Order Code RL32418
CRS Report for Congress
Received through the CRS Web
Navy Attack Submarine Force-Level
Goal and Procurement Rate:
Background and Issues for Congress
June 2, 2004
Ronald O’Rourke
Specialist in National Defense
Foreign Affairs, Defense, and Trade Division
Congressional Research Service ˜ The Library of Congress

Navy Attack Submarine Force-Level
Goal and Procurement Rate:
Background and Issues for Congress
Summary
The Navy is currently procuring one Virginia (SSN-774) class attack submarine
per year. Each submarine costs about $2.3 billion. The FY2005-FY2009 Future
Years Defense Plan (FYDP) submitted by the Department of Defense (DOD)
proposes increasing the procurement rate to two ships per year starting in FY2009.
DOD is also, however, conducting a study that could lead to a change in the current
attack submarine force-level goal of 55 boats. Submarine supporters are concerned
that Navy or DOD officials are seeking to reduce the attack submarine force-level
goal to justify keeping Virginia-class procurement at one per year beyond FY2008,
and thereby make additional funding available for Navy surface programs such as the
DD(X) destroyer or the Littoral Combat Ship (LCS).
Issues for Congress include the following: Should the attack submarine force-
level goal be 55 or some other number? At what rate should Virginia-class
submarines be procured in coming years? Should the current joint-production
arrangement for building Virginia-class submarines be continued or altered?
Congress’ decisions on these issues could significantly affect future Navy
capabilities, Navy funding requirements, and the submarine industrial base.
In considering whether the attack submarine force-level goal should be 55 or
some other number, key factors to consider include day-to-day demands for attack
submarines in recent years, recent and potential wartime demands for attack
submarines, submarine-launched unmanned vehicles (UVs), attack submarine
homeporting and crewing arrangements, the Trident cruise missile submarine
(SSGN) conversion program, and contributions by allied and friendly attack
submarines. Judgments on these factors could lead to an attack submarine force level
goal well below 55, well above 55, or about equal to 55.
In considering the rate at which Virginia-class submarines should be procured
in coming years, key factors to consider include the attack submarine force-level
goal, attack submarine service lives, the effect of annual procurement rates on unit
procurement costs, industrial-base considerations, and funding requirements for other
defense-spending priorities. Maintaining an attack submarine force of 40, 55, or 70
boats could in the future require average Virginia-class procurement rates of about
2 boats per year, 2.8 to 2.9 boats per year, or 3.7 to 3.8 boats per year, respectively.
Potential alternatives to the current two-yard, joint-production arrangement for
building Virginia-class submarines include a one-yard production strategy under
which construction of Virginia-class submarines would be consolidated at either
General Dynamics’ Electric Boat Division (GD/EB) or Northrop Grumman’s
Newport News Shipbuilding (NGNN), and a two-yard, separate-production strategy,
under which complete Virginia-class submarines would be built at both GD/EB and
NGNN. Compared to a one-yard strategy, approaches involving two yards may be
more expensive but offer potential offsetting benefits. This report will be updated
as events warrant.

Contents
Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Submarines in the U.S. Navy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Attack Submarine Force-Level Goal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Attack Submarine Force Levels . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Virginia (SSN-774) Class Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
Recent Procurement Rates And Congressional Concern . . . . . . . . . . . . . . . 11
Issues for Congress . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
Attack Submarine Force-Level Goal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
Key Factors To Consider . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
Summary of Key Points . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
Day-to-Day Demands for Attack Submarines in Recent Years . . . . . . 16
Recent and Potential Wartime Demands for Attack Submarines . . . . 24
Submarine-Launched Unmanned Vehicles (UVs) . . . . . . . . . . . . . . . . 27
Submarine Homeporting and Crewing Arrangements . . . . . . . . . . . . . 31
SSGN Conversion Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34
Allied and Friendly Attack Submarines . . . . . . . . . . . . . . . . . . . . . . . . 34
Future Virginia-Class Procurement Rate . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
Key Factors to Consider . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
Attack Submarine Force-Level Goal . . . . . . . . . . . . . . . . . . . . . . . . . . 37
Attack Submarine Service Lives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41
Annual Procurement Rates And Unit Procurement Costs . . . . . . . . . . 41
Industrial-Base Considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
Other Defense Spending Priorities . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
Joint-Production Arrangement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
Potential Production Approaches . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
Navy Statements in 2003 About Potential Alternatives . . . . . . . . . . . . 46
1997 Navy Cost Estimate For Some Approaches . . . . . . . . . . . . . . . . 48
Arguments For Alternative Approaches . . . . . . . . . . . . . . . . . . . . . . . 50
Questions For Congress . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
List of Tables
Table 1. Virginia-class procurement, FY1998-FY2004 . . . . . . . . . . . . . . . . . . . . 8
Table 2. Proposed Virginia-class procurement . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Table 3. U.S. SSNs In Recent Major Military Operations . . . . . . . . . . . . . . . . . . 24
Table 4. Steady-State Replacement Rates . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
Table 5. Notional Procurement Profiles for Various Force Sizes . . . . . . . . . . . . 39

Navy Attack Submarine Force-Level Goal
and Procurement Rate:
Background and Issues for Congress
Introduction
The Navy is currently procuring one Virginia (SSN-774) class attack submarine
per year. Each submarine costs about $2.3 billion to procure. The FY2005-FY2009
Future Years Defense Plan (FYDP) that the Department of Defense (DOD) submitted
to Congress in February 2004 proposes increasing the procurement rate to two ships
per year starting in FY2009. The previous FYDP that DOD submitted in February
2003 had proposed increasing the procurement rate two years sooner, in FY2007.
DOD is conducting a study on undersea warfare requirements, scheduled to be
completed in 2005, that could lead to a change in the current attack submarine force-
level goal of 55 boats, which was established in the 2001 Quadrennial Defense
Review (QDR). Submarine supporters are concerned that Navy or DOD officials are
seeking to reduce the attack submarine force-level goal to something less than 55
boats so as to justify keeping Virginia-class procurement at one per year beyond
FY2008 (or reduce it to less than one per year for some number of years). Submarine
supporters are concerned that Navy or DOD officials may want to do this to make
additional funding available in these years for procurement of Navy surface ships
such as the DD(X) destroyer or the Littoral Combat Ship (LCS).1
Issues for Congress include the following: Should the attack submarine force-
level goal be 55 or some other number? At what rate should Virginia-class
submarines be procured in coming years? Should the current joint-production
arrangement for building Virginia-class submarines be continued or altered?
Congress’ decisions on these issues could significantly affect future Navy
capabilities, Navy funding requirements, and the submarine industrial base.
The next section of this report provides background information on Navy attack
submarines and the Virginia-class program. The following section addresses the
above issues for Congress.
1 See for example, Robert A. Hamilton, “Some Submariners See Their Future Influence
Shrinking,” New London (CT) Day, May 17, 2004.
For more on the DD(X) and LCS programs, see CRS Report RS21059, Navy DD(X)
Destroyer Program: Background and Issues for Congress
, by Ronald O’Rourke; CRS
Report RS21305, Navy Littoral Combat Ship (LCS): Background and Issues for Congress,
by Ronald O’Rourke; and CRS Report RL32109, Navy DD(X) and LCS Ship Acquisition
Programs: Oversight Issues and Options for Congress
, by Ronald O’Rourke.

CRS-2
Background
Submarines in the U.S. Navy
Types of Submarines. Submarines are one of four principal categories of
combat ships that traditionally have helped define the size and structure of the U.S.
Navy. The other three are aircraft carriers, surface combatants (e.g., cruisers,
destroyers, and frigates), and amphibious ships.2
Submarines are powered by either nuclear reactors or non-nuclear power sources
such as diesel engines or fuel cells. All U.S. Navy submarines are nuclear-powered.3
U.S. Navy submarines fall into three types — nuclear-powered ballistic missile
submarines (SSBNs), nuclear-powered cruise missile submarines (SSGNs), and
nuclear-powered attack submarines (SSNs).4
Submarine Roles and Missions. The SSBNs’ basic mission is to remain
hidden at sea with their nuclear-armed submarine-launched ballistic missiles
(SLBMs) and thereby deter a strategic nuclear attack on the United States. Although
this mission is often associated with the Cold War-era nuclear competition between
the United States and the Soviet Union, it has continued, with some modifications,
2 The Navy also includes mine warfare ships and a variety of auxiliary and support ships.
3 An exception for the U.S. Navy is the non-combat auxiliary submarine Dolphin (AGSS-
555), a small submarine that the Navy uses for research and development work. As a non-
combat research asset, the Dolphin is not included in counts of the total number of
submarines (or battle force ships of all kinds) in the Navy.
Until the 1950s, the U.S. Navy included many non-nuclear-powered combat submarines.
Following the advent of nuclear power in the mid-1950s, construction of new non-nuclear-
powered combat submarines ended and the total number of non-nuclear-powered combat
submarines in Navy service began to decline. The Navy’s last in-service non-nuclear-
powered combat submarine was retired in 1990.
Most military submarines around the world are non-nuclear-powered. Five countries — the
United States, the United Kingdom (UK), France, Russia, and China — operate nuclear-
powered submarines. The latter three countries operate both nuclear- and non-nuclear-
powered submarines, while the United States and the UK operate all-nuclear submarine
fleets.
A submarine’s use of nuclear or non-nuclear power as its energy source is not necessarily
an indication of whether it is armed with nuclear weapons. A nuclear-powered submarine
can lack nuclear weapons, and a non-nuclear-powered submarine can be armed with nuclear
weapons.
4 In the designations SSBN, SSGN, and SSN, SS stands for submarine, N stands for nuclear-
powered, B stands for ballistic missile, and G stands for guided missile (such as a cruise
missile).

CRS-3
in the post-Cold War era.5 As of the end of FY2003, the Navy included 16 Ohio
(SSBN-726) class SSBNs, which are commonly called Trident submarines because
they carry Trident SLBMs. Each Trident SSBN can carry 24 Trident SLBMs.
The SSGNs are a new addition to the U.S. Navy.6 They are former Trident
SSBNs that are being converted (i.e., modified) to carry Tomahawk cruise missiles
and special operations forces (SOF) rather than SLBMs. A total of four SSGNs are
planned. The first two SSGNs are scheduled to complete conversion and enter Navy
service in FY2006; the other two are scheduled to do so in FY2007. The ships are
scheduled to remain in service for about 20 years.7
Each SSGN as converted will retain its 24 large (7-foot-diameter, 44-foot-long)
SLBM launch tubes. In one possible configuration, 22 of these tubes would be used
to carry a total of 154 Tomahawks (7 Tomahawks per tube) while the remaining two
would be used as lockout chambers for an embarked force of 66 SOF personnel. In
the future, the 24 tubes could be used to carry large numbers of other payloads, such
as unmanned vehicles. The SSGNs as converted will also retain their four original
21-inch-diameter torpedo tubes and their internal torpedo magazines. In discussing
the SSGNs, Navy officials often express a desire to take maximum advantage of the
very large payload volume on each SSGN by developing new unmanned vehicles or
other advanced payloads.
The SSNs — the focus of this report — are general-purpose submarines that
perform a variety of peacetime and wartime missions, including the following:
! covert intelligence, surveillance, and reconnaissance (ISR), much of
it done for national-level (as opposed to purely Navy) purposes;
! covert insertion and recovery of special operations forces;
! covertly launched strikes against land targets with the Tomahawk
cruise missiles;
! covert offensive and defensive mine warfare;
5 For a discussion of U.S. strategic nuclear weapons policy and force structure, see CRS
Report RL31623, U.S. Nuclear Weapons: Changes in Policy and Force Structure, by Amy
F. Woolf.
6 The Navy in the late 1950s and early 1960s built and operated two non-nuclear-powered
cruise missile submarines (or SSGs — the Grayback [SSG-574] and the Growler [SSG-577])
and one nuclear-powered cruise missile submarine (the Halibut [SSGN-587]). The
submarines could each carry two Regulus II strategic nuclear cruise missiles. In the mid-
1960s, following the deployment of the Navy’s initial SSBNs, the Regulus cruise missile
was removed from service and the Grayback, Growler, and Halibut were converted into
attack and auxiliary transport submarines.
7 For more on the Navy’s SSGN conversion program, see CRS Report RS21007, Navy
Trident Submarine Conversion (SSGN) Program: Background and Issues for Congress
, by
Ronald O’Rourke.

CRS-4
! anti-submarine warfare (ASW); and
! anti-surface ship warfare.
During the Cold War, ASW against the Soviet submarine force was the primary
stated mission of U.S. SSNs, although covert ISR and covert SOF insertion/recovery
operations were important on a day-to-day basis as well.8 In the post-Cold War era,
although maintaining a capability for conducting anti-submarine warfare against the
Russian submarine force remains a mission, the Navy has placed increased emphasis
on missions that contribute to U.S. military operations in littoral (near-shore) areas
against regional adversaries other than Russia.
Although the four planned SSGNs differ somewhat from SSNs in terms of
mission orientation (with the SSGNs being strongly oriented toward Tomahawk
strikes and SOF support, while the SSNs are more general-purpose in orientation),
SSGNs are sometimes included in counts of the projected total number of Navy
attack submarines.
Attack Submarine Force-Level Goal
Previous Administrations. The Reagan-era plan for a 600-ship Navy included
an objective of achieving and maintaining a force of 100 SSNs. The George H. W.
Bush Administration’s proposed Base Force plan of 1991-1992 originally called for
a Navy of more than 400 ships, including 80 SSNs.9 In 1992, however, the SSN goal
was reduced to about 55 boats as a result of a 1992 Joint Staff force-level
requirement study (updated in 1993) that called for a force of 51 to 67 SSNs,
including 10 to 12 with Seawolf-level acoustic quieting, by the year 2012.10
The Clinton Administration, as part of its 1993 Bottom-Up Review (BUR) of
U.S. defense policy, established a goal of maintaining a Navy of about 346 ships,
8 For an account of U.S. submarine surveillance and intelligence-collection operations
during the Cold War, see Sherry Sontag and Christopher Drew with Annette Lawrence
Drew, Blind Man’s Bluff, New York, Public Affairs, 1998.
9 For the 80-SSN figure, see Statement of Vice Admiral Roger F. Bacon, U.S. Navy,
Assistant Chief of Naval Operations (Undersea Warfare) in U.S. Congress, House Armed
Services Committee, Subcommittee on Seapower and Strategic and Critical Materials,
Submarine Programs, Mar. 20, 1991, p. 10-11, or Statement of Rear Admiral Raymond G.
Jones, Jr., U.S. Navy, Deputy Assistant Chief of Naval Operations (Undersea Warfare), in
U.S. Congress, Senate Armed Services Committee, Subcommittee on Projection Forces and
Regional Defense, Submarine Programs, June 7, 1991, p. 10-11.
10 See Richard W. Mies, “Remarks to the NSL Annual Symposium,” Submarine Review,
July 1997: 35; “Navy Sub Community Pushes for More Subs Than Bottom-Up Review
Allowed,” Inside the Navy, Nov. 7, 1994: 1, 8-9; Attack Submarines in the Post-Cold War
Era: The Issues Facing Policymakers
, op. cit., p. 14; Robert Holzer, “Pentagon Urges Navy
To Reduce Attack Sub Fleet to 50,” Defense News, Mar. 15-21, 1993: 10; Barbara Nagy,
“ Size of Sub Force Next Policy Battle,” New London Day, July 20, 1992, pp. A1, A8.

CRS-5
including 45 to 55 SSNs.11 The Clinton administration’s 1997 QDR supported a
requirement for a Navy of about 305 ships and established a tentative SSN force-
level goal of 50 boats, “contingent on a reevaluation of peacetime operational
requirements.”12 The Clinton administration later amended the SSN figure to 55
boats (and therefore a total of about 310 ships).
The reevaluation called for in the 1997 QDR was carried out as part of a Joint
Chiefs of Staff (JCS) study on future requirements for SSNs that was completed in
December 1999. The study had three main conclusions:
! “that a force structure below 55 SSNs in the 2015 [time frame] and
62 [SSNs] in the 2025 time frame would leave the CINC’s [the
regional military commanders-in-chief] with insufficient capability
to respond to urgent crucial demands without gapping other
requirements of higher national interest. Additionally, this force
structure [55 SSNs in 2015 and 62 in 2025] would be sufficient to
meet the modeled war fighting requirements;”
! “that to counter the technologically pacing threat would require 18
Virginia class SSNs in the 2015 time frame;” and
! “that 68 SSNs in the 2015 [time frame] and 76 [SSNs] in the 2025
time frame would meet all of the CINCs’ and national intelligence
community’s highest operational and collection requirements.”13
The conclusions of the 1999 JCS study were mentioned in discussions of
required SSN force levels, but the figures of 68 and 76 submarines were not
translated into official DOD force-level goals.

Bush Administration. The Bush Administration’s report on the 2001 QDR
revalidated the amended requirement from the 1997 QDR for a fleet of about 310
ships, including 55 SSNs. In revalidating this and other U.S. military force-structure
goals, the report cautioned that as DOD’s “transformation effort matures — and as
it produces significantly higher output of military value from each element of the
force — DOD will explore additional opportunities to restructure and reorganize the
Armed Forces.”14
DOD is currently conducting a study on undersea warfare requirements that has
the potential for changing the attack submarine force-level goal. This study is
11 Secretary of Defense Les Aspin, U.S. Department of Defense, Report on the Bottom-Up
Review
, Oct. 1993, pp. 55-57.
12 Secretary of Defense William S. Cohen, U.S. Department of Defense, Report of the
Quadrennial Defense Review, May 1997, pp. 29, 30, 47.
13 Department of Navy point paper dated February 7, 2000. This point paper is reprinted on
page 5 of the February 14, 2000 issue of Inside the Navy.
14 U.S. Department of Defense, [Report on] Quadrennial Defense Review, Sept. 2001, p.
23.

CRS-6
reportedly an extension or follow-on to an earlier DOD study on the same topic that
was announced in early 2003. The results of the earlier study effort were not
announced. The follow-on study is scheduled to be completed in 2005.
There is concern among submarine supporters that the DOD study could lead
to a reduction to the 55-boat attack submarine force-level requirement that was
established in the 2001 QDR. They are concerned in part because of an internal
Navy study, separate from the DOD study, that reportedly recommends reducing the
attack submarine force level requirement to as few as 37 boats. The study reportedly
recommends homeporting a total of 9 attack submarines at Guam and using satellites
and unmanned underwater vehicles (UUVs) to perform ISR missions now performed
by attack submarines.15 Submarine supporters are concerned that this internal Navy
study may influence the current DOD study on undersea warfare requirements.
A total of 37 attack submarines might be understood as four SSGNs plus 33
SSNs. Since Navy SSNs have estimated service lives of 33 years, a one-per-year
procurement rate would, over the long run, be sufficient to maintain a 33-boat SSN
force.
At a February 12, 2004, hearing before the House Armed Services Committee
on the Department of the Navy’s FY2005 budget, Admiral Vernon Clark, the Chief
of Naval Operations (CNO), was asked by Representative Schrock whether a force
of 30 attack submarines, perhaps in the year 2020, would be “an acceptable number
of boats, given the capability that we may require in that area.” After discussing
changing metrics for measuring military capability, precision weapons, the DD(X)
program, and the Joint Strike Fighter (JSF) program, the CNO stated:
I do not believe this nation can afford to have a submarine force with 30
submarines in it. The Congress has consistently funded the refueling of our fast-
attack fleet. That has given us a hedge against the reduction. If you look out
through the FYDP, it is 54, 55, 56 through the FYDP, and then we have SSGNs
coming, which goes on top of that. This is an issue we clearly have to deal with
and come to grips with what the right capitalization rate needs to be. I can just
tell you, congressman, that this is a major issue for us in the 2006 bill,
fundamentally, a zero-based scrub on how we are going to go about dealing with
the submarine underwater warfare requirement. We will have more and better
information for you and we will continue to be happy to keep you apprised as we
are working through that.16
Although the CNO’s response addressed the acceptability of a force of 30 boats,
it did not address the acceptability of a force falling anywhere in the range of 31 to
54 boats.
15 Bryan Bender, “Navy Eyes Cutting Submarine Force,” Boston Globe, May 12, 2004, p.
1; Lolita C. Baldor, “Study Recommends Cutting Submarine Fleet,” NavyTimes.com, May
13, 2004.
16 Source: Transcript of hearing as provided by Federal Document Clearing House, Inc. The
question was posed by Representative Schrock.

CRS-7
Attack Submarine Force Levels
Historical. During the first half of the Cold War, attack submarines (both
nuclear- and non-nuclear-powered) accounted for an increasing percentage of the
total size of the Navy, increasing from roughly 10% of total battle force ships in the
early 1950s to about 17% by the late 1970s. Since that time, attack submarines have
accounted for roughly 17% to 22% of total battle force ships. At the end of FY2003,
they accounted for about 18% (54 ships of 297).
The SSN force included more than 90 boats during most of the 1980s, peaked
at 98 boats at the end of FY1987, and then began to decline. The force included 85
to 88 boats during the early 1990s, 79 boats at the end of FY1996, 65 boats at the end
of FY1998, 57 boats at the end of FY1999, and 56 boats at the end of FY2000. It has
since numbered 54 to 56 boats.
Current. The 54 SSNs in service at the end of FY2003 included the following:
! 1 Sturgeon (SSN-637) class boat;
! 51 Los Angeles (SSN-688) class boats; and
! 2 Seawolf (SSN-21) class boats.
A total of 37 Sturgeon-class boats were procured between FY1962 and FY1969
and entered service between 1967 and 1975. The one Sturgeon class boat remaining
in service as of the end of FY2003 was the Parche (SSN-683), which entered service
in 1975.
A total of 62 Los Angeles-class submarines, commonly called 688s, were
procured between FY1970 and FY1990 and entered service between 1976 and 1996.
They are equipped with four 21-inch diameter torpedo tubes and can carry a total of
26 torpedoes or Tomahawk cruise missiles in their torpedo tubes and internal
magazines. The final 31 boats in the class (SSN-719 and higher) are equipped with
an additional 12 vertical launch system (VLS) tubes in their bows for carrying and
launching another 12 Tomahawk cruise missiles. The final 23 boats in the class
(SSN-751 and higher) incorporate further improvements and are referred to as
Improved Los Angeles class boats or 688Is. As of the end of FY2003, eight of the
62 boats in the class had been retired.
The two Seawolf-class submarines are the Seawolf (SSN-21) and the
Connecticut (SSN-22). These boats were procured in FY1989 and FY1991 and
entered service in 1997 and 1998, respectively. The third and final Seawolf-class
boat, the Jimmy Carter (SSN-23), was originally procured in FY1992. Its
procurement was suspended and then reinstated in FY1996. It is being built to a
different (i.e., longer) configuration than the first two Seawolf-class boats, and is
scheduled to enter service in 2005. Seawolf class boats are much larger than Los

CRS-8
Angeles-class boats or previous U.S. Navy SSNs,17 and are equipped with eight 30-
inch-diameter torpedo tubes and can carry a total of 50 torpedoes or cruise missiles.
The Seawolf class was originally intended to include about 30 boats, but Seawolf-
class procurement was stopped after three boats as a result of the end of the Cold War
and associated changes in military requirements.
Virginia (SSN-774) Class Program
General. The Virginia-class attack submarine was designed to be less
expensive and better optimized for post-Cold War submarine missions than the
Seawolf-class design. The Virginia-class design is slightly larger than the Los
Angeles-class design,18 but incorporates newer technologies. Virginia-class boats
currently cost about $2.3 billion each in constant FY2005 dollars to procure.
Procurement Through FY2004. The first Virginia-class boat was procured in
FY1998 and is scheduled to enter service in 2004. As shown in the table below, a
total of six Virginia-class boats have been procured through FY2004.
Table 1. Virginia-class procurement, FY1998-FY2004
FY1998
FY1999
FY2000
FY2001
FY2002
FY2003
FY2004
1
1
0
1
1
1
1
Joint Production Arrangement. Virginia-class boats are built jointly by
General Dynamics’ Electric Boat Division (GD/EB) of Groton, CT, and Quonset
Point, RI, and Northrop Grumman’s Newport News Shipbuilding (NGNN) of
Newport News, VA.19 Under the arrangement, GD/EB builds certain parts of each
boat, NGNN builds certain other parts of each boat, and the yards take turns building
the reactor compartments and performing final assembly of the boats. GD/EB is
building the reactor compartments and performing final assembly on boats 1, 3, and
so on, while NGNN is doing so on boats 2, 4, and so on. The arrangement results in
a roughly 50-50 dollar-value division of work between the two yards and preserves
both yards’ ability to build submarine reactor compartments (a key capability for a
submarine-construction yard) and perform final assembly work.
The joint production arrangement is a departure from past U.S. submarine
construction practices, under which complete submarines were built in individual
17 Los Angeles-class boats have a beam (i.e., diameter) of 33 feet and a submerged
displacement of about 7,150 tons. Seawolf-class boats have a beam of 40 feet and a
submerged displacement of about 9,150 tons (more for the Jimmy Carter).
18 Virginia-class boats have a beam of 34 feet and a submerged displacement of 7,800 tons.
19 GD/EB and NGNN are the only two shipyards in the country capable of building nuclear-
powered ships. GD/EB builds submarines only, while NGNN also builds nuclear-powered
aircraft carriers and is capable of building other types of surface ships. The submarine
industrial base also includes scores of materials and parts suppliers, and laboratories and
research facilities, in various parts of the country.

CRS-9
yards. The joint production arrangement is the product of a debate within Congress,
and between Congress and DOD, over the Virginia-class acquisition strategy that
occurred in 1995-1997 (i.e., during the markup of the FY1996-FY1998 defense
budgets). The goal of the arrangement is to keep both GD/EB and NGNN involved
in building nuclear-powered submarines, and thereby maintain two U.S. shipyards
capable of building nuclear-powered submarines, while minimizing the cost penalties
of using two yards rather than one to build a submarine design that is being procured
at a low annual rate.20
Deferral of Two-Per-Year Rate To FY2009. The FY2004-FY2009 FYDP that
the Administration submitted to Congress in February 2003 projected increasing the
Virginia-class procurement rate to two per year starting in FY2007. The amended
FY2005-FY2009 FYDP submitted in February 2004 delayed this projected increase
two years, to FY2009. The table below compares Virginia-class procurement in the
two FYDPs.
Table 2. Proposed Virginia-class procurement
FYDP
FY2004 FY2005 FY2006 FY2007 FY2008 FY2009
FY2004-FY2009 FYDP (2/03)
1
1
1
2
2
2
FY2005-FY2009 FYDP (2/04)
1
1
1
1
1
2
Multiyear Procurement (MYP) For FY2004-FY2008. As part of its proposed
FY2004 budget submitted to Congress in February 2003, the Navy requested
multiyear procurement authority (MYP) to procure a total of seven Virginia-class
boats during the five-year period FY2004-FY2008 (i.e., one boat per year for
FY2004-FY2006, then two boats per year for FY2007-FY2008, as shown in the top
line in the table above). Congress, as part of its action on the FY2004 defense
budget, granted authority in appropriation bill language for a five-boat MYP during
this period (i.e., one boat per year for FY2004-FY2008). The Navy estimates that the
five-boat MYP arrangement will reduce the total cost of the five boats by a total of
about $400 million, or an average of $80 million per boat.21
The five-boat MYP authority was accompanied by appropriation conference
report language that the Navy and other observers have interpreted as strongly
cautioning the Navy against including funding in future budgets to support the
procurement of a second boat in either FY2007 or FY2008.22 Consistent with this
20 For more on this debate and the legislation establishing the joint production arrangement,
see CRS Report RL30045, Navy Attack Submarine Programs: Background and Issues for
Congress
, by Ronald O’Rourke.
21 The Navy estimated that a 7-boat MYP arrangement would have reduced the cost of the
seven boats in question by an average of about $115 million per boat.
22 Section 8008 of the bill approves MYP authority for the Virginia-class program
“Provided, That the Secretary of the Navy may not enter into a multiyear contract for the
procurement of more than one Virginia Class submarine per year.” For the bill and report
(continued...)

CRS-10
interpretation, the Administration’s amended FY2005-FY2009 FYDP includes
funding for only one Virginia class boat per year for the period FY2005-FY2008.
Option for Procuring Second Boat in FY2007 or FY2008. Although the
FY2004 appropriation bill and report language may effectively discourage the Navy
from requesting funding in its budgets for a second boat in FY2007 or FY2008, they
do not necessarily prevent a future Congress from funding a second boat in FY2007
or FY2008 that the Navy has not requested funding for, if a future Congress wants
to fund such a boat and determines that there is sufficient funding available for the
purpose. A future Congress could alter the Virginia-class MYP authority to permit
a second boat procured in FY2007 or FY2008 to be covered under the MYP contract.
Alternatively, it might be possible to build a second boat procured in FY2007 or
FY2008 under a non-MYP contract (i.e., a regular, single-boat construction contract)
that is separate from the MYP contract.
In restructuring its budget to support the procurement of five (rather than 7)
Virginia-class submarines in FY2004-FY2008, the Navy eliminated advance
procurement (AP) funding in FY2005-FY2007 for long-leadtime nuclear-propulsion
components for second boats procured in FY2007 and FY2008. The absence of AP
funding in FY2005-FY2007, however, would not prevent a future Congress from
procuring a second boat in either year. It simply means that the interval between the
year of procurement and the year the boat enters service would be two or three years
longer than usual (i.e., eight or nine years rather than the usual six years).
Congress can, and has, fully funded the procurement of nuclear-powered ships
for which there was no prior-year AP funding for long-leadtime components. Doing
so involves funding the entire procurement cost of the ship in the year of
procurement, including the funding that normally would have been provided in prior
years as AP funding. For example, Congress in FY1988 fully funded the
procurement of the aircraft carriers CVN-74 and CVN-75 as a two-ship buy, even
though there had been no prior-year AP funding for the ships.23
22 (...continued)
language on Congress’ decision, see the conference report (H.Rept. 108-283 of September
24, 2003) on the FY2004 defense appropriations bill (H.R. 2658/P.L. 108-87 of September
30, 2004), pages 20, 185-186.
23 The Administration’s FY1988 budget and FY1988-FY1992 FYDP proposed procuring
CVN-74 in FY1990, with advanced procurement funding in FY1988 and FY1989, and
CVN-75 in FY1993, with advance procurement funding in FY1989-FY1992.
Following Congress’ decision in FY1988, construction of long-leadtime components began
right away, construction of CVN-74 itself began about two years later, and construction of
CVN-75 began about two years after that. CVN-74 entered service in 1995, seven years
after the year of procurement (a typical time to build a carrier), and CVN-75 entered service
in 1998, 10 years after the year of procurement.

CRS-11
Recent Procurement Rates And Congressional Concern
The post-Cold War downturn in procurement began sooner and was
proportionately deeper for attack submarines than for most other kinds of Navy ships.
As a result, achieving and maintaining certain potential future attack submarine force
levels in future years could be particularly challenging.
The rate of attack submarine procurement has been a concern in Congress since
the mid-1990s. It has been discussed by CRS in testimony to Congress in 1995,
1997, 1999, 2000, 2002, and 2004, in a 1997 CRS presentation to a Defense Science
Board task force on the submarine of the future, which issued its report in 1998;24 in
a 1999-2000 CRS report,25 and in a 2002 CRS report.26 This discussion is updated
to take into account DOD’s FY2005-FY2009 FYDP.
The Administration’s FY2005-FY2009 FYDP, if implemented, would result in
the procurement of 15 SSNs during the 20-year period FY1990-FY2009. These 15
boats include the final Los Angeles class boat (in FY1990), the second and third
Seawolf class boats (in FY1991 and FY1996), and the first 12 Virginia class boats
(one each in FY1998, FY1999, and FY2001-FY2008, and two in FY2009). A total
of 15 boats in 20 years would equate to an average procurement rate of 0.75 boats per
year for more than one-half of the SSN fleet’s 33-year replacement cycle.
If, during this 20-year period, SSNs were instead procured at an average rate of
1.67 boats per year, which is the steady-state replacement rate for a force of 55 boats
with 33-year service lives,27 a total of 33 SSNs would be procured. The FY2005-
FY2009 FYDP, if implemented, would thus create an SSN procurement backlog,
relative to the steady-state replacement rate, of 18 boats (33 minus 15) for the period
FY1990-FY2009.
This 18-boat backlog in procurement, which is equivalent to about 33% of the
55-boat force-level objective, will be masked between now and about 2015 by the
large numbers of SSNs procured during the 1980s. After about 2015, however, SSNs
procured during the 1980s will reach retirement age and begin to leave service, and
the FY1990-FY2009 backlog in SSN procurement relative to the steady-state
procurement rate, if not by then redressed, will begin to become apparent.
24 U.S. Department of Defense, Office of the Under Secretary of Defense For Acquisition
& Technology, Report of the Defense Science Board Task Force on [the] Submarine of the
Future
, July 1998, pp. 7, 19-20.
25 CRS Report RL30045, Navy Attack Submarine Programs: Background and Issues for
Congress
, by Ronald O’Rourke.
26 CRS Report RL31372, Navy Shipbuilding in the FY2003 Defense Budget: Issues for
Congress
, by Ronald O’Rourke.
27 The steady-state replacement rate is the average procurement rate that would be needed,
over the long run, to maintain a force at a given size over the long run. It is equal to the
force-level goal divided by expected service life — in this case, 55 boats divided by 33
years, or 1.67 boats per year.

CRS-12
The graph on the next page shows the consequences on the size of the SSN
force out to the year 2050 of various constant SSN procurement rates after FY2009,
assuming a 33-year life for existing SSNs. The graph assumes no early retirements
of SSNs beyond those that have already occurred (i.e., the refueling of all 688s that
will become available for refuelings over the next several years). The graph excludes
the four SSGNs that are scheduled to be in service between FY2006 and FY2026.
As shown in the graph, the attack submarine force under various constant future
procurement rates would reach a minimum level in the late 2020s.

CRS-13
Potential SSN Force Levels, 2000-2050
Notional projections resulting from post-FY2009 SSN
procurement rates ranging from 0 per year to 3 per year
110
Includes SSNs procured through FY2004, plus
100
those planned for procurement for FY2005-
3.0/year
90
FY2009, and no additional early retirements of
688s. Assumes 33-year life for SSNs. Excludes
80
2.5/year
4 SSGNs in service FY2006-FY2026.
70
60
2.0/year
50
1.5/year
40
30
1.0/year
20
10
0/year
0
0
10
20
30
40
50
Year

CRS-14
Issues for Congress
The current situation regarding attack submarines poses at least three potential
issues for Congress:
! Should the attack submarine force-level goal be 55 or some other
number?
! At what rate should Virginia-class submarines be procured in
coming years?
! Should the current joint-production arrangement for building
Virginia-class submarines be continued or altered?
Each of these issues is addressed below.
Attack Submarine Force-Level Goal
Should the attack submarine force-level goal be 55 or some other number?
Key Factors To Consider. In considering whether the attack submarine
force-level goal should be 55 or some other number, key factors to consider include
the following:
! day-to-day demands for attack submarines in recent years;
! recent and potential wartime demands for attack submarines;
! submarine-launched unmanned vehicles (UVs);
! attack submarine homeporting and crewing arrangements;
! the SSGN conversion program; and
! contributions by allied and friendly attack submarines.
The discussion of these key factors runs several pages. Accordingly, below is
a summary of some key points arising out of the discussion. Following the summary
are the sections discussing each factor.
Summary of Key Points. Key points regarding factors affecting the attack
submarine force-level goal include the following:
! Some Navy submarine officers in recent years have argued that an
attack submarine force of roughly 55 boats is insufficient to meet
day-to-day demands for attack submarines from U.S. regional
military combatant commanders, at least not without operating
attack submarines at higher-than-desired operational tempos. Much
of the day-to-day demand for attack submarines appears to be for
performing ISR missions. A force of 70 or more submarines, Navy
submarine officers and DOD officials have argued or implied, would
be needed to meet all day-to-day demands for attack submarines, at
least not without operating attack submarines at an elevated
operational tempo.

CRS-15
! Recent major U.S. warfighting operations have used relatively small
numbers of attack submarines — about a dozen or less in each case.
Certain potential future major U.S. warfighting scenarios, such as a
conflict on the Korean Peninsula or a conflict with China, may
feature a greater maritime component and consequently require a
larger number of attack submarines.
! Submarine-launched unmanned underwater vehicles (UUVs), by
permitting each submarine to perform a greater number of
underwater missions at the same time, could, other things held equal,
be used to argue in favor of having fewer attack submarines. On the
other hand, submarine-launched unmanned air vehicles (UAVs), by
permitting attack submarines to perform overhead and deep-inland
ISR operations now performed by satellites or by aircraft launched
from land bases and surface ships, could, other things held equal, be
used to argue in favor of having more attack submarines.
! Homeporting up to eight additional attack submarines at Guam
(beyond the three already homeported there) and operating attack
submarines with dual or multiple crews — both suggested by the
Congressional Budget Office (CBO) in a March 2002 report28 —
could, other things held equal, reduce the number of attack
submarines needed to perform a given set of submarine missions and
consequently could, other things held equal, be used to argue in
favor of having fewer attack submarines.
! Converting two or four additional Trident SSBNs into SSGNs
(beyond the four already planned for conversion) could, other things
held equal, reduce at the margin the number of attack submarines
needed to perform a given set of submarine missions and
consequently could, other things held equal, be used to argue in
favor of having fewer attack submarines. The opportunity to convert
two or four additional Trident SSBNs into SSGNs would depend on
a decision to reduce the SSBN force from the currently planned total
of 14 ships to 12 or 10 ships.
! Submarines from allied and friendly countries, particularly the
United Kingdom (UK) and Australia, might occasionally be able to
perform missions that might otherwise be performed by U.S. attack
submarines and thereby reduce requirements for U.S. attack
submarines. The reduction in requirements for U.S. attack
submarines, however, might be fairly small, and planning U.S.
forces on the assumption that foreign submarines will be available
to perform these missions entails some risk, given inherent
uncertainty over the future policies of foreign governments.
28 U.S. Congressional Budget Office, Increasing the Mission Capability of the Attack
Submarine Force,
Mar. 2002.

CRS-16
Day-to-Day Demands for Attack Submarines in Recent Years.
In General. Some Navy submarine officers and DOD officials in recent years
have argued that an attack submarine force of roughly 55 boats is insufficient to meet
day-to-day demands for attack submarines from U.S. regional military combatant
commanders, at least not without operating attack submarines at higher-than-desired
operational tempos. Navy submarine admirals have stated that since the end of the
Cold War, demands for attack submarines from regional U.S. commanders have
increased, not decreased, that some demands for attack submarines are going
unfilled, and that the high operational tempo of the attack submarine force could
reduce time available for training and expend submarine reactor core life more
quickly than planned, potentially shortening attack submarine service lives.
In March 2004, for example, Admiral Frank Bowman, the Director of the
Navy’s nuclear propulsion program, stated that “Today the navy is unable to meet all
the combatant commanders’ submarine requirements” and that “only about 65% of
requirements can be met.”29 In September 2003, John Grossenbacher, a recently
retired Navy submarine admiral, stated that attack submarines are more in demand
that at any time in the Cold War, that the attack submarine force is “about as thin as
we can be and still maintain a worldwide deployable and world class submarine
force,” and that as the force declines in size, some demands for submarines to
perform covert ISR missions may go unmet.30
29 Andrew Koch, “[Interview with] Adm Frank Bowman, Director Of US Naval Nuclear
Reactors,” Jane’s Defence Weekly, Mar. 31, 2004. The article stated:
[Admiral] Frank Bowman, director of US Naval Nuclear Reactors, the service’s
senior submariner, says he “fully supports those studies” if they lead to a
reduction in what is being asked of the force. “Today the navy is unable to meet
all the combatant commanders’ submarine requirements,” Adm Bowman says,
explaining that “only about 65% of requirements can be met. There is prima facie
evidence in the real world that to execute the missions those commanders have
been assigned, they need these submarines.
“I would not oppose a finding that said some of the submarine tasking today can
be assigned to other [existing] platforms or future platforms because it would
ease the tension between the desires of the combatant commanders and the
[submarine] inventory and therefore the ability of the navy to meet those
requirements,” Adm Bowman says.
One area being considered is whether intelligence, surveillance and
reconnaissance (ISR) missions can be performed by other means, such as
distributed sensor networks. Adm Bowman says he would like “to perhaps find
some relief for our submarines so that missions of higher priority that we are not
able to do today because of the ISR [taskings] could be [taken on].”
Except for “[Admiral],” material above in italics and brackets below appears as in the
original.
30 Robert A. Hamilton, “Lack Of Subs Could Slow Pace Of Technology, Admiral Warns,”
New London (CT) Day, Sept. 30, 2003. The article stated:
(continued...)

CRS-17
In June 2003, a senior DOD official wrote a letter to the General Accounting
Office stating: “Combatant commanders have requested 14.4 SSNs for [calendar
year 2003] for national and combatant commander intelligence, surveillance and
reconnaissance (ISR), Tomahawk strike, carrier battlegroup support, and Special
Operations Forces equipped SSN missions.” The letter also stated that “Considering
the sustainability and training requirements given its current SSN fore structure, the
Navy is able to provide 10.0 of the requested 14.4 SSNs deployed annually.”31
30 (...continued)
From almost 100 submarines in the early 1990s, the number has fallen
steadily to just over 50, and their services are more in demand than at any time
in the Cold War, said Vice Adm. John J. Grossenbacher, who retired as
commander of Naval Submarine Forces this month....
Grossenbacher said several studies that have looked at submarine force
requirements have set the minimum size of the fleet at 68 to 72 submarines.
Studies by other groups have set a smaller number, but he called them
“misinformed,” and often don’t allow for sufficient time between deployments....
“The problem we have today is just numbers,” Grossenbacher said. “We
don’t have enough. ... In my opinion, we’re about as thin as we can be and still
maintain a worldwide deployable and world class submarine force.”
As the size of the force continues to decline — the Navy is building one
submarine a year, which will eventually result in a force of 30 boats —
Grossenbacher said some requests for the covert surveillance services that
submarines provide are going to “drop off the plate.”
“The question becomes, ‘What is it that you don’t want to know?’ “
Grossenbacher said.
31 Keeter, Hunter. DOD Answers Concerns Over Virginia-class Multiyear, Details Sub
Force Shortfalls. Defense Daily, June 27, 2003. The article stated:
Glenn Lamartin, director of defense programs with the office of the
undersecretary of defense, in a June 23 letter to [the General Accounting Office],
outlined that “the pre-9/11 demand was 9.9 SSNs and the post 9/11 demand has
been 12.9 SSNs.”
“Combatant commanders have requested 14.4 SSNs for [calendar year
2003] for national and combatant commander intelligence, surveillance and
reconnaissance (ISR), Tomahawk strike, carrier battlegroup support, and Special
Operations Forces equipped SSN missions,” Lamartin wrote.
“Considering the sustainability and training requirements given its current
SSN force structure, the Navy is able to provide 10.0 of the requested 14.4 SSNs
deployed annually.”...
Citing a 1999 study by the Joint Chiefs of Staff, Lamartin said that dropping
below 55 attack submarines in the 2015 time frame and 62 in the 2025 time
frame would leave regional warfighting commanders “with insufficient capability
to respond to urgent crucial demands without gapping other requirements of high
(continued...)

CRS-18
The reference to the Navy being able to provide 10.0 attack submarines refers
to the fraction of the attack submarine force that, on average over the long run, can
be maintained on station in overseas operating areas at any given moment. The Navy
reported to CRS in 1999 that, on a global basis, an average of 5.8 attack submarines
are needed to keep one attack submarine continuously on station in a distant
operating area. This attack submarine “stationkeeping multiplier” changed little
between 1992 and 2002, and is broadly consistent with the stationkeeping multipliers
for other kinds of Navy ships.32 Using this multiplier, keeping a total of 10.0 attack
submarines continuously on station in overseas operating areas would require a total
attack submarine force of 58 boats. The DOD official’s letter suggests that as of
mid-2003, the stationkeeping multiplier was closer to 5.4, since this would enable the
54-boat attack submarine force of 1993 to keep 10.0 boats continuously on station.
Using this same multiplier, keeping 14.4 boats — the higher figure mentioned in the
DOD official’s letter — continuously on station would require a total force of about
78 boats.
In June 2003, Admiral Grossenbacher (then still on active duty) stated that the
attack submarine force was operating at its maximum rate but that this was still
insufficient to meet day-to-day demands for attack submarines. He stated that the
Navy would need about 70 attack submarines to meet the demands being placed on
the force.33 Another submarine admiral, in a different article, stated the same month
31 (...continued)
national interest.”
32 Source: Navy Office of Legislative Affairs (NOLA) point paper to CRS of March 25,
1999 (record number LA-586-002), and NOLA e-mail to CRS of December 17, 2002, stating
that the figures in the 1999 point paper had not changed significantly. An NOLA point
paper to CRS dated August 8, 1996 stated that the global stationkeeping multiplier for attack
submarines was 5.8. An NOLA point paper to CRS dated September 10, 1992 stated that
the number was 5.7. The 1992 figure was published by CRS in Report 92-803 F, Naval
Forward Deployments and the Size of the Navy
, by Ronald O’Rourke. Washington, 1992.
(November 13, 1992) p. 14.
33 Jason Ma, “Grossenbacher: Sub Force Is Operating At Fastest, Sustainable Pace,” Inside
the Navy
, June 23, 2003. The article stated:
The submarine force is operating at a maximum rate that still maintains a
surge capability, but that is still not enough to meet the needs of operational
commanders, said Vice Adm. John Grossenbacher, commander of naval
submarine forces.
Instead of the current 54 attack subs, the Navy really needs 70, he said at
the Naval Submarine League’s conference June 11 in Alexandria, VA. But with
54, “operational commanders are not getting all that they need” and the sub
forces are struggling to support tactical development, operational testing and
long-term “self-investments,” he said.
Grossenbacher and Rear Adm. John Padgett, commander of submarine
forces in the Pacific Fleet, closely monitor the fuel expenditure of the subs to
meet wartime demands or surges. To avoid early depletion of the reactor core,
(continued...)

CRS-19
that attack submarine operational tempo was about 15 percent to 20 percent higher
than preferred, and that this could affect the amount of time available for training.34
In March 2003, Admiral Bowman stated that the high operational tempo for
attack submarines has been using up reactor core life faster than planned and that as
a result, Los Angeles-class submarines may need to be retired earlier than expected.35
33 (...continued)
they would reduce operations if necessary, he said. “We’re walking that fine line
right now,” he added.
“I think we’re getting about as much as we can out of the force and running
them at the fastest pace that we can sustain over time, maintain long-term
readiness, as well as something in the bank for surges,” Grossenbacher said.
34 Jason Ma, “Admiral: Subs Must Be Both Surge-Ready And Deployed Forward,” Inside
the Navy
, June 16, 2003. The article stated:
In preparing for increased surge capability, the submarine force must also
remain deployed forward and should avoid becoming a “garrison force,” said
Rear Adm. John Padgett, commander of submarine forces in the Pacific Fleet.
Chief of Naval Operations Adm. Vern Clark’s “Fleet Response Plan” calls
for a more responsive fleet that can surge a large number of ships on short notice,
requiring new maintenance and training cycles to achieve increased readiness
and availability.
Submarines are forward-deployed to support battle space preparations and
to ensure that operators understand the battle space, Padgett said at the Naval
Submarine League’s annual conference last week in Alexandria, VA.
“I am concerned that the surge mentality might become a bastion
mentality,” he said. “I would argue, from my perspective, that we do not need a
garrison force submarine force. We need to remain a forward-deployed force.”
Submarines must maintain forward deployment because they conduct much
of their training with the navies of allied countries in the Western Pacific like
Japan, South Korea, Singapore and Australia, Padgett said. Such training
includes scenarios with diesel submarines, a threat that some Navy officials have
noted is becoming more sophisticated....
Ultimately, force structure dictates the ability to forward deploy subs, and
the Navy needs more subs, he said. Having submarine homeports in Guam and
Japan partly addresses the lack of enough subs, but the operational tempo is
about 15 percent to 20 percent higher than what he would like, affecting training
and maintenance, he said. Although the Navy is managing the shortfall in subs,
the tendency is to put operational requirements over exercise requirements,
which could have a “detrimental effect.” The problem is Navy-wide and not
unique to the sub forces, he added.
35 Ma, Jason. Industry, Navy Officials Push To Boost Annual Submarine Buy Rate. Inside
the Navy
, March 3, 2003. The article stated:
(continued...)

CRS-20
And in January 2003, Admiral Grossenbacher stated that demands for submarines to
perform covert ISR missions has been high since the terrorist attacks of September
11, 2001, and that the attack submarine force was having to turn down some requests
for attack submarines from regional combatant commanders due to insufficient
forces.36
Articles making similar points have been published since the mid-1990s, and
particularly since 1999, when the attack submarine force declined to less than 60
boats.37
35 (...continued)
The Los Angeles-class subs may retire sooner than expected, [Admiral
Frank Bowman] said.... Because demand for subs has increased since the war on
terrorism, the submarine fleet has been operating longer and at faster speeds than
usual. If that continues, sub reactor cores will not last for the expected 30 years,
he said.
Attack submarines are nearing a 90 percent operational tempo and are
transiting at 20 knots rather than 16 knots, he said. The ratio of time in port to
time deployed is about 2-to-1 instead of 3-to-1 before the war on terrorism, he
added.
“Something’s got to give; something will give,” Bowman said. “So we’re
trying to make ends meet, but what’s going to give at the end of the day is the
reactor core endurance.”
See also Eisman, Dale. Subs Could Be Exhausted Early If Heavy Usage Continues. Norfolk
Virginian-Pilot
, February 26, 2003; Lerman, David. Attack Subs May Be In Too Deep.
Newport News Daily Press, February 26, 2003.
36 Dolan, Matthew. Subs In High Demand, Force Commander Says. Norfolk Virginian-
Pilot
, January 27, 2003. The article stated:
Submarines have been pushed so hard in the war on terrorism that the Navy
is having to turn down requests from combat commanders around the world....
The stealthy ability of submarines to engage in surveillance, reconnaissance
and intelligence gathering has been in high demand since the Sept. 11 attacks,
[Admiral Grossenbacher] said....
“The current operational tempo that we’re operating at is manageable, but I’d
like it to be lower. It’s not a crisis.”
37 For examples between November 1994 and January 2003, see the following: Ma, Jason.
Grossenbacher: Subs Can Maintain Optempo A ‘Couple More Years.’ Inside the Navy,
November 25, 2002; Loeb, Vernon. Espionage Demands Prod Navy On Sub Construction.
Washington Post, July 5, 2002: 19; Woods, Randy. Atlantic, Pacific Admirals Say Subs
Cannot Sustain Current Optempo. Inside the Navy, June 17, 2002; Jaffe, Greg. Overuse Of
Nuclear Submarines Risks Burning Up Reactor Cores. Wall Street Journal, June 26, 2002;
Koch, Andrew. USN SSN Force Faces Overstretch. Jane’s Defence Weekly, June 19, 2002;
Keeter, Hunter. Bowman: Submarine Force Level Inadequate To Meet Requirements.
(continued...)

CRS-21
ISR Operations In Particular. ISR operations appear to form a key part of
the discussion over day-to-day demands for attack submarines. As mentioned earlier
(see Background section), the internal Navy study that reportedly recommends
reducing the attack submarine force-level goal to as few as 37 boats reportedly
recommends using satellites to perform ISR missions now done by attack
submarines.
Submarine ISR operations are a sensitive issue that is rarely discussed in public
in any detail. Some general comments about the matter, however, can be made.
One set of comments concerns the relative merits of SSNs as ISR platforms.
SSNs offer three basic strengths as platforms for performing ISR missions. One is
that they can perform such missions without their presence being detected by ISR
targets, increasing the chance of getting candid observations of the targets. Potential
ISR targets can consult reference sources on satellite orbits to understand when
certain satellites are likely to be overhead, or use radar to detect and track aircraft
flying nearby. Armed with this information, ISR targets can take steps to conceal
objects or to alter or avoid certain activities. In contrast, U.S. Navy submarines
operating stealthily are very difficult, if not impossible, for ISR targets to detect,
increasing the chance that the targets will behave candidly.
37 (...continued)
Defense Daily, June 13, 2002; Bohmfalk, Christian. Basing Attack Subs On Guam Expected
To Increase Fleet’s Presence. Inside the Navy, February 12, 2001; Holzer, Robert. With
Limited Subs, U.S. Navy Looks Westward to Guam. Defense News, August 28, 2000: 4;
Burns, Robert. U.S. Considers Increase In Submarine Fleet, Mainly For Spy Role. Fort
Worth Star-Telegram
, August 18, 2000; Brown, David. Officials Sound Alarm On Sub
Shortage. Navy Times, July 10, 2000: 20; Konetzni, Albert H. Jr. “Two Diverging Paths”
For Pacific Fleet Submarine Force. Sea Power, July 2000: 29; Wolfe, Frank. Submarine
Commanders Want 75 Fast Attack Subs For Missions, Exercises. Defense Daily, June 28,
2000: 5; Keeter, Hunter. Konetzni: Navy Needs Greater Funding Commitment To
Submarine Force. Defense Daily, June 16, 2000: 7; Holzer, Robert. Intelligence Operations
Suffer As Submarine Fleet Dwindles. Defense News, April 17, 2000: 1, 36; Holzer, Robert.
Utility of Subs Rises as Targeting Grows More Precise. Defense News, April 10, 2000: 17;
Corless, Josh. Numbers Count As Submarine Commitments Stretch USN. Jane’s Navy
International
, March 2000: 18-24; Hamilton, Robert A. Support Growing For More
Submarines. New London (CT) Day, March 7, 2000; Gordon, Mike. Opposition Surfaces,
‘Silent Service’ Says No To Further Cuts. Navy Times, January 17, 2000: 14-16; Graham,
Bradley. Pentagon Warns Against Cutting Attack Sub Fleet. Washington Post, January 4,
2000: 3; Holzer, Robert. U.S. Submariners Urge Halt To Dwindling Fleet. Defense News,
June 28, 1999: 6; Abel, David. Some Say US Sub Force Is Spread Too Thin. Boston Globe,
June 28, 1999: 5; Corless, Josh. Problems Beneath The Waves. Jane’s Navy International,
June 1999: 10; Holzer, Robert. Overwork Strains U.S. Sub Fleet. Defense News, March 15,
1999: 4, 42; Karniol, Robert. Intelligence Rises For US Pacific Subs. Jane’s Defence
Weekly
, December 16, 1998: 13; Wolfe, Frank. Navy Fears Drop Below 50 Attack
Submarines. Defense Daily, June 15, 1998: 6-7; Bender, Bryan. U.S. Submarine Operations
Rise Since End of Cold War. Defense Daily, November 1, 1996: 183; Holzer, Robert.
Study Reveals U.S. Sub Force Flaws. Defense News, June 10-16, 1996: 3; Navy Sub
Community Pushes For More Subs Than Bottom-Up Review Allowed. Inside the Navy,
November 7, 1994: 1, 8-9.

CRS-22
A second advantage of SSNs as ISR platforms is persistence on station. Low-
orbiting satellites can view a particular area only periodically as they pass overhead,
and perhaps only for a few minutes at a time. Aircraft might be able to remain
airborne in a viewing position for a matter of hours before needing to return to base.
An SSN, in contrast, can remain on station in a viewing location continuously for
days, weeks, or even months at a time, permitting the SSN to detect and provide
evidence of patterns of behavior that may be discernible only through continuous
observation over an extended period of time.
A third advantage of SSNs as ISR platforms is their viewing position offshore
and just under the surface of the water. This position permits them to observe certain
ISR targets — particularly ports, coastal areas, surface ships, other submarines, and
underwater mines — at potentially close ranges, permitting the collection of detailed
information on these targets.
SSNs, however, have two basic limitations as platforms for performing ISR
missions. One concerns overhead observations, which can be helpful or even critical
in understanding the totality of objects or activities being observed in a certain area.
Satellites and aircraft are inherently capable of performing overhead observations,
but SSNs are not. SSNs observe land targets from the side, but cannot observe the
totality of objects or activities in a certain area.
A second disadvantage of SSNs as ISR platforms concerns imaging inland
areas. Satellites and aircraft are inherently capable of imaging inland areas, but SSNs
have relatively little ability to do this. From their position just below the water’s
surface, SSNs in general can collect images of objects that are no further inland than
the first row of buildings or the first row of hills.
A second general comment about submarine ISR operations concerns how the
universe of ISR targets may have changed since the end of the Cold War. The end
of the Cold War may have reduced demands for ISR missions against what is now
Russia, but may have increased demands for ISR missions against both countries
other than Russia and non-state actors such as terrorist organizations.
A third general comment concerns the relationship of ISR missions to the attack
submarine force-level requirement. It is plausible that ISR missions by themselves
might generate a requirement for a relatively large attack submarine force,
particularly if those ISR missions require extended or continuous observations of
intelligence targets. Performing such missions brings the attack submarine
stationkeeping multiplier into play, and as explained earlier, only nine or 10 missions
requiring continuous attack submarine presences in overseas operating areas would
be needed to generate an attack submarine force level of about 55.
ISR missions, however, are not necessarily the only day-to-day missions that
might require attack submarines to remain on station on an extended or continuous
basis. Examples of other missions that might require such operations include
protection of forward-deployed Navy surface ships, covert insertion and recovery of
special operations forces, and Tomahawk strike (i.e., the mission of keeping a certain
number of Tomahawks ready in a given region to be fired on short notice if needed

CRS-23
— a mission that can also be performed, though not with the same level of
covertness, by surface ships).
If submarine supporters are generally correct about the existence and findings
of the internal Navy study on attack submarines (see Background section), then one
potential implication is that the authors of this study believe that submarine ISR
operations represent the “long pole in the tent” in driving the attack submarine force-
level requirement — the only mission requiring a force of 55 or more attack
submarines.
If this view is held by the authors of the internal Navy study, however, it is not
necessarily shared by all others. For example, Admiral Bowman’s above-cited
comments from March 2004 suggest that even if attack submarine ISR missions are
reduced, attack submarines will still have other, and possibly even higher-priority,
day-to-day missions to perform.38 This perspective suggests that a force of 55 or
more attack submarines might still be needed on a day-to-day basis even if attack
submarine ISR missions are reduced.
Questions for Congress. Potential questions for Congress regarding day-
to-day demands for attack submarines include the following:
! Is it still the case, as DOD indicated it was for calendar year 2003,
that combatant commanders are requesting 14.4 SSNs for national
and combatant commander ISR, Tomahawk strike, carrier
battlegroup support, and SOF support? If not, how many SSNs are
combatant commanders now requesting? What portion of current
combatant commander requests for SSNs is going unmet? What
kinds of missions are not being performed due to lack of available
attack submarines?
! What is the current operational tempo for U.S. attack submarines,
and how does this compare with the preferred operational tempo?
What effect might current operational tempo have on recruiting and
retention of submarine personnel, submarine training, submarine
maintenance, and reactor core life?
! What portion of combatant commander requests for SSNs are driven
by ISR missions vs. other kinds of missions? Do ISR missions
represent the “longest pole in the tent” in generating day-to-day
demands for attack submarines? How many SSNs do combatant
commanders require on a day-to-day basis for non-ISR missions
such as carrier battlegroup support, SOF support, and Tomahawk
strike?
! What fraction of the information collected by U.S. ISR operations of
all types is collected by U.S. attack submarines? How is the
38 See the details of Admiral Bowman’s comments in the earlier footnote quoting from the
March 2004 article.

CRS-24
information collected by submarines similar to, or different than,
information collected through other means? How important is
submarine-collected intelligence to national-level policymakers?
How important is it to military commanders? What is the potential
risk to the United States if U.S. attack submarines collect less of this
information?
! How might submarine-launched UAVs affect submarine ISR
missions? What new ISR missions could UAV-equipped
submarines perform?
! To what degree can this information be collected through other
means such as satellites, aircraft, or human intelligence?
Recent and Potential Wartime Demands for Attack Submarines.
Attack Submarines in Recent Conflicts. The table below summarizes the
numbers of U.S. Navy attack submarines reported to have participated in recent
major U.S. military operations.
Table 3. U.S. SSNs In Recent Major Military Operations
Number of
Year
Location
U.S. SSNs
Comments
involved
1991
Persian
13
2 US SSNs fired 12 of 288 Tomahawks used. SSNs also
Gulf War
performed war-related ISR missions.
1999
Kosovo
6
1 UK SSN, 1 Italian SS,* and 1 Dutch SS were also
involved. Submarines were used for sea control. Four
SSNs (3 US; 1 UK) fired some portion of 218 Tomahawks
used.
2001-
Afghan-
2
1 UK SSN was also involved. 2 U.S. SSNs fired about 1/3
2002
istan
of 82 Tomahawks used by the U.S. Navy. The UK SSN
fired additional Tomahawks. Submarines also conducted
war-related ISR, antisubmarine warfare, and anti-surface
warfare operations.
2003
Iraq
12
2 UK SSNs were also involved. 12 U.S. and UK SSNs
fired about 1/3 of 802 Tomahawks used.
* SS = non-nuclear-powered attack submarine.
Sources: DOD and Navy reports and press reports; see footnotes for discussions printed below.
The following discussions elaborate on the information in the above table.
1991 Persian Gulf War (Desert Shield). A total of 13 U.S. attack
submarines were deployed to the Gulf region for the 1991 Gulf War. Two of the

CRS-25
submarines launched a total of 12 Tomahawks, or about 4% of the 288 Tomahawks
fired in the war.39 A Navy report on the Navy’s participation in the Gulf war stated:
During Desert Shield/Storm attack submarines not only fired TLAMs, but
provided an array of multimission capabilities to battle group commanders. Prior
to and during hostilities, eight SSNs were involved in surveillance and
reconnaissance operations. They also provided indications and warning [a form
of intelligence about impending enemy actions] for the battle groups. After
hostilities began, an additional five submarines bolstered Navy forces already on
station.40
1999 Kosovo Conflict (Operation Allied Force). U.S. and allied naval forces
participating in this conflict included six U.S. SSNs, one UK SSN, one Italian non-
nuclear-powered attack submarine (SS), and one Dutch SS. The mission of all these
submarines was described as sea control,41 which means maintaining control of the
sea for one’s own use while preventing enemy forces from using it for their own
purposes. For submarines, this mission typically involves conducting antisubmarine
and anti-surface ship operations.42 A total of 218 Tomahawks were fired in the
conflict by six U.S. surface combatants, three U.S. attack submarines, and one UK
attack submarine.43 The UK submarine fired 21 of the Tomahawks.44
2001-2002 War in Afghanistan (Operation Enduring Freedom). Published
reports indicate that two U.S. attack submarines and at least one UK attack
submarine participated in the war in Afghanistan, that the U.S. submarines launched
about one-third of the 82 Tomahawks fired by U.S. Navy ships, and that the U.S. and
UK submarines together launched 37% of the more than 82 Tomahawks that were
collectively launched by U.S. and UK ships.45 A Navy submarine admiral stated that,
39 Norman Polmar, The Naval Institute Guide to the Ships and Aircraft of the U.S. Fleet,
15th ed. (Annapolis: Naval Institute Press, 1993), p. 63; Norman Polmar, “Going Downtown
the Safe Way,” U.S. Naval Institute Proceedings, Aug. 1992, pp. 105-106.
40 U.S. Department of Defense, Department of the Navy, Office of the Chief of Naval
Operations, “The Untied States Navy in “Desert Shield” [and] “Desert Storm,” May 15,
1991, p. 40. Curiously, Appendix B of the report, which presents a list of ships participating
in Desert Shield/Storm, includes only five submarines rather than 13.
41 Source: Information sheets on Operation Allied Forced provided to CRS by the Joint
Staff, October 19, 1999.
42 The Yugoslav navy at the time had a small number of aging diesel-electric submarines that
might have posed a threat to U.S. and allied surface ships.
43 U.S. Department of Defense, Kosovo/Operation Allied Force After-Action Report, Jan.
31, 2000, p. 92.
44 Slide entitled “Operational Firsts” from a package of briefing slides on the Kosovo
operation entitled “A View from the Top: Admiral James O. Ellis, U.S. Navy, Commander-
in-Chief, U.S. Naval Forces, Europe, Commander, Allied Forces Southern Europe,
Commander, Joint Task Force Noble Anvil during Operation Allied Force.”
45 Bill Gertz and Rowan Scarborough, “Navy Message,” Washington Times, June 14, 2002,
p. 10 [item in the Inside the Ring Column]; Hunter Keeter, “Bowman: Submarine Force
Level Inadequate To Meet Requirement,” Defense Daily, June 13, 2002; Jason Ma,
(continued...)

CRS-26
in addition to firing Tomahawks, the Navy attack submarines during the war in
Afghanistan conducted ISR operations, antisubmarine operations, and anti-surface
ship operations, such as maritime intercept operations.46 Since Afghanistan is a
landlocked country with no navy, the anti-submarine operations were presumably
tracking operations against third-party submarines operating in the region.
2003 Iraq War (Operation Iraqi Freedom). At the height of the buildup for
the Iraq war, a total of 14 attack submarines — 12 U.S. boats and two UK boats —
were in the Iraq theater of operations. Ten U.S. boats were in the Red Sea, while two
U.S. and two UK boats were in the Persian Gulf.47 Twelve of the 14 submarines
launched Tomahawks, accounting for about one-third of the 802 Tomahawks fired
in the Iraq war.48
Potential Demands for Attack Submarines in Future Conflicts.
Although the recent major U.S. military operations discussed above used relatively
small numbers of attack submarines, certain potential future conflicts might feature
a greater maritime component and consequently require a larger number of attack
submarines. Examples of such potential future conflicts include a war on the Korean
Peninsula or a conflict with China.
If China invests significantly in naval modernization for a number of years, it
could eventually field a sizeable and fairly modern fleet.49 Such a fleet would
represent the first significant naval competitor to the U.S. Navy since the dissolution
45 (...continued)
“Grossenbacher: Subs Can Maintain Optempo A ‘Couple More Years,’” Inside the Navy,
Nov. 25, 2002. Of the 82 Tomahawks fired by the Navy in the war, 65 were launched
during the first two days of the conflict. (Greg Seigle, “Experts Fear Shortage Of Missiles
For War In Iraq,” Denver Post, Jan. 5, 2003, p. 1.)
46 “Grossenbacher: Subs Can Maintain Optempo A ‘Couple More Years,’” Inside the Navy,
Nov. 25, 2002. For additional accounts of Navy attack submarine operations in the war in
Afghanistan, mostly in connection with firing Tomahawks, see John E. Mulligan, “Fire!
Submarine Providence Helps Counter The Attacks,” Providence Journal, Sept. 17, 2002;
and Scott Bawden, “Call To Action, A Submarine CO’s Account of the First Hours of the
War on Terror,” Undersea Warfare, Summer 2002, pp. 12-13.
47 David Rush and Mark Savage, “Submarine Warriors Return From Operation Iraqi
Freedom,” Undersea Warfare, Summer 2003, p. 3; “Remarks by CDR Michael Jabaley,
Commanding Officer, USS Louisville (SSN 724) to the Naval Submarine League
Symposium,” June 11, 2003. The Submarine Review, July 2003, p. 66.
48 Statement of Honorable Gordon R. England, Secretary of the Navy, in U.S. Congress,
House Armed Services Committee, Feb. 12, 2004, p. 3; and David Rush and Mark Savage,
“Submarine Warriors Return From Operation Iraqi Freedom,” Undersea Warfare, Summer
2003, p. 3; Robert A. Hamilton, “USS Pittsburgh Pave The Way For Submarines To Fire
On Iraq,” New London (CT) Day, Sept. 21, 2003; Hunter Keeter, “Bowman: Undersea
Communications Top Priority For Sub Force Transformation,” Defense Daily, June 12,
2003.
49 For a recent discussion of China’s naval modernization effort, see Edward Cody, “With
Taiwan In Mind, China Focuses Military Expansion On Navy,” Washington Post, Mar. 20,
2004.

CRS-27
of the Soviet Union in 1991 and the subsequent collapse of the large and capable
Soviet fleet. Estimates of when China might possess a large and capable fleet, should
it choose to build one, vary from as early as several years from now to as late as
roughly 2030.50
As mentioned in the background section, the 1999 JCS study on requirements
for attack submarines concluded that a force of 55 SSNs in 2015 and 62 in 2025
“would be sufficient to meet the modeled war fighting requirements.” One
suggestion of this conclusion is that a force of less than 55 boats might not be
sufficient to meet the modeled warfighting requirements. If so, this conclusion
contrasts with the reported conclusion of the internal Navy study that a force of as
few as 37 submarines would be sufficient to meet warfighting requirements.
Questions for Congress. Potential questions for Congress regarding recent
and potential future wartime demands for attack submarines include the following:
! In light of the number of attack submarines that have been used in
recent major U.S. military operations, and the number that might be
used in future major U.S. military operations, how many submarines
might be needed for “swiftly defeating attacks against U.S. allies and
friends in any two theaters of operation in overlapping timeframes,”
and for “decisively defeating an adversary in one of the two theaters
in which U.S. forces are conducting major combat operations by
imposing America’s will and removing any future theat it could
pose,” as called for in current U.S. military strategy?51
! How many additional attack submarines would the Navy need to
have, in addition to those engaged in warfighting operations, for
performing other critical operations around the world during time of
war, and to account for submarines that would be unavailable for
deployed operations at any given time due to maintenance or training
requirements? When these additional submarines are added in, is
the resulting total number of submarines closer to 55, the number in
the 1999 JCS study, or to as few as 37, the number reported to be in
the more recent internal Navy study? What factors may have
changed since 1999 that might now permit warfighting requirements
to be met by a force of as few as 37 submarines rather than 55?
Submarine-Launched Unmanned Vehicles (UVs). Submarine-launched
UVs promise to”extend their eyes and ears” of submarines and give them the ability
to perform multiple missions at the same time. Submarine-launched UVs could lead
to arguments in favor of having either larger or smaller numbers of attack
50 For a discussion of China’s military modernization efforts, including its naval programs,
see U.S. Department of Defense, Annual Report on the Military Power of the People’s
Republic of China
, July 28, 2003.
51 For an outline of current U.S. military strategy, including the two key goals quoted here,
see U.S. Department of Defense, Quadrennial Defense Review Report, Sept. 30, 2001 pp.
17-21.

CRS-28
submarines. On the one hand, UVs, by increasing the capabilities of attack
submarines, could make attack submarines more cost effective as platforms, which
could argue in favor of having more of them in the fleet. On the other hand, UVs,
by increasing the capabilities of attack submarines (and SSGNs), could permit a
smaller number of attack submarines (in conjunction with SSGNs) to perform a given
set of submarine missions, which could argue in favor of having fewer attack
submarines in the fleet.
Unmanned Underwater Vehicles (UUVs). As mentioned earlier (see
Background section), the internal Navy study that reportedly recommends reducing
the attack submarine force-level goal to as few as 37 boats reportedly recommends
using unmanned underwater vehicles (UUVs) to perform ISR missions now done by
attack submarines.
Public comments from Navy officials similarly suggest that the Navy may be
focusing on the potential for submarine-launched UUVs to permit a reduction in the
number of attack submarines needed to perform a given set of underwater submarine
missions. For example, at a hearing before the Projection Forces subcommittee of
the House Armed Services Committee on March 30, 2004, Vice Admiral John
Nathman, Deputy Chief of Naval Operations for Warfare Requirements and
Programs — that is, the Navy’s chief officer for determining Navy requirements —
stated the following in answer to a question from Representative Langevin about
submarine procurement and the future size of the attack submarine fleet:
I think everyone should appreciate — and I come back to what the chairman has
asked before about unmanned, underwater vehicles. But there are a lot of
dynamics in how you build force structure requirements for the submarine force.
Right now currently it is built on war-fighting and this compelling need by
the intelligence community for a distributed ISR surveillance capability that our
submarines bring because of their ability to get into those access areas.
The other debates that I see inside of this is there is a tremendous
requirement for intelligence preparation of the battlespace, again because of the
submarine’s covertness to get into those parts of the battlespace, as they build
that battlespace preparation before a conflict. And at the same time, there is this
dynamic of adding SSGNs to our budget over the last several years, buying four
of those. And then how do you leverage the [payload] volume of SSGN and
trying to understand what your total submarine force structure ought to be?
And I will make this point about ISR right now. Submarines do that very
well. And they do it for national needs primarily.
But it seems to make sense to me that if you are going to be asked to take
a very high value, very expensive, very complex device and — like a submarine
— and keep it in a constrained battlespace so that it can detect certain
communications and signals intelligence in a very confined area, that we might
be better off in the near term looking at investments in leveraging the volume of
SSGN to putting unmanned, underwater vehicles in those very same places.
A submarine would probably be the delivery vehicle. But it could be an
SSGN or it could be an SSBN.

CRS-29
So why couldn’t you leverage the force structure that you need by taking
more of this requirement and going offboard into unmanned, underwater vehicles
and that potentially leveraging the investment in SSGNs the same way.
So this is part of the debate we are having. We are having that debate now
in an underwater sea superiority study with the joint staff and our own significant
study, as you would expect, another study that says let’s look at our total force
structure requirements around the capabilities that we will need in these very
specific fights that we have been looking at, that we see in the future.
So this is the kind of rigor that we are trying to get to, sir, to understand
what that force structure requirement should be so we don’t under- or overinvest
in the total size of our submarine force.52
Unmanned Air Vehicles (UAVs). Equipping attack submarines with
unmanned air vehicles (UAVs) would give attack submarines an ability to conduct
deep-inland and overhead observations, potentially permitting attack submarines to
perform ISR missions now performed by satellites or by aircraft.
Compared to the option of performing these missions with satellites, the option
of performing them with submarine-launched UAVs offers potential advantages in
terms of greater persistence over the ISR target (hours for the UAV vs. perhaps
minutes for the satellite) and less predictability about when the observations are
made.
Compared to the option of performing these missions with manned aircraft or
UAVs launched from land bases or surface ships, the option of performing them with
submarine-launched UAVs offers three potential advantages:
! In-theater land bases. In-theater land bases for U.S. manned
aircraft or UAVs may not always be available. When such bases are
available, host nations might place restrictions on how U.S. manned
aircraft or UAVs launched from the bases could be used. And the
launch of manned aircraft or UAVs from such bases might be
observable to agents working on behalf of the intended ISR target.
Personnel at the ISR target, warned by the agent of the approaching
aircraft, could conceal objects, alter their behavior, or make
preparations for attempting to shoot the aircraft down. In contrast,
submarines could launch UAVs without need for host-nation base
access, with no host-nation limits on use, and from locations at sea
where there may be less risk of enemy agents observing the launch,
particularly if the submarine was not known by others to be in the
area.
52 Source: Transcript of hearing as provided by Federal Document Clearing House, Inc. See
also Jason Ma, “Navy Mulls UUVs Taking Over Attack Subs’ Suveillance Missions,”
Inside the Navy, Apr. 5, 2004. For more on Navy UV programs, see CRS Report RS21294,
Unmanned Vehicles for U.S. Naval Forces: Background and Issues for Congress, by Ronald
O’Rourke.

CRS-30
! Land bases in the United States. Manned aircraft or UAVs
launched from bases in the United States would likely require many
hours to reach the ISR target area, making them potentially
unsuitable for transitory ISR targets that could disappear during the
aircraft’s flight from the U.S. base. UAVs launched from land bases
in the Untied States would need to be large enough to fly long
distances to the ISR target area, making them potentially more
expensive and easier to detect and shoot down. In contrast,
submarines could launch UAVs from in-theater locations, permitting
relatively short flight times to the ISR target area and the use of
smaller UAVs that might be more difficult to detect and shoot down.
! Surface ships. The offshore presence of a surface ship equipped
with manned aircraft or UAVs could become known to personnel at
the ISR target area, which could prompt them to conceal objects,
alter their behavior, or make preparations for attempting to shoot the
aircraft down. The offshore presence of an attack submarine,
however, is less likely to become known to personnel at the ISR
target area, making them less likely to take such actions.
The Navy expressed interest in operating UAVs from attack submarines as early
as 1995.53 It conducted its first such experiment in 1996, in which the submarine
assumed control of a Predator UAV that had been launched from a land base.54 The
Navy publicly expressed further interest in the submarine-UAV concept in 2001.55
Directing a UAV from a submarine could require the submarine to remain close
to the surface, so as to keep an antenna exposed to the air, potentially compromising
the submarine’s stealth. Launching and recovering a UAV from a submarine,
moreover, is technically much more complex than doing so from land bases of
surface ships, particularly when the submarine is submerged, which may be critical
to maintaining the submarine’s stealth.
Launching a UAV from a submerged submarine would require a UAV that
could rise up through the water after leaving the submarine and then launch itself
from the surface. The Navy in the past has accomplished something similar with the
submarine-launched versions of the Tomahawk and Harpoon cruise missiles, and
with an older weapon, no longer in service, called the Submarine Rocket (SUBROC).
53 John Robinson, “Submarine To Test Linkup With Predator UAV Later This Year,”
Defense Daily, June 7, 1995, p. 345; Robert Holzer, “U.S. Subs Gear for Broader
Mission,”Defense News, June 12-18, 1995, p.3.
54 Bryan Bender, “Submarine Takes Control Of UAV In Demonstration,” Defense Daily,
June 13, 1996, pp. 434-435; Roman Schweizer, “Submarine Force Looks To UAVs,
NTACMS To Bolster Littoral Capabilities,” Inside the Navy, Nov. 11, 1996, pp. 1, 10;
Vincent Vigliotti, “Demonstration of Submarine Control of an Unmanned Aerial Vehicle,”
Johns Hopkins APL Technical Digest, vol. 19, no. 4, 1998, pp. 501-512.
55 Christian Bohmfalk, “Navy Exploring Large And Small UAVs, Better Comm. Relays For
Subs, “Inside the Navy, Apr. 9, 2001; Robert Wall, “Navy Investigates UAV-Sub Teaming,”
Aviation Week & Space Technology, July 9, 2001.

CRS-31
Bringing a UAV back aboard a submerged submarine would require a UAV that
could land safety on water and then perhaps be recovered by a grappling mechanism
of some kind from the submarine. The technical challenges of recovering the UAV,
and the cost of a grappling system, could be avoided by designing the UAVs as
expendable assets to be used on one-way missions. This strategy, however, could
substantially increase costs for procuring UAVs (due to the need to buy replacement
UAVs) and limit the number of UAV ISR missions that a submarine could perform
while operating on its own.
Another option would be to launch the UAV from the submarine but land it at
a land base or on a surface ship. This would permit the UAV to be reused and avoid
the cost of a grappling system, but still limit the number of UAV ISR missions a
submarine could perform while operating on its own. In addition, if personnel at the
ISR target learn that a UAV has landed at a land base or on a surface ship, it would
alert them to the possibility that their activities had recently been observed, and
possibly encourage them to take steps to reduce the effectiveness of any follow-on
UAV ISR operations against that site that U.S. commanders might want to conduct.
Questions for Congress.56 Potential questions for Congress regarding
submarine-launched UVs include the following:
! What are the Navy’s current plans for equipping attack submarines
and SSGNs with UUVs? At what point will submarine-launched
UUVs be sufficiently numerous to potentially permit a smaller
number of submarines to perform a given set of underwater
submarine missions?
! What are the Navy’s plans for developing UAVs that can be
launched from, directed from, and recovered aboard attack
submarines? In light of the potential operational advantages of
operating UAVs from attack submarines, are these plans adequate?
! What might be the net impact of submarine-launched UUVs and
submarine-launched UAVs on required numbers of attack
submarines?
Submarine Homeporting and Crewing Arrangements.
Guam Homeporting. The Navy in early 2004 completed an initiative
announced in 2001 to transfer three Pacific Fleet attack submarines to the U.S. island
territory of Guam in the Western Pacific.57 Guam is thousands of miles closer to
potential attack submarine operating areas in the Western Pacific and Indian Ocean
56 For more on Navy programs for Uvs, including UUVs and UAVs, see CRS Report
RS21294, Unmanned Vehicles for U.S. Naval Forces: Background and Issues for Congress,
by Ronald O’Rourke.
57 The first attack submarine to be homeported at Guam arrived in 2002, the second in 2003,
and the third in early 2004. See, for example, Doug Huddy “USS Houston To Make Guam
Its Homeport In 2004,” Pacific Stars and Stripes, Mar. 17, 2003.

CRS-32
than are the Navy’s other Pacific Fleet attack submarine home ports at Pearl Harbor
and San Diego. In addition, attack submarines homeported in Guam use a different
operating cycle than attack submarines homeported at Pearl Harbor or San Diego.
As a result of both these factors, Guam-homeported attack submarines can
generate significantly more days on station in Pacific Fleet attack submarine
operating areas than can attack submarines homeported in the other two locations.
Navy officials have stated that in terms of operating days, a Guam-homeported attack
submarine is the equivalent of an average of about 2.3 attack submarines homeported
in the Third Fleet (i.e., in San Diego or Pearl Harbor).58 CBO, in a March 2002
report on the attack submarine force, stated that the ratio might be higher, with a
Guam-homeported attack submarine equivalent in operating days to about three
attack submarines homeported elsewhere.59
In general, homeporting additional attack submarines at Guam could reduce the
total number of attack submarines needed to fulfill day-to-day Pacific Fleet attack
submarine missions. In its March 2002 report, CBO presented an option for
homeporting up to eight additional attack submarines at Guam, for a total of 11.60
CBO estimated the construction cost of the additional facilities needed to implement
this option at about $200 million, which is less than 10% of the procurement cost of
a Virginia-class submarine. CBO noted that homeporting additional attack
submarines posed some potential disadvantages, including reduced opportunities for
training with Navy ships based in Hawaii or on the U.S. West Coast. Even so, CBO
concluded that homeporting additional attack submarines at Guam was the most cost
effective of the various options it explored for increasing the mission capabilities of
the attack submarine fleet.61 As mentioned earlier (see Background section), the
internal Navy study that reportedly recommends reducing the attack submarine force-
level goal to as few as 37 boats reportedly recommends homeporting a total of 9
attack submarines at Guam.
Crewing Arrangements. The March 2002 CBO report also presented an
option for increasing submarine operating days through the use of dual crewing (two
crews for each submarine) or multiple crewing (three crews for two submarines).
The Navy has long used dual crewing for its SSBNs and plans to do so with its
58 In a “memorandum for interested members of Congress” on the homeporting of attack
submarines in Guam dated January 22, 2001, the Navy stated: “Three attack submarines
homeported in Guam will provide a total of 300 days (on average) of operations and
engagement per year. Those submarines would provide 130 days of operations and
engagement per year if they were homeported in [the] Third Fleet [i.e., Eastern Atlantic] and
deployed to [the] Seventh Fleet [i.e., Western Pacific] in accordance with current
guidelines.” 300 divided by 130 is about 2.3. The text of the memo was reprinted in the
February 12, 2001 issue of Inside the Navy under the headline, “Text: Navy Memo on Subs
in Guam.” For the accompanying news story, see Christian Bohmfalk, “Basing Attack Subs
On Guam Expected To Increase Fleet’s Presence,” Inside the Navy, Feb. 12, 2001.
59 U.S. Congressional Budget Office, Increasing the Mission Capability of the Attack
Submarine Force
, March 2002, p. 11.
60 Increasing the Mission Capability of the Attack Submarine Force, op cit, p. xvii, 30-32.
61 Increasing the Mission Capability of the Attack Submarine Force, op cit, p. ix, 32.

CRS-33
SSGNs. CBO estimated that dual-crewing could produce an 80% increase in an
attack submarine’s operating days, while multiple crewing could result in a 100%
increase.
CBO noted in its report that implementing this option would require additional
spending to support the additional crews, and that the Navy raised several concerns
about the option, including the time needed to recruit and train the additional crews,
the challenge of keeping the crews trained between deployments without access to
their boats, and increased wear and tear on attack submarines (which, unlike SSBNs,
are not engineered to be used intensively at sea by more than one crew).62 On at least
two occasions in 2000, however, Navy officials expressed some interest in the idea.63
Questions for Congress. Potential questions for Congress regarding
submarine homeporting and crewing arrangements include the following:
! What does the experience to date with the homeporting of three
attack submarines at Guam suggest about the potential for
homeporting additional attack submarines there? What is the
maximum number of additional attack submarines that could be
homeported at Guam? What would be the potential construction
cost for new facilities needed to homeport additional attack
submarines at Guam? How long would it take to build those
facilities and otherwise implement a decision to homeport additional
attack submarines at Guam?
! In light of recent Navy experiments with new approaches for
crewing and deploying surface ships, including the Sea Swap
62 Increasing the Mission Capability of the Attack Submarine Force, op cit, p. xv-xvi, 20-30.
For articles expressing Navy concerns with dual- or multiple crewing of attack submarines,
see Paul F. Sullivan, “Letter to the Editor,” U.S. Naval Institute Proceedings, Dec. 2002, pp.
14, 16; and Christian Bohmfalk, “Fages Says Navy Wary Of Double-Crewing Subs To
Increase Presence,” Inside the Navy, May 8, 2000. Sullivan’s letter to the editor was in
response to an article in the magazine based on the March 2002 CBO report. (See Eric J.
Labs, “Countering Attack Sub Shortfalls,” U.S. Naval Institute Proceedings, Sept. 2002, pp.
46-48, 50.)
63 See Christian Bohmfalk, “Submarine Chiefs Willing To Explore Double Crewing For
SSNs,” Inside the Navy, July 3, 2000; and P. J. Skibitski, “Pacific Submariners Consider
Basing Nuclear Attack Boats In Guam,” Inside the Pentagon, July 13, 2000, p. 1. The
second article about a Pacific Fleet study on forward-homeporting submarines at Guam
stated:
If one sub were based [in Guam], the service could “dual-crew” the boat by
shuttling sailors from Hawaii, [Rear Admiral Albert] Konetzni said. One crew
could take a sub on a deployment, and when it got back, another crew could take
the boat out....
If two or three of the early [Los Angeles-class submarines] were
homeported in Guam, sailors and their families could live there and only single-
crewing would be necessary. Numerous other arrangements, such as three crews
for two ships, are also being looked at in the study, Konetzni said.”

CRS-34
concept for sending ships on long (e.g., 18- or 24-month)
deployments and rotating multiple crews out to the ships,64 should
the Navy reexamine options for crewing and deploying attack
submarines?
SSGN Conversion Program. SSGNs can perform some missions that might
otherwise be performed by attack submarines, particularly Tomahawk strike, support
of special operations forces, and, in the future, missions enabled by UVs. Compared
to an attack submarine, an SSGN can carry much larger numbers of Tomahawks,
SOF personnel, and UVs. SSGNs can also deploy larger-sized UVs than can be
deployed by today’s attack submarines. The cost-effectiveness of the SSGNs in
performing these missions is increased by the Navy’s plan to operate these boats with
dual crews so as to increase the percentage of time that each SSGN is at sea in an
operating area.
In light of the SSGNs’ capabilities, the Navy’s planned force of four SSGNs
may reduce the number of attack submarines needed to perform submarine missions.
By the same token, increasing the number of SSGNs in the fleet beyond the four now
planned could, other things held equal, further reduce the number of attack
submarines needed to perform a given set of submarine missions.
The Navy procured a total of 18 SSBNs between FY1974 and FY1991. The
ships entered service between 1981 and 1997. The Clinton Administration’s 1994
Nuclear Posture Review (NPR) recommended a strategic nuclear force for the
START II strategic nuclear arms reduction treaty that included 14 Tridents rather
than 18. The Bush Administration’s 2002 NPR retained the idea of reducing the
Trident SSBN force to 14 boats. The reduction in the planned Trident SSBN force
from 18 boats to 14 made the first four Tridents available for conversion into SSGNs.
Any future decision to reduce the SSBN force further — to 12 or 10 boats, for
example — could make two or four additional Tridents available for conversion to
SSGNs.
Allied and Friendly Attack Submarines. As mentioned earlier in the
section reviewing recent wartime demands for attack submarines, allied submarines
on occasion have participated in U.S.-led military operations. In theory, allied
submarines might also be able to perform day-to-day missions that might otherwise
be performed by U.S. attack submarines. In light of the close security relationship
that the United States maintains with the UK,65 and the apparent growing security
64 For more on Sea Swap, see CRS Report RS21338, Navy Ship Deployments: New
Approaches — Background and Issues for Congress
, by Ronald O’Rourke.
65 The United States and the UK have a history of close cooperation on sensitive security
issues that dates back to World War II and the wartime effort to develop a nuclear weapon.
Following the war, the United States assisted the UK’s effort to develop nuclear-powered
submarines, which was experiencing technical difficulties, by providing the UK with a
complete U.S. submarine reactor plant for installation in the UK’s first SSN. The United
States closely guards its submarine and naval nuclear propulsion technology and has shared
the latter only with the UK. The United States has sold the UK Tomahawk cruise missiles
(continued...)

CRS-35
relationship that the United States is developing with Australia,66 submarines from
these two countries might be of particular interest as candidates for performing
missions that might otherwise be performed by U.S. attack submarines.
The UK operates a force of 12 SSNs, while Australia operates a force of six
large diesel-electric submarines. UK submarines might be able to assist the United
States in performing attack submarine missions in locations such as the Barents Sea,
the Norwegian Sea, the Mediterranean, the Red Sea, and the Indian Ocean/Persian
Gulf region. Australian submarines might be able to assist the United States in
performing attack submarine missions in locations such as parts of the Indian Ocean
and the waters around the Indonesian archipelago.
65 (...continued)
and Trident SLBMs for use on UK SSNs and SSBNs, respectively. U.S. facilities are used
to provide life-cycle maintenance support for the UK SLBMs.
66 In 1998-2000, it was reported that Australia’s new submarines, which were designed in
Sweden and built in Australia by the Australian Submarine Corporation (ASC), were
experiencing acoustic problems (i.e., excessive noise), problems with their combat systems,
and other difficulties, and that the U.S. Navy was helping to fix the acoustic and combat-
system problems. (Australia Say Serious Problems With New Submarines. Reuters wire
service, October 10, 1998; Antony Preston, “’Serious Problems’ Reported With New
Australian SSKs,” Sea Power, Dec. 1998, pp. 31-32; Gregor Ferguson, “Report Slams
Australia’s Project Management,” Defense News, July 19, 1999; Norman Friedman, “Sub
Problems Down Under Continue,” U.S. Naval Institute Proceedings, Sept. 1999, pp. 121-
123; “Report Targets Collins Class,” Jane’s Navy International, Sept. 1999, p. 4; David
Lague, “U.S. Experts In Salvage Efforts For Stricken Subs,” Sydney Morning Herald, Mar.
20, 2000; Norman Friedman, “Fixing the Collins Class,” U.S. Naval Institute Proceedings,
May 2000, pp. 98-100, 102; David Lague, “Sweden Goes To War: Australia Blasted Over
Submarine Secrets,” Sydney Morning Herald, Dec. 29, 2000, p. 1.
In 2000, it was reported that the U.S. Navy granted GD/EB permission to explore how it
might help Australia fix problems with its submarines, and that GD/EB sent a team of
experts to Australia. (Gregor Ferguson and Robert Holzer, “U.S. Releases Sub Info To
Australian Navy,” Defense News, Mar. 6, 2000, pp. 1, 26; Robert A. Hamilton, “EB Looking
For Business Down Under,” New London (CT) Day, Mar. 1, 2000.)
In 2001, it was reported that the U.S. Navy and the Australian Navy signed a statement of
principles for sharing classified technology and otherwise promoting interoperability
between the U.S. and Australian submarine fleets. (Robert Garran, “US Threat To Sink
Strategic Alliance,” The Australian, Dec. 23, 2000; Craig Skehan, “Huge Payout After US
Applies Pressure Over Defence Tenders,” Sydney Morning Herald, July 10, 2001; Robert
Garran, “Navy Ties Up To Uncle Sam,” The Australian, July 11, 2001; Jason Sherman,
Australian, “U.S. Navies To Share Classified Work,” Defense News, Aug. 27-Sept. 2, 2001,
p. 6; Ian Bostock, “About Face On RAN’s Collins Combat System,” Jane’s Navy
International
, Sept. 2001, p. 6; Gregor Ferguson, “Australian, U.S. Navies To Sign
Agreement Sept. 10,” Defense News, Sept. 10-16, 2001; Ian Bostock, “ RAN-USN Pact On
Submarine Strategy,” Jane’s Defence Weekly, Oct. 10, 2001, p. 29.)
In 2002-2003, it was reported that GD/EB had become a “capability partner” to ASC and
would provide technical support for Australia’s submarines. (Australia To Buy Raytheon
Submarine Combat System. Defense Daily, September 16, 2002; Australia Commissions
Final Collins-Class Submarine. Defense Daily, April 1, 2003.)

CRS-36
Given the relatively small sizes of the UK and Australian submarine forces, each
country might have only one or two submarines in deployed status at any given time.
Deployed UK and Australian submarines, moreover, might spend much of their
deployed time performing missions of specific interest to their own governments,
rather than missions that may also be of interest to the United States. And Australia’s
diesel-electric submarines may not be well suited for performing certain missions of
interest to the United States, particularly day-to-day ISR missions that might require
long, stealthy transits to the operating area, extended periods of submerged
operations in the operating area, and long, stealthy transits back to home port. Non-
nuclear-powered submarines are less well suited than SSNs for performing such
missions. As a result, the number of occasions when UK or Australian submarines
might be able to perform missions of interest to the United States might be fairly
small.
The submarine forces of U.S. allies and friendly countries other than the UK and
Australia are also rather small. In addition, with the exception of France, some of
whose attack submarines are nuclear-powered, the submarine forces of these other
countries consist entirely of non-nuclear-powered boats, which may limit their ability
to perform certain missions of interest to the United States. The reduction in
requirements for U.S. attack submarines that might be possible through use of
submarines from U.S. allies and friendly countries other than the UK and Australia
consequently would also likely be limited.
On the other hand, as suggested by the earlier discussion of the stationkeeping
multiplier for U.S. Navy attack submarines, even the occasional performance of a
submarine mission of interest to the United States by a submarine from the UK,
Australia, or another allied country could have a somewhat leveraged effect in
relieving strain on the U.S. attack submarine force, particularly for performing short-
duration missions that are relatively close to the allied country in question but far
from the home ports of U.S. attack submarines.
It can also be noted, however, that as a general matter, planning U.S. military
forces on the assumption that forces from other countries, even close allies, will be
available to perform certain missions of interest to the United States entails some
risk, given inherent uncertainty over the future policies of foreign governments. The
UK or Australia, for example, might decide at some point to reduce the size of its
submarine force for affordability reasons, reducing the contribution that the force
could make to performing missions of interest to the United States.67
67 In May 2004, for example, it was reported that UK government was considering reducing
the size of its navy, including its submarine force. (MichaelEvans, “Admiral Expects
Ruthless Cuts In Navy Strength,” London Times, May 12, 2004.)

CRS-37
Future Virginia-Class Procurement Rate
At what rate should Virginia-class submarines be procured in coming years?
Key Factors to Consider. In considering the rate at which Virginia-class
submarines should be procured in coming years, key factors to consider include the
following:
! the attack submarine force-level goal;
! attack submarine service lives;
! the effect of annual procurement rates on unit procurement costs;
! industrial-base considerations; and
! funding requirements for other defense-spending priorities.
Attack Submarine Force-Level Goal. The attack submarine force-level
goal, once determined, is a primary factor to consider in assessing at what rate
Virginia-class boats should be procured in coming years.
Long-Term Steady-State Replacement Rate. One potential starting point
in relating a force-level goal to required procurement rates is to calculate the steady-
state replacement rate, which is the average procurement rate that would be needed
over the long run to maintain a force of a given size over the long run.68 The table
below shows steady-state replacement rates for submarine forces varying in size from
30 to 80 (i.e., a range that varies 25 boats downward and upward from the current
force-level goal of 55 boats). The table assumes a 33-year service life for attack
submarines.
Table 4. Steady-State Replacement Rates
(assuming 33-year life for attack submarines)
Planned force
Steady-state replacement
size
rate (ships per year)
30
0.9
40
1.2
50
1.5
55
1.7
60
1.8
70
2.1
80
2.4
68 As mentioned in the background section, the steady-state replacement rate equals the
desired force level divided by the expected service life of the platforms in question.

CRS-38
Steady-state replacement rates are averages that must me met over the long term
(in this case, over a 33-year period). Over shorter periods, the actual procurement
rate can be either above or below the steady-state rate, depending on factors such as
the age distribution of the existing force, available funding, and industrial-base
considerations. If the actual procurement rate is below the steady-state rate for some
number of years, though, it must eventually be elevated above the steady-state rate,
so that the average rate, calculated over the entire period in question, comes back to
the steady-state rate.
Notional Procurement Profiles For Forces Of 30 To 80 Boats. The
table on the next page presents notional attack submarine procurement profiles for
the 25-year period FY2005-FY202929 for supporting attack submarine forces of 30,
40, 50, 55, 60, 70, and 80 boats (excluding any SSGNs), reflecting the age
distribution of the existing attack submarine force. The existing attack submarine
force is not evenly distributed in age because it includes a large number of SSNs
procured in the 1980s and a small number procured in the 1990s.
For each of the seven force sizes considered, two notional procurement profiles
(A and B) are presented. Profile A in each instance minimizes the procurement rate
during the FYDP, while profile B uses higher rates of procurement during the FYDP.
The profiles employ generally stable rates of procurement, if possible, between about
FY2010 and FY2023.
All 14 notional profiles procure at least one boat per year during the period
FY2004-FY2008, as called for in the FY2004-FY2008 MYP arrangement approved
for the Virginia-class program. For forces of 55 or more boats, profile B procures
two boats per year in FY2007-FY2008. None of the 14 notional profiles employ a
maximum procurement rate of more than four boats per year — the maximum annual
rate that was achieved for attack submarines during the Cold War years of the 1980s,
when the Navy was working toward achieving and maintaining a force of 100 SSNs.

CRS-39
Table 5. Notional Procurement Profiles for Various Force Sizes
(shading included for clarity)
FY
Size of force supported (two options — A and B — for each force size)
30
40
50
55
60
70
80
A
B
A
B
A
B
A
B
A
B
A
B
A
B
2005
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2006
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2007
1
1
1
1
1
1
1
2
1
2
1
2
1
2
2008
1
1
1
1
1
1
1
2
1
2
1
2
1
2
2009
0
1
0
1
1
2
2
2
2
3
2
3
2
3
2010
0
1
1
1
2
2
3
2
3
4
3
4
3
4
2011
1
1
1
1
2
2
3
3
4
4
4
4
4
4
2012
1
1
2
1
3
2
4
3
4
4
4
4
4
4
2013
1
1
2
2
2
2
3
3
4
3
4
4
4
4
2014
1
1
2
2
2
2
3
3
4
3
4
4
4
4
2015
1
1
2
2
2
2
2
2
3
2
4
4
4
4
2016
1
1
2
2
3
3
2
2
3
2
4
4
4
4
2017
1
1
2
2
3
3
3
3
2
2
4
4
4
4
2018
1
1
2
2
3
3
3
3
3
3
4
4
4
4
2019
1
1
2
2
3
3
3
3
3
3
4
4
4
4
2020
2
1
2
2
3
3
3
3
3
3
4
4
4
4
2021
2
1
2
2
3
3
3
3
3
3
4
3
4
4
2022
2
2
2
2
3
3
3
3
3
3
4
3
4
4
2023
2
2
2
2
2
2
3
3
3
3
4
2
4
4
2024
1
1
2
2
1
1
1
1
2
2
1
1
4
4
2025
1
1
1
1
1
1
0
0
0
0
1
1
4
4
2026
0
0
0
0
0
0
0
0
0
0
0
0
4
0
2027
0
0
0
0
0
0
0
0
0
0
0
0
0
0
2028
0
0
0
0
0
0
0
0
0
0
0
0
0
0
2029
0
0
0
0
0
0
0
0
0
0
0
0
0
0
The following points arise from the figures in the table and the data underlying the
figures:
! For a 30-boat force. Supporting a force of about 30 boats could
involve maintaining an average procurement rate of about one boat
per year into the 2020s. If industrial-base considerations do not
preclude a hiatus in Virginia-class procurement, a force of about 30
boats could be maintained without procuring any Virginia-class
boats in FY2009-FY2010, provided that two boats per year were
procured for a few years following the hiatus (profile 30A). If all
SSNs are operated to the end of their expected 33-year lives, then the
force would decline to 30 boats by about 2028 and remain about

CRS-40
there after that. The force could be reduced to 30 boats much sooner
by accelerating the retirement of older SSNs.
! For a 40-boat force. Supporting a force of about 40 boats could
involve maintaining an average procurement rate of about two boats
per year from about FY2011 or FY2012 to about FY2024. If
industrial-base considerations do not preclude a single-year hiatus in
Virginia-class procurement (as shown earlier in Table 1, the
Virginia-class program experienced single-year hiatus in FY2000),
a force of about 40 boats could be maintained without procuring any
Virginia-class boats in FY2009 (profile 40A). If all SSNs are
operated to the end of their expected 33-year lives, then the force
would decline to 40 boats by about 2027 and remain about there
after that. The force could be reduced to 40 boats much sooner by
accelerating the retirement of older SSNs.
! For a 50-boat force. Supporting a force of about 50 boats could
involve maintaining an average procurement rate of about 2.5 boats
per year during the period FY2009-FY2023. If all SSNs are
operated to the end of their expected 33-year lives, then the force
would decline to 50 boats by about 2018 and remain about there
after that. The force could be reduced to 50 boats much sooner by
accelerating the retirement of older SSNs.
! For a 55-boat force. Supporting a force of about 55 boats could
involve maintaining an average procurement rate of about 2.7 to 2.9
boats per year during the period FY2009-FY2023. The force would
grow to 60 or 61 boats by FY2013 before returning to 55 boats by
2016 or 2017. The force could be held to about 55 boats prior to
2016 of 2017 by accelerating the retirement of older SSNs.
! For a 60-boat force. Achieving and maintaining a force of about 60
boats could involve maintaining an average procurement rate of
about 3.0 to 3.1 boats per year during the period FY2009-FY2023.
Within that period, the procurement rate may need to climb to four
boats per year for a few years. The force would reach 60 boats
around 2013. Under profile 60A, the force would reach 60 boats
around 2013, then decline to the mid-50s for a few years and return
to 60 by about 2021. Under profile 60B, the force would reach 60
boats around 2013 and remain there after that.
! For a 70-boat force. Achieving and maintaining a force of about 70
boats could involve maintaining an average procurement rate of
about 3.7 or 3.8 boats per year during the period FY2009-FY2023.
The force would reach 70 boats around 2029 (profile 70A) or 2025
(profile 70B) and remain there after that.
! For an 80-boat force. Achieving and maintaining a force of about
80 boats could involve maintaining an average procurement rate of
about 3.7 or 3.8 boats per year during the period FY2009-FY2026.

CRS-41
The force would reach 80 boats around 2032 (profile 80A) or 2031
(profile 80B) and remain there after that.
Attack Submarine Service Lives. As mentioned earlier, SSNs have expected
service lives of 33 years. The notional procurement profiles outlined above reflect this
figure. As also mentioned earlier, however, the current high operational tempo for the attack
submarine force could reduce the service lives of SSNs to something less than 33 years by
accelerating the rate at which reactor core life is used up. If the service lives of existing
SSNs turn out to be less than 33 years due to either higher-than-planned rates of reactor core
use or general wear and tear on the ships, then the procurement rates needed to maintain
attack submarine forces of various sizes may need to be greater than shown in the notional
profiles outlined above.
Conversely, if the service lives of SSNs can be increased to something greater than 33
years, then procurement rates needed to maintain attack submarine forces of various sizes
could possibly be lower than shown in the notional profiles outlined above. If, for example,
the service lives of Navy SSNs can be extended to 40 years, then an annual procurement rate
of 1 or 1.5 boats per year would, over the long run, be sufficient to maintain a force of 40
to 60 boats, rather than 33 boats.
The feasibility and potential cost of extending the service lives of the Navy’s SSNs is
not clear. The Navy a few years ago increased the expected service lives of its SSBNs
(including the four being converted into SSGNs) from 30 years to 42 years, with the new
42-year life to consist of two 20-year operating periods with a two-year refueling in
between. The typical mission profile of an SSBN, however, may be less stressful on the
boat than is the typical mission profile of an SSN. Compared to SSBN operations, SSN
operations can involve submerging and surfacing more frequently (placing more frequent
cyclic stress on the submarine’s pressure hull) and more frequent high-speed runs (which
can lead to higher rates of wear and tear on propulsion machinery).
Unlike earlier Navy SSNs, which were built with reactor cores intended to last about
15 years, Seawolf- and Virginia-class boats have cores that are intended to last the 33-year
expected life of the ship. Extending the lives of Seawolf- or Virginia-class boats 40 years,
if feasible, would thus involve changing their life-cycle maintenance plans to include a
refueling at about age 33 or earlier.
Annual Procurement Rates And Unit Procurement Costs. A third factor
to consider in determining the rate at which Virginia-class submarines should be procured
in future years is the effect of annual procurement rates on unit procurement costs. Due to
increased spreading of fixed overhead costs at the shipyards and supplier firms, and reduced
loss of learning between ships at the shipyards and possibly also at supplier firms, procuring
attack submarines at higher annual rates can reduce their unit procurement cost by several
percent.69 Cost figures in the FY2004 and FY2005 budget submission, for example, suggest
that increasing the procurement rate from one boat per year to two per year can reduce unit
procurement cost by more than $100 million, and possibly more than $200 million.70
69 For a discussion of improved economies of scale in Navy shipbuilding due to increased
spreading of fixed overhead costs and reduced loss of learning between ships, see CRS
Report 96-785 F, Navy Major Shipbuilding Programs and Shipbuilders: Issues and Options
for Congress
, by Ronald O’Rourke. Washington, 1996. (September 24, 1996) pp. 58-59,
83-122.
70 In the FY2005 budget submission, the two Virginia-class boats programmed for FY2009
(continued...)

CRS-42
Industrial-Base Considerations. A fourth factor to consider in determining the
rate at which Virginia-class submarines should be procured in future years is the submarine
construction industrial base, which currently includes something more than one complete
submarine production line divided between two shipyards (GD/EB and NGNN),71 plus an
array of material and component suppliers, many of which are sole sources. Industrial-base
considerations include the following:
! the minimum annual production rate for maintaining the submarine
construction industrial base;
! the maximum annual production rate that could be achieved by the
submarine construction industrial base; and
! potential inefficiencies resulting from certain kinds of year-to-year
changes in the annual submarine procurement rate.
Minimum production rate. The current one-per-year Virginia-class procurement
rate appears to have been sufficient, in conjunction with other supporting forms of work
70 (...continued)
have an estimated total procurement cost of $4,940.1 million, or an average of $2,470.0
million per boat, while the one Virginia-class boat programmed for FY2008 has an
estimated total procurement cost of $2,593.5 million. The difference in unit procurement
costs between the two years is $123.5 million. The FY2008 boat, moreover, is being
procured under a MYP arrangement that is reducing its cost by roughly $80 million, while
the estimated procurement cost for the two FY2009 boats may not reflect an assumed
follow-on MYP. If so, then increasing the cost of the FY2008 boat to set aside differences
due to use or non-use of MYP, and thereby arrive at a more apples-to-apples comparison,
would increase the cost of that boat (and consequently the difference in unit procurement
costs between that boat and the FY2009 boats) by about $80 million, for a total difference
of more than $200 million. (This figure might be increased by another 2%, reflecting an
average 2% difference in purchasing power between the then-year dollars used to build a
boat procured in FY2008 vs. the then-year dollars used to build boats procured in FY2009.)
The cost difference might then be adjusted downward to reflect the later position on the
production learning curve of the FY2009 boats compared to the FY2008 boat.
In the FY2004 budget submission, on the other hand, the two Virginia-class boats
programmed for FY2007 had an estimated procurement cost of $4,424.0 million, or an
average of $2,212.0 million per boat, while the one Virginia-class boat programmed for
FY2006 had an estimated total procurement cost of $2,220.8 million. In this case, moving
from one boat per year to two boats per year did not appear to produce a significant apparent
reduction in unit procurement cost.
The FY2004 and FY2005 budget submissions can also be compared against one another to
examine differences in estimated unit costs for procuring one boat per year in FY2007 and
FY2008 (as in the FY2005 submission) vs. two boats per year in FY2007 and FY2008 (as
in the FY2004 submissions). This comparison is more difficult to make because the two
submissions appear to reflect different understandings of what Virginia-class boats would
cost to procure at any annual rate (with estimated costs in the FY2005 submission generally
higher). Attempting to adjust for the different understandings, however, suggests that
increasing the procurement rate from one ship per year to two ships per year might reduce
unit procurement cost by more than $100 million, and possibly more than $200 million.
71 Under the current joint-production arrangement for the Virginia class, the two yards each
maintain facilities for building submarine reactor compartments and for carrying out final
assembly and testing of submarines.

CRS-43
(including aircraft carrier procurement and SSGN conversions),72 to maintain the submarine
construction industrial base in recent years. The submarine construction industrial base also
appears to have managed the one-year hiatus in Virginia-class procurement in FY2000,
suggesting the industrial base might be able to manage occasional one-year gaps in the
future. In contrast, the submarine construction industrial base appears to have had greater
difficulty managing the longer gaps in submarine procurement that occurred in the 1990s.
This experience suggests that the minimum annual procurement rate for sustaining the
submarine construction industrial base in its current form might be one boat per year, or
perhaps something a bit less than one per year (as a result of occasional single-year gaps in
procurement), provided that other supporting forms of work, including aircraft carrier
construction, are also funded.
A procurement rate of significantly less than one per year, in contrast, might not be
sufficient to maintain the submarine construction industrial base in its current form. Under
this scenario, critical supplier firms might be at risk of going out of business, and shipyard
workers with skills critical to submarine construction might need to be laid off. Navy and
industry officials have cautioned on many occasions since the 1990s that reconstituting parts
of the submarine construction industrial base following a period of very-low-rate
procurement could require substantial time and cost due to the need to create and certify
replacement supplier firms and hire and train new submarine construction workers.
Maximum annual production rate. In the mid-1990s, GD/EB officials stated that
their shipyard could build a maximum of three attack submarines per year, while officials
at Newport News Shipbuilding (now NGNN) stated that their shipyard could build a
maximum of four attack submarines per year, making for a combined maximum production
capability of seven attack submarines per year.73
In the years since then, the two shipyards have streamlined their operations to bring
them more into alignment with the current one-per-year submarine procurement rate. In
doing so, however, the two yards do not appear to have taken any steps (such as selling
critical parcels of land that would be needed for additional production facilities) that would
72 Procurement of aircraft carriers results in additional nuclear-ship construction work at
NGNN and additional work for nuclear-propulsion component suppliers. The SSGN
conversion program includes manufacturing of components for the SSGN conversions. The
SSGN conversions are being carried out at government-operated naval shipyards at Norfolk,
VA, and Bremerton, WA.
73 Source: CRS Report 96-785 F, Navy Major Shipbuilding Programs and Shipbuilders:
Issues and Options for Congress
, by Ronald O’Rourke. Washington, 1996. (September 24,
1996) pp. 27-28. The figures were based on interviews with officials from the two
shipyards. The figure for GD/EB pertained to its Land Level Construction Facility (LLCF);
additional submarines could be built at GD/EB’s older inclined building ways. The figure
for Newport News Shipbuilding pertained to its Modular Outfitting Facility (MOF);
additional submarines could be built at the yard’s graving docks. As noted in the 1996 CRS
report, achieving and maintaining these maximum rates could require the yards to curtail or
eliminate other forms of work, or result in levels of employment at the yards that could
strain the managerial and supervisory capabilities of the yards. The figures also did not take
into account possible capacity limitations in critical supplier firms that could prevent these
rates from being achieved.

CRS-44
prevent them from returning to higher rates of production. Officials at both yards state that
they could return to a combined rate of four or more submarines per year.74
The supplier base for submarine construction was reduced during the 1990s to bring
it into alignment with the current one-per-year submarine procurement rate. Building the
supplier base back up to support a procurement rate of three or four boats per year is
possible. It would, however, require time and money, particularly for nuclear propulsion
plant component suppliers. Increasing the production capacity of the nuclear component
supplier base to support a procurement rate of three or four submarines per year starting
FY2011 would require roughly $100 million (for a rate of three submarines per year) or
$200 million (for a rate of four submarines per year). This additional funding would be
required over the next several years, with the first increment required in FY2005. If the
procurement rate is increased to three or four per year prior to FY2011 (as it would be under
notional profiles 55A, 60A or B, 70A or B, and 80A or B from table 5), some of the
submarines procured in those years would take a year or more longer to build than usual due
to nuclear component supplier bottlenecks.75
Inefficiencies From Certain Year-To-Year Rate Changes. Moving abruptly
from a lower annual production rate to a higher rate (i.e., moving from one boat in a given
year to three or four boats the following years) can lead to transitional strains at the
shipyards and suppliers as they attempt to increase their production facilities and hire and
train large numbers of new workers. Such strains can lead to production inefficiencies and
higher costs. The notional procurement profiles in Table 5 avoid such abrupt jumps by
increasing the procurement rate from one year to the next by no more than one boat per year.
Procurement profiles that, within a period of a few years, reduce the procurement rate
significantly and then increase it again (even by no more than one boat per year) can lead
to production inefficiencies and higher costs due to the need to either keep skilled workers
on the payroll during the period of decline, or to hire and train new workers during the
subsequent period of increase. Notional examples of such “roller coaster” procurement
profiles might be 2-0-1-2, 3-1-2-3, or 4-2-1-2-3. The notional procurement profiles in Table
5
avoid such profiles, though they all drop to zero boats per year by the late 2020s.
Other Defense Spending Priorities. A fifth factor to consider in determining the
rate at which Virginia-class submarines should be procured in future years is the need for
the Department of the Navy, and DOD generally, to provide funding for various programs
other than submarine procurement within a budget of a certain size. Starting within the
Navy’s shipbuilding budget and moving outward, examples of such defense spending
priorities include, among other things, the following:
! procurement of other kinds of Navy ships, including aircraft carriers,
DD(X) destroyers, CG(X) cruisers, Littoral Combat Ships (LCSs),
amphibious ships, Maritime Prepositioning Force (Future) ships, and
other auxiliary and support ships;
74 Source: CRS telephone conversations with General Dynamics and Northrop Grumman
officials, May 4, 2004.
75 Source: Information provided to CRS by Naval Nuclear Propulsion Office (NAVSEA-
08H), May 5, 2004.

CRS-45
! procurement of Navy and Marine Corps aircraft such as F/A-18E/F
strike fighters, F-35 Joint Strike Fighters (JSFs), V-22 tilt-rotor
aircraft, and helicopters;
! procurement of Navy and Marine Corps unmanned vehicles;
! procurement of Marine Corps ground combat equipment;
! procurement of Navy and Marine Corps missiles and other
munitions;
! Navy and Marine Corps research and development programs;
! Navy and Marine Corps operation and maintenance (O&M) funding;
! pay and benefits for Navy and Marine Corps personnel;
! analogous spending priorities for the Army, the Air Force, and the
Missile Defense Agency;
! national ISR systems; and
! programs, otherwise not included above, that support the war on
terrorism.
In considering these other defense spending priorities, a key question is how the risks
of procuring fewer SSNs than preferred might compare to the risks of providing less funding
than desired for one or more of these other priorities.
Joint-Production Arrangement
Should the current joint-production arrangement for building Virginia-class
submarines be continued or altered?

Potential Production Approaches. Judgments about the potential procurement
rate for Virginia-class submarines in future years could influence views on the approach that
should be used to build them. There are at least six potential approaches for building
Virginia-class submarines:
! the current two-yard, joint-production approach;
! a variant of the current two-yard, joint-production approach under
which certain portions of the process for building each submarine
would be competed between the two yards;
! a two-yard, separate-production strategy under which complete
Virginia-class submarines would be built at both GD/EB and
NGNN, with construction contracts for individual submarines
allocated to the yards either competitively or without the use of
competition;

CRS-46
! a one-yard production strategy under which construction of Virginia-
class submarines would be consolidated at GD/EB;
! a one-yard production strategy, under which construction of
Virginia-class submarines would be consolidated at NGNN; and
! a strategy under which parts for each submarine would be built at
both GD/EB and NGNN, but final assembly and testing of the
submarines would be consolidated at either GD/EB or NGNN.
Navy Statements in 2003 About Potential Alternatives. In March and April
2003, at a time when the Navy was concerned about rising procurement costs for Virginia-
class submarines, the Navy suggested that it was not necessarily permanently committed to
the current joint-production arrangement and was open to considering alternative approaches
that might reduce costs. A March 17, 2003 press report stated:
To control rising costs in the Virginia-class submarine program, the Navy
is negotiating down expensive bids submitted by General Dynamics and
Northrop Grumman for yet-to-be-built subs and might even start competing work
currently shared between the two companies, according to Navy acquisition
executive John Young.
In a March 10 interview with Inside the Navy, Young indicated the Navy
might rethink the current arrangement that divides work between GD’s Electric
Boat in Groton, CT, and Northrop’s Newport News, VA, shipyard. While
negotiations with the companies are proceeding well, Young said he would like
to see industry’s bids for future sub construction decrease even further, below the
program office’s estimate.
“In my mind, everything is on the table,” Young said. “Are there ways to
compete any common work between the yards? Does it make sense at these rates
of production to continue to have both yards doing final assembly? I’ve got to
look at every tool I have. In the end, we may say, we’ve got it right. But we are
going to . . . work very hard at continuing to bring down the costs because we’re
doing that in every program.”76
A follow-on article published March 24, 2003, stated that
a Navy official told [Inside the Navy] it could be challenging to inject such
competition into the program, because it would mean modifying the 1997
teaming arrangement between the Navy and the companies. Modifying the
arrangement is possible, but only with the consent of both companies, said the
official.
Further, if the Navy decided to compete specific, common work in the
program, it could well mean only one company would retain the capability to do
that kind of work once a winner was selected, the official noted.
76 Christopher J. Castelli, “Young Considers Competing Work To Control Rising Sub
Costs,” Inside the Navy, Mar. 17, 2003.

CRS-47
Young is considering numerous possible options, fully aware some challenges could
be involved, the official said.77
At an April 3, 2003 hearing before the Projection Forces subcommittee of the House
Armed Services Committee, Secretary Young was asked by Representative Simmons to
comment on the current two-yard, joint-production arrangement for building Virginia-class
submarines. Young stated in response:
I am not prepared [to say] any teaming agreement is in jeopardy. I mean, in
fact, as you well know, to build a Virginia class [submarine] right now, it is
critical to have both companies providing parts of that submarine.
Having said that, though, as you know also, our initial bids on the next
block of Virginia classes was substantially higher than the resources the Navy
had available at that point in time. I feel it is incumbent on me and my
responsibilities to you and the department to look at every option to build those
submarines and build them in a way that makes it more affordable to the
department.
Hopefully, any of those tools that we might apply to the program can be
executed within the teaming agreement. But I do have, I think, a requirement to
look very hard at trying to get an efficient build process.78
An April 11, 2003 press report stated:
The Navy’s top weapons buyer wants to re-examine the teaming deal
between the nation’s only two submarine builders to see whether there’s a way
to cut costs.
With a contract for a fifth Virginia-class sub still on hold as negotiations
continue on a long-term purchase plan, the Navy is looking for “adjustments” in
the partnership between Northrop Grumman Newport News and General
Dynamics Corp.’s Electric Boat shipyard, which jointly build all attack subs.
“This program has grown 24 percent in cost, and my job is to bring the cost
down,” said John J. Young, the Navy’s assistant secretary for research,
development and acquisition. “If the teaming agreement is an impediment to that,
we ought to at least talk about it.”
Young made clear that the teaming arrangement, begun in 1998, is sure to
continue in some form because it’s no longer practical to consider building all
subs at a single shipyard.
77 Christopher J. Castelli, “Navy Acknowledges Adding Competition To Sub Program May
Be Hard,” Inside the Navy, Mar. 24, 2003.
78 U.S. Congress, House Committee on Armed Services, Hearing on National Defense
Authorization Act for Fiscal Year 2004 — H.R. 1588, and Previously Authorized Programs
.
108th Cong., 1st sess, (Washington: GPO, 2003). (H.A.S.C. No. 108-8, Projection Forces
Subcommittee Hearings on Title I — Procurement, Title II — Research Development, Test
and Evaluation (H.R. 1588), Hearings Held March 27, and April 3, 2003.) p. 121. See also
Nick Jonson, “Navy Is Reviewing Arrangement For Building Virginia-Class Subs,”
Aerospace Daily, Apr. 4, 2003.

CRS-48
Each yard now specializes in building particular parts of subs. Transferring
all that expertise to a single shipyard would be costly, he said.
“Moving total construction to a single yard is not even viable at this point
in the program,” Young said in an interview Thursday.
But in the first sign of discontent with a teaming deal that has largely
escaped criticism, Young said he wanted to know whether different methods of
building the subs would cut costs.
Among the options, he said, is ending the practice of alternating the
assembly of subs between the two yards. Instead, one yard would be responsible
for all assembly work.
“I think there are inefficiencies in the teaming agreement that the
companies are trying to work through,” he said. “Is there a more efficient way?
I’m not prepared to say I have an answer. We’re going to at least have the
discussion.”79
An April 16, 2003 press report stated:
The US Navy’s strategy for building and acquiring Virginia-class
nuclear-powered attack submarines is under review following a 24% cost overrun
on the program, senior navy officials said.
The new strategy is based on lowering costs by trying to obtain a multi-year
procurement contract and possibly reconsidering whether to build the submarines
at a single yard....
In [negotiations with industry aimed at reducing costs], Young has said,
“everything is on the table.” That, [Vice Admiral Philip] Balisle added, “includes
the possibility of competing any common work between the shipyards and doing
final assembly at one rather than both yards.” However, Young later cautioned,
“I’m not prepared to say the teaming agreement is in jeopardy.”80
Officials from General Dynamics and Northrop Grumman, when asked about the
possibility of altering the joint-production approach, stated that the approach was working
well and expressed skepticism about introducing competition into the arrangement.81
1997 Navy Cost Estimate For Some Approaches. In 1997, when the Navy was
seeking congressional approval for the current joint-production arrangement, the Navy
testified that the procurement cost of Virginia-class submarines under this arrangement
would be greater than under a one-yard production approach, but less than under the two-
yard, separate-production approach. Specifically, the Navy testified that the procurement
cost of the fifth boat in the class (the boat used to benchmark the cost of follow-on boats in
the program), in constant FY1995 dollars, would be as follows:
79 David Lerman, “Navy Wants ‘Adjustments’ In Sub Pact,” Newport News Daily Press,
Apr. 11, 2003.
80 Andrew Koch, “Navy Rethinks Virginia Strategy,” Jane’s Defence Weekly, Apr. 16, 2003.
81 Jason Ma, “Industry, Simmons Support Keeping VA Sub Teaming Arrangements,” Inside
the Navy
, Apr. 14, 2003.

CRS-49
! about $1.55 billion under a one-yard production strategy;
! about $1.65 billion, plus or minus $50 million, under a two-yard,
joint-production strategy; and
! about $1.8 billion under a two-yard, separate-production strategy.82
The Navy, in other words, stated in 1997 that, relative to the one-yard approach, the
premium for adopting the joint-production approach would be about $100 million (plus or
minus $50 million) per boat, while the premium for adopting the two-yard, separate-
production approach would be about $250 million per boat. In percentage terms, these
premiums were equivalent to about 6.5% (plus or minus about 3.2 percentage points) and
16%, respectively, in additional procurement costs. When converted into constant FY2005
dollars, these figures become about $114 million (plus or minus $57 million) and $284
million, respectively.
Compared to the one-yard approach, the estimated premium for the joint-production
approach was due to costs for maintaining more than one complete submarine production
line between the two yards (i.e., some overlapping capabilities in the areas of reactor
compartment construction and final assembly and testing), reduced rates of learning at each
yard for building the reactor compartments and performing final assembly and testing of
each boat, costs of transporting submarine sections and personnel back and forth between
the two yards, and costs for the Navy of supervising submarine construction at two yards.
The estimated premium for the two-yard, separate-production approach was due to costs for
maintaining a complete submarine production line at each yard, reduced rates of learning
at each yard for the entire process of building the submarines, and costs for the Navy of
supervising submarine construction at two yards.
Estimate For One-Yard Strategy. It was not clear whether the Navy’s 1997
estimated cost for a one-yard strategy was based on the one yard being GD/EB or NGNN.
The Navy’s originally intended production strategy for the Virginia-class, however, was to
build at least the first two Virginia-class submarines at GD/EB. In light of this earlier
proposed strategy, the Navy’s estimate for a one-yard approach might have been based on
the one yard being GD/EB. As discussed below, however, a one-yard strategy using NGNN
might be less expensive than a one-yard strategy using GD/EB. If so, and if the Navy’s 1997
estimate for a one-yard strategy was based on the one yard being GD/EB, then an alternate
estimate based on the one yard being NGNN might have led, other things held equal, to a
greater difference in estimated costs between the one-yard strategy and the strategies
involving two yards.
Estimate For Two-Yard, Separate-Production Strategy. The Navy in 1997
acknowledged that using competition in the awarding of submarine construction costs could
help constrain costs and thereby possibly reduce the premium for pursuing the two-yard,
separate-production approach. The Navy stated, however, that using competition would not
be feasible in the near term because it would be “many years into the future” before the
attack submarine procurement rate would rise above one per year.83
The Navy in 1996 testified that the minimum procurement rate for maintaining
meaningful competition between the two yards for submarine construction contracts would
82 For a discussion, see CRS Issue Brief IB91098, Navy Attack Submarine Programs: Issues
for Congress
, by Ronald O’Rourke.
83 Ibid.

CRS-50
be 1.5 boats per year. At this rate, the Navy testified, the Navy could hold a competition
every other year by combining two years’ worth of procurement (i.e., three boats), allocating
one boat to each yard, and having the yards compete for the third boat.84 A higher
procurement rate, such as three boats per year, would be needed to support competition on
an annual basis.
At this point, however, even if the submarine procurement rate were increased to 1.5
or more boats per year, it might be difficult to resume the use of competition under a two-
yard, separate-production arrangement in a manner that would be fair to both yards, because
the joint-production arrangement has been in effect since 1997 and the two yards have now
shared many of their submarine production trade secrets with one another.
Real-World Experience Since 1997. Whether the premium for the joint-
production arrangement has turned out to be greater than, less than, or about equal to the
Navy’s 1997 estimate of $114 million (plus or minus $57 million) per boat in FY2005
dollars is unclear, because all Virginia-class boats have been built under the joint-production
arrangement and no real-world data is available on the cost to build Virginia-class boats
under a one-yard arrangement.
Virginia-class boats, however, have turned out to be more expensive to build than
originally estimated. The estimated unit cost of $1.65 billion in constant FY1995 dollars
for the joint-production arrangement is equivalent to about $1.9 billion in FY2005 dollars.
The unit procurement cost of the Virginia-class, however, is now about $2.3 billion in
constant FY2005 dollars, or about 21% greater than the $1.9-billion figure. If the premium
for the joint-production arrangement is proportional to other costs for building the
submarine, then the premium for the joint-production arrangement may be about 21% higher
than originally estimated, or roughly $138 million (plus or minus $69 million) in FY2005
dollars.
Arguments For Alternative Approaches. Below are potential arguments that can
be made in favor of each of the six potential production approaches listed above.
Current Two-Yard, Joint-Production Approach. Supporters could argue that
the current two-yard, joint-production approach is less expensive than a two-yard, separate-
production approach, as indicated in the Navy’s 1997 estimate.
Supporters could argue that introducing competition into the current joint-production
approach for producing certain submarine parts might not necessarily reduce costs because
it could compel the yards to maintain additional production equipment, complicate the
84 U.S. Congress, House Committee on National Security, Hearings on National Defense
Authorization Act For Fiscal Year 1997 — H.R. 3230 and Previously Authorized Programs,
104th Cong., 2nd sess., March 19, 21, 22, 29, 1996 ( Washington:GPO, 1997). [Title I —
Procurement, H.N.S.C. No. 104-24] p. 769, 778, 851, 877. (See also p. 890, which refers to
the FY1996 DDG-51 class destroyer solicitation, a combined solicitation for the six
DDG-51s procured in FY1996 and FY1997); U.S. Congress. Senate. Committee on Armed
Services. [Hearings on] Department of Defense Authorization for Appropriations For Fiscal
Year 1997 and The Future Years Defense Program (S. 1745), 104th Cong., 2nd sess., Part 2,
Seapower, March 19, 21, 26, 27, 28, 1996 ( Washington: GPO, 1997). [S. Hrg. 104-532, Pt.
2] p. 130.
See also CRS Report RL31400, Navy Shipbuilding: Recent Shipyard Mergers —
Background and Issues for Congress
, by Ronald O’Rourke.

CRS-51
yards’ ability to plan their production activities, and make the process for building and
assembling the submarines less uniform from one boat to the next.
Supporters could argue that, compared to a one-yard approach, the current two-yard,
joint-production approach offers the following potential benefits:
! It permits the Navy to use submarine production costs, production
quality, and schedule adherence at one yard to be used as a
benchmark for evaluating submarine production costs, production
quality, and schedule adherence at the other yard, giving the
government some leverage in achieving good results in submarine
construction work at both yards even though competition is not
being used in the awarding of submarine construction contracts.
! It could ease the task of accommodating an increase in the
submarine procurement rate by spreading the challenge of hiring,
training, and supervising new workers over two companies and two
regional labor markets.
! It permits a sustained procurement rate of four submarines per year
without compelling GD/EB to put its old inclined building ways
back into production (if the alternative would have been to have
GD/EB be the sole yard producing submarines), and with less risk
of straining supervisory skills at either GD/EB or NGNN.
! It preserves a potential for returning to two-yard, separate-production
for submarines, and for using competition in awarding submarine
construction contracts, should the submarine procurement rate
increase to a level sufficient to support two-yard, separate-
production, and to maintain effective competition. (As mentioned
earlier, however, even if the procurement rate increases to a level
sufficient for effective competition, the sharing of trade secrets
between the two yards during the period of joint production may
make it difficult to resume competition in a manner that is fair to
both yards.)
! It would permit the United States to continue building submarines
at one yard even if the other yard is rendered incapable of building
submarines permanently or for a sustained period of time by a
catastrophic event of some kind.85
85 One possibility for such an event would be a large-scale attack on the yard or an adjacent
area by a foreign country or terrorist group using a nuclear weapon or a so-called dirty bomb
(i.e., a radiological dispersion device). Another possibility is a powerful (i.e., category 4 or
5) hurricane. The National Hurricane Center estimates that Category 4 and 5 hurricanes
strike within 75 nautical miles of Newport, RI (which is close to GD/EB’s facilities) every
150 and 420 years, respectively, and within 75 nautical miles of the Norfolk, VA area
(which is close to NGNN) every 230 and more than 500 years, respectively. (Data taken
from CRS Report 96-785 F, Navy Major Shipbuilding Programs and Shipbuilders: Issues
and Options for Congress
, by Ronald O’Rourke. It is not clear, however, whether even a
(continued...)

CRS-52
! It broadens the geographic base of support for procurement of
submarines.
Two-Yard, Joint Production With Some Competition. Supporters could argue
that a two-yard, joint-production approach with competition for certain portions of the
process for building the submarines would:
! be less expensive than a two-yard, separate-production approach, as
implied by the Navy’s 1997 estimate,
! preserve all the potential benefits, compared to a one-yard approach,
of the current two-yard, joint-production approach, and
! potentially reduce costs for building certain parts, and
! broaden the Navy’s ability to use submarine production costs,
production quality, and schedule adherence at one yard to be used as
a benchmark for evaluating submarine production costs, production
quality, and schedule adherence at the other yard.
Two-Yard, Separate Production. Supporters could argue that compared to a one-
yard approach, a two-yard, separate-production approach would offer all the potential
benefits of a two-yard, joint-production approach, and that compared to a two-yard, joint-
production approach, it would offer the following additional potential benefits:
! It would more significantly broaden the Navy’s ability to use
submarine production costs, production quality, and schedule
adherence at one yard to be used as a benchmark for evaluating
submarine production costs, production quality, and schedule
adherence at the other yard.
! It could permit the current sharing of trade secrets by the two yards
to end, which could make it easier at some point further in the
future, should the submarine procurement rate increase to a level
sufficient to maintain effective competition, to implement, in a
manner that is fair to both yards, a decision to resume using
competition in awarding submarine construction contracts.
One-Yard Production At GD/EB. Consolidating submarine production at GD/EB
would keep two shipyards involved in building nuclear-powered warships of some kind,
with one yard (GD/EB) building submarines and the other yard (NGNN) building aircraft
carriers.
85 (...continued)
category 4 or 5 hurricane would cause enough damage to disrupt operations at the shipyard
by more than a few or several months, particularly if the yards have taken steps to protect
their facilities against the effects of a hurricane. A third possible catastrophic event is a
large-scale radiological accident that spreads radiation over much of the yard. In light of the
very high safety standards of the U.S. Navy nuclear propulsion program, such an event
might be exceedingly unlikely.

CRS-53
Supporters of this approach could argue that it would be less expensive than a two-yard
approach for building Virginia-class submarines, as indicated in the Navy’s 1997 estimate.
Supporters could argue that, compared to the option of consolidating submarine
construction at NGNN, this option offers the following potential benefits:
! It would permit work relating to nuclear propulsion plants at one
yard to be used as a benchmark for evaluating somewhat similar
work at the other yard, giving the government some potential
leverage in maintaining good results in nuclear-propulsion-plant-
related work at both yards.
! It would maintain nuclear-propulsion-plant-related skills at both
yards, making it possible for one yard to assist the other, when
needed, in nuclear-propulsion-plant-related work.86
! It would preserve a potential for returning to two-yard, joint-
production or two-yard, separate-production for submarines, and (in
the latter case) for resuming competition in awarding submarine
construction contracts, should the submarine procurement rate
increase to a level sufficient to support two-yard production and to
maintain effective competition. Restoring submarine production at
NGNN, however, could take many years and considerable capital
investment, particularly if many years had passed since NGNN had
last built submarines.
! It would permit the United States to continue building nuclear
propulsion plants at one yard even if the other yard is rendered
incapable of doing this work permanently or for a sustained period
of time by a catastrophic event of some kind.
! It broadens the geographic base of support for procurement of
nuclear-powered warships.
One-Yard Production At NGNN. Since submarine design, engineering, and
construction is GD/EB’s primary business, consolidating submarine production at NGNN
could lead to the closure of GD/EB or to its conversion into a primarily design and
engineering activity.
Supporters of this option could argue that it would be less expensive than consolidating
submarine production at GD/EB for at least two reasons:
! It would permit the country’s nuclear-powered-ship construction
capacity to be consolidated into a single facility, reducing the
shipyard fixed overhead costs associated with building nuclear-
powered ships.
86 GD/EB nuclear propulsion engineers are currently assisting NGNN in the design of the
nuclear propulsion plant for the new CVN-21 aircraft carrier to be procured in FY2007.

CRS-54
! It would reduce the number of sites at which the U.S. Navy needs to
supervise nuclear-propulsion-plant construction work.
Two-Yard Parts Production, One-Yard Final Assembly. Under this approach,
production of parts for each submarine would continue at both GD/EB and NGNN, but final
assembly and testing of the submarines would be consolidated at either GD/EB or NGNN.
If final assembly and testing is consolidated at NGNN, then one potential approach that
some observers have mentioned would be to produce GD/EB’s parts at GD/EB’s hull
cylinder section construction facility at Quonset Point, RI and either close down GD/EB’s
main assembly facility at Groton or convert it into primarily a submarine design and
engineering activity.
Supporters of producing submarine parts for each submarine at both yards while
consolidating final assembly and testing at either GD/EB or NGNN could argue that it
would offer some of the potential cost reductions of a one-yard strategy while preserving
some of the benefits of a two-yard strategy.
Questions For Congress. Potential questions for Congress regarding the approach
used for building Virginia-class submarines include the following:
! Does the Navy have an up-to-date estimate of the per-boat premium
for building Virginia-class boats under the current two-yard, joint-
production arrangement rather than under a one-yard approach, and
if so, what is it?
! Is the Navy still open, as it appears to have been in 2003, to
considering alternatives to the current joint-production arrangement?
! What is the Navy’s view on how the potential future submarine
procurement rate relates to the kind of production arrangement that
should be used, and if so, what is it? What is the Navy’s view of
how the costs and benefits of potential approaches compare at
various potential future procurement rates?