Order Code IB87111
Issue Brief for Congress
Received through the CRS Web
F-22 Raptor Aircraft Program
Updated July 3, 2002
Christopher Bolkcom
Foreign Affairs, Defense, and Trade Division
Congressional Research Service ˜ The Library of Congress

CONTENTS
SUMMARY
MOST RECENT DEVELOPMENTS
BACKGROUND AND ANALYSIS
Major Developments
FB-22?
Program Details
Program Acquisition Cost
Planned Procurement Quantity
Unit Cost
Funded through FY2000
System Description
Key Issues
Does the United States need to develop new tactical fighter aircraft at this time?
Main arguments of those favoring development of a new fighter
Main arguments of those favoring improvement of present systems
Congressional Action


IB87111
07-03-02
F-22 Raptor Aircraft Program
SUMMARY
The F-22 Raptor is a next-generation
out-year expenditures.
fighter/attack aircraft using the latest stealth
technology to reduce detection by radar.
The F-22 program raises questions about
Equipped with more advanced engines and
its cost and the need for this aircraft, the
avionics than the current F-15 Eagle, the F-22
capabilities it would have, and the number of
is expected to maintain U.S. Air Force capa-
these planes needed to meet military require-
bilities against more sophisticated aircraft and
ments. The F-22 has had strong congressional
missiles in the 21st century.
support, although some have criticized the
program on grounds of cost, requirements, and
In 1986 two contractors were selected to
coordination with other tactical aircraft pro-
build competing prototypes: Lockheed’s
grams. Deletion of procurement funds in the
YF-22 and Northrop’s YF-23, which were
FY2000 defense appropriation bill passed by
flight tested in late 1990. In April 1991, the
the House made the future of the program a
Air Force selected Lockheed’s YF-22 design
major issue for House and Senate conferees in
for full-scale development, now termed “En-
1999.
gineering & Manufacturing Development”
(EMD). The aircraft is powered by Pratt &
Some question the urgency of beginning
Whitney’s F119 engine, selected in competi-
production of the F-22 when production of
tion with General Electric’s F120 engine. If
comparable or better aircraft by other coun-
produced as now projected, F-22s could begin
tries appears unlikely. Others argue that the
replacing F-15s after 2005.
F-22 should enter production as early as possi-
ble to cope with future threats from more
The Administration’s FY2003 budget
advanced air defenses of potential enemies
requested $5.2 billion for the F-22 program in
and to maintain the U.S. position in aviation
procurement and development funds. Through
technology and production. The airframe will
FY2000, Congress provided some $22.8
be produced by Lockheed Martin in Marietta,
billion for the F-22. A 341-aircraft program
GA, and Ft. Worth, TX, and by Boeing in
was estimated in June 2000 to cost about
Seattle, WA, with engines by Pratt & Whitney
$61.9 billion in actual prior-year and projected
in West Palm Beach, FL.
Congressional Research Service ˜ The Library of Congress

IB87111
07-03-02
MOST RECENT DEVELOPMENTS
The Administration’s FY2003 budget requested $5.2 billion for the F-22 program in
procurement and development funds. In their mark ups of the FY2003 defense authorization
bill, both House and Senate authorizing committees met the Administration’s request for F-
22 funding.
House appropriators provided $4.1 billion to procure 23 F-22s in FY03.
On March 6, 2002, the GAO published a report (“F-22 Delays Indicate Initial
Production Rates Should be Lower to Reduce Risk” ) recommending that the Air Force cut
the number of F-22 Raptors procured during low rate initial production (LRIP) to 13
aircraft per year; which equates to a reduction of 113 aircraft over five years..

BACKGROUND AND ANALYSIS
Major Developments
Air Force officials regard the F-22 program as the service’s highest aviation priority.
Designed as a fighter with attack capability, the F-22 Raptor uses the latest developments in
stealth technology to reduce the probability of detection by enemy radar as well as
thrust-vectoring engines for more maneuverability and integrated avionics for rapid fusion
and display of target data. The first prototype of this next-generation stealth fighter/attack
plane was first flown on September 7, 1997, followed by test flights by two development
aircraft at Edwards Air Force Base, CA, where 184 test-flight hours were completed by
November 23, 1998. The first F-22s could be in service after 2005, with deliveries expected
to continue into the 2010s. The major contractors are Lockheed Martin in Marietta, GA, and
Fort Worth, TX, and Boeing in Seattle, WA, for the airframe, with engines made by Pratt &
Whitney in West Palm Beach, FL.
During the early 1980s, the Air Force began development of a stealth aircraft called the
Advanced Tactical Fighter (ATF), then expected to enter service in the 1990s to replace F-15
fighter planes developed in the early 1970s. The ATF was viewed as a necessary response
to expected advances in the Soviet Union’s development and production of combat aircraft
in the 1990s. A naval variant of the ATF that could operate from aircraft carriers (the NATF)
was expected to replace the Navy’s F-14 fighter; however, funding for the NATF was not
requested by the Defense Department after 1990, and development of a naval variant has not
been pursued.
In hopes of reducing costs, the Defense Department emphasized competitive prototypes
for airframes, engines, and avionics. The Air Force selected two teams of airframe
contractors to develop ATF prototypes: Lockheed teamed with Boeing and General
Dynamics; and Northrop teamed with McDonnell Douglas. On October 31, 1986, the Air
Force awarded each team a $691-million fixed-price contract to build two prototypes,
Lockheed’s YF-22 and Northrop’s YF-23, powered by new engines — one using Pratt &
Whitney’s F119 and one using General Electric’s F120 power plant. The Air Force
announced in 1989 that the full-scale development phase would be delayed to allow more
time for development of engines and avionics. Each contractor team reportedly spent over
CRS-1

IB87111
07-03-02
$1 billion in company funds to develop competing prototypes, two YF-22s and two YF-23s,
which were flight-tested and evaluated in late 1990.
On April 23, 1991, the Air Force selected the Lockheed team’s YF-22 design for
development as the F-22, powered by Pratt & Whitney’s new F119 engines. Secretary of the
Air Force Donald B. Rice stated that the choice was based on confidence in the ability of the
Lockheed team and Pratt & Whitney to produce the aircraft and its engine at projected costs.
Emphasizing the importance of the Lockheed team’s management and production plans, he
stated that the F-22 offered better reliability and maintainability and denied that either
prototype was significantly more maneuverable or stealthy. On August 2, 1991, contracts
totaling $11 billion were awarded to Lockheed and Pratt & Whitney for engineering and
manufacturing development (EMD) of the F-22, then including 11 development/prototype
aircraft.
The Defense Department’s Selected Acquisition Report (SAR) of September 30, 2000,
estimated the development and production cost of a 341-aircraft program at $61,940.1
million then-year dollars (actual funding in prior years and projected funding in future years).
The quantity of aircraft in the program was reduced from 750 to 648 in 1991, then to 442 in
late 1993, and later to 341(339 production and 2 development aircraft) in 1997. The F-22's
development/production schedule has also been delayed. Citing budgetary constraints,
reduced threats in Europe, and the F-15's longer service life as reasons for deferring
production, Secretary of Defense Cheney told Congress in April 1990 that production of the
aircraft could be delayed two years instead of beginning in FY1994 as originally planned,
with annual production peaking at 48 aircraft in 2001 instead of increasing to 72 by FY1999
as previously planned. These 1990 projections of the F-22's development and production
schedules were further revised later, when the development program was extended and the
number of prototypes was reduced.
The Defense Department’s 1993 Bottom-Up Review (BUR) resulted in the program’s
reduction to 442 aircraft — 438 production and four pre-production versions (later reduced
to two) — which would support four fighter wings in a force structure of 20 wings (13
active; seven Reserve/National Guard). The Defense Department’s Quadrennial Defense
Review (QDR) released on May 19, 1997, recommended a further reduction of the projected
buy from 438 to 339 production aircraft, which would support three fighter wings in a
20-wing force structure of 12 active and 8 Reserve/National Guard wings. The QDR also
recommended reducing the maximum production rate from 48 to 36 planes per year as a
more affordable rate of production.
The FY1997 budget projected procurement of 40 aircraft in FY1998-FY2001 (versus
the 76 projected in 1994 to be bought in these years), costing $11 billion in development and
procurement funds. The FY1999 budget projected procurement of 18 aircraft in FY1998-
FY2001 (versus the 40 projected in 1996 to be bought in these years) and 40 in FY2002-
FY2003, costing $18.6 billion for development and procurement of 58 aircraft. As projected
in 1998, two aircraft, termed “Production Representative Test Vehicles,” would be procured
in FY1999, followed by 6 (FY2000), 10 (FY2001), 16 (FY2002), and 24 (FY2003). These
annual buys were also in the FY2000 budget, which projected 36-plane buys in FY2004 and
FY2005. Procurement of six production aircraft in FY2000 as projected in early 1999 was
later changed by Congress to procurement of six test aircraft in FY2000.
CRS-2

IB87111
07-03-02
The F-22 has been a defense budget issue since 1990, when reassessments of Soviet
threats and capabilities have called into question the need to replace current fighters with
next-generation aircraft. Critics of the program argue that since the Soviet Union is unlikely
to continue producing the kinds of aircraft the F-22 stealth fighter/attack plane is designed
to combat, it would be more cost-effective to upgrade fighter/attack planes currently in
production (e.g., F-15Es and F-16s), which these critics think would be adequate for the most
probable threats. Some critics argue that production of the F-22 should at least be delayed,
pending the emergence of a credible military threat. Others argue that fewer F-22s would
be needed because of the greater combat capability the aircraft is expected to provide.
Defense Secretary William Cohen, for example, cited the F-22's superior combat capability
as a reason for the QDR’s proposed reduction to 339 production aircraft. Some believe that
fewer than 339 F-22s will be bought. Rep. John Murtha, ranking Democratic member of
the House Defense Appropriations Subcommittee, has reportedly stated that, depending on
the threat and budget constraints, “the Air Force will be lucky” to get 140 F-22s. In
September, 2000 Rep. Murtha reinforced his position, saying that he didn’t think the current
threat justified more than 150 Raptors, and that “I don’t think we’ll have the money to build
any more.”1
Proponents of the F-22 argue that fighters with its stealth (low radar-observability)
features and advanced combat capabilities would be needed in conflicts involving
sophisticated air defenses in the hands of competent enemies equipped with advanced
versions of Russian or European aircraft and missiles; e.g., the Russian Su-35 and the
Eurofighter EF-2000 and Russian SA-10 and SA-12 surface-to-air missiles. Its advocates
argue that the F-22 will be the first stealthy fighter/attack aircraft that combines supersonic
speed without resort to afterburners (requiring additional fuel), maneuverability via
thrust-vectoring engines, and fusion of multi-sensor avionics data via computers, and this
will enable pilots to destroy enemy aircraft and ground-based air defenses at greater standoff
ranges. They also believe the F-22 is needed as a hedge against a revived Russian threat as
well as unpredictable third-world dangers in the years ahead, and they see the program as
necessary to maintain U.S. industrial capabilities for development and production of
advanced aircraft. With some 30 major subcontractors and some 4,500 suppliers in 48 states,
the F-22 program is expected to generate up to 28,000 jobs at peak production, with indirect
employment adding up to 112,000 jobs, according to contractor estimates in 1999.
In December 1993, a General Accounting Office (GAO) report (“Tactical Air: Planned
F-15 Replacement Is Premature”) recommended that the F-22's initial operational capability
(IOC) be delayed until 2010, arguing that current F-15s can defeat expected threats until
2015 or later. GAO also noted a contradiction between development of the F-22 as a highly
specialized aircraft to be used by only one service for a single mission and the Defense
Department’s current emphasis on developing joint-service, multi-mission aircraft. Critics
of GAO’s position argue that the proliferation of advanced European and Soviet aircraft,
surface-to-air missiles, and radar capabilities in the Third World could pose threats that
would require the capabilities of the F-22, even if F-15s remain in service longer than earlier
expected. They argue that Russian Su-27s and MIG-29 fighters are technologically equal to
1 “Rep. Lewis: F-22, JSF Numbers to be Set in Two to Three Years.” Aerospace Daily, Oct. 8,
1999:43,46. Wolfe, Frank. “Murtha: Pentagon Can Afford only 150 F-22s.” Defense Daily.
September 22, 2000:2.
CRS-3

IB87111
07-03-02
the F-15 and could defeat an F-15 force in a scenario where these U.S. fighters might be
outnumbered. F-22 supporters cite its low radar-observability, superior fuel efficiency at
sustained supersonic speed, and greater range and maneuverability than the F-15.
Concerns about the cost of the F-22 were expressed in 1996 during Senate debate on
the FY1997 defense budget. In late 1996, the Air Force began negotiating with the
contractors to control cost overruns in development and production that some thought might
reduce the number of aircraft procured. Cost-reduction measures included eliminating two
of the four pre-production aircraft between the prototypes and production aircraft.
In 1997, the cost of the F-22 program was a major issue in Senate deliberations and
action on the FY1998 defense budget. The Senate Armed Services Committee’s Air-Land
Subcommittee hearing on April 16, 1997, focused on different estimates of the F-22's cost
by Defense Department and Air Force officials, and the FY1998 authorizations bill imposed
caps on development cost at $18.7 billion and production cost at $43.4 billion. (In early
2000 these caps were adjusted to $20.4 billion and $37.6 billion, respectively, to reflect
inflation and a congressionally mandated change in procurement and development funding
for FY2000.) In 1998, the program was again discussed in Senate Armed Services
Committee hearings, where Air Force plans to begin production of the aircraft in FY1999
were criticized. Despite such criticism, Congress appropriated $2,346.7 million of the
$2,367.5 million requested for the F-22 in the FY1999 defense budget.
In discussions with members of congressional defense committees, it was agreed that
at least 183 hours of flight testing would be completed before awarding contracts for
procurement of two aircraft termed “production representative test vehicles” and for advance
procurement funding of 6 production aircraft to be funded in FY2000. This flight-testing
goal and several other requirements for initial production were met by November 23, 1998,
clearing the way for contract awards.
The cost of the program again became an issue in late 1998, when it was reported that
cuts in production of Lockheed Martin’s C-130J cargo/transport planes would increase the
F-22's overhead cost, since both aircraft are produced at the contractor’s Marietta, GA,
facility. (See CRS Report RL30685, C-17 Cargo Aircraft Program, for references to the C-
130J.) In a December 1, 1998, letter to Defense Secretary Cohen, Representative Obey
expressed concerns about this matter, asking whether the F-22 contract will be tied to C-
120J purchases and whether there is precedent for such linkage between the overhead costs
of different programs.2
Concerns over the F-22 program’s cost were raised again in 2000. On June 15 Air Force
officials testified that the program’s cost is estimated to be $1 billion above the spending cap
placed on the production phase. However, they had identified $21 billion in future cost
reductions. However, the DoD office of Operational Test and Evaluation estimated the F-22
program cost had grown $8 billion higher than Air Force projections. Furthermore, in a
August 16, 2000 report, the GAO claimed that about one half of the $21 billion in cost
reductions identified by the Air Force have yet to be implemented, and that the Air Force
2 “Representative Obey Questions C-130J/F-22 Linkage.” Aerospace Daily, December 7, 1998.
p.380.
CRS-4

IB87111
07-03-02
may not be able to achieve many of these reductions because they depend on actions by
either DoD or Congress.3
Originally scheduled for December 21, 2000, the Pentagon’s Defense Acquisition Board
(DAB) approved on August 15, 2001 the F-22 to enter low-rate initial production (LRIP).
Lockheed Martin to build 10 Raptors using FY2001 funds, and 13 in FY2002 LRIP will
continue through FY2005, when the program is expected to shift to full rate production, of
up to 90 aircraft per year. As part of the LRIP decision, DoD officials reduced the overall
number of aircraft to be purchased from 333 to 297. The DAB reportedly reduced the
number of F-22s to be produced because of uncertainties regarding production costs. The
Pentagon’s Cost Analysis Improvement Group (CAIG) estimated that the production
program would be $9 billion over the $37.6 billion congressional cost cap. The Air Force
estimates it is $2 billion over the cap.4 The DAB chose the CAIG’s estimates to determine
the total production run.5
Completing EMD testing appeared to be a significant development for the F-22
program. On February 5, 2001, the Air Force announced that it had completed all required
tests. However, the next day, a Pentagon a spokesman announced that no meeting would be
scheduled on the F-22 LRIP decision until after Secretary of Defense Rumsfeld had a chance
to completely review the program.
In a December 20, 2000 letter to then Under Secretary of Defense Jacques Gansler,
DoD’s director of Operational Test and Evaluation recommended extending the F-22
engineering, manufacturing and development (EMD) phase an additional nine months to
conduct additional tests and to reduce “unacceptable risks.” General Michael Ryan, Air Force
Chief of Staff disputed this recommendation, calling the F-22 “The most extensively tested
fighter in history.”6 Yet, in May 2001, it was reported that the F-22 program manager, Brig.
Gen. Jay Jabour confirmed that the F-22's operational testing would be delayed up to nine
months.7 On June 6, 2001 Gen. Ryan confirmed Jabour’s statement, testifying that F-22's
EMD phase would be extended from November 2001 to the spring of 2002.8
On February 6, 2001, Deputy Secretary of the Air Force Darleen Druyan announced that
the Air Force would remove 14 to 15 F-22s from its low rate initial production purchase to
free up $475 million that it would invest in producibility improvements. The Air Force’s
FY2002 budget requested procurement funds for 13 Raptors, rather than the previously
planned 16 low-rate initial production aircraft. The Air Force anticipates buying the removed
3 “Quarterly Reports Urged on F-22 Production Costs.” Aerospace Daily. August 16, 2000.
4 De France, Linda. “F-22 Program Gets Reprieve with Postponement of DAB until Jan. 3.”
Aerospace Daily. December 19, 2000.
5 Weinberger, Sharon . Program Head: F-22 on course for LRIP, next contract due in October.
Aerospace Daily. September 24, 2001
6 Squeo, Anne Marie. “Lockheed’s Next-Generation F-22 Faces More Development Hurdles.” Wall
Street Journal.
January 5, 2001. p.4
7 Lowe, Christian. “F-22 Testing to Slip, Costs to Rise. Defense Week. May 21, 2001.
8 Selinger, Marc. “USAF Considers New Tanker, F-22 Development Phase. Aerospace Daily. June
7, 2001.
CRS-5

IB87111
07-03-02
F-22s in future years. If the Air Force were to extend the F-22 test program, however, it
would likely add cost to the overall program and also make it difficult for the aircraft to enter
operational service in late 2005.
A March 6, 2002 GAO report criticized the F-22 program, claiming that it “did not meet
key schedule goals for 2001, the cost to complete planned development is likely to exceed
the $21 billion reported to Congress, and the program is not far enough along in flight-testing
to confirm Air Force estimates of the aircraft’s performance.”9 The report projected that
airframe flight testing four years longer than currently planned. The report noted that the Air
Force is conducting F-22 flight tests at a rate that is 30 percent lower than planned.
According to Air Force records, first flight of F-22 development aircraft has been delayed
a total of 83 months. The GAO’s primary recommendation was for DoD to limit the low-rate
production (LRIP) of F-22 aircraft to 13 per year, until operational testing is completed and
manufacturing processes are under control. GAO wrote that more testing is needed to
confirm F-22 performance estimates.
GAO reported that DoD did not concur with the recommendation to limit LRIP aircraft.
DoD officials said there was not sufficient justification to limit production rate for the F-22
until operational testing is completed. Also, they argued that limiting the number of aircraft
procured during LRIP would make it difficult for sub-suppliers to make improvements
leading to full-rate production readiness.10 In fact, DoD officials claim that cost reduction
efforts are already paying dividends, and will allow the Air Force to purchase 23 Raptors in
FY2003, an increase of two aircraft over previous proposals.11 One senior DoD official
commented that implementing GAO’s LRIP recommendation could “destabilize program
cost and schedule.”12
The stability of the F-22 program is not always clear, however. In April 2002, Air Force
Secretary James Roche said that due to a variety of problems, the F-22 program had a “50-50
chance” of entering the dedicated initial operational test and evaluation (DIOT&E) phase on
schedule.13 This prediction was confirmed by Air Force officials in May 2002. Gen. William
Jabour estimated that the April 2003 target date for beginning the F-22's initial operational
testing and evaluation would likely be exceeded by three to six months.14 Also, due to a
9 General Accounting Office. Tactical Aircraft: F-22 Delays Indicate Initial Production Rates
Should Be Lower to Reduce Risks.
(GAO-02-298). March 6, 2002. P.2.
10 IBID. p. 27.
11 Hebert, Adam. “Air Force Sees Early Returns From F-22 Cost Savings.” Inside Defense.com.
March 7, 2002.
12 Daniel Dupont.. “Test Snags Prompt GAO to Call for Initial F-22 Buy Rate Reduction.” Inside the
Air Force.
March 8, 2002.
13 Frank Wolfe. “Roche: 50-50 Chance of F-22 Entry into DIOT&E by April 2003.” Defense Daily.
April 19, 2002. P.1.
14 Sharon Weinberger. “Air Force ‘unlikely’ to meet F-22 operational test schedule, official says.
Aerospace Daily. May 31, 2002.
CRS-6

IB87111
07-03-02
labor strike at Lockheed Martin’s Marietta GA plant, F-22 production is expected to be
delayed almost 50 days.15
FB-22?
Lockheed Martin has initiated a study, and has briefed initial results to Air Force
officials, of a radically modified version of the Raptor called the FB-22 (Fighter/Bomber).
The purpose of this variant would be to significantly increase the F-22's air-to-ground
capabilities; primarily through a redesign that would double the aircraft’s range, and
significantly increase the aircraft’s internal payload. These improvements would likely result
in some performance tradeoffs, such as reduced acceleration and maneuverability.
Although not officially part of the F-22 program, and still very much in the conceptual
phase, some Air Force leaders have expressed enthusiasm for the idea. Secretary of the Air
Force James Roche, reportedly touts the FB-22 idea as the potential platform of choice for
providing better close air support for tomorrow’s ground forces.16 Other Air Force leaders
appear less enthusiastic at this point.17 Potential costs and schedule of the FB-22 concept are
still quite notional. How this multi-role aircraft would compete with – or conversely
compliment – the JSF has not yet been determined.
Program Details
Program Acquisition Cost. The Defense Department’s Selective Acquisition
Report (SAR) of September 30, 2000, estimated the total program cost of 341 aircraft (339
production and two development aircraft) at $61,940.1 million then-year dollars (actual
amounts spent in prior years and estimated expenditures in future years, based on current
assumptions about inflation rates and annual production rates in the out-years). As projected
in 1997, the F-22's program cost was $70.9 billion then-year dollars for development and
production of 440 aircraft.
Planned Procurement Quantity. As currently projected, the Air Force plans to
procure 295 production aircraft. When the F-22 design was selected (April 23, 1991), the
service projected procurement of 648 aircraft instead of the 750 previously projected. In late
1993, the Air Force announced plans to procure 442 aircraft ( 438 production aircraft and
four development aircraft). The 1997 QDR called for further reduction to 339 production
aircraft. On July 26, 2000 then-Secretary of the Air Force Whitten Peters was reported to
have said that 339 F-22 Raptors “...is about the right number for 10 AEFs,” (Air
Expeditionary Forces), the USAF’s latest organizational scheme.18 The 2004 Defense
Planning Guidance (DPG) reportedly directs Pentagon leaders to study the pros and cons of
15 Laura Calarusso. “Lockheed Marting Strike Sets Back F-122 Production by at Lease 49 Days.”
Inside the Air Force. May 17, 2002.
16 Ron Laurenzo. “Roche Envisions Close Air Support F-22.” Defense Week. July 1, 2002.
17 Bill Sweetman. “Smarter Bomber.” Popular Science. June 25, 2002.
18 Frank Wolfe. “Peters. 339 F-22s ‘About The Right Number’ for 10 AEFs.” Defense Daily. July
26, 2000. p.8.
CRS-7


IB87111
07-03-02
trimming the overall F-22 purchase to 180 aircraft. This study is expected to be complete by
September 2002.19
Unit Cost. $182 million then-year dollars per plane in a 341- aircraft program (2
development and 339 production aircraft as currently projected by the Air Force) estimated
in June 2000 to cost $61,940.1 million then-year dollars.
Funded through FY2000. Some $22.8 billion (then-year $), mainly in R&D
funding, including $2.5 billion in FY2000. Through FY1992, the program received about
$165 million in Navy R&D funds for a naval variant that was not developed. Funding of
the ATF/F-22 began in the early 1980s and is projected to continue into the FY2010s.
System Description
The production version of the F-22 will have a wingspan of 44.5 ft, length of 62 ft, and
height of 16.5 ft. The aircraft’s maximum takeoff weight is estimated to be about 60,000 lb,
with a projected empty weight of about 32,000 lb (without fuel and munitions). Powered
by two Pratt & Whitney F-119 turbofan engines with afterburners and thrust-vectoring
nozzles, the F-22 is expected to have a supersonic level speed of about Mach 1.7 using
afterburners, and a supersonic cruise speed of about Mach 1.5 without afterburners. The
F-22's armaments include a 20-mm M61 gun and various loadings of air-to-air missiles
(visual-range AIM-9 Sidewinders and medium-range AIM-120 AMRAAMs) and
air-to-surface ordnance (e.g., Joint Direct Attack Munitions, and potentially future munitions
like the small diameter bomb), which can be carried internally or on underwing pylons. The
F-22's reduced radar-cross-section and stealth features of low radar-observability are
achieved through the use of radar-absorbing composite materials, the reduction of infrared
and radar signatures by shaping and blending of structures, and by exploiting low-probability
of intercept communications.
Figure 1. F-22 Prototype
19 Robert Wall. “F-22 Enters Critical Phase.” Aviation Week & Space Technology. June 24, 2002.
Frank Wolfe. “Defense Planning Guidance Directs Study of Optional Approaches to F-22 Program..”
Defense Daily. Dave Montgomery. “The F-22 and The Pentagon.” Fort Worth Star-Telegram. June
6, 2002.
CRS-8

IB87111
07-03-02
Key Issues
Does the United States need to develop new tactical fighter aircraft
at this time?

Main arguments of those favoring development of a new fighter. The
United States must develop a next-generation fighter if we are to maintain a technological
lead in the development and production of combat aircraft. Soviet Mig 29s and Su 27s are
roughly comparable to current U.S. fighters in combat capabilities, and European aerospace
industries are likely to produce more advanced aircraft in the years ahead. These aircraft
could pose serious threats in regional conflicts in the next century, when we would also face
serious threats from more advanced air defenses. When the F-22 enters service after 2005,
many U.S. Air Force and Navy fighters (developed in the mid-1970s) will be about 30 years
old. Moreover, they may be outnumbered by comparable or better foreign aircraft, given
recent procurement trends and projected force reductions. Currently operational fighters
cannot be further modified to provide the stealth and other combat capabilities needed to
cope with the air defenses many Third World countries may possess in the 2000s, when arms
reductions in the West and economic conditions in the former Soviet bloc may result in a
proliferation of sophisticated military technology, particularly in surface-to-air missiles and
air defenses. The F-15 will be unable to provide that measure of air superiority required in
the post-2005 world.
Main arguments of those favoring improvement of present systems. The
United States should concentrate on programs to upgrade and modernize existing U.S. fighter
and attack aircraft while improving their air-intercept missiles and avionics to counter future
advances in the aircraft and air defense capabilities of potential enemies. Production of a
new generation of fighter planes cannot be justified in light of the collapse of the Soviet
Union and recent Persian Gulf experience in which current U.S. aircraft operated effectively.
These factors raise serious doubts about the military threats the F-22 is designed to oppose.
Development of the F-22 might be continued as a hedge against long-term threats, but there
are too many uncertainties about the need for this aircraft to warrant major funding
commitments to the program over the near term, which may jeopardize funding of other
critical weapon systems, such as tactical and strategic missile defenses. Our limited defense
funds could be more prudently invested in improving fighter aircraft now in production,
while developing more lethal munitions of greater range and accuracy, as well as better
electronic warfare capabilities to counter the air defenses of likely enemies.
Congressional Action
The ATF/F-22 program has had strong support in Congress, which has generally
authorized funding for the program as requested, although in some years Congress has
appropriated less than the amounts requested and authorized, usually reflecting opposition
to the program in the House.
The Administration’s FY1997 defense budget, submitted March 4, 1996, requested
$2,003 million in Air Force development funds for the F-22 program (plus $4.4 million in
military construction funds). The House authorized funding as requested for the F-22 in its
FY1997 defense authorizations bill (H.R. 3230, passed May 15, 1996) as did the Senate in
CRS-9

IB87111
07-03-02
its authorizations bill (S. 1745, passed July 10, 1996). The Senate Armed Services
Committee expressed concern over the cost of the program, however. Noting that the last
independent cost estimate was in 1991 when Lockheed’s YF-22 design was selected for
full-scale development, the Committee called for an updated estimate by DOD’s Cost
Analysis Improvement Group (CAIG) to be submitted to Congress by March 30, 1997, with
eight percent of the program’s FY1997 funding (about $160 million) to be withheld until
receipt of this cost estimate (Sec. 218 of S. 1745). A floor amendment to Sec. 218 by
Senator Grassley specified the use of a July 1991 CAIG estimate as the baseline for cost
comparisons and called for a description and cost assessment of changes since July 1991 in
the program schedule, aircraft quantities, and projected production rates. (See Congressional
Record
, June 27, 1996: S7158-S7159.) Section 219 of S. 1745 called for additional reports
to Congress on major events and upcoming decisions affecting the development and
production of the F-22. These Senate provisions were included in the conference report
(H.Rept. 104-724), which was passed by the House on August 1, 1996, by the Senate on
September 10, and signed into law (P.L. 104-201) on September 23, 1996, by the President.
The House Appropriations Committee recommended $1,982 million ($20.5 million less
than the $2 billion requested and authorized by the House and Senate and appropriated by
the Senate), which was appropriated in the House version of the FY1997 defense
appropriations bill (H.R. 3610, passed June 13, 1996). The committee report described this
minor reduction as being “... without prejudice, noting that historically the Air Force has only
awarded 84 percent of the funds budgeted for award fees for the F-22 in a given fiscal year.”
The Senate Appropriations Committee recommended funding as requested and authorized
for FY1997. House and Senate conferees agreed in the FY1997 omnibus appropriations bill
(H.R. 3610, P.L. 104-208, September 30, 1996) to appropriate $1,987 million of the $2,003
million requested and authorized for the F-22.
The Administration’s FY1998 defense budget requested $2,152.1 million for the F-22
program ($2,071.2 million in R&D and $80.9 million in advanced procurement funds), while
projecting procurement of 70 aircraft in FY1999-FY2003 at a cost of $18.2 billion in
development and procurement funds. The previous year’s budget had projected procurement
of 40 F-22s in FY1998-FY2001 at a cost of $11.1 billion. In 1997, the cost of the F-22
program and the need for as many aircraft as projected became matters of more serious
concern in Congress. The Defense Department’s QDR, released in May 1997, called for
procurement to be reduced from 438 to 339 production aircraft.
On June 25, 1997, the House authorized FY1998 funding as requested for the F-22
($2,152.1 million in R&D and advance procurement funds), while the Senate on July 11,
1997, authorized only $1,651.2 million in R&D funding — a reduction of $420 million in
R&D funds and no advance procurement funds. The Senate version of the FY1998 defense
authorization bill (S. 936) included language (Sec. 212) limiting the F-22's development cost
to $18.7 billion and production cost to $43.4 billion and requiring annual GAO reports on
the cost and status of the program, via amendments by Senators Coats and Bumpers. (See
Congressional Record, July 11, 1997: S7244.)
The Senate Armed Services Committee stated that “Considering the disparities in the
statements of official witnesses on the cost estimates for F-22 production and the lack of
explanation of the program’s $2.2 billion overrun in EMD, failure to provide reports on the
substance of the program [as requested by Congress in 1996] does little to foster confidence
CRS-10

IB87111
07-03-02
in the program’s management or cost estimates....There is currently a lack of confidence due
to recently disclosed overruns and estimates of large overruns yet to come in the
production.... Increased development costs tend to imply increased procurement costs
throughout a program.” The committee denied advance procurement funds on grounds that
“... the F-22 program has $81.3 million from FY1997 advance procurement funds that could
be used to protect the schedule for the FY1999 production, thus ensuring that there is no
break in the early production of the F-22.” (S.Rept. 105-29: 100, 102.)
On July 15, 1997, the Senate appropriated $1,858.2 million in R&D funds but also
without advance procurement funds. The Senate Appropriations Committee was less critical
of the F-22, noting that the Senate version of the FY1998 defense appropriation bill (S. 1005)
recommended deletion of advance procurement funds “to ensure the program stays focused
on completion of the EMD program.” The Committee reduced the F-22's EMD funds only
by the $213 million budgeted for termination liability in FY1998, stating it “does not expect
the F-22 program to be terminated in FY1998" and expects this reduction to have “no impact
on the F-22 EMD program.” (S.Rept. 105-45: 115.)
The House version of the FY1998 defense appropriations bill (H.R. 2266, passed July
29, 1997) funded the F-22 program essentially as requested, with $6 million of the $80.9
million requested for advance procurement provided as R&D funding. An amendment by
Representative Nadler to reduce funding by $420 million was defeated by voice vote; an
amendment by Representative Obey forbidding the sale of F-22s to foreign governments
(Sec. 8104) was agreed to by voice vote. (See Congressional Record, July 29, 1997:
H5953-H5956, H5966-H5968.) The House version of H.R. 2266 in regard to the F-22
program was accepted by the conferees. The conference report on FY1998 defense
appropriations (H.R. 2266, passed by Congress September 25, 1997, and enacted as P.L. 105-
56 October 8, 1997) provided F-22 funding at the total level requested — $2,152.1 million
($2,077.2 million in R&D and $74.9 million in advance procurement funding).
This funding was authorized in the conference report (H.Rept. 105-340) on the FY1998
defense authorizations bill (H.R. 1119), which was approved by the House on October 28
and by the Senate on November 6, 1997. The authorizations bill included in Sec. 217 the
Senate’s restrictions on the aircraft’s EMD costs (capped at $18.7 billion) and productions
costs (capped at $43.4 billion), with these caps in FY1997 dollars that would be adjusted
annually to account for inflation.
The Administration’s FY1999 defense budget requested $2,367.5 million for the F-22
program ($1,582.2 million in R&D and $785.3 million in procurement funds), with projected
procurement of 58 aircraft in FY1998-FY2003 costing $18.6 billion in development and
procurement funding. In a Senate Armed Services Committee hearing on March 25, 1998,
the General Accounting Office (GAO) recommended delaying award of the F-22's first
production contract until October 1999, since only 4% of the development flight test program
would be completed by December 1998, when the Air Force planned to contract for the first
two production aircraft. Air Force officials stated that the flight tests were generating more
data than expected and argued that delaying the contract as recommended by GAO would
delay delivery of the aircraft, cause the program to exceed the cost caps imposed in 1997, and
weaken subcontractor commitment to the program. In response to concerns about inadequate
flight testing prior to the first production contract, the Air Force decided in April 1998 that
the two aircraft procured in December 1998 would be designated “production representative
CRS-11

IB87111
07-03-02
test vehicles” instead of production aircraft, although they would be bought with
procurement funds and could later be used as production planes.
In May 1998, the House National Security Committee and the Senate Armed Services
Committee recommended authorization of FY1999 funding for the F-22 as requested, with
Sec. 133 of the Senate authorizations bill (S. 2057) requiring certifications by DOD of
“sufficient testing prior to committing to production.” The House authorized F-22 funds as
requested in H.R. 3616, passed on May 21, 1998. The Senate also authorized F-22 funds as
requested when it passed S. 2057 on June 25, 1998, after an amendment by Senators Dale
Bumpers and Russell Feingold to prevent the release of advance procurement funds for the
F-22 before completion of 601 hours of flight tests was defeated 73 to 19. (See
Congressional Record, June 25, 1998: S7106-S7110, S7151.) The House version of the
FY1999 defense appropriations bill (H.R. 4103), passed on June 24, 1998, provided $70
million less than the $2,367.5 million requested for the F-22 program. The Senate version
(S. 2132), passed on June 24, 1998, funded the program as requested and authorized by the
House and Senate. The conferees on the FY1999 defense authorizations bill (H.R. 3616/S.
2057) approved $2,353.5 million for the F-22 ($14 million less that requested). The
conferees on the FY1999 defense appropriations bill (H.R. 4103) agreed in H.Rept. 105-746,
passed by the House on September 28 and the Senate on September 29, 1998, to provide
$2,346.7 million for the program ($20.8 million less than requested).
The Administration’s FY2000 budget requested $3,074.3 million for the F-22 program
— $1,852.1 million in procurement and $1,222.2 million in R&D funding for 6 low-rate
initial production (LRIP) aircraft. The F-22's increasing development cost was a major issue
in Congressional hearings and deliberations on the FY2000 defense budget (March 3, 10, and
17, 1999). GAO and CBO analysts noted that the program’s costs are higher than projected
earlier, with the Administration request for FY2000 including $312 million to cover
“procurement cost growth.”
The Senate version of the FY2000 defense authorization bill (S. 1059) as reported by
the Senate Armed Services Committee (S.Rept. 106-50) and passed by the Senate on May
27, 1999, funded the program as requested. Section 131 of S. 1059 required “the Secretary
of Defense to certify, before commencing low rate initial production of the F-22, that the test
program is adequate to determine its operational effectiveness and suitability, and that the
development and production programs are executable within the cost caps [imposed in the
FY1998 defense authorization act, P.L. 105-85].” The Senate version of the FY2000
defense appropriation bill (S. 1122) as reported by the Senate Appropriations Committee
(S.Rept. 106-53) and passed by the Senate on June 8, 1999, also included funding for the F-
22 program as requested.
The House version of the FY2000 defense authorization bill (H.R. 1401) as reported by
the House Armed Services Committee (H.Rept. 106-162) and passed by the House on July
10, 1999, also funded the F-22 program as requested. The committee directed the Secretary
of the Air Force to certify by February 1, 2000, that F-22 development and production
aircraft “can remain within the cost limits and that testing of the aircraft will be performed
in accordance with test plans that were in place when the cost limits were established
[1997],” adding that “If the Secretary is unable to make such certification, he shall inform
the committees of the reasons therefor and present a revised plan, including new cost
estimates, for the acquisition of this aircraft.” This language was included by House and
CRS-12

IB87111
07-03-02
Senate conferees in the conference report on FY2000 defense authorizations, which was
agreed to on August 5, 1999 (H.Rept. 106-301, Sec. 131).
On July 22, 1999, the House passed its version of the FY2000 defense appropriation bill
(H.R. 2561), which provided for the F-22 program only the $1,222.2 million requested in
R&D funding. The $1,852.1 million requested for procurement of 6 “low-rate initial
production” (LRIP) F-22s would instead be used to buy other aircraft ( 8 F-15s, 5 F-16s, 8
KC-130Js, and 2 E-8s) as well as for pilot retention and various readiness programs. After
citing the F-22's technical problems and cost growth, the House Appropriations Committee
report noted that “current threat projections for 2010 indicate that the United States will have
a 5 to 1 numerical advantage of advanced fighters against our most challenging adversaries
without the F-22.” (H.Rept. 106-244: 17-21). Calling for a “production pause,” the report
denied funding for procurement of 6 LRIP F-22s in FY2000. Supporters of the F-22 argued
that denying procurement funds in FY2000 could delay delivery of the plane by two years
and add $6.5 billion to the cost of the program. (See House debate in Congressional Record,
July 22, 1999: H6250-H6254, H6258-H6262, H6267-H6279.)
The amount of F-22 procurement funding in FY2000 was the most contentious issue
before the conferees, who reached an agreement in late September whereby some $2.5 billion
of the $3 billion requested and authorized for the program would be appropriated ($1,923
million for R&D and testing and evaluation of the aircraft, $277.1 million in advance
procurement funds for 6 test aircraft, and $300 million as a reserve fund for contract
termination liability), with production to be delayed from 2000 to 2001. Rep. Jerry Lewis,
Chairman of the House Defense Appropriations Subcommittee, stated on October 6, 1999,
that the “agreement precludes initiation of production in 2001 until the critical Block 3.0
software is successfully flown in an F-22 aircraft.” He added that “we hope the national
attention to the debate over the future of the F-22 program will lead to a heightened
awareness in Congress and the Defense Department to the need for intense scrutiny and
prioritization of all national defense programs, no matter how much we have already spent
on research and development or how vital they seemed when the process began.” (See
H.Rept. 106-371: Sec. 8146, Sec. 8147.)
The Administration’s FY2001 budget, submitted on February 7, 2000, requested
$3,957.9 million for the F-22 program – $2,546.1 million for procurement of ten low-rate
initial production (LRIP) aircraft and $1,411.8 million in R&D funding. In their reports
issued in May and June 2000, the congressional defense oversight committees recommended
authorization and appropriation of funds equal to the Administration’s request for both
procurement and R&D.
While they approved the Administration’s request for F-22 funding, the defense
oversight committees expressed marked concern over the aircraft’s testing program. House
appropriators noted that the F-22 flight test program continues to fall short of Air Force
projections. For instance, the program lost nine flight test months between November 1999
and March 2000. The committee was particularly concerned about slips in fatigue and static
testing, both of which are more than a year behind schedule. To emphasize the extent of their
concerns, the House Appropriations committee re-stated the criteria established in P.L. 106-
79 which prohibits award of a low rate production contract for the F-22 until: 1) first flight
of an F-22 aircraft incorporating block 3.0 software, 2) certification by the Secretary of
Defense that all Defense Acquisition Board exit criterial for award of low rate production has
CRS-13

IB87111
07-03-02
been met, and 3) submission of a report by the director of operational test and evaluation
assessing the adequacy of the testing to date. House appropriators were also concerned that
the Air Force may try to contain F-22 program cost increases by further reductions in the test
program. Therefore, the House Appropriations Committee proposed replacing existing,
individual statutory budget caps on F-22 development and production with a single, overall
cap for the entire program. The Senate Armed Services Committee also expressed concern
that the Air Force might reduce testing to accommodate growing program costs. To ensure
adequate testing is accomplished, Senate authorizers recommended a provision that would
increase the F-22 EMD cost cap by one percent.
The FY2001 Defense Appropriations Conference Report (H.Rept. 106-754) fully
funded the Administration’s request for F-22 RDT&E and procurement funding. ($2.5 billion
in FY2001 and Advance Year Procurement, and $1.4 billion in FY2001 RDT&E). Reflecting
congressional concern over growing costs, the conferees stipulated that “The total amount
expended by the Department of Defense for the F-22 aircraft program (over all fiscal years
of the life of the program) for engineering and manufacturing development and for
production may not exceed $58,028,200,000.” (Sec. 8125) Conferees also retained the House
Appropriations Report language regarding flight testing, Secretary of Defense certification
of meeting DAB goals, and requiring the director of operational test and evaluation to submit
a report assessing the adequacy of avionics, stealth and weapons delivery testing.
The FY2001 Defense Authorization Conference Report (H.Rept. 106-945, H.R. 4205)
recommended funding to match the Administration’s request for both procurement and
RDT&E funding. Consistent with the Senate Armed Services Committee recommendation
specifically and with concerns expressed by other defense oversight committees generally,
conferees recommended an increase of the F-22's EMD cost cap by 1.5% to ensure adequate
testing.
In a March 2001 letter to Defense Secretary Donald Rumsfeld, 59 lawmakers
recommended that DoD commence F-22 low rate initial production without delay.
Expressing their fear that further delay would jeopardize the program, the bi-partisan group
of Representatives said that the F-22 is ready to move into low-rate initial production. 20
On March 29, 2001 it was reported that Congress approved the Pentagon’s request to
reprogram $674.5 million in procurement funds from the projected purchase of the first 10
F-22 aircraft to sustain the EMD program. This reprogramming was requested because the
Defense Acquisition Board decision on whether the F-22 program was ready for LRIP was
postponed indefinitely, and FY2001 funds had run out. Congress had previously provided
$353 million in “bridge funding” in the Departments of Labor, Health and Human Services,
and Education Conference Report to finance work on the F-22 from December 31, 2000, to
March 30, 2001. The Air Force says these funds will be used to preclude a work stoppage,
which they say would have resulted in increased costs and a serious erosion of the supplier
base.
20 Wolfe, Frank. Further Delay Will “Effectively Kill F-22,” 59 Lawmakers Say. Defense Daily,
March 5, 2001.
CRS-14

IB87111
07-03-02
Both the House and Senate Armed Services Committees supported the Administration’s
FY2002 request for $865.4 million in R&D, $2.7 billion for 13 low-rate initial production
aircraft, and $379.2 million for advance procurement of 24 aircraft in FY2003. Both
authorization committees also matched the Air Force’s request for $865 million in RDT&E
funds. In their report on S. 1438 (H.Rept. 107-333) authorization conferees adopted a Senate
provision to remove the $20.4 billion legislative cost cap on F-22 Engineering,
Manufacturing and Development.
House appropriators also supported the Administration’s FY2002 request for 13 aircraft,
but citing delays in anticipated production, the HAC also cut $2.6 million from the program.
This adjustment included reductions in tooling (-$100 million) and ancillary equipment (-$14
million). This reduction was offset by an increase of $111.4 million to redesign obsolete
parts. House Appropriators increased the Air Force’s $865 million R&D request by $16
million. In their report on H.R. 3338 (S.Rept. 107-109), Senate appropriators matched the
Air Force’s procurement request for current and advance year procurement to build 13 F-22
Raptors, and the Air Force’s request for RDT&E funding
In their report on H.R. 3338 (H.Rept. 107-350), Appropriations conferees matched the
Air Force’s request for both procurement and R&D funding. Conferees transferred $111
million from the F-22's Advanced Procurement (Current Year) account to FY2002
procurement. Conferees also transferred $16 million from the F-22 Operational Systems
Development account to the EMD account.
The Administration’s FY2003 defense budget request included $5.2 billion for the F-22.
$4.6 billion was requested to procure 23 aircraft, $530 million was for FY04 advanced
procurement (current year) and $11 million was for modifications. Both the House and
Senate authorizing committees matched the Administration’s FY2003 request.21 House
appropriators provided $4.1 billion to procure 23 F-22's in FY03.22 However, the House
Appropriations Committee also expressed concern over the slippage in F-22 developmental
testing, the potential overlap between developmental testing and operational testing. Fearing
that this potential overlap could result in costly retrofits, the appropriations report bars the
Air Force from ordering more than 16 F-22s until DoD certifies that the proposed production
rate is the lowest risk and lowest cost solution.23
21 “Senate Armed Services Committee Completes Markup of National Defense Authorization Bill
for Fiscal Year 2003.” Press Release. United States Senate, Committee on Armed Services. May 10,
2002. P.5. “House Armed Services Committee Reports Fiscal Year 2003 Defense Authorization
Legislation.” Press Release. United States House of Representatives, Committee on Armed Services.
May 1, 2002. P.14.
22 Press Release: “House Passes FY03 Defense Appropriations Bill.” United States House of
Representatives. Committee on Appropriations. June 28, 2002.
23 Paul Mann. “House Acts to Allay Future F-22 Cost Woes.” Aviation Week & Space Technology.
July 1, 2002. Marc Selinger. “House Panel Slashes Funds for BAT Submunition, Seeks F-22
Assurances.” Aerospace Daily. June 26, 2002. Laura Colarusso. “House Appropriators Want Review
of F-22 Program Risk, Test Delays.” Inside the Air Force. June 28, 2002.
CRS-15