007.15 At the time of the study, the SSN force was projected to bottom out at
40 boats—an 8-boat shortfall. The addition of a second submarine to be procured in FY2011 has
since reduced the projected shortfall to seven boats, as shown in Table 3. Principal points in the
Navy study include the following:
• The day-to-day requirement for deployed SSNs is 10.0, meaning that, on
average, a total of 10 SSNs are to be deployed on a day-to-day basis.16
• The peak projected wartime demand is about 35 SSNs deployed within a certain
amount of time. This figure includes both the 10.0 SSNs that are to be deployed
on a day-to-day basis and 25 additional SSNs surged from the United States
within a certain amount of time.17
• Reducing Virginia-class shipyard construction time to 60 months—something
that the Navy already plans to do as part of its strategy for meeting the Virginia-
class cost-reduction goal (see earlier discussion on cost-reduction goal)—will

12 U.S. Department of Defense, Office of the Under Secretary of Defense For Acquisition & Technology, Report of the
Defense Science Board Task Force on [the] Submarine of the Future
, July 1998, pp. 7, 19-20.
13 CRS Report RL30045, Navy Attack Submarine Programs: Background and Issues for Congress (out of print; for a
copy, contact the author at 707-7610), by Ronald O’Rourke.
14 CRS Report RL31372, Navy Shipbuilding in the FY2003 Defense Budget: Issues for Congress (out of print; for a
copy, contact the author at 707-7610), by Ronald O’Rourke.
15 Navy briefing entitled, “SSN Force Structure, 2020-2033,” presented to CRS and CBO on May 22, 2007.
16 The requirement for 10.0 deployed SSNs, the Navy stated in the briefing, was the current requirement at the time the
study was conducted.
17 The peak projected wartime demand of about 35 SSNs deployed within a certain amount of time, the Navy stated, is
an internal Navy figure that reflects several studies of potential wartime requirements for SSNs. The Navy stated that
these other studies calculated various figures for the number of SSNs that would be required, and that the figure of 35
SSNs deployed within a certain amount of time was chosen because it was representative of the results of these other
studies.
Congressional Research Service
9

Navy Attack Submarine Procurement: Background and Issues for Congress

increase the size of the SSN force by two boats, so that the force would bottom
out at 42 boats rather than 40.18
• If, in addition to reducing Virginia-class shipyard construction time to 60 months,
the Navy also lengthens the service lives of 16 existing SSNs by periods ranging
from 3 months to 24 months (with many falling in the range of 9 to 15 months),
this would increase the size of the SSN force by another two boats, so that the
force would bottom out at 44 boats rather than 40 boats.19 The total cost of
extending the lives of the 16 boats would be roughly $500 million in constant
FY2005 dollars.20
• The resulting force that bottoms out at 44 boats could meet the 10.0 requirement
for day-to-day deployed SSNs throughout the 2020-2033 period if, as an
additional option, about 40 SSN deployments occurring in the eight-year period
2025-2032 were lengthened from six months to seven months. These 40 or so
lengthened deployments would represent about one-quarter of all the SSN
deployments that would take place during the eight-year period.
• The resulting force that bottoms out at 44 boats could not meet the peak projected
wartime demand of about 35 SSNs deployed within a certain amount of time.
The force could generate a total deployment of 32 SSNs within the time in
question—three boats (or about 8.6%) less than the 35-boat figure. Lengthening
SSN deployments from six months to seven months would not improve the
force’s ability to meet the peak projected wartime demand of about 35 SSNs
deployed within a certain amount of time.
• To meet the 35-boat figure, an additional four SSNs beyond those planned by the
Navy would need to be procured. Procuring four additional SSNs would permit
the resulting 48-boat force to surge an additional three SSNs within the time in
question, so that the force could meet the peak projected wartime demand of
about 35 SSNs deployed within a certain amount of time.
• Procuring one to four additional SSNs could also reduce the number of seven-
month deployments that would be required to meet the 10.0 requirement for day-
to-day deployed SSNs during the period 2025-2032. Procuring one additional
SSN would reduce the number of 7-month deployments during this period to
about 29; procuring two additional SSNs would reduce it to about 17, procuring

18 If shipyard construction time is reduced from 72 months to 60 months, the result would be a one-year acceleration in
the delivery of all boats procured on or after a certain date. In a program in which boats are being procured at a rate of
two per year, accelerating by one year the deliveries of all boats procured on or after a certain date will produce a one-
time benefit of a single year in which four boats will be delivered to the Navy, rather than two. In the case of the
Virginia-class program, this year might be around 2017. As mentioned earlier in the discussion of the Virginia-class
cost-reduction goal, the Navy believes that the goal of reducing Virginia-class shipyard construction time is a medium-
risk goal. If it turns out that shipyard construction time is reduced to 66 months rather than 60 months (i.e., is reduced
by 6 months rather than 12 months), the size of the SSN force would increase by one boat rather than two, and the force
would bottom out at 41 boats rather than 42.
19 The Navy study identified 19 existing SSNs whose service lives currently appear to be extendable by periods of 1 to
24 months. The previous option of reducing Virginia-class shipyard construction time to 60 months, the Navy
concluded, would make moot the option of extending the service lives of the three oldest boats in this group of 19,
leaving 16 whose service lives would be considered for extension.
20 The Navy stated that the rough, order-of-magnitude (ROM) cost of extending the lives of 19 SSNs would be $595
million in constant FY2005 dollars, and that the cost of extending the lives of 16 SSNs would be roughly proportional.
Congressional Research Service
10

Navy Attack Submarine Procurement: Background and Issues for Congress

three additional SSNs would reduce it to about 7, and procuring four additional
SSNs would reduce it to 2.
The Navy added a number of caveats to these results, including but not limited to the following:
• The requirement for 10.0 SSNs deployed on a day-to-day basis is a current
requirement that could change in the future.
• The peak projected wartime demand of about 35 SSNs deployed within a certain
amount of time is an internal Navy figure that reflects recent analyses of potential
future wartime requirements for SSNs. Subsequent analyses of this issue could
result in a different figure.
• The identification of 19 SSNs as candidates for service life extension reflects
current evaluations of the material condition of these boats and projected use
rates for their nuclear fuel cores. If the material condition of these boats years
from now turns out to be worse than the Navy currently projects, some of them
might no longer be suitable for service life extension. In addition, if world
conditions over the next several years require these submarines to use up their
nuclear fuel cores more quickly than the Navy now projects, then the amounts of
time that their service lives might be extended could be reduced partially, to zero,
or to less than zero (i.e., the service lives of the boats, rather than being extended,
might need to be shortened).
• The analysis does not take into account potential rare events, such as accidents,
that might force the removal an SSN from service before the end of its expected
service live.21
• Seven-month deployments might affect retention rates for submarine personnel.
Issues for Congress
48-Boat Force-Level Goal and Planned SSN Procurement
Some observers have argued that the Navy in coming years should seek to maintain a force of
more than 48 SSNs, particularly in light of Chinese naval modernization22 and the possibility of a
rejuvenated Russian submarine force. Other observers argue that given the kinds of irregular
warfare operations in which the United States appears likely to participate in coming years, the
United States can afford to reduce the SSN force-level goal to something less than 48 boats. The
issue of the SSN force-level goal could be a topic of discussion in the Quadrennial Defense
Review (QDR), which is currently in progress.

21 In January 2005, the Los Angeles-class SSN San Francisco (SSN-711) was significantly damaged in a collision with
an undersea mountain near Guam. The ship was repaired in part by transplanting onto it the bow section of the
deactivated sister ship Honolulu (SSN-718). (See, for example, Associated Press, “Damaged Submarine To Get Nose
Transplant,” Seattle Post-Intelligencer, June 26, 2006.) Prior to the decision to repair the San Francisco, the Navy
considered the option of removing it from service. (See, for example, William H. McMichael, “Sub May Not Be Worth
Saving, Analyst Says,” Navy Times, February 28, 2005; Gene Park, “Sub Repair Bill: $11M,” Pacific Sunday News
(Guam)
, May 8, 2005.)
22 For further discussion, see CRS Report RL33153, China Naval Modernization: Implications for U.S. Navy
Capabilities—Background and Issues for Congress
, by Ronald O'Rourke.
Congressional Research Service
11

Navy Attack Submarine Procurement: Background and Issues for Congress

A February press report suggests that the Navy may seek to reduce the cost of the FY2010
version of its 30-year shipbuilding plan by reducing planned procurements of certain higher-cost
ships. According to the report, proposals being considered by the Navy included reducing planned
procurement of attack submarines (SSNs) over 30 years from 53 boats to 40 boats, a reduction of
about 25%.23 This proposal, if implemented, could result in an SSN force that eventually declines
to the low- to mid-40s and stays there indefinitely. This profile raises a question as to whether
consideration is being given to reducing the attack submarine force-level goal from the current
figure of 48 to a figure in the low- to mid-40s.
For additional discussion of the 48-boat goal, see Appendix B.
Virginia-Class Technology Insertion
Regarding Navy plans for inserting new technology into the Virginia-class design, a March 2009
Government Accountability Office (GAO) report stated:
There are three new technologies that the Navy plans to incorporate on current and future
Virginia Class submarines once they mature. Advanced electromagnetic signature reduction
is a software package comprised of two systems that use improved algorithms to
continuously monitor and recalibrate the submarine’s signature. The basic algorithms
required to support this technology have been proven on other submarines, and Navy
officials stated they are now developing software and conducting laboratory tests in support
of algorithm development. Navy officials stated they expect the technology to be installed
during new construction starting with SSN 781 and back-fit during modernization for earlier
ships.
The flexible payload sail (formerly the advanced sail)—a redesign of the structure that sits
atop the main body of the submarine—will allow the sail to house additional systems and
payloads. According to Navy officials, the flexible payload sail design replaced the advanced
sail due to concerns about weight, hydrodynamic performance, and access to the weapons
trunk. The design of the flexible payload is under review for inclusion on later submarines.
The conformal acoustic velocity sensor wide aperture array is intended to be a more cost-
effective sensor array that replaces transducers with accelerometers, while providing the
same capability. According to the Navy, the new array is expected to save $11 milliion to
$12 million per submarine, and consists of panels that will be integrated with one of two
types of sensors designed to detect vibrations and acoustic signatures of targets—ceramic
accelerometers, a mature but more costly technology, or fiber-optic accelerometers, a less
expensive but immature technology. According to program officials, testing of panels
incorporating both types of sensors was completed in December 2008, and a decision on
which accelerometer will be selected is expected by the end of fiscal year 2009, and at-sea
testing is expected in 2010.24

23 Christopher P. Cavas, “U.S. May Cut 52 Ships From Plan,” Defense News, February 16, 2009, p. 1.
24 Government Accountability Office, Defense Acquisitions[:] Assessments of Selected Weapon Programs, GAO-09-
326SP, March 2009, p. 146.
Congressional Research Service
12

Navy Attack Submarine Procurement: Background and Issues for Congress

Potential Options for Congress
Potential options for Congress in FY2010 include approving or modifying the Navy’s FY2010
funding request for the Virginia-class program and directing the Navy to provide an update on
options for mitigating the projected attack submarine shortfall.
Legislative Activity For FY2010
FY2010 Funding Request
The Navy’s proposed FY2010 budget requests $1,964.3 million in procurement funding to
complete the procurement cost of a 12th Virginia-class boat. The FY2010 budget estimates the
procurement cost of this boat at $2,756.7 million, and the ship has received a total of $792.4
million in prior-year funding. The Navy’s proposed FY2010 budget also requests $1,346.4
million in advance procurement (AP) funding for Virginia-class boats to be procured in future
years, and $613.3 million in additional AP funding for Economic Order Quantity (EOQ)
purchases of long-leadtime items for Virginia-class boats to be procured under the FY2009-
FY2013 MYP arrangement.
FY2010 Defense Authorization Bill (H.R. 2647/S. 1390)
House
The House Armed Services Committee, in its report (H.Rept. 111-166 of June 18, 2009) on H.R.
2647, recommends approving the Administration’s FY2010 request for procurement and advance
procurement funding for the Virginia-class submarine program. (Page 70). The report states: “The
committee believes that two Virginia class submarines is the minimum that should be funded
annually.” (Page 72).
The report also states:
The budget request contained $1.7 million in PE 63513N [of the Navy’s research and
development account] for shipboard system component development but contained no
funding for development of the advanced steam turbine.
The committee supports developing multiple technologies for improved competition in the
procurement of major equipment for ships and submarines. Developing improved magnetic
bearing assemblies would provide a secondary turbine source for improved competition in
Virginia class submarines construction.
The committee recommends an increase of $7.5 million in PE 63513N for qualification of
magnetic bearing assemblies in advanced steam turbines. (Page 175)
The report also states:
Congressional Research Service
13

Navy Attack Submarine Procurement: Background and Issues for Congress

The budget request contained $154.8 million in PE 64558N for new design SSN [work] but
contained no funding for development of a common command and control system module
(CCCS) for advanced submarine construction.
The committee understands that development of a common command and control system
module for use on Virginia class submarines (Blk IV/V), SSGN’s, and the Ohio class
submarine replacement program will allow for rapid integration of new technologies due to
the highly reconfigurable CCCS.
The committee recommends an increase of $9.0 million in PE 64558N for development of
common command and control system module. (Page 176)
The report also states:
The committee believes that it is in the national interest to maintain the submarine design
industrial capacity to begin development efforts for a new class of submarines which could
either continue the mission of the current Ohio-class strategic submarines (SSBN) or serve as
the next generation of tactical guided missile submarines (SSGN). The committee is also
aware that the United States has agreements with the United Kingdom to jointly design and
develop a common missile compartment (CMC) module which would be used by both
countries for construction of next generation submarines.
The committee supports both the development of the CMC and the cooperative manner in
which research and design costs are being shared by the United States and the United
Kingdom. However, the committee is aware of the combatant commanders’ desire for
increased presence of the recently converted SSBN to SSGN submarines due to the
significant tactical strike and special operations capability those platforms can deliver.
Therefore, the committee strongly encourages the design of the CMC module account for a
non-strategic use with minimal back-fitting. (Pages 75-76)
Senate
Division D (Section 4001) of S. 1390 as reported by the Senate Armed Services Committee
(S.Rept. 111-35 of July 2, 2009) presents the detailed line-item funding tables that in previous
years have been included in the Senate Armed Services Committee’s report on the defense
authorization bill. Section 4001 recommends approving the Administration’s FY2010 request for
procurement and advance procurement funding for the Virginia-class submarine program. (Page
619 of the printed bill).
The committee’s report states:
The budget request included $154.8 million in PE 64558N [of the Navy’s research and
development account] to support design and development activities for submarines, but
included no funding for developing a common command and control module for application
to Virginia-class submarines or a potential Trident replacement program.
The committee understands that the Navy could design a new command and control module
for submarines that would enable rapid reconfiguration of mission equipment in these
spaces, reduce the demands on watch standers, and reduce the total ownership costs to the
Navy for supporting disparate command and control configurations. Starting such a design
now would permit the Navy to take best advantage of potential savings from achieving a
common configuration in the fleet.
Congressional Research Service
14

Navy Attack Submarine Procurement: Background and Issues for Congress

Therefore, the committee recommends an increase of $9.0 million in PE 64558N to support
these development activities. (Pages 68-69)
The report also states:
The committee recommends $1.0 billion for naval reactors, the amount of the budget request.
The committee notes that the Office of Naval Reactors has begun design work to support a
new strategic ballistic missile submarine, in advance of the Nuclear Posture Review (NPR).
While this work is premature from a policy perspective, the committee understands that the
work must start this year to support the replacement schedule for the current SSBN fleet
should the NPR determine that a follow-on ballistic missile submarine is needed. (Page 251)
Conference
The conference report (H.Rept. 111-288 of October 7, 2009) on H.R. 2647 approves the
Administration’s FY2010 request for procurement and advance procurement funding for the
Virginia-class submarine program. (Page 939)
FY2010 DOD Appropriations Bill (H.R. 3326)
House
The House Appropriations Committee, in its report (H.Rept. 111-230 of July 24, 2009) on H.R.
3326, recommends approving the Administration’s FY2010 request for procurement and advance
procurement funding for the Virginia-class submarine program. (Page 163).
Senate
The Senate Appropriations Committee, in its report (S.Rept. 111-74 of September 10, 2009) on
H.R. 3326, recommends approving the Administration’s FY2010 request for procurement and
advance procurement funding for the Virginia-class submarine program. (Page 112).
Congressional Research Service
15

Navy Attack Submarine Procurement: Background and Issues for Congress

Appendix A. Past SSN Force-Level Goals
This appendix summarizes attack submarine force-level goals since the Reagan Administration
(1981-1989).
The Reagan-era plan for a 600-ship Navy included an objective of achieving and maintaining a
force of 100 SSNs.
The George H. W. Bush Administration’s proposed Base Force plan of 1991-1992 originally
called for a Navy of more than 400 ships, including 80 SSNs.25 In 1992, however, the SSN goal
was reduced to about 55 boats as a result of a 1992 Joint Staff force-level requirement study
(updated in 1993) that called for a force of 51 to 67 SSNs, including 10 to 12 with Seawolf-level
acoustic quieting, by the year 2012.26
The Clinton Administration, as part of its 1993 Bottom-Up Review (BUR) of U.S. defense policy,
established a goal of maintaining a Navy of about 346 ships, including 45 to 55 SSNs.27 The
Clinton Administration’s 1997 QDR supported a requirement for a Navy of about 305 ships and
established a tentative SSN force-level goal of 50 boats, “contingent on a reevaluation of
peacetime operational requirements.”28 The Clinton Administration later amended the SSN figure
to 55 boats (and therefore a total of about 310 ships).
The reevaluation called for in the 1997 QDR was carried out as part of a Joint Chiefs of Staff
(JCS) study on future requirements for SSNs that was completed in December 1999. The study
had three main conclusions:
• “that a force structure below 55 SSNs in the 2015 [time frame] and 62 [SSNs] in
the 2025 time frame would leave the CINC’s [the regional military commanders-
in-chief] with insufficient capability to respond to urgent crucial demands
without gapping other requirements of higher national interest. Additionally, this
force structure [55 SSNs in 2015 and 62 in 2025] would be sufficient to meet the
modeled war fighting requirements;”
• “that to counter the technologically pacing threat would require 18 Virginia class
SSNs in the 2015 time frame;” and

25 For the 80-SSN figure, see Statement of Vice Admiral Roger F. Bacon, U.S. Navy, Assistant Chief of Naval
Operations (Undersea Warfare) in U.S. Congress, House Armed Services Committee, Subcommittee on Seapower and
Strategic and Critical Materials, Submarine Programs, March 20, 1991, pp. 10-11, or Statement of Rear Admiral
Raymond G. Jones, Jr., U.S. Navy, Deputy Assistant Chief of Naval Operations (Undersea Warfare), in U.S. Congress,
Senate Armed Services Committee, Subcommittee on Projection Forces and Regional Defense, Submarine Programs,
June 7, 1991, pp. 10-11.
26 See Richard W. Mies, “Remarks to the NSL Annual Symposium,” Submarine Review, July 1997, p. 35; “Navy Sub
Community Pushes for More Subs than Bottom-Up Review Allowed,” Inside the Navy, November 7, 1994, pp. 1, 8-9;
Attack Submarines in the Post-Cold War Era: The Issues Facing Policymakers, op. cit., p. 14; Robert Holzer, “Pentagon
Urges Navy to Reduce Attack Sub Fleet to 50,” Defense News, March 15-21, 1993, p. 10; Barbara Nagy, “ Size of Sub
Force Next Policy Battle,” New London Day, July 20, 1992, pp. A1, A8.
27 Secretary of Defense Les Aspin, U.S. Department of Defense, Report on the Bottom-Up Review, October 1993, pp.
55-57.
28 Secretary of Defense William S. Cohen, U.S. Department of Defense, Report of the Quadrennial Defense Review,
May 1997, pp. 29, 30, 47.
Congressional Research Service
16

Navy Attack Submarine Procurement: Background and Issues for Congress

• “that 68 SSNs in the 2015 [time frame] and 76 [SSNs] in the 2025 time frame
would meet all of the CINCs’ and national intelligence community’s highest
operational and collection requirements.”29
The conclusions of the 1999 JCS study were mentioned in discussions of required SSN force
levels, but the figures of 68 and 76 submarines were not translated into official Department of
Defense (DOD) force-level goals.
The George W. Bush Administration’s report on the 2001 QDR revalidated the amended
requirement from the 1997 QDR for a fleet of about 310 ships, including 55 SSNs. In revalidating
this and other U.S. military force-structure goals, the report cautioned that as DOD’s
“transformation effort matures—and as it produces significantly higher output of military value
from each element of the force—DOD will explore additional opportunities to restructure and
reorganize the Armed Forces.”30
DOD and the Navy conducted studies on undersea warfare requirements in 2003-2004. One of
the Navy studies—an internal Navy study done in 2004—reportedly recommended reducing the
attack submarine force level requirement to as few as 37 boats. The study reportedly
recommended homeporting a total of nine attack submarines at Guam and using satellites and
unmanned underwater vehicles (UUVs) to perform ISR missions now performed by attack
submarines.31
In March 2005, the Navy submitted to Congress a report projecting Navy force levels out to
FY2035. The report presented two alternatives for FY2035—a 260-ship fleet including 37 SSNs
and 4 SSGNs, and a 325-ship fleet including 41 SSNs and 4 SSGNs.32
In May 2005, it was reported that a newly completed DOD study on attack submarine
requirements called for maintaining a force of 45 to 50 boats.33
In February 2006, the Navy proposed to maintain in coming years a fleet of 313 ships, including
48 SSNs.

29 Department of Navy point paper dated February 7, 2000. Reprinted in Inside the Navy, February 14, 2000, p. 5.
30 U.S. Department of Defense, Quadrennial Defense Review, September 2001, p. 23.
31 Bryan Bender, “Navy Eyes Cutting Submarine Force,” Boston Globe, May 12, 2004, p. 1; Lolita C. Baldor, “Study
Recommends Cutting Submarine Fleet,” NavyTimes.com, May 13, 2004.
32 U.S. Department of the Navy, An Interim Report to Congress on Annual Long-Range Plan for the Construction of
Naval Vessels for FY 2006
. The report was delivered to the House and Senate Armed Services and Appropriations
Committees on March 23, 2005.
33 Robert A. Hamilton, “Delegation Calls Report on Sub Needs Encouraging,” The Day (New London, CT), May 27,
2005; Jesse Hamilton, “Delegation to Get Details on Sub Report,” Hartford (CT) Courant, May 26, 2005.
Congressional Research Service
17

Navy Attack Submarine Procurement: Background and Issues for Congress

Appendix B. Views Regarding 48-Boat SSN
Force-Level Goal

This appendix summarizes the Navy’s view and an alternative view regarding the appropriateness
of the Navy’s 48-boat SSN force-level goal.
Navy View34
In support of its position that 48 is the correct number of SSNs to meet future needs, the Navy in
2006 argued the following:
• The figure of 48 SSNs was derived from a number of force-level studies that
converged on a figure of about 48 boats, making this figure an analytical “sweet
spot.”
• A force of 48 boats is a moderate-risk (i.e., acceptable-risk) force, as opposed to
the low-risk force called for in the 1999 JCS study.
• A force of 48 boats will be sufficient in coming years to maintain about 10
forward-deployed SSNs on a day-to-day basis—the same number of forward-
deployed boats that the Navy has previously maintained with a force of more
than 50 SSNs. The Navy will be able to maintain 10 forward-deployed SSNs in
coming years with only 48 boats because the force in coming years will include
an increased number of newer SSNs that require less maintenance over their lives
and consequently are available for operation a greater percentage of the time.
• U.S. regional military commanders would prefer a day-to-day forward-deployed
total of about 18 SSNs, but total of 10 will be sufficient to meet their most
important needs.
• All 10 of the forward-deployed SSNs are needed for day-to-day missions such as
intelligence, surveillance and reconnaissance (ISR), while about 7.5 of these
submarines are also needed to ensure that an adequate number of SSNs are in
position for the opening phases of potential conflicts in various locations.
On the issue of meeting U.S. regional military commanders’ requirements for day-to-day
forward-deployed SSNs, the Navy states:
Each Combatant Commander (COCOM) requests assets to execute required missions
utilizing the Global Force Management Process. Broad categories of mission types are used
to make requests including National and Fleet ISR, Exercise and Training (supporting US
tactical development), Exercise and Operations (supporting US engagement strategy),
Carrier Strike Group (CSG) /Expeditionary Strike Group (ESG) tasking, OPLAN (war plans)
support, and Other. As assignment of Critical, High Priority, Priority or Routine is assigned
to each of the requested missions. The theater allocation request process prior to 2004 did not
include a priority breakdown. In general, ISR missions have been assigned as Critical or

34 This section is based on Navy testimony to the Projection Forces subcommittee of the House Armed Services
Committee on March 28, 2006, and to the Seapower subcommittee of the Senate Armed Services Committee on March
29, and April 6, 2006.
Congressional Research Service
18

Navy Attack Submarine Procurement: Background and Issues for Congress

High Priority requirements. Other mission areas have been assigned from High Priority to
Routine, based on the relative importance to the theater commander. No allocation is
currently requested to support OPLAN or Other mission areas.
Each COCOM has authority to use its allocated SSNs as required to meet current national
and theater priorities. The CJCS [Chairman Joint Chiefs of Staff] allocation order to the
Submarine Force strictly directs an allotted number of SSN days of presence be provided,
capable of meeting each theaters’ [sic] taskings. The breakdown of mission priorities into
Critical, High Priority, Priority and Routine is predominantly a construct to demonstrate how
a COCOM could meet their priorities, given a specific level of SSN presence. It serves as an
aid to the CJCS in apportioning limited SSN presence to the various theaters.
The number of SSNs allocated against Critical Missions enabled COCOMs to meet all
requirements in 2004 and 2005, and 99% of the requirements in 2006. For High Priority
missions, sufficient SSNs were allocated to meet 25%, 50% and 34% of requirements in
2004, 2005, and 2006 respectively. Overall, the number of SSNs forward deployed was
sufficient to cover 66%, 61% and 54% of Combatant Commanders’ requested SSN mission
taskings in 2004, 2005, and 2006 respectively.35
Alternative View
Some observers believe that more than 48 SSNs will be needed to meet future needs. One such
observer—retired Vice Admiral Albert Konetzni, Jr., a former commander of the U.S. Pacific
Fleet submarine force—argued the following in 2006:36
• The Navy’s SSN force-level analyses called for a force of 48 to 60 SSNs. In this
context, a force of 48 SSNs looks more like a sour spot than a sweet spot.
• The Navy’s SSN force-level analyses reflect “reverse engineering,” in which an
SSN force-level number is selected at the outset for affordability reasons, and
assumptions used in the force-level study are then adjusted to produce that figure.
• The 1999 JCS study on SSN requirements remains valid today.
• All of the U.S. regional military commanders’ requirements for day-to-day
forward-deployed SSNs, and not just the 60% or so of those requirements that are
being met, are critical.
• In light of the potential size of China’s submarine force in 2020, a force of 48
SSNs in that year will be insufficient.37

35 Source: Written response by Vice Admiral Charles L. Munns, Commander Naval Submarine Forces, to a question
posed by Representative Rob Simmons at a March 28, 2006, hearing before the Projection Forces Subcommittee of the
House Armed Services Committee on submarine force structure. Munns’ written response was provided to CRS on
July 5, 2006, by the office of Representative Simmons and is used here with the permission of that office.
36 These points are based on Konetzni’s testimony to the Projection Forces subcommittee of the House Armed Services
Committee on March 28, 2006.
37 For more on China’s submarine force, and China’s naval modernization effort in general, see CRS Report RL33153,
China Naval Modernization: Implications for U.S. Navy Capabilities—Background and Issues for Congress, by Ronald
O’Rourke.
Congressional Research Service
19

Navy Attack Submarine Procurement: Background and Issues for Congress

Appendix C. Options for Funding SSNs
This appendix presents information on some alternatives for funding SSNs that was originally
incorporated into this report during discussions in earlier years on potential options for Virginia-
class procurement.
Alternative Funding Methods
Alternative methods of funding the procurement of SSNs include but are not necessarily limited
to the following:
two years of advance procurement funding followed by full funding—the
traditional approach, under which there are two years of advance procurement
funding for the SSN’s long-leadtime components, followed by the remainder of
the boat’s procurement funding in the year of procurement;
one year of advance procurement funding followed by full funding—one year
of advance procurement funding for the SSN’s long-leadtime components,
followed by the remainder of the boat’s procurement funding in the year of
procurement;
full funding with no advance procurement funding (single-year full
funding)—full funding of the SSN in the year of procurement, with no advance
procurement funding in prior years;
incremental funding—partial funding of the SSN in the year of procurement,
followed by one or more years of additional funding increments needed to
complete the procurement cost of the ship; and
advance appropriations—a form of full funding that can be viewed as a
legislatively locked in form of incremental funding.38
Navy testimony to Congress in early 2007, when Congress was considering the FY2008 budget,
suggested that two years of advance procurement funding are required to fund the procurement of
an SSN, and consequently that additional SSNs could not be procured until FY2010 at the
earliest.39 This testimony understated Congress’s options regarding the procurement of additional
SSNs in the near term. Although SSNs are normally procured with two years of advance
procurement funding (which is used primarily for financing long-leadtime nuclear propulsion
components), Congress can procure an SSN without prior-year advance procurement funding, or

38 For additional discussion of these funding approaches, see CRS Report RL32776, Navy Ship Procurement:
Alternative Funding Approaches—Background and Options for Congress
, by Ronald O’Rourke.
39 For example, at a March 1, 2007, hearing before the House Armed Services Committee on the FY2008 Department
of the Navy budget request, Representative Taylor asked which additional ships the Navy might want to procure in
FY2008, should additional funding be made available for that purpose. In response, Secretary of the Navy Donald
Winter stated in part: “The Virginia-class submarines require us to start with a two-year advanced procurement, to be
able to provide for the nuclear power plant that supports them. So we would need to start two years in advance. What
that says is, if we were able to start in ‘08 with advanced procurement, we could accelerate, potentially, the two a year
to 2010.” (Source: Transcript of hearing.) Navy officials made similar statements before the same subcommittee on
March 8, 2007, and before the Senate Armed Services Committee on March 29, 2007.
Congressional Research Service
20

Navy Attack Submarine Procurement: Background and Issues for Congress

with only one year of advance procurement funding. Consequently, Congress currently has the
option of procuring an additional SSN in FY2009 and/or FY2010.
Single-year full funding has been used in the past by Congress to procure nuclear-powered ships
for which no prior-year advance procurement funding had been provided. Specifically, Congress
used single-year full funding in FY1980 to procure the nuclear-powered aircraft carrier CVN-71,
and again in FY1988 to procure the CVNs 74 and 75. In the case of the FY1988 procurement,
under the Administration’s proposed FY1988 budget, CVNs 74 and 75 were to be procured in
FY1990 and FY1993, respectively, and the FY1988 budget was to make the initial advance
procurement payment for CVN-74. Congress, in acting on the FY1988 budget, decided to
accelerate the procurement of both ships to FY1988, and fully funded the two ships that year at a
combined cost of $6.325 billion. The ships entered service in 1995 and 1998, respectively.40
The existence in both FY1980 and FY1988 of a spare set of Nimitz-class reactor components was
not what made it possible for Congress to fund CVNs 71, 74, and 75 with single-year full
funding; it simply permitted the ships to be built more quickly. What made it possible for
Congress to fund the carriers with single-year full funding was Congress’s constitutional authority
to appropriate funding for that purpose.
Procuring an SSN with one year of advance procurement funding or no advance procurement
funding would not materially change the way the SSN would be built—the process would still
encompass about two years of advance work on long-leadtime components, and an additional six
years or so of construction work on the ship itself. The outlay rate for the SSN could be slower, as
outlays for construction of the ship itself would begin one or two years later than normal.
Congress in the past has procured certain ships in the knowledge that those ships would not begin
construction for some time and consequently would take longer to enter service than a ship of that
kind would normally require. When Congress procured two nuclear-powered aircraft carriers
(CVNs 72 and 73) in FY1983, and another two (CVNs 74 and 75) in FY1988, it did so in both
cases in the knowledge that the second ship in each case would not begin construction until some
time after the first.
Procuring SSNs in a 2-1-2 Pattern
Some potential approaches for procuring additional boats in FY2009-FY2011 could result in a
pattern of procuring two boats in a given year, followed by one boat the following year, and two
boats the year after that—a 2-1-2 pattern. Navy testimony to Congress in early 2007 and early
2008 suggested that if the procurement rate were increased in a given year to two boats, it would
not be best, from an industrial-base point of view, to decrease the rate to a single boat the
following year, and then increase it again to two boats the next year, because of the workforce
fluctuations such a profile would produce.41

40 In both FY1988 and FY1980, the Navy had a spare set of Nimitz (CVN-68) class nuclear propulsion components in
inventory. The existence of a spare set of components permitted the carriers to be built more quickly than would have
otherwise been the case, but it is not what made the single-year full funding of these carriers possible. What made it
possible was Congress’ authority to appropriate funds for the purpose.
41 See, for example, the spoken remarks of Secretary of the Navy Donald Winter at hearings before the House Armed
Services Committee on March 1, 2007, and March 6, 2008, and spoken remarks by other Navy officials at a March 29,
2007, hearing before the Senate Armed Services Committee and at a March 14, 2008, hearing before the Seapower and
(continued...)
Congressional Research Service
21

Navy Attack Submarine Procurement: Background and Issues for Congress

This statement may overstate the production-efficiency disadvantages of a 2-1-2 pattern. If two
boats were procured in a given year, followed by one boat the next year—a total of three boats in
24 months—the schedule for producing the three boats could be phased so that, for a given stage
in the production process, the production rate would be one boat every eight months. A
production rate of one boat every 8 months might actually help the industrial base make the
transition from the current schedule of one boat every 12 months (one boat per year) to one boat
every 6 months (two boats per year). Viewed this way, a 2-1-2 pattern might actually lead to some
benefits in production efficiency on the way to a steady rate of two boats per year. The Navy’s
own 30-year (FY2009-FY2038) SSN procurement plan calls for procuring SSNs in a 1-2-1-2
pattern in FY2029-FY2038.

(...continued)
Expeditionary Forces subcommittee of the House Armed Services Committee.
Congressional Research Service
22

Navy Attack Submarine Procurement: Background and Issues for Congress

Appendix D. Maintaining Submarine Design and
Engineering Base

Navy and industry officials earlier in this decade appeared to agree that preserving the submarine
design and engineering base over the next several years would require funding substantial
submarine design and engineering work in the near term. The Navy plans to address the issue by
accelerating into the near term the start of design work on the next-generation SSBN. Given the
ages of the Navy’s 14 current SSBNs, work on a replacement SSBN design would normally not
need to start for another few years. The Navy, however, is accelerating the start of this project into
FY2010, with an eye toward carrying out the project as a steady-state effort over several years,
rather than as a more-concentrated effort starting several years from now. The Navy’s plan will
provide a significant amount of submarine design and engineering work for several years, and
engage a wide range of submarine design and engineering skills.
The Navy asked RAND to study the question of sustaining the submarine design and engineering
base. The RAND study, which was published in 2007, states that, based on RAND’s analysis,
we reach the following recommendations:
—Seriously consider starting the design of the next submarine class by 2009, to run 20 years,
taking into account the substantial advantages and disadvantages involved.
If the 20-year-design alternative survives further evaluation, the issue of a gap in submarine
design is resolved, and no further actions need be taken. If that alternative is judged too
risky, we recommend the following:
—Thoroughly and critically evaluate the degree to which options such as the spiral
development of the Virginia class or design without construction will be able to substitute for
new-submarine design in allowing design professionals to retain their skills.
If options to sustain design personnel in excess of demand are judged on balance to offer
clear advantages over letting the workforce erode, then the Navy should take the following
actions:
—Request sufficient funding to sustain excess design workforces at the shipyards large
enough to permit substantial savings in time and money later.
—Taking into account trends affecting the evolution of critical skills, continue efforts to
determine which shipyard skills need action to preserve them within the sustained design
core.
—Conduct a comprehensive analysis of vendors to the shipyards to determine which require
intervention to preserve critical skills.
—Invest $30 million to $35 million annually in the NSWC’s Carderock Division submarine
design workforce in excess of reimbursable demand to sustain skills that might otherwise be
lost.42

42 John F. Schank, et al, Sustaining U.S. Submarine Design Capabilities, RAND, Santa Monica (CA), 2007. pp. xxvii-
xxviii. (Prepublication copy posted on the Internet by RAND, accessed on May 9, 2007, at http://www.rand.org/pubs/
(continued...)
Congressional Research Service
23

Navy Attack Submarine Procurement: Background and Issues for Congress


Author Contact Information

Ronald O'Rourke

Specialist in Naval Affairs
rorourke@crs.loc.gov, 7-7610





(...continued)
monographs/2007/RAND_MG608.pdf.)