Order Code RL31384
CRS Report for Congress
Received through the CRS Web
V-22 Osprey Tilt-Rotor Aircraft
Updated January 7, 2005
Christopher Bolkcom
Specialist in National Defense
Foreign Affairs, Defense, and Trade Division
Congressional Research Service ˜ The Library of Congress

V-22 Osprey Tilt-Rotor Aircraft
Summary
The V-22 Osprey is a tilt-rotor aircraft that takes off and lands vertically like a
helicopter and flies like a plane by tilting its wing-mounted rotors to function as
propellers. Combining a helicopter’s operational flexibility with the greater speed,
range, and efficiency of fixed-wing aircraft, the V-22 can perform such missions as
troop/cargo transport, amphibious assault, special operations, and search and rescue
operations.
Begun in FY1982 by the Army and now funded in part by the Air Force, the
V-22 has been primarily a Marine Corps program funded by the Navy Department.
The aircraft is produced by Bell Helicopter Textron and Boeing Helicopters, with
engines produced by Rolls-Royce/Allison. Flight testing and operational evaluation
of pre-production V-22s began in early 1997, with procurement of production aircraft
approved in April 1997.
The future of the aircraft was at issue in 1989-92, when Secretary of Defense
Cheney sought to cancel the program on grounds of affordability. Congress
continued to fund the program, however, providing $16.4 billion through FY2004.
As of June 30, 2004, the Defense Department estimated the program’s total cost to
be about $48 billion to develop and produce 458 aircraft.
The Administration’s FY2002 defense budget requested $3,278.3 million for the
V-22 program. This included procurement of 12 MV-22s for the Marine Corps,
modification of existing aircraft, and RDT&E. Appropriations conferees reduced the
Navy procurement ($226 million and three airframes) and RDT&E. Air Force
procurement was also cut, but R&D was increased ($180 million) to buy three EMD
airframes. The Department of Defense included $1.9 billion in V-22 funding in its
FY2003 budget request. The Department of Defense procured 11 MV-22 aircraft in
FY2003, the minimum annual purchase required to keep the assembly lines intact.
The Bush Administration’s FY2004 budget requested $1.6 billion in overall V-22
funding, $1.1 billion to procure 11 aircraft (nine for the Marine Corps, 2 for the Air
Force), and $543.9 million in R&D funding. This request was matched by
appropriators, with a transfer of some R&D funding to the Special Operations
Command. The Administration’s FY2005 request included $1.6 billion in
procurement and RDT&E funding for the V-22. Appropriations conferees cut $38
million from the Navy’s RDT&E request, but otherwise approved all V-22 funding
for FY2005.
Congress has supported the V-22 as a new technology with multi-service
military applications as well as various civilian uses (if derivatives of this tilt-rotor
aircraft are developed for civil aviation) with potential commercial and foreign sales
implications. Critics of the V-22 have questioned its affordability and argued that its
performance would not justify the cost of procuring this new aircraft in the quantity
projected. Also, in light of several accidents, and a reported cover-up, critics argue
that the tilt-rotor technology is too risky, while supporters contend that risks are being
adequately addressed under a revamped program. This report will be updated.

Contents
Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Program Details . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Early Development . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Accidents and Fatalities Worsen . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Maintenance Falsification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Reviews, Reassessments, and Revamp . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
System Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
Key Issues . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
Should the Defense Department Procure the V-22 Aircraft? . . . . . . . . . . . 11
Main Arguments of Those Who Say “Yes” . . . . . . . . . . . . . . . . . . . . . 11
Main Arguments of Those Who Say “No” . . . . . . . . . . . . . . . . . . . . . 12
Congressional Action . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
FY2001-FY2005 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
List of Figures
Figure 1. V-22 Osprey in Flight . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
List of Tables
Table 1. Summary of V-22 FY2005 Congressional Action . . . . . . . . . . . . . . . . . 14

V-22 Osprey Tilt-Rotor Aircraft
Background
The U.S. Marine Corps considers the V-22 its highest aviation priority. Lt. Gen.
Frederick McCorkle, former Marine Corps Deputy Commandant for Aviation, has
written “The Osprey’s introduction to the Marine forces is of paramount importance
to the Marine Corps as it epitomizes our philosophy of procuring and fielding leap-
ahead, advanced technology systems to best employ our expeditionary forces.” The
Marine Corps believes that the Osprey will provide them an unprecedented capability
to quickly and decisively project power from well over the horizon. Indeed, the
Marine Corps considers the V-22 Osprey more than just an aircraft. Instead, the
Osprey is viewed as an important foundation upon which its vision for projecting
naval power ashore rests. The aircraft’s promise, however, has been dimmed by a
series of challenges to its affordability, safety, and program management.
The V-22 tilt-rotor design combines the helicopter’s operational flexibility of
vertical take off and landing with the greater speed, range, and fuel efficiency of a
turboprop aircraft. The V-22 Osprey takes off and lands vertically like a helicopter
but flies like a fixed-wing aircraft by tilting its wing-mounted rotors 90 degrees
forward to function as propellers. This “...combination of increased payload with
vastly improved speed and range,” McCorkle writes, “make the Osprey the aircraft
that defines the commander’s area of influence as it relates to placing Marines on the
ground.”1
The V-22 is intended to perform a variety of Army, Navy/Marine Corps, and Air
Force missions, including troop and equipment transport, amphibious assault, search
and rescue, and special operations. The Marines’ MV-22 version can transport 24
fully-equipped troops some 200 nautical miles (nm) at a speed of 250 knots (288
mi/h), exceeding the performance of the CH-46 medium-lift assault helicopters the
MV-22 will replace. The Navy’s HV-22 version will replace HH-3 helicopters now
used for search and rescue. The Air Force’s CV-22 version (with a range of 500 nm)
will be used for special operations. Army officials have testified that the service has
no requirement for the V-22, but the Air Force has expressed strong interest in the
CV-22 for its Special Operations Command, which plans to buy at least 50 CV-22s.
Developed and produced by Bell Helicopter Textron of Fort Worth, TX, and
Boeing Helicopters of Philadelphia, PA, the aircraft is powered by two T406
turboshaft engines produced by Allison Engine Company of Indianapolis, IN, a
1 Lt. Gen. Frederick McCorkle, “Transforming Marine Aviation,” Marine Corps Gazette,
May 2000, p.26.

CRS-2
subsidiary of Rolls-Royce North America. The contractors announced in August
1998 that the V-22 will be assembled in a new plant in Amarillo, TX.
Through FY2004, $16.4 billion had been provided for the V-22 program. The
Defense Department’s Selected Acquisition Report of June 30, 2004, estimated the
total acquisition of a 458-aircraft program would be $48 billion, which translates
into a program unit acquisition cost of $105 million per Osprey. The program
acquisition cost includes funding for both development and production of the aircraft
and related activities, whereas flyaway cost excludes research-development cost, thus
making such estimates significantly lower than estimates of total program acquisition
cost.
The V-22 program has proved controversial. Former Secretary of Defense
Cheney tried to terminate the program in 1989-92, for instance, but Congress
continued to provide funds for development of the V-22. The George H. Bush
Administration’s FY1990 budget requested no funds for the program. In submitting
that budget to Congress on April 25, 1989, Defense Secretary Cheney told the House
Armed Services Committee that he “could not justify spending the amount of money
... proposed ... when we were just getting ready to move into procurement on the
V-22 to perform a very narrow mission that I think can be performed ... by using
helicopters instead of the V-22.”
Program Details
The V-22 program has been under development for over 20 years. Safety and
maintenance concerns have arisen during this period, but the program has maintained
support from many in Congress nonetheless. The program has undergone
restructuring to accommodate recommendations from outside experts and DOD
managers.
Early Development
The V-22 is based on the XV-15 tilt-rotor prototype which was developed by
Bell Helicopter and first flown in 1977. The Department of Defense began the V-22
program in 1981, first under Army leadership, but with the Navy/Marine Corps later
taking the lead in developing what was then known as the JVX (joint-service vertical
take-off/landing experimental aircraft). Full-scale development of the V-22 tilt-rotor
aircraft began in 1986.
Like some other tactical aviation programs (such as the F/A-22 Raptor and Joint
Strike Fighter), the total number of V-22 aircraft planned for procurement has
decreased over time. In 1989 the Defense Department projected a 663-aircraft
program with six prototypes and 657 production aircraft (552 MV-22s, 55 CV-22s,
and 50 HV-22s). As projected in 1994, however, the program comprised 523
production aircraft (425 MV-22s, 50 CV-22s, and 48 HV-22s). Procurement of these
523 aircraft was to continue into the 2020s, since the Defense Acquisition Board
limited annual expenditures for Marine MV-22s to $1 billion (FY1994 dollars) when
it approved entry into engineering and manufacturing development (EMD) in

CRS-3
September 1994. The Quadrennial Defense Review (QDR), released May 19, 1997,
recommended accelerated procurement of 458 production aircraft (360 MV-22s for
the Marines; 50 Air Force CV-22s; and 48 Navy HV-22s). Such a 458-aircraft
program is now projected.
On March 19, 1989, the first of six MV-22 prototypes was flown in the
helicopter mode and on September 14, 1989 as a fixed-wing plane. Two of these
aircraft were destroyed in crashes. Prototype aircraft numbers three and four
successfully completed the Osprey’s first Sea Trials on the USS Wasp (LHD-1) in
December 1990. The fifth prototype crashed on its first flight (June 11, 1991),
because of incorrect wiring in a flight-control system; the fourth prototype crashed
on July 20, 1992, while landing at Quantico Marine Corps Air Station, VA, resulting
in loss of the aircraft and crew. This accident was caused by a fire resulting from
component failures and design problems in the engine nacelles.
Flight tests were resumed in August 1993 after changes were incorporated in the
prototypes. Flight testing of four full-scale development V-22s began in early 1997
when the first pre-production V-22 was delivered to the Naval Air Warfare Test
Center in Patuxent River, MD. The first EMD Flight took place on February 5,
1997. The first of four low-rate initial production aircraft, ordered on April 28,
1997, was delivered on May 27, 1999. Osprey number 10 completed the program’s
second Sea Trials, this time from the USS Saipan (LHA-2) in January 1999.
Operational evaluation (OPEVAL) testing of the MV-22 began in October 1999
and concluded in August 2000. On October 13, 2000, the Department of the Navy
announced that the MV-22 had been judged operationally effective and suitable for
land-based operations. This finding moves the program one step closer to full-rate
production, but a similar judgment is still required for ship-based operations. The
Navy’s Operational Test and Evaluation Command reported that the Osprey had yet
to conduct more tests to demonstrate the MV-22's wing-folding mechanism. On
November 15, 2000 the Marine Corps announced that the Osprey had successfully
completed sea trials and had been deemed operationally effective and suitable for
both land- and sea-based operations.
The V-22 Program Office reports the following flight test accomplishments:
More than 2500 hours flown (over 1300 hours on EMD aircraft). Achieved speeds
of 342 knots (402 mph); altitude of 25,000 ft; gross weight of 60,500 lbs., and a G
maneuver load factor of +3.9 at 260 knots. External loads of 10,000 lbs have been
carried at 230 knots. The Program Office reports that the MV-22 has flown more than
40 troop-lift missions and has carried more than 700 troops during OPEVAL flights.
Other tests conducted during OPEVAL included land and ship-board operations,
amphibious assault missions, over-water operations, night-vision goggle flights, low-
level navigation, external load lifting on single and dual hooks, in-flight refueling
with a C-130 tanker, and landings in difficult terrain.
Successfully completing OPEVAL should have cleared the way for full rate
production of 28 aircraft a year, although the Marines prefer a rate of 36 annually.
This decision was to have been made in December 2000, but was postponed
indefinitely, due to fatal accidents, and a mixed report from DOD’s director of
operational test and evaluation.

CRS-4
Accidents and Fatalities Worsen
On April 8, 2000, another Osprey crashed near Tucson, Arizona during an
exercise simulating a noncombatant evacuation operation. All four crew members
and 15 passengers died in the crash. An investigation of the accident found that the
pilot was descending in excess of the recommended flight envelope which may have
caused the aircraft to experience an environmental condition known as “power
settling” or “vortex ring state.” According to Lt. Gen. Fred McCorkle, the pilot was
descending more than a thousand feet per minute. The recommended descent rate is
800 feet per minute.” Following a two-month suspension of flight testing, the Osprey
recommenced OPEVAL in June 2000, with pilots flying a slightly tighter flight
envelope. A July 27, 2000 report by the Marine Corps Judge Advocate General
(JAG) (which had access to all non-privileged information from the safety
investigation) confirmed that a combination of “human factors” caused the crash.
“This mishap appears not to be the result of any design, material or maintenance
factor specific to tilt-rotors. Its primary cause, that of a MV-22 entering a Vortex
Ring State (Power Settling) and/or blade stall condition is not peculiar to tilt
rotors. The contributing factors to the mishap, a steep approach with a high rate
of descent and slow airspeed, poor aircrew coordination and diminished
situational awareness are also not particular to tilt rotors.”2
It was reported on June 28, 2000, that a draft DOD Inspector General study
concluded that the V-22 would not successfully demonstrate 23 major operational
effectiveness and suitability requirements prior to the December 2000 OPEVAL
Milestone III decision to enter full rate production in June 2001. The Marine Corps
agreed with DOD’s assessment of the deficiencies, but said that they had been aware
of these deficiencies before the beginning of OPEVAL. Furthermore, the Marine
Corps said that they had an approved plan designed to resolve the deficiencies prior
to the Milestone III decision.
On November 17, 2000, DOD’s Director of Operational Test and Evaluation
issued a mixed report on the Osprey; saying although “operationally effective” the
V-22 was not “operationally suitable, primarily because of reliability, maintainability,
availability, human factors and interoperability issues.” The report recommended that
more research should be conducted into the V-22's susceptibility to the vortex ring
state blamed for the April 8, 2000 crash.
On December 11, 2000, a MV-22 Osprey crashed near Jacksonville, NC, killing
all four Marines on board. This was the fourth Osprey crash since 1991 and the third
lethal accident. The aircraft’s pilot, Lt. Col. Keith M. Sweeney was the program’s
most experienced pilot and was in line to command the first squadron of Ospreys.
The aircraft’s copilot, Maj. Michael Murphy was second only to Sweeney in flying
time on the Osprey.3 The Marine Corps grounded the Osprey fleet pending a mishap
2 V-22 JAGMAN Executive Summary, United States Marine Corps, Division of Public
Affairs, July 27, 2000, p.1.
3 James Dao, “Marines Ground Osprey Fleet After Crash Kills Four,” New York Times, Dec.
(continued...)

CRS-5
board investigation. On April 5, 2001, the Marine Corps reported that the crash was
caused by a burst hydraulic line in one of the Osprey’s two engine casings, and a
software malfunction that caused the aircraft to accelerate and decelerate
unpredictably and violently when the pilots tried to compensate for the hydraulic
failure.4 The Marine Corps report called for a redesign of both the hydraulics and
software systems involved.5
Maintenance Falsification
In December 2000 an anonymous letter was mailed to the media by someone
claiming to be a mechanic in the Osprey program. The letter claimed that V-22
maintenance records had been falsified for two years, at the explicit direction of the
squadron commander. Enclosed in the letter was an audio tape that the letter’s author
claimed was a surreptitious recording of the squadron commander directing
maintenance personnel to lie about the aircraft until the V-22 TRIP decision was
made. On January 20, 2001, it was reported that the V-22 squadron commander
admitted to falsifying maintenance records. The Marine Corps subsequently relieved
him of command and reassigned him to a different position. The Department of
Defense’s Inspector General (IG) conducted an investigation. On September 15,
2001, it was reported that three Marines were found guilty of misconduct and two
were reprimanded for their actions.
Reviews, Reassessments, and Revamp
On April 19, 2001, a Blue Ribbon panel formed by then-Secretary of Defense
William Cohen to review all aspects of the V-22 program, reported its findings and
recommendations.6 These findings and recommendations were also discussed during
congressional testimony on May 1, 2001. The panel recommended that the program
continue, albeit in a restructured format. The panel concluded that there were
numerous problems with the V-22 program — including safety, training and
reliability problems — but nothing inherently flawed in basic tilt-rotor technology.
Because of numerous safety, training, and reliability problems, the V-22 is not
maintainable, or ready for operational use.
3 (...continued)
12, 2000.
4 An un-redacted version of JAG investigation into the April 2000 V-22 crash indicates that
investigators found three “noteworthy” maintenance “areas of concern”, including the
Osprey’s hydraulics system. A Naval Safety Center presentation to the Blue Ribbon Panel
brought to light several previously unreported maintenance problems — including
hydraulics failures — that caused engine fires or other problems during the Osprey’s
operational testing.
5 Mary Pat Flaherty, “Osprey Crash Blamed on Leak, Software,” Washington Post, Apr. 6,
2001.
6 This panel was chaired by retired Marine General John R. Dailey and included retired Air
Force General James B. Davis, Norman Augustine, and MIT professor Eugene Covert.

CRS-6
The panel recommended cutting production to the “bare minimum” while an
array of tests were carried out to fix a long list of problems they identified with
hardware, software and performance. Cutting near term production should free up
funds to pay for fixes and modifications. Once the changes had been made and the
aircraft was ready for operational use, the Panel suggested that V-22 out year
purchases could be made in large lots using multi year contracts to lower acquisition
costs. Program officials estimate that the minimal sustainable production rate is 12
aircraft per year, which would be less than half the Ospreys once planned for
FY2002.7
DOD appears to be taking managerial and budgetary steps to incorporate the
Blue Ribbon Panel’s recommendations. DOD’s FY2001 supplemental funding
request asked for a reduction of $475 million in procurement and an increase of $80
million in R&D funds. The additional R&D funding would be used to support initial
redesign and testing efforts to address deficiencies, logistics, flight test, and flight test
support for V-22 aircraft. The reduction in procurement funding reflects the need to
reduce production to the minimum rate while the aircraft design changes are being
developed and tested.
Secretary of Defense Rumsfeld’s FY2002 budget amendment, unveiled June 27,
2001, included a request for the procurement of 12 Ospreys. DOD comptroller Dov
Zakheim and Marine Corps Commandant Gen. James Jones both stated that the
procurement of 12 aircraft in FY2002 would allow them to sustain the V-22
subcontractor base while simultaneously addressing the Osprey program’s needs.8
Following the Blue Ribbon panel’s recommendations, it was reported that DOD
Under Secretary for Acquisition Edward “Pete” Aldridge had assumed acquisition
authority for the V-22 program. Under Secretary Aldridge changed the V-22
program’s status from an ACAT 1C program — which gives the Department of the
Navy the highest required authority for production decisions — to an ACAT 1D
program. Under the latter category, the Defense Acquisition Board (DAB) will
decide if and when the program is ready to enter full rate production. Other ACAT
1D programs, for example, include the F-22 Raptor and the RAH-66 Comanche.9
Navy officials say they are considering a series of block upgrades to the Osprey
to get the program back on track. Redesigns will be retrofitted onto aircraft already
on the assembly lines. Nineteen existing MV-22s will be placed in deep storage, and
7 Adam Hebert, “Minimal Sustainable Rate Will Dramatically Cut Near-Term V-22 Buys,”
Inside the Air Force, Apr. 20, 2001.
8 DOD News Briefing, Wed. June 27, 2001, 1:30PM and Kerry Gildea, “New V-22 Plan
Sustains Lower Tier Contractors, Jones Reports,” Defense Daily, May 15, 2001.
9 “Navy Loses Osprey Authority,” Washington Post, May 22, 2001 and Hunter Keeter,
“Aldridge Maneuvers V-22 Acquisition Authority Away from Navy,” Defense Daily, May
22, 2001 and Linda de France, “V-22 Osprey Production Authority Transferred from Navy
to DoD,” Aerospace Daily, May 22, 2001.

CRS-7
retrofitted later.10 These upgrades may combine up to 120 “fixes” identified by DOD.
Although purchases of the CV-22 variant have been postponed until the program is
restructured, Air Force Special Operations Command officials have said that they are
developing plans to accelerate future buys once the program is back on track. In
October 2001, it was reported that Undersecretary Aldridge estimated that the V-22
would require at least two years of flight testing before DOD could conclude that the
aircraft is safe, effective, and “worth the cost.”11
A NASA-led review of the V-22 program, released November 6, 2001,
concluded that there are no known aero-mechanical phenomena that would stop the
tilt rotor’s development and deployment. The study focused on several aero-
mechanics issues, including Vortex Ring State, power problems, auto-rotation, and
hover performance.12
In a December 21, 2001, memo to the Secretaries of the Air Force and the Navy,
and the Commander-in-Chief, Special Operations Command, Undersecretary of
Defense Aldridge gave his authorization for the V-22 to resume flight testing in the
April 2002 time frame. Secretary Aldridge expressed support for range, speed, and
survivability goals of the V-22. He noted, however that the program still had
numerous technical challenges to overcome, and emphasized that the V-22 must
demonstrate that “1) it can meet the needs of the warfighter better than any other
alternative, 2) it can be made to be reliable, safe, and operationally suitable, and 3)
it is worth its costs in contributing to the combat capability of U.S. forces.” Secretary
Aldridge approved the flight test program under the condition that the production rate
be slowed to the minimum sustaining level, that it be comprehensive and rigorous,
and that the restructured program is fully funded in accordance with current
estimates.13
Mechanical adjustments slowed the V-22 test schedule, and the MV-22 took its
first test flight on May 29, 2002. The Air Force CV-22 resumed flight tests on
September 11, 2002. Flight tests are designed to explore both technical and
operational concerns. Technical concerns include flight control software and the
reliability and robustness of hydraulic lines. Operational concerns being explored
include whether the Osprey is too prone to Vortex Ring State to make it a safe or
effective aircraft, whether this potential problem is further exacerbated by multiple
Osprey’s flying in formation, and how well the V-22 handles at sea.14
10 Christian Lowe, “Navy to Store MV-22s For Up To Four Years,” Marine Corps Times,
Mar. 11, 2002.
11 Tony Capaccio, “Textron-Boeing V-22 Needs Two years of Testing, Aldridge Says,”
Bloomberg.com, Oct. 16, 2001.
12 Christopher Castelli, “ NASA Review Panel Endorses Resumption of V-22 Flight Tests,”
InsideDefense.com,. Nov. 14, 2001.
13 “Text: Aldridge Memo on V-22,” Inside the Navy, Jan. 7, 2002.
14 Thomas Ricks, “V-22 Osprey to Face Make or Break Tests,” Washington Post, Dec. 25,
2002, p.14.

CRS-8
The principal difference between the aircraft that were grounded in 2000 and the
aircraft that are being tested 17 months later are re-routed hydraulic lines and an
improved caution and warning system.15 Hydraulic failures have continued during
the reinstated flight test program, once on August 4, 2003, (due to a mis-installed
clamp) and again on September 5, 2003. Improvements to the production V-22
aircraft are expected to be implemented in three blocks.16
In conjunction with resuming flight testing, the Navy Department modified
certain V-22 requirements. For instance, the V-22 is no longer required to land in
helicopter mode without power (also known as “autorotation”), protection from
nuclear, chemical and biological weapons has been eliminated. The V-22 is no longer
required to have an “air combat maneuvering” capability; instead it must demonstrate
“defensive maneuvering.” Also, the requirement that troops be able to use a rope or
rope ladder to exit the cabin at low altitudes has been eliminated.17 Also concurrent
with the resumption of V-22 flight testing, DOD began an in-depth study of
alternatives to pursue in case the aircraft does not pass muster. Options reportedly
include purchasing the S-92, or upgrading CH-53, or EH101 helicopters.18
After one year and 466 hours of flight testing, DOD reviewed the Osprey’s
progress. On May 15, 2003, Thomas Christie, DOD’s Director of Operational Test
and Evaluation (DOT&E) reportedly graded Bell-Boeing’s improvements to the
Osprey’s hydraulics as “reasonable and appropriate” and “effective.”19 Christie also
reportedly approved of the testing that had been completed and was satisfied with
what had been learned about the V-22's susceptibility to Vortex Ring State. On May
20, 2003, the Defense Acquisition Board also reviewed the program approved of the
flight test program’s progress.
Current Status
DOD currently plans on procuring the V-22 at 11 aircraft (the minimum
sustainable rate) through its FY2005 budget request. Marine Corps officials had
recommended increasing the production rate in FY2006 to 20 aircraft. However, in
a August 8, 2003, memorandum, Undersecretary of Defense for Acquisition Michael
Wynne announced that this acceleration “presents more risk than I am willing to
accept.” Instead, Wynne restructured the planned procurement, reducing the FY2006
purchase to 17 aircraft. “For subsequent years’ procurement planning, production
rates should increase by about 50% per year for a total of 152 aircraft through FY09,”
15 Jefferson Morris, “Pilot: Resumption of V-22 Testing To Be Treated Like First Flight,”
Aerospace Daily, Apr. 29, 2002.
16 Christopher Castelli, “Aldridge Reviews V-22, Clearing Way for Navy Decision to
Resume Flight Tests,” InsideDefense.Com, Apr. 25, 2002.
17 Joseph Neff, “Eased Standards ‘Fix’ Osprey,” Raleigh News & Observer, May 19, 2002,
p.1.
18 “Aldridge Makes Progress Check on MV-22 at NAS Patuxent River,” Defense Daily, Feb.
11, 2003.
19 Tony Capaccio, “Boeing-Textron B-22 Gets Favorable Review From Pentagon Tester,”
Bloomberg.com, May 19, 2003.

CRS-9
according to the August 8th memo. Wynne directed that the savings resulting from
the reduced procurement (estimated at $231 million) be invested in improving the V-
22's interoperability, by funding the Joint Tactical Radio System, Link 16 and
Variable Message Format communication. Wynne also directed that a multi-year
procurement (MYP) of the V-22 be accelerated. While some suggest that this
restructuring will more quickly deliver high-quality aircraft to the Marines and
Special Operations Forces, others fear that slowing procurement will inevitably raise
the platform’s cost.
In April 2004 it was reported that the CV-22 had fallen six months behind its
flight test schedule. The V-22 program office reported that it had developed a plan
to make up this lost time, and did not anticipate jeopardizing the resumption of
operational testing scheduled for January 2005.20 In July 2004 the V-22 passed an
interim Defense Acquisition Board (DAB) review that was viewed by some as a
“rehearsal” for a DAB review scheduled for fall 2005 that will determine whether the
V-22 is ready to move into full-rate production.21
As of January 2005, the Osprey program is preparing to enter into Operational
Evaluation Testing. Navy officials report that they are pleased with the ship-board
and other testing completed to date. Other observers say that V-22 testing was rocky.
In June 2004 a V-22 was forced twice to make an emergency landing. During one
landing, the aircraft suffered a “Class B” mishap (one causing between $200,000 and
$1 million in damage).22 An investigation revealed that the V-22 suffered from
widespread problems with an engine component that required replacement every 100
flight hours.23 Navy officials acknowledge that problems were encountered during
testing, but say that these are the kinds of problems which testing is designed to
identify and resolve. The Osprey is a stronger program thanks to the resolution of
these problems and is ready to move on to the next stage of development, they argue.
20 Ron Laurenzo, “Testing of Special Ops V-22 Six Months Behind Schedule,” Defense
Today,
Apr. 8, 2004.
21 Jefferson Morris. “V-22 Passes Interim Defense Acquisition Board Review.” Aerospace
Daily & Defense Report.
July 29, 2004.
22 Christopher Castelli. “Navy Convenes Mishap Board to Investigate Latest V-22 Incident.”
Inside the Navy. July 5, 2004.
23 Christian Lowe. “V-22 Ospreys Require New Engine Component Every 100 Hours.” Navy
Times.
July 16, 2004.

CRS-10
System Description
The V-22 is a tilt-rotor V/STOL aircraft, capable of vertical or short take off and
landing, with forward flight like a conventional fixed-wing aircraft. About 65% of
the airframe is made of graphite-epoxy composite materials. The Marine Corps’s
MV-22 version will have the following characteristics:
Propulsion:
2 T406 turboshaft engines
Crew:
3
Passengers:
24 combat troops
Max. vertical take off weight:
47,500 lb
Max. short take off weight:
55,000 lb
Speed at max. weight:
250 knots/hour
Combat radius:
200+ nm
The airframes of the Marine Corps MV-22 and the Air Force CV-22 variant for
Special Operations Command will have some 90% commonality. The CV-22 will
carry 18 troops, with auxiliary fuel tanks increasing combat radius to about 500
miles. This variant may carry a 50-cal GAU-19 nosegun for self defense. The Marine
Corps is also evaluating the efficacy of a gun, primarily for self defense purposes.24
The CV-22 will also carry advanced avionics, such as terrain-following radar, and
directed infrared countermeasures, that will allow special operations forces to
penetrate hostile areas in all weather and terrain. The CV-22 will also carry extra fuel
for greater range.
The V-22's potential capabilities relative to conventional helicopters and
turboprop aircraft are illustrated by two figures found on the USMC V-22 Website
[http://www.navair.navy.mil/v22/]. The V-22 has the ability to carry considerably
larger payloads much greater distances than the CH-46 helicopter that it will replace.
The V-22 could carry three times the payload, or fly five times the range of the CH-
46 (4,000 lbs and 132 nmi for the CH-46 respectively). While it will take off and land
vertically like a helicopter, the V-22 will fly twice as fast. While the V-22's range,
speed and payload capabilities are most frequently touted, the Bell/Boeing contractor
team reports the Osprey exhibits the following survivability traits: The V-22 is up to
21 times less vulnerable to small arms fire than current helicopters, it is 75 percent
quieter than helicopters, and it is the only U.S. tactical transport aircraft with
designed-in radiological, biological, and chemical warfare protection.
24 Hunter Keeter, “.50 Cal. Ramp Gun Interim Armament for V-22, Solution Follows
OPEVAL,” Defense Daily, Nov. 15, 2002.


CRS-11
Figure 1. V-22 Osprey in Flight
Key Issues
Should the Defense Department Procure the V-22 Aircraft?
Main Arguments of Those Who Say “Yes”. The Defense Department
should accelerate procurement of the V-22, which the Marine Corps considers its
most important aviation program, in order to obtain these aircraft sooner and at more
economical production rates. The V-22 is needed to replace aging military
helicopters in all the services, which are costly to maintain and operate safely and
effectively. The Army should reconsider its decision not to buy the V-22, which the
Air Force wants to procure for its Special Operations missions and combat search
and rescue. The Osprey represents a truly joint capability, as evidenced by the
Navy’s desire to purchase HV-22s for search and rescue, and other missions.
This tilt-rotor aircraft will provide the operational flexibility of a helicopter
without the helicopter’s inherent limitations of speed, range, and altitude. While
there may be new helicopters that could replace and improve on today’s military
helicopters, V-22 proponents say that none of them would match the Osprey’s
capabilities. When landing on hostile shores in a third-world conflict (typically
lacking important infrastructure such as airfields and roads), the V-22 would be
critical for the transport of Marines from ship to shore. Senior DOD officials have
testified that the V-22 would have, for example, made a significant contribution the
to war on terrorism in Afghanistan.
The Osprey has been rigorously tested and its accident rate is consistent with
other aircraft development programs, supporters say. While some technical problems
have been encountered, leading experts have testified that there are no technological
barriers to the employment of tilt-rotor technology. Engineering-level modifications
will, and have, put the Osprey program back on track.

CRS-12
Supporters of the V-22 also cite the tilt-rotor’s potential value for civil aviation,
law enforcement, and foreign sales by the U.S. aerospace industry.25 The
development of tilt-rotor aircraft for the armed services could have significant
spin-off effects for civil aviation and U.S. technology, giving the U.S. aerospace
industry a major competitive advantage in the international market.26
Main Arguments of Those Who Say “No”. The V-22 is unaffordable in
the present budgetary environment, when the cost of buying large numbers of these
transport/cargo aircraft would most likely be at the expense of more critical defense
needs. Ship-to-shore logistical operations can be performed by less expensive
helicopters for the kinds of landing operations in which the Marines are likely to be
involved, where the V-22's greater speed and range would not be needed. Moreover,
Marine assault missions in an opposed landing would involve ship-to-shore
movement of troops and equipment, which would require coordination with aircraft
having less speed and range than the V-22. Further, some challenge claims made by
V-22 supporters regarding how well the V-22 performs compared to legacy
helicopters.27
As currently funded, the V-22 program is not the joint-service effort it was
expected to be, despite Air Force use of the aircraft, and the Air Force may be
partially backing away from its commitment to the program. Air Force Secretary
James Roche has questioned the Osprey’s ability to conduct combat search and
rescue operations, and the Air Force is currently re-evaluating the Osprey’s
attractiveness for this mission.28
In light of several V-22 crashes, three involving fatalities, many argue that the
tilt-rotor technology is not sufficiently mature to merit the Osprey’s production and
fielding. Studies suggest that tilt-rotor aircraft are more susceptible to airflow
instabilities that can cause Vortex Ring State than are traditional helicopters.29 And
our understanding of the kinds of airflow anomalies that have caused numerous
25 Sen. Ted Stevens et al., “Continuation of the V-22 Aircraft Program,” remarks in the
Senate, Congressional Record, daily edition, Apr. 19, 1989, pp. S4507-S4509.
26 The potential civil application of tilt-rotor technology is also considered by some a good
reason to pursue the V-22 program. A February 1988 study by the FAA and NASA
concluded that tilt-rotors could help relieve airport congestion by diverting commuters and
short-distance passengers to vertiports in urban centers. The importance of U.S. production
of a tilt-rotor aircraft for civilian purposes was the subject of a hearing on July 17, 1990, by
the House Committee on Science, Space, and Technology’s Subcommittee on
Transportation, Aviation, and Materials. In 1992, Congress enacted legislation (H.R. 6168)
directing the Secretary of Transportation to establish a “civil tilt-rotor development advisory
committee” to evaluate the feasibility and viability of developing civil tilt-rotor aircraft and
infrastructure necessary to incorporate tilt-rotor aircraft into the national transportation
system.
27 See, for example, Everest Riccioni, “Osprey or Albatross?,” Defense News, Jan. 27, 2004.
28 Richard Whittle, “Mission for V-22 Questioned,” Dallas Morning News, Aug. 6, 2002.
29 Michael Dornheim, “Tiltrotor Wake ‘More Complex’ Than Classic Vortex Ring State,”
Aviation Week & Space Technology, July 15, 2002.

CRS-13
deaths in V-22 flight testing are still very immature. Critics also argue that the Navy
is “dumbing down” the V-22's requirements and making it a less effective aircraft.
Opponents cast doubt on the Osprey’s operational capabilities and operational
concepts. A January 12, 2001 presentation by the GAO to the V-22 Blue Ribbon
Panel for instance said that the V-22's cabin may not be large enough to carry 24
combat-equipped Marines, and that the severe rotor down wash might impede the
ability of troops to exit the aircraft and move into combat positions. Also, to avoid
entering Vortex Ring State, Osprey’s will have to descend slowly, which will make
them vulnerable to ground fire in combat situations. Others have argued that the
Osprey’s hypothetical contribution to the war in Afghanistan is questionable due to
the high altitude of that country, and the Osprey’s inability to improve greatly over
helicopter performance in this area. Whatever commercial value a tilt-rotor aircraft
might some day have for civil aviation, the V-22's value as a military system is
insufficient to justify its cost in these times of budgetary constraints and higher
priority defense needs.
Congressional Action
Overview
The V-22 program was an issue in the 1992 presidential campaign with
Democratic candidates Clinton and Gore supporting development of the aircraft
while the Bush Administration opposed the program until late October, when Vice
President Quayle announced a contract award to the development team. On October
22, 1992, the Navy awarded a $550-million contract to the Bell-Boeing team to build
four new V- 22 derivatives and to modify two existing V-22 prototypes for
evaluation of proposed design changes.
Throughout the program, supporters have called for accelerating procurement
beyond the levels projected in the Administration’s plan, arguing that this would
reduce program costs over the long term and would get more aircraft in service
sooner. In a potentially contrary development, on December 23, 2004, an internal
DOD Program Budget Decision (PBD 753) was leaked to the press. PBD 753
recommended cutting 22 aircraft from the V-22 production plan between FY2006
and FY2009. It is not clear yet whether this internal recommendation will be
implemented in the Navy’s FY2006 budget request.
V-22 detractors have urged caution, and tried to delay the V-22 program by
cutting procurement funding. In addition to overseeing cost and schedule, Congress
has requested studies into V-22 maintenance and testing issues.
FY2001-FY2005
The administration’s FY2005 request included $1.6 billion in procurement and
RDT&E funding for the V-22. The request, as well as congressional action, is
summarized in Table 1, below.

CRS-14
Table 1. Summary of V-22 FY2005 Congressional Action
(Millions of dollars)
USN
USAF SOCOM
Budget Request
Procurement

FY2005
846.6 (8 Aircraft)
305.6 (3 Aircraft)
0

AP
71.5
11.0
0

Mods
3.4
.3
0
RDT&E
304.1
16.4
75.1
Authorization, House
Matched all funding requests
Authorization, Senate
Matched all funding requests
Authorization Conference
Reduced USN RDT&E
Matched USAF and SOCOM
request by $42M.
funding requests
$262.1M provided
Appropriations, House
Recommended $51M
Matched USAF and SOCOM
reduction in USN
funding requests
RDT&E request
Appropriations, Senate
Recommended $7 M in
Matched USAF and SOCOM
USN RDT&E request
funding requests
Appropriations,
Reduced USN RDT&E
Matched USAF and SOCOM
Conference
request by $38M.
funding requests
$266.1 M provided
The Bush Administration’s FY2004 budget requested $1.6 billion in overall V-
22 funding, $1.1 billion to procure 11 aircraft (nine for the Marine Corps, 2 for the
Air Force), and $543.9 million in R&D funding. In their reports (S.Rept. 108-46, S.
1050) and (H.Rept. 108-106, H.R. 1588) House and Senate authorizers respectively
matched the Administration’s request for V-22 procurement and R&D funding.
Conferees (H.R. 1588, H.Rept. 108-354) also matched the Administration’s request.
House appropriators (H.R. 2658, H.Rept. 108-187) matched the
Administration’s request for V-22 procurement and R&D funding. Senate
appropriators (S. 1382, S.Rept. 108-87) matched the overall funding request, but
recommended a transfer of $34 million from the Navy’s V-22 RDT&E account to
Defense-wide RDT&E (SOCOM). Appropriations conferees (H.R. 2658, H.Rept.
108-283) supported the Senate’s transfer.
The Department of Defense requested $1.9 billion in V-22 funding in its
FY2003 budget request, submitted February 4, 2002.30 The Department of the Navy
intends to procure 11 MV-22 aircraft in FY2003, the minimum annual purchase
required to keep the Textron and Boeing assembly lines intact during two years of
new flight tests.
30 Program Weapon Acquisition Costs By Weapon System, Department of Defense Budget
for Fiscal Year 2003, Feb. 2003. p.i.

CRS-15
House and Senate authorizers and authorization Conferees matched DOD’s
FY2003 request for Navy, Air Force, and SOCOM (Special Operations Command)
R&D funding. House authorizers also matched all requests for procurement funding.
In their report (S.Rept. 107-151, S. 2514) Senate authorizers matched the
Navy’s procurement request but cut $9.2 million from Navy advanced procurement.
The committee recommended this reduction to keep V-22 procurement at the
minimum sustaining rate of 11 aircraft per year until operational testing has been
successfully completed. (P.68). Senate authorizers also matched the Air Force’s
procurement request, but eliminated the $10.1 request for APCY. Again, Senate
authorizers (p.97) recommended the reduction to keep procurement at the
congressionally mandated rate of 11 aircraft per year. In their report (H.Rept. 107-
772, H.R. 4546) Authorization conferees matched the request for Navy procurement,
Air Force procurement, and Air Force advance procurement. Conferees cut $19.3
million from the Navy’s advance procurement to fund procurement for 9 aircraft in
FY2004, instead of 11 aircraft.
House and Senate appropriators and appropriations Conferees matched DOD’s
FY2003 request for Navy, Air Force, and SOCOM (Special Operations Command)
R&D funding. In their report (H.Rept. 107-532, H.R. 5010), House appropriators cut
the Navy’s FY2003 procurement request by $20 million due to “unjustified cost
resolution claim” (p. 125) and matched the request for advance procurement. House
appropriators matched the Air Force’s procurement and advance procurement
requests. In their report (S.Rept. 107-213 , H.R. 5010), Senate appropriators followed
Senate authorization by matching Navy and Air Force procurement requests, but
cutting both requests for advance procurement. Appropriations conferees (H.Rept.
107-732, H.R. 5010) cut the Navy’s FY2003 procurement request by $10 million due
to “unjustified cost resolution claim” (p. 175). They also cut the Navy’s advance
procurement request by $18.4 million. Appropriations conferees matched the Air
Force’s request for procurement and advance procurement.
The Bush Administration’s FY2002 funding request for the V-22 included
$1 billion in Navy procurement for 2 aircraft. Navy procurement also included
requests for $48.4 million for advanced procurement (current year) and $35 million
for modification of in service aircraft. Air Force procurement totaled $95.1million
(no aircraft to be built), for FY2002, and $15 million for advanced procurement
(current year). Navy RDT&E funding of $546.7 million was requested. The Air
Force requested $10 million for RDT&E.
On August 1, 2001 the House Armed Services Committee (HASC) reduced
overall FY2002 funding for the V-22 program by $264.7 million. The HASC
matched the Administration’s request for: $1 billion to procure 12 MV-22s, $96.7
million for Special Operations Command CV-22 component development, and $10
million for Air Force CV-22 avionics development. House authorizers reported the
Administration’s request for: Navy RDT&E (-$100 million), Air Force CV-22
procurement (-$136.5 million), and Special Operations CV-22 procurement (-$28.2
million).
In S.Rept. 107-62 (S. 1416), dated September 12, 2001, the Senate Armed
Services Committee (SASC) provided its oversight of the V-22 program. In terms of

CRS-16
research and development, the SASC and HASC were largely in agreement. Like the
HASC, the SASC matched the Air Force’s request for CV-22 RDT&E, but the SASC
reduced the Navy’s RDT&E request by $95 million. The SASC and HASC were also
largely in agreement regarding Air Force procurement, as the SASC zeroed out funds
for procuring the CV-22, except for $295 million for spare and repair parts. The
biggest difference between the authorizing committees was that the SASC reduced
the Navy’s procurement request, authorizing $783 million to procure nine Ospreys.
Senate authorizers supported the Blue Ribbon Panel’s recommendation that until the
V-22 program resolves reliability and maintainability problems, “the V-22 program
should not move forward faster than the minimum sustaining production rate.”31
In their report to accompany S. 1438 (H.Rept. 107-333), FY2002 authorization
conferees cut $50 million from the Navy’s procurement request, providing enough
funding for 11 airframes rather than the 12 requested. House authorizers matched the
Administration’s request, Senate authorizers had cut $226.7 million to procure nine
airframes. Conferees rejected the Administration’s request for Air Force procurement
funding, reduced the Navy’s request for R&D funding by $100 million, and matched
the Air Force’s request for $10 million in R&D funding.
Authorization conferees also required DOD (Sec. 124, p. 514) to provide a
report 30 days prior to any resumption of V-22 flight testing. The report will notify
Congress of any waiver of any item capability or other requirement specified in the
V-22 Joint Operational Requirements Document, along with justification for any
such waiver. The report would also describe any hydraulics or flight control software
deficiencies and corrective actions, action to implement the recommendations of the
Senior Review Panel, and an assessment of the NASA report on tilt-rotor
aeromechanics.
The House Appropriations Committee recommended that until the V-22
program completes its restructuring, the overall production rate should be held to no
more than 11 aircraft per year. Accordingly, the committee cut $219 million and three
aircraft from the Navy’s FY2002 procurement request, and $100 million from the
Navy’s R&D account. Senate appropriators increased the Air Force’s CV-22 request
by $84 million to fund procurement of two aircraft, while zeroing out a $15 million
request for advanced procurement. This transfer of budgetary resources to the CV-22
was intended to enable DOD to commence and accelerate initial operational testing
of the special operations variant.
In their report to accompany H.R. 3338 (S.Rept. 107-109), the Senate
Appropriations Committee cut $226.7 million and three aircraft from the Navy’s
FY2002 procurement request and zeroed-out the Air Force’s procurement request of
$95.1 million. Senate appropriators matched the Navy’s RDT&E request, but denied
the Air Force’s $10 million R&D request.
In their report on H.R. 3338 (H.Rept. 107-350), FY2002 appropriation conferees
cut the Navy’s procurement request by $226 million, a reduction of three airframes.
31 U.S. Congress, National Defense Authorization Act for Fiscal Year 2002, report to
accompany S. 1416, 107th Cong., 1st sess., S.Rept. 107-62, (Washington: GPO, 2001), p. 78.

CRS-17
Like authorizers, appropriators rejected the Administration’s request for Air Force
procurement funding. However, appropriators increased Air Force R&D funding by
$180 million to produce 2 CV-22 EMD (engineering, manufacturing and
development) aircraft. $100 million was cut from the Navy’s R&D request.
In June 2001, DOD submitted its request for FY2001 supplemental
spending. To implement the Blue Ribbon Panel’s recommendation on restructuring
the V-22 program, DOD requested $80 million in additional Navy RDT&E funds,
and a reduction of $475 million in Navy and Air Force procurement accounts.
Congressional defense oversight committees made modifications to DOD’s
FY2001 supplemental spending request. On June 20, 2001, the House passed H.R.
2216, Making Supplemental Appropriations for the Fiscal Year Ending September
30, 2001 and for Other Purposes. In this bill the House supported the general thrust
of DOD’s adjustment to the V-22 program, but recommended additional
appropriations of $40 million for Navy RDT&E (for a total of $120 million) in order
to accelerate activities associated with fixing the V-22 program, such as risk
reduction, part redesign, and continued operational testing. Because it disagreed with
DOD assumptions on V-22 pricing, the House recommended additional reductions
in Navy and Air Force V-22 procurement of $120 million (for a total recision of $595
million).
The Senate Appropriations Committee Report (S.Rept. 107-33, to accompany
S. 1077) supported DOD’s request to add $80 million to FY2001 V-22 RDT&E.
Senate appropriators recommended a reduction of $513 million in Navy and Air
Force V-22 production, as opposed to the DOD request to rescind $475 million in
Navy and Air Force FY2001 production funds.
The Appropriations Conference Report (H.Rept. 107-148, H.R. 2216) Making
Supplemental Appropriations for FY2001 concurred with the Senate appropriators
desire to add $80 million for the correction of deficiencies, flight testing and flight
test support. Appropriations conferees approved a reduction of $199 million for MV-
22 procurement instead of the $235 million reduction proposed by DOD. Conferees
also approved recision of $327.5 million from CV-22 procurement, delaying initial
acquisition of this variant until deficiencies are corrected.
The Administration’s FY2001 defense budget requested $1,843.1 million for
the V-22 program — $1,314.9 million for procurement of 16 MV-22s for the Marine
Corps, $380 million for procurement of four CV-22 versions for the Air Force, and
$148.2 million in Navy R&D funding. In a February 9, 2000 letter to the House
Armed Services Committee, the Marine Corps stated that its first unfunded priority
was the $166 million procurement of two additional V-22s and spare parts, which
would bring its total procurement to18 aircraft. For FY2001 the House and Senate
defense committees consistently supported the V-22 by recommending authorizations
and appropriations that matched or slightly exceeded Administration’s request.
Defense appropriations (H.R. 4576) supported the program with only minor
modifications — a $4.5 million reduction in Force advanced procurement, current
year. Additionally, authorization conferees required that “all V-22 Osprey aircraft be
equipped with a state-of-the art cockpit voice recorder and a state-of the art flight
data recorder...”(p.35, H.Rept. 106-945, H.R. 4205).

CRS-18
On February 7, 2001 Senator Russ Feingold introduced the “Osprey Safety,
Performance and Reliability Evaluation Act of 2001.” This bill would rescind all
FY2001 procurement funding except for what would be required to maintain the V-
22 production base, and delay the program one year. The bill also requires a report
to Congress by the Secretary of the Navy regarding steps taken to ameliorate
concerns expressed by DOD’s Director of Operational Test and Evaluation. It also
requires a report to Congress by the DOD Inspector General on V-22 maintenance.
Both reports must be submitted prior to the V-22 Milestone III decision. On March
5, 2001 Senator Feingold followed up this bill with a letter to Defense Secretary
Donald Rumsfeld urging him to delay further procurement of the V-22 until all
investigations into the program have been completed and until further testing has
been completed to ensure that the Osprey is safe. Also, on April 24, 2001,
Representative Bob Filner introduced a bill that would mandate a one year
moratorium on V-22 procurement. Both Senator Feingold’s and Representative
Filner’s bills are pending in committee.