Order Code RL33875
Electric Transmission: Approaches for
Energizing a Sagging Industry
Updated October 3, 2007
Amy Abel
Specialist in Energy Policy
Resources, Science, and Industry Division

Electric Transmission: Approaches for Energizing
a Sagging Industry
Summary
The electric utility industry is inherently capital-intensive. At the same time, the
industry must operate under a changing and sometimes unpredictable regulatory
system at both the federal and state level. The transmission system was developed
to fit the regulatory framework established in the 1920 Federal Power Act — utilities
served local customers in a monopoly service territory. The transmission system was
not designed to handle large power transfers between utilities and regions.
Enactment of the Energy Policy Act of 1992 (P.L. 102-486) created tension between
the regulatory environment and the existing transmission system: The competitive
generation market encouraged wholesale, interstate power transfers across a system
that was designed to protect local reliability, not bulk power transfers.
The blackout of 2003 in the Northeast, Midwest, and Canada highlighted the
need for infrastructure improvements and greater standardization of operating rules.
The Energy Policy Act of 2005 (P.L. 109-58) set in place government activities
intended to relieve congestion on the transmission system. The law creates an
electric reliability organization that is to enforce mandatory reliability standards for
the bulk-power system. In addition, processes are established to streamline the siting
of transmission facilities. Many observers predict that until the electric power
industry reaches a new equilibrium with more regulatory certainty, investment in
transmission infrastructure and technology will continue to be inadequate.
This report discusses factors that have contributed to the lack of new
transmission capacity and some of the resulting issues, including
! background on the evolution of the regulatory structure, including
the creation of an electric reliability organization (ERO);
! issues associated with operating a congested transmission system;
! security of the physical assets;
! siting of transmission lines;
! cost implications of burying power lines;
! pricing of new transmission projects; and
! funding of these projects.
In addition, this report reviews approaches being taken to address the lack of
investment in transmission infrastructure and transmission congestion.

Contents
Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Historical Context . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Current Issues . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
Physical Limitations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
Congestion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
Security . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
Siting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
Alternatives to New Rights-of-Way . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Burying Power Lines . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
Undergrounding Transmission . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
Pricing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
Regulatory Uncertainty . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Investment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
Conclusion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
List of Figures
Figure 1. Western Transmission Congestion, 1999-2005 . . . . . . . . . . . . . . . . . . . 4
Figure 2. Mid-Atlantic Area National Interest Electric Transmission
Corridor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Figure 3. Southwest Area National Interest Electric Transmission
Corridor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Figure 4. Real Private Fixed Investment in Electrical Power
Generation, and Electricity Consumption, Generation, and Real Prices . . 10
Figure 5. Congested Lines in the Eastern Interconnection . . . . . . . . . . . . . . . . . . 24
List of Tables
Table 1. Revenue Requirements for IOUs To Convert Florida’s
Existing Transmission Facilities to Underground, and Rate Impact
Over 10-Year Period . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19

Electric Transmission: Approaches for
Energizing a Sagging Industry
Introduction
The electric utility industry is inherently capital-intensive. At the same time, the
industry must operate under a changing and sometimes unpredictable regulatory
system at both the federal and state level. Inconsistent rules and authorities can result
in inefficient operation of the interstate transmission system. The electric
transmission system has been affected by a combination of factors that has resulted
in insufficient investment in the physical infrastructure.
This report discusses factors that have contributed to the lack of new
transmission capacity and some of the resulting issues, including
! background on the evolution of the regulatory structure, including
the creation of an electric reliability organization (ERO);
! issues associated with operating a congested transmission system;
! security of the physical assets;
! siting of transmission lines;
! cost implications of burying power lines;
! pricing of new transmission projects; and
! funding of these projects.
In addition, this report reviews approaches being taken to address the lack of
investment in transmission infrastructure and transmission congestion.
The transmission system was developed to fit the regulatory framework
established in the 1920 Federal Power Act1 — utilities served local customers in a
monopoly service territory. The transmission system was not designed to handle
large power transfers between utilities and regions. Enactment of the Energy Policy
Act of 1992 (EPACT92)2 created tension between the regulatory environment and the
existing transmission system. EPACT92 effectively deregulated wholesale
1 16 U.S.C. 791a et seq.
2 P.L. 102-486.

CRS-2
generation by creating a class of generators that were able to locate beyond a typical
service territory with open access to the existing transmission system. The resulting
competitive market encouraged wholesale, interstate power transfers across a system
that was designed to protect local reliability, not bulk power transfers.
The blackout of August 2003 in the Northeast, Midwest, and Canada
highlighted the need for infrastructure and operating improvements. However, a
conflict exists between the apparent goal of increasing competition in the generation
sector and assuring adequate transmission capacity and management of the system
to move the power. Additions to generating capacity are occurring at a more rapid
pace than transmission additions. The traditional vertically integrated utility no
longer dominates the industry structure.3 In addition, demand for electric power
continues to increase. Unresolved regulatory issues that have emerged after 1992
have resulted in considerable uncertainty in the financial community. As a result of
all of these factors, investment in the transmission system has not kept pace with
demand for transmission capacity.
The Energy Policy Act of 2005 (EPACT05) addresses electric reliability and
infrastructure investment.4 In part, Title XII creates an electric reliability
organization (ERO) that is to enforce mandatory reliability standards for the bulk-
power system. These standards are necessary for reliable operation of the grid. The
Federal Energy Regulatory Commission (FERC) will be reviewing the ERO’s
proposed reliability standards before granting its approval.5 Under this title, the ERO
could impose penalties on a user, owner, or operator of the bulk-power system that
violates any FERC-approved reliability standard. FERC approved the North
American Electric Reliability Corporation, a wholly owned subsidiary of the North
American Electric Reliability Council (NERC), as the ERO.6 NERC is a nonprofit
corporation whose membership is composed of the eight regional reliability
councils.7
3 Seventeen states and the District of Columbia are implementing retail choice for
electricity. According to the Energy Information Administration, in 1996, 10% of
generating capacity was owned by non-utility generators. By 2005, 43% of net summer
generating capacity was owned by non-utility generators. See [http://www.eia.doe.gov/
cneaf/electricity/epa/epat2p3.html].
4 P.L. 109-58.
5 FERC Docket No. RM06-22-000. Approval status is available at [http://www.ferc.gov/
industries/electric/indus-act/reliability/standards.asp].
6 Order Certifying North American Electric Reliability Corporation As the Electric
Reliability Organization in Ordering Compliance Filing
. 116 FERC, 61,062. Docket No.
RR06-1-000. Issued July 20, 2006.
7 The regional reliability councils are Electric Reliability Council of Texas, Inc. (ERCOT);
Florida Reliability Coordinating Council (FRCC); Midwest Reliability Organization
(MRO); Northeast Power Coordinating Council (NPCC); Reliability First Corporation
(RFC); Southeastern Reliability Council (SERC); Southwest Power Pool, Inc. (SPP); and
Western Electricity Coordinating Council (WECC).

CRS-3
Title XII also addresses transmission infrastructure issues. As required by
EPACT05, the Department of Energy issued the first National Electric Transmission
Congestion Study
in August 2006.8 Additional studies are required every three years.
The study identified two areas of critical congestion: Southern California and the
eastern coastal area from metropolitan New York to Northern Virginia. This
congestion study included detailed information on the transmission congestion in the
western United States (Figure 1) but did not provide comparable detail on congestion
in the eastern United States.9 In determining whether to designate national interest
electric transmission corridors, DOE is required to identify transmission congestion
that adversely affects consumers. However, EPACT05 does not define “congestion
that adversely affects consumers,” nor does it require empirical analysis of the
specific adverse effects of transmission congestion.
As a result of EPACT05, DOE designated two national interest electric
transmission corridors on October 2, 2007: The Mid-Atlantic Area National Interest
Electric Transmission Corridor and the Southwest Area National Interest Electric
Transmission Corridor based on the 2006 congestion study (Figures 2 and 3).10 This
designation allows FERC, under certain circumstances to authorize “the construction
or modification of electric transmission facilities.”11 A permit holder would still need
to obtain rights-of-way from property owners. If the permit holder is not able to
successfully negotiate with each affected property owner, then FERC would entitle
a permit holder to acquire the rights-of-way by exercising the right of eminent
domain.12 In its designation, DOE stated that:
A National Corridor designation is not a determination that transmission must,
or even should, be built. Whether a particular transmission project, some other
transmission project, or a non-transmission project is an appropriate solution to
8 U.S. Department of Energy, National Electric Transmission Congestion Study, August
2006, available at [http://www.oe.energy.gov/DocumentsandMedia/Congestion_Study_
2006-9MB.pdf].
9 Figure 1 shows how many hours in a year the transmission system was loaded at or above
75% of Operating Transfer Capability (OTC) in the Western Electricity Coordinating
Council (WECC) region. The most heavily loaded lines include Bridger West, which
delivers power from the Bridger, Montana coal-fired plants to loads in Utah and Oregon;
Southwest of Four Corners-to-Cholla-to-Pinnacle Peak in Arizona, which is designed to
deliver power from baseload plants to load; western Colorado to Utah; Wyoming to
Colorado; and southern New Mexico to El Paso.
The Department of Energy will not be publishing a detailed map of eastern congestion until
the release of the next progress report (late 2006) or the next congestion study (2009.) This
is after it is expected that DOE will designate National Corridors in the congested eastern
coastal area to relieve constraints or congestion. (E-mail communication with Agrawal
Poonum, Manager, Markets and Technical Integration, Office of Electricity Delivery and
Energy Reliability, Department of Energy, January 19, 2007.)
10 Department Of Energy Docket Numbers 2007-OE-01 and 2007-OE-02. Issued October
2, 2007.
11 Federal Power Act §216(b), 16 U.S.C. 824p(b).
12 Federal Power Act §216(e)(1), 16 U.S.C. 824p (f)(2).


CRS-4
a congestion or constraint problem identified by a National Corridor designation
is a matter that market participants, applicable regional planning entities, State
authorities, and potentially FERC will consider and decide before any project is
built. A National Corridor designation itself does not preempt State authority or
any State actions, including action to approve or order the implementation of
non-transmission solutions to congestion and constraint problems.... FERC is
committed to considering non-transmission alternatives, as appropriate, during
its permit application review process.13
Figure 1. Western Transmission Congestion, 1999-2005
Source: U.S. Department of Energy, National Electric Transmission Congestion Study (2006), p. 33.
13 Department Of Energy Docket Numbers 2007-OE-01 and 2007-OE-02. October p. 7-8.



CRS-5
Figure 2. Mid-Atlantic Area National Interest Electric
Transmission Corridor
Source: U.S. Department of Energy, October 2007.
Figure 3. Southwest Area National Interest Electric
Transmission Corridor
Source: U.S. Department of Energy, October 2007.

CRS-6
Transmission pricing was also addressed in EPACT05 (§1241) to encourage
investment in transmission. FERC issued Order 679 on this issue, Promoting
Transmission Investment through Pricing Reform
, on July 20, 2006.14 The order
identifies specific incentives that FERC will allow, but the burden remains on an
applicant to justify the incentives.

Historical Context
There are three components to electric power delivery: generation, transmission,
and distribution. Transmission, by its nature, is generally considered an interstate
transaction, whereas distribution is considered intrastate. State public utility
commissions regulate the siting of all transmission and distribution lines within each
state’s borders, as well as distribution charges and retail electric rates. In states that
have not restructured, the system operates as it has since enactment of the Federal
Power Act, with retail consumers paying one price that includes transmission,
distribution, and generation. This is referred to as a bundled transaction. In states
that have restructured, consumers are billed for separate transmission, distribution,
and generation charges. This is referred to as unbundled electricity service. FERC
regulates all transmission, including unbundled retail transactions.15
Generators of electricity need to move their power to their ultimate customers
through the transmission system. The current system allows for power transfers
within, but not between, three major regions of the United States: the area west of the
Rockies (Western Interconnection), Texas, and the Eastern Interconnection.
Transmission lines and distribution lines are categorized by their voltage rating.
Transmission lines are typically rated 230 kilovolts (kV) and higher (765 kV is the
highest installed). Subtransmission systems are 69 kV to 138 kV, and distribution
systems are rated less than 69 kV.16 Existing transmission infrastructure was
14 Federal Energy Regulatory Commission Final Rule, Order Number 679, Promoting
Transmission Investment through Pricing Reform
, July 20, 2006, Docket Number RM06-4-
000.
15 On October 3, 2001, the U.S. Supreme Court heard arguments in a case (New York et al.
v. Federal Energy Regulatory Commission
) that challenged FERC’s authority to regulate
transmission for retail sales if a utility unbundles transmission from other retail charges. In
states that have opened their generation market to competition, unbundling occurs when
customers are charged separately for generation, transmission, and distribution. Nine states,
led by New York, filed suit, arguing that the Federal Power Act gives FERC jurisdiction
over wholesale sales and interstate transmission and leaves all retail issues up to the state
utility commissions. Enron in an amicus brief argued that FERC clearly has jurisdiction
over all transmission and FERC is obligated to prevent transmission owners from
discriminating against those wishing to use the transmission lines. On March 4, 2002, the
U.S. Supreme Court ruled in favor of FERC and held that FERC has jurisdiction over
transmission, including unbundled retail transactions.
16 Transmission lines generally carry bulk-power transfers between utilities and move power
to load centers. Distribution lines move power to ultimate customers. Subtransmission is
sometimes considered transmission and other times considered distribution for regulatory
(continued...)

CRS-7
designed to accommodate the old system of central station power plants with nearby
customers. Since enactment of the Energy Policy Act of 1992, there has been an
increase in interstate bulk power transfers, a purpose for which the existing system
was not designed.
The Energy Policy Act of 1992 (EPACT92) created a new category of wholesale
electric generators called Exempt Wholesale Generators (EWGs) that are not
considered utilities.17 EWGs, also referred to as merchant generators, were intended
to create a competitive wholesale electric generation sector. In addition, EPACT92
provided a means for these non-utility generators to have access to the transmission
system. As a result of EPACT92, FERC issued a policy statement on transmission
pricing policy:
Greater pricing flexibility is appropriate in light of the significant competitive
changes occurring in wholesale generation markets, and in light of our expanded
wheeling authority under the Energy Policy Act of 1992 (EPACT92)[footnote
omitted]. These recent events underscore the importance of ensuring that our
transmission pricing policies promote economic efficiency, fairly compensate
utilities for providing transmission services, reflect a reasonable allocation of
transmission costs among transmission users, and maintain the reliability of the
transmission grid. The Commission also recognizes that advances in computer
modeling techniques have made possible certain transmission pricing methods
that once would have been impractical.18
In May 1994, FERC established general guidelines for comparable access to the
transmission system.19 In April 1996, FERC clarified its open-access transmission
tariff policy with Orders 888 and 889, making it easier for merchant generators to
gain access to the transmission grid and requiring utilities to “functionally unbundle”
their operations. In practice, this means that a utility’s generation and transmission
operations must be conducted separately, without the sharing of resources, books,
and records. Some states that have opened their retail markets to competition,
including California, have required utilities to divest of either transmission and
distribution or of generation. In these states, most utilities have divested generation
assets and maintained their transmission and distribution business. By July 9, 1996,
all utilities that own or control transmission had filed a single open-access tariff with
FERC that provides transmission service to eligible wholesale customers at
16 (...continued)
purposes.
17 Exempt Wholesale Generators may sell electricity only at wholesale. EWGs may be
located anywhere, including foreign countries. Before enactment of EPACT05, utility
generators were limited by the Public Utility Holding Company Act of 1935 (PUHCA) to
operate within one state.
18 Inquiry Concerning the Commission’s Pricing Policy for Transmission Services Provided
by Public Utilities Under the Federal Power Act, policy statement, October 26, 1994, Docket
No. RM 93-19-000, 18 CFR 2, 59 FR 55031.
Wheeling is defined as the movement of electricity from one system to another over
transmission facilities of interconnecting systems.
19 67 FERC 61,168.

CRS-8
comparable terms to the service that the utilities provide themselves. Some merchant
generators asserted that they continued to be discriminated against by incumbent
transmission utilities and were denied access to the system.
Orders 888 and 889 established a pro forma open-access transmission tariff (pro
forma OATT). Many argued that this pro forma OATT allowed for opportunities for
the exercise of undue discrimination by transmission owners. On May 18, 2006,
FERC issued a Notice of Proposed Rulemaking (NOPR), Preventing Undue
Discrimination in Preference in Transmission Service
, to remedy some of the
deficiencies in the pro forma OATT.20 According to FERC, the major reforms in the
NOPR include
! greater consistency and transparency in the Available Transfer
Capability (ATC) calculation;21
! open, coordinated, and transparent planning;
! reform of energy imbalance penalties;
! clarification of tariff ambiguities; and
! increased transparency and customer access to information.
On February 16, 2007, FERC issued Order 890, Preventing Undue
Discrimination Preference in Transmission Service.22 The final Order reflected
much of what was addressed in the NOPR, including calculations of available
transfer capability, coordination of the transmission planning process, establishing
a requirement for conditional firm long-term point-point service contracts, reforming
energy and generator imbalance charges, and increasing the transparency of the
existing pro forma OATT.
Current Issues
Physical Limitations
Three types of constraints limit the transfer capability within the transmission
system: thermal constraints, voltage constraints, and system operating constraints.
Thermal constraints limit the capability of a transmission line or transformer to carry
power because the resistance created by the movement of electrons causes heat to be
produced. Overheating can lead to two possible problems: The transmission line
loses strength, which can reduce the expected life of the line, and the transmission
line expands and sags between the supporting towers. This presents safety issues as
the lines approach the ground, as well as reliability concerns. If a transmission line
comes in contact with the ground, trees, or other objects, the transmission line will
trip off-line and not be able to carry power.
20 FERC Docket Numbers RM05-25-000 and RM05-17-000.
21 ATC is the transfer capability remaining on a transmission provider’s transmission system
that is available for further commercial activity over and above already committed uses.
22 FERC Order 890. Docket Numbers RM05-17-000 and RM05-25-000. Preventing Undue
Discrimination Preference in Transmission Service
. Issued February 16, 2007.

CRS-9
Voltage can be likened to the pressure inside the transmission system.
Constraints on the maximum voltage levels are set by the design of the transmission
line. If voltage levels exceed the maximum, short-circuits, radio interference, and
noise may occur. Low voltages are also a problem and can cause customers’
equipment to malfunction and can damage motors.
System operating constraints refer to reliability and security. Maintaining
synchronization among generators on the system and preventing the collapse of
voltages are major aspects of the role for transmission operators.23 North American
Electric Reliability Council guidelines require utilities to be able to handle any single
outage through redundancy in the system. When practical, NERC recommends the
ability to handle multiple outages within a system. Reducing the constraints on the
system through technology improvements is one way to increase the transfer
capability over existing lines.24
The regulatory regime has shifted the operations of the electric utility industry,
creating larger and more frequent bulk power transfers across a transmission system
designed largely for local intrastate service. However, investment and infrastructure
have not kept up with increases in the bulk power transfers and electricity demand.
Between 1978 and 1998, electricity demand had been growing at an average rate of
2.8% per year.25 Transmission capacity expressed in relation to electricity demand
increased by 3.5% per year between 1978 and 1982 and then declined by 1.2% per
year between 1982 and 1998.26 Actual annual transmission investment had declined
from nearly $5 billion in 1975 to about $2.25 billion in 1998.27 Reversing this trend,
between 1999 and 2005, transmission investment increased at a 12% annual rate.28
However, during the same period, total circuit miles of 230 kV and above
transmission lines owned and operated by investor-owned utilities increased by 0.8%
annually.29 This long period of insufficient transmission investment has led to
transmission lines that are congested in several regions of United States.
23 Within each interconnection, all generators rotate in unison at a speed that produces a
consistent frequency of 60 cycles per second.
24 See Energy Information Administration, Upgrading the Transmission Capacity for
Wholesale Electric Power Trade
, available at [http://www.eia.doe.gov/cneaf/pubs_html/
feat_trans_capacity/w_sale.html].
25 Energy Information Administration, Annual Energy Review, Electricity Overview,
1949-2005. Available at [http://www.eia.doe.gov/emeu/aer/elect.html].
26 Hirst, Eric, Expanding U.S. Transmission Capacity (August 2000), p. 5. Available at
[http://www.eei.org/industry_issues/energy_infrastructure/transmission/hirst2.pdf].
Normalized transmission capacity is calculated using megawatt-miles of transmission per
megawatts of summer peak demand.
27 Real $2003. Edison Electric Institute, EEI Survey of Transmission Investment: Historical
and Planned Capital Expenditures (1999-2008)
, Washington (May 2005), p. 3.
28 Edison Electric Institute, EEI Statistical Yearbook/2005 Data (2006), p. 107.
29 NERC 2006 Long-Term Reliability Assessment and NERC Reliability Assessment 2000-
2009. Available at [http://www.nerc.com/~filez/rasreports.html].

CRS-10
Similarly, as is shown in Figure 4, investment in generation capacity has not
kept pace with electricity demand growth. This has led to lower capacity margins for
electric utilities.30 According to NERC, available capacity margins, which include
only committed resources, are projected to drop below minimum regional target
levels in several regions of the United States and Canada in two to three years.31 The
ERO has proposed enforceable standards for cyber- and physical security and
reliability of the electric system that are intended to ensure optimum operation of the
transmission system. FERC will be reviewing NERC’s proposed standards before
granting approval.32
Figure 4. Real Private Fixed Investment in Electrical Power
Generation, and Electricity Consumption, Generation, and Real
Prices
200.00
175.00
150.00
125.00
100.00
75.00
50.00
25.00
0.00
1980
1985
1990
1995
2000
2005
Investment
Generation
Consumption
Real Electricit y P rices
Source: Kliesen, Kevin L. , “Electricity: The Next Energy Jolt?” The Regional Economist, The
Federal Reserve Bank of St. Louis, October 2006, p. 6.
Note: Index, 1980 = 100.
30 Capacity margin is the amount of unused available capability of an electric power system
at peak load as a percentage of capacity resources. This gives an indication of the ability
of the system to meet demand. A narrow capacity margin indicates a risk that supply will
be interrupted because of a shortage of generation. On the other hand, excessive day-ahead
capacity margin could add to the cost of electricity.
31 North American Electric Reliability Council, 2006 Long-Term Reliability Assessment,
(October 2006), p. 6.
32 FERC Docket No. RM06-22-000.

CRS-11
Congestion. DOE has identified areas in the Eastern Interconnection and
Western Interconnection as congested. Problems with congestion on the
transmission system are not new. In 1987, CRS noted that bulk power transmission
lines in many parts of the country were already operating at or near capacity and the
chief capacity-related barrier to bulk-power transfers (wheeling) was that the
transmission system was not built for bulk-power transfers.33 According to NERC,
the number of requests to use the transmission system that were denied because of
congestion (transmission line relief, TLRs) rose from 305 in 1998 to 1,494 in 2002.
By 2005, there were 2,397 TLRs, dropping slightly in 2006 to 1,901 TLRs.34 Over
the next 10 years, the line-miles of high-voltage transmission are expected to increase
6%, in contrast to a 20% expected increase in generation demand and capacity.35 If
this projection is accurate, further pressure on reliability could occur in several
regions.36
Security. Another issue surrounding the reliability of the electric system
involves security. The system operates with built-in redundancies to minimize the
risk of outages resulting from myriad causes, including weather, equipment failure,
and terrorist activity. In general, physical attacks could target transformers,
transmission towers, substations, control centers, power plants (including nuclear
reactors or dams), and fuel-delivery systems. NERC reported that in 2006, of the 57
events that resulted in a system disturbance (outage), only one (1.75%) was caused
by physical attack. Between 2001 and 2006, 11.21% of the system disturbances were
caused by “system protection and controls”issues, which include physical attacks and
cyber-attacks.37
High-voltage transformers are a critical and vulnerable part of the nation’s
electric power network. High-voltage (HV) units make up less than 3% of
transformers in U.S. power stations, but they carry 60% to 70% of the nation’s
electricity.38 Power grid planners generally anticipate the possible loss of a single
HV transformer substation and are prepared to reroute power flows as necessary to
maintain regional electric service. Loss of multiple HV transformers simultaneously
could cause extended regional outages.
33 See CRS Report 87-289, Wheeling in the Electric Utility Industry, by Alvin Kaufman et
al. (out of print; available from the author of this report).
34 NERC data on Transmission Loading Relief (TLR) requests are available at [http://www.
nerc.com/pub/sys/all_updl/oc/scs/logs/trends.htm].
35 Department of Energy, National Transmission Grid Study, May 2002.
36 See CRS Report RL31469, Electric Utility Restructuring: Maintaining Bulk Power System
Reliability
, by Amy Abel, Larry Parker, and Steven Stitt.
37 A physical attack involves human caused damage to transmission infrastructure that
generally results in a major outage. Past incidents have included removing stabilizing bolts
from transmission lines and shooting transformers. NERC Reported System Events
available at [http://www.nerc.net/dashboard/].
38 Loomis, William M., consulting engineer for Strategic Partners-Technical Systems,
“Super-Grade Transformer and Defense: Risk of Destruction and Defense Strategies,”
presentation to NERC Critical Infrastructure Working Group, Lake Buena Vista, Florida,
(December 10-11, 2001).

CRS-12
Utilities generally do not maintain a stockpile of transformers to replace more
than a small percentage of their operating units. Large transformers generally cost
$2 million to $3 million, are custom made, require long lead times to build, and are
bulky and difficult to move around.39 NERC maintains a transformer information
database, a 15-year-old program used primarily for weather-related outages of large
transformers. In response to the growing need for a stockpile of large transformers,
the Edison Electric Institute (EEI) has begun a FERC-approved spare transformer
sharing program, which is to be used solely to deal with terrorist activity or deliberate
damage to utility substations.40 At the time of the FERC approval in September
2006, 43 entities had joined the EEI program, representing more than 60% of the
FERC-jurisdictional bulk-power transmission system. Unlike the NERC program,
which does not charge utilities to participate, EEI charges a $10,000 sign-up fee to
join the transformer sharing program, as well as annual dues of about $7,500. Some
utilities need to obtain state approval before joining the EEI program.
NERC also operates the Electricity Sector Information Sharing and Analysis
Center (ESISAC), as required by Presidential Decision Directive (PDD) 63 on critical
infrastructure protection. The ESISAC is a voluntary means for utilities to share
security-related information. In turn, the ESISAC is tasked with providing “timely,
reliable and actionable warnings of threats and impending attacks on our critical
infrastructures.”41
Siting
One reason additional transmission lines have not been built in recent years is
the problems encountered when siting them. Siting and building transmission lines
have been very difficult because of citizen opposition, as well as inconsistent siting
requirements among states. Even though the transmission of electricity is considered
interstate commerce, the siting of transmission lines has been the responsibility of the
states. In addition, several federal agencies play various roles in the siting process,
primarily with regard to environmental impacts.
Since the blackout of 2003, FERC commissioners have supported federal siting
backstop authority to help transmission companies overcome some of the siting
obstacles,42 although such support has been controversial. The electric industry is in
39 Stan Johnson, NERC Manager of Situation Awareness and Infrastructure Security, as
quoted in Electric Utility Week, “More Utilities Sign up to Share Transformers, Information
As Cost- Consciousness Grows”(January 8, 2007), p. 9.
40 FERC approved the Spare Transformer Equipment Program (STEP) on September 21,
2006. FERC Docket Nos. EC06-140-000 and EL06-86-000.
41 The ESISAC website is available at [http://www.esisac.com].
42 Statement of Nora Mead Brownell, FERC Reverses Position, Will Now Take Federal
Backstop Authority
, at [http://www.Energywashington.com], September 2, 2003.

CRS-13
favor of giving FERC siting authority.43 States are generally opposed to federal
backstop authority.44
EPACT05 established that the Secretary of Energy is required to certify
congestion on the transmission lines, but EPACT05 does not specifically define
congestion. The first congestion study was completed in August 2006.45 As a result
of this study, the Secretary may designate “any geographic area experiencing electric
energy transmission capacity constraints or congestion that adversely affects
consumers as a national interest electric transmission corridor.” FERC may issue
permits for construction of transmission lines to transmission owners within a
national interest transmission corridor if FERC finds that a state does not have the
authority to approve the siting of the facilities or that a state commission that has
authority to approve the siting of facilities has withheld its approval for more than
one year. Permit holders are able to petition in U.S. district court to acquire rights-
of-way for the construction of transmission lines through the exercise of the right of
eminent domain.46
On April 26, 2007, DOE issued two draft National Interest Electric
Transmission Corridor designations (draft report), one stretching from the mid-
Atlantic region through New York, and the other in Southern California.47 EPACT05
created a new Federal Power Act §216(a)(2) which states that:
After considering alternatives and recommendations from interested parties
(including an opportunity for comment from affected States), the Secretary shall
issue a report, based on the study, which may designate any geographic area
experiencing electric energy transmission capacity constraints or congestion that
adversely affects consumers as a national interest electric transmission corridor.
DOE broadly defines the term “constraints that adversely affects consumers” to
include “not only constraints that cause persistent congestion, but also constraints
that hinder the development or delivery of a generation source that is in the public
interest ... which allows for a National Corridor designation when there is a constraint
that adversely affects consumers even though there is no present congestion....”48
DOE did not consider alternatives to new transmission, such as conservation or
efficiency improvements in existing lines, in identifying National Corridors. DOE
received comments from many stakeholders that argued that DOE should conduct a
cost-benefit analysis on transmission versus non-transmission solutions for
43 Edison Electric Institute, Federal Siting Authority: Key to Expanding Electricity
Infrastructure
, available at [http://www.eei.org/industry_issues/energy_infrastructure/
transmission/federalsiting.pdf].
44 Statement of National Governors Association.
45 U.S. Department of Energy, National Electric Transmission Congestion Study, August
2006, available at [http://www.oe.energy.gov/DocumentsandMedia/Congestion_Study_
2006-9MB.pdf ].
46 P.L. 109-58, § 1221.
47 DOE Draft Report available at [http://nietc.anl.gov/].
48 Ibid. p. 20.

CRS-14
congestion before designating a National Corridor.49 DOE argues that nothing in §
216 of the Federal Power Act requires that the DOE demonstrate that transmission
is the best or most cost-effective solution to a congestion problem.50 In its final
order, DOE concluded that:
Consideration of non-transmission solutions to the congestion problems facing
the Mid-Atlantic Critical Congestion Area is neither required nor necessary as
a precondition to designating the Mid-Atlantic Area National Corridor. FPA
section 2 16(a)(2) calls for the Secretary to consider “alternatives and
recommendations from interested parties” before making a National Corridor
designation. The statute, however, does not specify what the term “alternatives”
refers to. Numerous commenters would have us to interpret the phrase to mean
alternative solutions to congestion or constraint problems, which would then
necessitate a comparison of non-transmission solutions against transmission
solutions. Nothing in the language of FPA section 216 requires or suggest such
an interpretation.51
Another controversial aspect of the National Corridor designation is their
geographic boundaries. EPACT05 did not define the term “corridor,” and DOE has
concluded “that, while there may be circumstances where a project-based approach
would be appropriate, in general the Department (DOE) will use a source-and-sink
approach to define National Corridor boundaries.”52 In this process, the sink (the
congested or constrained load area) and the source (an area of potential supply) are
identified and the two areas are connected as a National Corridor. DOE does not
intend to designate specific projects as National Corridors, but rather large areas with
specific geographic boundaries. The final order used county borders to determine the
corridor boundaries.
In advance of DOE designating national interest electric transmission corridors,
on November 16, 2006, FERC issued its Final Rule on Regulations for Filing
Applications for Permits to Site Interstate Electric Transmission Facilities.53 In part,
EPACT05 (§ 1221) allows FERC to issue construction permits for transmission
facilities within a national interest electric transmission corridor if a state has
“withheld approval for more than one year.” The term withheld approval was not
unanimously interpreted by the commissioners. The final rule adopted that withheld
49 For examples of these comments, see those submitted by the National Association of
Regulatory Utility Commissioners (NARUC), New York Public Service Commission, New
Jersey Board of Public Utilities, Electric Power Supply Association, Northern Indiana
Public Service Co., Old Dominion Electric Cooperative, Piedmont Environmental Council,
and the Wilderness Society. Available at [http://nietc.anl.gov/].
50 Ibid. p. 24.
51 Department of Energy Order on the Designation of Mid-Atlantic Area National Interest
Electric Transmission Corridor [Docket Number 2007-OE-01], and the Southwest Area
National Interest Electric Transmission Corridor [Docket Number 2007-OE-02]. October
2, 2007. p. 69.
52 Draft Report. p. 34.
53 FERC Order Number 689 (RM06-12). 117 FERC 61,202. 18 CFR Parts 50 and 380.
Issued November 16, 2006.

CRS-15
approval could mean a state failing to act on the siting permit application or denying
the application. Commissioner Kelly in her dissent found this interpretation to be a
preemption of state rights:
The authority to lawfully deny a permit is critically important to the states for
ensuring that the interests of local communities and their citizens are protected.
What the Commission does today is a significant inroad into traditional state
transmission siting authority. It gives states two options: either issue a permit,
or we’ll do it for them. Obviously this is no choice. This is preemption.54
Defending the final rule before the media, Chairman Kelliher stressed that
FERC must assume that the words Congress chooses to use in passing a law are
“deliberate and done with care. If Congress meant only failure to act, why didn’t they
just say that.”55
Several bills have been introduced in the 110th Congress that would repeal or
reform § 216 of the Federal Power Act. H.R. 810 would amend § 216(e) of the
Federal Power Act by repealing the section that allows a permit holder to acquire
the-right-of-way for transmission facilities through the exercise of eminent domain
in a federal district court and replaces it with acquisition of right-of-ways in
accordance with state laws. H.R. 829 would place additional requirements before
an area could be considered a National Corridor. This bill would require DOE to
perform an analysis of alternatives to new transmission construction to alleviate
congestion. The bill would prohibit National Corridors from including parks or
historic battlefield sites that are designated as scenic, natural, cultural, or historic
resources under federal or state law. H.R. 829 also amends the Federal Power Act
to limit FERC’s ability to issue construction permits to instances when a state’s
denial of transmission siting is found to have been arbitrary or capricious or the state
unreasonably withheld or delayed a siting decision beyond one year. H.R. 1945 (§
403) would repeal § 216 of the Federal Power Act, which provides for federal siting
authority for transmission lines.
Alternatives to New Rights-of-Way. Capacity of the existing transmission
system can be increased without siting new lines. In addition, new generation can be
sited closer to demand, reducing the need to use the transmission system. Additional
transmission lines could be added to existing rights-of-way or, in some cases,
existing towers could be restrung with higher capacity lines. However, in some
cases, reliability levels would increase with the redundancy of new transmission lines
sited on new rights-of-way; storms and other events that may cause physical damage
to one area may not affect transmission lines in another part of a state or region.
Many transmission systems could increase the capacity of the transmission
system with technology improvements. While many new technologies would require
significant capital investment, one study by the New York Independent System
54 Kelly, Commissioner, Dissenting in part. Docket No. RM06-12-000 (November 16,
2006), p. 3.
55 Foster Electric Report, FERC’s Electric Transmission Siting Rule Sparked Strong Dissent
by Kelly over Jurisdictional Concerns
(November 22, 2006), p. 2.

CRS-16
Operator concluded that relatively inexpensive equipment upgrades could
significantly increase the line ratings and could reduce congestion.56 The study
indicated that a significant number of transmission lines operate below their thermal
limits because of equipment limitations at substations. By remediating those
limitations with relatively inexpensive equipment (e.g., disconnect switches, bus
connectors, relays), according to the New York study, operation at thermal capacities
could be reached with little or no risk of service interruption.
Other technological improvements to increase transmission capacity and allow
the transmission system to be operated more efficiently include upgrading
transformers, retrofitting electromechanical devices with digital devices to allow
operation of the system closer to thermal limits, and restringing existing towers with
aluminum conductor composite core cable. These would require significant capital
investment.
Burying Power Lines
Many reasons have been given for burying power lines, including reduced
maintenance, less susceptibility to weather damage, fewer traffic accidents involving
poles, improved aesthetics, and increased property values. The primary reason
against burying power lines is the high cost. Design and installation of underground
systems is more complex and expensive, and takes longer than for overhead systems.
In addition, the cost and time involved to modify or repair an existing system is also
reportedly higher.57
The overwhelming damage to the electricity transmission and distribution
system in the wake of Hurricanes Katrina and Rita has increased interest in replacing
overhead lines with underground cable. However, studies suggest that both overhead
and underground lines have their vulnerabilities, and there are considerable cost
differences in constructing and maintaining them. A review of several studies has
found that overhead lines are more susceptible to storm and other damage, but the
sites requiring repairs can be identified more quickly and repaired faster.
Underground lines have above-ground transformers that are subject to immediate
storm damage. Although underground distribution is generally more reliable during
storms, corrosion from water infiltration can cause outages in the days and weeks
after severe storms. The uprooting of trees can damage underground lines directly.
Underground lines can be more expensive and take longer to repair. Replacing
overhead lines with underground cable is also expensive. Analysis by the Florida
Public Service Commission (FPSC) has found that replacing overhead transmission
lines
in Florida with underground lines over a 10-year period might require a rate
increase of nearly 50% spread over all kilowatt hours. Converting overhead
56 New York Independent System Operator, Investigation of Potential Low Cost
Transmission Upgrades Within the New York State Bulk Power System
, Interim Report
(April 19, 2001).
57 North Carolina Public Utilities Commission Staff, The Feasibility of Placing Electric
Distribution Facilities Underground
(November 2003).

CRS-17
distribution lines to underground over the same period could boost rates by more
than 80%.58
The majority of existing transmission and distribution lines are overhead, but
in the 10 years between 1993 and 2002, capital expenditures for new power lines
were almost equally divided between underground (49%) and overhead (51%) lines.59
According to the Edison Electric Institute (EEI), new underground distribution costs
average $1 million per mile, or $29,854 per customer, compared with $73,666 per
mile, or $2,199 per customer, for existing overhead lines.60
Undergrounding Transmission. During storms, large steel transmission
towers generally withstand high winds and rain. Because of their height, they are
also less susceptible to damage from falling trees. In the United States, there are
200,000 miles of transmission lines, only 5,000 of which are underground cable.
Transmission is placed underground typically to address a localized constraint, such
as an airport, river crossing, or a central business district. Several factors are
considered in evaluating whether burying transmission lines is feasible. As already
noted, underground transmission has been found to be less susceptible to damage, but
any damage is more difficult and time-consuming to locate and repair, according to
an Australian study.61 While overhead transmission lines generally take a few hours
to two days to repair, EEI reports that average outage durations for underground
transmission ranges from five days to nine months, depending on the technology
used.62
There are several reasons why laying underground cable is significantly more
expensive than overhead transmission. According to FPSC, an underground
transmission cable needs to be about 10 times more massive than an overhead cable
to transmit the same amount of power, with the cable cost being about 10 times
greater than overhead cable.63 Trenches need to have either concrete conduits or
metal pipes for both safety and operational reasons. Because of the weight and
58 Florida Public Service Commission, Preliminary Analysis of Placing Investor-Owned
Electric Utility Transmission and Distribution Facilities Underground in Florida
(March
2005), available at [http://www.psc.state.fl.us/publications/pdf/electricgas/Underground_
Wiring.pdf].
59 FERC Form 1 Data 1993-2002, as compiled by Edison Electric Institute, Out of Sight, Out
of Mind? A Study on the Costs and Benefits of Undergrounding Overhead Power Lines
,
avai l abl e at [ ht t p: / / www.eei .or g/ i ndust r y_i ssues/ ener gy_infrastructur e/
distribution/UndergroundReport.pdf].
60 Ibid.
61 Australian Department of Communications, Information Technology and the Arts,
Putting Cables Underground (1998).
62 Average outage durations for High-pressure Fluid Filled Pipe, 8-12 days; Extruded
Dielectric, 5-9 days; High-pressure Fluid Filled Pipe, 2-9 months. See [http://www.eei.org/
meetings/nonav_meeting_files/nonav_2003-03-30-km/WiseSiting.ppt].
63 Florida Public Service Commission, Preliminary Analysis of Placing Investor-Owned
Electric Utility Transmission and Distribution Facilities Underground in Florida
(March
2005).

CRS-18
thickness of underground cable, splices need to be made every 900 to 3,500 feet. At
the site of each splice, an underground vault needs to be constructed for maintenance
access. Above ground, a right-of-way of at least 20 to 50 feet must be completely
cleared. Some studies have found that electromagnetic fields (EMFs) are stronger
immediately above underground transmission than immediately below overhead
transmission. However the EMF fields diminish more quickly with distance for
buried transmission than for overhead transmission.64
FPSC completed a comprehensive analysis of burying transmission and
distribution facilities and updated the analysis in 2005.65 The study calculated a cost
to remove and replace existing 138 kV overhead transmission facilities for investor-
owned, municipally owned, and rural electric cooperatives. The cost calculations
included
! planning and permitting,
! labor to remove existing facilities,
! new underground transmission facilities,
! labor to install the new underground facilities,
! trucks and other equipment to remove and install facilities,
! credits for existing overhead facilities that could be employed in the
future, and
! disposal of facilities that could not be employed in the future.
The most recent study estimated that in 2003 dollars, the cost per mile to place
transmission underground was $3.6 million or a total of $51.8 billion for all investor-
owned utility transmission assets in Florida. The FPSC further calculated that
converting overhead transmission facilities to underground would increase rates
49.7% for customers of investor-owned utilities (IOUs) over a 10-year period (Table
1
).
64 Wise, K., Going Underground: A Growing Reality for Transmission Line Routing?
(April 2003), presentation at Edison Electric Institute Natural Resources Workshop, Burns
& McDonnell, available at [http://www.eei.org/meetings/nonav_meeting_files/nonav_2003-
03-30-km/WiseSiting.ppt].
65 Florida Public Service Commission, Report on Cost-Effectiveness of Underground
Electric Distribution Facilities
, vols. 1-4 (December 1991), and Florida Public Service
Commission, Preliminary Analysis of Placing Investor-Owned Electric Utility Transmission
and Distribution Facilities Underground in Florida
(March 2005).

CRS-19
Table 1. Revenue Requirements for IOUs To Convert Florida’s
Existing Transmission Facilities to Underground, and Rate
Impact Over 10-Year Period
(in 2003 dollars)
Rate Impact
Estimated cost of conversion
$51.8 billion
Estimated cost adjusted for inflation
$57.9 billion
over 10 years
Levelized annual revenue requirement
$6.5 billion
Percentage rate impact
49.7%
(spread over all kilowatt-hours)
Assumptions
Weighted rate of return
12.04%
Property tax rate
1.86%
Operation and maintenance savingsa
(0.7%)
Inflation rate
2.44%
Source: Florida Public Service Commission.
a. Federal Energy Regulatory Commission (FERC) Form 1 data do not separately identify
transmission operation and maintenance (O&M) for overhead and buried transmission. FPSC
used distribution O&M savings from the 2003 FERC Form 1 for its calculations.
Both the 1991 FPSC study and the 1998 Australian study included a cost
savings to utilities due to fewer automobile collisions with utility poles. Both studies
considered lost wages, medical expenses, insurance administration costs, property
damage, and loss of life. According to FPSC, utilities would avoid approximately
$117 million (2003 dollars) annually of accident-related costs.66 Neither study
considered that some communities would plant trees on old rights-of-way, and a
collision with a well-established tree could cause injury and death, though in this
case, a utility would not likely be liable for costs associated with the accident.
Another benefit of burying power lines is a reduction of electrocutions from
sagging or downed power lines. In addition, workers would be less likely to
inadvertently make contact with a buried distribution line. The FPSC study
calculated an annual avoided cost from contact accidents of $243,000 (2003 dollars)
if all power lines were buried.67
66 FPSC 1991. Volume II. For consistency, CRS used the same GDP deflator index ratio of
1.299 as was used in the 1995 FPSC report to index the 1990 findings to 2003 dollars.
67 Ibid.

CRS-20
Pricing
Some transmission-owning utilities argue that the current pricing mechanism
for transmission discourages investment. FERC regulates all transmission, including
unbundled retail transactions. Under the Federal Power Act (FPA), FERC is required
to set “just and reasonable” rates for wholesale transactions.68 FERC has traditionally
determined rates by using an embedded cost method that includes recovery of capital
costs, operating expenses, improvements, accumulated depreciation, and a rate of
return. Traditionally, transmission owners have been compensated for use of their
lines based on a contract path for the movement of electricity, generally the shortest
path between the generator and its customer. However, electricity rarely follows a
contract path and instead follows the path based on least impedance.69 Transmission
lines often carry electricity that has been contracted to move on a different path. As
more bulk power transfers are occurring on the transmission system, transmission
owners not belonging to RTOs (regional transmission organizations) are not always
being compensated for use of their lines, because a contract path rarely follows the
actual flow. This creates a disincentive for transmission owners to increase
capacity.70
Under Order 2000,71 FERC stated its interest in incentive ratemaking and, in
particular, performance-based ratemaking. Those in favor of incentive ratemaking,
including the electric utility industry, argue that incentives are needed (1) to
encourage participation in regional transmission organizations (RTOs),72 (2) to
compensate for perceived increases in financial risk because of participation in a
regional transmission organization, and (3) to facilitate efficient expansion of the
transmission system.
FERC has used a “license plate” rate for transmission: a single rate based on
customer location. As FERC is encouraging formation of large regional transmission
organizations, FERC may move toward a uniform access charge, sometimes called
postage stamp rates. With a postage stamp rate, users pay one charge for moving
electricity anywhere within the regional transmission organization.
Postage stamp rates eliminate so-called rate pancaking, or a series of
accumulated transmission charges as the electricity passes through adjacent
transmission systems, and increases the pool of available generation. On the other
hand, by moving to postage stamp rates, customers in low-cost transmission areas
68 16 U.S.C. 824(d)(a).
69 Impedance is a measure of the resistive and reactive attributes of a component in an
alternating-current circuit.
70 National Economic Research Associates, Transmission Pricing Arrangements and Their
Influence on New Investments
, World Bank Institute (July 6, 2000).
71 89 FERC 61,285.
72 A regional transmission organization is an independent organization that does not own
the transmission lines but operates a regional transmission system on a non-discriminatory
basis. For additional discussion on RTOs see, CRS Report RL32728, Electric Utility
Regulatory Reform: Issues for the 109th Congress
, by Amy Abel.

CRS-21
may see a rate increase, and high-cost transmission providers in the same area may
not recover embedded costs, because costs are determined on a regional basis.
In early 2003, FERC began to consider raising the rate of return as a way to
reflect the regulatory uncertainty in the industry and encourage transmission
investment.73 The proposal would give a 1% return-on-equity-incentive for new
transmission projects operating under an RTO. Transfer of transmission assets to an
RTO would also result in an incentive return on equity of between 0.5% and 2%.
This could raise return on equity to approximately 14% for some transmission
projects. Increases in the return on equity would increase consumers’ electric bills.
However, in 2000, the cost of transmission accounted for less than 10% of the final
delivered cost of electricity.74 While the industry is in favor of increasing the return
on equity as a way of providing an incentive to invest, consumer groups are opposed
to such proposals because of the potential to increase consumer rates.75
As required by § 1241 of EPACT05, FERC issued its Final Rule on
transmission pricing on July 20, 2006.76 Although the order identifies specific
incentives that FERC will allow, the burden remains on an applicant to justify the
incentives by showing that the new transmission capacity will reduce the cost of
delivered power by reducing transmission congestion or will ensure reliability. The
applicant will also have to show that the rate is just, reasonable, and not unduly
discriminatory or preferential.77
Although the order identifies specific incentives that FERC will allow, the
burden remains on an applicant to justify the incentives. Several consumer groups
argue that the Final Rule is too permissive in offering rate incentives. Under the
Final Rule, FERC requires that applicants pass a “nexus test,” meaning that the
requested incentives match the demonstrable risks and challenges faced by the
applicant undertaking the project. The final rule applies the “nexus test” to each
incentive, rather than to the package of incentives as a whole. The American Public
Power Association (APPA) and the National Rural Electric Cooperative Association
73 Federal Energy Regulatory Commission, Proposed Pricing Policy for Efficient Operation
and Expansion of the Transmission Grid,
Docket No. PL03-1-000 (January 15, 2003).
74 Energy Information Administration, Electric Sales and Revenue 2000.
75 Testimony of Gerald Norlander for the National Association of State Utility Consumer
Advocates before the House Committee on Energy and Commerce, March 14, 2003,
available at [http://energycommerce.house.gov/108/Hearings/03132003hearing818/hearing.
htm].
76 Federal Energy Regulatory Commission Final Rule, Order Number 679, Promoting
Transmission Investment through Pricing Reform
(July 20, 2006), Docket Number RM06-4-
000.
77 The final rule authorizes FERC to approve the following incentive-based rate treatments:
a rate of return on equity sufficient to attract new investment in transmission facilities;
allowance of 100% of prudently incurred Construction Work in Progress (CWIP) in the rate
base; recovery of prudently incurred pre-commercial operations costs; accelerated
depreciation used for rate recovery; recovery of 100% of prudently incurred costs of
transmission facilities that are canceled or abandoned due to factors beyond the control of
the public utility; and deferred cost recovery.

CRS-22
(NRECA) argue that this approach fails to protect consumers where an applicant
seeks incentives that both reduce the risk of the project and offer an enhanced return
on equity for increased risk. In response to comments on the Final Order, FERC
issued an Order on Rehearing and determined that the nexus requirement no longer
will be applied separately to each incentive but that the total package of incentives
must match the demonstrable risks or challenges.78
In addition, the National Association of Regulatory Utility Commissioners
(NARUC), APPA, NRECA, Transmission Dependent Utility Systems (TDU
Systems), and the Transmission Access Policy Study Group (TAPS) argued that
under the Final Rule, FERC erred in rebuttably presuming that certain review
processes such as state siting approvals and regional planning processes would satisfy
the requirement that a transmission project ensure reliability or reduce congestion.
Under FERC’s Order on Rehearing, FERC will require that each applicant explain
whether any process being relied upon for a rebuttable presumption includes a
determination that the project is necessary to ensure reliability or reduce congestion.79
Since Order 689 was issued, three projects have received transmission rate
incentives: American Electric Power (AEP) Service Corp. received approval from
FERC for incentive rates for a new 765 kV, 550-mile transmission line that is
expected to extend from West Virginia to New Jersey; Allegheny Energy Inc.
(Allegheny) was granted rate incentives on a proposed 500 kilovolt transmission line
within the PJM region; and Duquesne Light Co.’s (Duquesne) petition for incentive
rates was conditionally approved for several projects in Western Pennsylvania.
FERC has approved incentives for the AEP and Allegheny projects that include a
return on investment (ROE) “at the high end of the zone of reasonableness, with the
zone of reasonableness to be determined in a future proceeding,” recovery of
construction work in progress (CWIP) costs, the ability to expense and recover pre-
construction and pre-operating costs, and accelerated depreciation.80 FERC
conditionally granted Duquesne’s ROE request of up to one and one-half percentage
points above a base-level ROE, recovery of CWIP costs, recovery of prudently
incurred pre-commercial operations costs, and prudently incurred costs of the project
in the event the project is cancelled due to factors beyond Duquesne’s control.81
Regulatory Uncertainty
For many years, transmission owners and investors expressed concern that the
regulatory uncertainty for electric utilities is inhibiting both new investment in and
78 Federal Energy Regulatory Commission Final Rule, Order on Rehearing, Order Number
679-A, Promoting Transmission Investment through Pricing Reform, (December 22, 2006),
Docket Number RM06-4-001, p. 21.
79 Ibid., p. 4.
80 116 FERC 61,059. Docket Number EL06-50-000, p. 15, available at
[http://www.ferc.gov/whats-new/comm-meet/072006/E-15.pdf].
81 FERC, Docket No. EL06-109-000, et al. (February 6, 2007), available at
[http://www.ferc.gov/EventCalendar/Files/20070206185852-EL06-109-000.pdf].

CRS-23
construction of transmission facilities. For example, repeal of the Public Utility
Holding Company Act of 1935 (PUHCA) had been debated since 1996. Without
clarification on whether PUHCA would be repealed, utilities stated that they were
reluctant to invest in infrastructure. It was argued that repeal of PUHCA could
significantly expand the ability of utilities to diversify their investment options.82
EPACT05 repealed PUHCA, and FERC and state regulatory bodies are given access
to utility books and records. Removing this uncertainty could encourage additional
investment in the transmission system.
In addition, FERC has been moving toward requiring participation in regional
transmission organizations to create a more seamless transmission system. A fully
operational regional transmission organization would operate the entire transmission
system in a region and be able to replace multiple control centers with a single
control center.83 This type of control can increase efficiencies in the operation of the
transmission system. RTO participants are required to adhere to certain operational
guidelines, but these are not currently enforceable in court. Uncertainty over the
form of an RTO, its operational characteristics, and the transmission rates for a
specific region have apparently made utilities wary of investing in transmission.
FERC has granted RTO status to several entities and conditionally approved others.
If RTOs are able to operate successfully and develop a track record, some regulatory
uncertainty will diminish.
On July 31, 2002, FERC issued a Notice of Proposed Rulemaking (NOPR) on
standard market design (SMD).84 This NOPR was highly controversial. FERC’s
stated goal of SMD requirements in conjunction with a standardized transmission
service was to create “seamless” wholesale power markets that allow sellers to
transact easily across transmission grid boundaries. The proposed rulemaking would
have created a new tariff under which each transmission owner would be required to
turn over operation of its transmission system to an unaffiliated independent
transmission provider (ITP). The ITP, which could have been an RTO, would have
provided service to all customers and would have run energy markets. Under the
NOPR, congestion would have been managed with locational marginal pricing.
FERC withdrew its SMD proposal shortly before passage of EPACT05.
82 For discussion of PUHCA repeal issues, see CRS Report RL32728, Electric Utility
Regulatory Reform: Issues for the 109th Congress
, by Amy Abel.
83 PJM operates with a single control center.
84 FERC, Docket No. RM01-12-000.


CRS-24
Figure 5. Congested Lines in the Eastern Interconnection
Source: U.S. Department of Energy, National Transmission Grid Study, May 2002.
Investment
Some contend that obtaining funding is the major impediment to transmission
expansion.85 Utilities have traditionally raised capital from three sources: equity
investors, internal cash flow, and bondholders. Before 1978, utility stocks were seen
as safe investments for investors. The Three Mile Island nuclear accident and other
cost overruns of nuclear facilities made utility investment less attractive. Following
enactment of the Energy Policy Act of 1992, many found investing in non-traditional
utilities (Enron, Mirant, etc.) to once again be an attractive option. Following the
California energy crises and the bankruptcy of several energy-related companies,
investors once again withdrew from heavily investing in utility stock. Between 2000
and 2002, utility bonds had been unattractive to investors, according to Standard &
Poor’s.86 Since then, many utilities have had their bond ratings reduced. In 2002,
there were 182 bond rating downgrades of utility holding and operating companies
and only 15 upgrades. A majority of electric utilities (62%) had a bond rating of
BBB or below while the number of those rated A- or better fell from 51% to 38% in
one year. Also, according to Standard & Poor’s, debt and preferred securities
85 Roseman, E., and Paul De Martini, In Search of Transmission Capitalists, Public Utilities
Fortnightly (April 1, 2003).
86 Standard & Poor’s, U.S. Power Industry Experiences Precipitous Credit Decline in 2002;
Negative Slope Likely to Continue
(January15, 2003).

CRS-25
financing activity fell from $86 billion in 2001 to $74 billion in 2002. In addition,
internal investment declined. The lack of investment options for utilities for
transmission improvements had significantly slowed transmission capacity additions.
According to Standard & Poor’s, the power sector had begun to experience an
upward trend in bond ratings. During the first half of 2006, the U.S. power sector
showed positive ratings gains, with company bond ratings being upgraded more often
than downgraded. By the end of 2006, the investor-owned utility sector ratings
leveled off with an equal number of upgrades and downgrades for the year.87 This
starkly contrasts with 2004 and 2005, when rating downgrades outpaced upgrades by
about three to two.88
Conclusion
For the transmission system to operate efficiently and reliably, many observers
argue that the tensions between economic, regulatory, and technology issues must be
balanced. Currently, the transmission industry is widely viewed as being in a state
of disequilibrium with significant regulatory and economic uncertainty. In addition,
regional differences complicate regulatory solutions. A large component of
regulatory uncertainty originates with a piece-meal approach to electric utility
restructuring on both the federal and state level. In 1991, CRS stated that
comprehensive regulatory reform of the electric power industry is neither
desirable nor practical without a clearer vision of what form the industry should
take. Too many uncertainties leave the future nature of the electric power
industry such that a major overhaul of regulation would involve significant risks
to the present stability of available and reliable electric power with little
guarantee of improved service or lower costs.89
The Energy Policy Act of 1992 introduced competition to wholesale electric
transactions without provisions for a comprehensive plan to address reliability issues
and the development of efficient wholesale markets. In addition, many states have
passed legislation or issued regulatory orders to introduce retail competition, each
with its own set of rules for utilities to follow. Provisions in EPACT05 are intended
to address many issues left outstanding by EPACT92. Although regulatory certainty
may improve as a result of EPACT05, a clearer vision of the role of competition in
the electric power industry, and additional investment in transmission infrastructure
and technology, continues to be necessary to support an adequate and reliable
transmission system.
87 Standard & Poor’s, Pace of US Utility Raiding Activity Moderated in 2006 (January 23,
2007).
88 Standard & Poor’s, Industry Report Card: U.S. Utility Second-Quarter Upgrade Surge
Is Strongest in Years
(July 10, 2006).
89 Electricity: A New Regulatory Order? Report prepared by the Congressional Research
Service for the Committee on Energy and Commerce, U.S. House of Representatives,
Committee Print 102-F (June 1991).