Order Code RS20841
Updated March 5, 2002
CRS Report for Congress
Received through the CRS Web
Environmental Streamlining Provisions in the
Transportation Equity Act for the 21st Century:
Status of Implementation
David M. Bearden
Environmental Information Analyst
Resources, Science, and Industry Division
Summary
At the state and local level, many observers have expressed long-standing concerns
over delays, duplication of effort, and additional costs frequently associated with the
environmental review process for highway projects that must be completed under the
National Environmental Policy Act of 1969 (NEPA, P.L. 91-190). To address these
concerns, the Transportation Equity Act for the 21st Century (TEA21, P.L. 105-178),
enacted in 1998, requires the Federal Highway Administration (FHWA) to streamline the
environmental review process for highway projects. However, final streamlining
regulations have not been issued to date, and some Members of Congress have expressed
concerns over the pace of implementation. Thus far, the FHWA has proposed
regulations for a coordinated environmental review process that address some of the
provisions of TEA21, signed a National Memorandum of Understanding on streamlining
with six other federal agencies, and established a pilot program to gain practical
experiences in streamlining before applying it on a larger scale. In addition to the
FHWA’s activities, numerous states have undertaken efforts to streamline the review
process. Oversight hearings have been held in the 107th Congress to examine all of these
actions, and congressional oversight of this matter will likely continue as the FHWA
proceeds with its streamlining initiatives, and as Congress begins to consider the
reauthorization of TEA21. This report will be updated as relevant developments occur.
Introduction
The National Environmental Policy Act of 1969 (NEPA, P.L. 91-190) requires all
federal agencies to prepare Environmental Impact Statements (EISs) for major activities
that significantly affect the environment. The often substantial amount of time and funding
that is needed to prepare such documentation for highway projects has been an ongoing
issue at the state and local level for many years. To reduce the approval time for such
projects and speed the delivery of federal highway funds to states and local areas,
Congress included provisions in Section 1309 of the Transportation Equity Act for the 21st
Congressional Research Service ˜ The Library of Congress
CRS-2
Century (TEA21, P.L. 105-178), enacted in 1998, which require the Federal Highway
Administration (FHWA) to streamline the environmental review process. While the
FHWA has taken numerous actions to address these requirements, final regulations to
implement them have not been issued to date. While the law did not specify a deadline by
which implementation must occur, some Members of Congress have expressed concerns
over the pace at which implementation has proceeded.
This report describes the types of environmental documentation that must be
prepared prior to the approval of a highway project, indicates the average amount of time
required to complete this documentation, summarizes the environmental streamlining
provisions under TEA21, examines what has been done to implement these requirements,
and discusses oversight issues for the 107th Congress.
What types of environmental documents must be prepared?
Under NEPA, the FHWA must prepare an EIS for federally funded highway projects
that have a significant impact on the environment. This statement must describe the
project, characterize the surrounding environment, analyze the environmental effects of
all reasonable construction alternatives, and indicate plans for complying with applicable
environmental laws and mitigating environmental damage. Other federal agencies, such
as the Environmental Protection Agency, Army Corps of Engineers, and U.S. Fish and
Wildlife Service, often cooperate in the preparation of EISs for highway projects due to
their responsibilities under federal laws, such as the Clean Air Act, Clean Water Act, and
Endangered Species Act, to issue permits, licenses, approvals, and other opinions on
proposed actions. If it is clearly known that a highway project will not individually or
cumulatively have significant environmental impacts, a Categorical Exclusion may be
issued which eliminates the requirement for an EIS. However, if it is not clear whether
significant impacts would occur, an Environmental Assessment must be prepared. If
significant impacts are identified, an EIS will be required. Otherwise, a Finding of No
Significant Impact can be issued as a result of the assessment. When all necessary
environmental documentation is complete, a Record of Decision may be prepared to
approve federal funding and allow final design and construction to proceed.1
How long does the preparation of an EIS take?
According to the FHWA, less than 5% of all highway projects have a significant
enough impact on the environment to require the preparation of an EIS. While this
amount represents a small portion of the total projects that receive federal funding each
year, such projects are usually large and affect sizeable populations. Consequently,
construction delays are often controversial. The preparation of an EIS requires substantial
amounts of time and money, which can result in delaying construction for several years,
especially if plans for complying with environmental requirements are challenged as
inadequate. Numerous factors can contribute to the amount of time that is needed to
prepare an EIS, such as the degree to which there is adequate coordination and early
participation among the agencies involved, the adequacy of the data to prepare necessary
reviews, the technical complexity of the project, and the volume of public comments which
must be addressed.
1 The environmental review process for highway projects is specified at 23 CFR 771.
CRS-3
To provide information on the extent to which the environmental review process has
delayed highway projects, the FHWA released a study on May 8, 2001, which examines
the time needed to complete EISs.2 This study will be used as a baseline to determine the
level of progress made by streamlining efforts. The study is based on a sample of 100
highway projects which were approved for federal funding from the 1970's to the 1990's.
During this 30 year period, the average time required for total project development was
13.1 years, and 3.6 years, or 28% of this time, was necessary for the preparation of EISs.
Examined by decade, the average time to prepare an EIS increased over the years. In the
early days of NEPA in the 1970's, the preparation of an EIS for highway projects took 2.2
years on average. The average preparation time increased to 4.4 years in the 1980's, and
rose to an average of 5.0 years in the 1990's. The increase in the average time required
for the preparation of EISs can primarily be attributed to the rise in the number of
environmental laws during this period and the resulting increase in the stringency of
environmental requirements. The average review time increased to 5 years and 10 months
in 1999, and the FHWA reports that its streamlining efforts have reduced this time by 8
months, to 5 years and 2 months in 2001.3
What are the streamlining requirements under TEA21?
Section 1309 of TEA21 requires the FHWA to streamline the environmental review
process for highway projects. This section of the law outlines a process that encourages
early coordination among the agencies involved to help minimize potential conflicts which
often result in construction delays and higher costs. However, the law’s requirement to
streamline the review process does not exempt highway projects from meeting
environmental requirements under other federal laws, such as the Clean Air Act, Clean
Water Act, or Endangered Species Act, nor does TEA21 permit the FHWA to override
the authority of another agency to conduct environmental reviews in order to prevent
construction delays. In the conference report on TEA21, Congress stated that the goals
of Section 1309 are:
.... to establish an integrated review and permitting process that identifies key
decision points and potential conflicts as early as possible; integrates the NEPA
process as early as possible; encourages full and early participation by all
relevant agencies that must review a highway construction project or issue a
permit, license, approval or opinion relating to the project; and establishes
coordinated time schedules for agencies to act on a project.4
To accomplish these goals, Section 1309(a) requires the Secretary of Transportation
to develop and implement a “coordinated” environmental review process for each highway
project subject to such review under federal law, which ensures whenever practicable that
2 Federal Highway Administration. Evaluating the Performance of Environmental Streamlining:
Development of a NEPA Baseline for Measuring Continuous Performance. The full text of the
report is available at [http://www.fhwa.dot.gov/environment/strmlng/baseline].
3 Department of Transportation. Highway and Transit Environmental Streamlining Progress
Summary: 2002 Report to Congress. February 2002. p. 2.
4 U.S. House of Representatives. 105th Congress. Conference Report to Accompany H.R. 2400,
the Transportation Equity Act for the 21st Century. H.Rept. 105-550. May 22, 1998. p. 450.
CRS-4
environmental reviews are conducted concurrently, rather than sequentially, and that they
are completed within a cooperatively determined time period. This process is to be
specified in a memorandum of understanding between the Department of Transportation
and other federal agencies involved in the environmental review of a highway project.
Under Section 1309(b), the coordinated environmental review process outlined in the
memorandum for each affected project should:
! at the earliest possible time, identify all federal agencies that are required
to prepare environmental documentation under NEPA, or are required to
determine whether to issue a permit, license, approval, or other opinion;
! jointly establish time periods for concurrent reviews with all involved
federal agencies, unless concurrent review would result in significant
adverse impact to the environment, substantively conflict with
requirements under other federal laws, or not be possible without
information developed as part of the environmental review process; and
! be modified if the Secretary of Transportation and another federal agency
mutually agree upon an extension due to the necessity for further analysis
and review arising from new information being discovered that could not
have been anticipated when the original time period was established.
If a federal agency does not complete its environmental review for a project within
the established time period, or within a mutually agreed upon time extension, Section
1309(c) authorizes the Secretary of Transportation to close the record on the matter after
notice and consultation with the federal agency concerned, and enter dispute resolution to
mutually rectify the matter within 30 days. However, the closing of a record by the
Secretary due to a missed deadline is limited only to the matter pending before the
Secretary, and such action does not remove a federal agency from requirements under
NEPA to complete an environmental review or from requirements under other federal laws
to determine whether to issue a permit, license or approval for the project. Section
1309(f) includes a judicial review and savings clause which clarifies that the lack of
compliance with time periods established in a memorandum of understanding will not
affect the applicability of NEPA to a highway project or the reviewability of any final
federal agency action regarding a project in a U.S. district or state court.
Section 1309(d) allows state agencies to participate in the coordination of the review
process if such agencies have jurisdiction over environmental issues related to the project.
Section 1309(e) permits the use of federal highway funds to provide federal agencies with
the resources to meet time limits for review that are specified in a memorandum of
understanding. However, this funding is limited to assisting federal agencies in meeting
time limits that are shorter than those for customary reviews.
What has been done to implement these requirements?
Final regulations to implement the environmental streamlining requirements under
TEA21 have not been issued to date. While TEA21 did not specify a deadline by which
implementation must occur, some Members of Congress have expressed concerns over the
pace at which implementation has proceeded. Thus far, the FHWA has proposed
regulations for a coordinated environmental review process that address some of the
CRS-5
provisions of TEA21, signed a National Memorandum of Understanding with six other
federal agencies, and established a pilot program to gain practical experiences in exercising
the principles of streamlining.5 The President’s budget proposal includes $6 million to
support the Department of Transportation’s streamlining initiatives in FY2003, over $3
million more than in FY2002. In addition to the FHWA’s efforts, numerous states have
initiated practices intended to streamline the review process. Further information on the
FHWA’s major efforts to implement the streamlining requirements of TEA21 is provided
below.
NEPA Regulatory Proposal. On May 25, 2000, the FHWA and the Federal
Transit Administration (FTA) proposed regulations to streamline the environmental review
process for highway and transit projects, and public comments were accepted through
September 23, 2000.6 Some Members of Congress have criticized the proposal for not
fully addressing the streamlining requirements under TEA21, and for addressing other
planning and regulatory issues not required under the law. Some of the principal criticisms
are the absence of a requirement for environmental reviews to be conducted concurrently,
rather than sequentially, and to be completed within a cooperatively determined time
period. Thus far, this requirement has only been addressed outside of the regulatory
process in a National Memorandum of Understanding, discussed below. Some Members
also have criticized the proposal for not fulfilling the law’s requirement to develop
procedures for resolving disputes when federal agencies do not complete their reviews
within mutually agreed upon time frames. To address this requirement, the FHWA has
been working with the U.S. Institute for Environmental Conflict Resolution, and has issued
a discussion draft for dispute resolution procedures, which the Administration expects to
finalize by the end of 2002.7 The Department of Transportation reports that its proposal
lacked regulatory requirements to establish time frames for review and resolve disputes
due to its absence of authority over other federal agencies and a concern that “one-size-
fits-all” approaches could limit flexibility.8 A decision on how to proceed with the
proposed regulations has not been made to date.
National Memorandum of Understanding. The FHWA and six other federal
agencies signed a National Memorandum of Understanding on streamlining in July 1999.9
It expresses the commitment of each signatory agency to streamline the environmental
review process for highway projects in accordance with TEA21. To accomplish this
objective, the memorandum establishes several goals that are designed to reduce project
delays while continuing to protect and enhance environmental quality. These goals reflect
5 For additional information on these and other streamlining activities, refer to the FHWA’s web
site at [http://www.fhwa.dot.gov/environment/strmlng].
6 65 Federal Register 33980. While TEA21 only required streamlining for highway projects, the
Clinton Administration included transit projects to address similar concerns over delays.
7 For a copy of the discussion draft on dispute resolution procedures, refer to the FHWA’s web site
at [http://www.fhwa.dot.gov/environment/strmlng/npdjan22.htm].
8 Department of Transportation. Highway and Transit Environmental Streamlining Progress
Summary: 2002 Report to Congress. February 2002. p. 8.
9 The six other federal agencies which signed the memorandum are the Department of the Interior,
Department of Commerce, Department of Agriculture, Army Corps of Engineers, Environmental
Protection Agency, and Advisory Council for Historic Preservation.
CRS-6
the overall intent of the streamlining provisions in TEA21 and some of the specific
requirements in the law, such as the early identification of information needed to prepare
environmental documentation, the performance of concurrent reviews whenever possible,
and the development of national procedures for dispute resolution when an agency cannot
meet an agreed upon deadline. The FHWA has issued an action plan which outlines several
strategies and operating principles to carry out the streamlining goals established in the
memorandum.
Pilot Projects. In April 1999, the FHWA, Environmental Protection Agency, and
the American Association of State Highway and Transportation Officials established a pilot
program to examine effective and efficient ways to implement the environmental
streamlining requirements under TEA21. Federal and state officials established the
program to gain practical experience in streamlining the environmental review process
before applying it on a larger scale. States were given the opportunity to nominate
projects for the pilot program, and in July 2000, ten transportation projects in seven states
were selected that would demonstrate innovations in the preparation and processing of
environmental reviews.10 These projects are currently in the implementation stage and are
focusing on various aspects of the review process such as early coordination, integrating
environmental concerns into the planning process, and establishing specific time frames for
completing environmental documentation. An online site is being developed to track the
progress of these projects and provide an analysis of their results.
What are some of the issues for congressional oversight?
During the 107th Congress, several oversight hearings have been held to examine the
pace at which the Department of Transportation has been implementing the environmental
streamlining requirements under TEA21. Some Members have expressed concerns over
the inadequacies of the proposed streamlining regulations and have indicated their
disappointment in the lack of final regulations to put the principles of streamlining into
practice on a national scale. Further, how the National Memorandum of Understanding
would work in tandem with the streamlining regulations to fulfill the requirements of
TEA21 is an issue as well. A potential issue regarding the streamlining pilot projects will
be whether the knowledge gained from such experiments will prove to be limited in scope
or applicable to many different types of highway projects on a larger scale. Oversight of
these issues will likely continue as the Department of Transportation proceeds with its
efforts to implement the streamlining provisions of TEA21 and as Congress begins to
consider the reauthorization of the law, which expires at the end of FY2003.
10 The seven states in which pilot projects were selected include California, Florida, Georgia, New
Jersey, Oregon, Texas, and Wisconsin.