Navy Littoral Combat Ship (LCS) Program

Summary
The Navy is procuring a new type of surface combatant called the Littoral Combat Ship (LCS).
The LCS is a small, fast, relatively inexpensive combat ship that is to be equipped with modular
“plug-and-fight” mission packages. The basic version of the LCS, without any mission packages,
is referred to as the LCS sea frame. The Navy wants to procure a total of 55 LCSs.
The Navy substantially restructured the LCS program in 2007 in response to significant cost
growth and construction delays in the program. The first ship in the program—LCS-1—was
commissioned into service on November 8, 2008. A second—LCS-2—is to be delivered to the
Navy later this year. Two more LCSs were funded in FY2009 at a cost of $1,020 million and are
now under construction.
The Navy’s proposed FY2010 budget requests $1,380 million for the procurement of three more
LCSs. This figure equates to $460 million per ship—the unit procurement cost cap for the LCS
program, which applies to LCSs procured in FY2010 and subsequent years.
The Navy’s proposed FY2010 budget also requests $360.5 million in research and development
funding for the LCS program. The $360.5 million includes $75.5 million to cover cost growth on
the construction of LCSs 1 and 2, which were procured through the Navy’s research and
development account.
The issue for Congress is whether to approve, reject, or modify the Navy’s plans for the LCS
program. The LCS program raises potential oversight issues for Congress relating to cost growth,
total program acquisition cost, the procurement cost cap, technical risk, operational evaluation
and competition for production, a proposed common combat system, and coordination of sea
frames and mission packages. This report will be updated as events warrant.

Congressional Research Service

Navy Littoral Combat Ship (LCS) Program

Contents
Introduction ................................................................................................................................ 1
Background ................................................................................................................................ 1
The LCS ............................................................................................................................... 1
Two Industry Teams, Each With Its Own Design ................................................................... 2
Planned Procurement ............................................................................................................ 2
Program Funding .................................................................................................................. 3
Unit Procurement Cost Cap................................................................................................... 3
Total Acquisition Cost ........................................................................................................... 4
2007 Program Restructuring.................................................................................................. 4
March 2007 Navy Restructuring Plan.............................................................................. 4
April 2007 Termination of LCS-3.................................................................................... 5
November 2007 Termination of LCS-4............................................................................ 5
Summary of Status of LCSs Funded in FY2005-FY2009....................................................... 5
Acquisition Strategy for FY2009 and Subsequent Ships ........................................................ 6
FY2009 and FY2010 Ships ............................................................................................. 6
FY2011 and Subsequent Ships ........................................................................................ 8
Cost Growth on LCS Sea Frames .......................................................................................... 9
Summary of Cost Growth................................................................................................ 9
Review of Cost Growth Over Time ................................................................................. 9
June 2008 CBO Report ................................................................................................. 11
Reasons for Cost Growth .............................................................................................. 12
Summary of Congressional Action in FY2005-FY2009 ....................................................... 18
FY2005......................................................................................................................... 18
FY2006......................................................................................................................... 19
FY2007......................................................................................................................... 19
FY2008......................................................................................................................... 19
FY2009......................................................................................................................... 19
Potential Oversight Issues for Congress..................................................................................... 20
Building LCSs Within Unit Procurement Cost Cap.............................................................. 20
Cost Growth on LCS Sea Frames ........................................................................................ 21
Total Program Acquisition Cost........................................................................................... 22
Acquisition Strategy for LCSs Procured in FY2011 and Beyond.......................................... 22
Technical Risk .................................................................................................................... 23
Seaframe....................................................................................................................... 23
Mission Packages.......................................................................................................... 24
Options for Congress ................................................................................................................ 25
General Options .................................................................................................................. 26
Potential for Common Hulls................................................................................................ 26
In General ..................................................................................................................... 26
Reported Proposal to Build Variant of NSC for Navy .................................................... 26
Legislative Activity for FY2010 ................................................................................................ 30

Congressional Research Service

Navy Littoral Combat Ship (LCS) Program

Tables
Table 1. LCS Program Acquisition Funding, FY2007-FY2013 .................................................... 3
Table 2. Status of LCSs Funded in FY2005-FY2009 ................................................................... 6
Table A-1. Congressional Action on FY2009 Funding Request .................................................. 31

Appendixes
Appendix A. Legislative Activity for FY2009............................................................................ 31
Appendix B. March 2009 Navy Testimony on LCS Program ..................................................... 38

Contacts
Author Contact Information ...................................................................................................... 47

Congressional Research Service

Navy Littoral Combat Ship (LCS) Program

Introduction
The Navy is procuring a new type of surface combatant called the Littoral Combat Ship (LCS).
The LCS is a small, fast, relatively inexpensive combat ship that is to be equipped with modular
“plug-and-fight” mission packages. The basic version of the LCS, without any mission packages,
is referred to as the LCS sea frame. The Navy wants to procure a total of 55 LCSs. The Navy’s
planned force of 55 LCSs accounts for about 18% of its planned fleet of 313 ships of all types.1
The Navy substantially restructured the LCS program in 2007 in response to significant cost
growth and construction delays in the program. The first ship in the program—LCS-1—was
commissioned into service on November 8, 2008. A second—LCS-2—is to be delivered to the
Navy later this year. Two more LCSs were funded in FY2009 at a cost of $1,020 million and are
now under construction.
The Navy’s proposed FY2010 budget requests $1,380 million for the procurement of three more
LCSs. This figure equates to $460 million per ship—the unit procurement cost cap for the LCS
program, which applies to LCSs procured in FY2010 and subsequent years.
The Navy’s proposed FY2010 budget also requests $360.5 million in research and development
funding for the LCS program. The $360.5 million includes $75.5 million to cover cost growth on
the construction of LCSs 1 and 2, which were procured through the Navy’s research and
development account.
The issue for Congress is whether to approve, reject, or modify the Navy’s plans for the LCS
program. Decisions that Congress makes on this issue could affect future Navy capabilities and
funding requirements, and the shipbuilding industrial base.
Background
The LCS
The LCS program was announced on November 1, 2001.2 The LCS is a small, fast, relatively
inexpensive surface combatant that is to be equipped with modular “plug-and-fight” mission
packages, including unmanned vehicles (UVs). Rather than being a multimission ship like the
Navy’s larger surface combatants, the LCS is to be a focused-mission ship equipped to perform
one primary mission at any one time. The ship’s mission orientation is to be changed by changing

1 For more on the Navy’s planned 313-ship fleet, see CRS Report RL32665, Navy Force Structure and Shipbuilding
Plans: Background and Issues for Congress
, by Ronald O’Rourke.
2 On November 1, 2001, the Navy announced that it was launching a Future Surface Combatant Program aimed at
acquiring a family of next-generation surface combatants. This new family of surface combatants, the Navy stated,
would include three new classes of ships: a destroyer called the DD(X)—later redesignated the DDG-1000—for the
precision long-range strike and naval gunfire mission; a cruiser called the CG(X) for the air defense and ballistic
missile mission, and a smaller combatant called the Littoral Combat Ship (LCS) to counter submarines, small surface
attack craft, and mines in heavily contested littoral (near-shore) areas. For more on the DDG-1000 program, see CRS
Report RL32109, Navy DDG-1000 and DDG-51 Destroyer Programs: Background, Oversight Issues, and Options for
Congress
, by Ronald O'Rourke. For more on the CG(X) program, see CRS Report RL34179, Navy CG(X) Cruiser
Program: Background, Oversight Issues, and Options for Congress
, by Ronald O'Rourke.
Congressional Research Service
1

Navy Littoral Combat Ship (LCS) Program

out its mission packages. The basic version of the LCS, without any mission packages, is referred
to as the LCS sea frame.
The LCS’s primary intended missions are shallow-water antisubmarine warfare, mine
countermeasures, countering small boats, and intelligence, surveillance, and reconnaissance
(ISR). Secondary intended missions include homeland defense, maritime intercept operations,
and support of special operations forces.
The LCS displaces about 3,000 tons, making it about the size of a corvette (i.e., a light frigate) or
a Coast Guard cutter. It has a maximum speed of more than 40 knots, compared to something
more than 30 knots for the Navy’s larger surface combatants. The LCS has a shallower draft than
the Navy’s larger surface combatants, permitting it to operate in certain coastal waters and visit
certain ports that are not accessible to the Navy’s larger surface combatants. The LCS employs
automation to achieve a reduced “core” crew of 40 sailors. Up to 35 or so additional sailors are to
operate the ship’s embarked aircraft and mission packages, making for a total crew of about 75,
compared to more than 200 for the Navy’s frigates and about 300 (or more) for the Navy’s current
destroyers and cruisers.
Navy plans call for procuring a total of 55 LCSs. The Navy currently plans to procure a total of
64 mission packages for the 55 ships. Earlier Navy plans anticipated procuring between 90 and
110 mission packages for a 55-ship fleet.
Two Industry Teams, Each With Its Own Design
On May 27, 2004, the Navy awarded contracts to two industry teams—one led by Lockheed
Martin, the other by General Dynamics (GD)—to design two versions of the LCS, with options
for each team to build up to two LCSs each. The two teams’ LCS designs are quite different—
Lockheed’s design is based on a semi-planing steel monohull, while GD’s design in based on an
aluminum trimaran hull. The Lockheed team was assigned LCS-1 and (the subsequently
canceled) LCS-3, while the GD team was assigned LCS-2 and (the subsequently canceled) LCS-
4.3 Lockheed announced plans to build its LCSs at Marinette Marine of Marinette, WI, and
Bollinger Shipyards of Lockport, LA, with LCS-1 being built by Marinette and LCS-3 to have
been built by Bollinger. GD announced plans to build its LCSs at the Austal USA shipyard of
Mobile, AL.4
Planned Procurement
The Navy plans to procure a total of 55 LCSs. The Administration’s proposed FY2010 defense
budget, which was submitted to Congress in early May, was not accompanied by a Future Years
Defense Plan (FYDP) for the period FY2010-FY2015 or a 30-year Navy shipbuilding plan for the
period FY2010-FY2039. The Administration’s FY2010 budget submission consequently does not

3 The designations LCS-3 and LCS-4 are now being reused by the Navy to refer to two other LCSs—the two LCSs
funded in FY2009. The “new” LCS-3 and LCS-4 are not the same ships as those that the Navy cancelled; see Table 2.
4 Austal USA was created in 1999 as a joint venture between Austal Limited of Henderson, Western Australia and
Bender Shipbuilding & Repair Company of Mobile, AL. The GD LCS team also includes GD/BIW as prime contractor
to provide program management and planning, provide technical management, and to serve as “LCS system production
lead.”
Congressional Research Service
2

Navy Littoral Combat Ship (LCS) Program

include information on planned annual LCS procurement quantities for fiscal years after FY2010.
Navy budget submissions for previous years, however, have showed the annual LCS procurement
rate increasing over time to a sustained rate of five or six ships per year.
Program Funding
Table 1 shows LCS acquisition (i.e., research and development plus procurement) funding for
FY2007 through FY2010. The figures in the table reflect reprogramming of prior-year program
funding undertaken as part of the Navy’s 2007 restructuring of the LCS program. In addition to
the funding shown in the table, the LCS program also received about $1.7 billion in acquisition
funding between FY2003 and FY2006.
Table 1. LCS Program Acquisition Funding, FY2007-FY2013
(millions of dollars; figures rounded to nearest million)
Budget accounta
FY07 FY08 FY09 FY10
RDT&EN
664 309 368 361
SCN 93
0b 1017 1380
APN
37 37 50 78
WPN
0 0 3 0
OPN 79
0
74
137
TOTAL
873
347
1511
1955
Source: Navy FY2010 budget submission and (for FY2007) FY2009 budget submission. Figures may not add due
to rounding. The program also received about $1.7 billion in acquisition funding between FY2003 and FY2006.
a. RDT&EN = Research, Development, Test, and Evaluation, Navy account; SCN = Shipbuilding and
Conversion, Navy account; APN = Aircraft Procurement, Navy account; WPN = Weapons Procurement,
Navy account; OPN = Other Procurement, Navy account.
b. $337 million in FY2008 SCN funding was rescinded by Congress as part of its action on the FY2009 budget.
With Congress’s permission, the Navy procured the first and second LCSs through the Navy’s
research and development account. Subsequent LCSs are being procured through the Navy’s
ship-procurement account, called the Shipbuilding and Conversion, Navy (SCN) account. The
Navy is procuring LCS mission packages through the Other Procurement, Navy (OPN) account.
Unit Procurement Cost Cap
LCS sea frames procured in FY2010 and subsequent years are subject to a unit procurement cost
cap of $460 million.
The cost cap was originally established by Section 124 of the FY2006 defense authorization act
(H.R. 1815/P.L. 109-163 of January 6, 2006). Under this provision, the fifth and sixth ships in the
class were to cost no more than $220 million each, plus adjustments for inflation and other
factors.
The cost cap was amended by Section 125 of the FY2008 defense authorization act (H.R.
4986/P.L. 110-181 of January 28, 2008). This provision amended the cost cap to $460 million per
Congressional Research Service
3

Navy Littoral Combat Ship (LCS) Program

ship, with no adjustments for inflation, and applied the cap to all LCSs procured in FY2008 and
subsequent years.
The cost cap was amended again by Section 122 of the FY2009 defense authorization act (S.
3001/P.L. 110-417 of October 14, 2008). This provision deferred the implementation of the cost
cap by two years, applying it to all LCSs procured in FY2010 and subsequent years.
Total Acquisition Cost
The Navy has not provided an estimated total acquisition (i.e., development plus procurement)
cost for the LCS program. CRS estimates that the LCS program (including mission packages)
might have a total acquisition cost of roughly $29.4 billion. This estimate includes $2.5 billion in
research and development costs (including the construction of first two LCS sea frames and the
procurement of the first four mission packages), procurement of 53 additional LCS sea frames at
a cost of $460 million each, and procurement of 60 additional mission packages procured at an
average cost of about $42.3 million each.5 This estimate does not include costs for LCS-related
aircraft procurement or weapon procurement, such as those shown in the APN and WPN rows of
Table 1.
2007 Program Restructuring
March 2007 Navy Restructuring Plan
In response to significant cost growth and schedule delays in the building of the first LCSs that
first came to light in January 2007 (see next section), the Navy in March 2007 announced a plan
for restructuring the LCS program that:
• canceled the two LCSs funded in FY2007 and redirected the funding for those
two ships to pay for cost overruns on earlier LCSs;
• announced an intention to lift a 90-day stop-work order that the Navy had placed
on LCS-3 in January 2007—provided that the Navy reached an agreement with
the Lockheed-led industry team by April 12, 2007, to restructure the contract for
building LCSs 1 and 3 from a cost-plus type contract into a fixed price incentive
(FPI)-type contract—or terminate construction of LCS-3 if an agreement on a
restructured contract could not be reached with the Lockheed team by April 12,
2007;
• announced an intention to seek to restructure the contract with the General
Dynamics-led industry team for building LCSs 2 and 4 into an FPI-type
contract—if LCSs 2 and 4 experienced cost growth comparable to that of LCSs 1
and 3—and, if such a restructuring were sought, terminate construction of LCS-4

5 The Navy reportedly wants to procure 24 mine warfare mission packages at an average cost of $68 million each, 16
antisubmarine warfare packages at an average cost of $42.3 million each, and 24 surface warfare packages at an
average cost of $16.7 million each. (Emelie Rutherford, Littoral Combat Ship Mission Packages Range In Costs,
Features,” Inside the Navy, September 3, 2007; for similar figures, see Christopher P. Cavas, “First LCS Mission
Package Ready For Delivery,” DefenseNews.com, August 29, 2007.)
Congressional Research Service
4

Navy Littoral Combat Ship (LCS) Program

if an agreement on a restructured contract for LCS-2 and LCS-4 could not be
reached;
• reduced the number of LCSs requested for FY2008 from three to two (for the
same requested FY2008 procurement funding of $910.5 million), and the number
to be requested for FY2009 from six to three; and
• announced an intention to conduct an operational evaluation to select a favored
design for the LCS that would be procured in FY2010 and subsequent years, and
to conduct a full and open follow-on competition among bidders for the right to
build that design.6
April 2007 Termination of LCS-3
On April 12, 2007, the Navy announced that it had not reached an agreement with Lockheed on a
restructured FPI-type contract for LCS-1 and LCS-3, and consequently was terminating
construction of LCS-3.7 (The Navy subsequently began referring to the ship as having been
partially terminated—a reference to the fact that Lockheed was allowed to continue procuring
certain components for LCS-3, so that a complete set of these components would be on hand to
be incorporated into the next LCS built to the Lockheed design.) (The designation LCS-3 is now
being reused to refer to one of the two LCSs procured in FY2009.)
November 2007 Termination of LCS-4
In late-September 2007, it was reported that the Navy on September 19 had sent a letter to
General Dynamics to initiate negotiations on restructuring the contract for building LCSs 2 and 4
into an FPI-type contract. The negotiations reportedly were to be completed by October 19,
2007—30 days from September 19.8 On November 1, 2007, the Navy announced that it had not
reached an agreement with General Dynamics on a restructured FPI-type contract for LCS-2 and
LCS-4, and consequently was terminating construction of LCS-4.9 (The designation LCS-4 is
now being reused to refer to one of the two LCSs procured in FY2009.)
Summary of Status of LCSs Funded in FY2005-FY2009
Table 2 below summarizes the status of the nine LCSs funded by Congress from FY2005 through
FY2009. As shown in the table, of the nine ships, five were later canceled, leaving four ships in
place through FY2009—LCSs 1 and 2, and the two LCSs funded in FY2009. Ship designations
LCS-3 and LCS-4 are being reused as the designations for the two ships funded in FY2009.

6 Source: Navy briefing to CRS and Congressional Budget Office (CBO) on Navy’s proposed LCS program
restructuring plan, March 21, 2007.
7 Department of Defense News Release No. 422-07, April 12, 2007, “Navy Terminates Littoral Combat Ship 3.”
8 Geoff Fein, “Navy Seeking To Negotiate FPI Contract With General Dynamics,” Defense Daily, September 24, 2007;
Geoff Fein, “Navy, General Dynamics Meet To Discuss New LCS Fixed Price Structure,” Defense Daily, September
27, 2007; Tony Capaccio, “General Dynamics Urged To Take Fixed Price On Warship Contract,” Bloomberg News,
September 28, 2007; Jason Sherman, “Navy, General Dynamics Discuss Fixed-Price Contract For LCS,” Inside the
Navy
, October 1, 2007.
9 Department of Defense News Release No. 1269-07, November 1, 2007, “Navy Terminates Littoral Combat Ship
(LCS 4) Contract.”
Congressional Research Service
5

Navy Littoral Combat Ship (LCS) Program

Table 2. Status of LCSs Funded in FY2005-FY2009
Ships
FY
Navy hull
funded funded
designation
Status
1st 2005
LCS-1
Commissioned into service on November 8, 2008.
2nd LCS-2
Under construction; ship launched April 26, 2008 and
scheduled to be delivered to the Navy in late-2009.
3rd LCS-3
Canceled by Navy in April 2007 after being placed under
contract due to inability to come to agreement with contractor
(not the same ship as LCS-3
2006
on revised (fixed-price) contract terms for LCSs 1 and 3.
below)
4th
LCS-4
Canceled by Navy in November 2007 after being placed under
contract due to inability to come to agreement with contractor
(not the same ship as LCS-4 on revised (fixed-price) contract terms for LCSs 2 and 4.
below)
5th none

Canceled by Navy in March 2007 before being placed under
(ship canceled before being contract as part of Navy’s LCS program restructuring; funds
placed under contract)
reapplied to cover other program costs.
2007
6th
none
Canceled by Navy in March 2007 before being placed under
(ship canceled before being contract as part of Navy’s LCS program restructuring; funds
placed under contract)
reapplied to cover other program costs.
7th
LCS-5
Canceled by Navy following Congress’ decision in
(for a while, at least,
September 2008, as part of its action on the FY2009 defense
2008
although the ship was
appropriations bill, to rescind the funding for the ship.
canceled before being
placed under contract)
8th LCS-3
Funded in FY2009 and Under Construction. Contract to
build the ship awarded to Lockheed Martin on March 23, 2009.
(not the same ship as LCS-3 Ship is currently under construction.
above; the ship designation
is being reused)
2009
9th
LCS-4
Funded in FY2009 and Under Construction. Contract to
build the ship awarded to General Dynamics on May 1, 2009.
(not the same ship as LCS-4 Ship is currently under construction.
above; the ship designation
is being reused)
Source: Prepared by CRS.
Acquisition Strategy for FY2009 and Subsequent Ships
FY2009 and FY2010 Ships
Under the Navy’s acquisition strategy for the LCS program, the FY2009 and FY2010 LCSs are to
be built under fixed-price type contracts.
The Navy bundled together the two LCSs funded in FY2009 (LCSs 3 and 4) with the three LCSs
that are to be requested in FY2010 into a single, five-ship solicitation. The Navy announced that
each LCS industry team would be awarded a contract for one of the FY2009 ships, and that the
prices that the two teams bid for both the FY2009 ships and the FY2010 ships would determine
the allocation of the three FY2010 ships, with the winning team getting two of the FY2010 ships
Congressional Research Service
6

Navy Littoral Combat Ship (LCS) Program

and the other team getting one FY2010 ship. This strategy is intended to use the carrot of the third
FY2010 ship to generate bidding pressure on the two industry teams for both the FY2009 ships
and the FY2010 ships.
The Navy stated that the contracts for the two FY2009 ships would be awarded by the end of
January 2009. The first contract (for Lockheed Martin, to build LCS-3) was awarded March 23,
2009; the second contract (for General Dynamics, to build LCS-4) was awarded May 1, 2009.
The delay in the awarding of the contracts past the end-of-January target date may have been due
in part to the challenge the Navy faced in coming to agreement with the industry teams on prices
for the two FY2009 ships that would permit the three FY2010 ships to be built within the $460
million LCS unit procurement cost cap.
At a March 10, 2009, hearing on the LCS program, the Navy stated the following regarding the
acquisition strategy for LCSs procured in FY2009 and FY2010:
In October 2008, the Undersecretary of Defense for Acquisition, Technology and Logistics
(USD(AT&L)) approved a revised acquisition strategy for LCS to cover procurement of the
FY 2009 and FY 2010 ships. The updated acquisition strategy combines the FY 2009
procurement and FY 2010 options in order to maximize competitive pressure on pricing as a
key element of cost control. Increasing the quantity solicited by adding the FY 2010 ships to
the FY 2009 solicitation as options will also enable industry to better establish longer term
supplier relationships and offer the potential for discounting to the prime contractors and
subcontractors. FY 2010 ship options will be a competition for quantity....
As a result of congressional direction contained in the FY 2009 Defense Appropriations Act,
the Navy amended the LCS seaframe construction solicitation to delete the FY 2008 ship.
This amended solicitation continues the competition between the two incumbent industry
teams. The Navy may award one ship to each industry team in FY 2009 and intends to hold a
competition for the FY 2010 option ships soon after award of the FY 2009 contracts.
Affordability remains a key tenet of the LCS program as the Navy works with industry to
provide this capability for the lowest cost.
The FY 2009 and FY 2010 awards will be fixed-price incentive contracts, with the Navy
anticipating that each LCS prime contractor receives one ship in FY 2009. The Navy remains
committed to effective cost control and has modified contracting strategies and management
practices to provide program stability. The FY 2009 and FY 2010 ships will be designated as
Flight 0+ and will include only existing approved engineering changes along with
improvements to construction or fabrication procedures. The Navy will incorporate further
lessons learned from LCS 1 and 2 sea trials into the FY 2009 and FY 2010 ships prior to
production. Any such changes will be limited to those essential for safety, operability or
affordability. Furthermore, the RFP requests that the proposals for the FY 2010 option ships
include alternative prices for both a full-up ship and separately priced contract line item
numbers (CLINs) for a core seaframe (only systems for safe operation at sea), core combat
system and individual combat systems and equipments (such as the gun or radar). This
allows us the opportunity to manage the integration of the combat systems separately if that
proved to be more affordable.
In the interim prior to FY 2009 contract awards, both industry teams were authorized and
funded to pursue limited design and construction efforts while source selection proceeded.
The scope of these efforts was carefully coordinated with prime contractors with an eye on
preserving critical shipbuilding skills or to improve production process engineering. Once
Congressional Research Service
7

Navy Littoral Combat Ship (LCS) Program

the FY 2009 ships are awarded, these sustaining efforts will be subsumed in the shipbuilding
contracts.10
FY2011 and Subsequent Ships
The Navy has not yet settled on an acquisition strategy for LCSs to be procured in FY2011 and
subsequent years. Areas of uncertainty include whether and when the Navy will neck down to a
single LCS design, which yard or yards will build the ships, and whether a common combat
system will developed for the two designs (should they both remain in production).
Keeping both designs in production could permit the Navy to use competition between the two
designs to control production costs, and could permit the Navy to field a combination of LCSs of
both designs that bests takes advantage of the somewhat differing capabilities of the two designs.
(The Navy has testified, for example, that the Lockheed design has, among other things, good
features for handling small boats that are deployed from the LCS, while the General Dynamics
design has, among other things, a generously sized fight deck for supporting helicopter and UAV
operations.)
Necking down to a single design could permit the Navy to make maximum use of production
learning-curve benefits in reducing LCS construction costs, and would not necessarily preclude
the use of competition between competing firms to control costs for producing that one design.
The two LCS designs currently use two different, contractor-furnished combat systems.11 The
Navy testified in July 2007 that it wanted to shift to a common, government-furnished combat
system for LCSs procured in FY2010 and beyond.12 The Navy now states that it is reviewing the
question of whether to shift to a common combat system.
At the March 10, 2009, hearing on the LCS program, the Navy stated the following regarding the
acquisition strategy for LCSs procured in FY2011 and subsequent years:
Acquisition strategies for FY 2011 and outyear ships are under development. The Navy’s
strategy will be guided by cost and performance of the respective designs, as well as options
for sustaining competition throughout the life of the program. Evaluations of combat systems
and hull, mechanical and electrical (HM&E) performance will be conducted throughout
those tests and trial periods and, as was mentioned earlier, we are already looking for
opportunities to reduce total ownership costs through commonality, reductions or
consolidations based on return-on-investment analysis.13

10 Statement of RADM Victor Guillory, U.S. Navy Director of Surface Warfare, and RADM William E. Landay, III,
Program Executive Officer Ships, and Ms. E. Anne Sandel, Program Executive Officer Littoral and Mine Warfare,
before the Subcommittee on Seapower and Expeditionary Forces of the House Armed Services Committee [hearing] on
the Current Status of the Littoral Combat Ship Program, March 10, 2009, pp. 7-8.
11 A ship’s combat system typically includes its sensors, computers, displays, and weapon launchers. The discussion
here refers to the part of the LCS combat system that is permanently built into each sea frame, and not to the part that
would be added by a modular mission package.
12 Statement of VADM Paul Sullivan et al., Before the Subcommittee on Seapower and Expeditionary Forces of the
House Armed Services Committee on Surface Combatant Construction Update, July 24, 2007, p. 8.
13 Statement of RADM Victor Guillory, U.S. Navy Director of Surface Warfare, and RADM William E. Landay, III,
Program Executive Officer Ships, and Ms. E. Anne Sandel, Program Executive Officer Littoral and Mine Warfare,
before the Subcommittee on Seapower and Expeditionary Forces of the House Armed Services Committee [hearing] on
the Current Status of the Littoral Combat Ship Program, March 10, 2009, p. 7.
Congressional Research Service
8

Navy Littoral Combat Ship (LCS) Program

Cost Growth on LCS Sea Frames
Summary of Cost Growth
The Navy originally spoke of building LCS sea frames for about $220 million each in constant
FY2005 dollars. Estimated LCS sea frame procurement costs have since grown substantially
above that figure. The estimate for LCS-1 has grown from $215.5 million in the FY2005 budget
to $537 million in the FY2010 budget. The estimate for LCS-2 has grown from $213.7 million in
the FY2005 budget to $575 million in the FY2010 budget. Subsequent LCSs are expected to cost
less than LCS-1 and LCS-2.
The figures of $537 million and $575 million in the previous paragraph are end-cost figures. End
cost is the figure often reported as the total procurement cost of a Navy ship. It is a fairly
comprehensive figure for a ship’s procurement cost, but it does exclude certain cost elements. The
FY2010 budget submission states that when additional costs for outfitting and post delivery
(OF/PD) and for “final system design/mission systems and ship integration team” (FSD/MSSIT)
are included, the total estimated procurement costs of LCS-1 and LCS-2 become $637 million
and $704 million, respectively.
The Navy stated in 2008 that although FSD/MSSIT costs are shown in budget-justification
documents as part of the total estimated procurement costs of LCS-1 and LCS-2, the work in
question is normally funded from a shipbuilding program’s general research and development
funds, rather than from funds used to pay for the construction of individual ships in the program.
The Navy stated that in the case of the LCS program, these costs are shown as part of the total
procurement costs of LCS-1 and LCS-2 because this is where there was room in the LCS
program’s line-item funding breakdown to accommodate these costs.14 Removing these costs
from the total procurement costs of LCS-1 and LCS-2 would lead to adjusted total procurement
costs of $612 million and $650 million, respectively, for the two ships.
Review of Cost Growth Over Time
2006
The proposed FY2007 Navy budget, submitted in February 2006, showed that:
• the estimate for the first LCS had increased from $215.5 million in the FY2005
budget and $212.5 million in the FY2006 budget to $274.5 million in the
FY2007 budget—an increase of about 27% from the FY2005 figure and about
29% form the FY2006 figure;
• the estimate for the second LCS increased from $213.7 million in the FY2005
budget and $256.5 million in the FY2006 budget to $278.1 million—an increase
of about 30% from the FY2005 figure and about 8% from the FY2006 figure;
and
• the estimate for follow-on ships scheduled for FY2009-FY2011, when the LCS
program was to have reached a planned maximum annual procurement rate of six

14 Source: Navy briefing to CRS and CBO on the LCS program, May 2, 2008.
Congressional Research Service
9

Navy Littoral Combat Ship (LCS) Program

ships per year, had increased from $223.3 million in the FY2006 budget to $298
million—an increase of about 33%.
The Navy stated in early 2006 that the cost increase from the FY2006 budget to the FY2007
budget was due mostly to the fact that LCS procurement costs in the FY2006 budget did not
include items that are traditionally included in the so-called end cost—the total budgeted
procurement cost—of a Navy shipbuilding program, such as Navy program-management costs,
an allowance for changes, and escalation (inflation). The absence of these costs from the FY2006
LCS budget submission raised certain potential oversight issues for Congress.15
2007
On January 11, 2007, the Navy reported that LCS-1 was experiencing “considerable cost
overruns.” The Navy subsequently stated that the estimated shipyard construction cost of LCS-1
had grown to $350 million to $375 million. This suggested that the end cost of LCS-1—which
also includes costs for things such as Navy program-management costs and an allowance for
changes—could be in excess of $400 million. The Navy did not publicly provide a precise cost
overrun figure for LCS 2, but it stated that the cost overrun on LCSs 1 and 2 was somewhere
between 50% and 75%, depending on the baseline that is used to measure the overrun.
The Government Accountability Office (GAO) testified in July 2007 that according to its own
analysis of Navy data, the combined cost of LCSs 1 and 2 had increased from $472 million to
$1,075—an increase of 128%.16 The Congressional Budget Office (CBO) testified in July 2007
that:
Several months ago, press reports indicated that the cost could well exceed $400 million
each for the first two LCS sea frames. Recently, the Navy requested that the cost cap for the
fifth and sixth sea frames be raised to $460 million, which suggests that the Navy’s estimate
of the acquisition cost for the first two LCSs would be around $600 million apiece....
As of this writing, the Navy has not publicly released an estimate for the LCS program that
incorporates the most recent cost growth, other than its request to raise the cost caps for the
fifth and sixth ships. CBO estimates that with that growth included, the first two LCSs would
cost about $630 million each, excluding mission modules but including outfitting,

15 These oversight issues included the following:
—Why were these costs excluded? Was this a budget-preparation oversight? If so, how could such an oversight occur,
given the many people involved in Navy budget preparation and review, and why did it occur on the LCS program but
not other programs? Was anyone held accountable for this oversight, and if so, how? If this was not an oversight, then
what was the reason?
—Did the Navy believe there was no substantial risk of penalty for submitting to Congress a budget presentation for a
shipbuilding program that, for whatever reason, significantly underestimated procurement costs?
—Do LCS procurement costs in the budget now include all costs that, under traditional budgeting practices, should be
included? If not, what other costs are still unacknowledged?
—Have personnel or other resources from other Navy programs been used for the LCS program in any way? If so, have
the costs of these personnel or other resources been fully charged to the LCS program and fully reflected in LCS
program costs shown in the budget?
16 Defense Acquisitions[:] Realistic Business Cases Needed to Execute Navy Shipbuilding Programs, Statement of Paul
L. Francis, Director, Acquisition and Sourcing Management Team, Testimony Before the Subcommittee on Seapower
and Expeditionary Forces, Committee on Armed Services, House of Representatives, July 24, 2007 (GAO-07-943T),
pp. 4 and 22.
Congressional Research Service
10

Navy Littoral Combat Ship (LCS) Program

postdelivery, and various nonrecurring costs associated with the first ships of the class. As
the program advances, with a settled design and higher annual rates of production, the
average cost per ship is likely to decline. Excluding mission modules, the 55 LCSs in the
Navy’s plan would cost an average of $450 million each, CBO estimates.17
2008
The proposed FY2009 budget, submitted in February 2008, showed that the estimated end costs
of LCS-1 and LCS-2 had increased to $531 million and $507 million, respectively (or to $631
million and $636 million, respectively, when OF/DP and FST MSSIT costs are included, or to
$606 million and $582 million, respectively, when OF/DP costs are included, but FST MSSIT
costs are not included).
2009
The proposed FY2010 budget, submitted in May 2009, showed that the estimated end costs of
LCS-1 and LCS-2 had increased to $537 million and $575 million, respectively (or to $637
million and $704 million, respectively, when OF/DP and FST MSSIT costs are included, or to
$612 million and $650 million, respectively, when OF/DP costs are included, but FST MSSIT
costs are not included).
June 2008 CBO Report
CBO reported on June 9, 2008 that:
Historical experience indicates that cost growth in the LCS program is likely. In particular,
using the lead ship of the FFG-7 Oliver Hazard Perry class frigate as an analogy, historical
cost-to-weight relationships indicate that the Navy’s original cost target for the LCS of $260
million in 2009 dollars (or $220 million in 2005 dollars) was optimistic. The first FFG-7 cost
about $670 million in 2009 dollars to build, or about $250 million per thousand tons,
including combat systems. Applying that metric to the LCS program suggests that the lead
ships would cost about $600 million apiece, including the cost of one mission module. Thus,
in this case, the use of a historical cost-to-weight relationship produces an estimate that is
less than the actual costs of the first LCSs to date but substantially more than the Navy’s
original estimate.
Based on actual costs the Navy has incurred for the LCS program, CBO estimates that the
first two LCSs could cost about $700 million each, including outfitting and postdelivery and
various nonrecurring costs associated with first ships of a class but excluding mission
modules. However, as of May 1, 2008, LCS-1 was 83 percent complete and LCS-2 was 68
percent complete. Thus, additional cost growth is possible, and CBO’s estimate reflects that
cost risk.
Overall, CBO estimates that the LCSs in the Navy’s plan would cost about $550 million
each, on average, excluding mission modules. That estimate assumes that the Navy would
select one of the two existing designs and make no changes. As the program advanced with a

17 Statement of J. Michael Gilmore, Assistant Director for National Security, and Eric J. Labs, Senior Analyst, [on] The
Navy’s 2008 Shipbuilding Plan and Key Ship Programs, before the Subcommittee on Seapower and Expeditionary
Forces Committee on Armed Services U.S. House of Representatives, July 24, 2007, p. 18.
Congressional Research Service
11

Navy Littoral Combat Ship (LCS) Program

settled design and higher annual rates of production, average ship costs would probably
decline. If the Navy decided to make changes to that design, however, the costs of building
future ships could be higher than CBO now estimates.18
Reasons for Cost Growth
Various reasons have been cited for cost growth in the LCS program, including the following:
Unrealistically low original estimate. Some observers believe that the original
cost estimate of $220 million for the LCS sea frame was unrealistically low. If so,
a potential follow-on question would be whether the LCS represents a case of
“low-balling”—using an unrealistically low cost estimate in the early stages of a
proposed weapon program to help the program win approval and become an
established procurement effort.
Impact of Naval Vessel Rules (NVR). Navy and industry officials have
attributed some of the cost growth to the impact of applying new Naval Vessel
Rules (NVR)—essentially, new rules specifying the construction standards for
the ship—to the LCS program. The NVR issued for the LCS program
incorporated, among other things, an increase in the survivability standard (the
ability to withstand damage) to which LCSs were to be built.19 Building the ship
to a higher survivability standard represented a change in requirements for the
ship that led to many design changes, including changes that made ship more
rugged and more complex in terms of its damage-control systems. In addition,
Navy and industry officials have testified, the timing of the issuing of NVR
created a situation of concurrency between design and construction in the LCS
program, meaning that the ship was being designed at the same time that the
shipyard was attempting to build it—a situation long known to be a potential
cause of cost growth. This concurrency, Navy officials testified, was a
consequence of the compressed construction schedule for the LCS program,
which in turn reflected an urgency about getting LCSs into the fleet to meet
critical mission demands.
Improperly manufactured reduction gear. Navy and industry officials testified
that cost growth on LCS-1 was partly due to a main reduction gear20 that was
incorrectly manufactured and had to be replaced, forcing a reordering of the
construction sequence for the various major sections of the ship.

18 Congressional Budget Office, Resource Implications of the Navy’s Fiscal Year 2009 Shipbuilding Plan, June 8,
2008, pp. 26-27.
19 The LCS was earlier conceived as a ship that would be built to a survivability standard that would be sufficient, in
the event of significant battle damage, to save the ship’s crew, but not necessarily the ship. The survivability standard
for the LCS was increased as part of the issuing of NVR to one that would be sufficient to save not only the ship’s
crew, but the ship as well. (Other U.S. Navy combat ships are built to a still-higher survivability standard that is
sufficient not only to save the crew and the ship, but to permit the ship to keep fighting even though it has sustained
damage.)
20 A ship’s reduction gear is a large, heavy gear that reduces the high-speed revolutions of the ship’s turbine engines to
the lower-speed revolutions of its propellers.
Congressional Research Service
12

Navy Littoral Combat Ship (LCS) Program

Increased costs for materials. Some observers have attributed part of the cost
growth in the program to higher-than-estimated costs for steel and other materials
that are used in building the ships.
Emphasis on meeting schedule combined with cost-plus contract. Some
portion of cost growth on LCS-1 has been attributed to a combination of a Navy
emphasis on meeting the ship’s aggressive construction schedule and the Navy’s
use of a cost-plus contract to build the ship.21
Shipyard Performance. Shipyard performance and supervision of the LCS
shipyards by the LCS team leaders and the Navy has been cited as another cause
of cost growth.22
Press Reports on Shipyard Performance and Supervision
Regarding shipyard performance and supervision of the LCS shipyards by the LCS team leaders
and the Navy, a February 4, 2008, press report stated:
Marinette Marine, the Wisconsin shipyard building the first Littoral Combat Ship, never
received proper certification to manage the project, which has suffered severe cost growth
and schedule delays, according to an internal naval audit obtained by sister publication Inside
the Pentagon [ITP].
The interim report is the most damning account yet of the LCS program’s failure to use
earned value management (EVM). Pentagon officials and contractors are supposed to use the
process to manage the cost, schedule and performance of acquisition efforts. The idea is to
coordinate key project goals and objectively measure progress.
In prepared testimony for his Senate confirmation hearing last October, Pentagon acquisition
executive John Young noted that EVM was a “serious deficiency” in the LCS program.

21 The Senate Armed Services Committee, as part of its discussion of the LCS program in its report (S.Rept. 110-77 of
June 5, 2007) on the FY2008 defense authorization bill (S. 1547), stated:
Reviewing this LCS situation will undoubtedly result in a new set of “lessons learned”‘ that the
acquisition community will dutifully try to implement. However, the committee has previously
expressed concerns about the LCS concept and the LCS acquisition strategy. The LCS situation
may be more a case of “lessons lost.” Long ago, we knew that we should not rush to sign a
construction contract before we have solidified requirements. We also knew that the contractors
will respond to incentives, and that if the incentives are focused on maintaining schedules and not
on controlling cost, cost growth on a cost-plus contract should surprise no one. After the fact,
everyone appears ready to agree that the original ship construction schedule for the lead ship was
overly aggressive. (Page 98)
22 A recent press report based on remarks made by Admiral Gary Roughead, the Chief of Naval Operations, included
remarks on causes of cost growth in the LCS program:
“There was a rush, and we thought we could get by with some commercial specifications,”
Roughead said. “As we got into building the ship, some of those commercial applications weren’t
going to do it from a survivability standpoint. That required some recasting of specifications.”...
The Navy sought to design and build the ship concurrently, “which is not necessarily a good thing,”
Roughead said. And in an effort to improve efficiency, the service “backed off” staffing in
technical and oversight areas in the shipyards. “That came back to bite us,” he said.
(Katherine McIntire Peters, “Navy’s Top Officer Sees Lessons In Shipbuilding Program Failures,” September 24,
2008.)
Congressional Research Service
13

Navy Littoral Combat Ship (LCS) Program

The audit reveals how this deficiency has undermined work on the Freedom (LCS-1), which
Marinette Marine is building for Lockheed Martin.
The review, which began a year ago, is still ongoing. However, ITP obtained a redacted copy
of the Jan. 7 interim report, originally stamped “for official use only,” through the Freedom
of Information Act....
The review reveals Marinette Marine’s poor management and faults the Navy, the Defense
Contract Management Agency (DCMA) and Lockheed for failing to notice and fix the
problem.
The press report also states:
Robert Herre, the president and general manager of Manitowoc Marine Group, which
operates the shipyard, told ITP in an interview that Marinette Marine never worked on a
project before that required the robust EVM needed for the Freedom contract. The
management software that the shipyard acquired several years ago was not up to the task.
Marinette Marine tried to adapt for the Freedom project by using a manual system, too,
Herre said, but it became “more of a cumbersome process than first thought.”
Lockheed spokesman Craig Quigley blamed “cost and schedule baseline disconnects” on the
Navy for making big changes to the Freedom without agreeing, until last November, to
rebaseline both the program’s cost and schedule. Previously only the schedule had been
rebaselined, he said. Lockheed’s team has maintained an EVM system baseline on the
program and accurately reported monthly variances, he said.
“Not having the cost and schedule baseline in synchronization prohibits accurate system
predictions, but that was accounted for via adjunct reports,” he added.
The report says DCMA and Naval Sea Systems Command did not provide sufficient
oversight to ensure proper management of the contract; the Navy’s Gulf Coast-based
shipbuilding office and industry did not effectively review the EVM, or lack thereof; and the
program office and the shipyard “placed limited emphasis” on the implementation of EVM
for the contract.
DCMA initially granted a “conditional approval” for Marinette Marine’s EVM system in
April 2006, the report says. The conditional nod was based on a Navy-led EVM system
review conducted the year before. However, Pentagon policy does not allow for a
“conditional approval” of a contractor’s EVM system. DCMA only recognized its error 10
months later, in February 2007, according to the report. The agency then alerted the program
office, Lockheed and Marinette Marine that the “conditional approval” had been
inappropriate.
Now all agree Marinette Marine lacks a DCMA-validated EVM system, a problem that must
be fixed.
The report says Marinette Marine’s EVM system did not provide valid and reliable cost,
schedule, and technical performance data to support the LCS program office’s decision-
making. Auditors found the shipyard was not following 24 of the Pentagon’s 32 EVM rules.
DCMA failed to check whether the 32 rules were being followed. Further, the Navy and
DCMA failed to perform formal surveillance to ensure the shipyard heeded the rules, the
report says. And Marinette Marine failed to use EVM as an integrated program management
tool.
Congressional Research Service
14

Navy Littoral Combat Ship (LCS) Program

As a result, the Navy is “not receiving full value for program management services and
information paid for under this contract,” the report states.
The press report also states:
The report describes a “significant breakdown in internal controls.” Navy decision-makers
are not receiving accurate and reliable earned value data for the Freedom, the review says.
The shipyard’s projected estimates-at-completion for the Freedom contract are “not
supported.” Further, the program office “did not have visibility” for project work totaling
approximately $51 million. The lack of oversight left the Navy’s financial interest in the
ship’s construction unprotected, the review concludes....
Auditors recommended eight fixes. The report says four remain to be done, but Quigley said
two remain to be done. Last November, the Navy completed a new estimate for the cost of
completing the Freedom contract, conducted a schedule review and had the program develop
a new baseline for the ship. Officials have also had Lockheed start work on a plan to fix the
problems.
Quigley said officials have reviewed, approved and monitored Lockheed’s plan. He also said
the shipyard’s efforts are now being checked continuously against the 32 rules.
In March [2008], the Navy plans to review the new baseline. And DCMA is due to conduct a
review to ensure the shipyard is following the rules by year’s end, the report says. Quigley
said that last step could take 18 months.
Unlike Marinette Marine, Lockheed and Gibbs & Cox (another team member), have EVM
certification, he said.
Young’s predecessor, Kenneth Krieg, warned in a memo last summer that the Pentagon’s
EVM efforts were “insufficient, especially given the number of major defense programs
experiencing execution problems.”23
A July 14, 2008, press report states:
The Navy’s Littoral Combat Ship program has not one, but two black eyes on earned value
management because both LCS shipbuilders violated Defense Department rules for
managing the cost, schedule and performance of acquisition efforts, a new audit finds.
The June 12 report by the Naval Audit Service reveals that Austal, General Dynamics and
the Navy all failed to apply the rules to the second Littoral Combat Ship, Independence
(LCS-2). The report is stamped “for official use only.” Inside the Pentagon obtained a
redacted version through the Freedom of Information Act.
This finding is nearly as bad as the failure of Marinette Marine, Lockheed Martin and the
Navy to apply the rules to the first LCS, Freedom (LCS-1), a debacle documented by
auditors earlier this year. In that case, Marinette Marine ran afoul of more rules and also
lacked the required management certification.
The idea behind earned value management is to coordinate key project goals and objectively
measure progress. Many Pentagon contractors and programs have failed to use the tool

23 Christopher J. Castelli, “Audit Exposes Failed Management of Troubled Littoral Warship,” Inside the Navy,
February 4, 2008.
Congressional Research Service
15

Navy Littoral Combat Ship (LCS) Program

properly. But the failures in the LCS program are particularly well documented, providing a
road map for how not to do earned value management.
The latest audit—conducted from February 2007 to April 2008—reveals Alabama-based
Austal, the shipyard building LCS-2 for prime contractor General Dynamics, failed to heed
20 of the Pentagon’s 32 rules for earned value management.
GD spokesman Jim DeMartini said the company had not yet reviewed the June 12 report.
“However, we are aware of the issue and we are aggressively taking actions to improve the
implementation and oversight of EVM in the LCS program,” he told ITP. “We are working
in close cooperation with our Navy customer and have achieved a number of noteworthy
accomplishments along the path to improving the implementation of EVM in the LCS
program.”
GD intends to “continue to aggressively address these issues until they are resolved, and to
execute the established processes and procedures for the duration of the LCS program,”
DeMartini said....
“We found that EVM was not sufficiently implemented and overseen by any of the
responsible parties on the LCS-2 ‘Independence’ detailed design and construction contract,”
the report states.
The audit warns the Navy’s supervisor at GD’s Bath Iron Works shipyard did not provide
adequate surveillance over Austal’s EVM implementation.
GD, as the prime contractor, did not effectively oversee Austal’s EVM implementation,
auditors write.
And the Navy’s program executive office for ships, as well as the program manager, lacked
adequate visibility over the LCS contractor’s cost, schedule, and technical performance
because they “placed limited emphasis on the implementation of EVM,” the report says.
The report faults the Defense Contract Management Agency and Naval Sea Systems
Command for insufficient oversight that failed to ensure EVM was properly implemented for
LCS-2. The Defense Contract Audit Agency did not perform the required audits of Austal’s
earned value management system, the report adds.
“The Navy is committed to earned value management and is working proactively to ensure
that it is implemented properly,” Navy spokesman Lt. Clay Doss told ITP. “We asked the
Naval Audit Service to independently review how EVM was being used on the Littoral
Combat Ship program in order to provide a baseline for continuous self-assessment. We are
in the process of taking the corrective actions as recommended in the report.”
The report’s recommendations aim to bring Austal into compliance with the 32 rules,
provide better oversight and ensure required audits are conducted.
The audit also critiques the work of the Navy’s LCS program management assist group
(PMAG), which studied the cost growth on the first LCS and the projected costs for three
more LCSs in early 2007. Though the PMAG answered all nine questions regarding cost
estimates, cost growth, contractor and subcontractor arrangement, EVM, and oversight
issues, the review was “not comprehensive,” the audit finds, noting the PMAG was given
less than 15 working days to do its study.
Congressional Research Service
16

Navy Littoral Combat Ship (LCS) Program

“Given the complexity of the ship design and construction process, use of multiple
contractors, geographical dispersion of the key players, and the size of the LCS acquisition
program, we believe 15 days was not sufficient time to adequately conduct in-depth analyses
to fully assess the validity and accuracy of program data and decisions used to support their
findings,” the report says.24
July 2007 GAO Testimony
GAO testified in July 2007 that:
We have frequently reported on the wisdom of using a solid, executable business case before
committing resources to a new product development effort....
A sound business case would establish and resource a knowledge-based approach at the
outset of a program. We would define such a business case as firm requirements, mature
technologies, and an acquisition strategy that provides sufficient time and money for design
activities before construction start. The business case is the essential first step in any
acquisition program that sets the stage for the remaining stages of a program, namely the
business or contracting arrangements and actual execution or performance. If the business
case is not sound, the contract will not correct the problem and execution will be subpar.
This does not mean that all potential problems can be eliminated and perfection achieved, but
rather that sound business cases can get the Navy better shipbuilding outcomes and better
return on investment. If any one element of the business case is weak, problems can be
expected in construction. The need to meet schedule is one of the main reasons why
programs cannot execute their business cases. This pattern was clearly evident in both the
LPD 17 [amphibious ship] and LCS programs. In both cases, the program pushed ahead with
production even when design problems arose or key equipment was not available when
needed. Short cuts, such as doing technology development concurrently with design and
construction, are taken to meet schedule. In the end, problems occur that cannot be resolved
within compressed, optimistic schedules. Ultimately, when a schedule is set that cannot
accommodate program scope, delivering an initial capability is delayed and higher costs are
incurred....
What happens when the elements of a solid business case are not present? Unfortunately, the
results have been all too visible in the LPD 17 and the LCS. Ship construction in these
programs has been hampered throughout by design instability and program management
challenges that can be traced back to flawed business cases. The Navy moved forward with
ambitious schedules for constructing LPD 17 and LCS despite significant challenges in
stabilizing the designs for these ships. As a result, construction work has been performed out
of sequence and significant rework has been required, disrupting the optimal construction
sequence and application of lessons learned for follow-on vessels in these programs....
In the LCS program, design instability resulted from a flawed business case as well as
changes to Navy requirements. From the outset, the Navy sought to concurrently design and
construct two lead ships in the LCS program in an effort to rapidly meet pressing needs in
the mine countermeasures, antisubmarine warfare, and surface warfare mission areas. The
Navy believed it could manage this approach, even with little margin for error, because it
considered each LCS to be an adaptation of an existing high-speed ferry design. It has since
been realized that transforming a high-speed ferry into a capable, networked, survivable

24 Christopher J. Castelli, “Audit Reveals Both LCS and Industry Teams Violated Management Rules,” Inside the
Pentagon
, July 10, 2008. The article was reprinted in essentially identical form, with the same headline, in the July 14,
2008, issue of sister publication Inside the Navy.
Congressional Research Service
17

Navy Littoral Combat Ship (LCS) Program

warship was quite a complex venture. Implementation of new Naval Vessel Rules (design
guidelines) further complicated the Navy’s concurrent design-build strategy for LCS. These
rules required program officials to redesign major elements of each LCS design to meet
enhanced survivability requirements, even after construction had begun on the first ship.
While these requirements changes improved the robustness of LCS designs, they contributed
to out of sequence work and rework on the lead ships. The Navy failed to fully account for
these changes when establishing its $220 million cost target and 2-year construction cycle
for the lead ships.
Complicating LCS construction was a compressed and aggressive schedule. When design
standards were clarified with the issuance of Naval Vessel Rules and major equipment
deliveries were delayed (e.g., main reduction gears), adjustments to the schedule were not
made. Instead, with the first LCS, the Navy and shipbuilder continued to focus on achieving
the planned schedule, accepting the higher costs associated with out of sequence work and
rework. This approach enabled the Navy to achieve its planned launch date for the first
Littoral Combat Ship, but required it to sacrifice its desired level of outfitting. Program
officials report that schedule pressures also drove low outfitting levels on the second Littoral
Combat Ship design as well, although rework requirements have been less intensive to date.
However, because remaining work on the first two ships will now have to be completed out-
of-sequence, the initial schedule gains most likely will be offset by increased labor hours to
finish these ships.
The difficulties and costs discussed above relate to the LCS seaframe only. This program is
unique in that the ship’s mission equipment is being developed and funded separately from
the seaframe. The Navy faces additional challenges integrating mission packages with the
ships, which could further increase costs and delay delivery of new antisubmarine warfare,
mine countermeasures, and surface warfare capabilities to the fleet. These mission packages
are required to meet a weight requirement of 180 metric tons or less and require 35 personnel
or less to operate them. However, the Navy estimates that the mine countermeasures mission
package may require an additional 13 metric tons of weight and 7 more operator personnel in
order to deploy the full level of promised capability. Because neither of the competing ship
designs can accommodate these increases, the Navy may be forced to reevaluate its planned
capabilities for LCS.25
Summary of Congressional Action in FY2005-FY2009
FY2005
In FY2005, Congress approved the Navy’s plan to fund the construction of the first two LCS sea
frames using research and development funds rather than shipbuilding funds, funded the first
construction cost of the first LCS (LCS-1), required the second LCS (LCS-2) to be built (when
funded in FY2006) to a different design from the first, prohibited the Navy from requesting funds
in FY2006 to build a third LCS, and required all LCSs built after the lead ships of each design to
be funded in the SCN account rather than the Navy’s research and development account.

25 Defense Acquisitions[:] Realistic Business Cases Needed to Execute Navy Shipbuilding Programs, Statement of Paul
L. Francis, Director, Acquisition and Sourcing Management Team, Testimony Before the Subcommittee on Seapower
and Expeditionary Forces, Committee on Armed Services, House of Representatives, July 24, 2007 (GAO-07-943T),
pp. 8-11.
Congressional Research Service
18

Navy Littoral Combat Ship (LCS) Program

FY2006
In FY2006, Congress funded the procurement of LCSs 2, 3, and 4. (The Navy requested one LCS
for FY2006, consistent with Congress’s FY2005 action. Congress funded that ship and provided
funding for two additional ships.) Congress in FY2006 also established a unit procurement cost
limit on the fifth and sixth LCS sea frames of $220 million per ship, plus adjustments for inflation
and other factors (Section 124 of the FY2006 defense authorization bill [H.R. 1815/P.L. 109-163]
of January 6, 2006), required an annual report on LCS mission packages, and made procurement
of more than four LCSs contingent on the Navy certifying that there exists a stable design for the
LCS.
FY2007
In FY2007, Congress funded the procurement of LCSs 5 and 6. (The Navy canceled these two
ships in 2007 before they were placed under contract for construction.)
FY2008
In FY2008, Congress accepted the Navy’s cancellation of LCSs 3 through 6; funded the
procurement one additional LCS in FY2008 (which the Navy called LCS-5);26 significantly
reduced the Navy’s FY2008 funding request for the LCS program; amended the LCS sea frame
unit procurement cost cap to $460 million per ship for LCSs procured in FY2008 and subsequent
years (Section 125 of the conference report [H.Rept. 110-477 of December 6, 2007] on H.R.
1585, the FY2008 defense authorization bill, which was enacted as H.R. 4986/P.L. 110-181 of
January 28, 2008); and required the Navy to use fixed-price-type contracts for the construction of
LCSs procured in FY2008 and subsequent years.
The Navy in 2007 requested that Congress amend the existing unit procurement cost cap for the
fifth and sixth ships to $460 million, plus adjustments for inflation and other factors. Congress
amended the cost cap to $460 million, but applied it not only to the fifth and sixth LCSs, but to all
LCSs procured in FY2008 and subsequent years. The use of fixed-price contracts for future LCSs
was something that the Navy had stated an intention to do as part of its plan for restructuring the
LCS program.
FY2009
In FY2009, Congress delayed the implementation of the LCS sea frame unit procurement cost
cap by two years, to ships procured in FY2010 and subsequent years (Section 122 of the FY2009
defense authorization bill [S. 3001/P.L. 110-417 of October 14, 2008]); rescinded $337 million in
FY2008 shipbuilding funds for the LCS program, effectively canceling the funding for the LCS
procured in FY2008 (Section 8042 of the FY2009 defense appropriations bill [Division C of H.R.
2638/P.L. 110-329 of September 30, 2008]); and funded the procurement of two LCSs at a cost of
$1,020 million.

26 The Navy apparently called this ship LCS-5 because the original LCS-5 and LCS-6 were canceled by the Navy
before they were replaced under contract, leaving LCS-4 as last LCS under contract to have been canceled. In spite of
its designation, LCS-5 would have been the third LCS in the restructured LCS program, and was the seventh to have
been funded by Congress.
Congressional Research Service
19

Navy Littoral Combat Ship (LCS) Program

Potential Oversight Issues for Congress
Building LCSs Within Unit Procurement Cost Cap
Although subsequent LCSs are expected to cost substantially less to build than LCSs 1 and 2, one
potential oversight issue for Congress is whether the Navy will be able to build LCSs funded in
FY2010 in complete form (i.e., without having to remove certain components from the ships’
design) within the $460-million unit procurement cost cap. As mentioned earlier (see section
above on “Acquisition Strategy for FY2009 and Subsequent Ships”), the Navy’s delay in
announcing contract awards for the two LCSs funded in FY2009 may have been due in part to the
challenge the Navy faced in coming to agreement with the industry teams on prices for the two
FY2009 ships that would permit the three FY2010 ships to be built within the cost cap.
A related question is whether the Navy will be able to build LCSs funded in FY2011 and
subsequent years in complete form within the $460-million unit procurement cost cap,
particularly since the cap does not include a provision permitting the $460-million figure to be
adjusted for inflation. Observers have noted that cost caps legislated for other Navy shipbuilding
programs have included such a provision.27
Potential issues for Congress include the following:
• Will the Navy be able to build LCSs funded in FY2010 in complete form within
the $460-million cost cap? More specifically, are the contract-award costs for
LCSs 3 and 4 (which the Navy has not released, because they are considered
competition-sensitive in connection with bidding for the FY2010 ships) generally
consistent with being able to build the FY2010 ships in complete form within the
$460-million cost cap?
• Given the lack of a provision in the cost cap for making adjustments over time in
the $460-million figure due to inflation, will the Navy be able to build LCSs
funded in FY2011 and subsequent years in complete form within the $460-
million cost cap? How do the estimated economies of moving down the LCS
production learning curve and building LCSs in larger annual quantities compare
with the potential impact of inflation on the construction costs of future LCSs?
• Will the Navy at some point need to ask Congress to amend the cost cap to
increase the $460-million figure, to permit adjustments for inflation, or both? The
Navy testified in February 2008 that it anticipated asking Congress at some point
to amend the cost cap to permit the cap to be adjusted over time for inflation.28

27 See, for example, Andrea Shalal-Esa, “Navy Unhappy With LCS Bids, Wants Cost Cap Raised,” Reuters, September
9, 2008; Emelie Rutherford, “Defense Authorization Conferees Weighing Changes To LCS Cost Cap,” Defense Daily,
September 22, 2008.
28 Source: transcript of spoken remarks of Allison Stiller at February 27, 2008 hearing on Navy shipbuilding before the
Defense subcommittee of the House Appropriations Committee.
Congressional Research Service
20

Navy Littoral Combat Ship (LCS) Program

Cost Growth on LCS Sea Frames
Potential oversight questions for Congress concerning cost growth on LCS sea frames include the
following:
• Has the Navy taken sufficient action to prevent further growth in LCS sea frame
unit procurement costs?
• How much of the cost increases on LCSs 1 and 2 are attributable to Navy actions
in managing the program? To prime contractor performance? To shipyard
performance? To performance by supplier firms?
• Concurrency in design and construction has long been known as a source of risk
in shipbuilding and other weapon-acquisition programs. Eliminating concurrency
forms part of DOD’s effort to move toward best practices in acquisition. In
retrospect, did the Navy make a good decision in letting its sense of urgency
about the LCS override the known risks of concurrency in design and
construction?
• In light of cost growth on LCS sea frames, where does the LCS program now
stand in relation to the Nunn-McCurdy provision (10 U.S.C. §2433), which
requires certain actions to be taken if the cost of a defense acquisition program
rises above certain thresholds?
• Do the estimated costs of LCSs 1 and 2 reflect systems, components, or materials
provided by vendors at reduced prices as part of an effort by those vendors to
secure a role in the 55-ship LCS program? If so, how much more expensive
might these systems, components, or materials become on later LCSs? Is this a
source of concern regarding the potential for cost growth on follow-on LCSs?
• How might the increase in LCS unit procurement costs affect the number of
LCSs that the Navy can afford to procure each year, and the total number it can
afford to procure over the long run?
• Has the Navy financed cost growth on LCS sea frames by reducing funding for
the procurement of LCS mission packages? For example, is cost growth on LCS
sea frames linked in some way to the reduction in the planned number of LCS
mission packages from an earlier figure of 90 to 110 to the current figure of 64?
If the Navy has financed cost growth on LCS sea frames by reducing funding for
the procurement of LCS mission packages, how might this have affected the
capabilities of the planned 55-ship LCS fleet?
• In light of the cost growth, is the LCS program still cost-effective? For follow-on
LCSs, what is the unit procurement cost above which the Navy would no longer
consider the LCS program cost-effective?
• If Congress had known in 2004, when it was acting on the FY2005 budget that
contained funding to procure LCS-1, that LCS sea frame unit procurement costs
would increase to the degree that they have, how might that have affected
Congress’s views on the question of approving the start of LCS procurement?
Congressional Research Service
21

Navy Littoral Combat Ship (LCS) Program

• How might the increase in LCS unit procurement costs affect the affordability
and executability of the Navy’s overall shipbuilding program?29
• What implications, if any, does the increase in LCS unit procurement costs have
for estimated procurement costs of other new Navy ship classes?30
Total Program Acquisition Cost
Although this CRS report estimates that a 55-ship LCS program with 64 mission packages might
have a total acquisition cost of roughly $29.4 billion, the potential total acquisition cost of the
LCS program is uncertain. Supporters could argue that total program acquisition cost will become
clearer as the Navy works through the details of the program. Critics could argue that a major
acquisition program like the LCS program should not proceed at full pace until its potential total
acquisition costs are better understood.
Acquisition Strategy for LCSs Procured in FY2011 and Beyond
Potential oversight questions for Congress regarding the Navy’s acquisition strategy for the LCSs
procured in FY2011 and subsequent years include the following:
• When does the Navy plan to settle on an acquisition strategy for LCSs to be
procured n FY2011 and subsequent years?
• What are the comparative costs and benefits of keeping both LCS designs in
production versus necking down to a single design?
• Should competition for building LCSs be opened up to shipbuilders that are not
members of either LCS industry team? What are the costs and benefits of this
option compared to having LCSs built only by the current LCS industry teams?
• What are the comparative costs and benefits of maintaining the current
contractor-furnished LCS combat systems vs. shifting to a common, government-
furnished combat system?
• Given the shifts that have occurred over the years in the announced LCS
acquisition strategy, why should Congress have confidence that the acquisition
strategy for these ships will not shift again at some point? How might such shifts
affect Congress’s ability to evaluate and conduct oversight of the LCS program?

29 For a discussion of the potential affordability of the Navy’s overall shipbuilding program, see CRS Report RL32665,
Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress, by Ronald O’Rourke.
30 On this point, CBO testified in March 2008: “The relatively simple design of the LCS and the substantial cost
increases that have occurred in the program suggest that the Navy may also have trouble meeting its cost targets for the
larger, much more complex surface combatants in its shipbuilding plan, such as the DDG-1000 and the CG(X).”
(Statement of Eric J. Labs, Senior Analyst, [on] Current and Projected Navy Shipbuilding Programs, before the
Subcommittee on Seapower and Expeditionary Forces, Committee on Armed Services, U.S. House of Representatives,
March 14, 2008, p. 24.)
Congressional Research Service
22

Navy Littoral Combat Ship (LCS) Program

Technical Risk
Seaframe
Regarding technical risk in developing the LCS seaframe, GAO reported the following in March
2009:
Technology Maturity
Fifteen of 19 critical technologies for the two seaframe designs are fully mature, and 2
technologies are approaching maturity. The overhead launch and retrieval system in the LCS
1 design and the aluminum structure in the LCS 2 design are immature. The Navy identified
the watercraft launch and recovery concept as a major risk to both seaframe designs. This
capability is essential to complete the LCS anti-submarine warfare and mine
countermeasures missions. According to the Navy, industry watercraft launch and recovery
designs are unproven. To itigate risk, the Navy is conducting launch and recovery modeling
and simulation, model basin testing, and experimentation and is encouraging the seaframe
industry teams to adopt similar approaches. Final integration of mission package vehicles
with each seaframe will not occur until post-delivery test and trials—planned first for LCS 1
in 2010 using the mine countermeasures mission package. Any problems detected could
require redesign and costly rework, which could delay the introduction of LCS to the fleet.
Design and Production Maturity
The Navy assesses LCS design stability by monitoring changes to requirements documents,
execution of engineering change proposals, and the completion of contract deliverables
related to drawings, ship specifications, and independent certification of the design.
Construction is monitored using earned value management and through evaluation of
manufacturing hours spent on rework, deficiencies detected and corrected, and the number of
test procedures performed.
The Navy adopted a concurrent design-build strategy for the first two LCS seaframes, which
has proven unsuccessful. Contributing challenges included the implementation of new design
guidelines, delays in major equipment deliveries, and an unwavering focus on achieving
schedule and performance goals. These events drove low levels of outfitting, out-of-sequence
work, and rework—all of which increased construction costs. Also, incomplete designs
during construction led to weight increases for both seaframes. According to the Navy, this
weight growth contributed to a higher than desired center of gravity on LCS 1 that degraded
the stability of the seaframe. In fact, an inclining experiment performed during acceptance
trials showed LCS 1 may not meet Navy stability requirements for the damaged ship
condition. The Navy is taking steps to remove weight and implement stability improvements
for LCS 1, while also incorporating design changes for future seaframes.
Other Program Issues
As part of LCS 1 acceptance trials, the Navy’s Board of Inspection and Survey (INSURV)
identified 21 critical “starred” deficiencies and recommended the Chief of Naval Operations
authorize delivery of LCS 1 after correction or waiver of these deficiencies. According to
Navy officials, only 9 of these deficiencies were corrected prior to delivery. Navy officials
report that transiting the ship away from Marinette, Wisconsin, prior to the winter freeze was
a higher priority than timely correction of starred deficiencies. The Navy intends to correct
remaining deficiencies during planned post-delivery maintenance availabilities. The Navy
Congressional Research Service
23

Navy Littoral Combat Ship (LCS) Program

plans to hold an INSURV review of LCS 2 upon completion of construction and builder’s
trials for that seaframe.
Navy officials report that the earned value management systems in each of the LCS
shipyards do not meet Defense Contract Management Agency requirements for validation.
Thus, the cost and schedule data reported by the prime contractors cannot be considered fully
reliable by the Navy when evaluating contractor cost proposals or negotiating for
construction of follow-on ships.
Program Office Comments
The Navy stated the LCS program is delivering vital capabilities to the fleet and will be a
critical component of the Navy. It noted that LCS 1 was delivered September 18, 2008—6
years and 1 day after the LCS program was established. In fiscal year 2009, the program will
deliver a second ship of a completely different design. According to the Navy, while the
initial cost and schedule objectives were overaggressive—and necessitated a concurrent
design and construction plan—they provided the tension and urgency for these
achievements, and lessons learned will be applied to future shipbuilding programs. In August
2008, INSURV evaluated LCS 1 and found it to be “capable, well-built, and inspection-
ready.” The Navy stated it is leveraging lessons learned from LCS 1 and LCS 2 to ensure
future ship awards provide the right mix of capability and affordability.31
Mission Packages
Regarding technical risk in developing the modular mission packages for the LCS, GAO reported
the following in March 2009:
Technology Maturity
Operation of the MCM, SUW, and ASW packages on the LCS requires a total of 25 critical
technologies, including 13 sensors, 5 weapons, and 7 vehicles. Of these technologies, 17 are
currently mature and 8 are nearing maturity.
The first of 24 MCM packages was delivered in September 2007 and included 7 of 10
planned mission systems. Four systems are not yet mature; two of these are struggling to
reach full maturity. Officials note the Organic Airborne and Surface Influence Sweep is
being redesigned to address corrosion issues and the Rapid Airborne Mine Clearance System
requires design changes to perform in all environmental conditions. An airborne mine
countermeasures system was decertified and its tow cable is being redesigned following the
results of testing with the helicopter. The Navy also decertified the Remote Minehunting
System during testing in 2007 due to reliability issues, and, according to officials, results of a
recent operational assessment are pending. The Navy now plans to deliver the third and
fourth mission packages in fiscal year 2011 and has delayed delivery of the baseline package
until fiscal year 2012.
The first of 24 SUW packages was delivered in July 2008 and included 1 of 2 planned
mission systems. The SUW package includes the fully mature 30mm gun and a variant of the
Army’s Non-Line-of-Sight (NLOS) system (missile and launcher), which is nearing
maturity. The first package consisted of two gun engineering development models, without

31 Government Accountability Office, Defense Acquisitions[:] Assessments of Selected Weapon Programs, GAO-09-
326SP, March 2009, p. 106.
Congressional Research Service
24

Navy Littoral Combat Ship (LCS) Program

the NLOS launcher or missiles. The NLOS design for LCS has not yet been validated.
Integration of the gun with LCS is not complete. A design review for the gun module is
scheduled for October 2009. Delivery of a baseline package has been delayed to fiscal year
2013.
The first of 16 ASW packages was delivered in September 2008 and included 4 of 10
planned mission systems. Three systems remain immature including the Unmanned Surface
Vehicle’s Dipping Sonar, the Remotely Towed Array and the Remotely Towed Array
Source. Failure to develop these technologies as expected could increase reliance on the MH-
60R helicopter. The Navy has delayed delivery of a second ASW package until fiscal year
2011, and delayed baseline capability from fiscal year 2011 to 2013.
Other Program Issues
The development cost of the LCS packages has increased by more than $300 million, or 64
percent since last year. Procurement costs have decreased for MCM, in part because the
delivery of the more expensive baseline capability has been delayed. Reductions in fiscal
year 2008 and 2009 budget requests have slowed mission package procurement to account
for continuing delays in seaframe acquisition. The explanatory statement accompanying
DOD Appropriation Act for Fiscal Year 2009 Congress asked the Navy to develop a plan for
fielding the MCM capability independent of LCS. The program office indicates all packages
are currently scheduled to undergo operational assessments with both LCS seaframe designs,
beginning in June 2010. According to program officials, in September 2008, the Navy
conducted a shore based integration exercise using simulated seaframe mission bays.
Officials note this activity accelerated MCM mission package integration with both
seaframes and reinforced previous crew training.
Program Office Comments
Program officials noted that changes to the program between the 2008 and 2009 president’s
budgets resulted in an apparent increased development cost. Costs for the SUW package
bought in fiscal year 2009 were realigned from procurement to development to support
technical and operational evaluations. In addition, data provided to GAO for last year’s
assessment did not include costs of common equipment that was subsequently distributed
among the MCM and ASW packages. The program office acknowledges technical maturity
challenges for some mission systems and is working closely with mission system program
offices to resolve any issues. The program office is leading a coordinated test approach to
prove mission package capabilities and suitability for fleet delivery. The program office also
provided technical comments that were incorporated as appropriate. 32
Options for Congress
A primary issue for Congress in 2009 is whether to approve, reject, or modify the Navy’s
restructured LCS program as presented in the proposed FY2010 budget.

32 Government Accountability Office, Defense Acquisitions[:] Assessments of Selected Weapon Programs, GAO-09-
326SP, March 2009, p. 108.
Congressional Research Service
25

Navy Littoral Combat Ship (LCS) Program

General Options
Potential options for Congress included but are not limited to the following:
FY2010 budget request. Congress could approve, reject, or modify the Navy’s
FY2010 budget request for the LCS program in areas such as research and
development funding, sea frame procurement, or mission package procurement.
Acquisition Strategy for Follow-On Ships in Program. Congress could
establish terms and conditions for the acquisition strategy for LCSs procured in
FY2011 and subsequent years.
Reporting requirements. Congress could impose new reporting requirements
for the program so as to facilitate congressional oversight on issues such as cost
growth.
Potential for Common Hulls
In General
Some observers, including some Members of Congress, have expressed interest in the idea of
using common hulls for certain Navy and Coast Guard ships, so as to improve economies of scale
in the construction of these ships and thereby reduce their procurement costs. In earlier years, this
interest focused on using a common hull for the LCS and the Offshore Patrol Cutter (OPC), a
cutter displacing roughly 3,000 tons that is to be procured under the Coast Guard’s Deepwater
acquisition program.33 More recently, this interest has focused on using a common hull for the
LCS and the National Security Cutter (NSC), a cutter displacing about 4,300 tons that is also
being acquired under the Deepwater program.
Reported Proposal to Build Variant of NSC for Navy
In January 2008, it was reported that Northrop Grumman, the builder of the NSC, had submitted
an unsolicited proposal to the Navy to build a version of the NSC for the Navy as a complement
to, rather than a replacement for, the LCS.
January 14, 2008, Press Report
A press report dated January 14, 2008, stated:
The U.S. Navy is stumbling to build the ship it wants—the Littoral Combat Ship (LCS)—so
shipbuilder Northrop Grumman is urging the service to turn to a ship it can get sooner and
cheaper: a patrol frigate version of the Coast Guard’s National Security Cutter (NSC).
“We have listened to what the Navy has said—to be more efficient, be innovative and
produce affordable and capable ships,” said Phil Teel, president of Northrop’s Ship Systems

33 For more on the Deepwater program, see CRS Report RL33753, Coast Guard Deepwater Acquisition Programs:
Background, Oversight Issues, and Options for Congress
, by Ronald O’Rourke.
Congressional Research Service
26

Navy Littoral Combat Ship (LCS) Program

sector. “The patrol frigate is a response to that, and to the Navy’s new National Maritime
Strategy.”
Northrop’s analysts have studied remarks and themes oft repeated by senior Navy leaders
and concluded a de facto requirement exists for a frigate-size ship capable of handling a
range of low- and mid-intensity missions. Those missions, said Eric Womble, head of Ship
Systems’ Advanced Capabilities Group, are detailed in the Navy’s new Maritime Strategy
and include forward presence, deterrence, sea control, maritime security, humanitarian
assistance and disaster response.
“You don’t want a high-end Aegis ship to handle those missions,” Womble said, “you want
something cheaper and smaller.”
The National Security Cutter (NSC) as configured for the Coast Guard could easily handle
those roles, Womble said.
The first NSC, the Bertholf, successfully carried out its initial trials in early December and
will be commissioned this year by the Coast Guard. Womble said a Navy version would
avoid the first-of-class issues that have plagued numerous Navy programs, including both
designs being built for the LCS competition.
Northrop in late December began briefing select Navy leaders on its unsolicited proposal.
The company is taking pains to avoid presenting the ship as an LCS alternative, instead
calling it an LCS “complement,” which is being built under a competition between Lockheed
Martin and General Dynamics.
Key features of Northrop’s concept are:
—The ship is based on a proven design already under construction.
—The NSC’s weapons, sensors and systems already have a high degree of commonality with
Navy systems, increasing affordability.
—While the NSC is 15 knots slower than the 45-knot LCS, the cutter can stay at sea up to
two months, much longer than the LCS.
The report also stated:
Northrop is claiming it can deliver the first ship at the end of 2012 at an average cost of less
than $400 million per ship, exclusive of government-furnished equipment, in fiscal 2007
dollars. That’s close to the $403 million contract cost of the third NSC, which incorporates
all current design upgrades.
A major element of Northrop’s proposal, Womble said, is that the Navy should make no
changes to the current Block 0 design. “That’s the only way we can deliver the ship at this
price.”
The design, however, has plenty of room for upgrades, Womble claimed, and Northrop is
proposing future upgrades be handled in groups, or blocks, of ships, rather than modifying
individual ones. Those upgrades could include non-line-of-sight missiles, SeaRAM missile
launchers and more capabilities to handle unmanned systems. The design even has room for
an LCS-like reconfigurable mission area under the flight deck, he claimed.
Congressional Research Service
27

Navy Littoral Combat Ship (LCS) Program

Northrop admits the ships are deficient in one significant Navy requirement: full
compatibility with the Naval Vessel Rules (NVR), essentially building codes developed by
the Naval Sea Systems Command and the American Bureau of Shipping. The belated
application of the NVR to both LCS designs was a major factor in the cost growth on those
ships.
Most of the NSC design already is NVR-compatible, Womble said, but upgrading the entire
design to NVR standards would involve a fundamental redesign and eliminate the proposal’s
cost and construction time attributes.
“We’d need a waiver [from the NVR rules] to make this proposal work,” he said.
The report also stated:
Navy Response: ‘No Requirement’
The official response from the Navy to Northrop’s proposal so far is unenthusiastic.
“There is currently no requirement for such a combatant,” said Lt. Clay Doss, a Navy
spokesman at the Pentagon. The Navy’s other surface ship programs, he said, “address
specific requirements.”
Doss did note that “the Navy and Coast Guard have considered a common platform for the
LCS and the Coast Guard’s National Security Cutter. However, due to the unique mission
requirements of each service, a common hull is not a likely course of action.”
Problems with the LCS have caused some observers to predict the program’s demise, but the
Navy “is completely committed to the LCS program,” Doss said. “We need 55 Littoral
Combat Ships sooner rather than later, and we need them now to fulfill critical, urgent war-
fighting gaps.”
Northrop however, is not alone in proposing the NSC as an LCS alternative. Coast Guard
Capt. James Howe, writing in the current issue of the U.S. Naval Institute’s Proceedings
magazine, is urging Navy leaders to consider the NSC.
“I think the Navy should look at it,” he said Jan. 10. “Northrop is building a naval combatant
here. It has standard U.S. Navy weapon systems as part of its packages. Its communications
are interoperable. It can handle underway replenishment. If there’s a possibility it could be a
cost saver or a good deal for the Navy, it needs to be explored.”
Howe, who said he was unaware of Northrop’s patrol frigate proposal, agreed the NSC is
capable of further enhancements. “There’s a lot of space on that ship,” he said.
‘Potential Game-changer’
Northrop likely is facing an uphill battle with its patrol frigate, as the Navy culturally prefers
to dictate requirements based on its own analysis.
But the Navy is having trouble defending the affordability of its shipbuilding plan to
Congress and bringing programs in on budget. One congressional source noted the service
“can’t admit their plan won’t work.” An unsolicited proposal, the source said, “opens the
way for someone else to come up with a potential game-changer.”
Northrop’s plan, the source said, may be an unexpected opportunity.
Congressional Research Service
28

Navy Littoral Combat Ship (LCS) Program

“Northrop is listening to the people who have been criticizing the Navy’s shipbuilding plan,”
the source said. “They’ve gotten a sense that maybe the Navy is looking for a solution, and
the Navy can’t produce a solution because it might be too embarrassing.”
One more aspect that could be at work in the Northrop proposal: “I think there’s something
coy going on here,” the source said. “They may be promoting this as an LCS complement,
but their idea might be part of a strategic plan to replace the LCS.”34
January 17, 2008, Press Report
A press report dated January 17, 2008, stated:
Northrop Grumman Corp said on Wednesday [January 16, 2008, that] a proposal to turn its
418-foot Coast Guard cutter into a new class of Navy frigates is sparking some interest
among U.S. Navy officials and lawmakers.
Northrop is offering the Navy a fixed price for the new ship of under $400 million and could
deliver the first one as early as 2012 to help out with maritime security, humanitarian aid and
disaster response, among other things, said Eric Womble, vice president of Northrop
Grumman Ship Systems.
So far, the officials briefed have found Northrop’s offer “intriguing,” Womble told Reuters
in an interview. “They like the fact that we’re putting an option on the table. No one has told
us, ‘Go away, don’t come back, we don’t want to hear this’,” Womble said.
At the same time, the Navy says it remains committed to another class of smaller, more agile
ships—the Littoral Combat Ships (LCS) being built by Lockheed Martin Corp (LMT.N:
Quote, Profile, Research) and General Dynamics Corp (GD.N: Quote, Profile, Research)—
amid huge cost overruns.
“There currently is no requirement for a frigate,” Navy spokesman Lt. Clay Doss said. He
said the Navy and Coast Guard had discussed a common hull during the initial stage of the
LCS competition, but agreed that was “not a likely course of action due to the unique
mission capabilities.”
For now, he said the Navy was proceeding as quickly as it could with the 55-ship LCS
program as well as design work on a new DDG-1000 destroyer, and a planned cruiser, CG-
X....
The report also stated:
Virginia-based defense consultant Jim McAleese said the fixed-price offer could be good
news for the Navy, which has typically borne the risk of cost-based shipbuilding contracts.
“That is a potential catalyst that could have a huge impact on the way the Navy buys small-
and mid-sized surface combatants,” McAleese said.
Northrop says its new Coast Guard cutter also experienced some cost growth, but says that
was mainly due to requirements added after the Sept. 11, 2001, hijacking attacks. The first of

34 Christopher P. Cavas, “Northrop Offers NSC-Based Vessel To Fill LCS Delays,” Defense News, January 14, 2008.
Congressional Research Service
29

Navy Littoral Combat Ship (LCS) Program

the new ships is due to be delivered to the Coast Guard in March, followed by one ship
annually over the next few years.
Northrop said it could offer the Navy a fixed price on the frigate because design work on the
ships is already largely completed. Its price excludes government-furnished equipment that
would still have to be put on board.
“We’re not advocating an LCS replacement,” said spokesman Randy Belote. “But after
listening to the Navy leadership and studying the new maritime strategy, we think we can get
hulls and capabilities into the water at a much faster pace.”
Womble said Northrop analysts and an outside consultant studied the Navy’s needs and
concluded the Navy could use another ship that can operate in shallow water, be forward
deployed, has the range and endurance to operate independently, and can work with U.S.
allies, if needed.
The press report also stated:
The proposed ship can be deployed for 60 days without new supplies, has a range of 12,000
nautical miles, and can travel at 29 knots, fast enough to keep up with other warships. That
compares to 20 days and a range of 3,500 miles for LCS.
Northrop began sharing a PowerPoint presentation about the proposal with Navy officials
and lawmakers at the end of December, and has already met with several senior officials,
including Chief of Naval Operations Adm. Gary Roughead.
It could deliver the first frigate by 2012, if the Navy was able to add $75 million for long
lead procurement items into the fiscal 2009 budget proposal to be sent to Congress next
month, Northrop said.
The frigate is about 75 percent compliant with special requirements that apply only to U.S.
Navy ships. Northrop said it believed it could qualify for waivers on the remaining 25
percent because similar waivers were granted in the past.35
Legislative Activity for FY2010
The Navy’s proposed FY2010 budget, which was submitted to Congress in early May, requests
$1,380 million for the procurement of three more LCSs. The Navy’s proposed FY2010 budget
also requests $360.5 million in research and development funding for the LCS program.
On March 10, 2009, the Seapower and Expeditionary Forces subcommittee of the House Armed
Services Committee held a hearing to review the status of the LCS program. (See Appendix B
for the full text of the Navy’s prepared statement for the hearing.)


35 Andrea Shalal-Esa, “Northrop Offers US Navy New Ship For Fixed Price,” Reuters, January 17, 2008.
Congressional Research Service
30

Navy Littoral Combat Ship (LCS) Program

Appendix A. Legislative Activity for FY2009
Table A-1 summarizes congressional action on the Navy’s FY2009 funding request for the LCS
program.
Table A-1. Congressional Action on FY2009 Funding Request
(millions of dollars; figures rounded to nearest tenth of a million)
Authorization
Appropriation
Budget
accounta Request HASC SASC Comp.a HAC/Db SAC/Dc Comp.a
RDT&EN 371.0
371.0
371.0
371.0
n/a
n/a
369.3
SCN 920.0
840.0
797.0
920.0
n/a
1090.0
1020.0
APN 55.3
55.3
55.3
55.3
n/a
n/a
50.3
WPN 2.8
2.8
2.8
2.8
n/a
n/a
2.8
OPN 131.2
81.2
131.2
106.2
n/a
n/a
73.9
Sources: Prepared by CRS based on FY2009 Navy budget submission, committee reports on FY2009 defense
authorization bills, joint explanatory statement and associated funding tables on compromise version of FY2009
defense authorization bill, press releases on the HAC/D and SAC/D markups of the FY2009 defense
appropriation bills, and explanatory statement on compromise version of FY2009 defense appropriation bill.
Notes: HASC is House Armed Services Committee; SASC is Senate Armed Services Committee, HAC/D is
Defense subcommittee of House Appropriations Committee; SAC/D is Defense subcommittee of Senate
Appropriations Committee; Comp. is compromise version of bill. n/a = not available.
a. In lieu of conference reports on the FY20009 defense authorization and appropriation bills, there were
compromise versions of the two bills, each accompanied by an explanatory statement intended to serve the
same general function as a conference report.
b. A House committee report was not filed. A July 30, 2008, press release from Representative John Murtha,
chairman of the Defense subcommittee of the HAC, summarized the subcommittee’s markup that day of
the FY2009 defense appropriation bill. The press release did not mention the LCS program.
c. A Senate committee report was not filed. On September 10, 2008, the Senate Appropriations Committee
issued a press release summarizing the markup that day by the committee’s Defense subcommittee of the
FY2009 defense appropriations bill. The press release stated, in its section on procurement funding for
shipbuilding, that the subcommittee “Adds $170 million for the Littoral Combat Ship (LCS).”
FY2009 Defense Authorization Bill (H.R. 5658/S. 3001/P.L. 110-417)
House
Section 123 of H.R. 5658 as reported by the House Armed Services Committee would amend the
cost cap on the LCS program, which was previously amended by Section 125 of the FY2008
defense authorization act (H.R. 4986/P.L. 110-181 of January 28, 2008). As described by the
committee, Section 123:
would amend section 124 of the National Defense Authorization Act for Fiscal Year 2006
(P.L. 109-163) as amended by section 125 of the John Warner National Defense
Authorization Act for Fiscal Year 2007 (P.L. 109-364) by allowing costs associated with
economic inflation to exceed the cost cap of $460.0 million per vessel, provided that the
increase for economic inflation does not exceed $10.0 million per vessel. The provision
Congressional Research Service
31

Navy Littoral Combat Ship (LCS) Program

would also allow costs associated with the introduction of new technology, not fielded on the
first two ships of the class, provided that the insertion of new technology would reduce life-
cycle cost of the vessel, or the new technology is required to meet an emergent warfighting
threat. (Page 141)
Section 123 states:
SEC. 123. LITTORAL COMBAT SHIP (LCS) PROGRAM.
Section 124 of the National Defense Authorization Act for Fiscal Year 2006 (P.L. 109-163;
119 Stat. 3157), as amended by section 125 of the National Defense Authorization Act for
Fiscal Year 2008 (P.L. 110-181; 122 Stat. 29), is amended in subsection (d) by adding at the
end the following:
‘(3) The amounts of increases or decreases in costs attributable to economic inflation after
September 30, 2007. However, in the case of a vessel the procurement of which is funded
from amounts appropriated pursuant to an authorization of appropriations or otherwise made
available for fiscal year 2008 or 2009, the amount of such an increase for such a vessel may
not exceed $10,000,000.
‘(4) The amounts of increases or decreases in costs of that vessel that are attributable to
insertion of new technology into that vessel, as compared to the technology built into the first
and second vessels, respectively, of the Littoral Combat Ship (LCS) class of vessels.
However, the Secretary of the Navy may make an adjustment under this paragraph only if—
‘(A) the Secretary of the Navy determines, and certifies to the congressional defense
committees, that insertion of the new technology would lower the life-cycle cost of the
vessel; or
‘(B) (i) the Secretary of the Navy determines, and certifies to the congressional defense
committees, that insertion of the new technology is required to meet an emerging threat; and
‘(ii) the Secretary of Defense certifies to those committees that such threat poses grave harm
to national security.’
The House Armed Services Committee, in its report (H.Rept. 110-652 of May 16, 2008) on H.R.
5658, approved the Navy’s request for procurement of two LCSs in FY2009 but reduced the
Navy’s FY2009 procurement funding request for the LCS program by $80 million. (Page 79, line
013)36 The report recommended reducing the Navy’s FY2009 funding request for LCS mission
modules by $50 million. (Page 87, line 029)
The report states that “The committee disagrees with the submitted Future Years Defense Plan
and budget request” for several reasons, including “the failure to deliver a coherent strategy for
Littoral Combat Ship acquisition.” (Pages 82 and 83) The report also states that “The committee
expects the budget submission for fiscal year 2010 to contain” several things, including “a
comprehensive decision on the acquisition plan for surface combatants including the plan for the
Littoral Combat Ship class.” (Page 83) The report does not discuss the recommended $80-million
reduction in ship procurement funding, but the committee’s summary of its markup states that

36 The report’s table on page 79 states that the committee recommended procurement of one LCS rather than two in
FY2009, but this appears to be a typo, as the report does not elsewhere mention reducing the procurement request from
two ships to one, and the committee’s summary of its markup states that it approved procurement of two LCSs.
Congressional Research Service
32

Navy Littoral Combat Ship (LCS) Program

“reduction of $80 million [is] due to the availability of material previously procured for
construction of ships that were subsequently canceled by the Navy.”37 The committee’s report
does not discuss the recommended $50-million reduction in procurement funding for LCS
mission modules.
Senate
The Senate Armed Services Committee, in its report (S.Rept. 110-335 of May 12, 2008) on S.
3001, approved the Navy’s request for procurement of two LCSs in FY2009 but reduced the
Navy’s FY2009 procurement funding request for the LCS program by $123 million, which the
repot states would “Fully fund two ships to [the LCS program] cost cap in FY[20]09, reflecting
government furnished material (GFM) from cancelled ships.” (Page 58, line 013) Regarding
funding for ship procurement, the report stated:
The first ship (LCS-1) was scheduled to deliver in late 2006. The Navy is now estimating
that the first ship will deliver sometime in late 2008. The LCS-1 contractor team had barely
started on their second ship (LCS-3) when the program ran into major cost problems earlier
last year. The Navy then issued a stop work order on LCS-3 in order to reduce expenditures
and limit further cost exposure on the program while it separately re-evaluated program cost
estimates.
The Navy entered into negotiations with the LCS-1 team to sign up to a fixed price contract
on the two ships or face outright cancellation on the second ship. The Navy terminated the
contract for LCS-3 for the convenience of the government. As a result of that termination,
the government will take delivery of some sizeable inventory of equipment and material for
the cancelled LCS-3.
The second contractor team had a contract to build two LCS vessels of another design (LCS-
2 and LCS-4). The Navy awarded this contract almost a year later, so LCS-2 was roughly 1
year behind the LCS-1. The Navy went ahead with activities leading to the start of
construction on LCS-4, despite internal warnings that the second contractor would face
similar cost and schedule problems as those faced by the first contractor. Late last year, the
same poor performance and fixed priced negotiation scenario also played out on the LCS-2
and LCS-4. This led the Navy to also cancel the LCS-4, again with the result that the
government will take delivery of some sizeable inventory of equipment and material for the
cancelled LCS-4.
Section 125 of the National Defense Authorization Act for Fiscal Year 2008 (P.L. 110-181)
places a cost ceiling on LCS contracts of $460.0 million per ship, a dollar value provided by
the Navy. Congress also authorized and appropriated one LCS in fiscal year 2008.
The Navy has not awarded the one LCS approved in the fiscal year 2008 budget. The Navy’s
acquisition strategy, which has been extremely fluid, is to award this ship, plus the two ships
from the fiscal year 2009 program later this calendar year. The Navy’s intent is that the
award be a limited competition, with each yard assured of being awarded at least one ship.
The total funding provided in fiscal year 2007 and prior budgets for the six previously
authorized Littoral Combat Ships totals $1,639.0 million. The Navy has determined that
$1,162.0 million of these funds is required for construction, test, trials, outfitting, and post-
delivery of LCS-1 and LCS-2. The remaining $477.0 million funding is allocated against the

37 House Armed Services Committee summary of H.R. 5658, page 13.
Congressional Research Service
33

Navy Littoral Combat Ship (LCS) Program

terminated ships, LCS-3 and LCS-4, including material purchased for those ships prior to
termination. Within the remaining funding allocated against the terminated ships, sufficient
funding should also be available for LCS class design to ensure that the follow-on ships
commence production with “clean,” producible drawings and planning products. Presuming
the Navy maintains stable design requirements, the availability of clean drawings and
planning products should ensure healthy learning curve performance in production. This
learning curve performance, in conjunction with material purchased in prior years (from the
terminated ships), should more than offset the effects of one year’s escalation for ships
purchased in 2009.
The fiscal year 2008 budget has resources sufficient to award one LCS within the cost cap to
either shipyard, when taking into account the inventory of equipment and material available
from that shipyard’s cancelled ship. The Navy would provide this equipment and material to
the shipyard that wins the fiscal year 2008 ship as government furnished material (GFM).
The value of this GFM would count against the cost cap.
Under their plan, the Navy would also award at least one of the two ships in the fiscal year
2009 budget to the other shipyard. The Navy would likewise provide the GFM from that
shipyard’s cancelled ship to offset the cost of that one ship. Similarly, the value of this GFM
would count against the cost cap on this ship as well.
The fiscal year 2009 budget request, however, would fund both ships to the full cost cap and
not take the value of this GFM for the second cancelled ship into account. This means that
the budget request of $920.0 million includes more funding than can be placed on contract
without violating the cost cap, unless the Navy were to withhold the GFM for the second
shipyard.
The committee believes that the Navy should apply the GFM to both contractors’ vessels as
soon as a second ship is purchased from either yard. Therefore, the committee recommends a
reduction of $123.0 million to take that GFM into account. This will leave sufficient funds in
the Navy’s hands to award two ships in fiscal year 2009, with both ships fully funded to the
congressional cost cap of $460.0 million. (Pages 77-78)
Regarding LCS mission packages, the report states:
The Navy has embarked on a program to develop modular counter-mine, anti-surface, and
anti-submarine warfare systems, referred to as mission packages, to be deployed on the
Littoral Combat Ship (LCS). The Navy envisions fielding 60 mission packages, which Navy
commanders could interchange across the 55-ship LCS class as operational requirements
dictate. This total system capability of the LCS program has been identified by the Chief of
Naval Operations as a top priority for operations in the littorals. The committee similarly
views the capability provided by a family of LCS mission packages as a key component of
the maritime strategy. The committee is, therefore, concerned by the delays to mission
package initial operational capability, deployment, and full operational capability caused by
delays to the LCS construction program.
The Navy has designed the LCS mission packages with modularity and with open
architecture. Having done this, the Navy should be able to deploy this capability on other
ship classes. Such an expanded concept of operations would provide opportunities to employ
mission packages more rapidly, and against threats and in operational scenarios perhaps not
envisioned today.
Therefore, the committee directs the Secretary of the Navy to evaluate alternatives for
employing LCS mission packages on other ship classes of the battle force, and to provide a
report on his findings to the congressional defense committees with submission of the 2010
Congressional Research Service
34

Navy Littoral Combat Ship (LCS) Program

budget request. The report shall outline the feasibility, cost, and impacts associated with
integrating mine countermeasures and anti-submarine mission packages on other surface
combatant and amphibious force ship classes, and provide an assessment of the operational
utility afforded by being able to deploy mission packages across the broader battle force.
(Page 126)
Compromise
In lieu of a conference report, there was compromise version of S. 3001 that was accompanied by
a joint explanatory statement. Section 4 of S. 3001 states that the joint explanatory statement
“shall have the same effect with respect to the implementation of this Act as if it were a joint
explanatory statement of a committee of conference.”
Section 122 of S. 3001 amends the unit procurement cost cap on LCS sea frames so as to delay
the implementation of the cost cap to ships procured in FY2010 and subsequent years. (The cost
cap previously was to be applied to ships procured in FY2008 and subsequent years.)
The joint explanatory statement for S. 3001 states:
The agreement would authorize the budget request of $920.0 million for two LCS vessels.
Elsewhere in the agreement, we recommend a provision that would delay implementation of
the cost cap for the LCS program until fiscal year 2010. We note that the Navy has taken
delivery of the first ship of this class and anticipates taking delivery of the second by the end
of the calendar year. While these are significant milestones, we remain concerned that the
Navy has not taken sufficient actions to control costs for follow-on vessels. Moreover, in
repeated testimony before the Committees on Armed Services of the Senate and the House of
Representatives, we have been told that a primary benefit of utilizing mid-tier shipyards is
that such yards can easily balance commercial and government workload to ensure that the
Navy does not have to pay overhead costs to maintain capability during periods of limited
government funding. Nevertheless, the Navy has requested, for the second year in a row, an
adjustment to the cost cap in order to preserve industrial capability because the Navy is
unable to purchase a ship at or below its budgetary estimate and lacks a coherent acquisition
strategy for the program. We strongly encourage the Navy to take steps to procure follow-on
vessels with required warfighting capability, while prioritizing the aggressive management
of cost and the most efficient utilization of the industrial base. Likewise, we direct the
Secretary to develop and submit to the Congress a long-term acquisition strategy for LCS
vessels with the submission of the fiscal year 2010 budget request.
The compromise recommended reducing the OPN request for the LCS program to $106.15
million—a reduction of $25.091 million from the request.
FY2009 Defense Appropriations Bill (H.R. 2638/P.L. 110-329)
House
A House committee report was not filed. A July 30, 2008, press release from Representative John
Murtha, chairman of the Defense subcommittee of the HAC, summarized the subcommittee’s
Congressional Research Service
35

Navy Littoral Combat Ship (LCS) Program

markup that day of the FY2009 defense appropriations bill.38 The press release did not mention
the LCS program.
Senate
A Senate committee report was not filed. On September 10, 2008, the Senate Appropriations
Committee issued a press release summarizing the markup that day by the committee’s Defense
subcommittee of the FY2009 defense appropriations bill. The press release stated, in its section
on procurement funding for shipbuilding, that the subcommittee “adds $170 million for the
Littoral Combat Ship (LCS).”39
Compromise
In lieu of a conference report, there was compromise version of the FY2009 defense
appropriations bill that was incorporated as Division C of H.R. 2638. (H.R. 2638, which was
introduced as the FY2008 Department of Homeland Security appropriations bill, was later
amended to become an FY2009 consolidated appropriations bill that included, among other
things, the FY2009 defense appropriations bill.) The compromise version of H.R. 2638 was
accompanied by an explanatory statement. Section 4 of H.R. 2638 states that the explanatory
statement “shall have the same effect with respect to the allocation of funds and implementation
of this Act as if it were a joint explanatory statement of a committee of conference.”
The explanatory statement provides $1,020 million for procurement of two LCSs in FY2009.
Section 8042 of the bill rescinds $337 million in FY2008 shipbuilding funds for the LCS
program, effectively canceling the LCS procured in FY2008. The explanatory statement states:
The bill includes $1,020,000,000 for [procurement of] two LCS seaframes [in FY2009] and a
rescission of $337,000,000 in fiscal year 2008 LCS [shipbuilding] funding. Additionally,
funds and material from fiscal year 2006 can be used to supplement the fiscal year 2009 LCS
program. Due to industrial base concerns, the Navy is directed to make contract awards for
the two fiscal year 2009 LCS seaframes as soon as practicable.
The explanatory statement provides $369.3 million in research and development funding for the
LCS program—a reduction of $1.7 million from the request. The net reduction of $1.7 million
consists of a reduction of $12 million for “Combat System C4I Development,” an increase of
$2.0 million for “Autonomous Acoustic Array Advanced Tubular Solid Oxide Fuel Cell,” an
increase of $4.5 million for “LCS Common Mission Package Training Environment,” and an
increase of $3.8 million for “Alternative Use of Mine Warfare Modules.”
The explanatory statement provides $50.3 million in Aircraft Procurement, Navy (APN) funding
for the LCS program—a reduction of $5 million from the request.
The explanatory statement provides $73.902 million in Other Procurement, Navy (OPN) funding
for the LCS program—a reduction of $57.339 million from the request. The reduction consists of

38 September 10, 2008, press release from Senate Appropriations Committee entitled “Senate Defense Appropriations
Subcommittee Approves Fiscal Year 2009 Defense Appropriations Bill.”
39 Source: September 10, 2008, press release from Senate Appropriations Committee entitled “Senate Defense
Appropriations Subcommittee Approves Fiscal Year 2009 Defense Appropriations Bill,” p. 2.
Congressional Research Service
36

Navy Littoral Combat Ship (LCS) Program

a reduction of $9.291 million for “Mission Package Integrator,” and a reduction of $48.048
million for “Delay One Mission Module.”
Congressional Research Service
37

Navy Littoral Combat Ship (LCS) Program

Appendix B. March 2009 Navy Testimony on LCS
Program

On March 10, 2009, the Seapower and Expeditionary Forces subcommittee of the House Armed
Services Committee held a hearing to review the status of the LCS program. Reprinted below is
the full text of the Navy’s prepared statement for the hearing. 40
INTRODUCTION / REQUIREMENT
Mr. Chairman, distinguished members of the Subcommittee, thank you for the opportunity to
appear before you today to address the Navy’s Littoral Combat Ship (LCS) program. We
thank the Committee for its continued support and active interest in Navy shipbuilding
programs.
The Navy remains committed to the LCS program. LCS fills warfighting gaps in support of
maintaining dominance in the littorals and strategic choke points around the world. The
Navy remains committed to procuring 55 LCSs, and is aggressively pursuing cost reduction
measures to ensure delivery of future ships on a schedule that affordably paces evolving
threats. This will be accomplished by matching required capabilities, to a recurring review of
warfighting requirements through applying lessons learned from the construction and test
and evaluation periods of seaframes and mission packages.
The LCS program is structured in flights of seaframes and spirals of mission packages. This
allows the relatively rapid change in technologies and threats associated with the modular
mission packages to be continuously improved through incremental upgrades without major
design impacts to seaframes. The result is a program that minimizes the risks of a highly
interdependent system of systems by decoupling seaframe procurement from mission
package procurement. This allows continuous cost efficient delivery of state-of-the-art
capability to the warfighter via new mission package upgrades.
The LCS program capabilities address specific and validated capability gaps in Mine
Countermeasures (MCM), Surface Warfare (SUW) and Anti-Submarine Warfare (ASW).
The Concept of Operations and design specifications for LCS were developed to meet these
gaps with focused mission packages that deploy manned and unmanned vehicles to execute a
variety of missions. LCS’s inherent characteristics (speed, agility, shallow draft, payload
capacity, reconfigurable mission spaces, air/water craft capabilities) combined with its core
Command, Control, Communications, Computers and Intelligence (C4I), sensors, and
weapons systems, make it an ideal platform for hosting additional Maritime Strategy mission
areas, such as Irregular Warfare and Maritime Security Operations.
The Navy, as part of its annual review of its shipbuilding program, expects there will be
sufficient force structure with our existing frigates and mine warfare ships until LCS delivers
in quantity to meet overarching deployment requirements.

40 Statement of RADM Victor Guillory, U.S. Navy Director of Surface Warfare, and RADM William E. Landay, III,
Program Executive Officer Ships, and Ms. E. Anne Sandel, Program Executive Officer Littoral and Mine Warfare,
before the Subcommittee on Seapower and Expeditionary Forces of the House Armed Services Committee [hearing] on
the Current Status of the Littoral Combat Ship Program, March 10, 2009. 11 pp. (including the cover as page 1).
Congressional Research Service
38

Navy Littoral Combat Ship (LCS) Program

Legacy mine warfare ships and frigates are planned to be phased out gradually. These
decommissionings will be balanced with LCS mission package and seaframe deliveries to
mitigate warfare risks.
LCS 1, USS FREEDOM, was delivered to the Fleet on September 18, 2008—six years and
one day after the program was established. LCS 2, the future USS INDEPENDENCE, was
christened in Mobile, AL, on October 4, 2008. Later this year the program will have
delivered a second ship of a completely different design.
While the initial cost and schedule objectives for the program were overaggressive, they did
provide the tension and urgency for these achievements. Although the concurrent design and
construction of LCS revealed challenges for meeting the original cost and schedule
objectives, the Navy will apply lessons learned to this program as well as other shipbuilding
programs.
At the Subcommittee’s request, the Navy is pleased today to discuss an overview of the
history of the LCS program, the current status of LCS 1 and LCS 2, and the future
acquisition strategy for the LCS program.
BACKGROUND
The LCS acquisition strategy, approved in May 2004, was based on the tenets of modular
and open system architecture, Cost-As-an-Independent-Variable design process, a rapid
construction cycle and continuous competition at all levels of the program. The Navy
awarded contracts for construction of the first four LCS seaframes, with Lockheed Martin
(LM) and General Dynamics (GD) awarded two ships each. Fabrication of LCS 1, the first
LM ship, began in February 2005 and the ships delivered in September 2008. Fabrication on
LCS 2 , the first GD ship, began in November 2005 and this ship will deliver this year. LCS
3 and 4 options were exercised in June and December 2006, respectively.
Cost growth on both variants resulted in a detailed assessment of program cost and structure.
The Navy sought to restructure the contracts for LCS 3 and 4 to fixed-price incentive terms
to more equitably balance cost and risk, but could not come to terms and conditions that
were acceptable to both parties. On April 12, 2007, the Navy terminated construction of LCS
3 for convenience under the Termination clause of the contract. On November 1, 2007, the
Navy terminated construction of LCS 4 for convenience under the Termination clause of the
contract. Based on program restructuring, the Navy requested and received congressional
approval to reprogram FY 2007 shipbuilding appropriations to fund cost increases on LCS 1
and 2.
At the direction of Assistant Secretary of the Navy for Research, Development, and
Acquisition (ASN(RDA)), the LCS program underwent a thorough independent assessment
to review the cause of the cost growth and evaluate the way forward.
The results of that assessment identified a number of factors key to the program’s poor
performance. The Navy has actively addressed those key findings in the program as it
operates today:
— The design for both ships is mature and we are incorporating revisions to specific areas
based on the lessons learned from the construction of the initial ships, proposed production
improvements, acceptance inspections and the early stages of the post delivery testing
period. Those revisions will be in place for the start of construction of the FY 2009 ships.

Congressional Research Service
39

Navy Littoral Combat Ship (LCS) Program

— The Navy has increased the staff assigned in the program office and at the shipyards to
monitor performance. The program office staff has grown from eight to 20 civilian
personnel, focusing on critical production, acquisition, and financial management specialties.
An additional 12 billets have been assigned as the two lead ships complete delivery and post
delivery milestones this year and more ships are placed under contract. Military staff has
increased from three to five assigned. Officers with new ship construction experience were
assigned to the program manager and production manager positions.
— The Supervisors of Shipbuilding doubled the staff at each LCS shipbuilder. Focusing
resources to the waterfront, the program office works closely with the Supervisors to sustain
a daily drumbeat in monitoring production progress on these lead ships, identifying and
monitoring key metrics that maintain progress to key events.
— To improve technical decision making and reduce the time to resolve technical issues,
especially as related to the application of Naval Vessel Rules, the program office and the
Naval Sea Systems Command Chief Engineer have placed senior managers and technical
authorities on the waterfront.
— New performance baselines were implemented for each contract to help monitor and
control cost, with contracting incentive structures to support improved progress. We continue
to work closely with the industry teams to improve their performance and Earned Value
Management System measurement and reporting capabilities.
— The FY 2009 and FY 2010 contracts will be fixed-price contracts to ensure cost and
schedule adherence remain a primary focus of both the industry and the government program
teams.
AFFORDABILITY
The Navy has implemented a comprehensive cost-reduction program for LCS. Taking
advantage of lessons from other shipbuilding programs’ affordability initiatives such as the
DDG 51 value engineering program, the T-AKE “take cost” program and the Virginia-class
cost-reduction initiative, this ongoing effort seeks to reduce acquisition cost and total
ownership cost through continuous assessment of operational and technical requirements,
improvement of production processes, and implementation of acquisition strategies that will
lead to stable production and improved purchasing leverage. Examples of areas under review
by this program include:
— A joint team of industry, government and independent experts have conducted a “stem-
to-stern” inspection of each ship to identify areas of inefficiency or where alternative
production methods can improve production efficiencies.
— The Navy implemented a Total Ownership Cost (TOC) reduction review jointly
overseen by the ASN(RDA) and Vice Chief Naval Operations to look for improvements in
total lifecycle costs.
— The Navy has initiated a second study to look at the Total Ownership Cost return on
investment of a common combat system. The initial study conducted in 2007 did not support
a payback sufficient to support the upfront integration and additional procurement costs. The
Navy’s development of its objective architecture for combat systems provided a different set
of assumptions to be considered for this new study.

Congressional Research Service
40

Navy Littoral Combat Ship (LCS) Program

— Finally, infrastructure improvements are either under review or in progress at both yards
that will improve production efficiencies and reduce costs.
CURRENT STATUS OF LCS 1 AND LCS 2
USS FREEDOM (LCS 1)
USS FREEDOM was built by the Lockheed Martin-led team at the Marinette Marine
shipyard in Marinette, WI, and was commissioned on November 8, 2008. Due to restrictions
on some testing in the Great Lakes, acceptance testing was broken into two phases.
Acceptance Trial 1 (AT) evaluated the ship, propulsion, navigation and some
communications. Acceptance Trial 2 will evaluate the remaining communications and most
of the combat systems. In August 2008, the Navy’s Board of Inspection and Survey
(INSURV) conducted Acceptance Trial 1 on LCS 1 and found the ship to be “capable, well-
built, and inspection-ready,” and recommended that the Chief of Naval Operations authorize
delivery of the ship following the correction or waiver of cited material deficiencies, a
standard practice in Navy shipbuilding.
During inspection, INSURV identified 21 “starred” deficiencies onboard LCS 1. This is a
relatively low number and compares favorably to other first-of-class ships. The Navy
developed a plan to address these deficiencies in a timely, prioritized sequence – 12 were
closed prior to delivery, five more will be closed during the ship’s current Industrial Post
Delivery Availability, and the final four will be closed during Post Shakedown Availability
(PSA) in FY 2010.
After acceptance, the crew conducted a vigorous shakedown of the ship during her transit
from the building yard to Norfolk, VA. Encountering adverse weather and numerous
instances of challenging ship handling evolutions, the crew reported the ship performed
superbly during the 2,400 mile journey. LCS 1 will undergo AT 2 and additional test and
trials period intended to complete certifications and mission package integration testing.
INDEPENDENCE (LCS 2)
INDEPENDENCE is being built by the General Dynamics team at the Austal USA shipyard
in Mobile, AL. She was christened on October 4, 2008, and is expected to deliver in 2009,
with Initial Builder’s Trials and Acceptance Trials to complete prior to ship delivery.
Following delivery and commissioning, LCS 2 will transit to Norfolk, VA, and conduct a
post delivery test and trials period similar to FREEDOM.
Facing similar lead ship challenges on INDEPENDENCE, Navy leadership directed General
Dynamics to take a phased approach to completing the ship. The initial phase prioritized
efforts on that scope of work required to safely take INDEPENDENCE to sea, demonstrating
propulsion and additional systems and components necessary for communications and safe
navigation. Based on performance to this goal, a second phase of work would be authorized
focusing on only those core combat systems necessary to demonstrate a basic detect-to-
engage capability required during an acceptance trial. The third phase is the remaining
systems and components required to demonstrate complete combat systems and
communications capabilities of the complete sea frame. At this time, the program manager
has authorized phase 1 and 2 work. Phase 3 remains contingent on performance of the first
two phases. It is still the program manager’s intention to present a complete ship to INSURV
at acceptance trial.
The Navy monitors progress through daily assessments, weekly analysis of key metrics on
production and test progress, and conducts monthly progress and cost reviews with the
contractor to ensure that corrective actions are implemented and effective. As of February
Congressional Research Service
41

Navy Littoral Combat Ship (LCS) Program

2009, all four of the ship’s generators have been started and vital shipboard electrical
systems have completed initial testing, aligning with current schedule projections for ship
delivery. The program expects to achieve main propulsion engines light-off in April and
May, with a goal of Builder’s Trials in late June. The program is prudently managing
resources to be able to address any potential challenges.
Status of Mission Package Procurement
The modular open system architecture used for the LCS design allows independent
development of seaframes and mission packages that integrate across a controlled interface
specification to ensure complete interoperability. This allows the relatively rapid change in
technologies associated with the modular mission packages (MPs) to be continuously
improved through incremental upgrades without major design impacts to seaframes. The
result is a program that minimizes the risks of a highly interdependent system of systems by
decoupling seaframe procurement from mission package procurement, and allows continous
cost efficient delivery of state-of-the-art capability to the warfighter via new misison package
upgrades.
The underlying strength of the LCS lies in its innovative design approach, applying
modularity for operational flexibility. Fundamental to this approach is the capability to
rapidly install interchangeable mission packages into the seaframe. The ability to modify the
LCS physical configuration with different MPs in less than a 96-hour period gives the
operational commander a uniquely flexible response to changing theater warfighting
requirements. This also allows the LCS warfighting capability to quickly adapt to evolving
threats, using improved technology. To achieve this flexibility, the Navy is developing and
procuring specific numbers of MPs to meet the Fleet’s warfighting requirements. A mission
package consists of mission systems which are integrated to form mission modules, Sailors
organized into mission module and aviation crew detachments and supporting aircraft. Each
mission package provides warfighting capability for one of three focused mission areas:
— Mine Countermeasures (MCM)
— Surface Warfare (SUW)
— Anti-Submarine Warfare (ASW)
The first SUW and ASW mission packages were rolled out in FY 2008 and joined the first
MCM mission package, which was delivered in FY 2007. Land-based and at-sea testing of
mission package components began in FY 2008 and continues in FY 2009. Through an
Integrated Test and Evaluation framework, the LCS Mission Modules program office is
working very closely with the responsible mission systems program offices in Naval Sea
Systems Command, Naval Air Systems Command and the Army to ensure that all Mission
System Program of Record, as well as LCS shipboard testing events, demonstrates required
warfighting effectiveness and suitability. Formal LCS sea frame testing of mission packages
commences in FY 2009 and continues through FY 2012.
The LCS Mission Modules program office has adopted an open business model that
leverages Participating Acquisition Resource Managers’ (PARMs) developmental efforts for
both program-of-record and non-program-of-record systems and components. This process
minimizes LCS Mission Modules program investments of research and development dollars
required to mature unique technologies. In addition, the process allows for package
procurement flexibility by limiting integration of immature technologies/systems. This is
done by continuous evaluation of system maturity through a disciplined system engineering
framework. Through this open business model, the LCS Mission Modules program procures
Congressional Research Service
42

Navy Littoral Combat Ship (LCS) Program

mature mission systems from PARMs and then engages an industry partner for Package
Production and Assembly (PP&A) of mission packages.
FUTURE ACQUISITION STRATEGY FOR THE LCS PROGRAM
LCS Acquisition Strategy
In October 2008, the Undersecretary of Defense for Acquisition, Technology and Logistics
(USD(AT&L)) approved a revised acquisition strategy for LCS to cover procurement of the
FY 2009 and FY 2010 ships. The updated acquisition strategy combines the FY 2009
procurement and FY 2010 options in order to maximize competitive pressure on pricing as a
key element of cost control. Increasing the quantity solicited by adding the FY 2010 ships to
the FY 2009 solicitation as options will also enable industry to better establish longer term
supplier relationships and offer the potential for discounting to the prime contractors and
subcontractors. FY 2010 ship options will be a competition for quantity.
Acquisition strategies for FY 2011 and outyear ships are under development. The Navy’s
strategy will be guided by cost and performance of the respective designs, as well as options
for sustaining competition throughout the life of the program. Evaluations of combat systems
and hull, mechanical and electrical (HM&E) performance will be conducted throughout
those tests and trial periods and, as was mentioned earlier, we are already looking for
opportunities to reduce total ownership costs through commonality, reductions or
consolidations based on return-on-investment analysis.
FY 2009 and FY 2010 Contract Awards
As a result of congressional direction contained in the FY 2009 Defense Appropriations Act,
the Navy amended the LCS seaframe construction solicitation to delete the FY 2008 ship.
This amended solicitation continues the competition between the two incumbent industry
teams. The Navy may award one ship to each industry team in FY 2009 and intends to hold a
competition for the FY 2010 option ships soon after award of the FY 2009 contracts.
Affordability remains a key tenet of the LCS program as the Navy works with industry to
provide this capability for the lowest cost.
The FY 2009 and FY 2010 awards will be fixed-price incentive contracts, with the Navy
anticipating that each LCS prime contractor receives one ship in FY 2009. The Navy remains
committed to effective cost control and has modified contracting strategies and management
practices to provide program stability. The FY 2009 and FY 2010 ships will be designated as
Flight 0+ and will include only existing approved engineering changes along with
improvements to construction or fabrication procedures. The Navy will incorporate further
lessons learned from LCS 1 and 2 sea trials into the FY 2009 and FY 2010 ships prior to
production. Any such changes will be limited to those essential for safety, operability or
affordability. Furthermore, the RFP requests that the proposals for the FY 2010 option ships
include alternative prices for both a full-up ship and separately priced contract line item
numbers (CLINs) for a core seaframe (only systems for safe operation at sea), core combat
system and individual combat systems and equipments (such as the gun or radar). This
allows us the opportunity to manage the integration of the combat systems separately if that
proved to be more affordable.
In the interim prior to FY 2009 contract awards, both industry teams were authorized and
funded to pursue limited design and construction efforts while source selection proceeded.
The scope of these efforts was carefully coordinated with prime contractors with an eye on
preserving critical shipbuilding skills or to improve production process engineering. Once
the FY 2009 ships are awarded, these sustaining efforts will be subsumed in the shipbuilding
contracts.
Congressional Research Service
43

Navy Littoral Combat Ship (LCS) Program


Mission Modules Acquisition Strategy
At the time of its inception in FY 2004, the Mission Modules program office decided to
utilize government labs to build the first two of each type of mission package. The Navy
Labs (Naval Surface Warfare Center Panama City (NSWC PC), Naval Undersea Warfare
Center Newport (NUWC NPT), SPAWAR Systems Center San Diego (SSC SD) and Naval
Surface Warfare Center Dahlgren (NSWC DD)) are developing, integrating, testing and
delivering the first six mission packages. This approach was implemented to ensure
responsiveness to refined requirements and reduce the financial risk to the Navy associated
with cost-type contracts for this unique concept. This strategy has been very advantageous to
the Mission Modules program. Once these initial mission packages are completed by the
warfare centers, the package production and assembly will transition to Northrop Grumman.
Following a competitive solicitation, Northrop Grumman was awarded a contract in January
2006 to provide a range of package production and assembly functions specified by the
Navy. The contract contains Award Fee/Award Term provisions covering a term of up to ten
years, with contract options exercised annually. Awarding the options is contingent on
continued excellent contractor performance in preceding years, and is assessed annually.
As Northrop Grumman steps into a production and assembly role, the Navy labs will
transition into the Technical Direction Agent and In-Service Engineering Agent role. This
transition began in 2008 with the transfer of the Technical Data Packages from the Navy labs
to Northrop Grumman in 2008 and continues in 2009.
Rights in Technical Data and Computer Software
It is the Navy’s legal and contractual position that the Navy has Government Purpose Rights
(GPR) to the seaframe designs of both LCS variants and, as such, can solicit full and open
competition for either seaframe design after an adequate design package for such a
competition is developed.
For clarity, those rights are as follows:
— Seaframe – The government has GPR to the design of both seaframes. We did not seek
the rights to the individual equipments in the seaframe (for example we do not have GPR to
the Rolls Royce engine that we could provide to another engine manufacturer to produce for
the government). Another shipbuilder or the government would have to contract with the
individual equipment manufacturers for fabrication and delivery of the equipment for
shipboard installation or, alternatively, negotiate a license with the individual equipment
manufacturers based on the equipment, specifications and interfaces detailed in the seaframe
design.
— Combat Systems – We have GPR to the technical data pertaining to the LM combat
systems, architecture and interfaces. It currently resides in our shared repository. The GD
Integrated Combat Management Systems (ICMS) is based on the Thales TACTICOS system
for which Northrop Grumman is the sole U.S. licensee. Another shipbuilder or the
government would have to either enter into a contract with Northrop Grumman for
production and delivery of the ICMS or, alternatively, obtain a license for that system from
Northrop Grumman. As with the seaframe, we do not possess GPR to the specific
equipments for either system such as the gun, electronic warfare system or radar.
Any third parties seeking to compete on LCS would need to either contract directly with the
equipment manufacturers for fabrication and delivery of the required equipment and
Congressional Research Service
44

Navy Littoral Combat Ship (LCS) Program

associated software or, alternatively, negotiate licensing agreements for the equipment and
software with the respective vendors. This is similar to the current approach in place with the
LM and GD teams. An alternative approach would be for the government to contract directly
with the equipment manufacturers and provide the equipment and software to the shipbuilder
as Government Furnished Equipment/Government Furnished Information.
LCS “Build-to-Print” Design Concept
To implement a competitive “build-to-print” seaframe acquisition, there remains a significant
effort to finalize those revisions to the design that have resulted during construction, as well
as lessons learned from LCS Flight 0 production improvement initiatives, developmental/
operational testing and at-sea testing. There is a considerable amount of work necessary to
convert a design package developed by a specific shipyard based on its own particular
production capabilities and processes to one that can be provided to another qualified
shipbuilder as a government furnished design.
The amount of effort necessary to prepare the LCS data packages to support a full and open
competition derives from the structure of the initial LCS acquisition strategy. The foundation
of the LCS procurement is not a traditional detailed drawing package but the Navy-
established requirements detailed in the Capabilities Development Document (CDD). Each
industry team developed from the CDD a Specified Performance Document (SPD) that
describes the required performance to meet the CDD requirements, then a build specification
detailing how to build a ship to meet that performance. From these three documents,
drawings and specifications detailing exactly what to construct were then developed. The
contractual technical baseline is defined by the CDD, SPD and the build specifications, not
the drawings. Configuration management is accomplished at the build specification level.
At present in the LCS acquisition, industry has developed drawing packages for LCS 1 and
LCS 2. These include digital product models, extracted drawings and drawing liens,
representing multiple changes accomplished to the drawings during production. Thus, while
appropriate for use in construction by the existing industry teams, these packages were not
envisioned to be used as the foundation documents for a build to print solicitation. It would
not be prudent to pursue a build-to-print contract for the current design package until it fully
reflects those changes.
The Navy’s FY 2009 budget request did request funds to begin refinement of the Flight 0+
baseline design drawings and associated documentation into detailed production drawings
and documents. These drawings will also incorporate production, assembly and fabrication
lessons learned from the previous seaframes as well as operator feedback from the seaframe
and mission package crews obtained during the testing and trials period. Additional time and
resources will be necessary to complete a build-to-print package.
The build to print package requires the development of a neutral-format computer-aided
design model (both 2-D and 3-D and STEP compliant) for the total ship, clearing all
interferences for the model, and review and update of all additional required documentation
to ensure that requirements are sufficiently detailed and “generic” to enable providers other
than the incumbent to bid (e.g., the design can’t reflect six-inch bent pipe if only the
incumbent has facilities sufficient to accomplish this). The timing for completion of such a
drawing package is dependent on completion of testing for the LCS lead ships. LCS 1 must
complete Acceptance Trials 2 in Spring 2009 as well as seaframe developmental
testing/operational testing or integration testing with mission packages. LCS 2 has not been
delivered and must complete a similar test and trials period. The Navy is developing an
estimate for LCS class design services needed to support this maturation.

Congressional Research Service
45

Navy Littoral Combat Ship (LCS) Program

Furthermore, to implement a full-and-open acquisition targeted at gaining increased access to
additional shipyards, an approach must also be developed for the acquisition of the combat
systems/networks/control systems/C4I equipment. To mitigate this risk for combat systems
efforts under a build-to-print acquisition, the Navy would either need to direct the shipyards
to contract with the current primes as subcontractors, or assume the role of providing the
combat systems/networks/control systems/C4I equipment as GFE and develop the
infrastructure necessary to serve as the integrator for the program.
LESSONS LEARNED
The Navy has incorporated many of the lessons learned from the initial LCS ships into
overall acquisition policy and in specific shipbuilding programs.
On February 26, 2008, the Navy issued SECNAVNOTE 5000, which instituted an
Acquisition Governance Improvement Six-Gate reporting, reviewing and oversight process
that provides specific criteria for areas such as requirements, funding, and technical
performance including a Probability of Program Success (PoPS) tool. This new process
ensures that the various stakeholders from the resources, requirements and acquisition
communities address and revisit at defined intervals, issues associated with technical
maturity, affordability and program health.
Guidance emphasizing the use of independent engineering technical review boards and
responsibility for Configuration Steering Boards to monitor requirements changes has been
promulgated.
Initiatives to expand the size of the acquisition workforce and to evaluate the composition
and experience of program offices are underway. Similar initiatives are underway in the
technical and SUPSHIPS areas.
A rigorous production readiness review (PRR) prior to the start of fabrication is in place for
shipbuilding programs. It was utilized for the start of fabrication for the DDG 1000, and will
be used in the Joint High Speed Vessel (JHSV) program as well as the FY 2009 LCS ships.
A critical aspect of the PRR is design maturity. DDG 1000 requirements were that the design
was at least 85% complete prior to start fabrication, including all units scheduled to start
construction in the first six months. Similar criteria will govern the start of fabrication for
JHSV and subsequent new ship designs.
SUMMARY
In summary, the Navy remains committed to the LCS program. LCS remains a critical
warfighting requirement for our Navy to maintain dominance in the littorals and strategic
choke points around the world.
The Navy continues to address the problems encountered in the early stages of the program
and to implement improvements across the entire shipbuilding portfolio. We appreciate your
strong support and the opportunity to testify before the Subcommittee. We will be pleased to
answer any questions you may have.

Congressional Research Service
46

Navy Littoral Combat Ship (LCS) Program