

Order Code RL32109
Navy DDG-1000 Destroyer Program: Background,
Oversight Issues, and Options for Congress
Updated February 27, 2008
Ronald O’Rourke
Specialist in National Defense
Foreign Affairs, Defense, and Trade Division
Navy DDG-1000 Destroyer Program: Background,
Oversight Issues, and Options for Congress
Summary
The Navy is procuring a new kind of destroyer called the DDG-1000 (formerly
the DD(X)). Navy plans call for procuring a total of seven DDG-1000s. The first
two DDG-1000s were procured in FY2007 using split funding (i.e., incremental
funding) across FY2007 and FY2008. The Navy estimates their combined
procurement cost at $6,325 million. The Navy wants to procure the third DDG-1000
in FY2009; the Navy estimates its procurement cost at $2,653 million. The ship
received $150 million in advance procurement funding in FY2008, and the Navy’s
proposed FY2009 budget requests the remaining $2,503 million. The Navy’s
proposed FY2009 budget also requests $51 million in advance procurement funding
for the fourth DDG-51, which the Navy wants to procure in FY2010.
The DDG-1000 program raises several potential oversight issues for Congress,
including the accuracy of Navy cost estimates for the program, technical risk and
system integration, the acquisition strategy for the third and subsequent ships in the
program, the shared-production arrangement for the program, and the program’s
potential implications for the shipbuilding industrial base.
Potential options for Congress for the DDG-1000 program include supporting
the Navy’s proposed plans, using a block-buy arrangement for procuring several
DDG-1000s, and curtailing procurement of DDG-1000s, perhaps to help fund the
procurement of other Navy ships.
This report will be updated as events warrant.
Contents
Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
DDG-1000 Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Surface Combatant Industrial Base . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Oversight Issues for Congress . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Accuracy of Navy Cost Estimate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Technical Risk and System Integration . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
Acquisition Strategy for Third and Subsequent Ships . . . . . . . . . . . . . . . . . 12
Shared Production Arrangement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
Industrial Base . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
Options for Congress . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
FY2009 Legislative Activity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
Appendix A. Earlier DDG-1000 Program Oversight Issues . . . . . . . . . . . . . . . . 15
Program Affordability and Cost Effectiveness . . . . . . . . . . . . . . . . . . . . . . 15
Mission Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
Appendix B. Potential Lower-Cost Ships . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
Lower-Cost Gunfire Support Ship . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
Lower-Cost Cruiser-Destroyer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
Notional Procurement Profiles With Lower-Cost Ships . . . . . . . . . . . . . . . 29
CSBA Report Recommendations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
List of Tables
Table 1. Actual and Planned DDG-1000 Procurement . . . . . . . . . . . . . . . . . . . . . 3
Table 2. DDG-1000 Program Funding, FY2002-FY2013 . . . . . . . . . . . . . . . . . . 4
Table 3. Follow-ship DDG-51 and DDG-1000 Costs . . . . . . . . . . . . . . . . . . . . . 17
Table 4. Alternative With LPD (AGS) and Smaller Cruiser-Destroyer . . . . . . . 29
Table 5. Alternative With Smaller Cruiser-Destroyer . . . . . . . . . . . . . . . . . . . . 30
Navy DDG-1000 Destroyer Program:
Background, Oversight Issues, and Options
for Congress
Introduction
The Navy is procuring a new kind of destroyer called the DDG-1000 (formerly
the DD(X)). Navy plans call for procuring a total of seven DDG-1000s. The first
two DDG-1000s were procured in FY2007 using split funding (i.e., incremental
funding) across FY2007 and FY2008. The Navy estimates their combined
procurement cost at $6,325 million. The Navy wants to procure the third DDG-1000
in FY2009; the Navy estimates its procurement cost at $2,653 million. The ship
received $150 million in advance procurement funding in FY2008, and the Navy’s
proposed FY2009 budget requests the remaining $2,503 million. The Navy’s
proposed FY2009 budget also requests $51 million in advance procurement funding
for the fourth DDG-51, which the Navy wants to procure in FY2010.
The issue for Congress is whether to approve, modify, or reject the Navy’s
proposals for the DDG-1000 program. Decisions that Congress makes on
procurement of surface combatants will significantly affect future Navy capabilities,
Navy funding requirements, and the shipbuilding industrial base.
Background
DDG-1000 Program
Origin of Program. The program known today as the DDG-1000 program
was announced on November 1, 2001, when the Navy stated that it was replacing a
destroyer-development effort called the DD-21 program, which the Navy had
initiated in the mid-1990s, with a new Future Surface Combatant Program aimed at
developing and acquiring a family of three new classes of surface combatants:1
1 The DD-21 program was part of a Navy surface combatant acquisition effort begun in the
mid-1990s and called the SC-21 (Surface Combatant for the 21st Century) program. The SC-
21 program envisaged a new destroyer called DD-21 and a new cruiser called CG-21. When
the Navy announced the Future Surface Combatant Program in 2001, development work on
the DD-21 had been underway for several years, while the start of development work on the
CG-21 was still years in the future. The current DDG-1000 destroyer CG(X) cruiser
programs can be viewed as the descendants, respectively, of the DD-21 and CG-21. The
acronym SC-21 is still used in the Navy’s research and development account to designate
(continued...)
CRS-2
! a destroyer called DD(X) for the precision long-range strike and
naval gunfire mission,
! a cruiser called CG(X) for the air defense and ballistic missile
mission,2 and
! a smaller combatant called the Littoral Combat Ship (LCS) to
counter submarines, small surface attack craft (also called “swarm
boats”) and mines in heavily contested littoral (near-shore) areas.3
On April 7, 2006, the Navy announced that it had redesignated the DD(X)
program as the DDG-1000 program. The Navy also confirmed in that announcement
that the first ship in the class, DDG-1000, is to be named the Zumwalt, in honor of
Admiral Elmo R. Zumwalt, the Chief of Naval operations from 1970 to 1974. The
decision to name the first ship after Zumwalt was made by the Clinton
Administration in July 2000, when the program was still called the DD-21 program.4
Planned Surface Combatant Force Structure. The Navy in coming
years wants to achieve and maintain a fleet of 313 ships, including 88 cruisers and
destroyers and 55 LCSs.5 The 88 cruisers and destroyers are to include 7 DDG-
1000s, 19 CG(X) cruisers, and 62 older Arleigh Burke (DDG-51) class Aegis
destroyers.6
Planned DDG-1000 Procurement Through FY2013. Table 1 shows
actual and planned procurement of DDG-1000s in the FY2009-FY2013 Future Years
Defense Plan (FYDP). As shown in the table, the Navy plans to procure all 7 DDG-
1000s by the end of the FYDP. The Navy originally envisaged procuring a total of
16 to 24 DDG-1000s. Navy officials subsequently testified in February and March
1 (...continued)
the line item (i.e., program element) that funds development work on both the DDG-1000
and CG(X).
2 For more on the CG(X) program, see CRS Report RL34179, Navy CG(X) Cruiser
Program: Background, Oversight Issues, and Options for Congress, by Ronald O’Rourke.
3 For more on the LCS program, see CRS Report RL33741, Navy Littoral Combat Ship
(LCS) Program: Oversight Issues and Options for Congress, by Ronald O’Rourke.
4 For more on Navy ship names, see CRS Report RS22478, Navy Ship Names: Background
For Congress, by Ronald O’Rourke.
5 For more on the proposed 313-ship fleet, see CRS Report RL32665, Navy Force Structure
and Shipbuilding Plans: Background and Issues for Congress, by Ronald O’Rourke.
6 The Navy’s 62 DDG-51s were procured between FY1985 and FY2005. The first entered
service in 1991. By the end of FY2006, 49 had entered service and the remaining 13 were
in various stages of construction, with the final ships scheduled to be delivered in 2010 or
2011. The Navy plans to give DDG-51s a mid-life modernization and operate them to age
35. (See CRS Report RS22595, Navy Aegis Cruiser and Destroyer Modernization:
Background and Issues for Congress, by Ronald O’Rourke.) The DDG-51s, which displace
about 9,200 tons, are equipped with the Aegis combat system and are therefore referred to
as Aegis destroyers.
CRS-3
2005 that they had a requirement for 8 to 12. The Navy’s 313-ship plan, announced
in February 2006, reduced the planned total to 7.
Table 1. Actual and Planned DDG-1000 Procurement
FY07
FY08
FY09
FY10
FY11
FY12
FY13
DDG-1000
2a
0a
1
1
1
1
1
Source: FY2009-FY2013 Future Years Defense Plan (FYDP).
a. Two DDG-1000s procured in FY2007 using split funding across FY2007 and FY2008.
Ship Missions and Design Features. The DDG-1000 program is
essentially a restructured continuation of the earlier DD-21 program, and the DDG-
1000 will resemble the DD-21 in terms of mission orientation and ship design: The
DDG-1000 is to be a multimission ship with an emphasis on land-attack operations,
reflecting a Navy desire to replace the large-caliber naval gunfire support capability
that the Navy lost in 1990-1992, when it removed its four reactivated Iowa-class
battleships from service.
The DDG-1000 is to have a reduced-size crew (compared to the Navy’s current
destroyers and cruisers) of about 142 sailors so as to permit reduced operating and
support (O&S) costs. The ship is to incorporate a significant number of new
technologies, including a wave-piercing, tumblehome hull design for reduced
detectability, a superstructure made partly of large sections of composite materials
rather than steel or aluminum, an integrated electric-drive propulsion system, a total-
ship computing system for moving information about the ship, automation
technologies for the reduced-sized crew, a dual-band radar, a new kind of vertical
launch system (VLS) for storing and firing missiles, and two copies of a 155mm gun
called the Advanced Gun System (AGS).
With a full load displacement of 14,564 tons, the DDG-1000 design is roughly
50% larger than the Navy’s current 9,500-ton Aegis cruisers and destroyers, and
larger than any Navy destroyer or cruiser since the nuclear-powered cruiser Long
Beach (CGN-9), which was procured in FY1957.
Program Funding. Table 2 shows DDG-1000 funding through FY2013.
The table excludes about $1.1 billion in research and development funding provided
for the predecessor DD-21 program from FY1999 through FY2001. Additional
funding for research and development and for outfitting and post-delivery costs is
programmed for the DDG-1000 program after FY2013.
As can be seen in the table, the Navy is requesting $507 million in FY2009
research and development funding for the DDG-1000 program. This $507 million
is included within $679 million that the Navy is requesting in FY2009 for a line item
(i.e., program element) in the Navy’s research and development account called “SC-
21 Total Ship System Engineering” (PE0604300N, the 100th line item in the
account). This line item includes research and development funding for both the
CRS-4
DDG-1000 and CG(X) programs. The other $172 million requested in this line item
is for the CG(X) program.7
Table 2. DDG-1000 Program Funding, FY2002-FY2013
(millions of then-year dollars, rounded to nearest million)
FY02
Total
thru FY 07 FY08 FY09 FY10
FY11
FY12
FY13
thru
FY06
FY13
Research, Development, Test and Evaluation, Navy (RDTEN) account
DDG-1000a
4548
782
544
507
601
656
419
269
8326
Shipbuilding and Conversion, Navy (SCN) account
DDG-1000 and
1010
2557
2757
0
0
0
0
0
6325
DDG-1001
DDG-1002
0
0
150 2503
0
0
0
0
2653
DDG-1003
0
0
0
51
2663
0
0
0
2714
DDG-1004
0
0
0
0
51
2377
0
0
2428
DDG-1005
0
0
0
0
0
50
2569
0
2619
DDG-1006
0
0
0
0
0
0
50
2347
2397
Outfitting/post-
0
0
0
0
16
61
87
132
295
delivery costsb
Subtotal SCN
1010
2557
2907 2554
2730
2488
2706
2479
19431
TOTAL
5558
3339
3451 3061
3331
3144
3125
2748
27757
Sources: FY2009-FY2013 budget submission of February 2008 and Navy Office of
Legislative Affairs, March 28, 2007. Figures may not add due to rounding.
a. DDG-1000 portion of SC-21 Total Ship System Engineering (PE0604300N). Figures do
not include $1,111.4 million in RDT&E funding provided for DD-21/DD(X) program
in FY1995-FY2001. Additional funding required after FY2013.
b. $513 million in additional outfitting/post-delivery costs programmed after FY2013.
Based on the figures in the table, when $1.1 billion in FY1995-FY2001 DD-
21/DD(X) research and development costs and $513 million in post-FY2013
outfitting and post-delivery costs are included, the Navy estimates the total
acquisition (i.e., development plus procurement) cost of the seven-ship DDG-1000
program at about $29.4 billion in then-year dollars, or an average of about $4.2
billion per ship, not including additional DDG-1000 research and development costs
after FY2013.
Several major technologies developed for the DDG-1000 are to be used on the
CG(X) cruiser and other future Navy ships, so at least some portion of the DDG-1000
7 As discussed in a previous footnote, SC-21 means surface combatant for the 21st Century
and refers to the Navy’s pre-November 2001 SC-21 program to develop a destroyer called
the DD-21 (now called the DDG-1000) and an eventual cruiser called the CG-21 (now
called CG(X)).
CRS-5
program’s research and development costs might be viewed as not truly specific to
the DDG-1000 program. Based on the figures in the table, when the DDG-1000
program’s research and development costs are excluded, the Navy estimates the total
procurement cost of the DDG-1000 program (including $513 million in post-FY2013
outfitting and post-delivery costs) at about $19.9 billion in then-year dollars, or an
average of about $2.8 billion per ship.
Navy Contracting and Management. Since September 30, 2005, the Navy
has managed the DDG-1000 program through a series of separate contracts with
major DDG-1000 contractors, including Northrop Grumman Shipbuilding (NGSB),
General Dynamics Bath Iron Works (GD/BIW), Raytheon, and BAE Systems (the
maker of the AGS). Under this arrangement, the Navy is acting as the overall system
integrator for the program.
Earlier Proposal for Winner-Take-All Acquisition Strategy. Under a
DDG-1000 acquisition strategy approved by the Under Secretary of Defense for
Acquisition, Technology, and Logistics (USD AT&L) on February 24, 2004, the first
DDG-1000 was to have been built by NGSB, the second ship was to have been built
by GD/BIW, and contracts for building the first six were to have been equally divided
between NGSB and GD/BIW.
In February 2005, Navy officials announced that they would seek approval from
USD AT&L to instead hold a one-time, winner-take-all competition between NGSB
and GD/BIW to build all DDG-1000s. On April 20, 2005, the USD AT&L issued
a decision memorandum deferring this proposal, stating in part, “at this time, I
consider it premature to change the shipbuilder portion of the acquisition strategy
which I approved on February 24, 2004.”
Several Members of Congress also expressed opposition to Navy’s proposal for
a winner-take-all competition. Congress included a provision (Section 1019) in the
Emergency Supplemental Appropriations Act for 2005 (H.R. 1268/P.L. 109-13 of
May 11, 2005) prohibiting a winner-take-all competition. The provision effectively
required the participation of at least one additional shipyard in the program but did
not specify the share of the program that is to go to the additional shipyard.
On May 25, 2005, the Navy announced that, in light of Section 1019 of P.L.
109-13, it wanted to shift to a “dual-lead-ship” acquisition strategy, under which two
DDG-1000s would be procured in FY2007, with one to be designed and built by
NGSB and the other by GD/BIW.
Section 125 of the FY2006 defense authorization act (H.R. 1815/P.L. 109-163)
again prohibited the Navy from using a winner-take-all acquisition strategy for
procuring its next-generation destroyer. The provision again effectively requires the
participation of at least one additional shipyard in the program but does not specify
the share of the program that is to go to the additional shipyard.
Milestone B Approval. On November 23, 2005, the USD AT&L, granted
Milestone B approval for the DDG-1000, permitting the program to enter the System
Development and Demonstration (SDD) phase. As part of this decision, the USD
AT&L approved the Navy’s proposed dual-lead-ship acquisition strategy and a low
CRS-6
rate initial production quantity of eight ships (one more than the Navy currently plans
to procure).
Shared Production Arrangement. NGSB and GD/BIW have agreed on a
shared-production arrangement for building DDG-1000s. Under this arrangement,
certain parts of each ship will be built by NGSB, certain other parts of each ship will
be built by GD/BIW, and the remaining parts of each ship would be built by the yard
that does final-assembly work on that ship. The arrangement can be viewed as
somewhat analogous to the joint-production arrangement for Virginia-class
submarines that was proposed by industry and the Navy, and then approved by
Congress in Section 121 of the FY1998 defense authorization act (H.R. 1119/P.L.
105-85 of November 18, 1997).8
GD/BIW will be the final-assembly yard for the first DDG-1000 and NGSB will
be the final-assembly yard for the second. The difference in the two ships’
construction schedules (about six months) is driven in large part by the production
capacities of vendors making certain components for the ships — some of these
vendors can make only one ship-set worth of components at a time. The government
provides these components to the shipyards as government-furnished equipment
(GFE).
Construction Sequence for Two Lead Ships. Until July 2007, it was
expected that NGSB would be the final-assembly yard for the first DDG-1000 and
that GD/BIW would be the final-assembly yard for the second. On July 17 and 18,
2007, it was reported that the Navy was considering the option of instead assigning
the first ship to GD/BIW and the second to NGSB. The potential switch in
construction sequence reportedly was being considered by the Navy in part because
the Navy believed it could provide some additional help in maintaining GD/BIW’s
work force as its DDG-51-related construction work winds down, and because it
could also provide some additional time for NGSB to recover from Katrina-related
damage.9 On September 10, 2007, it was reported that the Navy on July 27 had
issued a request for proposal (RFP) to NGSB and GD/BIW seeking “updated pricing
to reflect a proposed re-sequencing of government furnished equipment.”10 On
September 25, 2007, the Navy announced that it had decided to build the first DDG-
1000 at GD/BIW, and the second at NGSB.11
8 For more on the Virginia-class joint-production arrangement, see CRS Report RL32418,
Navy Attack Submarine Force-Level Goal and Procurement Rate: Background and Issues
for Congress, by Ronald O’Rourke.
9 Christopher P. Cavas, “First DDG 1000 Could Shift To Bath,” Defense News, July 17,
2007; Geoff Fein, “Navy Exploring Workload Options For DDG-1000,” Defense Daily, July
18, 2007.
10 Chris Johnson, “Navy Seeks Information On Possible Schedule Change For DDG-1000,”
Inside the Navy, September 10, 2007.
11 Geoff Fein, “Bath Iron Works To Take Delivery of First Set of DDG-1000 Equipment,”
Defense Daily, September 26, 2007; Christopher P. Cavas, “Bath To Build First DDG
1000,” DefenseNews.com, October 1, 2007; and Chris Johnson, “Navy Changes Equipment
Delivery For First Two DDG-1000 Destroyers,” Inside the Navy, October 1, 2007.
CRS-7
Procurement Cost Cap. Section 123 of the FY2006 defense authorization
act (H.R. 1815/P.L. 109-163 of January 6, 2006), limits the procurement cost of the
fifth DDG-1000 to $2.3 billion, plus adjustments for inflation and other factors.
Surface Combatant Industrial Base
All cruisers, destroyers, and frigates procured since FY1985 have been built at
two shipyards — General Dynamics’ Bath Iron Works (GD/BIW) in Bath, ME, and
the Ingalls shipyard in Pascagoula, MS, that forms part of NGSB.12 Both yards have
long histories of building larger surface combatants. Construction of Navy surface
combatants in recent years has accounted for virtually all of GD/BIW’s ship-
construction work and for a significant share of Ingalls’ ship-construction work.
Navy surface combatants are overhauled, repaired, and modernized at GD/BIW,
NGSB, other private-sector U.S. shipyards, and government-operated naval shipyards
(NSYs).
Lockheed Martin and Raytheon are generally considered the two leading Navy
surface ship radar makers and combat system integrators. Boeing is another system
integrator and maker of Navy surface ship weapons and equipment.
The surface combatant industrial and technological base also includes hundreds
of additional firms that supply materials and components. The financial health of the
supplier firms has been a matter of concern in recent years, particularly since some
of them are the sole sources for what they make for Navy surface combatants.
Oversight Issues for Congress
Accuracy of Navy Cost Estimate
Although the Navy substantially increased its estimates of DDG-1000
procurement costs between 2004 and 2005, some observers believe the Navy is still
underestimating these costs.
October 2007 Report on CAIG Estimate. On October 1, 2007, it was
reported that the Cost Analysis Improvement Group (CAIG), a cost-estimating office
within the Office of the Secretary of Defense, had recently estimated that the first two
DDG-1000s would together cost about $7.2 billion to procure, or about 14% more
than the Navy’s combined estimate for the two ships.13
CBO July 2007 Estimate. The Congressional Budget Office (CBO) believes
that the Navy is significantly underestimating DDG-1000 procurement costs. CBO
12 NGSB also includes the Avondale shipyard near New Orleans, Newport News
Shipbuilding of Newport News, VA, and a fourth facility at Gulfport, MS.
13 “Sticker Price,” Defense Daily, October 1, 2007. See also Christopher P. Cavas, “DDG
1000 Contract Talks Hit Rough Seas,” DefenseNews.com, October 15, 2007, which refers
to “a recent non-Navy estimate” of $7.2 billion for the two ships.
CRS-8
testified in 2007 that it believes the first two DDG-1000s will each cost about 60%
more than the Navy estimates, that the other five ships in the program would each
cost about 75% more than the Navy estimates, and that the complete seven-ship class
consequently would cost about 70% more than the Navy estimates. CBO testified in
July 2007 that:
The [Navy’s FY]2008 budget suggests that the Navy expects the first two
ships to cost $3.0 billion each and the following five to cost an average of $2.0
billion apiece — meaning that the entire class would have an average cost of $2.3
billion per ship. CBO, by contrast, estimates that the first two DDG-1000s would
cost $4.8 billion apiece and the next five would cost an average of $3.5 billion
each. The average per-ship cost of the class would be $3.9 billion....
The Navy’s estimate for the two lead ships of the DDG-1000 class is
equivalent to about $230 million (in 2008 dollars) per thousand tons of lightship
displacement (the weight of the ship without its fuel, payload, or crew). That
figure is smaller than the cost of the lead DDG-51 class destroyer or the lead
Ticonderoga class cruiser.... CBO’s estimate for the first two DDG-1000s —
which equals $380 million per thousand tons — is based on the cost of the lead
DDG-51, adjusted for differences in the size of the two types of ships.
The Navy has argued that comparing the new DDG-1000 with the DDG-51
may not be valid because the older destroyer had various problems in the early
stages of construction that increased its cost. In particular, the design of the ship
was disrupted and delayed because a new design tool being used at the time was
incomplete and not well understood. The design tool had to be abandoned and
the design restarted using more-traditional methods. In comparison, the design
process for the DDG-1000 is going far more smoothly, and the Navy expects to
have the design largely settled when construction begins. In addition, the Navy
says, the DDG-51 was a smaller, more densely built ship and thus, on a
ton-for-ton basis, was more difficult to construct than the DDG-1000 class will
be.
In CBO’s view, however, several factors offset those arguments. First, as
Navy officials often state, lead ships are generally very difficult to build and
typically encounter many problems during construction. The problems with the
first few littoral combat ships and with the lead ship of the LPD-17 class of
amphibious transport docks — both of which are much less complex
technologically than the DDG-1000 — illustrate those difficulties. A survey of
lead-ship programs shows that although many experience problems in design or
construction, those problems vary from program to program. In other words, the
lead DDG-1000 may not face the same difficulties as the lead DDG-51, but it
will have problems of its own that will increase costs and delay construction.
Second, the DDG-1000 program is incorporating 10 new technologies into
the class that are not found on the current generation of destroyers. Those
technologies include an electric drive and a distributed-power system, a
tumblehome hull (which slopes inward above the waterline to make the ship less
visible to radar), the Advanced Gun System, and new radars, as well as
composite materials and stealth coatings for the deckhouse. In the past, the Navy
has typically introduced just three or four new technologies in a new class of
surface combatants.
CRS-9
Finally, a comparison of the Navy’s cost estimates for two more DDG-51s
and for the seventh DDG-1000 (to be purchased in 2013) illustrates the risk for
cost growth in the new destroyer program. The Navy has stated that if the
Congress authorized and bought two additional DDG-51s in 2008 — which
would be the 63rd and 64th ships of their class — those destroyers would cost
a total of $3.0 billion to $3.1 billion, or $1.5 billion to $1.6 billion apiece (in
2008 dollars). At the same time, the Navy’s 2008 budget submission to the
Congress estimates the cost of building the seventh DDG-1000 in 2013 at about
$2.1 billion (in 2013 dollars). Deflated to 2008 dollars (using the inflation index
for shipbuilding that the Navy provided to CBO), that estimate equals about $1.6
billion — or the same as for an additional DDG-51, which would have the
benefit of substantial efficiencies and lessons learned from the 62 models built
previously. The lightship displacement of the DDG-1000 is about 5,000 tons
greater than that of the DDG-51s under construction today. In effect, the Navy’s
estimates imply that those 5,000 extra tons, as well as the 10 new technologies
to be incorporated into the DDG-1000 class, will be free.14
The Navy and CBO have been engaged in an extended conversation about
potential procurement costs for the DDG-1000 and other Navy ships. CBO testified
in July 2007 that in developing its cost estimates,
CBO looks at the relationship between cost and weight (specifically, the cost per
thousand tons of lightship displacement) of analogous past or present ships to
estimate the prices of future naval vessels. That method assumes, broadly
speaking, that what has happened in the past will be repeated in the future. CBO
takes into account changes or productivity improvements in shipbuilding
practices and procedures; but such changes are frequently offset by, for example,
cost increases for labor and materials, unexpected production problems,
increased requirements, or new technologies.
In testimony before the Congress, some Navy officials have characterized
CBO’s methodology as “worst-case analysis” or an “extremely conservative”
estimating technique that seeks to include all possible sources of cost risk.
Despite its purported conservatism, however, that method would have
understated the actual costs of the littoral combat ship [LCS], the LPD-17
amphibious warfare ship, and the CVN-76 and CVN-77 aircraft carriers, and it
would have closely approximated the cost of the lead Virginia class attack
submarine.15
GAO July 2007 Testimony. Although the Navy publicly stands by its DDG-
1000 cost estimates, the Government Accountability Office (GAO) testified in July
2007 that the Navy has assigned a confidence level of about 45% to its own
estimates, meaning that the Navy itself believes there is about a 55% chance that
DDG-1000s will exceed the Navy’s estimates. GAO testified that:
14 Statement of J. Michael Gilmore, Assistant Director for National Security, and Eric J.
Labs, Senior Analyst, [on] The Navy’s 2008 Shipbuilding Plan and Key Ship Programs,
before the Subcommittee on Seapower and Expeditionary Forces, Committee on Armed
Services, U.S. House of Representatives, July 24, 2007, pp. 14-16.
15 Ibid, p. 22.
CRS-10
One way to improve the cost-estimating process is to present a confidence
level for each estimate, based on risk and uncertainty analyses. By conducting
an uncertainty analysis that measures the probability of cost growth, the Navy
can identify a level of confidence for its estimates and determine whether
program costs are realistically achievable. Navy cost analysts told us that they
used quantitative risk analyses to test the validity of cost estimates of CVN 78
and DDG 1000. We believe that the Navy and the Department of Defense (DOD)
should take this a step further — requiring a high confidence level threshold
when making program commitments and budget requests. The Defense
Acquisition Performance Assessment Panel recommended an 80 percent
confidence level, meaning that a program has an 80 percent chance of achieving
its estimated costs. Whether this is the right level warrants thoughtful discussion,
but it is worth noting that analyses for CVN 78 and DDG 1000 were well below
an 80 percent confidence level (in the case of DDG 1000 at around 45 percent)
— increasing the likelihood that costs will grow above budget.16
Technical Risk and System Integration
Over the past few years, GAO has reported on the technical risks involved in
developing the several significant new technologies that are to be incorporated into
the DDG-1000. The Navy over the years has worked to retire these risks. GAO
testified in July 2007 that:
The DDG 1000 development has been framed by challenging multi-mission
requirements, resultant numerous technologies and a tight construction schedule
driven by industrial base needs. In the DDG 1000 program, the Navy estimates
that approximately 75 percent of detail design will be completed prior to the start
of lead ship construction in July 2008. Successfully meeting this target, however,
depends on maturing 12 technologies as planned. Currently, three of these
technologies are fully mature. Two DDG 1000 technologies — the volume
search radar and total ship computing environment — have only completed
component-level demonstrations and subsequently remain at lower levels of
maturity. Schedule constraints have also forced the Navy to modify its test plans
for the integrated power system and external communication systems.
The volume search radar, one of two radars in the dual band radar system,
will not have demonstrated the power output needed to meet requirements even
after integrated land-based testing of the prototype radar system is completed in
2009. Production of the radars, however, is scheduled to begin in 2008,
introducing additional risk if problems are discovered during testing. According
to Navy officials, in the event the volume search radar experiences delay in
testing, it will not be integrated as part of the dual band radar into the DDG 1000
deckhouse units that will be delivered to the shipbuilders. Instead, the Navy will
have to task the shipbuilder with installing the volume search radar into the
deckhouse, which program officials report will require more labor hours than
currently allocated. The DDG 1000 program’s experience with the dual band
radar has added significance as the same radar will be used on CVN 78.
16 Government Accountability Office, Defense Acquisitions[:] Realistic Business Cases
Needed to Execute Navy Shipbuilding Programs, Statement of Paul L. Francis, Director,
Acquisition and Sourcing Management Team, Testimony Before the Subcommittee on
Seapower and Expeditionary Forces, Committee on Armed Services, House of
Representatives, July 24, 2007 (GAO-07-943T), pp. 17-18.
CRS-11
In the case of the DDG 1000 total ship computing environment, the Navy
is developing hardware infrastructure and writing and releasing six blocks of
software code. Although development of the first three software blocks
progressed in line with cost and schedule estimates, the Navy has been forced to
defer some of the functionalities planned in software release four to software
blocks five and six due to changes in availability of key subsystems developed
external to the program, introduction of non development items, and changes in
program integration and test needs. The Navy now plans to fully mature the
integrated system following ship construction start — an approach that increases
program exposure to cost and schedule risk in production.
The DDG 1000 program also faces challenges completing testing for its
integrated power system and external communications systems. Currently,
shipbuilder-required equipment delivery dates for these systems do not permit
time for system-level land-based integration testing prior to delivery. As a result,
the Navy has requested funds in fiscal year 2008 for the third shipset of this
equipment so that testing can be completed without interrupting the planned
construction schedules of the first two ships. However, in the event problems are
discovered, DDG 1000 construction plans and costs could be at risk.17
As individual DDG-1000 technologies mature, technical risk in the DDG-1000
program will shift more to the follow-on task of system integration — of getting all
ship’s technologies to work together smoothly in a single platform. In past defense
acquisition programs, system integration has often proven to be at least as
challenging as the task of developing individual new technologies.
As mentioned in the Background Section, the Navy since September 30, 2005,
has been acting as the system integrator for the DDG-1000 program. Problems in the
execution of the Coast Guard Deepwater program18 and the Littoral Combat Ship
(LCS) program led to a reexamination in Congress in 2007 of the concept of the
private-sector lead system integrator (LSI), and to a desire among some Members to
shift certain acquisition functions, including system design and integration, from the
private sector, to where they had migrated starting in the 1990s, back to the federal
government. The Navy’s decision in 2005 to begin acting as the system integrator
for the DDG-1000 program will make the program an early test of DOD’s ability to
once again perform the system-integration function following the downsizing of
DOD’s technical and acquisition workforce that occurred when acquisition functions
were earlier transferred to the private sector. The DDG-1000 program, in addition
to being an early test of DOD’s abilities in this area, may represent a fairly
challenging test, given the number of significant new technologies that are to be
integrated into the ship. Potential oversight questions for Congress include the
following:
17 Government Accountability Office, Defense Acquisitions[:] Realistic Business Cases
Needed to Execute Navy Shipbuilding Programs, Statement of Paul L. Francis, Director,
Acquisition and Sourcing Management Team, Testimony Before the Subcommittee on
Seapower and Expeditionary Forces, Committee on Armed Services, House of
Representatives, July 24, 2007 (GAO-07-943T), pp. 12-13.
18 For additional discussion of the Deepwater program, see CRS Report RL33753, Coast
Guard Deepwater Program: Background, Oversight Issues, and Options for Congress, by
Ronald O’Rourke.
CRS-12
! Does the Navy retain sufficient in-house acquisition and technical
expertise to perform the system-integration functions that the Navy
is to perform under its DDG-1000 contracting strategy?
! Does the Navy’s contracting strategy for the DDG-1000 program
have any implications for how other defense acquisition programs
should be pursued?
Acquisition Strategy for Third and Subsequent Ships
The Navy’s intended acquisition strategy for the third and subsequent DDG-
1000s is unclear. The issue has potentially significant implications for the shared-
production arrangement and the industrial-base effects of the DDG-1000 program
(see discussions below).
Shared Production Arrangement
As mentioned in the Background section, NGSB and GD/BIW have agreed on
a shared-production arrangement for building DDG-1000s. Under this arrangement,
certain parts of each ship will be built by NGSB, certain other parts of each ship will
be built by GD/BIW, and the remaining parts of each ship would be built by the yard
that does final-assembly work on that ship.
It is possible that the Navy might wish to have the two yards compete for the
role of final-assembly yard for the third and subsequent ships in the class. Such a
competition could be done on a one-time basis for all the ships in question, or
serially, for each ship. One potential question for Congress is whether competing the
role of final-assembly yard for the third and subsequent ships, particularly if done on
a one-time basis, would be consistent with the intent of Section 1019 of the
Emergency Supplemental Appropriations Act for 2005 (H.R. 1268/P.L. 109-13 of
May 11, 2005) and Section 125 of the FY2006 defense authorization act (H.R.
1815/P.L. 109-163 of January 6, 2006). As discussed in the Background section,
both of these provisions prohibit the Navy from using a winner-take-all acquisition
strategy for the DDG-1000 program. The provisions require the participation of a
second shipyard in the program, but they do not specify the share of the program that
is to go to the second yard.
Industrial Base
The Navy’s 30-year shipbuilding plan calls for procuring an average of about
1.5 DDG-1000s/CG(X)s over the next 17 years. The light-ship displacement of the
DDG-1000 (about 12,435 tons) is about 79% greater than that of the DDG-51 Flight
IIA design (about 6,950 tons). If shipyard construction work for these two ship
classes is roughly proportional to their light-ship displacements, and if the CG(X) is
about the same size as the DDG-1000, then procuring an average of 1.5 DDG-
1000s/CG(X)s per year might provide an amount of shipyard work equivalent to
procuring about 2.7 DDG-51s per year. Splitting this work evenly between GD/BIW
and the Ingalls shipyard that forms parts of NGSB might thus provide each yard with
the work equivalent of about 1.35 DDG-51s per year.
CRS-13
Supporters of these two yards argued in the 1990s that a total of 3 DDG-51s per
year (i.e., an average of 1.5 DDG-51s per year for each yard), in conjunction with
other work being performed at the two yards (particularly Ingalls), was the minimum
rate needed to maintain the financial health of the two yards.19 Navy officials in
subsequent years questioned whether this figure remained valid. Building the
equivalent of about 2.7 DDG-51s per year equates to about 90% of this rate.
If affordability considerations limit DDG-1000/CG(X) procurement to one ship
per year in FY2011 and subsequent years, the workload for the cruiser-destroyer
industrial base in those years would be reduced substantially from levels that would
be achieved under the Navy’s 30-year plan. Procuring one DDG-1000/CG(X) per
year might provide an amount of shipyard work equivalent to procuring about 1.8
DDG-51s per year, and splitting this work evenly between GD/BIW and Ingalls
might provide each yard with the work equivalent of about 0.9 DDG-51s per year,
which would be equivalent to 60% of the rate cited in the 1990s by supporters of the
two shipyards as the minimum needed to maintain the financial health of the two
yards.
If the Navy at some point holds a competition between the two yards for the
right to be the final assembly yard for all remaining DDG-1000s, the yard that loses
could experience a significant reduction in workloads, revenues, and employment
levels.
Options for Congress
Potential options for Congress for the DDG-1000 program, some of which could
be combined, include the following:
! approve the seven-ship DDG-1000 program as proposed by the
Navy;
! use a block-buy contract for DDG-1000s procured during the five-
year period FY2009-FY2013;
! establish terms and conditions for the acquisition strategy to be used
for the third and subsequent ships in the program;
! defer procurement of the third DDG-1000 from FY2009 to a future
fiscal year, and use the funding requested in FY2009 for the third
DDG-1000 to instead procure other Navy ships in FY2009, such as
an additional San Antonio (LPD-17) amphibious ship and two Lewis
and Clark (TAKE-1) class dry cargo ships;20
19 See, for example, CRS Report 94-343, Navy DDG-51 Destroyer Procurement Rate: Issues
and Options for Congress, by Ronald O’Rourke (out of print, available from author).
20 At a February 27, 2008, hearing on Navy shipbuilding programs before the Defense
subcommittee of the House Appropriations Committee, the chairman of the subcommittee,
(continued...)
CRS-14
! to help accelerate CG(X) procurement, procure three CG(X)s in
FY2011, FY2012, and FY2013 in lieu of the fifth, sixth, and seventh
DDG-1000s;
! as an annual affordability measure, limit DDG-1000/CG(X)
procurement to a combined total of no more than one ship per year;
! as total-program affordability measure, limit DDG-1000/CG(X)
procurement to a combined total of 12 ships (one for each of 12
planned carrier strike groups (CSGs));21
! procure no more than two DDG-1000s for use as technology
demonstrators for future surface combatants (and also as operational
warships), and supplement the industrial base with other work; and
! start design work now on a lower-cost naval gunfire support ship
and/or a lower-cost cruiser-destroyer, and start procuring these ships,
rather than additional DDG-1000s or CG(X)s, when these new
designs are ready for procurement.
With regard to the final option above, for additional discussion of potential
lower-cost ships, see Appendix B.
FY2009 Legislative Activity
The Navy’s proposed FY2009 budget was submitted to Congress in early
February 2009.
20 (...continued)
Representative Murtha, stated that, at the suggestion of subcommittee staff, the
subcommittee is considering the option of deferring procurement of the third DDG-1000
from FY2009 to a future fiscal year and using the funding requested for that ship to instead
procure in FY2009 an additional LPD-17 class ship and two additional TAKE-1 class ships.
For a press report, see, for example, Ashley Roque, “Murtha, Young Press Navy on
Shipbuilding Plan, Look to Alter 2009 Budget,” CongressNow, February 27, 2008.
21 Carrier strike group (CSG) is the Navy’s term for what used to be called carrier battle
group (CVBG).
CRS-15
Appendix A. Earlier DDG-1000 Program Oversight
Issues
Program Affordability and Cost Effectiveness
Procurement Cost Affordability. At the end of a July 19, 2005, hearing on
the DDG-1000 program before the Projection Forces Subcommittee of the House
Armed Services Committee, DOD and Navy witnesses were asked to provide the
subcommittee with their own individual views on the procurement cost figures at
which the lead DDG-1000 and a follow-on DDG-1000 (defined as the fifth ship)
would become unaffordable. At the beginning of part two of the hearing, which was
held on July 20, the chairman of the subcommittee, Representative Roscoe Bartlett,
stated that the figures provided by the witnesses ranged from $4 billion to $4.5
billion for the lead ship and $2.5 billion to $2.9 billion for the fifth ship. CBO’s cost
estimates for the DDG-1000 program are higher than these figures.
Total Life-Cycle Cost Affordability. The Navy argues that, in terms of total
life-cycle cost (i.e., procurement plus lifetime O&S cost), the DDG-1000 is more
affordable than might appear from looking only at procurement cost, because the ship
will have lower lifetime O&S costs than existing Navy cruisers and destroyers. The
Navy has estimated that over a 35-year life cycle, a DDG-1000 would cost an average
of about $12 million or $13 million less per year to operate and support than a DDG-
51. Over a 35-year life, this would equate to a savings of $420 million to $455
million in O&S costs relative to a DDG-51. On this basis, the Navy has argued that
a force of 10 DDG-51s would have a total 35-year O&S cost of $4.2 billion to $4.5
billion less than that of a force of 10 DDG-51s.
Skeptics could argue that reducing a ship’s future O&S costs, though desirable,
does not make that ship any more affordable to procure in the budget that funds its
procurement. Skeptics could also argue that, in terms of total life-cycle cost, the
DDG-1000 is not as affordable as the Navy argues, for the following reasons:
! The Navy’s estimated 35-year O&S savings of $420 million to $450
million only partially offsets difference between the DDG-1000’s
higher procurement cost and the procurement cost of a DDG-51
when DDG-51s are procured at a rate of two per year.
! Office of Management and Budget (OMB) Circular A-9422 and
standard business procedures call for future funding flows to be
calculated on a present-value basis so as to capture the investment
value of money over time. When calculated on this basis, the single-
ship 35-year savings figure is reduced by about 46%, to $226 million
to $242 million, and the 10-ship 35-year savings figure of $4.5 billion
22 U.S. Office of Management and Budget, Circular A-94, Guidelines And Discount Rates
For Benefit-Cost Analysis of Federal Programs, available at [http://www.whitehouse.
gov/omb/circulars/a094/a094.pdf].
CRS-16
(assuming procurement of one ship per year) is reduced by about 53%,
to about $2.1 billion.23
! The above calculations accept the Navy’s estimate that a DDG-1000
would, on a 35-year basis, have an annual O&S cost $12 million to
$13 million less than that of a DDG-51. CBO has questioned the
accuracy of the Navy’s estimate of relative DDG-1000 and DDG-51
O&S costs, and has estimated that the difference might range from
zero to $10 million per year.
Table 3 compares follow-ship DDG-51 and DDG-1000 total procurement and
life-cycle O&S costs using the above figures, which date to 2005. The table uses
constant FY2007 dollars, which results in some adjustments to the above figures. As
can be seen in the table, on a present-value basis, the combined procurement and 35-
year life-cycle O&S cost of the follow-on DDG-1000 is 16% greater than that of the
DDG-51 using the Navy’s estimates, or 91% to 101% greater using CBO’s estimates.
Cost Effectiveness. The Navy argues that the DDG-1000 would be cost
effective because the higher procurement cost of the DDG-1000 compared to
previous Navy surface combatants would be more than offset by the DDG-1000’s
numerous and significant improved capabilities.24 Skeptics could argue that these
23 CRS calculations using the 3.1% real discount rate set forth in Appendix B (Revised
January 2005) for discounting constant-dollar flows of 30 years or more.
24 The Navy states that, compared to the DDG-51, these capability improvements include,
among other things:
— three-fold improvement in capability against anti-ship cruise missiles, including
significantly better radar performance in situations involving near-land radar clutter;
— a 10-fold improvement in overall battle force defense capability, in part because
of a 5-fold improvement in networking bandwidth capacity;
— 15% more capability to defend against group attacks by enemy surface craft (i.e.,
“swarm boats”);
—
a 50-fold improvement (i.e., reduction) in radar cross-section, which dramatically
enhances survivability and reduces by half the total number of missiles that need to be fired
in an intercept engagement;
— a 10-fold increase in operating area against mines in shallow-water regions;
— 3 times as much naval surface fire support capability, including an ability to
answer 90% of Marine Corps calls for fire within 5 minutes, permitting the ship to meet
stated Marine Corps firepower requirements — a capability otherwise unavailable in the
surface fleet — giving the ship a capability roughly equivalent to one-half of an artillery
battalion, and permitting a 65% reduction in Marine Corps artillery;
— a ship design that allows underway replenishment of gun shells, creating the
equivalent of an almost-infinite ammunition magazine and permitting nearly continuous fire
support;
— about 10 times as much electrical capacity available for ship equipment, giving
the ship an ability to support future electromagnetic rail guns and high-energy laser
weapons; and
— features such as an automated fire-suppression system, peripheral vertical launch
system, and integrated fight-through-damage power system that significantly increase ship
survivability.
(continued...)
CRS-17
capability improvements, though significant, are not worth the ship’s cost,
particularly if that cost is closer to CBO’s estimates than to the Navy’s estimates, and
that if the DDG-1000’s most-needed contribution to fleet capabilities is the naval
surface fire support capability provided by the ship’s two AGSs, then the DDG-1000
represents a very expensive way to add this capability to the fleet.
Table 3. Follow-ship DDG-51 and DDG-1000 Costs
(using 2005 cost estimates, expressed in millions of constant FY2007 dollars)
Constant FY2007 dollars
Present-value calculation
35-year
35-year
Procure-
lifecycle
Procure-
lifecycle
ment cost O&S cost Total
ment cost
O&S cost
Total
Navy Estimate
Follow-on DDG-51
1,393
2,115
3,508
1,393
1,133
2,526
Follow-on DDG-1000
2,058
1,627
3,685
2,058
871
2,929
DDG-1000 less DDG
665
(488)
177
665
(262)
403
DDG-1000 as %
148%
77%
105%
148%
77%
116%
DDG-51
CBO Estimate (with $10-million annual DDG-1000 O&S cost savings vs. DDG-51)
Follow-on DDG-51
1,393
1,120
2,513
1,393
600
1,993
Follow-on DDG-1000
3,400
770
4,170
3,400
412
3,812
DDG-1000 less DDG
2,007
(350)
1,657
2,007
(188)
1,819
DDG-1000 as %
244%
69%
166%
244%
69%
191%
DDG-51
CBO Estimate (with zero annual DDG-1000 O&S cost savings vs. DDG-51)
Follow-on DDG-51
1,393
1,120
2,513
1,393
600
1,993
Follow-on DDG-1000
3,400
1,120
4,520
3,400
600
4,000
DDG-1000 less DDG
2,007
0
2,007
2,007
0
2,007
DDG-1000 as %
244%
100%
180%
244%
100%
201%
DDG-51
Source: CRS calculations based on 2005 Navy and CBO DDG-1000 and DDG-51 cost data and a
3.1% real discount rate, as specified in Appendix B to OMB Circular A-94 for discounting constant-
dollar flows of 30 years or more. DDG-51 procurement cost is an average unit cost based on a two-
per-year procurement. (For a three-per-year procurement rate, the average unit procurement cost
would be $1,251 million.)
24 (...continued)
(Source: Points taken from Statement of Admiral Vern Clark, U.S. Navy, Chief
of Naval Operations, Before The House Armed Services Committee Projection
Forces Subcommittee, July 19th, 2005, and Statement of The Honorable John J.
Young, Jr., Assistant Secretary of the Navy (Research, Development and
Acquisition), and RADM Charles S. Hamilton, II, Program Executive Officer For
Ships, Before the Projection Forces Subcommittee of the House Armed Services
Committee on DD(X) Shipbuilding Program, July 19, 2005.)
CRS-18
Mission Requirements
The DDG-1000’s size and procurement cost appear to have been driven not by
any one technology or payload element, but rather by the ship’s total collection of
payload elements, which reflect requirements to perform various missions. These
payload elements include, among other things:
! more gunfire capability than any cruiser the Navy has built since
World War II;
! a vertical launch system (VLS) whose weapon storage volume and
weapon weight capacity are between that of the DDG-51 and Aegis
cruiser designs;25
! an area-defense anti-air warfare (AAW) capability that in some
respects is greater than that of the DDG-51;26
! sonars and other antisubmarine warfare (ASW) systems that are
roughly equivalent to that of the DDG-51;27
! command facilities for a flag-level officer and his command staff
— a feature that previously has been installed on cruisers but not
destroyers;
! a large helicopter flight deck and a hangar and maintenance facilities
for two helicopters or one helicopter and three UAVs;
! additional berthing, equipment-stowage space, and mission-planning
space for a platoon of 20 special operations forces (SOF) personnel;
and
25 Although the DDG-1000 has 80 VLS cells, compared to 96 on the DDG-51 and 122 on
the Aegis cruiser, the DDG-1000’s VLS cells are larger. The Mk 41 VLS cells on DDG-51s
and Aegis cruisers can fire a missile up to 21 inches in diameter, 21 feet in length, and about
3,000 pounds in weight. The Advanced VLS (AVLS) cells on the DDG-1000 can fire a
missile up to 24 inches in diameter, 22 feet in length, and about 4,000 pounds in weight.
26 The Navy states that radars on the DDG-1000 and DDG-51 are roughly equivalent in
terms of dB gain (sensitivity) and target resolution, that the firm track range of the DDG-
1000’s dual-band radar — the range at which it can maintain firm tracks on targets — is
25% greater for most target types than the firm track range of the DDG-51’s SPY-1 radar,
that the DDG-1000’s radar has much more capability for resisting enemy electronic
countermeasures and for detecting targets amidst littoral clutter, that the DDG-1000’s AAW
combat system would be able to maintain 10 times as many tracks as the DDG-51’s Aegis
system, and that the two ships can support roughly equal numbers of simultaneous AAW
engagements. Given the features of the DDG-1000’s AAW system, plus its much-greater
C4I/networking bandwidth, the Navy has stated that replacing a DDG-51 with a DDG-1000
in a carrier strike group would increase the strike group’s AAW capability by about 20%.
27 The Navy states that due to differences in their sonar designs, the DDG-1000 would have
more littoral-water ASW capability, while the DDG-51 would have more blue-water ASW
capability.
CRS-19
! facilities for embarking and operating two 11-meter boats and four
rubber raiding craft (as opposed to two 7-meter boats on the DDG-
51).
The payload elements of the DDG-1000 design reflect an Operational
Requirements Document (ORD) for the DDG-1000 that was approved by the Joint
Staff of DOD in February 2004. Key performance parameters included in this
document include having two AGSs that can each fire 10 rounds per minute, for a
total of 20 rounds per minute.28 DOD states that
During the restructuring of the DD-21 program into the DD(X) program, the
Navy re-evaluated each DD-21 Key Performance Parameter (KPP) to determine
the potential for minimizing the size of the ship and ultimately the cost. The
Navy made many adjustments and the resulting DD(X) KPPs represent the
Navy’s minimum requirements. No other known alternative meets all of the
DD(X) KPPs and provide the sustained, precision, long-range naval surface fire
support that the United States Marine Corps requires.29
Skeptics could argue that, notwithstanding the February 2004 DDG-1000 ORD,
at least some requirements for the DDG-1000 are not clear. A November 2006 GAO
report states:
In December 2005, more than a decade after the Navy and Marine Corps began
to formulate requirements, agreement was reached on the capabilities needed for
naval surface fire support. However, quantifiable measures are still lacking for
volume of fire — the delivery of a large quantity of munitions simultaneously or
over a period of time to suppress or destroy a target. Until further quantifiable
requirements are set for volume of fire, it is difficult to assess whether additional
investment is necessary or the form it should take.30
Skeptics could argue that with estimated DDG-1000 procurement costs now
much higher than they were in February 2004, and in light of the effect that increased
cost appears to have had in reducing planned DDG-1000 procurement, the February
2004 ORD might not reflect a sufficiently up-to-date consideration of how increasing
DDG-1000 capability (and therefore cost) might reduce DDG-1000 numbers and
therefore reduce the collective capability of the total DDG-1000 force. In light of the
reduction in planned DDG-1000 procurement, skeptics could argue, certain
capabilities that might have been viewed as desirable in February 2004 might now
be viewed as less desirable because of their role in increasing DDG-1000 unit cost
and thereby reducing planned DDG-1000 procurement.
Some observers speculate that the Navy and DOD established requirements for
the DDG-1000 without a full appreciation of how large and expensive a ship design
28 Statement by The Honorable Kenneth J. Krieg, Under Secretary of Defense (Acquisition,
Technology and Logistics), Before the Subcommittee on Projection Forces, House Armed
Services Committee, United States House of Representatives, July, 19, 2005, p. 2.
29 Ibid, pp. 6-7.
30 Government Accountability Office, Defense Acquisitions[:] Challenges Remain in
Developing Capabilities for Naval Surface Fire Support, GAO-07-115, November 30, 2006.
CRS-20
the requirements would generate. Naval analyst Norman Friedman, the author of
numerous books on U.S. warship designs, states in a 2004 book on U.S. destroyer
designs that
In past [Navy ship design] practice, the naval policymakers in OpNav [the
Office of the Chief of Naval Operations] would write a draft set of [ship]
characteristics.... The Preliminary Design branch of BuShips [the Bureau of
Ships] or NAVSEA [the Naval Sea Systems Command] would develop sketch
designs to meet the requirements. Often the OpNav policymakers would find the
results outrageous — for example, exorbitantly expensive. Such results would
force them to decide just how important their various requests had been.
Eventually Preliminary Design would produce something OpNav found
acceptable, but that might not actually be built....
In contrast to past practice, no preliminary design [for the DDG-1000] was drawn
up to test the cost of various requirements. Each requirement was justified in
operational terms, (e.g., a level of stealth that would reduce detectability by some
percentage); but those sponsoring the ship had no way of knowing the impact
that a particular combination of such requirements would have. Normally
NAVSEA would have created a series of sketch designs for exactly that
purpose.31
An August 2005 trade press article suggests that growth in DD-21/DDG-1000
requirements (and cost) over time may have been related to the disestablishment of
a Navy ship-design board called the Ship Characteristics Improvement Board (SCIB)
— an entity that Admiral Michael Mullen, who became the Chief of Naval
Operations on July 22, 2005, reestablished under a new name:
Adm. Michael Mullen, the chief of naval operations, has directed the Navy
to re-establish a high-level panel to closely monitor and control the requirements
and configurations of new ships in a bid to rein in the skyrocketing cost of new
vessel procurement.
Adm. Robert Willard, vice chief of naval operations, is leading the effort
as part of a larger undertaking to draw up alternative options for the Navy’s
current shipbuilding program....
In essence, sources said, Mullen is looking to reconstitute the Ship
Characteristics Improvement Board, which eventually became inactive in 2002.
For more than 100 years, the Navy has maintained a high-level group of officials
to advise service leaders on ship design and configuration. This group,
established in 1900 as the General Board has gone through many name changes,
including the Ship Characteristics and Improvement Board in the early 1980s
and, until 2002, the Ship Characteristics and Improvement Panel.
Navy officials say that the panel’s oversight began to wane in the late
1990s, just as the DD-21 program — originally envisioned as a $750 million
replacement for Spruance-class destroyers — took off, before becoming
officially inactive in 2002. Requirements during this time were added to the new
31 Norman Friedman, U.S. Destroyers, An Illustrated Design History, Revised Edition.
Annapolis, Naval Institute Press, 2004, pp. 437 and 447-448. Punctuation as in the original.
CRS-21
destroyer program, some of which raised eyebrows in the Navy, such as the need
for a flag officer quarters. No other ship in that class has accommodations for
an admiral. Still, the DDG-1000 has come to be regarded as a technology carrier
for future surface ships and the price tag has ballooned to $3 billion a copy.
Mullen’s goal, spelled out in a July 25 memo to Willard and provided to
InsideDefense.com, is to put in place a “process that adequately defines warship
requirements and manages changes to those requirements (e.g. Ship
Characteristics Improvement Board) in a disciplined manner, with cost and
configuration control as the paramount considerations.”...
A recent RAND study conducted at the request of Mullen’s predecessor,
retired Adm. Vern Clark, concluded that a key cause for climbing ship costs is
the number of requirements tacked on to a program, according to a consultant
familiar with the findings of the study, which has not been made public.
“So, what I think Mullen has in the back of his head is, ‘I’ve got to get the
requirements process for ships back under control or we’re always going to end
up, every time we talk about a new destroyer, with a $3 billion ship,’” said a
former senior Navy official.
This senior official, who was in a key Pentagon position as the DD-21
program commenced, said that without a panel overseeing the ship’s
configuration and true requirements the new destroyer program became weighed
down with capabilities that carried a high price tag.
“In hindsight, we realized that we had put requirements on the ship that no
one had really vetted for its cost impact on the ship. For example, it was to
operate acoustically silent and risk free in minefields,” said the official. “If the
SCIB had existed, this probably would not have happened.”32
A March 2007 report from the Center for Strategic and Budgetary Assessments
(CSBA) makes a similar point:
For nearly a century, the Navy’s SCIB — a group of high-ranking DoN
[Department of the Navy] officials — worked to balance desired warship
warfighting requirements against their impact on a ship’s final design and
production costs. The primary reason why the Navy lost cost control over the
DD-21/DD(X)/DDG-1000 was that just as the ship entered its design definition
phase, the power of the Navy’s SCIB was waning, replaced by a Joint
requirements definition process with no fiscal checks and balances.33
Some observers, such as Norman Friedman, have raised questions about the
Navy’s decision to use a tumblehome (i.e., inward-sloping) hull for the DDG-1000.
A 2006 magazine article by Friedman, for example,
32 Jason Sherman, “Mullen To Bring Back Panel To Control Ship Configuration, Cost,”
Inside the Navy, August 8, 2005.
33 Robert Work, Know When To Hold ‘Em, Know When To Fold ‘Em: Thinking About Navy
Plans For The Future Surface Battle Line, Washington, Center For Strategic and Budgetary
Assessments, 2007. p. 6. (CSBA Backgrounder, March 7, 2007).
CRS-22
! raises questions about the implications of a tumblehome hull for the
ship’s ability to deal with underwater damage;34
! asks whether the Navy knew at the outset of the DDG-1000 design
process how much a decision to incorporate a tumblehome hull (and
other survivability features) would increase the size of the ship; and
! questions whether the reduced visibility of the tumblehome hull to
certain types of radars — the central reason for using a tumblehome
hull — will be negated by its visibility to high-frequency (HF)
surface wave radars that are now for sale on the international market.
The article, which refers to the DDG-1000 by the previous designation DD(X), states:
In the case of the DD(X), the overriding requirement [in determining the
hull design] was to minimise radar cross section — stealth. Much of the hull
design was dictated by the attempt to reflect radar pulses away from the radar
emitting them, so that radar returns would be minimised. By now the main
technique is well known: slope all flat surfaces and eliminate the corner reflector
created by the juncture of the hull and water....
If the ship could be stabilized sufficiently [against rolling from side to side], then
she would never (or almost never) present any vertical surfaces [to a radar]. In
the case of DD(X), stabilization is apparently achieved using ballast tanks. Such
tanks in turn demand internal volume deep in the ship. Overall, stealth demands
that as much as possible of the overall volume of the ship be buried in her hull,
where the shape of the ship can minimise radar returns. That is why,
paradoxically, a carefully-designed stealthy ship will be considerably larger —
for more internal volume — than a less stealthy and more conventional
equivalent. In the case of DD(X), there were also demands for improved
survivability. The demand for stealth implied that anti-ship missiles were the
most important envisaged threat. They hit above water, so an important
survivability feature would be to put as much of the ship’s vitals as possible
below water — which meant greater demands for underwater volume....
Once the tumblehome hull had been chosen, [the ship’s designers] were
apparently also constrained to slope the bow back [creating a surface-piercing or
ram bow] instead of, as is usual, forward....
There were numerous reasons why [past] naval architects abandoned
tumblehome hulls and ram bows. Tumblehome reduces a ship’s ability to deal
with underwater damage. When a conventional flared (outward-sloping) hull
sinks deeper in the water, its waterplane area [the cross-section of the ship where
it intersects the plane of the water] increases. It becomes somewhat more stable,
and it takes more water to sink it deeper into the water. Because the waterplane
area of a tumblehome ship decreases as it draws more water, such a ship is easier
to sink deeper. Tumblehome also apparently makes a ship less stable, and hence
less capable of resisting extreme weather conditions. The larger the ship, the
34 Other observers have also expressed concerns about the stability of the DDG-1000’s
tumblehome hull in certain see conditions. For a discussion, see Christopher P. Cavas, “Is
New U.S. Destroyer Unstable?,” DefenseNews.com, April 2, 2007.
CRS-23
more extreme the weather has to be to make that critical. Critics of DD(X) have
concentrated on the danger; defenders have concentrated on how extreme the
critical weather condition would be.
In the end, whether the DD(X) hull form is attractive depends on an
evaluation of anti-radar stealth as a design driver. About a decade ago, the
DD(X) design concept was sold on the basis of a lengthy (and, incidentally,
unclassified) analysis, the gist of which was that a heavily-armed surface
combatant could play a decisive role in a Korean scenario...
The key analytic point... was that it would be very important for the ship to
come reasonably close to enemy shores unobserved. That in turn meant anti-
radar stealth. However, it soon came to mean a particular kind of anti-radar
performance, against centimetric-wave radars [radars with wavelengths on the
order of centimeters] of the sort used by patrol aircraft (the ship would fire [its
weapons] from beyond the usual horizons of shore-based radars). As it happens,
anti-ship missiles use much the same kinds of radars as patrolling aircraft, so it
could be argued that the same anti-radar techniques would be effective in the
end-game in which missiles would approach the ship....
Without access to files of the time, it is impossible to say whether those
approving the [DDG-1000] project realised that its stealth and survivability
characteristics would produce a 14,000 to 17,000 ton destroyer. About the same
time that DD(X) characteristics (requirements) were being approved, the decision
was taken at [the] Defense Department (not Navy) level that there would be no
internal feasibility design. In the past, the feasibility stage had the very useful
role of showing those setting requirements what their implications would be. At
the very least, the Navy’s senior leadership would have been given warning that
they would have to justify a drastic jump in destroyer size when they wanted to
build DD(X). That jump might well have been considered justified, but on the
other hand the leadership might also have asked whether a somewhat less
dramatic approach would have been acceptable.
About a decade after the requirements were chosen, with DD(X) well
advanced, the situation with regard to stealth may be changing. Shaping is
relevant only at relatively short [radar] wavelengths. For about a quarter-century,
there has been talk of HF surface wave radars, which operate at wavelengths of
about 10 to 200 meters — i.e. at wavelengths the size of a ship. Canada currently
operates this type of radar, made by Raytheon, for surveillance of the Grand
Banks; another is being tested in the Caribbean. Australia has bought this kind
of radar to fill gaps in over-the-horizon radar coverage. Turkey is buying such
radars for sale for some years. In 2005 it was reported unofficially that China
had bought [a] Russian HF surface wave radar the previous year.
It seems almost certain that HF surface wave radar can defeat any kind of
stealth shaping designed primarily to deal with shorter-wave[length] radars.
Moreover, [HF surface wave] radars have an inherent maximum range (due to the
way they operate) of about 180nm.... At long range [the radar’s beam] is not
nearly accurate enough to aim a missile. However, we can easily imagine a
netted system which would use the long-range [HF surface wave] radar to define
a small box within which the target ship would be. A missile with GPS [Global
Positioning System] guidance could be flown to that box, ordered to search it....
CRS-24
If the argument given here is realistic, then the considerable sacrifices inherent
in the DD(X) design no longer seem nearly as attractive. It can still be argued
that a design like the DD(X) is attractive well out to sea, beyond the reach of
coastal radars. In that case, however, there may be other signatures which can
be exploited. For example, ships proceeding at any speed create massive
wakes.... it is clear that the wake produces a radar return very visible from an
airplane or, probably, from a space-based radar....
In the end, then, how much is stealth worth? As a way of avoiding
detection altogether, probably less than imagined. That leaves the rather
important end-game, the hope being that decoys of some sort greatly exceed
actual ship radar cross-section. That is probably not a foolish hope, but it does
not require the sort of treatment reflected in [the] DD(X).
Now, it may be that the Untied States typically faces countries which have
not had the sense to buy anti-stealth radars (though we would hate to bet on that).
In that case, DD(X) may well be effectively invisible to them. So will a lot of
less thoroughly stealthy ships.35
Potential oversight questions for Congress include the following:
! SCIB and DDG-1000 requirements. Are the DDG-1000’s
requirements partly a result of inadequate discipline, following the
disestablishment of the SCIB, in the Navy’s process for setting
requirements for new ships? If the SCIB had remained in existence
during the DD-21/DDG-1000 design process, which of the DDG-
1000’s current requirements would have been reduced or
eliminated?
! Tumblehome hull. How much did the decision to use a
tumblehome hull (and other survivability features) increase the size
and cost of the DDG-1000? In the mid-1990s, when design work
began on the ship now known as DDG-1000, how well did the Navy
understand the relationship between using a tumblehome hull and
ship size and cost? What effect does the tumblehome hull have on
the DDG-1000’s ability to deal with underwater damage? To what
degree will HF surface wave radars negate the stealth characteristics
of the DDG-1000 design?
! AGSs. Since the DDG-1000 is the only ship planned to carry AGSs,
and since AGSs are viewed by the Marine Corps as necessary to
meet Marine Corps requirements for naval surface fire support
capability, should the AGSs be considered the most-critical payload
element on the DDG-1000, and certain other payload elements,
though desirable, be considered as possibly less critical by
comparison?
35 Norman Friedman, “The New Shape of Ships,” Naval Forces, No. II, 2006: 56-58, 60, 62-
63. Italics as in the original. Friedman makes somewhat similar comments in chapter 17
(pages 431-450) of U.S. Destroyers, An Illustrated Design History, Revised Edition, op cit.
CRS-25
! Hangar. In light of the 167 or more current or planned helicopter
hangar spaces on other Navy surface combatants (2 spaces on each
of 22 Aegis cruisers and the final 34 DDG-51s, and at least 1 space
on each of 55 LCSs), and the relatively limited number of Navy
helicopters available for filling those spaces, how critical is it for the
DDG-1000 to have a hangar with spaces for two helicopters?
Would it be acceptable for the DDG-1000 instead to have only a
helicopter landing platform and an ability to refuel and rearm
helicopters, like the first 28 DDG-51s?
! VLS tubes. In light of the 8,468 vertical launch system (VLS)
missile tubes on the Navy’s planned force of 84 VLS-equipped
Aegis ships (22 cruisers with 122 tubes each, 28 earlier DDG-51s
with 90 tubes each, and 34 later DDG-51s with 96 tubes each), the
ability of VLS tubes to store and fire either one 21-inch diameter
missile or four smaller-diameter Evolved Sea Sparrow Missiles
(ESSMs), the ability in a networked force for a ship to control a
missile fired by another ship, and the DDG-1000’s key role in
providing naval gunfire support with its two AGSs, how critical is
it for the DDG-1000 to have 80 enlarged VLS tubes as opposed to
a smaller number, such as 64, 48, or 32?
! Command facilities. In light of the flag-level command facilities
on the 22 Aegis cruisers, as well as additional command facilities on
aircraft carriers and planned amphibious assault ships, how critical
is it for the DDG-1000 to have flag-level command facilities?
! SOF support facilities. In light of SOF support facilities on the
Navy’s planned force of four converted Trident submarines, or
SSGNs (66 or more SOF personnel for each ship),36 support
facilities for smaller numbers of SOF on Navy attack submarines
(SSNs), and the secondary SOF support role for the Navy’s planned
force of 55 LCSs, how critical is it for the DDG-1000 to have SOF
support facilities?
! AAW system. In light of the Aegis area-defense AAW systems on
the Navy’s 84 Aegis cruisers and destroyers — which, though not as
capable in some respects as the DDG-1000’s AAW system in littoral
operating environments, would still be quite capable, particularly
when numbers of Aegis ships are taken into account — how critical
is it for the DDG-1000 to have an area-defense-capable AAW
system, as opposed to a more modest point-defense AAW system
capable of defending only the DDG-1000 itself (which might be
36 For more on the SSGN program, see CRS Report RS21007, Navy Trident Submarine
Conversion (SSGN) Program: Background and Issues for Congress, by Ronald O’Rourke.
CRS-26
closer to the more modest AAW system that was originally
envisaged for the DD-21, the precursor to the DDG-1000)?37
37 Earlier editions of this report also asked the following question:
Gun shell capacity. In light of the DDG-1000 design feature that allows
underway replenishment of gun shells, creating the equivalent of an
almost-infinite ammunition magazine and permitting nearly continuous fire
support, how critical is it for the DDG-1000 to have a total gun shell capacity of
920 shells, as opposed to a smaller number, such as 600?
A December 2005 press stated that, as part of an effort to reduce the cost of the DDG-1000, the
Navy had reduced the magazine capacity of the design from 920 shells to 600. (Christopher P.
Cavas, “U.S. Ship Plan To Cost 20% More,” Defense News, December 5, 2005: 1, 8.)
CRS-27
Appendix B. Potential Lower-Cost Ships
Lower-Cost Gunfire Support Ship
CBO and naval analyst Robert Work of the Center for Strategic and Budgetary
Assessments (CSBA) have both suggested, as a lower-cost naval gunfire support
ship, an AGS-equipped version of the basic hull design of the San Antonio (LPD-17)
class amphibious landing ship. Such a ship might begin procurement in FY2009,
following procurement of a final “regular” LPD-17 amphibious landing ship in
FY2008. CBO estimates that an initial AGS-armed LPD-17 might cost about $1.9
billion, including $400 million detailed design and nonrecurring engineering costs,
and that subsequent ships might cost about $1.5 billion each.38
Lower-Cost Cruiser-Destroyer
A new-design, lower-cost cruiser-destroyer might:
! start procurement as soon as FY2011, if design work were started
right away;
! incorporate many of the same technologies now being developed for
the DDG-1000 and CG(X);
! employ a modular, “plug-and-fight” approach to some of its weapon
systems, like the LCS;
! be similar to the DDG-1000 and CG(X) in terms of using a reduced-
size crew reduce annual operation and support costs;
! use a second-generation surface combatant integrated electric-drive
propulsion system that is smaller and lighter than the first-generation
system to be installed in the first DDG-1000s;39
! carry a payload — a combination of sensors, weapon launchers,
weapons, and aircraft — that is smaller than that of the DDG-1000
or CG(X), but still sizeable; and
! be built in one or two variants — an air- and missile-defense version
to replace the CG(X), which would preserve CG(X) radar
38 See Congressional Budget Office, Options for the Navy’s Future Fleet, May 2006, pp. 56-
57 (Box 3-1).
39 The integrated electric-drive system to be installed in the first DDG-1000s uses advanced
induction motors. A second-generation system could use smaller and lighter motors and
generators that employ permanent magnet or high-temperature superconducting technology.
Both of these technologies are currently being developed. For more on these technologies,
see CRS Report RL30622, Electric-Drive Propulsion for U.S. Navy Ships: Background and
Issues for Congress, by Ronald O’Rourke. (July 31, 2000)
CRS-28
capabilities while reducing other payload elements, and possibly also
a surface fire support version to supplement the DDG-1000, which
would preserve the DDG-1000’s two AGSs while reducing other
payload elements.
Notional options for a lower-cost cruiser-destroyer include, but are not limited
to, the following:
! a ship displacing about 9,000 tons — about the same size as the
DDG-51; or
! a ship displacing about 11,000 tons — about 25% less than the
DDG-1000’s displacement of about 14,500 tons, about the same size
as the nuclear-powered cruisers procured for the Navy in the 1960s
and 1970s, and about 1,800 tons larger than the DDG-51.
Such a ship might be based on either the DDG-51 hull design, which is a
conventional flared hull that slopes outward as it rises up from the waterline, 40 or a
new flared hull design, or a reduced-sized version of the DDG-1000’s tumblehome
(inwardly sloping) hull design.
The Navy in 2002 identified the following ship-design characteristics as items
that, if varied, would lead to DDG-1000 concept designs of varying sizes,
capabilities, and procurement costs:
! cruising range,
! maximum sustained speed,
! number of Advanced Gun Systems (AGSs) and AGS shells,
! hangar space for helicopters and UAVs,
! undersea warfare systems (i.e., sonars and mine countermeasures
systems), and
! numbers and types of boats for special operations forces.
Using these variables, the Navy in 2002 developed notional DDG-1000 concept
designs with estimated full load displacements ranging from 12,200 tons to about
16,900 tons. One of the concept designs, with an estimated full load displacement
of about 12,700 tons, included 32 Advanced Vertical Launch System (AVLS) cells
(rather than the DDG-1000’s 80), two AGSs (like the DDG-1000), 600 AGS shells
(like the DDG-1000), a maximum sustained speed a few knots lower than the DDG-
1000’s, and a helicopter flight deck smaller than the DDG-1000’s. Another concept
design, with an estimated full load displacement of about 12,200 tons, included 64
AVLS cells, 1 AGS, 450 AGS rounds, a maximum sustained speed a few knots lower
than the DDG-1000’s, and helicopter flight deck smaller than the DDG-1000’s.
40 Using the DDG-51 hull in its current dimensions might produce a ship of about 9,000
tons; lengthening the DDG-51 hull with a mid-hull plug might produce a ship of about
11,000 tons.
CRS-29
The Navy in 2003 developed another set of notional DDG-1000 concept designs
with estimated full load displacements ranging from 11,400 tons to 17,500 tons. One
of the concept designs, with an estimated full load displacement of 13,400 tons,
included 64 AVLS cells, 1 AGS, and 450 AGS rounds. Another concept design, with
an estimated full load displacement of 11,400 tons, included 32 AVLS cells, 1 AGS,
and 300 AGS rounds.
The 2002 and 2003 notional DDG-1000 concept designs with displacements of
less than 14,000 tons appear to have preserved other DDG-1000 features, such as the
wave-piercing, tumblehome hull, the integrated electric drive system (though with
reduced total power in at least some cases), the total ship computing environment,
the autonomic fire-suppression system and other features permitting a reduced-sized
crew, the DDG-1000 radar suite, the hull and towed-array sonars, medium-caliber
guns for use against surface targets, and a helicopter hangar (though not necessarily
as large a hangar as on the DDG-1000).
Reducing payload features a bit more than under the smallest of the 2002 and
2003 notional concept designs might lead to a design with a displacement of about
9,000 to 11,000 tons. The Navy has viewed designs of less than 14,000 tons as
unsatisfactory because of their reduced individual capabilities. It is not clear,
however, to what degree the Navy’s assessment of such designs also takes into
account the difference that size (and thus unit procurement cost) can have on the total
number of ships that might be procured within available resources, and consequently
on future cruiser-destroyer force levels. Total cruiser-destroyer force capability is
dependent on both cruiser-destroyer unit capability and the total number of cruisers
and destroyers.
Notional Procurement Profiles With Lower-Cost Ships
Table 4 and Table 5 show notional procurement profiles incorporating the ships
described above. In Table 4, an AGS-equipped version of the basic LPD-17 hull
design is procured to supplement the Navy’s DDG-1000s, and an air- and missile-
defense version of the smaller cruiser-destroyer is procured starting in FY2011 in lieu
of the CG(X). In Table 5, a smaller cruiser-destroyer in two versions — an AGS-
equipped version to supplement the Navy’s DDG-1000s, and air- and missile-defense
version in lieu of the CG(X) — is procured starting in FY2011.
Table 4. Alternative With LPD (AGS)
and Smaller Cruiser-Destroyer
(annual quantities procured, FY2007-FY2021)
07
08
09
10
11
12
13-21
Total
DDG-1000
2a
0a
1
1
4
LPD (AGS)b
1
1
1
2
5
SCDc
1
2/year
19
Source: Prepared by CRS.
a. Each of the two ships to be procured in FY2007 is to be split-funded across FY2007 and FY2008.
b. Basic LPD-17 hull equipped with 2 Advanced Gun Systems (AGSs).
c. Air- and missile-defense version of smaller cruiser-destroyer (SCD), in lieu of CG(X).
CRS-30
Table 5. Alternative With Smaller Cruiser-Destroyer
(annual quantities procured, FY2007-FY2022)
07
08
09
10
11
12
13-22
Total
DDG-1000
2a
0a
1
1
1
5
SCDb
1
2/year
21b
Source: Prepared by CRS.
a. Each of the two ships to be procured in FY2007 is to be split-funded across FY2007 and FY2008.
b. Includes 2 AGS-equipped versions of smaller cruiser-destroyer (SCD), for a total (along with 5
DDG-1000s) of 7 AGS-equipped ships, and 19 air- and missile-defense versions, in lieu of
CG(X).
CSBA Report Recommendations
A March 2007 report from the Center for Strategic and Budgetary Assessments
(CSBA) on the Navy’s surface combatant force discusses existing and future Navy
surface combatants and makes the following recommendations (emphasis as in the
original):
— First, “fold” the CG-21 hand: cancel all planned new CG-21s [i.e., DDG-
1000s and CG(X)s] beyond the two DDG-1000s already authorized.41 A
variation of this plan would be to build just one ship. By building two (or one)
operational test beds/technology demonstrators, the Navy can recoup most of the
previous “bets” made on the CG-21s. Having one or two test ships would allow
further testing and refinement of the SPY-3 multifunction radar, which is to be
installed on future aircraft carriers regardless of what happens with the
DDG-1000, and perhaps on other ships. Over time, the ships could be modified
to test other future surface combatant combat systems such as underwater combat
systems or electronic warfare systems. Regardless of configuration, the ships
would provide the battle fleet with a test article for new integrated power system
components as well as electrically-powered weapons. In this role, the less
capable advanced induction motor to be installed on the first two DDG-1000s
ships will be as effective as the permanent magnet motor — the Navy’s desired
electric motor. The ships’ larger VLS cells would allow the Navy to test larger
diameter guided missiles. In fleet exercises, the ships would help to identify the
true operational payoffs of ship stealth within the context of distributed naval
battle networks. Finally, these large ships with small crews would help the Navy
to refine the maintenance concepts for future optimally manned fleet combatants
(i.e., warships with reduced crews).
— Second, “hold” the Aegis/VLS fleet: design a comprehensive, Aegis/VLS
Battle Network Reliability and Maintenance (BNRAM) program, with the
goal of producing the maximum number of interchangeable, Interim Large
Battle Network Combatants. (I-LBNCs). The Navy’s ultimate goal is to shift
to a new Large Battle Network Combatant, or LBNC — a far better description
of future Total Force Battle Network [TFBN] ships-of-the-line than the
multimission guided-missile “cruisers” and “destroyers” or general-purpose
“destroyers” associated with today’s legacy Total Ship Battle Force. Until they
can be designed, betting an additional $10-15 billion on five or six additional
41 The CSBA report uses the term CG-21s to refer collectively to DDG-1000s and CG(X)s.
CRS-31
DDG-1000s would appear to provide far less of a TFBN payoff than making a
similar sized or even smaller bet on a well-thought-out and executed BNRAM
program to convert the 84 programmed Aegis/VLS warships into more powerful
I-LBNCs. This conversion program would be patterned after earlier
modernization and conversion efforts, like the Fleet Reliability and Maintenance
(FRAM) program, which converted many of the large legacy fleet of World War
II destroyers into effective Cold War ASW escorts. The BNRAM would include
a thorough mid-life upgrade to the ships’ hull, machinery and electrical (HM&E)
systems; a combat systems upgrade to allow the ships to counter emerging
threats; and a battle network upgrade to allow the ships to operate as part of a
coherent naval battle network. Consistent with battle network precepts, the intent
of the BNRAM would be to bring as many ships as possible to a common
I-LBNC combat system baseline. The BNRAM would also aim to lower
substantially the operations and maintenance costs (O&M) costs necessary to
operate the legacy Aegis/VLS fleet, in order to save money in the near term, and
to offset to some degree the added costs necessary to keep older ships in service
over the longer term. A key part of this effort centers on reducing the crew size
needed to operate, maintain, and fight the ships. Importantly, because this effort
can justifiably be seen as converting legacy Aegis/VLS ships into more capable
I-LBNCs, the BNRAM should be funded out of more stable Ship Construction
Navy (SCN) funds rather than the more volatile O&M accounts.
— Third, immediately kick-start a clean-sheet competition to develop and
design a family of next-generation Large Battle Network Combatants, with
close oversight by the newly reconstituted Ship Characteristics
Improvement Board (SCIB). For nearly a century, the Navy’s SCIB — a group
of high-ranking DoN [Department of the Navy] officials — worked to balance
desired warship warfighting requirements against their impact on a ship’s final
design and production costs. The primary reason why the Navy lost cost control
over the DD-21/DD(X)/DDG-1000 was that just as the ship entered its design
definition phase, the power of the Navy’s SCIB was waning, replaced by a Joint
requirements definition process with no fiscal checks and balances. One of the
first things Admiral Mike Mullen, the current Chief of Naval Operations, did
upon assuming his office was to reconstitute the Navy’s SCIB. With a chance to
start from a clean sheet of paper, naval design architects could leverage an
additional decade of experience in the post-Cold War era to design an entirely
new family of next-generation LBNCs, under the close oversight of the newly
reconstituted SCIB. These new warships would have a common gas turbine or
perhaps even a nuclear power plant that supplies enormous shipboard electrical
generating capacity; common electric propulsion motors; common integrated
power systems that distribute electric power to the ships’ electric motors, combat
systems, and weapons, as needed; and advanced automation to enable them to
operate with relatively small crews. Their single common hulls, or network
frames, should be large and easily produced, based on the best ideas of naval
engineers, with an affordable degree of stealth. The network frames would be
able to accept a range of open architecture battle network mission modules
consisting of sensors and onboard and offboard weapons designed explicitly to
support a battle network rapid capability improvement strategy. The
cost-constrained goal for the combination of network frames and network
mission modules would be to build new LBNCs at a rate of five every two years,
allowing the complete transition from 84 Aegis/VLS I-LBNCs to 88
next-generation LBNCs in 35 years. The ships would be built under a
profits-related-to-offer arrangement. While each of the two remaining surface
combatant shipyards could count on building one LBNC per year, they would
compete for an extra ship every other year. The yard with the lowest bid would
CRS-32
be able to claim higher profit margins on the two LBNCs it would build until the
next bi-annual competition. In this way, in addition to the natural cost savings
due to learning curve efficiencies, the Navy would be able to spark continuous
competition between the two building yards.
— Starting in FY 2008, build a minimum of seven additional [Arleigh]
Burke-class DDGs [i.e., DDG-51s] to help sustain the industrial base until
the new LBNC is ready for production. In effect, building one modified Burke
each year between FYs 2008 and 2014 would replace the seven DDG-1000s in
the current plan. For reasons that are detailed in the forthcoming report, the first
four modified Burkes would be configured with the same Area Air Defense
Command Capability System (AADCCS) found on the Ticonderoga-class CGs.
In addition, all seven ships would serve as active test beds for DDG
improvements identified as possible candidates for further BNRAM backfits, or
to test next-generation LBNC technologies. As such, the ships would serve much
the same purpose as both the Forrest Sherman-class destroyers — which helped
to bridge the shipbuilding gap between World War II combatants and Cold War
combatants designed to battle jets, missiles, and high-speed submarines — and
modified legacy combatants like the USS Gyatt, DDG-1, which helped to
illuminate the way forward toward a new generation of BFC combatants.
Provided all went as planned, Congress would authorize two of the
next-generation LBNCs in FY 2015, split funded as in the current arrangement
for the DDG-1000, giving each of the two remaining surface combatant
construction yards one ship. The general fleet-wide transition from Aegis/VLS
I-LBNCs to the new LBNC design would then begin in FY 2017, with three ships
authorized after a bidding competition. Of course, if the design was not ready for
production, additional Burkes could be built until it was.
— Task each of the planning yards for CG and DDG modernization to
design and implement a comprehensive follow-on maintenance regime to
ensure all Aegis/VLS combatants are able to serve out the remainder of
their 35-year service lives effectively. The Navy’s plan counts on every one of
the 84 programmed Aegis/VLS combatants of completing 35 years of
commissioned service. Yet, since the end of World War II, few surface
combatants remain in commission beyond 25-30 years of service — even after
receiving mid-life upgrades. Unless the BNRAM program includes a sustained
maintenance regime beyond its mid-life HM&E, combat systems, and battle
network upgrades and crew reduction measures, it is unlikely the ships will see
their 35th year. The building shipyards might be the logical organizations to
implement this new maintenance regime on the Navy’s behalf. By establishing
financial incentives that provide the yards with bonuses for every year a ship
stays in service beyond 25 years, the Navy will maximize the probability that the
ships will remain in service. As part of their efforts, the yards and the Navy
should also solicit ideas for further ship improvements from vendors, and
complete the trade studies for an expanded service life extension program
(SLEP) of the existing ships, with a goal of extending their expected service lives
to 40 years. This would provide a hedge should design work on the next-
generation LBNC be delayed for any reason, or if a future maritime challenge
spurs the need to rapidly expand the number of large combatants beyond the 88
included in the 313-ship Navy.42
42 Robert Work, Know When To Hold ‘Em, Know When To Fold ‘Em: Thinking About Navy
(continued...)
CRS-33
crsphpgw
42 (...continued)
Plans For The Future Surface Battle Line, Washington, Center For Strategic and Budgetary
Assessments, 2007. pp. 5-8. (CSBA Backgrounder, March 7, 2007).