Nuclear Power Plant Security and
Vulnerabilities

Mark Holt
Specialist in Energy Policy
Anthony Andrews
Specialist in Energy and Energy Infrastructure Policy
March 18, 2009
Congressional Research Service
7-5700
www.crs.gov
RL34331
CRS Report for Congress
P
repared for Members and Committees of Congress

Nuclear Power Plant Security and Vulnerabilities

Summary
The physical security of nuclear power plants and their vulnerability to deliberate acts of
terrorism was elevated to a national security concern following the September 11, 2001 attacks.
Since then, Congress has repeatedly focused oversight and legislative attention on nuclear power
plant security requirements established and enforced by the Nuclear Regulatory Commission
(NRC).
The Energy Policy Act of 2005 (P.L. 109-58) imposed specific criteria for NRC to consider in
revising the “Design Basis Threat” (DBT), which specifies the maximum severity of potential
attacks that a nuclear plant’s security force must be capable of repelling. In response to the
legislative mandate, NRC revised the DBT (10 C.F.R. Part 73.1) on April 18, 2007. Among other
changes, the revisions expanded the assumed capabilities of adversaries to operate as one or more
teams and attack from multiple entry points.
To strengthen nuclear plant security inspections, the Energy Policy Act of 2005 act required NRC
to conduct “force-on-force” security exercises at nuclear power plants at least once every three
years. In these exercises, a mock adversary force from outside a nuclear plant attempts to
penetrate the plant’s vital area and simulate damage to key safety components. The first three-
year cycle of force-on-force exercises was completed for all U.S. nuclear plants at the end of
calendar year 2007. During that period, 172 force-on-force exercises were conducted (an average
of three per site), and 10 security inadequacies were cited. Two of the exercises, both in 2007,
resulted in simulated damage or destruction of a vital target by the adversary team. In both cases,
NRC ordered corrective actions and conducted follow-up exercises to confirm the improvements.
The Energy Policy Act also included provisions for fingerprinting and criminal background
checks of security personnel, their use of firearms, and the unauthorized introduction of
dangerous weapons. The designation of facilities subject to enforcement of penalties for sabotage
was expanded to include treatment and disposal facilities.
Nuclear power plant vulnerability to deliberate aircraft crashes has been a continuing issue. After
much consideration, NRC voted February 17, 2009, to require all new nuclear power plants to
incorporate design features that would ensure that, in the event of a crash by a large commercial
aircraft, the reactor core would remain cooled or the reactor containment would remain intact, and
radioactive releases would not occur from spent fuel storage pools.
NRC rejected proposals that existing reactors also be required to protect against aircraft crashes,
such as by adding large external steel barriers. However, NRC did impose some additional
requirements related to aircraft crashes on all reactors, both new and existing, after the 9/11
attacks. In 2002, NRC ordered all nuclear power plants to develop strategies to mitigate the
effects of large fires and explosions that could result from aircraft crashes or other causes. An
NRC regulation on fire mitigation strategies, along with requirements that reactors establish
procedures for responding to specific aircraft threats, was approved December 17, 2008.
Other ongoing nuclear plant security issues include the vulnerability of spent fuel pools, which
hold highly radioactive nuclear fuel after its removal from the reactor, standards for nuclear plant
security personnel, and nuclear plant emergency planning. NRC’s December 2008 security
regulations addressed some of those concerns and included a number of other security
enhancements.
Congressional Research Service

Nuclear Power Plant Security and Vulnerabilities

Contents
Overview of Reactor Security ..................................................................................................... 1
Design Basis Threat .................................................................................................................... 2
Large Aircraft Crashes ................................................................................................................ 4
Force-On-Force Exercises ........................................................................................................... 5
Emergency Response .................................................................................................................. 7
Spent Fuel Storage ...................................................................................................................... 7
Security Personnel and Other Issues ............................................................................................ 8

Contacts
Author Contact Information ...................................................................................................... 10

Congressional Research Service

Nuclear Power Plant Security and Vulnerabilities

Overview of Reactor Security
Physical security at nuclear power plants involves the threat of radiological sabotage—a
deliberate act against a plant that could directly or indirectly endanger public health and safety
through exposure to radiation. The Nuclear Regulatory Commission (NRC) establishes security
requirements at U.S. commercial nuclear power plants based on its assessment of plant
vulnerabilities to, and the consequences of, potential attacks. The stringency of NRC’s security
requirements and its enforcement program have been a significant congressional issue, especially
since the September 11, 2001, terrorist attacks on the United States.
Nuclear plant security measures are designed to protect three primary areas of vulnerability:
controls on the nuclear chain reaction, cooling systems that prevent hot nuclear fuel from melting
even after the chain reaction has stopped, and storage facilities for highly radioactive spent
nuclear fuel. U.S. plants are designed and built to prevent dispersal of radioactivity, in the event
of an accident, by surrounding the reactor in a steel-reinforced concrete containment structure.
NRC requires commercial nuclear power plants to have a series of physical barriers and a trained
security force, under regulations already in place prior to the 9/11 attacks (10 C.F.R. 73—Physical
Protection of Plants and Materials). The plant sites are divided into three zones: an “owner-
controlled” buffer region, a “protected area,” and a “vital area.” Access to the protected area is
restricted to a portion of plant employees and monitored visitors, with stringent access barriers.
The vital area is further restricted, with additional barriers and access requirements. The security
force must comply with NRC requirements on pre-hiring investigations and training.1
A fundamental concept in NRC’s physical security requirements is the design basis threat (DBT),
which establishes the severity of the potential attacks that a nuclear plant’s security force must be
capable of repelling. The DBT includes such characteristics as the number of attackers, their
training, and the weapons and tactics they could use. Specific details are classified. Critics of
nuclear plant security have contended that the DBT should be strengthened to account for
potentially larger and more sophisticated terrorist attacks.
Reactor vulnerability to deliberate aircraft crashes has also been a major concern since 9/11. Most
existing nuclear power plants were not specifically designed to withstand crashes from large
jetliners, although analyses differ as to the damage that could result. NRC has determined that
commercial aircraft crashes are beyond the DBT but voted in February 2009 to require that new
reactor designs be able to withstand such crashes without releasing radioactivity. Nuclear power
critics have called for retrofits of existing reactors as well.
Since the 9/11 attacks, NRC and Congress have taken action to increase nuclear power plant
security. NRC issued a series of security measures beginning in 2002, including a strengthening
of the DBT and establishing the Office of Nuclear Security and Incident Response (NSIR). The
office centralizes security oversight of all NRC-regulated facilities, coordinates with law
enforcement and intelligence agencies, and handles emergency planning activities. In 2004, NRC
implemented a program to conduct “force on force” security exercises overseen by NSIR at each
nuclear power plant at least every three years. The Energy Policy Act of 2005 (P.L. 109-58)
required NRC to further strengthen the DBT, codified the force-on-force program, and established

1 General NRC requirements for nuclear power plant security can be found in 10 C.F.R. 73.55.
Congressional Research Service
1

Nuclear Power Plant Security and Vulnerabilities

a variety of additional nuclear plant security measures. In December 2008, NRC approved a
series of security regulations that require power plants to prepare cyber security plans, develop
strategies for dealing with the effects of aircraft crashes, strengthen access controls, improve
training for security personnel, and take other new security measures.
Design Basis Threat
The design basis threat describes general characteristics of adversaries that nuclear plants and
nuclear fuel cycle facilities must defend against to prevent radiological sabotage and theft of
strategic special nuclear material. NRC licensees use the DBT as the basis for implementing
defensive strategies of a specific nuclear plant site through security plans, safeguards contingency
plans, and guard training and qualification plans.
General requirements for the DBT are prescribed in NRC regulations,2 while specific attributes of
potential attackers, such as their weapons and ammunition, are contained in classified adversary
characteristics documents (ACDs).
Fundamental policies on nuclear plant security threats date back to the Cold War. In 1967, the
Atomic Energy Commission (AEC) instituted a rule that nuclear plants are not required to protect
against an attack directed by an “enemy of the United States.”3 That so-called “Enemy of the
State Rule” specifies that nuclear power plants are
not required to provide for design features or other measures for the specific purpose of
protection against the effects of (a) attacks and destructive acts, including sabotage, directed
against the facility by an enemy of the United States, whether a foreign government or other
person, or (b) use or deployment of weapons incident to U.S. defense activities.4
The Nuclear Regulatory Commission (NRC), the AEC’s successor regulatory agency, says that
the rule “was primarily intended to make clear that privately-owned nuclear facilities were not
responsible for defending against attacks that typically could only be carried out by foreign
military organizations.”5 NRC’s initial DBT, established in the late 1970s, was intended to be
consistent with the enemy of the state rule, which remains in effect.
However, the 9/11 attacks drew greater attention to the potential severity of credible terrorist
threats. Following the attacks, NRC evaluated the extent to which nuclear plant security forces
should be able to defend against such threats, and ordered a strengthening of the DBT, along with
other security measures, on April 29, 2003. That order changed the DBT to “represent the largest
reasonable threat against which a regulated private guard force should be expected to defend
under existing law,” according to the NRC announcement.6

2 10 C.F.R. § 73.1.
3 It was feared that Cuba might launch an attack on Florida reactors. Government Accountability Office, Nuclear
Power Plants—Efforts Made to Upgrade Security, but the Nuclear Regulatory Commission’s Design Basis Threat
Process Should Be Improved
(GAO-06-388), March 2006, p. 2. Regulations at 10 CFR 50.13.
4 10 C.F.R. § 50.13. Attacks and destructive acts by enemies of the United States; and defense activities.
5 Nuclear Regulatory Commission, “Design Basis Threat,” 72 Federal Register 12714, March 19, 2007.
6 Federal Register, May 7, 2003 (vol. 68, no. 88). NRC, All Operating Power Reactor Licensees; Order Modifying
Licenses.
Congressional Research Service
2

Nuclear Power Plant Security and Vulnerabilities

In the Energy Policy Act of 2005 (EPACT), Congress imposed a statutory requirement on the
NRC to initiate rulemaking for revising the design basis threat.7 EPACT required NRC to
consider 12 factors in revising the DBT, such as an assessment of various terrorist threats, sizable
explosive devices and modern weapons, attacks by persons with sophisticated knowledge of
facility operations, and attacks on spent fuel shipments.
NRC approved its final rule amending the DBT (10 C.F.R. Part 73.1) on January 29, 2007,
effective April 18, 2007.8 Although specific details of the revised DBT were not released to the
public, in general the final rule
• clarifies that physical protection systems are required to protect against diversion
and theft of fissile material;
• expands the assumed capabilities of adversaries to operate as one or more teams
and attack from multiple entry points;
• assumes that adversaries are willing to kill or be killed and are knowledgeable
about specific target selection;
• expands the scope of vehicles that licensees must defend against to include water
vehicles and land vehicles beyond four-wheel-drive type;
• revises the threat posed by an insider to be more flexible in scope; and
• adds a new mode of attack from adversaries coordinating a vehicle bomb assault
with another external assault.
The DBT final rule excluded aircraft attacks, a decision that raised considerable controversy. In
approving the rule, NRC rejected a petition from the Union of Concerned Scientists to require
that nuclear plants be surrounded by aircraft barriers made of steel beams and cables (the so-
called “beamhenge” concept). Critics of the rule charged that deliberate aircraft crashes were a
highly plausible mode of attack, given the events of 9/11. However, NRC contended that power
plants were already required to mitigate the effects of aircraft crashes and that “active protection
against airborne threats is addressed by other federal organizations, including the military.”9
Additional NRC action on aircraft threats is discussed below.
NRC Commissioners in January 2009 rejected a proposal by the NRC staff to strengthen the
classified portion of the DBT to include additional capabilities by potential attackers, according to
news reports. The staff proposal lost in a 2-2 vote, with one commissioner position currently
vacant. In an interview afterward, NRC Chairman Dale Klein said the vote could be reconsidered
after completion of an ongoing interagency study.10
Critics of NRC’s security regulations have pointed out that licensees are required to employ only
a minimum of five security personnel on duty per plant, which they argue is not enough for the
job.11 Nuclear spokespersons responded that the actual security force for the nation’s 65 nuclear

7 P.L. 109-58, Title VI, Subtitle D—Nuclear Security (Secs. 651-657). Sec. 651 adds Atomic Energy Act Sec. 170E.
Design Basis Threat Rulemaking.
8 Federal Register, March 19, 2007 (vol. 72, no. 52), NRC, Design Basis Threat, Final Rule, pp. 12705-12727.
9 NRC, “NRC Approves Final Rule Amending Security Requirements,” News Release No. 07-012, January 29, 2007.
10 Jeff Beattie, “NRC Chairman Questions Case for Tougher DBT,” Energy Daily, February 17, 2009, p. 1.
11 10 C.F.R. 73.55 (h)(3) states: “The total number of guards, and armed, trained personnel immediately available at the
(continued...)
Congressional Research Service
3

Nuclear Power Plant Security and Vulnerabilities

plant sites numbers more than 5,000, an average of about 75 per site (covering multiple shifts).
Nuclear plant security forces are also supposed to be aided by local law enforcement officers if an
attack occurs.
Large Aircraft Crashes
Nuclear power plants were designed to withstand hurricanes, earthquakes, and other extreme
events. But deliberate attacks by large airliners loaded with fuel, such as those that crashed into
the World Trade Center and Pentagon, were not analyzed when design requirements for today’s
reactors were determined.12 Concern about aircraft crashes was intensified by a taped interview
shown September 10, 2002, on the Arab TV station al-Jazeera, which contained a statement that
Al Qaeda initially planned to include a nuclear plant in its list of 2001 attack sites.
In light of the possibility that an air attack might penetrate the containment structure of a nuclear
plant or a spent fuel storage facility, some interest groups have suggested that such an event could
be followed by a meltdown or spent fuel fire and widespread radiation exposure. Nuclear industry
spokespersons have countered by pointing out that relatively small, low-lying nuclear power
plants are difficult targets for attack, and have argued that penetration of the containment is
unlikely, and that even if such penetration occurred it probably would not reach the reactor vessel.
They suggest that a sustained fire, such as that which melted the steel support structures in the
World Trade Center buildings, would be impossible unless an attacking plane penetrated the
containment completely, including its fuel-bearing wings. According to former NRC Chairman
Nils Diaz, NRC studies “confirm that the likelihood of both damaging the reactor core and
releasing radioactivity that could affect public health and safety is low.”13
NRC proposed in October 2007 to amend its regulations to require newly designed power
reactors to take into account the potential effects of the impact of a large commercial aircraft. 14
As discussed in the previous section, NRC considers an aircraft attack to be beyond the design
basis threat that plants must be able to withstand, so the requirements of the proposed rule were
intended to provide an additional margin of safety. The proposed rule would affect only new
reactor designs not previously certified by NRC, because the previous designs were still
considered adequately safe. Nevertheless, Westinghouse submitted changes in the certified design
of its AP1000 reactor to NRC on May 29, 2007, proposing to line the inside and outside of the
reactor’s concrete containment structure with steel plates to increase resistance to aircraft
penetration.15

(...continued)
facility to fulfill these response requirements shall nominally be ten (10), unless specifically required otherwise on a
case by case basis by the Commission; however, this number may not be reduced to less than five (5) guards.”
12 Meserve, Richard A., NRC Chairman, “Research: Strengthening the Foundation of the Nuclear Industry,” Speech to
Nuclear Safety Research Conference, October 29, 2002.
13 Letter from NRC Chairman Nils J. Diaz to Secretary of Homeland Security Tom Ridge, September 8, 2004.
14 Federal Register, October 3, 2007 (vol. 72, no. 191), Consideration of Aircraft Impacts for New Nuclear Power
Reactor Designs.
15 MacLachlan, Ann, “Westinghouse Changes AP1000 Design to Improve Plane Crash Resistance,” Nucleonics Week,
June 21, 2007.
Congressional Research Service
4

Nuclear Power Plant Security and Vulnerabilities

Under NRC’s 2007 proposed rule, applicants for new certified designs or for new reactor licenses
using uncertified designs would have been required to assess the effects that a large aircraft crash
would have on the proposed facilities. Each applicant would then describe how the plant’s design
features, capabilities, and operations would avoid or mitigate the effects of such a crash,
particularly on core cooling, containment integrity, and spent fuel storage pools.
In response to comments, the NRC staff proposed in October 2008 that the aircraft impact
assessments be conducted by all new reactors, including those using previously certified
designs.16 The NRC Commissioners, in a 3-1 vote, approved the change February 17, 2009, and
added specific design requirements that all new reactors would have to meet:17
Each applicant subject to this section shall perform a design-specific assessment of the
effects on the facility of the impact of a large, commercial aircraft. Using realistic analyses,
the applicant shall identify and incorporate into the design those design features and
functional capabilities to show that, with reduced use of operator actions:
(A) the reactor core remains cooled, or the containment remains intact; and
(B) spent fuel cooling or spent fuel pool integrity is maintained.
As noted above, NRC rejected proposals that existing reactors—in addition to new reactors—be
required to protect against aircraft crashes, such as by adding “beamhenge” barriers. However,
NRC did impose some additional requirements related to aircraft crashes on all reactors after the
9/11 attacks. In 2002, NRC ordered all nuclear power plants to develop strategies to mitigate the
effects of large fires and explosions that could result from aircraft crashes or other causes.18 As
part of a broad security rulemaking effort, NRC proposed in October 2006 to incorporate the
2002 order on fire and explosion strategies into its security regulations (10 CFR Part 73).19 In
response to comments, NRC published a supplemental proposed rule in April 2008 to move the
fire and explosion requirements into its reactor licensing regulations at 10 CFR Part 50, along
with requirements that reactors establish procedures for responding to specific aircraft threat
notifications.20 Those regulations received final approval by the NRC Commissioners December
17, 2008.21
Force-On-Force Exercises
EPACT codified an NRC requirement that each nuclear power plant conduct security exercises
every three years to test its ability to defend against the design basis threat. In these “force-on-

16 Nuclear Regulatory Commission, Final Rule—Consideration of Aircraft Impacts for New Nuclear Power Reactors,
Rulemaking Issue Affirmation, SECY-08-0152, October 15, 2008.
17 Nuclear Regulatory Commission, Final Rule—Consideration of Aircraft Impacts for New Nuclear Power Reactors,
Commission Voting Record, SECY-08-0152, February 17, 2009.
18 Nuclear Regulatory Commission, Final Rule—Consideration of Aircraft Impacts for New Nuclear Power Reactors,
Rulemaking Issue Affirmation, SECY-08-0152, October 15, 2008, p. 2.
19 Nuclear Regulatory Commission, “Power Reactor Security Requirments, Proposed Rule,” 71 Federal Register
62664, October 26, 2006.
20 Nuclear Regulatory Commission, “Power Reactor Security Requirements, Supplemental Proposed Rule,” 73 Federal
Register
19443, April 10, 2008.
21 Nuclear Regulatory Commission, “NRC Approves Final Rule Expanding Security Requirements for Nuclear Power
Plants,” press release, December 17, 2008, http://www.nrc.gov/reading-rm/doc-collections/news/2008/08-227.html.
Congressional Research Service
5

Nuclear Power Plant Security and Vulnerabilities

force” exercises, monitored by NRC, a mock adversary force from outside the plant attempts to
penetrate the plant’s vital area and simulate damage to key safety components. Participants in the
tightly controlled exercises carry weapons modified to fire only blanks and laser bursts to
simulate bullets, and they wear laser sensors to indicate hits. Other weapons and explosives, as
well as destruction or breaching of physical security barriers, may also be simulated. While one
squad of the plant’s guard force is participating in a force-on-force exercise, another squad is also
on duty to maintain normal plant security. Plant defenders know that a mock attack will take
place sometime during a specific period of several hours, but they do not know what the attack
scenario will be. Multiple attack scenarios are conducted over several days of exercises.
Full implementation of the force-on-force program began in late 2004. Standard procedures and
other requirements have been developed for using the force-on-force exercises to evaluate plant
security and as a basis for taking regulatory enforcement action. Many tradeoffs are necessary to
make the exercises as realistic and consistent as possible without endangering participants or
regular plant operations and security.
NRC required the nuclear industry to develop and train a “composite adversary force” comprising
security officers from many plants to simulate terrorist attacks in the force-on-force exercises.
However, in September 2004 testimony, GAO criticized the industry’s selection of Wackenhut, a
security company that guards about half of U.S. nuclear plants, to also provide the adversary
force. In addition to raising “questions about the force’s independence,” GAO noted that
Wackenhut had been accused of cheating on previous force-on-force exercises by the Department
of Energy.22 Exelon terminated its security contracts with Wackenhut in late 2007 after guards at
the Peach Bottom reactor in York County, Pennsylvania, were discovered sleeping while on
duty.23 EPACT requires NRC to “mitigate any potential conflict of interest that could influence
the results of a force-on-force exercise, as the Commission determines to be necessary and
appropriate.” NRC’s 2007 annual security report to Congress found that the industry adversary
teams “continued to meet expectations for a credible, well-trained, and consistent mock adversary
force.”24
The first three-year cycle of force-on-force exercises was completed for all 64 U.S. nuclear plant
sites at the end of calendar year 2007.25 During that period, 172 force-on-force exercises were
conducted (an average of three per site), and 10 security inadequacies were cited. Two of the
exercises, both in 2007, resulted in simulated damage or destruction of a vital target by the
adversary team. If such an attack had been real, the plant could have released unacceptable levels
of radioactivity. Both cases resulted from “the failure of licensee armed security personnel to
interpose themselves between the mock adversary and the vital areas and target set components,”

22 GAO. “Nuclear Regulatory Commission: Preliminary Observations on Efforts to Improve Security at Nuclear Power
Plants.” Statement of Jim Wells, Director, Natural Resources and Environment to the Subcommittee on National
Security, Emerging Threats, and International Relations, House Committee on Government Reform. September 14,
2004. p. 14.
23 Washington Post, “Executive Resigns in Storm Over Sleeping Guards,” January 10, 2008.
24 Nuclear Regulatory Commission, Office of Nuclear Security and Incident Response, Report to Congress on the
Security Inspection Program for Commercial Power Reactor and Category 1 Fuel Cycle Facilities: Results and Status
Update; Annual Report for Calendar Year 2007, NUREG-1885, July 2008, p. 7, http://www.nrc.gov/reading-rm/doc-
collections/congress-docs/correspondence/2008/boxer-07-01-2008.pdf.
25 NRC generally lists 65 U.S. plant sites, but the adjacent Hope Creek and Salem sites in New Jersey are considered to
be a single site for security exercises. E-mail message from David Decker, NRC Office of Congressional Affairs,
March 13, 2009.
Congressional Research Service
6

Nuclear Power Plant Security and Vulnerabilities

according to NRC’s 2007 security report to Congress. In response to the failures, NRC imposed
“immediate compensatory measures followed by long-term corrective actions.” Follow-up force-
on-force exercises were conducted to verify that the necessary security improvements had been
made.26
Emergency Response
After the 1979 accident at the Three Mile Island nuclear plant near Harrisburg, PA, Congress
required that all nuclear power plants be covered by emergency plans. NRC requires that within
an approximately 10-mile Emergency Planning Zone (EPZ) around each plant, the operator must
maintain warning sirens and regularly conduct evacuation exercises monitored by NRC and the
Federal Emergency Management Agency (FEMA). In light of the increased possibility of terrorist
attacks that, if successful, could result in release of radioactive material, proposals have been
made to expand the EPZ to include larger population centers.
The release of radioactive iodine during a nuclear incident is a particular concern, because iodine
tends to concentrate in the thyroid gland of persons exposed to it. Emergency plans in many states
include distribution of iodine pills to the population within the EPZ. Taking non-radioactive
iodine before exposure would prevent absorption of radioactive iodine but would afford no
protection against other radioactive elements. In 2002, NRC began providing iodine pills to states
requesting them for populations within the 10-mile EPZ.
Spent Fuel Storage
When no longer capable of sustaining a nuclear chain reaction, highly radioactive “spent” nuclear
fuel is removed from the reactor and stored in a pool of water in the reactor building and at some
sites later transferred to dry casks on the plant grounds. Because both types of storage are located
outside the reactor containment structure, particular concern has been raised about the
vulnerability of spent fuel to attack by aircraft or other means. If terrorists could breach a spent
fuel pool’s concrete walls and drain the cooling water, the spent fuel’s zirconium cladding could
overheat and catch fire.
The National Academy of Sciences (NAS) released a report in April 2005 that found that
“successful terrorist attacks on spent fuel pools, though difficult, are possible,” and that “if an
attack leads to a propagating zirconium cladding fire, it could result in the release of large
amounts of radioactive material.” NAS recommended that the hottest spent fuel be interspersed
with cooler spent fuel to reduce the likelihood of fire, and that water-spray systems be installed to
cool spent fuel if pool water were lost. The report also called for NRC to conduct more analysis
of the issue and consider earlier movement of spent fuel from pools into dry storage.27 The

26 Nuclear Regulatory Commission, Office of Nuclear Security and Incident Response, Report to Congress on the
Security Inspection Program for Commercial Power Reactor and Category 1 Fuel Cycle Facilities: Results and Status
Update; Annual Report for Calendar Year 2007, NUREG-1885, July 2008, p. 8, http://www.nrc.gov/reading-rm/doc-
collections/congress-docs/correspondence/2008/boxer-07-01-2008.pdf.
27 National Academy of Sciences, Board on Radioactive Waste Management, Safety and Security of Commercial Spent
Nuclear Fuel Storage, Public Report (online version), released April 6, 2005.
Congressional Research Service
7

Nuclear Power Plant Security and Vulnerabilities

FY2006 Energy and Water Development Appropriations Act (P.L. 109-103, H.Rept. 109-275)
provided $21 million for NRC to carry out the site-specific analyses recommended by NAS.
NRC has long contended that the potential effects of terrorist attacks are too speculative to
include in environmental studies for proposed spent fuel storage and other nuclear facilities.
However, the U.S. Court of Appeals for the 9th Circuit ruled in June 2006 that terrorist attacks
must be included in the environmental study of a dry storage facility at California’s Diablo
Canyon nuclear plant. NRC reissued the Diablo Canyon study May 29, 2007, to comply with the
court ruling, but it did not include terrorism in other recent environmental studies.28
Long-term management of spent nuclear fuel is currently undergoing review, but spent fuel stored
at reactor sites is expected to be moved eventually to central storage, permanent disposal, or
reprocessing facilities. Large-scale transportation campaigns would increase public attention to
NRC transportation security requirements and related security issues.
Security Personnel and Other Issues
After video recordings of inattentive security officers at the Peach Bottom (PA) nuclear power
plant were aired on local television, an NRC inspection in late September 2007 confirmed that
there had been multiple occasions on which multiple security officers were inattentive.29
However, after a follow-up inspection into security issues at the Peach Bottom plant, run by
Exelon Nuclear, the NRC concluded that the plant’s security program had not been significantly
degraded as a result of the guards’ inattentiveness. NRC issued a bulletin December 12, 2007,
requiring all nuclear power plants to provide written descriptions of their “managerial controls to
deter and address inattentiveness and complicity among licensee security personnel.”30
The incident drew harsh criticism from the House Committee on Energy and Commerce. “The
NRC’s stunning failure to act on credible allegations of sleeping security guards, coupled with its
unwillingness to protect the whistleblower who uncovered the problem, raises troubling
questions,” said Representative John D. Dingell, then-Chairman of the Committee.31 NRC
proposed a $65,000 fine on Exelon Nuclear on January 6, 2009.32
Following the 9/11 terrorist attacks, NRC conducted a “top-to-bottom” review of its nuclear
power plant security requirements. On February 25, 2002, the agency issued “interim
compensatory security measures” to deal with the “generalized high-level threat environment”
that continued to exist, and on January 7, 2003, it issued regulatory orders that tightened nuclear
plant access. On April 29, 2003, NRC issued orders to restrict security officer work hours,

28 Beattie, Jeff, “NRC Takes Two Roads on Terror Review Issue,” Energy Daily, February 27, 2007.
29 NRC, NRC Commences Follow-up Security Inspection at Peach Bottom, November 5, 2007 http://www.nrc.gov/
reading-rm/doc-collections/news/2007/07-057.i.html.
30 Nuclear Regulatory Commission, Security Officer Attentiveness, NRC Bulletin 2007-1, Washington, DC, December
12, 2007.
31 Committee on Energy and Commerce, Energy and Commerce Committee to Probe Breakdowns in NRC Oversight,
January 7, 2008 http://energycommerce.house.gov/Press_110/110nr149.shtml.
32 Nuclear Regulatory Commission, “NRC Proposes $65,000 Fine for Violations Associated with Inattentive Security
Guards at Peach Bottom Nuclear Plant,” press release, January 6, 2009, http://www.nrc.gov/reading-rm/doc-
collections/news/2009/09-001.i.html.
Congressional Research Service
8

Nuclear Power Plant Security and Vulnerabilities

establish new security force training and qualification requirements, and increase the DBT that
nuclear security forces must be able to defend against, as discussed previously.
In October 2006, NRC proposed to amend the security regulations and add new security
requirements that would codify the series of orders issued after 9/11 and respond to requirements
in the Energy Policy Act of 2005.33 The new security regulations were approved by the NRC
Commissioners on December 17, 2008, with the following provisions34:
Safety and Security Interface. Explicit requirements are established for nuclear
plants to ensure that necessary security measures do not compromise plant safety.
Mixed-Oxide Fuel. Enhanced physical security requirements are established to
prevent theft or diversion of plutonium-bearing mixed-oxide (MOX) fuel.
Cyber Security. Nuclear plants must submit security plans to prevent cyber
attacks on digital computer and communications systems and networks. The
cyber security plan will become a license condition for each plant.
Aircraft Attack Mitigative Strategies and Response. As discussed in the earlier
section on vulnerability to aircraft crashes, nuclear plants must prepare strategies
for responding to warnings of an aircraft attack and for mitigating the effects of
large explosions and fires.
Plant Access Authorization. Nuclear plants must implement more rigorous
programs for authorizing access, including enhanced psychological assessments
and behavioral observation.
Security Personnel Training and Qualification. Modifications to security
personnel requirements include additional physical fitness standards, increased
minimum qualification scores for mandatory personnel tests, and requirements
for on-the-job training.
Physical Security Enhancements. New requirements are intended to ensure the
availability of backup security command centers, uninterruptible power supplies
to detection systems, enhanced video capability, and protection from waterborne
vehicles.
A proposal by NRC staff to release more details about the results of nuclear plant security
inspections was defeated by the NRC Commissioners in a 2-2 vote on January 21, 2009. Under
current policy, NRC announces after a security inspection whether any violations that were found
were of low safety significance or moderate-or-higher safety significance. Critics of the current
policy contend that the public needs more detail to be assured of plant security. The policy’s
supporters counter that greater information about security inspection findings could inadvertently
provide useful information to terrorists.35



33 Federal Register, October 26, 2006 (vol. 71, no. 207), NRC, Power Reactor Security Requirements, Proposed Rule.
34 E-mail message from David Decker, NRC Office of Congressional Affairs, February 27, 2009.
35 Jenny Weil, “Commissioners Reach Stalemeat on Security-Related Amendment,” Inside NRC, February 2, 2009.
Congressional Research Service
9

Nuclear Power Plant Security and Vulnerabilities

Author Contact Information

Mark Holt
Anthony Andrews
Specialist in Energy Policy
Specialist in Energy and Energy Infrastructure
mholt@crs.loc.gov, 7-1704
Policy
aandrews@crs.loc.gov, 7-6843




Congressional Research Service
10